Escolar Documentos
Profissional Documentos
Cultura Documentos
TABLE OF CONTENTS
3.5 Noise....................................................................................................................................................... 9
Appendix 1 - Maps
1. GENERAL INFORMATION
Both projects will be hereafter referred to as the “Kent Breeze Wind Farms”.
Project 2 – Part Lots 4-6, Concession 1 & 2, in the geographic Township of Camden,
in the Municipality of Chatham-Kent, on the north and south side of Smoke Line, west
of Huffs Side Road.
May 2010
IBI GROUP REA PROJECT DESCRIPTION REPORT
Kent Breeze Corporation
MacLeod Windmill Project Inc.
KENT BREEZE WIND FARMS
1.3 Contacts
1.3.1 NAME OF APPLICANTS
The applicants are Kent Breeze Corporation and MacLeod Windmill Project Inc., which share the
same owners, located within the Municipality of Chatham-Kent. The principal contact for the
applicants is:
Brad West
Suncor Energy Services Inc.
Manager, Business Development, Wind
P.O. Box 38
112 - 4th Avenue S.W.
Calgary, AB T2P 2V5
Tel: 403-205-6744
Fax: 403-269-6223
Email: brwest@suncor.com
Jack Jensen
Technical Advisor, ecoENERGY for Renewable Power
Renewable and Electrical Energy Division
Natural Resources Canada
Tel 613-943-7008
Fax 613-995-8343
jjensen@nrcan.gc.ca
2. PROJECT INFORMATION
The electricity generated by each turbine will be transformed to 27.6kV the same voltage as the
local distribution system. Thus, there are no electrical transformers or transmission lines associated
with either of the projects.
Total lot coverage (ie. the area of land covered by the components outlined above) will be
approximately 120,000 m², or 2.8% of the project areas.
The project includes three phases: construction, operations, and decommissioning. Construction
includes the delivery of materials including, heavy machinery, metal re-bar and wiring, which will be
stored temporarily at the construction service area and temporary storage area which are shown on
Map 6. Temporary office areas will be established within the existing dwelling shown on Map 6.
Access roads, underground cabling routes, and turbine staging areas will be cleared of crops and
graded for construction to a width of 10 metres. Topsoil will be stripped and stockpiled separately
from subsurface soil and kept for remediation activities post construction. Aggregate for the access
roads and turbine staging areas will be delivered on-site as required by local firms. A rubber tire
backhoe or trenching machine will excavate a trench for underground cabling. Directional drilling
will be required under train tracks and under surface drains.
Completion of the roads and underground cabling will provide access for excavating for turbine
foundations. Due to the soil conditions at the site it is anticipated that piling will be required at each
foundation to anchor the turbines to bedrock located approximately 10 to 15 m below grade.
Concrete for the turbine foundations will be delivered and the foundation cap will be secured to the
piles. Following curing of the concrete, turbines will be delivered and temporarily laid down
adjacent to foundation areas. The length of time for the erection of the wind turbine components is
dependent on weather conditions specifically lower wind speeds for safe crane operation. In
parallel with the erection of turbines foundations will be poured for up to two switching stations. The
switching stations will be delivered to site, installed on the foundations and all underground cabling
from the turbines will be terminated there. The switching stations will house only electrical control
cabinets and SCADA operating system. Hydro One will install up to two wooden hydro poles to
mount a disconnect switch. Hydro One will also connect the facility to their distribution grid.
Access Roads will be reduced to 6 metres in width as the final part of construction by removing the
excess gravel from the site and reclaiming the farm land with stockpiled top soil. The remaining
roads will be graded with the same slope as the adjacent fields such that surface runoff will not be
interrupted.
The operational phase will include electrical generation by the wind turbines. The turbines will be
controlled and monitored remotely. The project will maintain a minimum of one full-time employee
to co-ordinate ongoing maintenance, emergency response, and public communications. Remote
monitoring will include meteorological monitoring as well as monitoring of all operational data of
each individual wind turbine. This information will be used to monitor the performance of the
machines and to identify maintenance issues early. During the operational phase of the projects,
on-site activities will generally be limited mostly to scheduled maintenance. Additional activities that
will or may occur during the operational phase includes:
Field monitoring for impacts to bird and bat populations within the first 3 years of
operation;
The decommissioning phase involves the removal of the project from the lands either due to project
abandonment, or after the technology has reached its operational lifespan. This phase will involve
the following activities:
Removal of wind turbines, meteorological tower, and switching station from site for
salvage;
Internal access road and driveways will be retained for agricultural purposes.
It is expected that project construction will take approximately six (6) months to complete.
Operation of the projects will last approximately 20 years with the expectation to possibly renew /
refit the project based on future policy regimes. Otherwise, the project would be decommissioned
which would take approximately three (3) months.
Construction of the project will begin as soon as building permits are granted by the Municipality of
Chatham-Kent. Our expected construction commencement date will be late Summer 2010.
There are currently no plans to expand the project beyond its current scope.
Waste and emissions associated with the construction phase will involve typical construction noise,
dust, vehicular emissions, and lubricating fluids associated with typical heavy construction activities.
Waste and emissions associated with operations will be limited to vehicular emissions of periodic
maintenance vehicles and operational noise associated with the turbines. Waste and emissions
associated with the decommissioning phase will involve typical construction noise, dust, vehicular
emissions, and handling of lubricating fluids associated with typical heavy construction activities.
Disposal of hazardous wastes will only be required for accidental spills and will be addressed in a
manner consistent with Provincial guidelines. More specific details are outlined in the Construction
Plan Report, Design and Operations Report, and the Decommissioning Plan Report.
2 . 3 . 5 S T O R M , S E WE R A N D W A T E R - T A K I N G A C T I V I T I E S
The Projects do not involve the any sewage activities. Storm water at the site runs over ground,
permeates into the ground or is diverted by agricultural tile drainage to a network of open and
closed municipal drainage ditches. The installation of the wind farm will have very little impact to
the existing storm water management as all damaged agricultural drainage tiles will be fixed and
turbine access roads will be designed as low profile roads such that surface water can run over
them with the natural grade of the land. Water-taking activities will be limited to the construction
phase at the turbine foundations and will not exceed 50m³ per day based on the existing soil
conditions, depth of the water table (approximately 5 metres below ground surface), and shallow
depth of concrete foundations (approximately 2.5 metres below ground surface) poured for the
turbines. The proponent is aware that exceeding 50m³ per day triggers the requirement for an
additional permit to take water, and confirms it will not exceed this specified limit as a condition of
this REA.
De-watering activities from the foundations will only occur periodically after rain events as surface
water accumulates in the excavation. Because dewatering will be kept below 50m³ per day and
is only to keep excavations clear of water, and those excavations will have a maximum depth of
2.5m, it is not expected that local water levels, including those for private wells, will be impacted.
Since such activities will be temporary in nature, occurring over a 4 month period, after which the
excavations will be filled in, there will not be any permanent impact to water levels. In the unlikely
event that local wells are temporarily impacted, the proponent will provide potable water through
temporary portable tanks. Water taken from the excavations will be pumped over the surrounding
agricultural fields; to prevent silt from entering into drainage ditches, screens will be used at pump
inlets and silt bags at the outlets as per the BMP identified in the stormwater management memo.
3. ENVIRONMENTAL EFFECTS
In addition to the archaeological assessments, a Built Heritage and Cultural Landscape Study was
undertaken in the fall of 2009. The results of this study were that the location of project
components would have no direct impacts on any such heritage resources. Clearance from the
Ministry of Culture for this report was obtained in writing in a letter dated June 23, 2010 (Appendix
2).
Background work conducted with respect to the natural heritage resources included a one (1)
kilometre study area surrounding the subject lands and indicates the following regarding the
proposed projects:
Possible presence of two significant faunal species (Azure Bluet Damselfly, Eastern
Fox Snake) within the study area but located within woodlots that will not be physically
altered in any manner by any components of the projects;
Majority of unnamed tributaries converted into farm drains on subject lands. Further
consideration to impacts created where crossings are required. The Lower Thames
Valley Conservation Authority and St. Clair Region Conservation Authority has been
consulted in connection with this project and will be responsible for granting permits
where any water crossings are required.
Bald eagle nesting location was confirmed as being over 1km south of the project
area, which is beyond the 800m tertiary buffer for such nesting locations as described
by the Ministry of Natural Resources;
Vertical distribution of birds observed during spring migration were primarily (93%)
identified within 40 metres of ground (ie. below blade swept area);
Bat research indicated no significant bat habitat and a low site sensitivity rating.
The Ministry of Natural Resources has confirmed the background findings and issued a letter of
clearance on June 7, 2010 (Appendix 2).
Final design indicates that there are no permanent watercourses within the project area that will be
impacted by any components of the projects. There are no at-grade water crossings required over
any open municipal drains. Two direct drilling operations beneath drains are required for
underground cabling and will be constructed within the St. Clair River Conservation Authority’s
(SCRCA) jurisdiction, where a permit is required. Within the jurisdiction of the Lower Thames
Valley Conservation Authority’s (LTVCA), 30 days notice is required prior to drilling, and the LTVCA
will have a representative on site to supervise the activity. The LTVCA has published a procedure
for directional drilling under drains, and the Kent Breeze construction team will follow this
procedure. The observer will verify the procedure is followed. The SCRCA and LTVCA have
reviewed such crossings with no issues identified.
The conservation authorities act as the representatives for the Department of Fisheries and
Oceans. Since the drains being crossed are warm water agricultural drains, they have a low
potential for fish habitat. The directional drilling beneath the drains will follow DFO standard
operational procedures to avoid impacts on fish habitat.
There are no navigable waterways located on the subject lands. Any waterways running through
the project areas are used for the drainage of agricultural fields. The closest navigable waterway is
the Thames River located over 600 metres south of the project areas visible in the attached maps.
Use of watercrafts on this waterway is limited to light non-motorized recreational boats. The closest
recreational fishing grounds are located on the Thames River. There are no commercial or
aboriginal fisheries located within the Project Area. The projects will not have an impact on the
navigation of the Thames River or to recreational fishing.
3.5 Noise
Noise emissions will occur during the construction and decommissioning phase of the project
associated with heavy truck traffic and heavy machinery operation. Appropriate measures for
mitigation will be outlined in the Construction Plan Report and the Decommissioning Plan Report.
Noise emissions during the operational phase will be encountered with the operation of the
turbines. Appropriate mitigation measures, namely compliance with applicable setbacks and sound
limits are outlined in the Design and Operations Report. A wind energy project would expect
negligible noise emissions associated with periodic maintenance vehicles during the operational
phase of the project.
The subject lands are currently used for agricultural purposes and have been used for such
purposes for over 80 years. The majority of the surrounding land uses are agricultural in nature.
Agricultural activities are primarily cash crop in nature due to the highly productive soils throughout
the region. There is also a large greenhouse operation directly south of the project lands. In
addition, there are a number of non-farm residential lots, generally described as being 4 hectares
or less in area that have been severed from farm parcels over the past 40 years.
During initial public consultation, three (3) private unregistered airstrips were identified near the
project areas. In each instance, the owners of the airstrips have verbally indicated that the
proposed turbine locations will not interfere with typical take-off or landing routes. None of the
proposed turbine locations are positioned in line with the axis of any airstrip.
An active railway line runs through the project area in an east-west direction. This rail line is the
Canadian Pacific Rail’s main expressway between Windsor and Montreal. CPR has been
consulted, and has indicated no concerns with proposed turbine locations.
There are no identified mineral, aggregate, or petroleum resources in the project areas.
There is no reason to believe that there is any past contamination of the sites involved in the
projects, based on the owner’s knowledge of the properties and past history of land use.
3 . 6 . 2 P R O X I M I T Y T O F I R S T N A T I O N S R E S E R V E S / L A N D S U S E D B Y A B O R I G I N A L PE O P L E S
There are no First Nations Reserves within the study area. In addition, there are no First Nations
claims on the project area. The closest First Nations Reserve is the 1285 hectare Moravian of the
Thames reserve located 8 kilometres east of the project area along the Thames River. First
Nations notified for the projects included:
Munsee-Delaware Nation
The Ontario Ministry of Aboriginal Affairs indicated (in a letter dated February 10, 2009 from Pam
Wheaton, Director) that the project areas do “not appear to be located in an area where First
Nations may have existing or asserted rights that could be impacted by your project”, and a list of
only two First Nations to contact was provided (Bkejwanong and Delaware Nation).
Bkejwanong has provided verbal comments that they do not have any issues with any
environmental impacts of the projects and also sent along observers during the Stage 2
archaeological fieldwork. Full details of consultation with the above-noted First Nations can be
found within the Consultation Report.
There are no important or designated cultural or natural heritage sites within the project area or
study area. The St. Clair Region Conservation Authority owns a woodlot (Huff’s Woodlot)
immediately adjacent to the subject lands, which is used for woodlot management purposes, and is
not a publicly accessible conservation area. The closest turbine to this woodlot is approximately
220 metres away.
3 . 6 . 4 P R O X I M I T Y T O R E S I D EN T I A L A N D U R B A N A R E A S
None of the proposed turbine locations would be located within 550 metres of a noise receptor. In
terms of municipally designated settlement areas, the closest turbines would be approximately 1.8
kilometres from the Village of Thamesville, which is located due east of the subject lands.
3.6.5 TELECOMMUNICATIONS
Temporary road blockages for large loads (for several minutes at a time)
Municipal infrastructure that may be impacted include modifications to highway exits and
intersections. Impacts include temporarily relocating signage, hydro poles and adding aggregate to
roadway shoulders to meet turning radius requirements of delivery vehicles. These temporary
modifications will be removed, as required, and the roads returned to their original condition after
construction is complete. The transportation route for the wind turbine components has been
determined by the wind turbine supplier working with the proponent. Transporting the equipment is
part of the turbine supplier’s scope of work, as outlined in the Turbine Supply Agreement. Shipping
dates are dependant on REA approval and the current planned route may require modifications if
shipping is delayed due to part load restrictions on certain roads.
Advising the local school of the increased construction traffic; the school will also be
contacted in advance of anticipated interference with school bus routes to make
arrangements to modify the route
Flag people to control traffic as large trucks enter / leave / back up on municipal roads
More details of the traffic impacts are included in the traffic management plan and road use
agreement between the Municipality and the proponent, both of which are under review between
the two parties. Final approval of the traffic management plan and execution of the Road Use
Agreement will occur in conjunction with issuing the building permits, which is anticipated to be in
early November, 2010.
In addition to the work with the Municipality outlined above, the Ministry of Transportation will be
advised of shipments occurring on provincially regulated highways, and at the time of shipping the
carrier will confirm all weights with the Ministry of Transportation. The turbine supplier will
subcontract the transportation of the equipment to a carrier agent that specializes in shipping heavy
and oversized equipment. The final permit submission to the Ministry of Transportation is
anticipated to occur in mid November, with the first piece of turbine equipment to be shipped in mid
J:\20443\10.0 Reports\REA\PTR-1project_description_final2010-03-25.doc\2010-10-19\DD
APPENDIX 1 – MAPS
BEAR CREEK RD
OAKDALE RD
FLOR ENCE RD
Kent Breeze Wind Farms & !
BRICK RD
ZONE 1 RD
Macleod Windmill Project
!
BASE LINE
!
!
Study Area
1
!
LI
NE NE
!
LI
SH R
AB
A
IN
TE !
W PL Thamesville
S !
MACLEOD-5
ª
(WTG-10)
NE !
LI
KE
k
DE
SM
O ! Key Map : Municipality of Chatham-Kent
W
DR
!
O
HU
P
Map 1
R
FF
D
E ! MACLEOD-4
S
N
LI KENT-1 Project Areas &
SD
N (WTG-5) LOT 15
R
SO (WTG 1) ! k
D
A
M
k Study Area
! MACLEOD-1 LI
NE
(WTG-4) EN
RE
!KENT-5 k E RG MACLEOD-3
EV
(WTG-3)
k (WTG-6)
! k
KENT-4 Legend
(WTG-8)
! KENT-3 k Turbine
L
LI
N E
(WTG-2)
k Project Area
L
RE k
J:\20443\5.8 GIS\Maps\Map Created For Suncore 2010-03-24\PMMkentbreeze_map1-2010-07-09.mxd
Study Area
NT
N E
LI
BR
NE ! RI
G
LI
E
S
FT NE
D
A LI Parcel
CR RD L LA
DS VI
! W
OO NA
Private Airstrip
NG AG
ª
NE LO
M ! Utility Line
LI
ER !
NE
O
PI
0 0.75 1.5
! Kilometres
(11x17 Layout) 1:30,000
July 9, 2010
NE
LI
S H
!
SC
FY
AN
E
FU
RD
1
L
LE
! N
R
O
RD
MERRITT LINE
C
OAKDALE RD
ZONE 1 RD
CON 9
Kent Breeze Wind Farms &
BRICK RD
Macleod Windmill Project
BASE LINE
Study Area
1
NE
LI
A SH 4
AB
Thamesville
N
W O
C
12
T
LO
IN
D
U
ª
ST
11
R
IA
E T
LO
L
N
LI
k Macleod-5
R
D
KE
3 Key Map : Municipality of Chatham-Kent
DE
O 10
E SM
W
T
LI
N N LO
DR
N O
HU
C NE
O
O
AS LI Map 2
P
FF
R
M R 9
D
E T
SD
NT LO
LI Aerial Photo
R
SP
LOT 15
D
kKent-1 T
8 k Macleod-4
LO
2 j Removed Turbine
Removed
O
N Turbine
C
j T
7
kLOMacleod-1 NE
EE
N
LI
k Macleod-3
LO
T
6
k Kent-5 R G
R
1 E VE
Legend
N
O T5
C LO
k Turbine
N E
k Kent-4 j Removed Turbine
LI 4 Project Area
LL T
E LO
J:\20443\5.8 GIS\Maps\Map Created For Suncore 2010-03-24\PMMkentbreeze_map2-2010-07-09.mxd
RR
Study Area
DA
kKent-3 NE Significant Woodlot (As per Official Plan)
LI
3 R
T VE Other Vegetation
LO RI
NE
Aerial Photo: Chatham - Kent Ortho 2006
LI
F TS 2
T
C RA LO RD
S
O OD
1 W
T NG
LO LO
NE
LI
PI
O
NE
ER
T
24 O
BF
LO
0 0.75 1.5
Kilometres
23 (11x17 Layout) 1:30,000
T
LO
NE
NE LI
LI H July 9, 2010
22 S
SC
A FY
T LL
AN
LO VI
E
NA
RD
AG
21 M 1
T N
LO O
C
BEAR CREEK RD
OAKDALE RD
FLOR ENCE RD
Kent Breeze Wind Farms &
BRICK RD
ZONE 1 RD
CON 9
221
222 223 Macleod Windmill Project
BASE LINE
195
72 73 196
71 70
74 68 69 90
263 87 89 197 91
75 220 224 93 Study Area
264
1
92
NE 66 86
LI 48 67
A SH 4
49 64
225
63 65
AB O
N
62 10
210 98 99
W C 226 15
61 12
104 T
217 18 11 LO
Thamesville
17 LO
T 103
216 219 105
218 266
85 14
16 265 201 T
60 11 LO
215 E T 206 267
IN 84 LO
k
ª
L 204 106
247 KE Macleod-5 0
O 83
DE
1 268 13 107
E SM 81 T
W
N T
3 LO Key Map : Municipality of Chatham-Kent
LI LO 270 108
DR
N 80
O 248
HU
N C 78 59
NE
O
SO
FF
LI 249
P
A 79 7 109
R
229
S
M
ER 86
D
77 9
Map 3
SD
NT 50
T 4 118 113
I 260 LO 123
R
L 259 228 122 115
SP
D
LOT 15
250 51 76
k 227 116 Receptor Locations
47 251 k Kent-1 T
8 Macleod-4 269
133
128
Legend
53 52 LO 149
244 246 j
Removed Turbine
148
140
55
245 O
N
2
Removed Turbine
C
j 19
T
7 151 147 k Turbine
214
243
LO
k
Macleod-1
N E
Macleod-3 S
R D 39
38
152
j Turbine
56 20 EN
L I
kG
OO
W 35
D
277 154 1.5km Turbine Buffer
242 E
57
258
LO
T
6
k Kent-5
E RG
R 274 ON
L
29 32 275
34
156
155 2km Turbine Buffer
EV
240 157 Points of Reception - Existing Dwelling,
25721 273 276 Participating
239 N
1 5 291
28
O T 212 Points of Reception - Vacant Lot
LO
C
213 Points of Reception - Existing Dwelling,
L
LI
NE 46 k Kent-4 278
2425 27 Non Participating
26 Study Area
283 180
DA 255
KE
22 Parcel
59
NT
3 280 182 N E
T
LI Private Airstrip
BR
58 LO 284 179 R
VE
ID
NE
Significant Woodlot (As per Official Plan)
253 RI
G
LI 237 286
E
TS 2
D
236 T
AF 43 LO 177
CR 40 288
176 158 ! Utility Line
287
290
1
T 289
LO 159
NE
O
LI BF
ER 256 230
NE T
24 235 175 231
O
PI LO 193 185 173 233
172 160 0 0.75 1.5
192
169 Kilometres
23 189 163 234 (11x17 Layout) 1:30,000
T
LO
161
162 NE
NE LI
LI H July 9, 2010
22 S
SC
LO
T
LL
A FY
AN
VI
E
NA
FU
RD
AG
L
LE
21 M
R
T 1
LO MERRITT LINE N
RD
O
C
61 10
185 5 217
18 Kent Breeze Wind Farms &
5
216 18 219 11
215 218
17
18 210 Macleod Windmill Project
\
N E 60
\
LI
R 185 15 12 \
E 85
NT
16 \Study Area
I 14
L \
SP 247 13
\
84 \
82 262
\
248 NE 83 k Macleod-5
18
LI \
5
KE 81
\
18
O \
SM
5
249 \
80 207
78 \
268 209
ª
50 79 \
261 \ 5 270 Key Map : Municipality of Chatham-Kent
77 \
18
51 95
HU \ 7
260
FF
S 259 76 \
\
8
6
271
Map 4
85
\ 1 Renewable Energy
SD
4
kKent-1 \ 23
Approval Setbacks
RD
1
\
\ k Macleod-4 Legend
\
18
5 Removed Turbine k Turbine
j \
19
j Removed
Turbine LI
NE j Removed Turbine
18
5 \ E N Points of Reception - Existing Dwelling, Non Participating
RE
k Macleod-1
J:\20443\5.8 GIS\Maps\Map Created For Suncore 2010-03-24\PMMkentbreeze_map4-2010-07-09.mxd
185
k 33
277 550m Off Site Receptor Setback
Building_Envelope
185 \
257 31 35 Significant Woodlot (As per Official Plan)
21
292 272 30 34
\ Other Vegetation
274 275
120m Significant Woodlot Setback
\ 29 32
291 Project Area
211 273 276
\ 213
\ Utility Line
D
212 28 SR
\ k Kent-4 OO
D
Contour Line
Railroad
W
\ NG
LO Road
k Kent-3 2425
23
278
279
181 27
Watercourse
0
18
22
280 26 0 Metres
18 18 1:15,000 (11 X 17 Layout)
5
284 179 July 9, 2010
182
285 5
281 18
286 282 85
185 1 185
180
178
177
185 5
5
18 Kent Breeze Wind Farms &
18
Macleod Windmill Project
NE
LI
R 185
!
N TE Study
! Area
I
S PL !
!
Macleod-5
NE k
LI
!
18
E
OK
5
!
18 SM
BE
!
5
NJ
HU
AM
!
IN
FF
DR
S KENT MACLEOD ! Key Map : Municipality of Chatham-Kent
ª
AI
SD SWITCHING SWITCHING
N
85
LI B
STATION STATION
! 1
RD DIRECT DRILL
ER
Map 5
! UNDER TRACKS
Y T
A
DR
5 IN
18
Project Infrastructure
!
k Kent-1 !
NE
LI
Macleod-4 EN
!
k E
GR
AI
N !
DR
E R
REMOVED EV Legend
E
TN REMOVED
Y
5
R j 18
! TURBINE
TURBINE DIRECT DRILL
185
j
U
k Turbine
O
j Removed Turbine
!DIRECT DRILL
k
J:\20443\5.8 GIS\Maps\Map Created For Suncore 2010-03-24\PMMkentbreeze_map5-2010-07-09.mxd
Underground Cable
!
! Utility Line
IN
D RA DIRECT DRILL k Macleod-3 Significant Woodlot (As per Official Plan)
N
185
! k Kent-5 M
A SO UNDER TRACKS
DIRECT DRILL Other Vegetation
UNDER ROAD Contour Line
! Railroad
Road
185 Watercourse
!
Closed Tile Drain
S RD
Kent-4 D
OO
! k
N GW
Kent-3 LO
DO
O
BS
k N
DR
O
A IN
N
RA I
ND
0
18
Metres
GU
0
18 18 1:15,000 (11 X 17 Layout)
ER
F
AW 5
SH
July 9, 2010
5
5 18
185 18 185
180
IBI GROUP REA PROJECT DESCRIPTION REPORT
Kent Breeze Corporation
MacLeod Windmill Project Inc.
KENT BREEZE WIND FARMS
RESOP10306, RESOP13162
This letter constitutes the Ministry of Tourism and Culture’s written comments as required by s. 23(3)(a) of
O. Reg. 359/09 under the Environmental Protection Act regarding heritage assessments undertaken for the
above project.
Based on the information contained in the report(s) you have submitted for this project, the Ministry is
satisfied with the heritage assessment(s). Please note that the Ministry makes no representation or
warranty as to the completeness, accuracy or quality of the heritage assessment report(s). *
The study area and project area have been determined to represent one homogenous rural cultural
heritage landscape, with no separate or highly sensitive cultural landscapes identified. The
construction of the project turbines and associated structure will have a visual impact on the rural
cultural heritage landscape of the project and study areas. The land is flat and it is anticipated that the
turbines will be prominent, new visual features in the landscape. It is recommended that the visual
impact of the two proposed switching stations that are to be located at the intersection of Smoke Line
and Huffs Side Road should be minimized with appropriate landscape design, such as massing and
screening in order to lessen the impact on the surrounding cultural heritage landscape.
A number of historic structures located within the larger study area, but no direct or indirect on this
structure are anticipated. One farmstead is located on an optioned property within the project area
and has been evaluated according to OHA Regulation 9/06 and determined not be a feature of cultural
heritage value. Regardless, due to the REA regulations, this farmstead is located along the edge of
the 550 metre noise setback and therefore no direct or indirect impacts are anticipated.
The final layout for the proposed turbine locations and associated structures, access roads and
underground cables were evaluated with regards to potential direct and indirect impacts to built
heritage features and cultural landscapes. No direct or indirect impacts are anticipated.
This letter does not waive any requirements which you may have under the Ontario Heritage Act. Also, this
letter does not constitute approval of the renewable energy project. Approvals of the project may be
required under other statutes and regulations. It is your responsibility to obtain any necessary approvals or
licences.
Please feel free to contact me if you have questions or require additional information.
Sincerely,
Penny Young
Heritage Planner
Programs and Services Branch, MTC
cc:
Christopher Andreae, Project Manager
Golder Associates
______________________________________________________________________________________
*
In no way will the Ministry be liable for any harm, damages, costs, expenses, losses, claims or actions that may result: (a) if the
Report(s) or its recommendations are discovered to be inaccurate, incomplete, misleading or fraudulent; or (b) from the issuance
of this letter. Further measures may need to be taken in the event that additional heritage resources are identified or the Report(s) is
otherwise found to be inaccurate, incomplete, misleading or fraudulent.
Ministry of Ministère des
Natural Resources Richesses naturelles
615 John Street North 615, rue John Nord
Aylmer ON N5H 2S8 Aylmer ON N5H 2S8
Tel: 519-773-9241 Tél: 519-773-9241
Fax: 519-773-9014 Téléc: 519-773-9014
Derek Dudek
IBI Group
Suite 203 – 350 Oxford Street West
London, ON N6H 1T3
Thank you for your response sent on July 13, 2010 to the Ministry of Natural Resources (MNR) regarding the
unknown status of Well #F002377, according to the Petroleum Resources Centre (PRC).
As outlined under Section 7.8 of the MNR’s Approvals and Permitting Requirements Document for Renewable
Energy Projects (APRD), “development is not permitted within 75 metres of a petroleum resources operation unless
the applicant submits an engineers report demonstrating that there are no effects to the development.” Based on
your response and according to the MNR’s records, Well #F002377 is located outside the 75 m setback in relation to
both the turbine (Kent-1) and the underground cable trench along Smoke Line. Since the distances between the well
and these project components are well in excess of 75 m, the MNR’s previous request for a site investigation has
been withdrawn.
Based on the information above, it has been determined that the requirement with respect to the petroleum resources
operations setback under section 7.8 of the APRD has been met for the Kent Breeze and MacLeod wind farm project,
and as such an engineers report is not required.
Please be advised that the MNR cannot guarantee the accuracy of the data in the Ministry’s records, as some of the
information is historical and may be inaccurate or incomplete. Also, please note that the well data retrieved in the
search of the MNR’s database are only the wells that we are currently aware of. Other wells may exist in the project
area for which we do not have any records.
If any wells in addition to the wells identified in the database search are encountered during the development, please
contact Sandra Gilbert at PRC at 519-873-4638 or sandra.gilbert@ontario.ca.
Sincerely,
Heather Riddell
A/Planning Ecologist, Aylmer District
(519) 773-4723