Escolar Documentos
Profissional Documentos
Cultura Documentos
26
NEW YORK
FEELS THE HEAT
For a city that’s a byword for
bright lights, surely New York
should be able to keep the power
on? Laurie Wiegler investigates
July’s nine-day outage
THIS SUMMER, in the middle of a heat the verge of collapse, while others had Queens substation to Astoria, Long Island
wave, around 100,000 people in the New actually filed for bankruptcy, according to City, Woodside, Sunnyside and Hunters Point
York borough of Queens endured a massive Sunnyside-based Council Member Eric Gioia, as well as La Guardia Airport and the Rikers
power failure that lasted over a week and who spoke at one hearing. “What happened Island jail complex. At the height of the crisis,
left the local utility company, Con Edison to our community should never happen to 10 of the network’s 22 primary feeders had
(Con Ed), publicly floundering as it struggled another,” Gioia said, while other speakers stopped working.
to restore service. railed against the “antiquated and In its report, Con Ed states that at
Up to nine days without power in record- inadequate” electrical distribution system 3.30pm on Monday 17 July, one 27kV
setting heat meant severe hardship for serving north west Queens. primary feeder went out. In the subsequent
thousands – and even death for a few. Con Ed, with its people and resources several hours, another five feeders failed.
Moreover, families in the affected tied up in restoration efforts and ongoing Following this, the network operator
neighbourhoods lost significant amounts of investigations into what happened, was reduced voltage by 8% to cut demand and
food or parts of their livelihood (for which unable to provide a spokesman for customers using life-support equipment
Con Ed is currently offering a partial comment at the time of writing, but much were contacted. The New York City Office of
reimbursement). Business and transport can be learned from its ‘Initial Report on the Emergency Management was also informed
were also disrupted. Power Outages in Northwest Queens’, dated of the problems and the impact on major
The regulator for utilities in New York 2 August and submitted to Mayor Michael customers such as La Guardia, Rikers Island,
State is the Public Service Commission, Bloomberg. the Bowery Bay Water Treatment Plant and
which organised a series of hearings in The problems occurred within the Long the Metropolitan Transit Authority.
August to investigate the impact of the Island City (LIC) network, an underground The next day, after initial repairs were
blackout. By then, some businesses were on system that provides electricity via the North completed, and with temperatures rising