Você está na página 1de 2

ANALYSIS

26

NEW YORK
FEELS THE HEAT
For a city that’s a byword for
bright lights, surely New York
should be able to keep the power
on? Laurie Wiegler investigates
July’s nine-day outage

Con Ed employees worked round


the clock to cope with the
cascading failures
[Getty]

THIS SUMMER, in the middle of a heat the verge of collapse, while others had Queens substation to Astoria, Long Island
wave, around 100,000 people in the New actually filed for bankruptcy, according to City, Woodside, Sunnyside and Hunters Point
York borough of Queens endured a massive Sunnyside-based Council Member Eric Gioia, as well as La Guardia Airport and the Rikers
power failure that lasted over a week and who spoke at one hearing. “What happened Island jail complex. At the height of the crisis,
left the local utility company, Con Edison to our community should never happen to 10 of the network’s 22 primary feeders had
(Con Ed), publicly floundering as it struggled another,” Gioia said, while other speakers stopped working.
to restore service. railed against the “antiquated and In its report, Con Ed states that at
Up to nine days without power in record- inadequate” electrical distribution system 3.30pm on Monday 17 July, one 27kV
setting heat meant severe hardship for serving north west Queens. primary feeder went out. In the subsequent
thousands – and even death for a few. Con Ed, with its people and resources several hours, another five feeders failed.
Moreover, families in the affected tied up in restoration efforts and ongoing Following this, the network operator
neighbourhoods lost significant amounts of investigations into what happened, was reduced voltage by 8% to cut demand and
food or parts of their livelihood (for which unable to provide a spokesman for customers using life-support equipment
Con Ed is currently offering a partial comment at the time of writing, but much were contacted. The New York City Office of
reimbursement). Business and transport can be learned from its ‘Initial Report on the Emergency Management was also informed
were also disrupted. Power Outages in Northwest Queens’, dated of the problems and the impact on major
The regulator for utilities in New York 2 August and submitted to Mayor Michael customers such as La Guardia, Rikers Island,
State is the Public Service Commission, Bloomberg. the Bowery Bay Water Treatment Plant and
which organised a series of hearings in The problems occurred within the Long the Metropolitan Transit Authority.
August to investigate the impact of the Island City (LIC) network, an underground The next day, after initial repairs were
blackout. By then, some businesses were on system that provides electricity via the North completed, and with temperatures rising

Engineering & Technology | September 2006 | www.theiet.org/engtechmag


ANALYSIS
27
above 33°C, more feeders began to fail. neighbourhoods, looking for buildings with advisory panel, Russell arrived in Manhattan
Con Ed states that by 8.38pm on Tuesday no lights on. on the night of 16 July, a trip planned two or
18 July it had lost 10 of its 22 primary In general, Burke went on, the network three months in advance of the outage. As
feeders, requiring consistent reduction of system is highly reliable. “In fact, our to what caused the record power cuts,
electricity usage in the affected areas. The networks are designed to allow for the loss Russell says his comments now are “pure
report states that usage was reduced by an of any two primary feeders, at peak summer speculation”, but feels that the cables were
estimated 43MW on 18 July and 67MW on consumption levels, without any impact on stressed “due to heavy loads by summer
19 July. Peak demand fell from 382MW on customers. But the loss of 10 feeders peaks and hot weather”.
17 July to 224MW two days later. caused significant stress that damaged the Global warming not withstanding – and
Eventually, with Con Ed staff working secondary system and created a difficult New York did endure its share of above-
round the clock and back-up support from challenge for our crews.” average days – other hot cities managed to
other utilities and contractors, all the primary That is not the only challenge Con Ed keep on the lights and air conditioning. The
feeders were restored to service by morning currently faces. The extraordinary outage, which Paris Metro was still running, as was the
of Friday 21 July. However, knock-on damage was broadcast in media outlets around the London Underground. Even California, one of
to the 120/208V secondary grid meant that world, created a public relations nightmare. the hottest states in the nation, had some
around 25,000 customers were still without This is the same utility that could proudly tout outs, but didn’t lose as many days of power
power. Most had service restored by Sunday, its help as part of the Mutual Assistance as Queens did.
but it was not until the morning of Wednes- programme in restoring power to New Orleans So what went wrong in New York? Russell
day 26 July that every customer had last year (see ‘The Challenge For Those in says: “Systems are designed with safety
electricity once more. Power’, IEE Review, November 2005). Con Ed, factors so they can withstand the loss of
In the midst of this, naturally Con Ed was with its unique experience in underground substations, but if several primary feeders are
receiving a flurry of calls from its customers systems, had been brought in by Entergy, the out, [the situation is problematic]. And the
– nearly 2000 calls by the end of the day on local utility, to help during the crisis. outage was caused, to the best of my
Wednesday 19 July. Usually a strong A spokesperson for Entergy says of knowledge, by the loss of more than the
barometer for affected outages, the system Con Ed’s situation that “the problem is not maximum number of cables that can be
failed the utility this time. For, based on the unique to New York in any way, shape or sustained to give service to a given area.”
number of calls, the utility significantly form. Any electrical company feeding Perhaps. New York City Attorney General
underestimated the extent of the problem. customers through a substation can Elliott Spitzer believes the outage could have
Kevin Burke, CEO of Con Ed, addressing experience a problem like this. New York is been avoided. Spitzer points out that, in
the New York City Council’s Consumer Affairs like New Orleans in that there is a huge March 2000, his office issued a report
Committee, admitted that the company concentration of people in a small area, so detailing the causes of a 1999 blackout,
needs a better way to monitor failures. when one substation fails it affects a large “including Con Ed’s failure to address the
Unlike overhead supply systems, he number of people.” effects of heat on its underground feeder
explained, a network system provides many The spokesperson called the New York cables, its inability to identify components at
possible paths for electricity to take to supply heat wave and its subsequent power risk of failure and its failure to recognise the
the customer. “As a result, on the network problems “the perfect storm” in terms of the scope of the problem.”
system, while we know that a certain feeder ripple effect of outages. Further, unlike Six years on, says Spitzer, “it is clear that
or transformer is out of service, we do not overhead systems – which are the norm in Con Ed did not heed the warnings from the
necessarily know that any customers are out the US – underground systems take much earlier blackout, and that the PSC’s oversight
unless they tell us,” he said. longer to repair, because damage isn’t of the utility has been wholly inadequate”.
“During this period, operating personnel immediately visible or accessible. Recommending that the PSC should develop
were reviewing information from various Electrical engineering professor B. Don a test for detecting equipment vulnerable to
systems,” Burke continued. “Individual Russell, from Texas A&M University, says heat stress, overload or other sudden
feeders were being monitored and the “when you have a totally buried cabling failures, establish a protocol for power grid
ongoing feeder repairs, testing and system it takes longer to fix … Most of the management, and improve crisis
restoration systems closely coordinated. US is served by overhead lines. They’re very communications, among other actions, he
Operators continuously assessed the easy to take out … [but the underground concludes: “It is imperative that the steps are
condition of the LIC network.” lines are the more] dangerous and difficult implemented as soon as possible to avoid
However, as it became apparent that task to fix.” problems in the future”. ■
power losses were much more widespread Russell says he just happened to be in Con Ed’s preliminary report is online at:
than indicated by the number of calls, New York assisting Con Ed when the outage www.coned.com/messages/Mayors%20
Con Ed resorted to surveying the affected occurred. As part of a three-person safety Report.pdf

Engineering & Technology | September 2006 | www.theiet.org/engtechmag

Você também pode gostar