Escolar Documentos
Profissional Documentos
Cultura Documentos
LP-02
SS-01
SS-02
Consulting Services
For The Core Team Consultant 2 (CTC2)
Contract No. 03-20/CTC/PM/LN/ADB/2184/0909
Road Rehabilitation 2 Project, Indonesia
Under ADB Loan No. 2184-INO
RENARDET S.A
in association with
PT. DAYA CREASI PT. LENGGOGENI PT. FORMASI EMPAT POLA PT J AKARTA R ENCANA S ELARAS
ARCHITECT, PLANNERS AND ENGINEERS
Planning, Designing & Engineering Consulting SELARAS KONSULTAN
Mitrayasa
MONTHLY PROGRESS REPORT No. 40 April 2010
TABLE OF CONTENTS
1 SUMMARY ...................................................................................................... 3
1.1 Current Project Status .............................................................................. 3
1.2 Overall Loan Progress ............................................................................. 6
1.3 Financial Summary .................................................................................. 8
1.4 Major Issues ............................................................................................. 8
1.6 Environmental & Socio Economic Aspects ………………………………10
2 INTRODUCTION ...........................................................................................11
2.1 Introduction............................................................................................. 11
2.2 The Project ............................................................................................. 11
3 THE LOAN ....................................................................................................11
3.1 Financial Status ...................................................................................... 11
3.2 ADB Mission ........................................................................................... 13
3.3 Overall Project Progress ........................................................................ 13
4 STATUS OF PROJECT COMPONENTS .....................................................14
4.1 Road and Bridge Works ......................................................................... 14
4.1.1 Phase 1 Subprojects, 15 Packages ................................................ 14
4.1.2 Phase 2 Subprojects, 11 Packages ................................................ 17
4.2 Core Team Consultants ......................................................................... 20
4.2.1 General Activities during the Month ................................................ 21
4.2.2 Office Establishment ....................................................................... 22
4.2.3 Contract Memorandum of Agreement ............................................ 20
4.2.4 Contract Addendum ........................................................................ 20
4.2.5 Physical Progress ........................................................................... 21
4.2.6 Financial Progress .......................................................................... 21
4.2.7 Documentation produced during the Month ................................... 22
4.2.8 Meetings and Site Visits during the Month ..................................... 22
4.3 Design and Supervision Consultants ..................................................... 22
4.3.1 Sumatra........................................................................................... 22
4.3.2 Kalimantan ...................................................................................... 22
4.4 Enforcing Control over Truck Overloading ........................................... 234
4.4.1 Consulting Services ...................................................................... 236
4.4.2 Civil Works .................................................................................... 236
4.4.3 Equipment ....................................................................................... 23
4.5 Road Safety Awareness......................................................................... 26
4.6 Environmental and Social Impact Management .................................... 26
4.7 Training Consultants .............................................................................. 27
4.8 Road Maintenance Management ........................................................... 27
TABLES
Table 1 Loan Category and Disbursement Table
Table 2 The Overall Financial Status
Table 3 CTC Human Resources: Physical Progress
Table 4 CTC Financial Progress
APPENDICES
Appendix A1-A2 Regional Maps
Appendix B Proposed Financing Plan
Appendix C1 Payments for Individual Contracts
Appendix C2 Actual and Projected Monthly Disbursement
Appendix D1-D5 Progress Status
Appendix E Progress Forms for Civil Works
Appendix F Overview of Tenders Submitted
Appendix G Status of Procurement, Road and Bridge Work
Appendix H Status of Procurement, Other Components
Appendix I Documentation Produced
Appendix J CTC Meetings and Site Visit
Appendix K Project Management Organization
Appendix L Evaluation of Environmental Monitoring Reports
1 SUMMARY
1.1 CURRENT PROJECT STATUS
ROAD AND BRIDGE WORKS Next Step Responsible
Phase 1, 15 Packages
Detailed Design: All DEDs have been completed.
NOL from ADB for PQ: All NOLs issued
Tenders Submitted: All 15 tenders have been
submitted.
Tenders Evaluated: 15 tenders.
NOLs from ADB received for 15 packages.
160,000
140,000
120,000
L o a n S u m ( M illio n U S $ )
100,000
80,000
60,000
40,000
20,000
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Quarter (since January 2007)
Planned 702.62 753.09 1,548.08 9,104.74 1,229.95 5,064.93 6,617.81 16,056.66 8,661.38 14,791.86 16,278.35 23,079.47 11,785.51 14,472.20 9,541.54 5,524.66
Cummulative 702.62 1,455.71 3,003.79 12,108.53 13,338.48 18,403.41 25,021.22 41,077.88 49,739.26 64,531.12 80,809.47 103,888.94 115,674.45 130,146.64 139,688.19 145,212.84
Total Planned 2007 = 12,108.53 Total Planned 2008 = 28,969.35 Total Planned 2009 = 62,811.05 Total Planned 2010 = 41,323.91
Disbursed 750.67 697.51 842.84 4,244.50 7,588.93 2,083.20 4,224.14 11,528.24 8,260.29 10,170.27 12,025.89 22,203.58 10,949.34 4,135.79
Cummulative 750.67 1,448.19 2,291.03 6,535.52 14,124.45 16,207.65 20,431.79 31,960.03 40,220.32 50,390.60 62,416.48 84,620.06 95,569.41 99,705.20
Total Disbursed 2007 = 6,535.52 Total Disbursed 2008 = 25,424.51 Total Disbursed 2009 = 52,660.03 Total Disbursed 2010 = 15,085.14
II.c.1 Civil Works, Phase I, Prequalification/bidding and award ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### 15 10.01 100 10.010
II.c.2 Civil Works, Phase I, Implementation 144,865,740.40 ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### 85 56.73 92.23 52.320
II.d.1 Civil Works, Phase II, Bidding and award ##### ##### ##### ##### ##### ##### ##### 10 2.58 100.00 2.584
II.d.2 Civil Works, Phase II, Implementation 56,084,151.05 ##### ##### ##### ##### ##### ##### ##### ##### ##### ##### 90 23.25 84.45 19.636
Total 217,072,626.87
Target (%) 1.5 2.9 4.3 9.7 15.0 20.6 26.4 34.5 42.5 49.9 57.0 64.2 71.1 77.9 85.6 92.2 98.7 100 100.00 89.011
Progress (%) 0.5 1.7 2.9 6.8 9.4 15.2 18.3 24.7 30.4 36.3 43.1 54.4 65.7 78.0 86.0 89.0
April 2010
Page 7 of 25
MONTHLY PROGRESS REPORT No. 40 April 2010
The cost overrun was resolved by rearranging the financing plan. The Government
agreed to finance the shortfall, whilst the ADB loan of $151 million remained unchanged.
The financing of seven contract packages out of 26, i.e. two in Sumatra and five in
Kalimantan is totally financed by the Government budget.
As of to date the allocation of loan proceeds for Sumatra have been in shortfall, whilst the
allocation for Kalimantan in surplus. Reallocation is needed to accommodate the actual
costs of subprojects in Sumatra which are higher than subprojects in Kalimantan. The
loan reallocation involves the move of the Cat.01 B – Civil Works for Kalimantan, to
Cat.01 A – Civil Works for Sumatra. DGH also indicated using the unused IDC and DGLT
funds for the financing of the civil works.
2 Equipment 2,030.00 100.00% 0.00% 2,030.00 100.00% 0.00% 0.00 100.00% 0.00%
3 Consulting Services 11,020.00 100.00% 0.00% 11,512.00 100.00% 0.00% 12,077.00 100.00% 0.00%
3A DGH TA CTC, DSC-1 Sumatra, DSC-2 Kalimantan, dan 9,670.00 10,162.00 10,976.00
Capacity Builidng and Training
3B DGLT TA Enforcing Controls Over Truck Overloading and 750.00 750.00 201.00
Road Safety Awareness Campaign
3C BAPPENAS Road Maintanance and Management 600.00 600.00 900.00
4 Interest and Commitment Charge 17,465.00 100.00% 0.00% 17,465.00 100.00% 0.00% 8,000.00 100.00% 0.00%
5 Unallocated 1,500.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
0.00
Notes:
- The numbers of "Proposed Reallocation" are rounded.
- Construction and price escalation cost for 19 civil works subprojects will be funded by the loan (except SB-03A and RI-02 which are not subjected for price escalation).
- Construction and price escalation cost for 7 civil works subprojects will be funded by the GOI budget (APBN and APBD).
- Weighbridge Stations (Equipment & Civil works) and some of IDC are reallocated to Civil Works and DGH TAs.
- TA for truck over loading of DGLT is reallocated to Bappenas TA and DGH TAs.
- Required APBN (GOI) Fund for price escalation :
GOI Portion IDR 93,410,589,408.53
Murni IDR 0.00
Total IDR 93,410,589,408.53
- The estimation of price adjustment between 1.3% - 28,1%
- 1 USD/IDR = 9,400
On 16 April 2010, ADB approved the proposed reallocation of loan proceeds which
include a major changes in the project scope to cancel the construction of weighbridge
stations in Sumatra and kalimantan.
The contractor proposed to continue the works until 15 April, 31 March, and 28 February
2010 respectively for SU-02, SU-03, and SU-04 to reach 100% completion of the works.
As the quality of the works is good the ADB supports the extension of the said dates.
The last ADB Mission fielded in May 2009 found that part of land owned by some families
seemed to have been acquired for the road shoulders and drainages. The Mission
requested DGH to verify the process of land acquisition, if any, including re-survey of the
land requirements, and prepare a due diligence report to ensure that the land is being
used properly in accordance with the ADB resettlement policy.
The ADB Mid Term Review Mission Team fielded in December 2009 verified the
submitted due diligence report and concluded that further information and justification
are needed as most of land owners along the project road both in West Kotawaringin
Disrict and Lamandau District may not be affected heavily but they have not yet been
surveyed. The new CTC (CTC2) is requested to extend the survey to the buildings and
land ownership in Lamandau District and Kota Waringin Barat under subproject BV-02-I
in Central Kalimantan to ensure that the land acquisition along the subproject (if any) has
been conducted properly. The Mission supports DGH to hire additional surveyors under
CTC2 contract for this purpose.
Additional survey to the buildings and land ownership in Lamandau District and Kota
Waringin Barat under subproject BV-02-I in Central Kalimantan has been conducted by
the new CTC. Draft of Revised Due Diligence Report has been submitted to ADB on 25
March 2010. The report is still being reviewed by ADB.
Evaluation of the result of environmental monitoring carried out by Site Engineer has
been executed for the month of April 2010 (shown in Appendix L).
2 INTRODUCTION
2.1 INTRODUCTION
This is the seventh Monthly Progress Report prepared by the Core Team Consultant 2
(CTC2), or in sequence to the 40th Monthly Progress Report of the previous CTC
covering the activities during the month of April 2010.
3 THE LOAN
3.1 FINANCIAL STATUS
The ADB Loan 2184-INO provides funding for various components of the Project. The
ADB allocation percentage varies between components, with 69% for civil works for
roads and bridges, 91% for civil works for weigh bridges (Enforcing Control over Truck
Overloading), 100% for equipment for weigh bridges and 100% for consulting services.
The total of estimated cost increase figures for individual projects, as a result of the
Review Design process, indicates that the loan shortfall would probably be increased
significantly.
This larger than expected increase is the result of the substantial fuel and asphalt price
increase which more than doubled in October 2005, and the high level of deterioration of
the project roads since the original estimates were produced, and the redesign to the
new National Road Width Standards which was issued by the MPW on March 2007.
To help alleviate the necessity for an increase in the loan amount, GOI funding is being
provided from the multiyear contract for the central south corridor in Kalimantan during
FY 2008 and 2009. This will include RR2P subprojects BU-02, BV-03, BV-04, BX-03 and
BX-04.
On 13 November 2008, ADB approved a major change in project implementation
arrangements to shift the financing of seven contract packages originally under the loan
to full financing by the Government of Indonesia. The changes include reallocation of
loan proceeds from the unallocated loan category of US$ 1.5 million to civil works and
consulting services categories. Out of the 26 civil works subprojects, only 19 subprojects
will be financed by the loan, for which whole of the 19 contracts have been awarded.
On 16 April 2010, ADB also approved a major change in the project scope to cancel the
construction of weighbridge stations in Sumatra and Kalimantan, and to field a consultant
team under Bappenas to evaluate the operation of selected weighbridges – as part of the
contract with the existing New Approach on Integrated Transportation Management
System. ADB has also endorsed the proposed additional of 16 km of road to be
rehabilitated as part of the contract package JM-01-I in Jambi.
The overall financial status according to the original loan allocation is shown in the
following Table2 and the detailed payments for individual contracts are shown in
Appendix C.
P h a se 2 5 3 ,1 3 8 ,0 0 0 .0 0 2 4 ,1 2 3 ,4 3 4 .9 1 7 ,8 7 3 ,9 2 3 .3 6 ,2 4 9 ,5 1 1 .5 2 0 .0 9 ,3 9 4 ,7 0 2 .2 5 2 .6 8 ,4 7 9 ,2 2 1 .1 4 7 .4 6 ,2 4 9 ,5 1 1 .5
1b C o n su ltin g S e rvice s
C o re T e a m C o n su lta n t 3 ,2 0 0 ,0 0 0 .0 0 9 8 3 ,1 7 3 .3 9 8 3 ,1 7 3 .3 0 .0 0 0 .0 9 8 3 ,1 7 3 .3 1 0 0 .0 0 .0 0 .0 0 .0
2 R o a d S e c to r P o lic ie s / C o m m u n ity A s s is ta n c e
C ivil W o rks 5 1 0 ,0 0 0 .0 0 0 .0 0 .0 0 .0 0 0 .0 0 .0 0 .0 0 .0
E q u ip m e n t 2 ,0 3 0 ,0 0 0 .0 0 0 .0 0 .0 0 .0 0 0 .0 0 .0 0 .0 0 .0
2b R o a d S a fe ty A w a re n e ss C a m p a ig n C o n su lta n t 2 0 4 ,0 0 0 .0 0 2 0 0 ,6 4 5 .1 2 0 4 ,7 3 3 .2 -4 ,0 8 8 .1 6 0 .0 1 2 0 ,6 9 9 .6 5 9 .0 8 4 ,0 3 3 .7 4 1 .0 -4 ,0 8 8 .2
2c D e ve lo p in g N e w A p p ro a ch e s to R o a d M a in te n a n ce 6 0 0 ,0 0 0 .0 0 9 0 0 ,0 0 0 .0 4 6 6 ,9 5 0 .9 4 3 3 ,0 4 9 .1 4 4 4 9 .0 0 .0 4 6 6 ,9 5 0 .9 1 0 0 .0 4 3 2 ,6 0 0 .1
3 C a p a c ity B u ild in g a n d T ra in in g
3a T ra in in g in E n viro n m e n ta l & S o cia l M a n a g e m e n t C o n su lta n t 3 0 0 ,0 0 0 .0 0 2 9 3 ,4 4 3 .6 2 9 4 ,0 3 0 .9 -5 8 7 .3 2 0 .0 2 9 2 ,0 6 4 .8 9 9 .3 1 ,9 6 6 .1 0 .7 -5 87 .3
3b S tre n g th e n in g P ro je ct M a n a g e m e n t P ra ctice s 2 7 7 ,0 0 0 .0 0 2 7 5 ,2 1 2 .4 2 5 3 ,4 6 1 .6 2 1 ,7 5 0 .8 3 0 .0 1 4 8 ,7 6 5 .7 5 8 .7 1 0 4 ,6 9 5 .9 4 1 .3 2 1 ,7 5 0 .8
4 In te re s t a n d C o m m itm e n t C h a rg e 1 7 ,4 4 3 ,0 0 0 .0 0 8 ,0 0 0 ,0 0 0 .0 0 .0 8 ,0 0 0 ,0 0 0 .0 0 0 .0 3 ,3 0 6 ,4 5 8 .2 1 9 .0 -3 ,3 0 6 ,4 5 8 .2 1 9 .0 8 ,0 0 0 ,0 0 0 .0
5 U n a llo c a te d 1 ,5 0 0 ,0 0 0 .0 0 0 .0 0 .0 0 .0 0 0 .0 0 .0
T OT A L 1 5 1 ,0 0 0 ,0 0 0 .0 1 5 1 ,0 0 0 ,0 0 0 .0 1 2 3 ,4 3 2 ,1 3 6 .7 2 7 ,5 6 7 ,8 6 3 .3 4 4 9 .0 9 9 ,7 0 5 ,1 9 8 .2 6 6 .0 3 2 3 ,7 2 6 ,9 3 8 .6 1 9 .2 2 2 7 ,5 6 7 ,4 1 4 .2
Page 12 of 25
April 2010
MONTHLY PROGRESS REPORT No. 40 April 2010
Project progress status was reported as 91.08% on 25 April 2010. This is behind the
revised scheduled progress of 100%.
Revised Intended Completion Date is 22 April 2010 and the Contractor could not
complete the overall works because of his suspended payment due to the land problems.
ADB supported 60 days extension after the approval of Revised Due Diligent Report
prepared by the CTC.
JAMBI PROVINCE
JM-01-II, Muara Tembesi – Bts. Sarko – Sarolangun
Bid evaluation report was approved by ADB on 29 October 2008. The contract with PT
Adhi Karya – PT Sumber Sedayu JO was signed on 7 November 2008 and the
commencement date was 20 November 2008.
The technical justification for revised design has been discussed and decided in DGH
office Jakarta on 23 March 2009. The proposal has been submitted to ADB on 22 April
2009 and approved by ADB on 15 May 2009.
Project progress status was reported as 90.36% on 25 April 2010. This is slightly behind
of the revised scheduled progress of 90.90%.
The ADB supports the inclusion of 16 km of road link to be rehabilitated which was not
included in the contract, subject to: (i) availability of the loan fund; and (ii) improvement of
the performance of the contractor. The proposal (which is based on technical justification)
is being prepared.
The second technical justification will include : (i) Realignment at Sta 75+375 to 75+575,
(ii) Additional retaining wall installation, (iii) Additional new and replacement of box
culverts and (iv) Pavement thickness calculation on additional 16 km section which
should be based on the Benkelman Beam test and traffic survey results.
LAMPUNG PROVINCE
LP-02-II, Terbanggi Besar – Kotabumi
Bid evaluation report was approved by ADB on 28 October 2008. The contract with PT
Tri Citra Perdana was signed on 6 November 2008 and the commencement date was 1
December 2008.
The technical justification for revised design has been completed and discussed in DGH
office Jakarta on 1 May 2009. The document should be improved prior to submission to
ADB.
The revised design proposal has been submitted to ADB and being reviewed.
Table 4 - CTC1, Bridging Consultant and CTC2 Financial Progress as of 30 April 2010.
Total
Amount excluding Tax, 1 USD = IDR 9,200 USD IDR
Equiv. USD
CTC-1
Contract Value (Closing Addendum) 371,632.68 5,724,186,683.00 983,173.32
Amount to be invoiced up to termination date 371,632.68 5,724,186,683.00 983,173.32
Percent 100.00% 100.00% 100.00%
Paid to date 371,632.68 5,724,186,683.00 983,173.32
Percent 100.00% 100.00% 100.00%
Bridging (Interim) Consultant
Contract Value (Addendum No.3) 4,999,420,000.00 439,281.76
Amount to be invoiced up to Invoice No.16 4,062,032,425.00 337,391.81
Percent 81.25% 76.81%
Actually paid to date (LFIS) (Invoice No.1-16) 4,062,032,425.00 (LFIS) 337,391.81
Percent 81.25% 76.81%
CTC-2
Contract Value (Original Contract) 381,549.00 7,897,050,000.00 1,239,924.00
Estimated to be invoiced up to date 117,694.07 1,920,083,910.00 326,398.84
Percent 30.85% 24.31% 26.32%
Paid to date (excluding Advanced Payment) 28,277.40 500,068,901.00 81,773.00
Percent 7.41% 6.33% 6.60%
4.3.1 Sumatra
The contract agreement between DGH and Katahira Engineers International &
associates was signed on 16 February 2007. The Team Leader was mobilized on 20
March 2007 and the Assistant Team Leader/Pavement Material Engineer was mobilized
on 14 2007. Office in Palembang has been established at Jl. PHDM II No.79, Kalidoni,
Palembang-30118. The Highway Engineers were mobilized on 31 May 2007 and 11
November 2007.
DSC-1 office has been moved from Palembang to Jakarta due to difficulties in travelling
route from Palembang to all subprojects in Sumatra. ADB supported the relocation of the
office and the Addendum No. 2 has been approved by ADB on 3 February 2009.
Signed Addendum No.3 regarding revised staffing schedule has been approved by ADB
on 4 September 2009.
Draft Addendum No.4 is being prepared to reflect additional assignment of DSC-1 staff
following the civil work subprojects implementation.
Aside from day to day supervision of the construction of civil works, general activities of
DSC-1 during the month are summarized as follow:
Site Visit Package LP-01 and LP-02 on April 05 – 07, 2010.
Meeting Package RI-01 regarding design Soft Ground on April 07 – 08, 2010.
Attend coordination meeting RR2P Project on April 09, 2010 in ADB Office.
Site Visit Package SS-03 on April 12 – 14, 2010.
Kick of meeting ADB mission on April 16, 2010 in BAPPENAS.
Site Visit Package SB-03 for ADB Mission on April 19 – 21, 2010.
Meeting in PMU regarding Addendum no. 4 DSC-1 RR2P on April 26, 2010.
Meeting Review Design Package JM-01 on April 27, 2010 in Bina Marga Office
Jakarta.
Meeting flood problem Package JM-01 on April 28, 2010 in Bina Marga Office
Jakarta.
Site Visit Package JM-01, SS-02 and SS-03 for ADB mission on April 29 until May
1, 2010.
4.3.2 Kalimantan
The contract agreement between DGH and China Engineering Consultants, Inc. &
associates was signed on 23 February 2007. The Team Leader was mobilized on 2 April
2007 and the Assistant Team Leader/Pavement Material Engineer was mobilized on 18
April 2007. The Highway Engineers was mobilized on 20 November 2007. Office
premises have been rented in Banjarmasin. at Jl. Brigjen H. Hasan Basri No.47,
Banjarmasin.
The Memorandum of Agreement (MOA) No. 1, No.2 and No.3 have been approved by
ADB on 6 February 2009.
4.4.3 Equipment
ADB agreed to cancel this sub component. But ADB suggested to reactivate the
functioning of the weighbridge in Kintap (South Kalimantan) to ensure that the subproject
BX-01 can meet the design lifetime.