Escolar Documentos
Profissional Documentos
Cultura Documentos
1
CONTENTS
¾Objective of Presentation
¾QC Plan
2
OBJECTIVE
3
OVERALL WORK FLOW CHART
CLIENT
APPROVED RFI
(Next Phase)
Document Review
PROCUREMENT PROJECT Technical Information CLIENT QA/QC
mitted
DEPARTMENT MANAGER Job Execution Procedure ENGINEER
port,
Project Requirement
INFORMATION
Invoice Submittal
Material Requirement
Material Approval
Material Availability
Material Issuance
Reports
E ACTION MEMO
MATERIALS /
OMPLIANCE/
STORE
SAFETY
Material Distribution DEPARTMENT
NON CO
and Control
CORRECTIVE
Sch
ADMIN PLANNING Daily Reports E&I RESULTS/CONFORMANCE QA/QC
Resources Availability
DEPARTMENT DEPARTMENT MANAGER DEPARTMENT
Return Superceded
Resource Requirement
q Drawings &
Documents Quality Work Assurance
Work Programme
Site Inspection
EQUIPMENT Construction Procedure
PLANNING Material Testing & Review
QA/QC
CONTROLLER
Material Approval
ENGINEER ENGINEER QA/QC Documentation & ENGINEER
Interim Progress Report
System Filling
Progress Monitoring
Equipment Schedule
Invoice
Mobilization and SUPERVISOR RFI
Demobilization of Equipment
Utili ti Record
Utilization R d
Quantity Surveying QUANTITY NON COMPLIANCE
TIME KEEPER/ Actual Progress Quantification
SURVEYOR FOREMAN
PMENT, RESOURCE
GRAMME PRIORITY
MATION ON WORK
Final Remeasurement
HUMAN Quantity & Manpower
RESOURCE Allocation Analysis Direct Work Execution
Site Physical Planning
Daily Reports
Daily Manpower Record Documentation DOCUMENT Work Supervision
Manpower Allocation Record Control
CONTROLLER MAIN ACTIVITY
C - BLACK
C
INFORM
DEVELOP
& PROG
QUALITY
ASSURANCE
• Inspections Compile
activities from documents into
receiving to final Final Dossiers
as per approved and Handover
ITP’ &
ITP’s
SATISFIED
maintenance of CLIENT
records
¾ Establishing
g
inspection test
plans and ¾ Periodic audits
recording
formats
¾ Key performance
analysis
¾ Materials and
Subcontract ¾ Handling discrepancies
approvals and resolving Non
conformances
IN-HOUSE MATERIAL
Material Requirement
Purchase Request
raised by Supervisor/QS
Verification
Requireed
Not Project
Approved Manager
BAD BAD
Condition
GOOD
Use on Site
CLIENT SUPPLIED MATERIAL
Client Function
E&I
Function
Store/ Material
Reconciliation
Controller
ADDITIONAL •No CO
CONFIRMATION
O OF
O
WORK SCOPE OF WORK CHECK FOR LATEST
REVISION DRAWING
• Yes
MOS / ITP
DOCUMENT
INTER CONTROLLER
DEPARTMENT
COORDINATION
1. GROUNDING SYSTEM
3. LIGHTING SYSTEM
4. POWER SYSTEM
5 COMMUNICATION SYSTEM
5.
3. NFPA – NATIONAL
3 O FIRE PROTECTION
O C O ASSOCIATION
SSOC O
5. UL – UNDERWRITERS LABOURATORY
GROUNDING SYSTEM
GROUNDING SYSTEM [PURPOSE – PROTECTION]
BURRIED CABLES
TYPES
¾ Copper
¾ PVC Insulated Copper
Copper Cable
NON BURRIED CABLES
TYPES
¾ Full Green [Common Ground)
¾ Yellow Green [ Panel ground]
Precautions:
¾ Detailed study of drawing
¾ Co-ordination
PVC Insulated Copper cable
12
Yellow Green Cable
Excavation
Excavation depth 13
TYPES OF GROUND
Electro-Static Ground
¾STATIC EQUIPTMENTS
¾ROTARY EQUIPMTENT
Static Rotary
HUMAN SAFETY GROUND
The enclosure of the equipment and N.G.R shall be connected with the
main grid of the grounding system. The low voltage electrical equipments
and panels shall be connected to the grounding system by looping from
main grid grounding system. All layers of cable tray and supports shall be
bonded every 30 meters.
SYSTEM EARTHING
The medium
Th di voltage
lt electrical
l t i l equipments
i t shall
h ll be
b connected
t d with
ith low
l
resistance grounding system for the protection. The low resistance grounding
system shall be formed by connecting the neutral point of the equipment with
Neutral g
ground resistor and the N.G.R shall be connected with individual
ground wells.
All the instruments shall be connected with intrinsically safety grounding to avoid the direct
secondary current flow to the instruments. This can protect the instruments from component
degradation and physical damage.
18
CAD WELDING
Procedure
19
CAD WELDING AT A GLANCE
Rod Length: 3m
Resistance value:
21
LIGHTNING ARRESTOR SYSTEM
CLASSIFICATION
1.External Lightning
¾ Lightning Protection System (LPS)
¾ For Protecting Structures from direct lightning strikes
LPZ OA
LPZ OB
e.g Computer
Cables, Lines
Related Pipe Room
Works Bonding of shield 2
Example for dividing a structure into several LPZ s 22
and adequate bonding
CATHODIC PROTECTION SYSTEM
23
CATHODIC PROTECTION
Purpose
Types of Bedding
¾ Vertical
¾ Horizontal
Classification
24
CATHODIC PROTECTION SYSYTEM
25
WORK METHODOLOGY
¾ Cad Welding
¾ Cable Laying
In Tanks
Under Ground Pipe Line
¾ Installation of Anodes
¾ Installation
I t ll ti off Tr.
T Rectifiers
R tifi
Materials Used
27
LIGHTING SYSTEM
TYPES OF FIXTURES
1. Industrial Type
2 Commercial Type
2.
¾ Recessed Type
¾ Surface Type
Indoor Fluorescent
Outdoor Flood Light
High Bay Light
Street Light
Emergency Exit Light
28
MOUNDING SCHEME
Conduiting
¾ Exposed Conduiting
¾ Concealed
C C
Conduiting
¾ Trunking system
E.M.T
¾ Common Materials Used
¾ End
E dB Bush
h
¾ Condulets (Fitiings)
¾ Clamps
¾ Supporting
pp g Channels
¾ Fixing Hardware
PVC Conduit 29
General Tips for Conduiting
T t Equipments
Test E i t I
Insulation
l i T Tester
31
Typical Wall Top Mounting Type Fixture
Conduits
32
Indoor Surface Mounting Type Fixture
Flexible Conduits
Hanging Support
33
Flood Lights
34
Recess Mounting
Street Light
g
35
Explosion Proof Light Fixture Exit Light
37
POWER SYSTEM
TRANSFORMER INSTALLATION
1.
1 Execution
E ti plan
l and
d rigging
i i plan
l
2. Lifting arrangements
3. Transportation
4. Installation
sta at o
Rigging Plan
38
T
Transportation
t ti Transportation
Sign Boards
Erection
39
TRANSFORMER ASSEMBLY
Conservator
Cooling Fans
Radiator
40
MV Termination
41
DIESEL GENERATOR SET
42
¾ Oil Filteration & Filling
¾ BDV of oil.
No load test for 2 – 3 Hours dry run for Performance check of motor
Measuring Parameters
¾Temperature
¾Vibration
¾Speed
¾Voltage ½ Hour Duration Value Check
¾Starting Current for each parameters
¾Running Current
¾Rotation
¾Noise
MV Cable Test
¾Megger
Insulation Test
44
HV, MV & LV SWITCHGEARS
PLANNING • Materials Issue Notes EXECUTION TEAM
DEPARTMENT ENGINEER / SUPERVISOR
erials, Supports
DOCUMENT
PREPERATION OF
CONTROLLER
RIGGING PLAN
PERMIT SYSTEM
Draw
Mate
VISUAL
INSPECTION
Final Verification of Supports, materials
p
etc. for Material SpecEtc.
•Precommisiioning, Commissioning
• Yes
QA/QC DAMAGES
•No
CABLING
C G/
Material Verification &
FIELD WORK TERMINATION
Confirmation
EXECUTION
• Daily Progress Report 45
PANELS
49
RISK ASSESSMENT
EQUIPMENT INSTALLATION(TRANSFORMERS & PANELS)
50
CABLE PULLING FLOW
PLANNING • Materials Issue Notes EXECUTION TEAM
DEPARTMENT ENGINEER / SUPERVISOR
• Drawings & Specification • Drawings & Specification
• Release notes for Erection
CABLE DRUM
IDENTIFICATION &
RECEIVING
wings & Specificatiion
PREPERATION OF
METHOD STATEMENT
erials, Supports
PREPERATION OF
CABLE ROUTE
DOCUMENT
Draw
Mate
TRANSPORTATION/
ARRANGEMENT OF APPROVAL FROM
MATERIAL CONTROL
TOOLS CLIENT
•No
(cables will not be
QA/QC CONTINUITY pulled by machines)
CHECK
PREPARATION OF
CABLE ROUTE
52
Duct Bank Manhole
Corner Roller
The installed cables shall be dressed tidily with cable tie for each 6 meters in
horizontal run and each 2 meters in vertical run. The power cables shall be
grouped according to the voltage rating, insulation level, and dressed with
cable
bl titie and
d the
th control
t l cables
bl shall
h ll b
be grouped d accordingly.
di l
Dressed Cables
55
CABLE TERMINATION
¾ The color coding and wire numbers are identified with suitable ferrules and
bunched if required. Then the connections are given to the terminals as
per wiring diagrams with suitable Lugs.
¾ Ensured that all the terminal Junctions are properly connected without any
loose contacts.
¾ The shielded cables are properly wired and the shield is seperated and
provided suitable sleeve and connected to the Busbars.
56
CABLE TAGGING
All the cables shall be identified with PVC band tags at both ends
58
Lugs & Glands S.S Cable Glands Cable Glands Cable Glands
59
RISK ASSESSMENT
CABLE INSTALLATION
¾Dust Generation
¾Fall of Objects and materials and personal
¾Cavitational soil subsidence due to inadequate sloping.
¾Body injury.
¾Fall hazard of cable drum.
60
¾Cable
C bl Drum
D and
d Cable
C bl Stand
St d Lifting,
Lifti Cable
C bl Pulling
P lli By
B Hand
H d
Fatigue
Dust Generation
Heavy equipment hazards.
Body Hurt.
Hurt
61
COMMUNICATION SYSTEM
¾Public Address
¾Paging
¾Telephone
¾Data System
¾Addressable
¾Conventional System
Photoelectric
Ionization
Heat Detector
Gas Detector
Remote Detector
62
Smoke Detector Fire Extinguisher
Series ΔV
ΔV
Parallel r r r r r
Σ
I I
=
R r
64
¾ Typically Consists of:
z 500′′
Piping Runs Less Than 500
z Multiple Pipe Diameters
z Numerous Inline Equipment
• Valves
• Pumpsp
• Strainers
65
MI Cables Polymer Zone Heating Self Regulating Power-Limiting Skin Effect
Insulated Cables Cables Current Tracing
Cables
Cables
Max. Maintain Temp: 150°F Max. Maintain Temp: 250°F Max. Maintain Temp: 300°F
Max. Exposure Temp: 185°F Max. Exposure Temp: 375°F Max. Exposure Temp: 450°F
T-Rating: T6 T-Rating: T3 T-Rating: T3
66
TOOLS & TACKLES A GLANCE
67
Hydraulic Crimping Tool Contact Resistance Tester
69
I
Insulation
l ti Tape
T Manual Crimping Tool Cutter
70
Hole Saw Kit Tongue Tester
72
SAFETY KEY FUNCTIONS
Electrical cord in
Contact with the
cylinder
Cylinder laying
in a horizontal
position.
75
HOUSE KEEPING
¾ You, (Yes
(Yes YOU!
YOU!) are responsible for keeping your work area clean & tidy
at all times.
¾ D ’t block
Don’t bl k access ways, doorways
d etc.
t
76
THANK YOU
77