Escolar Documentos
Profissional Documentos
Cultura Documentos
VALUE MANAGEMENT
PMI Pittsburgh Chapter Meeting
February 8, 2001
Marilyn McCauley
McManagement Group
703-455-0602
703-455-0598 (f)
McMgtGrp@aol.com
AGENDA
Twelve Reasons Why Programs Fail
Program Management Principles
Earned Value Management’s Role in PM
What is Earned Value Management
History of Earned Value Management
The Value of Earned Value Management
REASONS WHY PROGRAMS FAIL
John Gioia, Robbins Gioio, Inc., PM Network, November 1986
4. No Measurable Controls
5. Requirements Creep
1. Incomplete requirements
2. Lack of user involvement
3. Lack of resources
4. Unrealistic expectations
5. Lack of executive support
6. Changing requirements and specifications
7. Lack of planning
8. Didn’t need it any longer
9. Lack of IT management
10. Technology illiteracy
PROGRAM MANAGEMENT PROCESSES
Initiating Recognizing that a project or phase should begin
and committing to do so
Initiate
develop a realistic plan of
organize the work and
Plan the teams the work scope, the
budget, and the schedule
Close out
EVMS fits naturally into the
Project Management Cycle
program manager needs
Project management cycle
Initiate
develop a realistic plan of
organize the work and
Plan the teams the work scope, the
budget, and the schedule
EXECUTE - Work and resources are driven down to lowest level for execution
– Budgets are “earned” as work is completed = EARNED VALUE
NE
LI
SE
BA
D
TE
RA
G
TE
IN
3. ALLOCATE BUDGETS
40
100
$
60
15
25
30
TIME
30
ESTABLISH OBJECTIVE
MEASURES
Earned Value techniques
Discrete
• physical, tangible end product
Apportioned
• discrete, dependent on another discrete work package
• example: quality assurance
• planned as historical estimating factor (e.g., 7%)
Level of Effort
• no tangible end product
• basis of measurement: time
• when clock starts ticking, you automatically accumulate earned value
• no schedule variance
• example: management personnel
Should be a quantitative and discrete way to measure the work
May tie in with success criteria or technical measure
• e.g., successful completion of a specific test, reliability growth curve
FIVE BASIC PERFORMANCE DATA
QUESTIONS & ANSWERS
BC WS
of the work I scheduled to have done,
BUDGET BASED
BC WP
how much did I budget for it to cost?
SCHEDULE VARIANCEisisthe
SCHEDULEVARIANCE thedifference
differencebetween
betweenwork
workscheduled
scheduled
and work performed (expressed in terms of budget dollars)
and work performed (expressed in terms of budget dollars)
formula:
formula: SV
SV$$==BCWP
BCWP--BCWS
BCWS
example:
example: SV
SV==BCWP
BCWP--BCWS
BCWS==$1,000
$1,000--$2,000
$2,000
SV= -$1,000
SV= -$1,000 (negative
(negative==behind
behindschedule)
schedule)
Cost Variance
PERFORMANCE BASED
BC WP
of the work I actually performed,
how much did I budget for it to cost?
AC WP
how much did it actually cost?
COST
COSTVARIANCE
VARIANCEisisthe
thedifference
differencebetween
betweenbudgeted
budgetedcost
cost
and
andactual
actualcost
cost
formula:
formula: CV
CV$$==BCWP
BCWP--ACWP
ACWP
example:
example: CV
CV==BCWP
BCWP--ACWP
ACWP==$1,000
$1,000--$2,400
$2,400
CV= -$1,400
CV= -$1,400 (negative
(negative==cost
costoverrun)
overrun)
Variance at
Completion (VAC)
VARIANCE
VARIANCEAT
ATCOMPLETION
COMPLETIONisisthe
thedifference
differencebetween
betweenwhat
whatthe
thetotal
total
job
jobisissupposed
supposedtotocost
costand
andwhat
whatthe
thetotal
totaljob
jobisisnow
nowexpected
expectedtotocost.
cost.
FORMULA:
FORMULA: VAC
VAC==BAC
BAC--EAC
EAC
Example:
Example: VAC
VAC==$5,000
$5,000--$7,500
$7,500
VAC
VAC==--$2,500
$2,500 (negative
(negative==overrun)
overrun)
WHAT WILL BE THE FINAL
COST?
Estimate at Completion (EAC)
defined as actual cost to date + estimated cost of work remaining
supplier develops comprehensive EAC at least annually
• reported by WBS in cost performance report
customer should develop a range of independent EACs for comparison
should examine on monthly basis
consider the following in EAC generation
• performance to date
• impact of approved corrective action plans
• known/anticipated downstream problems
• best estimate of the cost to complete remaining work
EAC = BAC
CPI
=
ACWPcum + Budgeted Cost of Work Remaining
CPI3
=
ACWPcum + Budgeted Cost of Work Remaining
.8(CPI) +.2(SPI)
=
ACWPcum + Budgeted Cost of Work Remaining
CPI * SPI
THE VALUE OF EARNED VALUE
MANAGEMENT
Early and accurate identification of trends and
problems
32 Guidelines 1. Organization
2. Planning and Budgeting
3. Accounting
4. Analysis
5. Revisions and Access to Data
CANADA
JAPAN
SWEDEN
UNITED KINGDOM
REFERENCES
INDUSTRY EVM STANDARD – ANSI/EIA-748-98
www.cpm-pmi.org
www.pmi.org
www.acq.osd.mil/pm
www.deskbook.osd.mil