Você está na página 1de 26

SUPREME COURT REPORTS ANNOTATED the rules applicable to acts of God.

—In order for a fortuitous


Mindex Resources Development vs. Morillo event to exempt one from liability, it is necessary that one has
G.R. No. 138123. March 12, 2002.* committed no negligence or misconduct that may have
MINDEX RESOURCES DEVELOPMENT, petitioner, vs. occasioned the loss. An act of God cannot be invoked to protect a
EPHRAIM MORILLO, respondent. person who has failed to take steps to forestall the possible
adverse consequences of such a loss. One’s negligence may have
Appeals; Evidence; Well-settled is the rule that factual findings concurred with an act of God in producing damage and injury to
of the trial court, particularly when affirmed by the Court of another; nonetheless, showing that the immediate or proximate
Appeals, are binding on the Supreme Court.—Both the RTC and cause of the damage or injury was a fortuitous event would not
the CA found petitioner negligent and thus liable for the loss or exempt one from liability. When the effect is found to be partly
destruction of the leased truck. True, both parties may have the result of a person’s participation—whether by active
suffered from the burning of the truck; however, as found by intervention, neglect or failure to act—the whole occurrence is
both lower courts, the negligence of petitioner makes it humanized and removed from the rules applicable to acts of
responsible for the loss. Well-settled is the rule that factual God.
findings of the trial court, particularly when affirmed by the
Court of Appeals, are binding on the Supreme Court. Contrary to Same; Same; Requisites; The often-invoked doctrine of
its allegations, petitioner has not adequately shown that the RTC “fortuitous event” or “caso fortuito” has become a convenient
and the CA overlooked or disregarded significant facts and and easy defense to exculpate an obligor from liability.—This
circumstances that, when considered, would alter the outcome often-invoked doctrine of “fortuitous event” or “caso fortuito”
of the disposition. Article 1667 of the Civil Code holds lessees has become a convenient and easy defense to exculpate an
responsible for the deterioration or loss of the thing leased, obligor from liability. To constitute a fortuitous event, the
unless they prove that it took place without their fault. following elements must concur: (a) the cause of the unforeseen
and unexpected occurrence or of the failure of the debtor to
Obligations and Contracts; Fortuitous Events; An act of God comply with obligations must be independent of human will; (b)
cannot be invoked to protect a person who has failed to take it must be impossible to foresee the event that constitutes the
steps to forestall the possible adverse consequences of such a caso fortuito or, if it can be foreseen, it must be impossible to
loss-when the effect is found to be partly the result of a person’s avoid; (c) the occurrence must be such as to render it impossible
participation, whether by active intervention, neglect or failure for the debtor to fulfill obligations in a normal manner; and (d)
to act, the whole occurrence is humanized and removed from
the obligor must be free from any participation in the pecuniary losses that result from an act or omission of the
aggravation of the injury or loss. defendant. Having been found to be negligent in safeguarding
Same; Same; Words and Phrases; Negligence, as commonly the leased truck, petitioner must shoulder its repair and
understood, is that conduct that naturally or reasonably creates overhaul costs to make it serviceable again. Such expenses are
undue risk or harm to others.—As can be gleaned from the duly supported by receipts; thus, the award of P132,750 is
foregoing testimony, petitioner failed to employ reasonable definitely in order.
foresight, diligence and care that would have exempted it from
liability resulting from the burning of the truck. Negligence, as Attorney’s Fees; Where granted, the court must explicitly state
commonly understood, is that conduct that naturally or in the body of the decision, and not only in the dispositive
reasonably creates undue risk or harm to others. It may be a portion thereof, the legal reason for the award of attorney’s fees.
failure to observe that degree of care, precaution or vigilance —We find the award of attorney’s fees to be improper. The
that the circumstances justly demand; or to do any other act that reason which the RTC gave—because petitioner had compelled
would be done by a prudent and reasonable person, who is respondent to file an action against it—falls short of our
guided by considerations that ordinarily regulate the conduct of requirement in Scott Consultants and Resource Development v.
human affairs. CA, from which we quote: “It is settled that the award of
attorney’s fees is the exception rather than the rule and
Same; Same; Leases; Damages; Article 1667 of the Civil Code counsel’s fees are not to be awarded every time a party wins
holds the lessee responsible for the deterioration or loss of the suit. The power of the court to award attorney’s fees under
thing leased; Courts begin with the assumption that Article 2208 of the Civil Code demands factual, legal, and
compensatory damages are for pecuniary losses that result from equitable justification; its basis cannot be left to speculation or
an act or omission of the defendant.—The P132,750 repair and conjecture. Where granted, the court must explicitly state in the
overhaul costs was correctly granted by the lower courts. Article body of the decision, and not only in the dispositive portion
1667 of the Civil Code holds the lessee responsible for the thereof, the legal reason for the award of attorney’s fees.”
deterioration or loss of the thing leased. In addition, Article 1665
of the same Code provides that “the lessee shall return the thing Same; In the absence of stipulation, a winning party may be
leased, upon the termination of the lease, just as he received it, awarded attorney’s fees only in case plaintiff’s action or
save what has been lost or impaired by the lapse of time, or by defendant’s stand is so untenable as to amount to gross and
ordinary wear and tear, or from an inevitable cause.” Courts evident bad faith.—Moreover, a recent case ruled that “in the
begin with the assumption that compensatory damages are for absence of stipulation, a winning party may be awarded
attorney’s fees only in case plaintiff’s action or defendant’s stand of P76,000.00 and costs of repair in the amount of P132,750.00
is so untenable as to amount to gross and evident bad faith.” is six (6%) percent per annum from June 22, 1994, the date of
Indeed, respondent was compelled to file this suit to vindicate the decision of the court a quo to the date of its finality.
his rights. However, such fact by itself will not justify an award Thereafter, if the amounts adjudged remain unpaid, the interest
of attorney’s fees, when there is no sufficient showing of rate shall be twelve (12%) percent per annum from the date of
petitioner’s bad faith in refusing to pay the said rentals as well finality of the decision until fully paid.”2
as the repair and overhaul costs.
PETITION for review on certiorari of a decision of the Court of The Facts
Appeals. The factual antecedents of the case are summarized by the CA in
this wise:
The facts are stated in the opinion of the Court. “On February 1991, a verbal agreement was entered into
     Quisumbing and Torres for petitioner. between Ephraim Morillo and Mindex Resources Corporation
     Westwood Law and Edgardo C. Aceron for private (MINDEX for brevity) for the lease of the former’s 6 x 6 ten-
respondent. wheeler cargo truck for use in MINDEX’s mining operations in
PANGANIBAN, J.: Binaybay, Bigaan, San Teodoro, Oriental Mindoro, at the
stipulated rental of ‘P300.00 per hour for a minimum of eight
Attorney’s fees cannot be granted simply because one was hours a day or a total of P2,400.00 daily.’ MINDEX had been
compelled to sue to protect and enforce one’s right. The grant paying the rentals until April 10, 1991.
must be proven by facts; it cannot depend on mere speculation “Unknown to Morillo, on April 11, 1991, the truck was burned by
or conjecture—its basis must be stated in the text of the unidentified persons while it was parked unattended at Sitio
decision. Aras, Bigaan, San Teodoro, Oriental Mindoro, due to mechanical
trouble. The findings of the Mindoro Oriental Integrated
The Case National Police in their investigation report read:
Before us is a Petition for Review under Rule 45 of the Rules of ‘3. On 121005H April 1991, Mr. Alexander Roxas, project
Court, assailing the March 26, 1999 Decision1 of the Court of coordinator of MINDEX MINING CORP. reported to this office
Appeals (CA) in CA-GR CV No. 46967. The dispositive portion of that on the morning of 12 April 1991 while he was supposed to
the challenged Decision reads as follows: report for his work at their office at Sitio Tibonbon, Bigaan, San
“WHEREFORE, the appealed decision is AFFIRMED with Teodoro, Oriental Mindoro, he x x x noticed that their hired 6 x 6
MODIFICATION that the legal interest to be paid on the rentals Ten wheeler Cargo Truck temporarily parked at Sitio Aras,
Bigaan, San Teodoro, Oriental Mindoro for Alpha Engine Trouble      ‘Second payment
was burned on the night of April 11, 1991 by still unidentified - May 15/91
person. 50,000.00
‘x x x      x x x      x x x      ‘Third payme(n)t
‘5. x x x Based also on the facts gathered and incident scene - June 15/91
searched it was also found out that said 6 x 6 Ten Wheeler Cargo 50,000.00
Truck was burned by means of using coconut leaves and as a      ‘Fourth payme(n)t
result of which said 6 x 6 was totally burned excluding the - July 15/91
engine which was partially damaged by still undetermined 25,000.00
amount.’  
“Upon learning of the burning incident, Morillo offered to sell      TOTAL
the truck to MINDEX but the latter refused. Instead, it replaced P275,000.00
the vehicle’s burned tires and had it towed to a shop for repair ‘I promise to relinquish all the necessary documents upon full
and overhauling. payment of said account.
“On April 15, 1991, Morillo sent a letter to Mr. Ami Isberg, the ‘x x x      x x x      x x x
Finance Manager of MINDEX, thru Mr. Ramoncito Gozar, Project “Through Mr. Gozar, MINDEX responded by a handwritten letter
Manager, proposing the following: to his cousin Malou (wife of Ephraim Morillo), expressing their
‘x x x      x x x      x x x reservations on the above demands due to their tight financial
‘I have written to let you know that I am entrusting to you the situation. However, he made the following counter offers:
said vehicle in the amount of P275,000.00 which is its cost price. ‘a) Pay the rental of the 6 x 6 truck (actual) in the amount of
I will not charge your company for the encumbrance of P76,800 P76,000.00.
+ since you used it as my friendly gesture on account of the ‘b) Repair and overhaul the truck on our own expenses and;
unforeseen adversity. ‘c) Return it to you on (A1) good running condition after repair.’
‘In view of the tragic happening, I am asking you to pay us, in a “Morillo replied on April 18, 1991, (1) that he will relinquish to
way which will not be hard for you to settle to pay us in four MINDEX the damaged truck; (2) that he is amenable to receive
installment monthly as follows: the rental in the amount of P76,000.00; and (3) that MINDEX
     ‘First payment will pay fifty thousand pesos (P50,000.00) monthly until the
- April 25/91 balance of P275,000.00 is fully paid. It is noteworthy that except
P[1]50,000.00 for his acceptance of the proffered P76,000.00 unpaid rentals,
Morillo’s stand has virtually not been changed as he merely down. The place was about twelve (12) kilometers away from
lowered the first payment on the P275,000.00 valuation of the the camp site of the appellant corporation and was sparsely
truck from P150,000.00 to P50,000.00. populated. It was guarded only during daytime. It stayed in that
“The parties had since remained intransigent and so on August place for two (2) weeks until it was burned on April 11, 1991
1991, Morillo pulled out the truck from the repair shop of while its transfer case was being repaired elsewhere. It was only
MINDEX and had it repaired elsewhere for which he spent the after it had been burned that the appellant had it towed to a
total amount of P132,750.00.”3 (Citations omitted) repair shop.

Ruling of the Trial Court “The appellant [respondent] was thus not free from fault for the
After evaluating the evidence adduced by both parties, the burning of the truck. It miserably failed to overcome the
Regional Trial Court (RTC) found petitioner responsible for the presumption of negligence against it. Neither did it rescind the
destruction or loss of the leased 6x6 truck and ordered it to pay lease over the truck upon its burning. On the contrary, it offered
respondent (1) P76,000 as balance of the unpaid rental for the 6 to pay P76,000.00 as rentals. It did not also complete the needed
x 6 truck with interest of 12 percent from June 22, 1994 (the repair. Hence, the appellee was forced to pull out the truck and
rendition of the judgment) up to the payment of the amount; (2) had it repaired at his own expense. Since under the law, the
P132,750 representing the costs of repair and overhaul of the ‘lessee shall return the thing leased, upon the termination of the
said truck, with interest rate of 12 percent until fully paid; and lease, just as he receive it,’ the appellant stands liable for the
(3) P20,000 as attorney’s fees for compelling respondent to expenses incurred for the repair in the aggregate amount of
secure the services of counsel in filing his Complaint. P132,750.00.”
Ruling of the Court of Appeals
The appellate court sustained the RTC’s finding that petitioner Nevertheless, the appellate court modified the Decision of the
was not without fault for the loss and destruction of the truck trial court. The 12 percent interest rate on the P76,000 rentals
and, thus, liable therefor. The CA said: and the P132,750 repair costs, imposed by the RTC, was
changed by the CA to 6 percent per annum from June 22, 1994 to
“The burning of the subject truck was impossible to foresee, but the date of finality of the said Decision; and 12 percent per
not impossible to avoid. MINDEX could have prevented the annum thereafter, if the amounts adjudged would remain
incident by immediately towing the truck to a motor shop for unpaid from such date of finality until the rentals and the repair
the needed repair or by having it guarded day and night. Instead, costs were fully paid. It affirmed the award of attorney’s fees.
the appellant just left the vehicle where its transfer case broke Hence, this Petition.5
truck. True, both parties may have suffered from the burning of
Issues the truck; however, as found by both lower courts, the
In its Memorandum, petitioner raises the following issues for the negligence of petitioner makes it responsible for the loss. Well-
Court’s consideration: settled is the rule that factual findings of the trial court,
“4.1. Whether or not the Court of Appeals gravely erred in particularly when affirmed by the Court of Appeals, are binding
finding that petitioner failed to overcome the presumption of on the Supreme Court. Contrary to its allegations, petitioner has
negligence against it considering that the facts show, as not adequately shown that the RTC and the CA overlooked or
admitted by the respondent, that the burning of the truck was a disregarded significant facts and circumstances that, when
fortuitous event. considered, would alter the outcome of the disposition.8 Article
“4.2. Whether or not the Court of Appeals gravely erred in 1667 of the Civil Code9 holds lessees responsible for the
affirming the decision of the trial court finding petitioner liable deterioration or loss of the thing leased, unless they prove that it
to pay unpaid rentals and cost of repairs. took place without their fault.
“4.3. Whether or not the Court of Appeals also erred in affirming ______________
the decision of the trial court finding petitioner liable to pay
attorney’s fees.”6 7 Article 1174 provides:
This Court’s Ruling “Except in cases expressly specified by the law, or when it is
The Petition is partly meritorious; the award of attorney’s fees otherwise declared by stipulation or when the nature of the
should be deleted. obligation requires the assumption of risk, no person shall be
responsible for those events which could not be foreseen, or
First Issue: which though foreseen, were inevitable.”
Petitioner’s Negligence 8 Spouses Belo v. Philippine National Bank, G.R. No. 134330,
Petitioner claims that the burning of the truck was a fortuitous March 1, 2001, 353 SCRA 359; Republic v. CA, 349 SCRA 451,
event, for which it should not be held liable pursuant to Article January 18, 2001; Halili v. CA, 287 SCRA 465, March 12, 1998.
11747 of the Civil Code. Moreover, the letter of respondent 9 “Art. 1667. The lessee is responsible for the deterioration or
dated April 15, 1991, stating that the burning of the truck was an loss of the thing leased, unless he proves that it took place
“unforeseen adversity,” was an admission that should exculpate without his fault. This burden of proof on the lessee does not
the former from liability. apply when the destruction is due to earthquake, flood, storm or
We are not convinced. Both the RTC and the CA found petitioner other natural calamity.”
negligent and thus liable for the loss or destruction of the leased
Fortuitous Event Article 1174 of the Civil Code states that no person shall be
In order for a fortuitous event to exempt one from liability, it is responsible for a fortuitous event that could not be foreseen or,
necessary that one has committed no negligence or misconduct though foreseen, was inevitable. In other words, there must be
that may have occasioned the loss.10 An act of God cannot be an exclusion of human intervention from the cause of injury or
invoked to protect a person who has failed to take steps to loss.13
forestall the possible adverse consequences of such a loss. One’s
negligence may have concurred with an act of God in producing A review of the records clearly shows that petitioner failed to
damage and injury to another; nonetheless, showing that the exercise reasonable care and caution that an ordinarily prudent
immediate or proximate cause of the damage or injury was a person would have used in the same situation. Witness
fortuitous event would not exempt one from liability. When the Alexander Roxas testified how petitioner fell short of ordinary
effect is found to be partly the result of a person’s participation diligence in safeguarding the leased truck against the accident,
—whether by active intervention, neglect or failure to act—the which could have been avoided in the first place. Pertinent
whole occurrence is humanized and removed from the rules portions of his testimony are reproduced hereunder:
applicable to acts of God.11 “ATTY. ACERON
Q
This often-invoked doctrine of “fortuitous event” or “caso Now, this Barangay Aras where the 6 x 6 truck had transmission
fortuito” has become a convenient and easy defense to exculpate trouble, how far is it from the camp site of the defendant
an obligor from liability. To constitute a fortuitous event, the corporation?
following elements must concur: (a) the cause of the unforeseen ALEXANDER ROXAS
and unexpected occurrence or of the failure of the debtor to A
comply with obligations must be independent of human will; (b) Twelve (12) kilometers, more or less, sir.
it must be impossible to foresee the event that constitutes the Q
caso fortuito or, if it can be foreseen, it must be impossible to Is this Barangay Aras populated?
avoid; (c) the occurrence must be such as to render it impossible A
for the debtor to fulfill obligations in a normal manner; and (d) Not so many, sir.
the obligor must be free from any participation in the Q
aggravation of the injury or loss.12 The place where the 6 x 6 truck had transmission trouble, how
far is the nearest house from it?
A
Perhaps three hundred meters, sir. Q
Q How did you come to know that the 6 x 6 truck was burned on
And how many houses are within the three hundred meter April 11, 1991?
radius from the place where the truck had engine trouble? A
A I together with my daughter, I met the service of the company
Ten, more or less, in scattered. near the ORMECO and I was informed by the Project Engineer
Q that the 6 x 6 truck was burned, so, we returned to San Teodoro
You said that after hauling several sand to be used in the camp and have the incident blottered at the police station.
site the 6 x 6 truck had transmission trouble, what did the Q
company do after the truck had that engine trouble? Aside from that, what other action did you undertake in
A connection with the burning of the 6 x 6 truck?
For at least two weeks the truck was installed in the place where A
the said truck had engine trouble. When we were at the police station, the Project Manager of the
Q company arrived and from the police station we proceeded to
Meaning in Barangay Aras? the place where the 6 x 6 truck was burned and the Project
A Manager took pictures of the 6 x 6 truck.
Yes, sir. Q
Q Now, did you come to know who was responsible or who were
Was there any guard in that place by the company during the responsible for the burning of the 6 x 6 truck?
time that the truck was in that place? A
A The responsible is the Mindex Resources Development
Yes, sir, during daytime but at nighttime, there was no guard. Corporation, and as far as I know, the persons who actually
Q burned the said 6 x 6 truck were the dismissed employees of the
What happened to that 6 x 6 truck? Min-dex Resources Development Corporation.
A Q
In the month of March, 1991, the company dismissed thirteen These dismissed employees of the corporation, why were they
(13) to seventeen (17) employees and these employees came employed by the corporation?
from Barangays Aras, Botolan, Calsapa, Camatis and Tibon- bon A
and on April 11, 1991, the 6 x 6 truck was burned.
Because we have to make a road going to the mining site and in Moreover, the RTC based the P76,000 rental and the costs of
the process of opening the road these dismissed employees repair and overhaul on Exhibit “B,” wherein Chito Gozar, the
happened to be the owners of the land where the road will pass, Project Manager of Mindex Resources Development
so, we paid the land. The corporation likewise gave jobs to the Corporation, proposed through a letter dated April 17, 1991, the
owners of the land.”14 following: (1) to pay the P76,000 rental, (2) to repair the truck
As can be gleaned from the foregoing testimony, petitioner failed at the expense of petitioner, and (3) to return the truck in good
to employ reasonable foresight, diligence and care that would running condition after the repair.
have exempted it from liability resulting from the burning of the Likewise, the nonpayment of the said amount was corroborated
truck. Negligence, as commonly understood, is that conduct that by Roxas thus:
naturally or reasonably creates undue risk or harm to others. It “Q
may be a failure to observe that degree of care, precaution or During that time when the 6 x 6 truck was already burned and
vigilance that the circumstances justly demand;15 or to do any when you went to the Petron Gasoline Station to inform plaintiff
other act that would be done by a prudent and reasonable about the burning, was the plaintiff paid any amount for the
person, who is guided by considerations that ordinarily regulate rental of the 6 x 6 truck?
the conduct of human affairs.16 A
Before the burning of the 6 x 6 truck, the plaintiff Morillo was
Second Issue: already paid partially and there was a balance of P76,000.00.”18
Unpaid Rentals and Cost of Repairs The P132,750 repair and overhaul costs was correctly granted
Petitioner proceeds to argue that “it should be deemed to have by the lower courts. Article 1667 of the Civil Code holds the
already paid the unpaid rentals in the amount of P76,000.00,” lessee responsible for the deterioration or loss of the thing
and that it should not be made to pay the P132,750 repair and leased. In addition, Article 1665 of the same Code provides that
overhaul costs. Nothing in the records, not even in the “the lessee shall return the thing leased, upon the termination of
documentary evidence it presented, would show that it already the lease, just as he received it, save what has been lost or
paid the aforesaid amounts. In fact, it seeks to avoid payment of impaired by the lapse of time, or by ordinary wear and tear, or
the rental by alleging that respondent already condoned it in his from an inevitable cause.”
letter dated April 15, 1991. However, a perusal of the letter Courts begin with the assumption that compensatory damages
would show that his offer not to charge petitioner for the are for pecuniary losses that result from an act or omission of
P76,000 rental was premised on the condition that it would buy the defendant. Having been found to be negligent in
the truck.17 safeguarding the leased truck, petitioner must shoulder its
repair and overhaul costs to make it serviceable again. Such petitioner’s bad faith in refusing to pay the said rentals as well
expenses are duly supported by receipts; thus, the award of as the repair and overhaul costs.21
P132,750 is definitely in order. WHEREFORE, the Petition is DENIED, but the assailed CA
Decision is MODIFIED by DELETING the award of attorney’s
fees. Costs against petitioner.
Third Issue: SO ORDERED.
Attorney’s Fees
We find the award of attorney’s fees to be improper. The reason      Melo (Chairman), Vitug, Sandoval-Gutierrez and Carpio, JJ.,
which the RTC gave—because petitioner had compelled concur.
respondent to file an action against it—falls short of our Petition denied, judgment modified.
requirement in Scott Consultants and Resource Development v. Notes.—In order that a fortuitous event may exempt a person
CA,19 from which we quote: from liability, it is necessary that he be free from negligence—an
“It is settled that the award of attorney’s fees is the exception act of God cannot be urged for the protection of a person who
rather than the rule and counsel’s fees are not to be awarded has been guilty of gross negligence in not trying to avert its
every time a party wins suit. The power of the court to award results. (Metal Forming Corporation vs. Office of the President,
attorney’s fees under Article 2208 of the Civil Code demands 247 SCRA 731 [1995])
factual, legal, and equitable justification; its basis cannot be left Factual findings of the trial court shall not be disturbed on
to speculation or conjecture. Where granted, the court must appeal unless the trial court has overlooked or ignored some
explicitly state in the body of the decision, and not only in the fact or circumstance of sufficient weight or significance which, if
dispositive portion thereof, the legal reason for the award of considered, would alter the situation. (AHS/Philippines, Inc. vs.
attorney’s fees.” Court of Appeals, 257 SCRA 319 [1996])
——o0o——
Moreover, a recent case20 ruled that “in the absence of
stipulation, a winning party may be awarded attorney’s fees only
in case plaintiff’s action or defendant’s stand is so untenable as
to amount to gross and evident bad faith.”
Indeed, respondent was compelled to file this suit to vindicate
his rights. However, such fact by itself will not justify an award
of attorney’s fees, when there is no sufficient showing of
SUPREME COURT REPORTS ANNOTATED of a person who has been guilty of gross negligence in not trying
Southeastern College, Inc. vs. Court of Appeals to forestall its possible adverse consequences. When a person’s
G.R. No. 126389. July 10, 1998.* negligence concurs with an act of God in producing damage or
SOUTHEASTERN COLLEGE, INC., petitioner, vs. COURT OF injury to another, such person is not exempt from liability by
APPEALS, JUANITA DE JESUS VDA. DE DIMAANO, EMERITA showing that the immediate or proximate cause of the damage
DIMAANO, REMEDIOS DIMAANO, CONSOLACION DIMAANO or injury was a fortuitous event. When the effect is found to be
and MILAGROS DIMAANO, respondents. partly the result of the participation of man—whether it be from
active intervention, or neglect, or failure to act—the whole
Obligations and Contracts; Fortuitous Events; Words and occurrence is hereby humanized, and removed from the rules
Phrases; The antecedent of fortuitous event or caso fortuito is applicable to acts of God.
found in the Partidas which defines it as “an event which takes
place by accident and could not have been foreseen.”—The Same; Same; Typhoons; Words and Phrases; “Negligence,”
antecedent of fortuitous event or caso fortuito is found in the Explained; There is no question that a typhoon or storm is a
Partidas which defines it as “an event which takes place by fortuitous event, a natural occurrence which may be foreseen
accident and could not have been foreseen.” Escriche elaborates but is unavoidable despite any amount of foresight, diligence or
it as “an unexpected event or act of God which could neither be care.—There is no question that a typhoon or storm is a
foreseen nor resisted.” Civilist Arturo M. Tolentino adds that fortuitous event, a natural occurrence which may be foreseen
“[f]ortuitous events may be produced by two general causes: (1) but is unavoidable despite any amount of foresight, diligence or
by nature, such as earthquakes, storms, floods, epidemics, fires, care. In order to be exempt from liability arising from any
etc. and (2) by the act of man, such as an armed invasion, attack adverse consequence engendered thereby, there should have
by bandits, governmental prohibitions, robbery, etc.” been no human participation amounting to a negligent act. In
other words, the person seeking exoneration from liability must
Same; Same; An act of God cannot be invoked for the protection not be guilty of negligence. Negligence, as commonly
of a person who has been guilty of gross negligence in not trying understood, is conduct which naturally or reasonably creates
to forestall its possible adverse consequences.—In order that a undue risk or harm to others. It may be the failure to observe
fortuitous event may exempt a person from liability, it is that degree of care, precaution, and vigilance which the
necessary that he be free from any previous negligence or circumstances justly demand, or the omission to do something
misconduct by reason of which the loss may have been which a prudent and reasonable man, guided by considerations
occasioned. An act of God cannot be invoked for the protection which ordinarily regulate the conduct of human affairs, would
do. From these premises, we proceed to determine whether very least, prima facie evidence of the regular and proper
petitioner was negligent, such that if it were not, the damage construction of a building.—On the other hand, petitioner
caused to private respondents’ house could have been avoided? elicited from one of the witnesses of private respondents, city
Same; Same; Same; Same; Ocular Inspections; Damages; A building official Jesus Reyna, that the original plans and design
person claiming damages for the negligence of another has the of petitioner’s school building were approved prior to its
burden of proving the existence of fault or negligence causative construction. Engr. Reyna admitted that it was a legal
of his injury or loss; As the term imparts, an ocular inspection is requirement before the construction of any building to obtain a
one by means of actual sight or viewing—what is visual to the permit from the city building official (city engineer, prior to the
eye though, is not always reflective of the real cause behind.—At passage of the Building Act of 1977). In like manner, after
the outset, it bears emphasizing that a person claiming damages construction of the building, a certification must be secured
for the negligence of another has the burden of proving the from the same official attesting to the readiness for occupancy of
existence of fault or negligence causative of his injury or loss. the edifice. Having obtained both building permit and certificate
The facts constitutive of negligence must be affirmatively of occupancy, these are, at the very least, prima facie evidence of
established by competent evidence, not merely by presumptions the regular and proper construction of subject school building.
and conclusions without basis in fact. Private respondents, in Same; Same; Same; Judicial Notice; It is a matter of judicial
establishing the culpability of petitioner, merely relied on the notice that typhoons are common occurrences in this country.—
aforementioned report submitted by a team which made an Moreover, the city building official, who has been in the city
ocular inspection of petitioner’s school building after the government service since 1974, admitted in open court that no
typhoon. As the term imparts, an ocular inspection is one by complaint regarding any defect on the same structure has ever
means of actual sight or viewing. What is visual to the eye been lodged before his office prior to the institution of the case
though, is not always reflective of the real cause behind. For at bench. It is a matter of judicial notice that typhoons are
instance, one who hears a gunshot and then sees a wounded common occurrences in this country. If subject school building’s
person, cannot always definitely conclude that a third person roofing was not firmly anchored to its trusses, obviously, it could
shot the victim. It could have been self-inflicted or caused not have withstood long years and several typhoons even
accidentally by a stray bullet. The relationship of cause and stronger than “Saling.”
effect must be clearly shown.
Same; Same; Damages; It is not enough that the damage be
Same; Same; Same; Building Permits; Having obtained both capable of proof but must be actually proved with a reasonable
building permit and certificate of occupancy, these are, at the degree of certainty, pointing out specific facts that afford a basis
for measuring whatever compensatory damages are borne.— The Resolution under attack denied petitioner’s motion for
Private respondents failed to adduce adequate and competent reconsideration.
proof of the pecuniary loss they actually incurred. It is not Private respondents are owners of a house at 326 College Road,
enough that the damage be capable of proof but must be actually Pasay City, while petitioner owns a four-storey school building
proved with a reasonable degree of certainty, pointing out along the same College Road. On October 11, 1989, at about 6:30
specific facts that afford a basis for measuring whatever in the morning, a powerful typhoon “Saling” hit Metro Manila.
compensatory damages are borne. Private respondents merely Buffeted by very strong winds, the roof of petitioner’s building
submitted an estimated amount needed for the repair of the roof was partly ripped off and blown away, landing on and
of their subject building. What is more, whether the “necessary destroying portions of the roofing of private respondents’ house.
repairs” were caused ONLY by petitioner’s alleged negligence in After the typhoon had passed, an ocular inspection of the
the maintenance of its school building, or included the ordinary destroyed buildings was conducted by a team of engineers
wear and tear of the house itself, is an essential question that headed by the city buildings official, Engr. Jesus L. Reyna.
remains indeterminable. Pertinent aspects of the latter’s Report5 dated October 18, 1989
stated, as follows:
PETITION for review on certiorari of a decision of the Court of
Appeals. “5. One of the factors that may have led to this calamitous event
is the formation of the buildings in the area and the general
The facts are stated in the opinion of the Court. direction of the wind. Situated in the peripheral lot is an almost
     Eladio B. Samson for petitioner. U-shaped formation of 4-storey building. Thus, with the strong
     Galileo P. Brion for private respondents. winds having a westerly direction, the general formation of the
PURISIMA, J.: buildings becomes a big funnel-like structure, the one situated
along College Road, receiving the heaviest impact of the strong
Petition for review under Rule 45 of the Rules of Court seeking winds. Hence, there are portions of the roofing, those located on
to set aside the Decision1 promulgated on July 31, 1996, and both ends of the building, which remained intact after the storm.
Resolution2 dated September 12, 1996 of the Court of Appeals3 6. Another factor and perhaps the most likely reason for the
in CA-G.R. No. 41422, entitled “Juanita de Jesus vda. de Dimaano, dislodging of the roofings structural trusses is the improper
et al. vs. Southeastern College, Inc.,” which reduced the moral anchorage of the said trusses to the roof beams. The 1/2”
damages awarded below from P1,000,000.00 to P200,000.00.4 diameter steel bars embedded on the concrete roof beams which
serve as truss anchorage are not bolted nor nailed to the trusses.
Still, there are other steel bars which were not even bent to the The trial court, giving credence to the ocular inspection report to
trusses, thus, those trusses are not anchored at all to the roof the effect that subject school building had a “defective roofing
beams.” structure,” found that, while typhoon “Saling” was accompanied
It then recommended that “to avoid any further loss and damage by strong winds, the damage to private respondents’ house
to lives, limbs and property of persons living in the vicinity,” the “could have been avoided if the construction of the roof of
fourth floor of subject school building be declared as a [petitioner’s] building was not faulty.” The dispositive portion of
“structural hazard.” the lower court’s decision7 reads, thus:

In their Complaint6 before the Regional Trial Court of Pasay “WHEREFORE, in view of the foregoing, the Court renders
City, Branch 117, for damages based on culpa aquiliana, private judgment (sic) in favor of the plaintiff (sic) and against the
respondents alleged that the damage to their house rendered defendants, (sic) ordering the latter to pay jointly and severally
the same uninhabitable, forcing them to stay temporarily in the former as follows:
other’s houses. And so they sought to recover from petitioner a) P117,116.00 as actual damages, plus litigation expenses;
P117,116.00, as actual damages, P1,000,000.00, as moral b) P1,000,000.00 as moral damages;
damages, P300,000.00, as exemplary damages and P100,000.00, c) P100,000.00 as attorney’s fees;
for and as attorney’s fees; plus costs. d) Costs of the instant suit.
The claim for exemplary damages is denied for the reason that
In its Answer, petitioner averred that subject school building the defendants (sic) did not act in a wanton, fraudulent, reckless,
had withstood several devastating typhoons and other oppressive or malevolent manner.”
calamities in the past, without its roofing or any portion thereof In its appeal to the Court of Appeals, petitioner assigned as
giving way; that it has not been remiss in its responsibility to see errors,8 that:
to it that said school building, which houses school children, I
faculty members, and employees, is “in tip-top condition”; and THE TRIAL COURT ERRED IN HOLDING THAT TYPHOON
furthermore, typhoon “Saling” was “an act of God and therefore “SALING,” AS AN ACT OF GOD, IS NOT “THE SOLE AND
beyond human control” such that petitioner cannot be ABSOLUTE REASON” FOR THE RIPPING-OFF OF THE SMALL
answerable for the damages wrought thereby, absent any PORTION OF THE ROOF OF SOUTHEASTERN’S FOUR (4)
negligence on its part. STOREY SCHOOL BUILDING.
_______________
II without proof or receipts of actual damage, [sic] legally feasible
THE TRIAL COURT ERRED IN HOLDING THAT “THE or justified.
CONSTRUCTION OF THE ROOF OF DEFENDANT’S SCHOOL 2. Whether or not the award of moral damages to respondent
BUILDING WAS FAULTY” NOTWITHSTANDING THE ADMISSION Dimaanos, without the latter having suffered, actual damage has
THAT THERE WERE TYPHOONS BEFORE BUT NOT AS GRAVE legal basis.
AS TYPHOON “SALING” WHICH IS THE DIRECT AND 3. Whether or not respondent Dimaanos who are no longer the
PROXIMATE CAUSE OF THE INCIDENT. owner of the property, subject matter of the case, during its
III pendency, has the right to pursue their complaint against
THE TRIAL COURT ERRED IN AWARDING ACTUAL AND MORAL petitioner when the case was already rendered moot and
DAMAGES AS WELL AS ATTORNEY’S FEES AND LITIGATION academic by the sale of the property to third party.
EXPENSES AND COSTS OF SUIT TO DIMAANOS WHEN THEY 4. Whether or not the award of attorney’s fees when the case
HAVE NOT INCURRED ACTUAL DAMAGES AT ALL AS was already moot and academic [sic] legally justified.
DIMAANOS HAVE ALREADY SOLD THEIR PROPERTY, AN 5. Whether or not petitioner is liable for damage caused to
INTERVENING EVENT THAT RENDERS THIS CASE MOOT AND others by typhoon “Saling” being an act of God.
ACADEMIC. 6. Whether or not the issuance of a writ of execution pending
IV appeal, ex-parte or without hearing, has support in law.”
THE TRIAL COURT ERRED IN ORDERING THE ISSUANCE OF The pivot of inquiry here, determinative of the other issues, is
THE WRIT OF EXECUTION INSPITE OF THE PERFECTION OF whether the damage on the roof of the building of private
SOUTHEASTERN’S APPEAL WHEN THERE IS NO COMPELLING respondents resulting from the impact of the falling portions of
REASON FOR THE ISSUANCE THERETO. the school building’s roof ripped off by the strong winds of
typhoon “Saling,” was, within legal contemplation, due to
As mentioned earlier, respondent Court of Appeals affirmed fortuitous event? If so, petitioner cannot be held liable for the
with modification the trial court’s disposition by reducing the damages suffered by the private respondents. This conclusion
award of moral damages from P1,000,000.00 to P200,000.00. finds support in Article 1174 of the Civil Code, which provides:
Hence, petitioner’s resort to this Court, raising for resolution the “Art. 1174. Except in cases expressly specified by the law, or
issues of: when it is otherwise declared by stipulation, or when the nature
“1. Whether or not the award of actual damage [sic] to of the obligation requires the assumption of risk, no person shall
respondent Dimaanos on the basis of speculation or conjecture, be responsible for those events which could not be foreseen, or
which, though foreseen, were inevitable.”
The antecedent of fortuitous event or caso fortuito is found in in position especially when battered by strong winds.” Based on
the Partidas which defines it as “an event which takes place by such finding, the trial court imputed negligence to petitioner and
accident and could not have been foreseen.”9 Escriche adjudged it liable for damages to private respondents.
elaborates it as “an unexpected event or act of God which could After a thorough study and evaluation of the evidence on record,
neither be foreseen nor resisted.”10 Civilist Arturo M. Tolentino this Court believes otherwise, notwithstanding the general rule
adds that “[f]ortuitous events may be produced by two general that factual findings by the trial court, especially when affirmed
causes: (1) by nature, such as earthquakes, storms, floods, by the appellate court, are binding and conclusive upon this
epidemics, fires, etc. and (2) by the act of man, such as an armed Court.14 After a careful scrutiny of the records and the
invasion, attack by bandits, governmental prohibitions, robbery, pleadings submitted by the parties, we find exception to this
etc.”11 rule and hold that the lower courts misappreciated the evidence
proffered.
In order that a fortuitous event may exempt a person from
liability, it is necessary that he be free from any previous There is no question that a typhoon or storm is a fortuitous
negligence or misconduct by reason of which the loss may have event, a natural occurrence which may be foreseen but is
been occasioned.12 An act of God cannot be invoked for the unavoidable despite any amount of foresight, diligence or
protection of a person who has been guilty of gross negligence in care.15 In order to be exempt from liability arising from any
not trying to forestall its possible adverse consequences. When a adverse consequence engendered thereby, there should have
person’s negligence concurs with an act of God in producing been no human participation amounting to a negligent act.16 In
damage or injury to another, such person is not exempt from other words, the person seeking exoneration from liability must
liability by showing that the immediate or proximate cause of not be guilty of negligence. Negligence, as commonly
the damage or injury was a fortuitous event. When the effect is understood, is conduct which naturally or reasonably creates
found to be partly the result of the participation of man— undue risk or harm to others. It may be the failure to observe
whether it be from active intervention, or neglect, or failure to that degree of care, precaution, and vigilance which the
act—the whole occurrence is hereby humanized, and removed circumstances justly demand,17 or the omission to do
from the rules applicable to acts of God.13 something which a prudent and reasonable man, guided by
considerations which ordinarily regulate the conduct of human
In the case under consideration, the lower court accorded full affairs, would do.18 From these premises, we proceed to
credence to the finding of the investigating team that subject determine whether petitioner was negligent, such that if it were
school building’s roofing had “no sufficient anchorage to hold it
not, the damage caused to private respondents’ house could establish that the construction of such building was basically
have been avoided? flawed.21
On the other hand, petitioner elicited from one of the witnesses
At the outset, it bears emphasizing that a person claiming of private respondents, city building official Jesus Reyna, that the
damages for the negligence of another has the burden of original plans and design of petitioner’s school building were
proving the existence of fault or negligence causative of his approved prior to its construction. Engr. Reyna admitted that it
injury or loss. The facts constitutive of negligence must be was a legal requirement before the construction of any building
affirmatively established by competent evidence,19 not merely to obtain a permit from the city building official (city engineer,
by presumptions and conclusions without basis in fact. Private prior to the passage of the Building Act of 1977). In like manner,
respondents, in establishing the culpability of petitioner, merely after construction of the building, a certification must be secured
relied on the aforementioned report submitted by a team which from the same official attesting to the readiness for occupancy of
made an ocular inspection of petitioner’s school building after the edifice. Having obtained both building permit and certificate
the typhoon. As the term imparts, an ocular inspection is one by of occupancy, these are, at the very least, prima facie evidence of
means of actual sight or viewing.20 What is visual to the eye the regular and proper construction of subject school
though, is not always reflective of the real cause behind. For building.22
instance, one who hears a gunshot and then sees a wounded
person, cannot always definitely conclude that a third person Furthermore, when part of its roof needed repairs of the damage
shot the victim. It could have been self-inflicted or caused inflicted by typhoon “Saling,” the same city official gave the go-
accidentally by a stray bullet. The relationship of cause and signal for such repairs—without any deviation from the original
effect must be clearly shown. design—and subsequently, authorized the use of the entire
fourth floor of the same building. These only prove that subject
In the present case, other than the said ocular inspection, no building suffers from no structural defect, contrary to the report
investigation was conducted to determine the real cause of the that its “U-shaped” form was “structurally defective.” Having
partial unroofing of petitioner’s school building. Private given his unqualified imprimatur, the city building official is
respondents did not even show that the plans, specifications and presumed to have properly performed his duties23 in
design of said school building were deficient and defective. connection therewith.
Neither did they prove any substantial deviation from the
approved plans and specifications. Nor did they conclusively In addition, petitioner presented its vice president for finance
and administration who testified that an annual maintenance
inspection and repair of subject school building were regularly cause damage was alleged and proven to warrant moral
undertaken. Petitioner was even willing to present its damages.
maintenance supervisor to attest to the extent of such regular Private respondents failed to adduce adequate and competent
inspection but private respondents agreed to dispense with his proof of the pecuniary loss they actually incurred.26 It is not
testimony and simply stipulated that it would be corroborative enough that the damage be capable of proof but must be actually
of the vice president’s narration. proved with a reasonable degree of certainty, pointing out
specific facts that afford a basis for measuring whatever
Moreover, the city building official, who has been in the city compensatory damages are borne.27 Private respondents
government service since 1974, admitted in open court that no merely submitted an estimated amount needed for the repair of
complaint regarding any defect on the same structure has ever the roof of their subject building. What is more, whether the
been lodged before his office prior to the institution of the case “necessary repairs” were caused ONLY by petitioner’s alleged
at bench. It is a matter of judicial notice that typhoons are negligence in the maintenance of its school building, or included
common occurrences in this country. If subject school building’s the ordinary wear and tear of the house itself, is an essential
roofing was not firmly anchored to its trusses, obviously, it could question that remains indeterminable.
not have withstood long years and several typhoons even
stronger than “Saling.” The Court deems unnecessary to resolve the other issues posed
by petitioner.
In light of the foregoing, we find no clear and convincing As regards the sixth issue, however, the writ of execution issued
evidence to sustain the judgment of the appellate court. We thus on April 1, 1993 by the trial court is hereby nullified and set
hold that petitioner has not been shown negligent or at fault aside. Private respondents are ordered to reimburse any
regarding the construction and maintenance of its school amount or return to petitioner any property which they may
building in question and that typhoon “Saling” was the have received by virtue of the enforcement of said writ.
proximate cause of the damage suffered by private respondents’ WHEREFORE, the petition is GRANTED and the challenged
house. Decision is REVERSED. The complaint of private respondents in
Civil Case No. 7314 before the trial court a quo is ordered
With this disposition on the pivotal issue, private respondents’ DISMISSED and the writ of execution issued on April 1, 1993 in
claim for actual and moral damages as well as attorney’s fees said case is SET ASIDE. Accordingly, private respondents are
must fail.24 Petitioner cannot be made to answer for a purely ORDERED to return to petitioner any amount or property
fortuitous event.25 More so because no bad faith or willful act to
received by them by virtue of said writ. Costs against the private shall earn default interest, and the respondent-banks have four
respondents. alternative remedies without prejudice to the application of the
SO ORDERED. provisions on collaterals and any other steps or action which
     Narvasa (C.J., Chairman), Romero and Kapunan, JJ., concur. may be adopted by the majority lender. The four remedies are
Petition granted, judgment reversed. alternative, with the right of choice given to the lenders, in this
Notes.—Considering the weather situation in the country where case the respondents. Under Article 1201 of the Civil Code, the
storms and typhoons are not a rare or unusual occurrence, these choice shall produce no effect except from the time it has been
terms ought to, as they should only be, understood as communicated. This is the reason why a written notice is
comprehending and referring practically to the same thing, at required under Section 6.02 of the Omnibus Agreement.
least insofar as the jural effects of petitioner’s
misrepresentations are concerned. (Metal Forming Corporation Same; Same; Breach; Fortuitous Event; Requisites; To exempt
vs. Office of the President, 247 SCRA 731 [1995]) the obligor from liability for a breach of an obligation by reason
It is within a judge’s right to conduct an ocular inspection since of a fortuitous event, the following requisites must concur.—
it is an exercise of his judicial prerogative. (Webb vs. People, 276 Said event, the Asian financial crisis of 1997, is not among the
SCRA 243 [1997]) [Southeastern College, Inc. vs. Court of fortuitous events contemplated under Article 1174[19] of the
Appeals, 292 SCRA 422(1998)] Civil Code. To exempt the obligor from liability for a breach of an
obligation by reason of a fortuitous event, the following
requisites must concur: (a) the cause of the breach of the
Mondragon Leisure and Resorts Corporation vs. Court of obligation must be independent of the will of the debtor; (b) the
Appeals event must be either unforeseeable or unavoidable; (c) the event
G.R. No. 154188. June 15, 2005.* must be such as to render it impossible for the debtor to fulfill
MONDRAGON LEISURE AND RESORTS CORPORATION, his obligation in a normal manner; and (d) the debtor must be
petitioner, vs. COURT OF APPEALS, ASIAN BANK free from any participation in, or aggravation of the injury to the
CORPORATION, FAR EAST BANK AND TRUST COMPANY, and creditor.
UNITED COCONUT PLANTERS BANK, respondents. PETITION for review on certiorari of the decision and resolution
of the Court of Appeals.
Civil Law; Contracts; Defaults; The four remedies are alternative,
with the right of choice given to the lenders, in this case the The facts are stated in the opinion of the Court.
respondents.—As a consequence of default, the unpaid amount
     Angara, Abello, Concepcion, Regala and Cruz for private To secure the repayment of the loan, petitioner pledged in favor
respondents. of respondents US$20M worth of MIPI shares of stocks;
QUISUMBING, J.: assigned, transferred and delivered all rights, title to and
interest in the pledged shares; and assigned by way of security
In its Decision1 dated March 12, 2002, the Court of Appeals in its leasehold rights over the project and all the rights, title,
CA-G.R. SP No. 61047 dismissed the petition for certiorari filed interests and benefits in, to and under any and all agreements in
by Mondragon Leisure and Resorts Corporation against the connection with the project.
Order2 dated March 9, 2000, of the Regional Trial Court of
Angeles City, Branch 61, in Civil Case No. 9527. Likewise, in its On July 3, 1997, petitioner fully availed of and received the full
Resolution dated July 3, 2002, the CA denied the motion for amount of the syndicated loan agreement. Petitioner, which had
reconsideration. regularly paid the monthly interests due on the promissory
notes until October 1998, thereafter failed to make payments.
The facts of the case are undisputed. Consequently, on January 6 and February 5,1999, written
On February 28, 1994, Mondragon International Philippines, Inc. notices of default, acceleration of payment and demand letters
(MIPI), Mondragon Securities Corporation (MSC) and herein were sent by the lenders to the petitioner. Then on August 27,
petitioner entered into a lease agreement with the Clark 1999, respondents filed a complaint, docketed as Civil Case No.
Development Corporation (CDC) for the development of what is 9527, for the foreclosure of leasehold rights against petitioner.
now known as the Mimosa Leisure Estate. Petitioner moved for the dismissal of the complaint on the
following grounds: (1) a condition precedent for the filing of the
To help finance the project, petitioner, on June 30, 1997, entered complaint has not been complied with and/or the instant
into an Omnibus Loan and Security Agreement3 (hereafter complaint failed to state a cause of action, or otherwise the filing
Omnibus Agreement) with respondent banks for a syndicated was premature; (2) the certification of non-forum shopping
term loan in the aggregate principal amount of US$20M. Under appended to the complaint was fatally defective since one of the
the agreement, as amended on January 19, 1999,4 the proceeds plaintiffs, UCPB, deliberately failed to mention that it had
of the loan were to be released through advances evidenced by previously filed another complaint; and (3) plaintiffs had
promissory notes to be executed by petitioner in favor of each engaged in forum shopping in filing the instant complaint.
lender-bank, and to be paid within a six-year period from the The trial court denied the motion and ruled as follows:
date of initial advance inclusive of a one year and two quarters ...
grace period.
“After a careful study of the arguments of the parties, this court of the respondents to attach the board resolutions authorizing
finds that the motion to dismiss is without merit. As correctly them to file the complaint.7
pointed out by the plaintiffs under par. 6.01, the borrower The Court of Appeals dismissed the petition and denied the
defaults when interests due at stated maturity are not paid and subsequent motion for reconsideration. Hence, this appeal by
the lenders are authorized to accelerate any amount payable certiorari8 imputing the following errors:
under the loan agreements. One of the consequences of such I
default is the foreclosure of collaterals. This is the action taken
by the herein plaintiffs-lenders. THE RESPONDENT-APPELLEE COURT OF APPEALS
This court also finds the alleged force majeure baseless. The COMMITTED A SERIOUS ERROR OF LAW AND ACTED WITH
same are not those provided for under Sec. 1, Article 41 of the GRAVE ABUSE OF DISCRETION AMOUNTING TO LACK OR
loan agreement. EXCESS OF JURISDICTION IN RULING THAT THE COMPLAINT IN
As to the allegation of forum shopping, the herein parties Asian CIVIL CASE NO. 9527 COMPLIED WITH THE MANDATORY
Bank Corporation and Far East Bank and Trust Company are not REQUIREMENTS OF CERTIFICATION OF NON-FORUM
parties to this case in 9510 (sic). The subject matter of Civil Case SHOPPING.
No. 9527 is not the same with the subject matter in Civil Case II
No. 9510.
THE RESPONDENT-APPELLEE COURT OF APPEALS
Wherefore, premises considered, the motion to dismiss is COMMITTED A SERIOUS ERROR OF LAW AND ACTED WITH
denied. The defendant is given 15 days from receipt hereof GRAVE ABUSE OF DISCRETION AMOUNTING TO LACK OR
within which to file its answer and/or responsive pleading. EXCESS OF JURISDICTION IN NOT RULING THAT A CONDITION
SO ORDERED.”5 PRECEDENT FOR THE FILING OF THE COMPLAINT IN CIVIL
CASE NO. 9527 HAS NOT BEEN COMPLIED WITH, OR THAT IT IS
Petitioner moved for the reconsideration of the order and OTHERWISE PREMATURE, AND/OR THAT IT FAILS TO STATE A
argued that the complaint is premature, since it had not been CAUSE OF ACTION AGAINST PETITIONER-APPELLANT.
validly declared in default.6 The trial court denied the motion III
for reconsideration. Seasonably, petitioner filed a special civil
action for certiorari with the Court of Appeals. THE RESPONDENT-APPELLEE COURT OF APPEALS
Before the appellate court, petitioner reiterated its arguments in COMMITTED A SERIOUS ERROR OF LAW AND ACTED WITH
its motion to dismiss before the trial court, including the failure GRAVE ABUSE OF DISCRETION AMOUNTING TO LACK OR
EXCESS OF JURISDICTION IN NOT RULING THAT RESPONDENT- not err in denying the motion to dismiss. The issue concerning
APPELLEE BANKS, IN FILING THE COMPLAINT IN CIVIL CASE the signatories’ authorization was never raised before it.
NO. 9527, DELIBERATELY ENGAGED IN FORUM SHOPPING.9 Likewise, the appellate court did not err in refusing to take
In brief, three issues are presented for resolution, namely, (1) cognizance of the issue, since the parties did not raise it
Was the certificate of non-forum shopping defective? (2) Did beforehand. Issues not raised in the trial court cannot be raised
respondents engage in forum shopping? and (3) Do respondents for the first time on appeal.10
have a cause of action against the petitioner? On the second issue, petitioner claims that respondent UCPB
engaged in forum shopping since it earlier instituted an action
On the first issue, petitioner asserts that the verification and for foreclosure of mortgage and/or collection, docketed as Civil
certificate of forum shopping were defective because there was Case No. 9510.11 This claim, in our view, is untenable. A
no proof as to the authority of the signatories to file the comparison of the two complaints would show its utter lack of
complaint. Petitioner avers that UCPB Resolution 48-87, which merit.
was only presented in the Court of Appeals, merely authorized
the signatory to “appear, act for, or otherwise represent the Civil Case No. 9510 pertains to an Omnibus Credit and Security
bank in all judicial, quasi-judicial or administrative hearings or Agreement executed by and between the petitioner and
incidents, including pre-trial conference, and in connection respondent UCPB on November 23, 1995. This is separate and
therewith, to do any and all of the following acts and deeds . . .” distinct from the Omnibus Agreement involved in Civil Case No.
and clearly pertains to a pending proceeding. 9527. Moreover, respondents Asian Bank and Far East Bank are
not among the parties to Civil Case No. 9510.
Respondents, on the other hand, contend that the lack of As pointed out by the Court of Appeals, forum shopping exists
authority of the persons who verified and certified the when both actions involve the same transactions, with the same
complaint was neither raised in the motion to dismiss nor in the essential facts and circumstances; and where identical causes of
motion for reconsideration of the petitioner. They aver that the actions, subject matter and issues are raised. The test to
verification and certification of non-forum shopping contained a determine the existence of forum shopping is whether the
statement by the persons who signed it that they had been so elements of litis pendentia are present, or whether a final
authorized by the board of directors of their respective judgment in one case will amount to res judicata in another.12
corporations. The requisites in order that an action may be dismissed on the
Considering the submissions of the parties, we are constrained ground of litis pendentia are (a) the identity of parties, or at
to agree with the respondents’ contention. The trial court did least such as representing the same interest in both actions; (b)
the identity of rights asserted and relief prayed for, the relief On this issue, we are unable to agree with the petitioner.
being founded on the same facts; and (c) the identity of the two Section 2.06 (a) of Part B of the Omnibus Agreement provides
cases such that judgment in one, regardless of which party is that the borrower shall pay interest on the advances
successful, would amount to res judicata in the other.13 Such outstanding from time to time on each interest payment date,
requisites are not present in this controversy. while Section 6 of Part A reads
6.01 Events of Default
Apropos the third issue, petitioner contends the subject Each of the following events shall constitute an Event of Default
obligation of the instant case is not yet due and demandable under this Omnibus Agreement:
because the Omnibus Agreement allows a full six-year term of (a) Payment Default—The BORROWER defaults in the payment
payment. Even if it failed to pay some installments, petitioner when due at stated maturity, by acceleration or otherwise, of
insists it is not in default because respondents merely sent any amount payable under the Loan Documents.14
collection and demand letters, but failed to give the written ...
notice of default required under their agreement. Moreover, Clearly, under the foregoing provisions of the Agreement,
petitioner avers that the provisions on default in the Omnibus petitioner may be validly declared in default for failure to pay
Agreement have been rendered inapplicable and unenforceable the interest. As a consequence of default, the unpaid amount
by fortuitous events, namely the Asian economic crisis and the shall earn default interest,15 and the respondent-banks have
closure of the Mimosa Regency Casino, which was petitioner’s four alternative remedies without prejudice to the application of
primary source of revenues. the provisions on collaterals and any other steps or action which
may be adopted by the majority lender.16
Respondents counter that the Omnibus Agreement defines, as an
event of default, the failure of petitioner to pay when due at Notwithstanding anything in this Omnibus Agreement to the
stated maturity, by acceleration or otherwise, any amount contrary, if the BORROWER fails to make payment when due of
payable under the loan documents. Since petitioner is also any sum hereunder (whether at stated maturity, by acceleration
required to pay interest, respondents posit that non-payment or otherwise), the BORROWER shall, in addition to the interest
thereof constituted a clear and unmistakable case of default. then applicable as determined pursuant to Section 2.06(b) of
Respondents add that they had properly advised the petitioner Part B, pay to the LENDERS default interest on such past due
that it had been declared in default, referring to the January 6 and unpaid amount from due date until date of full payment
and February 5, 1999 letters as their compliance with the notice (both before as well as after judgment) to be computed at the
requirement. rate of two percent (2%) per month.
16 Ibid. hereunder, to be forthwith due and payable, whereupon the
(Part B) 6.02 Consequences of Default same shall become immediately due and payable, without
demand, protest or further notice of any kind, all of which are
If an event of Default shall have occurred then at any time hereby expressly waived by the BORROWER, [iii] foreclose on
thereafter, if any such event shall then be continuing, the the Collaterals or take such other necessary steps conformably
Majority Lenders, upon written notice to the Borrower, may [i] with the Collaterals, or [iv] immediately, without notice to the
declare all Commitments to be terminated whereupon the BORROWER, apply and compensate or set-off toward the partial
obligation of the LENDERS to make or maintain the Advances or full liquidation of such amount or amounts, any funds,
securities, or other property of the BORROWER held by the
The four remedies are alternative, with the right of choice given LENDERS in deposit or under any other concept without
to the lenders, in this case the respondents. Under Article 1201 prejudice to the adoption by the Majority Lenders of any other
of the Civil Code, the choice shall produce no effect except from steps or action, which, in the Majority Lender’s sole discretion, is
the time it has been communicated. This is the reason why a needed to protect the LENDERS’ rights and interests, and
written notice is required under Section 6.02 of the Omnibus without prejudice to the application of the provisions of the
Agreement. Collaterals, as provided in Section 3 of Part A. For purposes of
this provision, the BORROWER hereby appoints each LENDER as
In the present case, we find that written notices were sent to the its attorney-in-fact with full power and authority to do any and
petitioner by the respondents. The notices clearly indicate all acts required to give full force and effect to this provision.
respondents’ choice of remedy: to accelerate all payments [Emphasis supplied] payable shall be declared due and
payable under the loan agreement. On January 6, 1999, demandable.17 The letter clearly indicated the choice of remedy
respondents notified petitioner that it was in default, and by the respondents, pursuant to the Omnibus Agreement.
demanded payment of the stated amount within five days from Even though subsequent demand is waived by the petitioner in
receipt of the letter, otherwise all outstanding availments of the Section 6.02 of Part B of the Omnibus Agreement, on February 5,
US$20M term loan together with interests and other sum 1999, the respondents nevertheless actually made their demand
_______________ in writing for the payment of the principal plus interest and
penalty charges due on or before February 28, 1999, with
hereunder shall forthwith terminate, [ii] accelerate payment and express notice that they would take all legal remedies available
declare the Loan, all interest accrued and unpaid thereon and all to protect the interests of their clients.18 Clearly, respondents
other amounts payable hereunder, and default interest
have more than complied with the requirement concerning As pointed out by the respondents, the loan agreement was
notice to the petitioner. entered into on June 30, 1997, or when the Asian economic
It should be noted that the agreement also provides that the crisis had already started. Petitioner, as a long established
choice of remedy is without prejudice to the action on the corporation, should have been well aware of the economic
collaterals. Thus, respondents could properly file an action for environment at that time, yet it still took the risk to expand
foreclosure of the leasehold rights to obtain payment for the operations. Likewise, the closure of the Mimosa Regency Casino
amount demanded. was not an unforeseeable or unavoidable event, in the context of
the contract of lease between petitioner and CDC. Every
Petitioner’s claim, that the respondents could not be held in business venture involves risks. Risks are not unforeseeable;
default because of a fortuitous event, is untenable. Said event, they are inherent in business.
the Asian financial crisis of 1997, is not among the fortuitous
events contemplated under Article 117419 of the Civil Code. To Worthy of note, risk is an exception to the general rule on
exempt the obligor from liability for a breach of an obligation by fortuitous events. Under the law, these exceptions are: (1) when
reason of a fortuitous event, the following requisites must the law expressly so specifies; (2) when it is otherwise declared
concur: (a) the cause of the breach of the obligation must be by the parties; and (3) when the nature of the obligation
independent of the will of the debtor; (b) the event must be requires the assumption of risks.21 We find that in the Omnibus
either unforeseeable or unavoidable; (c) the event must be such Agreement, the parties expressly agreed that any enactment,
as to render it impossible for the debtor to fulfill his obligation official action, act of war, act of nature or other force majeure or
in a normal manner; and (d) the debtor must be other similar circumstances shall in no way affect the obligation
_______________ of the borrowers to make payments.22
19 Art. 1174. Except in cases expressly specified by the law, or In sum, the appellate court did not err in dismissing petitioner’s
when it is otherwise declared by stipulation, or when the nature action for certiorari and in denying the motion for
of the obligation requires the assumption of risk, no person shall reconsideration. It committed no reversible error, much less
be responsible for those events which could not be foreseen, or (Part A) 7.13 Force Majeure
which, though foreseen, were inevitable.
free from any participation in, or aggravation of the injury to the The LENDERS shall not be responsible for any damage resulting
creditor.20 from any enactment, official action, act of war, strike, lockout,
--------------- boycott, blockade, act of nature or other force majeure or other
similar occurrence beyond the control of the LENDERS. Any
such circumstances shall in no way affect the obligations of the
BORROWER to make payments which are or may become due
under this Omnibus Agreement.

Information Technology Foundation of the Philippines vs.


Commission on Elections
any grave abuse of discretion amounting to lack or excess of
jurisdiction, contrary to petitioner’s contentions.
WHEREFORE, the appeal is DENIED for lack of merit. The
Decision dated March 12, 2002 and the Resolution dated July 3,
2002 of the Court of Appeals in CA-G.R. SP No. 61047 are hereby
AFFIRMED.
Costs against petitioner.
SO ORDERED.
     Davide, Jr. (C.J., Chairman), Ynares-Santiago, Carpio and
Azcuna, JJ., concur.
Appeal denied, judgment and resolution affirmed.
Note.—In determining the intention of the parties, the language
that is used is primordial. (Mondragon International Philippines,
Inc. vs. Blanco, 356 SCRA 608 [2001])
——o0o—— [Mondragon Leisure and Resorts Corporation vs.
Court of Appeals, 460 SCRA 279(2005)]

Você também pode gostar