Escolar Documentos
Profissional Documentos
Cultura Documentos
Miscellaneous
Table of Contents
Standard Title
MS 800 Substation Power Cable Trench
MS 800.1 Substation Power Cable Trench — Precast (Preferred) or Poured (Non-Traffic)
MS 860 Inspection and Repair Procedures for Precast Vaults and Manholes
MS 860.1 Inspection and Repair Procedures for Precast Vaults and Manholes
MS 870 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
MS 870.1 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
MS 870.2 Removable Curbing (Steel Cover Plates)
MS 890 Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers
MS 890.1 Electrolier Foundation Detail
MS 890.2 Marbelite Nostalgic Electrolier Foundation Detail
MS 890.3 Electrolier Foundation Requirements
Approved by:
Miscellaneous
Table of Contents
Sheet
MS
Effective Date: i
01-30-2009
UGS
SCE Internal
This page intentionally left blank.
Underground Structures Standards
Figure MS 800–1: Substation Power Cable Trench — Precast or Poured — Entrance Detail and Trench Plan
Full
14" Encasement 18" Grade 6"
2' Typ.
1-1/2" Typ.
4'-6" Double Insert
2" Recess Each End
6" 33" 45° Bevel (See Note 2.) 6"
2"
18" MIN
6"
6"
Note(s):
1. A 1" double coil insert on trench center-line is required in each end wall as shown. One is also required directly opposite the side entrance
1'-6" from the trench floor.
2. See AC 720.
3. See CD 172.
Length as Shown 6"
on Working Drawing
6"
2"
1" finger holes
for lifting every
4th board 48"
2"
6" Trench Plan
Approved by:
Substation Power Cable Trench MS 800
Sheet
Effective Date: What’s Changed? 1 of 4
04-25-2008
UGS
SCE Public
Underground Structures Standards
6"
1/2" 1/2"
Curb Smooth
Finish
13-1/2" 12"
M-2
12"
28-1/2"
12"
12" 12"
12"
8" M-1
Materials:
Concrete:
3000 psi @ 28 days (See Note 1.)
0.259 cu. yd. per lin. foot of trench.
56"
Note(s):
1. See GI 020.
Approved by:
MS 800
Sheet
Substation Power Cable Trench
UGS 04-25-2008
SCE Public
Underground Structures Standards
Figure MS 800–2: Substation Power Cable Trench — Precast or Poured — Conduit Bank Exits, Trench End
Walls, and Section View of Trench
25°
All Sweeps
12-1/2' R
10'
8'-0"
25°
12-1/2' R
1-1/2" Typ.
1" Double Coil
18" 6" Insert
2" Typ.
6"
1" MAX
(At entrance only)
Figure MS 800–2.2: Trench End Wall (2 Conduit Banks
1" Double
Coil Insert 18"
2" Typ.
6"
Approved by:
Substation Power Cable Trench MS 800
Sheet
Effective Date: What’s Changed? 3 of 4
04-25-2008
UGS
SCE Public
Underground Structures Standards
Pad Surface
Flush
6" 6" Grade
6"
9" 4'-0" 6"
5'-3"
Figure MS 800–2.4: Section View of Trench Adjacent to Pad for Metal Clad Unit (Poured in Place)
Note(s):
1. Pouring of trench and pad to be monolithic. Trench to be finished smooth with drainage as indicated in MS 800. If precast trench is used,
pour pad level with top of trench wall. Pad should butt against precast wall.
Approved by:
MS 800
Sheet
Substation Power Cable Trench
4 of 4 What’s Changed? Flus changed to Flush. All dimensions added back in. Effective Date:
UGS 04-25-2008
SCE Public
Underground Structures Standards
Roof
Seal
1"
(MIN)
2"
Wall
Wall
Wall
2"
2" Seal
2"
4"
Floor
Floor
Note(s):
1. Dimensions are approximate. Sloped surfaces approximately 45° from vertical. Joint surface must be free of debris when second pour is
made. Use 2 coats of “Sika-Seal” or equal for sealing.
Approved by:
Cold Joints (Approved for Use at Contractor’s Request) MS 810
Sheet
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards
Old
Construction
Roof
4"
Old Construction
F (12 " MIN)
6"
4"
Seal
2 " MIN
6"
New Construction
D B E
Elevation
Note(s):
1. Dimensions indicated by letters will be tabulated on working drawings with same letters for identification.
2. Subscript “1” when used will indicate a dimension referenced to the existing wall; subscript “2” when used will indicate a dimension
referenced to the new wall.
3. Cut existing steel near center line of opening and turn into new structure as shown. Move new steel, otherwise passing through opening, to
nearest edge with 1-inch clearance and 1-inch spacing between pieces.
4. Turn ends of new steel coming around corners up or down when necessary to clear opening. Paint 4-inch-wide band on outer surface
around opening broken in old structure, with 2 coats of Sika Seal (1 gallon) black liquid or equivalent bonding agent before pouring.
Approved by:
Joining Old and New Structures MS 820
Sheet
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards
Barriers
Equipment
Foundation
Typical
4'-6"
MAX
Barriers
3'-0"
MIN Pole or
Vent
4'-6"
MAX
Approved by:
Protective Barrier for Underground Distribution Structures MS 830
Sheet
Effective Date: What’s Changed? 1 of 3
01-30-2009
UGS
SCE Public
Underground Structures Standards
30"
5" Hdg. Pipe Sleeve
(1/4" MIN Wall)
3"
6" MIN
Figure MS 830–1.3: Removable Barrier Detail
30"
Grade
30"
3"
6" MIN
Figure MS 830–1.4: Protective Barrier Detail
1. Structures will normally be installed only in nontraffic areas. Protective barriers are to be used where construction exposes equipment to
traffic.
2. Tops of protective barriers are to be smooth cut and top edges are to be rounded.
3. At least one barrier is to be removable, with a means of lifting to support the weight of the barrier, when overhead obstacles prevent
equipment removal or installation by crane. See Figure MS 830–1.3 (Sheet 2). The location of the removable barrier(s) shall be approved
by the Underground Inspector.
4. Adequate clearance must be provided for doors, cooling radiators, and so forth.
Approved by:
MS 830
Sheet
Protective Barrier for Underground Distribution Structures
2 of 3 What’s Changed? On Figures MS 830-1.3 and MS 830 1.4, a 3" concrete foundation dimension Effective Date:
was added below the barrier to avoid corrosion.
UGS 01-30-2009
SCE Public
Underground Structures Standards
5. Protective barriers, as shown above, indicate typical requirements. Field conditions will necessitate changes for adequate equipment
protection. Application of protective barriers is site-specific.
6. The Underground Inspector in the field must approve all protective barrier installations prior to construction. The Underground Inspector
will determine (a) status of overhead obstructions, (b) the front and back of equipment foundations, and (c) the clearances required on
doors, cooling radiators, and so forth.
7. When a 72" x 94" pad is being installed, (a) increase the distance to 36 inches minimum between the protective barriers and the front edge
of the pad; and (b) increase the distance between the protective barriers and the back edge of the pad for capacitor bank (door side only)
to 36 inches minimum. The Underground Inspector will determine the front and back of this equipment foundation.
8. With prior SCE approval, the following alternatives may be used in lieu of protective barriers for padmounted structures:
a. When specified on working drawing, a 6-inch (minimum vertical face) concrete curb may be installed in place of protective barriers.
This curb must be at least 6 inches thick and its front face at least 60 inches (minimum spacing) from the equipment foundation.
b. When specified on working drawing for residential tract developments, protected barriers will not be required when there are rolled
curbs or 6-inch vertical face curbs that have at least 60 inches (minimum spacing) from the curb to the edge of the equipment
foundation.
c. Where equipment is located adjacent to a residential driveway, protective barriers may not be required when there is 30-inch
(minimum) clearance from the equipment foundation to the edge of the driveway. In addition, a 60-inch clearance shall be maintained
from a fire hydrant to a pole. Field conditions will necessitate changes for adequate equipment protection. If the minimum clearances
cannot be obtained, protective barriers are required.
9. With prior SCE approval, the following alternatives may be used in lieu of protective barriers for primary surface or semi buried structures
including BURD structures:
a. When specified on working drawing, a 6-inch (minimum vertical face) concrete curb, 8-feet in length may be installed in place of
protective barriers. This curb must be at least 6 inches thick.
b. Where there are rolled curbs or curbs that have less than 6-inches of vertical face, protective barriers may not be required when there
is at least 60 inches (minimum spacing) from the curb to the edge of the primary surface or semi buried structures. (See Figure MS
830-1.5)
c. Where equipment is located adjacent to a residential driveway, protective barriers may not be required when there is 30-inch
(minimum) clearance from the equipment foundation to the edge of the driveway. (See Figure MS 830-1.5)
d. Field conditions will necessitate changes for adequate equipment protection. If the minimum clearances cannot be obtained or there
is no curb, protective barriers shall be required.
e. In addition, a 60-inch clearance shall be maintained from a fire hydrant to a pole, transformers, PME switches, or any primary surface
or semi buried structure.
Residential 30" E T
Driveway MIN
Property Line
Street Street
Top of “X”
Approved by:
Protective Barrier for Underground Distribution Structures MS 830
Sheet
Effective Date: What’s Changed? 3 of 3
01-30-2009
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards
Back of Walk
E.C.R E.C.R
B.C.R.
B.C.R.
Ra
dia
l Li
ne
W
2'
Ra
2'
dia
4'
lL
ine
A
4'
Y=5' MIN
(X) (W) (X)
Slope 1/4" per Foot 6"
Top of Curb 4' 4' 4'
3/8" Curb Face
Flow Line
4"
P.C.C
3/8"
Section A-A Curb Face Detail
Note(s):
1. Score lines are required at points “W” on all ramps.
2. Ramps shall have a rough broom finish transverse to the axis of the ramp. The finish must be rougher than the adjacent sidewalk.
3. Design my vary due to local regulations.
Approved by:
Wheelchair Ramps
Sheet
MS 840
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards
Floor
Floor
Other Utility
Wall
Edison Company
Wall
Plan — Section
Approved by:
Structure Offsets for Joint Construction MS 850
Sheet
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards
MS 860 Inspection and Repair Procedures for Precast Vaults and Manholes
Scope MS 860.1 Inspection and Repair Procedures for Precast Vaults and Manholes
1.0 General
This procedure covers the inspection and repairs of cracks and/or spalling in precast concrete vaults,
manholes, and other similar structures.
2.0 Background
A main source of strength in precast concrete structures is provided by the rebar (reinforcing steel). The
principal component of the reinforcing steel is iron which has a persistent tendency to return to its natural
state, generally iron oxide, or rust. Whenever an excessive amount of heat or moisture is present, the
rebar will rust at a rapid rate. The presence of admixtures, such as calcium chloride, and moisture
increases the probability of rebar rusting.
When the rebar rusts, it begins to lose strength, but more importantly the rust occupies a much greater
volume than the iron from which it came. This rust exerts expansion pressures exceeding the ability of
even the strongest concrete to resist. The result is cracking and, if corrosion continues, concrete will spall
off. Such spalling is frequently accompanied by leaching of rust to the concrete surface, leaving unsightly
stains. Remedial action must be taken so that progressive deterioration does not ultimately threaten the
structure’s adequacy.
As stated above, structures that have high humidity and excessive heat are very likely to eventually start to
crack or spall.
A spall is a fragment of concrete, usually in the shape of a flake, detached from the larger mass by a blow,
by action of weather, or by pressure or expansion within the large mass. In the case of vaults, it is
frequently caused by expansion that accompanies the corrosion of reinforcing steel.
Approved by:
Inspection and Repair Procedures for Precast Vaults and Manholes MS 860
Sheet
Effective Date: What’s Changed? 1 of 4
01-26-2007
UGS
SCE Public
Underground Structures Standards
5.1 General
Cracks should be repaired by injecting epoxy grout under pressure into the crack. The procedure
for preparation and application of the epoxy injection shall be in accordance with the
manufacturer’s recommendations and as described below:
A. Cracks to be filled shall be cleaned of dust, silt, and any other material that would impair bond
of the epoxy to the concrete. For small cracks, cleaning shall be done by vacuuming. Large
cracks may be blown out with compressed air.
B. Suitable fixed injection ports shall be established along the cracks at intervals not less than the
thickness of the concrete being injected. At the end of a crack, the first port shall be about half
this distance from the end.
C. The surface of the crack between ports on both faces of the structure, if they are accessible,
shall be sealed with tape or other temporary surface sealant which is capable of retaining the
epoxy adhesive in the crack during pressure injection and until the epoxy has hardened.
Sealing tape and/or temporary surface sealant should remain in place until the epoxy has
hardened.
D. Epoxy adhesive shall be pumped into the cracks through the injections ports. The pump, hose,
injection gun, and appurtenances shall be capable of injecting the epoxy at a sufficient rate and
pressure to completely fill all designated cracks. The temperature of the concrete shall be not
less than 45°F at the time the epoxy is injected.
E. Before starting injection work and at hourly intervals during injection work, a sample of mixed
epoxy shall be taken from the injection gun. Should these samples show any evidence of
improper proportioning or mixing, injection work shall be suspended until the equipment or
procedures are corrected.
F. The epoxy adhesive shall be forced into the first port at one end of a crack until adhesive runs
in substantial quantity from the next adjacent port. The first port shall then be sealed and
injection started at the next port where the epoxy has just begun to show. Injection shall then
continue from port to port in this manner until the crack is fully injected. For slanting or vertical
cracks, pumping shall start at the lower end of the crack and progress upward. Where
approximately vertical and horizontal cracks intersect, the vertical crack below the intersection
shall be injected first. For horizontal structural elements, the crack shall be injected from the
bottom of the element, filling upward.
Approved by:
MS 860
Sheet
Inspection and Repair Procedures for Precast Vaults and Manholes
UGS 01-26-2007
SCE Public
Underground Structures Standards
A. Automatic pressure injection systems shall contain positive displacement pumps with variable
feedrate to ensure components are mixed at the correct ratio.
B. The recommended injection pressure for epoxy injection shall be 10 to 15 psi at the beginning
of the injection at each injection location. The pressure may be gradually increased to 20 to 25
psi if the injection progresses too slowly. The maximum injection pressure should not exceed
75 psi.
For best results, it is recommended that lower injection pressure, in the range of 10 to 25 psi,
and slower injection progressive speed be maintained at all times. This can be verified with the
use of a pressure gauge located on the discharge side of the mixer.
C. Transparent reservoirs shall be used to verify that the ratio of the components mixed are in
accordance with manufacturer’s recommendations. Metering systems shall be used to ensure
mixing accuracy is within 2%.
5.3 Material
A. Epoxy shall be a two-component, waterproof system specifically manufactured for use in filling
cracks by means of pressure injection. All epoxy resin shall conform to the requirements of the
American Society for Testing and Materials (ASTM) Standard Specification for Epoxy Resin
Base Bonding Systems, ASTM C 881.
6.1 Preparation
A. Remove all loose material to sound concrete. The perimeter of the prepared area should have
perpendicular edges with a minimum depth of 1/8".
B. Concrete shall be chipped to a minimum clearance of one inch all around corroded reinforcing
bars. The exposed bars shall be cleaned of corrosion.
C. Existing concrete surface at the repairing area shall be roughened to a minimum magnitude of
1/8" and shall be damaged with water prior to patching.
D. If the diameter of the rebar is reduced by 1/16" or more, additional reinforcement shall be
installed. Precast manufacturers should be contacted for installation details.
Approved by:
Inspection and Repair Procedures for Precast Vaults and Manholes MS 860
Sheet
Effective Date: What’s Changed? 3 of 4
01-26-2007
UGS
SCE Public
Underground Structures Standards
6.2 Patching
Overhead grout patches shall be applied in layers not to exceed 1/2" in thickness.
6.3 Materials
All materials to be applied in accordance with manufacturer’s recommendations.
Nonshrink Grouts Manufacturer
Nonshrink grouts from manufacturers other than those listed above are subject to Edison approval
before use.
8.1 When repairs are made, the following information should be recorded on a 3" x 5" card.
A. Date of repair
B. Materials used
C. Contractor
8.2 The card should be placed in a watertight container and left in a conspicuous location in the vault. A
sealable plastic map container (M/C 061-31007) is available for this application.
Approved by:
MS 860
Sheet
Inspection and Repair Procedures for Precast Vaults and Manholes
UGS 01-26-2007
SCE Public
Underground Structures Standards
MS 870 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
Scope MS 870.1 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
Figure MS 870–1: Removable Curb for 4' x 5' Vault Covers and Manhole Covers
3/8" Threaded
Inserts Centered Variable
in Recess (See Cover Plate 1 Cover Plate 2 Cover Plate 3
Notes 4 and 5.) C/L
Curb Top
Curb Face
Manhole Cover
Vault Cover
2-1/8" x 1/4"
Recess Top View
Curb Face
(See Note 2.)
Cover Necking
Gutter Line
Vault Cover
Front View
Note(s):
1. The three-sided offset curbing around the vault necking, or manhole necking, shall be constructed to the dimensions of the existing or
proposed curbing.
2. A 2-1/8" wide by 1/4" deep recess shall be placed on top of the offset curb, and curb face, as shown on the drawing.
3. Three plate covers are required for 4' x 5' vault covers. Manhole covers require two plate covers (plate #1 and 3).
4. Threaded 3/8" inserts shall be placed in the 2-1/8" wide curb recesses, to the dimensions shown on the “Top View” drawing. A minimum of
five inserts are required for the 4' x 5' vault cover, four for a manhole cover.
5. Whenever the plate depth exceeds 36", an additional insert, equally spaced, shall be placed into the recess of the offset curbing sides.
6. For steel cover plate details, see Scope MS 870.2 (Sheet 2).
Approved by:
Removable Curb for 4' x 5' Vault Covers and Manhole Covers MS 870
Sheet
Effective Date: What’s Changed? 1 of 2
01-26-2007
UGS
SCE Public
Underground Structures Standards
5"
26-9/16"
1-3/4"
Threaded Hole
for 3/8" S.S.
Flathead Screw 7/16" Holes
Weld Countersunk
for 3/8" S.S.
1" Flathead
1" Dia. Lift Hole Screws
(2 Places) (2 Places MIN)
Note(s):
1. Nonskid 1/4" thick steel floor plates shall be constructed to the dimensions shown. See MS 860 for plate location sequence on curb offset.
2. The 2" x 2" x 1/4" steel L shall be welded to the top and angled floor plate face.
3. Angled floor plate face may be bent or welded in place to the top plate.
4. Angle and depth of floor plate face shall match standard curb.
5. A minimum of seven 3/8" stainless steel flathead screws are required for the 4' x 5' vault cover plates, and a minimum of five screws for the
manhole plates.
6. All plate covers, after fabrication, shall be covered with one coat of Subalox #511FD primer, and then with one coat of Subox #5FD light
gray paint.
Approved by:
MS 870
Sheet
Removable Curb for 4' x 5' Vault Covers and Manhole Covers
UGS 01-26-2007
SCE Public
Underground Structures Standards
MS 890 Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers
Scope MS 890.1 Electrolier Foundation Detail
12-1/2"
8-7/8"
Concrete Apron
(See Note 5.) 24" (MIN)
Flow Line
30" (MIN)
“H” — See Note 1.
4" (Typ.)
3" (MIN) Clearance
“D”
CIC Sleeve (See Note 3.)
Note(s):
1. The footing depth will vary depending on the type of soil and wind loading requirements. Consult local government agency for
requirements. See Table MS 890–1 (Sheet 4) through Table MS 890–4 (Sheet 5).
2. Foundation shall be installed after conduit or CIC (for Underground Service), curbs, and sidewalks are in place and grades are established.
3. 1-1/2" Plastic CIC Sleeve for UG Concrete Electrolier (tape both ends to prevent debris from entering the sleeve).
Approved by:
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers MS 890
Sheet
Effective Date: What’s Changed? 1 of 5
01-26-2007
UGS
SCE Public
Underground Structures Standards
4. Concrete to reach a minimum compression strength of 2800 psi in 28 days. See UGS 20.3.
5. Place a minimum size concrete apron of 30" x 30" x 4" thick around the pole at the ground level to provide a constrained surface condition
when required. Grout to be placed after pole is set and plumbed.
Approved by:
MS 890
Sheet
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers
UGS 01-26-2007
SCE Public
Underground Structures Standards
Concrete Apron
24" (MIN)
Flow Line
30" (MIN)
4" (Typ.)
3" (MIN) Clearance
“D”
CIC Sleeve
Note(s):
1. The footing depth will vary depending on the type of soil and wind loading requirements. Consult local government agency for
requirements. See Table MS–1 (Page MS-21) through Table MS–4 (Page MS-22).
2. Foundation shall be installed after conduit or CIC (for Underground Service), curbs, and sidewalks are in place and grades are established.
3. 1-1/2" Plastic CIC Sleeve for UG Concrete Electrolier (tape both ends to prevent debris from entering the sleeve).
4. Concrete to reach a minimum compression strength of 2800 psi in 28 days. See UGS 20.3.
5. Place a minimum size concrete apron of 30" x 30" x 4" thick around the pole at the ground level to provide a constrained surface condition
when required. Grout to be placed after pole is set and plumbed.
Approved by:
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers MS 890
Sheet
Effective Date: What’s Changed? 3 of 5
01-26-2007
UGS
SCE Public
Underground Structures Standards
2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 3'-0" 20" dia. 3'-0" 20" dia. 24" dia
III. Sandy Gravel, Gravel
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 3'-6" 20" dia. 3'-6" 20" dia. 3'-6" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 4'-0" 20" dia. 4'-6" 20" dia. 4'-0" 20" dia. 24" dia.
V.
Clay, Clayey Silt 2'-6" 30" x 30" 3'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30'
a/
Uniform Building Code — 1991
Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.
2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 3'-6" 20" dia. 3'-0" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-6" 20" dia. 4'-0" 20" dia. 3'-6" 20" dia. 24" dia
III. Sandy Gravel, Gravel
3'-0" 30" x 30" 3'-0" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 4'-0" 20" dia. 4'-6" 20" dia. 4'-0" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 3'-0" 30" x 30" 3'-6" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 4'-6" 20" dia. 5'-0" 20" dia. 4'-6" 20" dia. 24" dia.
V.
Clay, Clayey Silt 3'-6" 30" x 30" 4'-0" 30" x 30" 3'-6" 30" x 30" 30" x 30'
a/ Uniform Building Code — 1991
Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.
Approved by:
MS 890
Sheet
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers
UGS 01-26-2007
SCE Public
Underground Structures Standards
2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 3'-6" 20" dia. 3'-0" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 4'-0" 20" dia. 3'-6" 20" dia. 24" dia
III. Sandy Gravel, Gravel
3'-0" 30" x 30" 3'-0" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 4'-0" 20" dia. 4'-6" 20" dia. 4'-0" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 3'-0" 30" x 30" 3'-6" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 4'-6" 20" dia. 5'-0" 20" dia. 4'-6" 20" dia. 24" dia.
V.
Clay, Clayey Silt 3'-6" 30" x 30" 4'-0" 30" x 30" 3'-6" 30" x 30" 30" x 30'
a/ Uniform Building Code — 1991
Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.
2'-6" 20" dia. 3'-0" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
4'-0" 20" dia. 4'-0" 20" dia. 4'-0" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
3'-0" 30" x 30" 3'-0" 30" x 30" 3'-0" 30" x 30" 30" x 30"
5'-0" 20" dia. 5'-6" 20" dia. 5'-0" 20" dia. 24" dia
III. Sandy Gravel, Gravel
3'-6" 30" x 30" 4'-0" 30" x 30" 3'-6" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 5'-6" 20" dia. 6'-0" 20" dia. 5'-6" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 4'-0" 30" x 30" 4'-6" 30" x 30" 4'-0" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 6'-0" 20" dia. 6'-6" 20" dia. 6'-0" 20" dia. 24" dia.
V.
Clay, Clayey Silt 4'-6" 30" x 30" 5'-0" 30" x 30" 4'-6" 30" x 30" 30" x 30'
a/
Uniform Building Code — 1991
Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.
Approved by:
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers MS 890
Sheet
Effective Date: What’s Changed? 5 of 5
01-26-2007
UGS
SCE Public
This page intentionally left blank.