May 05
- Cycle control line 10 times. No indication of piston movement (100 ml
hydraulic returns)
- RIH slowly with 1-7/8" sinker bar tagged 162.1mRKB. Tool hung-up
(potential flapper partially open).
- Pressure up control line to 4000 psi, pumping @ 1bpm for 30 min.
Increase pumping to 2 bpm and pull sinker bar weight at 650 lbs - able to free
sinker bar.
- Recommend not to use toolstring with 90o shoulder.
Attendees:
• Suspect lower no-go dogs (Item 4) and upper no-go dogs (Item 26) are in
expanded position and might be wedged inside the polished bore.
• Top rope socket/ top sub of the SLOT was backed-off / has been parted
during lock-open job.
Possibility of hydraulic ram / cylinder rod (Item 2) is dropped in hole due to
aggressive jarring action during the lock-open job. Bottom section (Item 21,
22, 25, and 23) is possible dropped in hole as well.
-
- B) Condition of the BDK Releasable Spear inside SLOT
-
• Top sub was retrieved and spear is attached inside the SLOT causing the
upper no-go dogs (Item 26) to be expanded.
• Need to have a cylinder rod to be jarred down on the top of the BDK upper
portion to release spear.
• Once spear is released, to RIH overshot to fish out the whole BDK
Releasable Spear.
-
-
- OPTIONS AVAILABLE
A) To attempt to kill D-90 sand from the annulus (through gas lift valves).
If D-90 can be killed from the annulus, proceed with blind back-off tubing
during workover. If well cannot be killed through annulus, proceed to Step B.
- (Tentatively 2nd week of April) - EMEPMI
-
B) To run in hole wireline fishing tools to retrieve the spear (To plan job by
2nd week of April) - Geowell to submit proposal.
a. To RIH cylindrical rod/6 ft length sinker bar to jar down on the spear
to release into locked position.
b. To fish BDK spear with overshot -> Use hard material / releasable
overshot.
- Will be manufactured based on the size of the top body of the
BDK spear. (Geowell/Asep)
- Once spear is retrieved, test the tubing injectivity.
c. If no injectivity, run in hole long rod (OD = hydraulic ram inside
SLOT) to tag top of hydraulic ram inside the SLOT.
d. Mill SLOT up to upper no-go dogs (Item 26). [Run burn shoe may
not be feasible due to limited clearance from tubing ID to OD of SLOT].
Then RIH overshot to retrieve SLOT (evaluating COS) - (Baker) Targeted
first week of May.
-
C) To proceed with milling overall SLOT, will need to consider cementing
top of fish (unlikely due to extended duration required based on hard
materials).
-
D) To go with workover rig and to perform straight pull on the tubing (36
kips). D-90 estimated BHP = 900 psi.