Você está na página 1de 30

Underground Structures Standards

Miscellaneous
Table of Contents
Standard Title
MS 800 Substation Power Cable Trench
MS 800.1 Substation Power Cable Trench — Precast (Preferred) or Poured (Non-Traffic)

MS 810 Cold Joints (Approved for Use at Contractor’s Request)


MS 810.1 Cold Joints (Approved for Use at Contractor’s Request)

MS 820 Joining Old and New Structures


MS 820.1 Joining Old and New Structures

MS 830 Protective Barrier for Underground Distribution Structures


MS 830.1 Protective Barrier for Underground Distribution Structures

MS 840 Wheelchair Ramps


MS 840.1 Wheelchair Ramps

MS 850 Structure Offsets for Joint Construction


MS 850.1 Structure Offsets for Joint Construction

MS 860 Inspection and Repair Procedures for Precast Vaults and Manholes
MS 860.1 Inspection and Repair Procedures for Precast Vaults and Manholes

MS 870 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
MS 870.1 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
MS 870.2 Removable Curbing (Steel Cover Plates)

MS 890 Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers
MS 890.1 Electrolier Foundation Detail
MS 890.2 Marbelite Nostalgic Electrolier Foundation Detail
MS 890.3 Electrolier Foundation Requirements

Approved by:
Miscellaneous
Table of Contents
Sheet
MS
Effective Date: i
01-30-2009
UGS
SCE Internal
This page intentionally left blank.
Underground Structures Standards

MS 800 Substation Power Cable Trench


Scope MS 800.1 Substation Power Cable Trench — Precast (Preferred) or Poured (Non-Traffic)

Figure MS 800–1: Substation Power Cable Trench — Precast or Poured — Entrance Detail and Trench Plan

Cover Boards One per Foot


2" x 12" x 51-1/2" Untreated
Redwood Construction Heart— Cleat boards in threes 6"
Well Seasoned with 1" x 6"s. 4"
Grade

Full
14" Encasement 18" Grade 6"
2' Typ.
1-1/2" Typ.
4'-6" Double Insert
2" Recess Each End
6" 33" 45° Bevel (See Note 2.) 6"

2"
18" MIN
6"
6"

4/0 Bare Copper


Recess 24" to face of Soakage Pit 18" DIA x Neutral Wire
conduit; walls of recess 30" Fill with Crushed 6" DIA
to be same thickness as Rock (Typ.) Sump (Typ.)
Riser Entrance from Rack or Metal-
trench walls.
Clad Sub. See working drawing
for location. (See Note 3.) Slope conduits to proper
depth to meet incoming
conduits at substation
fence.
Figure MS 800–1.1: Side Entrance Detail Figure MS 800–1.2: End Entrance Detail

Note(s):
1. A 1" double coil insert on trench center-line is required in each end wall as shown. One is also required directly opposite the side entrance
1'-6" from the trench floor.
2. See AC 720.
3. See CD 172.
Length as Shown 6"
on Working Drawing

6"
2"
1" finger holes
for lifting every
4th board 48"

2"
6" Trench Plan

Ledge All Around Cleat


6"
Figure MS 800–1.3: Trench Plan

Approved by:
Substation Power Cable Trench MS 800
Sheet
Effective Date: What’s Changed? 1 of 4
04-25-2008
UGS
SCE Public
Underground Structures Standards

6"
1/2" 1/2"
Curb Smooth
Finish
13-1/2" 12"
M-2

12"

28-1/2"
12"

12" 12"
12"
8" M-1

3/8" Inserts Spaced as M-1


Shown Both Sides of
Drain Floor to of
Trench Every 3'. Start 18"
Trench. Drain to Sumps
from End Walls
with Slope of 3" per 100'

Figure MS 800–1.4: Typical Trench Section

Materials:

Concrete:
3000 psi @ 28 days (See Note 1.)
0.259 cu. yd. per lin. foot of trench.

Straight Reinforcing Steel:


Mark 1 Slicing overlap to be 15" MIN
12 required continuous #4 steel.

One per 8" of trench — #6 steel


56"

56"

Use 2 x 2 - 12/12 welded wire mesh


for reinforcing deep recess. Extend
fabric 6" MIN into walls and floor.
55"
Mark 2

Figure MS 800–1.5: Mark 1 and Mark 2

Note(s):
1. See GI 020.

Approved by:
MS 800
Sheet
Substation Power Cable Trench

2 of 4 What’s Changed? Effective Date:

UGS 04-25-2008
SCE Public
Underground Structures Standards

Figure MS 800–2: Substation Power Cable Trench — Precast or Poured — Conduit Bank Exits, Trench End
Walls, and Section View of Trench

6' MIN 1-1/2"

25°
All Sweeps
12-1/2' R

10'
8'-0"

25°
12-1/2' R

Figure MS 800–2.1: Conduit Bank Exits — Plan

1-1/2" Typ.
1" Double Coil
18" 6" Insert
2" Typ.

6"

1" MAX
(At entrance only)
Figure MS 800–2.2: Trench End Wall (2 Conduit Banks

1" Double
Coil Insert 18"
2" Typ.

6"

1" MAX All precast units have 12


(At entrance only) terminators installed. Use
only outside 6 for 1 conduit
bank installations.

Figure MS 800–2.3: Trench End Wall (1 Conduit Bank)

Approved by:
Substation Power Cable Trench MS 800
Sheet
Effective Date: What’s Changed? 3 of 4
04-25-2008
UGS
SCE Public
Underground Structures Standards

Pad Surface
Flush
6" 6" Grade

Pad reinforcing to enter


trench wall a MIN of 15" 4'-0"
(poured trench)

6"
9" 4'-0" 6"
5'-3"
Figure MS 800–2.4: Section View of Trench Adjacent to Pad for Metal Clad Unit (Poured in Place)

Note(s):
1. Pouring of trench and pad to be monolithic. Trench to be finished smooth with drainage as indicated in MS 800. If precast trench is used,
pour pad level with top of trench wall. Pad should butt against precast wall.

Approved by:
MS 800
Sheet
Substation Power Cable Trench

4 of 4 What’s Changed? Flus changed to Flush. All dimensions added back in. Effective Date:

UGS 04-25-2008
SCE Public
Underground Structures Standards

MS 810 Cold Joints (Approved for Use at Contractor’s Request)


Scope MS 810.1 Cold Joints (Approved for Use at Contractor’s Request)

Figure MS 810–1: Cold Joints

Roof

Seal
1"
(MIN)

2"

Wall

Applicable to structures in general.


Joint may be formed after pouring.

Wall
Wall

2"
2" Seal
2"

4"

Floor
Floor

Walls poured first.


Applicable where walls are Floor poured first.
poured against firm earth. Applicable where walls are to be double formed.
Form before pouring. May be formed as poured.

Note(s):
1. Dimensions are approximate. Sloped surfaces approximately 45° from vertical. Joint surface must be free of debris when second pour is
made. Use 2 coats of “Sika-Seal” or equal for sealing.

Approved by:
Cold Joints (Approved for Use at Contractor’s Request) MS 810
Sheet
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards

MS 820 Joining Old and New Structures


Scope MS 820.1 Joining Old and New Structures

Figure MS 820–1: Joining Old and New Structures

Old
Construction

Old Steel Turned


into New Wall

Plan Typical Section at Edge of Opening

Roof

4"
Old Construction
F (12 " MIN)
6"

4"

Seal

2 " MIN
6"

New Construction

Opening C Old Steel Turned into New


Wall or Floor.

Typical Section Where New Wall


or Floor is in Line With Old

D B E

Elevation

Note(s):
1. Dimensions indicated by letters will be tabulated on working drawings with same letters for identification.
2. Subscript “1” when used will indicate a dimension referenced to the existing wall; subscript “2” when used will indicate a dimension
referenced to the new wall.
3. Cut existing steel near center line of opening and turn into new structure as shown. Move new steel, otherwise passing through opening, to
nearest edge with 1-inch clearance and 1-inch spacing between pieces.
4. Turn ends of new steel coming around corners up or down when necessary to clear opening. Paint 4-inch-wide band on outer surface
around opening broken in old structure, with 2 coats of Sika Seal (1 gallon) black liquid or equivalent bonding agent before pouring.

Approved by:
Joining Old and New Structures MS 820
Sheet
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards

MS 830 Protective Barrier for Underground Distribution Structures


Scope MS 830.1 Protective Barrier for Underground Distribution Structures

Figure MS 830–1: Protective Barrier for Underground Distribution Structures

Barriers

Equipment
Foundation

4'-6" For 72" x 94" pad.


24"
MAX See Note 7.
MIN
24"
MIN

Typical
4'-6"
MAX

Figure MS 830–1.1: Plan Equipment Foundation

Barriers

3'-0"
MIN Pole or
Vent

4'-6"
MAX

Figure MS 830–1.2: Plan Pole or Vent

Approved by:
Protective Barrier for Underground Distribution Structures MS 830
Sheet
Effective Date: What’s Changed? 1 of 3
01-30-2009
UGS
SCE Public
Underground Structures Standards

4" Hdg. Pipe (1/4" MIN Wall)


Filled with Concrete

Note: Lubricate in-ground


portion of the pipe to prevent
adhesion to the sleeve.

30"
5" Hdg. Pipe Sleeve
(1/4" MIN Wall)

3" MIN above


Finished Surface
30"
Concrete
Foundation

3"

6" MIN
Figure MS 830–1.3: Removable Barrier Detail

Barrier to be one of the following:


1. 4" MIN galvanized steel pipe
(1/4" MIN wall) filled with concrete
2. 8" x 8" reinforced concrete
3. Special barriers by prior SCE approval

30"

Grade

30"

3"

6" MIN
Figure MS 830–1.4: Protective Barrier Detail

1. Structures will normally be installed only in nontraffic areas. Protective barriers are to be used where construction exposes equipment to
traffic.
2. Tops of protective barriers are to be smooth cut and top edges are to be rounded.
3. At least one barrier is to be removable, with a means of lifting to support the weight of the barrier, when overhead obstacles prevent
equipment removal or installation by crane. See Figure MS 830–1.3 (Sheet 2). The location of the removable barrier(s) shall be approved
by the Underground Inspector.
4. Adequate clearance must be provided for doors, cooling radiators, and so forth.

Approved by:
MS 830
Sheet
Protective Barrier for Underground Distribution Structures

2 of 3 What’s Changed? On Figures MS 830-1.3 and MS 830 1.4, a 3" concrete foundation dimension Effective Date:
was added below the barrier to avoid corrosion.
UGS 01-30-2009
SCE Public
Underground Structures Standards

5. Protective barriers, as shown above, indicate typical requirements. Field conditions will necessitate changes for adequate equipment
protection. Application of protective barriers is site-specific.
6. The Underground Inspector in the field must approve all protective barrier installations prior to construction. The Underground Inspector
will determine (a) status of overhead obstructions, (b) the front and back of equipment foundations, and (c) the clearances required on
doors, cooling radiators, and so forth.
7. When a 72" x 94" pad is being installed, (a) increase the distance to 36 inches minimum between the protective barriers and the front edge
of the pad; and (b) increase the distance between the protective barriers and the back edge of the pad for capacitor bank (door side only)
to 36 inches minimum. The Underground Inspector will determine the front and back of this equipment foundation.
8. With prior SCE approval, the following alternatives may be used in lieu of protective barriers for padmounted structures:
a. When specified on working drawing, a 6-inch (minimum vertical face) concrete curb may be installed in place of protective barriers.
This curb must be at least 6 inches thick and its front face at least 60 inches (minimum spacing) from the equipment foundation.
b. When specified on working drawing for residential tract developments, protected barriers will not be required when there are rolled
curbs or 6-inch vertical face curbs that have at least 60 inches (minimum spacing) from the curb to the edge of the equipment
foundation.
c. Where equipment is located adjacent to a residential driveway, protective barriers may not be required when there is 30-inch
(minimum) clearance from the equipment foundation to the edge of the driveway. In addition, a 60-inch clearance shall be maintained
from a fire hydrant to a pole. Field conditions will necessitate changes for adequate equipment protection. If the minimum clearances
cannot be obtained, protective barriers are required.
9. With prior SCE approval, the following alternatives may be used in lieu of protective barriers for primary surface or semi buried structures
including BURD structures:
a. When specified on working drawing, a 6-inch (minimum vertical face) concrete curb, 8-feet in length may be installed in place of
protective barriers. This curb must be at least 6 inches thick.
b. Where there are rolled curbs or curbs that have less than 6-inches of vertical face, protective barriers may not be required when there
is at least 60 inches (minimum spacing) from the curb to the edge of the primary surface or semi buried structures. (See Figure MS
830-1.5)
c. Where equipment is located adjacent to a residential driveway, protective barriers may not be required when there is 30-inch
(minimum) clearance from the equipment foundation to the edge of the driveway. (See Figure MS 830-1.5)
d. Field conditions will necessitate changes for adequate equipment protection. If the minimum clearances cannot be obtained or there
is no curb, protective barriers shall be required.
e. In addition, a 60-inch clearance shall be maintained from a fire hydrant to a pole, transformers, PME switches, or any primary surface
or semi buried structure.

Residential 30" E T
Driveway MIN
Property Line

60" Placement for


Parkway 30" MIN Rolled Curb
MIN or Curb < 6" Vertical Face
Placement for
6" Box Curb

Street Street
Top of “X”

Figure MS 830–1.5: Placement of Primary or Semi-Buried Structure from Driveway

Approved by:
Protective Barrier for Underground Distribution Structures MS 830
Sheet
Effective Date: What’s Changed? 3 of 3
01-30-2009
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards

MS 840 Wheelchair Ramps


Scope MS 840.1 Wheelchair Ramps
Wheelchair ramps are required only when specified on the working drawings. They shall be constructed as shown
below in the location specified on the working drawings.

Figure MS 840–1: Wheelchair Ramps

Back of Walk
E.C.R E.C.R

Back of Walk Curb


Curb
A

B.C.R.
B.C.R.

Ra
dia
l Li
ne
W
2'
Ra

2'
dia

4'
lL
ine

A
4'

Standard Design and Location Standard Design and Alternate Location


Back of Walk
R/W

Y=5' MIN
(X) (W) (X)
Slope 1/4" per Foot 6"
Top of Curb 4' 4' 4'
3/8" Curb Face
Flow Line
4"

P.C.C
3/8"
Section A-A Curb Face Detail

Note(s):
1. Score lines are required at points “W” on all ramps.
2. Ramps shall have a rough broom finish transverse to the axis of the ramp. The finish must be rougher than the adjacent sidewalk.
3. Design my vary due to local regulations.

Approved by:
Wheelchair Ramps
Sheet
MS 840
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards

MS 850 Structure Offsets for Joint Construction


Scope MS 850.1 Structure Offsets for Joint Construction

Figure MS 850–1: Structure Offsets for Joint Construction

Floor

Floor
Other Utility

Wall

Edison Company

Wall

Location of Counduit Entrance

18" — For pull boxes


33" — When Edison manholes
and vaults are involved.

Plan — Section

Approved by:
Structure Offsets for Joint Construction MS 850
Sheet
Effective Date: What’s Changed? 1 of 1
01-26-2007
UGS
SCE Public
This page intentionally left blank.
Underground Structures Standards

MS 860 Inspection and Repair Procedures for Precast Vaults and Manholes
Scope MS 860.1 Inspection and Repair Procedures for Precast Vaults and Manholes
1.0 General
This procedure covers the inspection and repairs of cracks and/or spalling in precast concrete vaults,
manholes, and other similar structures.

2.0 Background
A main source of strength in precast concrete structures is provided by the rebar (reinforcing steel). The
principal component of the reinforcing steel is iron which has a persistent tendency to return to its natural
state, generally iron oxide, or rust. Whenever an excessive amount of heat or moisture is present, the
rebar will rust at a rapid rate. The presence of admixtures, such as calcium chloride, and moisture
increases the probability of rebar rusting.
When the rebar rusts, it begins to lose strength, but more importantly the rust occupies a much greater
volume than the iron from which it came. This rust exerts expansion pressures exceeding the ability of
even the strongest concrete to resist. The result is cracking and, if corrosion continues, concrete will spall
off. Such spalling is frequently accompanied by leaching of rust to the concrete surface, leaving unsightly
stains. Remedial action must be taken so that progressive deterioration does not ultimately threaten the
structure’s adequacy.
As stated above, structures that have high humidity and excessive heat are very likely to eventually start to
crack or spall.
A spall is a fragment of concrete, usually in the shape of a flake, detached from the larger mass by a blow,
by action of weather, or by pressure or expansion within the large mass. In the case of vaults, it is
frequently caused by expansion that accompanies the corrosion of reinforcing steel.

3.0 Inspection - Precast Vaults and Manholes


Cracks less than .012" wide are not an immediate source of concern. Cracks .012" wide or greater, or
spalling .375" deep or greater are of concern, especially in high moisture vaults or where excessive heat is
present. These cracks and spalls should be repaired, especially if the damage is extensive or cracks are
as wide as .062". If they are not repaired, they should be inspected periodically. Any cracks or spalling that
make the reinforcing steel visible should be repaired immediately. If a crack is 1/8" (.125") wide or more,
the Civil Engineering Section of the Engineering, Planning and Research Department should be called to
determine if the entire structure or roof should be replaced, or to provide detailed procedures for major
repairs. Generally, the precast supplier will look at the defect and give an opinion. Where insufficient
concrete cover (see GI 030) is found over the reinforcing steel, the supplier should be notified. It should be
noted that any structure under one year old (covered by warranty) that has cracks or spalling, as described
in GI 031, should immediately be brought to the attention of the contractor and/or supplier.
Vaults being inspected should be tested by hammering the walls. A hollow sound will indicate loose
concrete.
Note(s):
1. Before replacing any defective concrete, the supplier should be notified in order to determine if he/she is liable for any portion of the repair.

Approved by:
Inspection and Repair Procedures for Precast Vaults and Manholes MS 860
Sheet
Effective Date: What’s Changed? 1 of 4
01-26-2007
UGS
SCE Public
Underground Structures Standards

4.0 Inspection - Vault Covers


Any cracks are a concern when they appear in vault covers. When the cracks appear to be emanating from
the ladder inserts, it could indicate corrosion of the inserts or rebar is taking place, demonstrating that a
general weakening of the cover is occurring. This should be of great concern if the cover is in a heavy
traffic area. The supplier and/or contractor and Civil Engineering should be contracted for advice on
replacement. Cracks .062" wide or greater in a cover indicates a faulty cover and it should be replaced.

5.0 Repair Procedure — Cracks

5.1 General
Cracks should be repaired by injecting epoxy grout under pressure into the crack. The procedure
for preparation and application of the epoxy injection shall be in accordance with the
manufacturer’s recommendations and as described below:

A. Cracks to be filled shall be cleaned of dust, silt, and any other material that would impair bond
of the epoxy to the concrete. For small cracks, cleaning shall be done by vacuuming. Large
cracks may be blown out with compressed air.

B. Suitable fixed injection ports shall be established along the cracks at intervals not less than the
thickness of the concrete being injected. At the end of a crack, the first port shall be about half
this distance from the end.

C. The surface of the crack between ports on both faces of the structure, if they are accessible,
shall be sealed with tape or other temporary surface sealant which is capable of retaining the
epoxy adhesive in the crack during pressure injection and until the epoxy has hardened.
Sealing tape and/or temporary surface sealant should remain in place until the epoxy has
hardened.

D. Epoxy adhesive shall be pumped into the cracks through the injections ports. The pump, hose,
injection gun, and appurtenances shall be capable of injecting the epoxy at a sufficient rate and
pressure to completely fill all designated cracks. The temperature of the concrete shall be not
less than 45°F at the time the epoxy is injected.

E. Before starting injection work and at hourly intervals during injection work, a sample of mixed
epoxy shall be taken from the injection gun. Should these samples show any evidence of
improper proportioning or mixing, injection work shall be suspended until the equipment or
procedures are corrected.

F. The epoxy adhesive shall be forced into the first port at one end of a crack until adhesive runs
in substantial quantity from the next adjacent port. The first port shall then be sealed and
injection started at the next port where the epoxy has just begun to show. Injection shall then
continue from port to port in this manner until the crack is fully injected. For slanting or vertical
cracks, pumping shall start at the lower end of the crack and progress upward. Where
approximately vertical and horizontal cracks intersect, the vertical crack below the intersection
shall be injected first. For horizontal structural elements, the crack shall be injected from the
bottom of the element, filling upward.

Approved by:
MS 860
Sheet
Inspection and Repair Procedures for Precast Vaults and Manholes

2 of 4 What’s Changed? Effective Date:

UGS 01-26-2007
SCE Public
Underground Structures Standards

5.2 Injection Equipment

A. Automatic pressure injection systems shall contain positive displacement pumps with variable
feedrate to ensure components are mixed at the correct ratio.

B. The recommended injection pressure for epoxy injection shall be 10 to 15 psi at the beginning
of the injection at each injection location. The pressure may be gradually increased to 20 to 25
psi if the injection progresses too slowly. The maximum injection pressure should not exceed
75 psi.
For best results, it is recommended that lower injection pressure, in the range of 10 to 25 psi,
and slower injection progressive speed be maintained at all times. This can be verified with the
use of a pressure gauge located on the discharge side of the mixer.

C. Transparent reservoirs shall be used to verify that the ratio of the components mixed are in
accordance with manufacturer’s recommendations. Metering systems shall be used to ensure
mixing accuracy is within 2%.

5.3 Material

A. Epoxy shall be a two-component, waterproof system specifically manufactured for use in filling
cracks by means of pressure injection. All epoxy resin shall conform to the requirements of the
American Society for Testing and Materials (ASTM) Standard Specification for Epoxy Resin
Base Bonding Systems, ASTM C 881.

B. The following are approved epoxies and suppliers:

1. Sikadur 52 Injection Resin by Sika Corporation

2. Ceilcote 647 Repair Grout by Ceilcote General Signal

3. Other materials may be submitted for approval.

6.0 Repair Procedure — Spalls

6.1 Preparation

A. Remove all loose material to sound concrete. The perimeter of the prepared area should have
perpendicular edges with a minimum depth of 1/8".

B. Concrete shall be chipped to a minimum clearance of one inch all around corroded reinforcing
bars. The exposed bars shall be cleaned of corrosion.

C. Existing concrete surface at the repairing area shall be roughened to a minimum magnitude of
1/8" and shall be damaged with water prior to patching.

D. If the diameter of the rebar is reduced by 1/16" or more, additional reinforcement shall be
installed. Precast manufacturers should be contacted for installation details.

Approved by:
Inspection and Repair Procedures for Precast Vaults and Manholes MS 860
Sheet
Effective Date: What’s Changed? 3 of 4
01-26-2007
UGS
SCE Public
Underground Structures Standards

6.2 Patching
Overhead grout patches shall be applied in layers not to exceed 1/2" in thickness.

6.3 Materials
All materials to be applied in accordance with manufacturer’s recommendations.
Nonshrink Grouts Manufacturer

Sika Top 122 and 123 Repair Mortars Sika Corporation


Masterpatch DOT Repair Mortar Master Builders
Five-Star Nonshrink Grout U.S. Grout Corporation

Nonshrink grouts from manufacturers other than those listed above are subject to Edison approval
before use.

7.0 Repair Procedure - Vault Covers


Generally, covers cannot be repaired. Replacement of covers may require neck replacement also. Utility
Vault and Jensen covers can be replaced. Contact the individual supplier for more information on cover
replacement.

8.0 Documentation of Repairs

8.1 When repairs are made, the following information should be recorded on a 3" x 5" card.

A. Date of repair

B. Materials used

C. Contractor

D. Brief description of repairs

8.2 The card should be placed in a watertight container and left in a conspicuous location in the vault. A
sealable plastic map container (M/C 061-31007) is available for this application.

Approved by:
MS 860
Sheet
Inspection and Repair Procedures for Precast Vaults and Manholes

4 of 4 What’s Changed? Effective Date:

UGS 01-26-2007
SCE Public
Underground Structures Standards

MS 870 Removable Curb for 4' x 5' Vault Covers and Manhole Covers
Scope MS 870.1 Removable Curb for 4' x 5' Vault Covers and Manhole Covers

Figure MS 870–1: Removable Curb for 4' x 5' Vault Covers and Manhole Covers

2-1/8" x 1/4" Vault Cover — 76"


See Note 2. Manhole Cover — 49"
11-9/32"
Curb Offset
See Note 1.

3/8" Threaded
Inserts Centered Variable
in Recess (See Cover Plate 1 Cover Plate 2 Cover Plate 3
Notes 4 and 5.) C/L

Curb Top

Curb Face

Manhole Cover

5" Cover Necking


Gutter
(4 Sides)

Vault Cover
2-1/8" x 1/4"
Recess Top View
Curb Face
(See Note 2.)

Cover Plate 1 Cover Plate 2 Cover Plate 3

Cover Necking
Gutter Line
Vault Cover

Front View

Note(s):
1. The three-sided offset curbing around the vault necking, or manhole necking, shall be constructed to the dimensions of the existing or
proposed curbing.
2. A 2-1/8" wide by 1/4" deep recess shall be placed on top of the offset curb, and curb face, as shown on the drawing.
3. Three plate covers are required for 4' x 5' vault covers. Manhole covers require two plate covers (plate #1 and 3).
4. Threaded 3/8" inserts shall be placed in the 2-1/8" wide curb recesses, to the dimensions shown on the “Top View” drawing. A minimum of
five inserts are required for the 4' x 5' vault cover, four for a manhole cover.
5. Whenever the plate depth exceeds 36", an additional insert, equally spaced, shall be placed into the recess of the offset curbing sides.
6. For steel cover plate details, see Scope MS 870.2 (Sheet 2).

Approved by:
Removable Curb for 4' x 5' Vault Covers and Manhole Covers MS 870
Sheet
Effective Date: What’s Changed? 1 of 2
01-26-2007
UGS
SCE Public
Underground Structures Standards

Scope MS 870.2 Removable Curbing (Steel Cover Plates)

Figure MS 870–2: Removable Curbing (Steel Cover Plates)

5"

2" x 2" x 1/4" Steel L 3/4"


2 Required 1"
(See Note 2.) 1" Dia. Lift
Hole (2 Places)
1"
Variable
Length
7/16" Holes Countersunk
for 3/8" S.S. Flathead
1/4" Steel Screws (3 Places MIN)
Floor Plate 5"

26-9/16"

Side See Note 4. Cover Plate #1 Top

1-3/4"

2" x 2" x 1/4" Steel L 3/4" Plate 2


1"
2 Required 1" Plate 3
3"
(See Note 2.)
13/16"

Threaded Hole
for 3/8" S.S.
Flathead Screw 7/16" Holes
Weld Countersunk
for 3/8" S.S.
1" Flathead
1" Dia. Lift Hole Screws
(2 Places) (2 Places MIN)

Angled Floor Plate


Face (See Note 3.)
26-9/16"
See Note 4.
Side Cover Plates #2 and 3 Top

Note(s):
1. Nonskid 1/4" thick steel floor plates shall be constructed to the dimensions shown. See MS 860 for plate location sequence on curb offset.
2. The 2" x 2" x 1/4" steel L shall be welded to the top and angled floor plate face.
3. Angled floor plate face may be bent or welded in place to the top plate.
4. Angle and depth of floor plate face shall match standard curb.
5. A minimum of seven 3/8" stainless steel flathead screws are required for the 4' x 5' vault cover plates, and a minimum of five screws for the
manhole plates.
6. All plate covers, after fabrication, shall be covered with one coat of Subalox #511FD primer, and then with one coat of Subox #5FD light
gray paint.

Approved by:
MS 870
Sheet
Removable Curb for 4' x 5' Vault Covers and Manhole Covers

2 of 2 What’s Changed? Effective Date:

UGS 01-26-2007
SCE Public
Underground Structures Standards

MS 890 Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers
Scope MS 890.1 Electrolier Foundation Detail

Figure MS 890–1: Electrolier Foundation Detail


30" Square or
20" Dia. Round

12-1/2"
8-7/8"

Electrolier 12-1/2" Bolt Circle

Four 1" Anchor Bolts and Nuts


meeting ASTM A-307

Concrete Apron
(See Note 5.) 24" (MIN)

4" Electrolier Curb

Flow Line
30" (MIN)
“H” — See Note 1.

“B” 30" (MIN) Below Flow Line


45" (MIN) for CIC

1-1/2" Conduit for


B = 30" for H ≤ 3'-0"
Conventional
B = 36" for H ≥ 3'-6"
Underground

4" (Typ.)
3" (MIN) Clearance
“D”
CIC Sleeve (See Note 3.)

Note(s):
1. The footing depth will vary depending on the type of soil and wind loading requirements. Consult local government agency for
requirements. See Table MS 890–1 (Sheet 4) through Table MS 890–4 (Sheet 5).
2. Foundation shall be installed after conduit or CIC (for Underground Service), curbs, and sidewalks are in place and grades are established.
3. 1-1/2" Plastic CIC Sleeve for UG Concrete Electrolier (tape both ends to prevent debris from entering the sleeve).

Approved by:
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers MS 890
Sheet
Effective Date: What’s Changed? 1 of 5
01-26-2007
UGS
SCE Public
Underground Structures Standards

4. Concrete to reach a minimum compression strength of 2800 psi in 28 days. See UGS 20.3.
5. Place a minimum size concrete apron of 30" x 30" x 4" thick around the pole at the ground level to provide a constrained surface condition
when required. Grout to be placed after pole is set and plumbed.

Approved by:
MS 890
Sheet
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers

2 of 5 What’s Changed? Effective Date:

UGS 01-26-2007
SCE Public
Underground Structures Standards

Scope MS 890.2 Marbelite Nostalgic Electrolier Foundation Detail

Figure MS 890–2: Marbelite Nostalgic Electrolier Foundation Detail


30" Square or
24" Dia. Round
22"
15-9/16"

Electrolier 22" Bolt Circle

Four 1" Anchor Bolts and Nuts


meeting ASTM A-307

Concrete Apron
24" (MIN)

4" Electrolier Curb

Flow Line
30" (MIN)

“B” 30" (MIN) below Flow Line


45" (MIN) for CIC

1-1/2" Conduit for


B = 30" for H ≤ 3'-0"
Conventional
B = 36" for H ≥ 3'-6"
Underground

4" (Typ.)
3" (MIN) Clearance
“D”
CIC Sleeve
Note(s):
1. The footing depth will vary depending on the type of soil and wind loading requirements. Consult local government agency for
requirements. See Table MS–1 (Page MS-21) through Table MS–4 (Page MS-22).
2. Foundation shall be installed after conduit or CIC (for Underground Service), curbs, and sidewalks are in place and grades are established.
3. 1-1/2" Plastic CIC Sleeve for UG Concrete Electrolier (tape both ends to prevent debris from entering the sleeve).
4. Concrete to reach a minimum compression strength of 2800 psi in 28 days. See UGS 20.3.
5. Place a minimum size concrete apron of 30" x 30" x 4" thick around the pole at the ground level to provide a constrained surface condition
when required. Grout to be placed after pole is set and plumbed.

Approved by:
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers MS 890
Sheet
Effective Date: What’s Changed? 3 of 5
01-26-2007
UGS
SCE Public
Underground Structures Standards

Scope MS 890.3 Electrolier Foundation Requirements


Table MS 890–1: 70 MPH Wind Zone, Constrained Surface Condition
Electrolier Foundation Requirements

Soil Type Fiberglass, Concrete, or Steel Nostalgic

23' Shaft 28' Shaft All Poles Fiberglass Marbelite


a/
Per UBC H D H D H D D

2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 3'-0" 20" dia. 3'-0" 20" dia. 24" dia
III. Sandy Gravel, Gravel
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 3'-6" 20" dia. 3'-6" 20" dia. 3'-6" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 4'-0" 20" dia. 4'-6" 20" dia. 4'-0" 20" dia. 24" dia.
V.
Clay, Clayey Silt 2'-6" 30" x 30" 3'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30'
a/
Uniform Building Code — 1991

Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.

Table MS 890–2: 70 MPH Wind Zone, Non-Constrained Surface Condition


Electrolier Foundation Requirements

Soil Type Fiberglass, Concrete, or Steel Nostalgic


23' Shaft 28' Shaft All Poles Fiberglass Marbelite
a/
Per UBC H D H D H D D

2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 3'-6" 20" dia. 3'-0" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-6" 20" dia. 4'-0" 20" dia. 3'-6" 20" dia. 24" dia
III. Sandy Gravel, Gravel
3'-0" 30" x 30" 3'-0" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 4'-0" 20" dia. 4'-6" 20" dia. 4'-0" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 3'-0" 30" x 30" 3'-6" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 4'-6" 20" dia. 5'-0" 20" dia. 4'-6" 20" dia. 24" dia.
V.
Clay, Clayey Silt 3'-6" 30" x 30" 4'-0" 30" x 30" 3'-6" 30" x 30" 30" x 30'
a/ Uniform Building Code — 1991

Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.

Approved by:
MS 890
Sheet
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers

4 of 5 What’s Changed? Effective Date:

UGS 01-26-2007
SCE Public
Underground Structures Standards

Table MS 890–3: 90 MPH Wind Zone, Constrained Surface Condition


Electrolier Foundation Requirements

Soil Type Fiberglass, Concrete, or Steel Nostalgic


23' Shaft 28' Shaft All Poles Fiberglass Marbelite
a/
Per UBC H D H D H D D

2'-6" 20" dia. 2'-6" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 3'-6" 20" dia. 3'-0" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
3'-0" 20" dia. 4'-0" 20" dia. 3'-6" 20" dia. 24" dia
III. Sandy Gravel, Gravel
3'-0" 30" x 30" 3'-0" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 4'-0" 20" dia. 4'-6" 20" dia. 4'-0" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 3'-0" 30" x 30" 3'-6" 30" x 30" 3'-0" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 4'-6" 20" dia. 5'-0" 20" dia. 4'-6" 20" dia. 24" dia.
V.
Clay, Clayey Silt 3'-6" 30" x 30" 4'-0" 30" x 30" 3'-6" 30" x 30" 30" x 30'
a/ Uniform Building Code — 1991

Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.

Table MS 890–4: 90 MPH Wind Zone, Non-Constrained Surface Condition


Electrolier Foundation Requirements

Soil Type Fiberglass, Concrete, or Steel Nostalgic

23' Shaft 28' Shaft All Poles Fiberglass Marbelite


a/
Per UBC H D H D H D D

2'-6" 20" dia. 3'-0" 20" dia. 2'-6" 20" dia. 24" dia.
I. Massive Crystalline Bedrock
2'-6" 30" x 30" 2'-6" 30" x 30" 2'-6" 30" x 30" 30" x 30"
4'-0" 20" dia. 4'-0" 20" dia. 4'-0" 20" dia. 24" dia.
II. Sedimentary and Foliated Rock
3'-0" 30" x 30" 3'-0" 30" x 30" 3'-0" 30" x 30" 30" x 30"
5'-0" 20" dia. 5'-6" 20" dia. 5'-0" 20" dia. 24" dia
III. Sandy Gravel, Gravel
3'-6" 30" x 30" 4'-0" 30" x 30" 3'-6" 30" x 30" 30" x 30"
Sand, Silty Sand, Clayey Sand, 5'-6" 20" dia. 6'-0" 20" dia. 5'-6" 20" dia. 24" dia.
IV.
Silty Gravel, Clayey Gravel 4'-0" 30" x 30" 4'-6" 30" x 30" 4'-0" 30" x 30" 30" x 30"
Clay, Sands, Sandy Clay, Silty 6'-0" 20" dia. 6'-6" 20" dia. 6'-0" 20" dia. 24" dia.
V.
Clay, Clayey Silt 4'-6" 30" x 30" 5'-0" 30" x 30" 4'-6" 30" x 30" 30" x 30'
a/
Uniform Building Code — 1991

Note(s):
1. H = Depth of footing
2. D = Diameter of round footing or the side dimension of square footing.

Approved by:
Foundation Detail for Fiberglass Nostalgic, Fiberglass, Steel, or Concrete Electroliers MS 890
Sheet
Effective Date: What’s Changed? 5 of 5
01-26-2007
UGS
SCE Public
This page intentionally left blank.

Você também pode gostar