Escolar Documentos
Profissional Documentos
Cultura Documentos
Chapter 13
Capital investment decision are those decisions that involve current outlay (i.e.
capital) in return for a stream of benefits in future years. These decisions
include:-
• There is no inflation
Compounding
Invest $100,000 at 10% payable at the end of each year for 4 years with the
interest re-invested (i.e. compounding interest)
Long Way
End of Year Interest earned Total Accumulat
Invested ed Total
0 100,000
1 0.10 x 100,000 10,000 110,000
2 0.10 x 110,000 11,000 121,000
3 0.10 x 121,000 12,100 133,100
4 0.10 x 133,100 13,310 146,410
Formula
FV = Vo(1 + K)n
FV = Future Value
Vo = Invested Sum
K = Interest rate
n = Number of years
= (100,000)(factor using compound table for $1 for 4 years @ 10%) you get
100,000 x 1.464 =$146,410
2
3
Present Value
The concept that $1 received in the future is not equal to $1 received today is
known as the ‘time value of money’.
The process of converting cash to be received in the future into value at the
present time by the use of an interest rate is called ‘discounting’. Discounting is
the opposite of compounding.
Project A Project B
Year 1 300,000 600,000
Year 2 1,000,000 600,000
Year 3 400,000 600,000
IRR also called the “Discount Rate of Return” is the interest rate K which will
cause the NPV of an investment to be zero.
3
4
Choose Project where the IRR is greater than the Company’s Cost of Capital
Payback Period
The simplest and most frequently used method of capital investment. It is the
length of time that is required for a stream of cash proceeds from an investment
to recover the original cash outlay.
Note Pay back period must be based on cash flows not profits. If profits are give it
must be converted to cash flows by adding back depreciation etc.
Cost
Project X – Constructing and operating a Toll $400,000
Road
Project Y – Operating a Train Service $450,000
Accept project with the shortest payback period or projects that is within the
company’s required payback period.
4
5
Project A
Initial 50,000 Note
Cost These are cash Fl0ws
Cash not profit hence
Inflow initial capital must
Year 1 10,000 be subtracted
Year 2 20,000
Year 3 20,000
Year 4 20,000
Year 5 10,000
.
ARR is based on profits. Therefore if cash flows are given you must convert it to
profit by subtracting the cash outlay and depreciation if given.
Chapter 14
Capital Rationing
Where a company cannot undertake all those projects that yield a positive net
present value due to insufficient funds , this called “Capital Rationing”.
Soft capital rationing , the company internally imposes a budget ceiling on its
capital expenditure
Where capital rationing exist management should allocate the limited available
capital to maximise the NPVs of the firm.
Profitability Index
Profitability Index = Present Value of Projects
Investment Outlay
Projects with PI greater than 1 should be accepted as they have NPV greater than
0
Example
PROJECT A PROJECT B
Investment Outlay $20 million $10 million
Present Value of Cash Flows $2 million $1.5 million
Profitability Index 2 1.5
5
6
20 10
= 0.10 = 0.15
Capital Allowance
Depreciation is not an allowable deduction instead taxation legislation enables
capital allowances to be claimed on capital expenditure. These are also called
writing-down allowances or depreciation tax shield.
Example
• Cost of machine = $1,000,000
• Expected additional net cash flows and profits expected from machine =
$500,000 for 4 years
• Machine will be sold at the end of year 4 for its WDV.
• Capital allowance 25% on the Written Down Value (WDV) of plant and
equipment based on the reducing balance basis
• Assume a one year lag in the payment of taxes
• Cost of Capital – 10%
SOLUTION
(1)Calculating the annual WDA
Annual writing-down Written-down value
allowance
0 0 1,000,000
1 250,000(25% X $ 750,000
1,000,000)
2 187,500(25% X $750,000) 562,500
3 140,630(25% X 562,500) 421,870
4 105,470(25% X 421,870) 316,400
683,600
7
8
Present value interest factor of an (ordinary) annuity of $1 per period at i% for n periods,
PVIFA(i,n).
Perio
d 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12%
1 0.990 0.980 0.971 0.962 0.952 0.943 0.935 0.926 0.917 0.909 0.901 0.893
2 1.970 1.942 1.913 1.886 1.859 1.833 1.808 1.783 1.759 1.736 1.713 1.690
3 2.941 2.884 2.829 2.775 2.723 2.673 2.624 2.577 2.531 2.487 2.444 2.402
4 3.902 3.808 3.717 3.630 3.546 3.465 3.387 3.312 3.240 3.170 3.102 3.037
5 4.853 4.713 4.580 4.452 4.329 4.212 4.100 3.993 3.890 3.791 3.696 3.605
6 5.795 5.601 5.417 5.242 5.076 4.917 4.767 4.623 4.486 4.355 4.231 4.111
7 6.728 6.472 6.230 6.002 5.786 5.582 5.389 5.206 5.033 4.868 4.712 4.564
8 7.652 7.325 7.020 6.733 6.463 6.210 5.971 5.747 5.535 5.335 5.146 4.968
9 8.566 8.162 7.786 7.435 7.108 6.802 6.515 6.247 5.995 5.759 5.537 5.328
10 9.471 8.983 8.530 8.111 7.722 7.360 7.024 6.710 6.418 6.145 5.889 5.650
10.36
11 8 9.787 9.253 8.760 8.306 7.887 7.499 7.139 6.805 6.495 6.207 5.938
11.25 10.57
12 5 5 9.954 9.385 8.863 8.384 7.943 7.536 7.161 6.814 6.492 6.194
12.13 11.34 10.63
13 4 8 5 9.986 9.394 8.853 8.358 7.904 7.487 7.103 6.750 6.424
13.00 12.10 11.29 10.56
14 4 6 6 3 9.899 9.295 8.745 8.244 7.786 7.367 6.982 6.628
8
9
Present value interest factor of an (ordinary) annuity of $1 per period at i% for n periods,
PVIFA(i,n).
13.86 12.84 11.93 11.11 10.38
15 5 9 8 8 0 9.712 9.108 8.559 8.061 7.606 7.191 6.811
14.71 13.57 12.56 11.65 10.83 10.10
16 8 8 1 2 8 6 9.447 8.851 8.313 7.824 7.379 6.974
15.56 14.29 13.16 12.16 11.27 10.47
17 2 2 6 6 4 7 9.763 9.122 8.544 8.022 7.549 7.120
16.39 14.99 13.75 12.65 11.69 10.82 10.05
18 8 2 4 9 0 8 9 9.372 8.756 8.201 7.702 7.250
17.22 15.67 14.32 13.13 12.08 11.15 10.33
19 6 8 4 4 5 8 6 9.604 8.950 8.365 7.839 7.366
18.04 16.35 14.87 13.59 12.46 11.47 10.59
20 6 1 7 0 2 0 4 9.818 9.129 8.514 7.963 7.469
22.02 19.52 17.41 15.62 14.09 12.78 11.65 10.67
25 3 3 3 2 4 3 4 5 9.823 9.077 8.422 7.843
25.80 22.39 19.60 17.29 15.37 13.76 12.40 11.25 10.27
30 8 6 0 2 2 5 9 8 4 9.427 8.694 8.055
29.40 24.99 21.48 18.66 16.37 14.49 12.94 11.65 10.56
35 9 9 7 5 4 8 8 5 7 9.644 8.855 8.176
32.83 27.35 23.11 19.79 17.15 15.04 13.33 11.92 10.75
40 5 5 5 3 9 6 2 5 7 9.779 8.951 8.244
39.19 31.42 25.73 21.48 18.25 15.76 13.80 12.23 10.96
50 6 4 0 2 6 2 1 3 2 9.915 9.042 8.304
Present value interest factor of an (ordinary) annuity of $1 per period at i% for n periods,
PVIFA(i,n).
48.88 60.40 75.40 95.02 120.8 154.7 199.6 259.0 337.8 442.5 581.8 767.0
40 6 2 1 6 0 6 4 6 8 9 3 9
64.46 84.57 112.8 152.6 209.3 290.3 406.5 573.7 815.0 1,163 1,668 2,400.
50 3 9 0 7 5 4 3 7 8 .9 .8 0
Future value interest factor of an ordinary annuity of $1 per period at i% for n periods,
FVIFA(i,n).
Perio
d 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12%
1 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000
2 2.010 2.020 2.030 2.040 2.050 2.060 2.070 2.080 2.090 2.100 2.110 2.120
3 3.030 3.060 3.091 3.122 3.153 3.184 3.215 3.246 3.278 3.310 3.342 3.374
4 4.060 4.122 4.184 4.246 4.310 4.375 4.440 4.506 4.573 4.641 4.710 4.779
5 5.101 5.204 5.309 5.416 5.526 5.637 5.751 5.867 5.985 6.105 6.228 6.353
6 6.152 6.308 6.468 6.633 6.802 6.975 7.153 7.336 7.523 7.716 7.913 8.115
10.08
7 7.214 7.434 7.662 7.898 8.142 8.394 8.654 8.923 9.200 9.487 9.783 9
10.26 10.63 11.02 11.43 11.85 12.30
8 8.286 8.583 8.892 9.214 9.549 9.897 0 7 8 6 9 0
10.15 10.58 11.02 11.49 11.97 12.48 13.02 13.57 14.16 14.77
9 9.369 9.755 9 3 7 1 8 8 1 9 4 6
10.46 10.95 11.46 12.00 12.57 13.18 13.81 14.48 15.19 15.93 16.72 17.54
10 2 0 4 6 8 1 6 7 3 7 2 9
11.56 12.16 12.80 13.48 14.20 14.97 15.78 16.64 17.56 18.53 19.56 20.65
11 7 9 8 6 7 2 4 5 0 1 1 5
12.68 13.41 14.19 15.02 15.91 16.87 17.88 18.97 20.14 21.38 22.71 24.13
12 3 2 2 6 7 0 8 7 1 4 3 3
13.80 14.68 15.61 16.62 17.71 18.88 20.14 21.49 22.95 24.52 26.21 28.02
13 9 0 8 7 3 2 1 5 3 3 2 9
14.94 15.97 17.08 18.29 19.59 21.01 22.55 24.21 26.01 27.97 30.09 32.39
14 7 4 6 2 9 5 0 5 9 5 5 3
16.09 17.29 18.59 20.02 21.57 23.27 25.12 27.15 29.36 31.77 34.40 37.28
15 7 3 9 4 9 6 9 2 1 2 5 0
17.25 18.63 20.15 21.82 23.65 25.67 27.88 30.32 33.00 35.95 39.19 42.75
16 8 9 7 5 7 3 8 4 3 0 0 3
18.43 20.01 21.76 23.69 25.84 28.21 30.84 33.75 36.97 40.54 44.50 48.88
17 0 2 2 8 0 3 0 0 4 5 1 4
19.61 21.41 23.41 25.64 28.13 30.90 33.99 37.45 41.30 45.59 50.39 55.75
18 5 2 4 5 2 6 9 0 1 9 6 0
20.81 22.84 25.11 27.67 30.53 33.76 37.37 41.44 46.01 51.15 56.93 63.44
19 1 1 7 1 9 0 9 6 8 9 9 0
22.01 24.29 26.87 29.77 33.06 36.78 40.99 45.76 51.16 57.27 64.20 72.05
20 9 7 0 8 6 6 5 2 0 5 3 2
28.24 32.03 36.45 41.64 47.72 54.86 63.24 73.10 84.70 98.34 114.4 133.3
25 3 0 9 6 7 5 9 6 1 7 1 3
34.78 40.56 47.57 56.08 66.43 79.05 94.46 113.2 136.3 164.4 199.0 241.3
30 5 8 5 5 9 8 1 8 1 9 2 3
41.66 49.99 60.46 73.65 90.32 111.4 138.2 172.3 215.7 271.0 341.5 431.6
35 0 4 2 2 0 3 4 2 1 2 9 6
48.88 60.40 75.40 95.02 120.8 154.7 199.6 259.0 337.8 442.5 581.8 767.0
40 6 2 1 6 0 6 4 6 8 9 3 9
64.46 84.57 112.8 152.6 209.3 290.3 406.5 573.7 815.0 1,163 1,668 2,400.
50 3 9 0 7 5 4 3 7 8 .9 .8 0
10