Highlight
India's largest single stream COUNOU of Essar Refinery at Vadinar
successfully commissioned on November 27, 2006.

BUSINESS TREND

BUSINESS SECURED BY -ElL DURING 2006-2007 -- .. --


I November Cumulative upto I

Business Secured 2006 November 2006


Domestic Rs. Crores 87 864
..•
Overseas Rs. Crores 33 58
(US $ Million) (7.5) (13)
Total Rs. Crores 120 922

MAJOR JOBS SECURED DURING THE MONTH

Domestic
SI. No. Project Title & Scope of Services Client I Location
I
1. Consultancy services for PX-PTA Project IOCL, Panipat
!
at Panipat Refinery (additional work) I

2. Consultancy services for preparatory GGSRL, Bhatinda


activities of Punjab Refinery Project
(additional work)
3. Consultancy services for replacement of BPCL, Kochi
fired heater with a Reboiler in BPCL-
Kochi Refinery's Naphtha Stabiliser unit of
CDU-1
-j
4. HAZOP,and related studies for New Depot L&T, Chennai
I
Project of KAFCO, Kuwait
---J
5 Consultancy services for Pretreater & BRPL, Bongaigaon i

I Reformer Revamp Project for Xylene Plant


of BRPL, Bongaigaon I
\ .-

1
l

[ Project Title & Scope of Services .. lCiient I Location


I Consultancy services for Upcoming
1-----1
INational Mineral
I Projects of NMDC, Hyderabad I Development I

Corporation Limited, !
,
I,Hyderabad I
I Review of NIO scope of work for SPM i HPCL, Mumbai-'
facility at Visakh Refinery
~_ .. _ .. ~-
PMC services for Strategic Crude Oil IISPRL, Delhi
facilities at Visakhapatnam
9. PMC services for B-22 Field Development
I Project
'-,
,10. ' Design
and detail engineering for
L. .modification
I jobs in FCCU

Overseas
ISI. No. Project Title & Scope of Services Client/Location
r1. Technical assistance to SABIC, Saudi Saudi Basic Ind
Arabia Corp., Saudi Ara bia

2. Engineering Consultancy Services for Crest Strategies


Preparation of Front End Loading (FEL) Limited (CSL), British
Document for Ammonia Urea Complex at Virgin Islands (BVI)
I
Papua New Guinea (PNG) _J
ACTIVE PROSPECTS

PROPOSALS SUBMITTED

Domestic
I
S. No. Project Title & Scope of Services Client I Location
1. Detailed feasibility report for LNG Adani Group, I
Terminal at Mundra Ahmedabad ,

2. PMC Services for Strategic Crude Oil Indian Strategic


Storage Facilities at Visakhapatnam Petroleum i
New Delhi I

3 Vetting of Cost Analysis for Infrastructure Oil India Limited,


I
Development for Supply of Gas to Assam NaiDA I,
I
Gas Cracker Project. i
I
4. Process Engineering Package and other BRPL, Bongaigaon
I
Services for LPG Treating Unit at BRPL,
Bongaiga~ I

2
!

--------,."._--------_._----~
5. 'I' Techno Economic Feasibility Study for I BRPL, Bongaigaon:l
HS Crude Processing at BRPL, !

I Bongaigaon I
6. -'1 DFR for'T~a-p-.~O~ff~T~e-r-m~i-na-I-F-a-c-il-ity-a-t
-·-~N-R-L,-Numalrgarhl
L..._~' _G._u_w_a_ha_ti
__ . . ., . _

Overseas
irS!: I Project Title & Scope of Services ~ient I Location ..
. No.
IT' : Technical Assistance Services for Bintan ~m-in-iu-m-I-ndustry-
Alumina PrOJect,Indonesia Professionals Inc.
, .1
Canada
~-2-.- Feasibility Report & Mining Plan for SRK Consulting,
h
Ii

Jayamkondam Lignite Mine in India Australia


. 3. I Engineering Consultancy Services for KNPC, Kuwait
i preparation of FEED for Clean Fuel
I

I Project in Kuwait
r---;----+-O;C-~~---o--~=c=--~___+=c----='~~~
' 4 Consultancy Services for FEED Review The National Co. for
I
of Revamp of Meena AI-Ahmedi Burnery Mech & Elect.
f- for smokeless Operation of MAA Refinery Works Ltd, Kuwai!.J
I PMC services Phase-I for the ENIP, Algeria I

' 5. Rehabilitation of the Petrochemical [' ,


I Complex at SKIKDA & ARZEW i

PROJECT HIGHLIGHTS

------- Annexure I u _

FINANCIAL HIGHLIGHTS

Cumulative position of Turnover and Profit After Tax from April 2006 till
November 2006 was Rs. 360.31 crores and Rs. 82.86 crores respectively.

EMPLOYEE RELATIONS & MANPOWER

Overall Industrial Relations situation remained cordial during November


2006.

The regular manpower strength as on 30.11.2006 was 2587.

3
l

ANNEXURE - I

REFINERY DIVISIONS

PANIPAT REFINERY ADDITIONAL EXPANSION PROJECT (lOCll


Cum. Physical Pro~ress- Sch.:35.6%, Act.:25.7%.

130 Nos Structural drawings and 54 Nos Piping AFC Drawings released
for Construction. RFQ for all 18 MRs of I MTO Piping Materials issued,
order placed for 16 MRs out of 18 MR's. Order placed for Controlled
volume pumps, Ejectors, HV Switchgear, Displacer level instruments
Magnetic level gauges, On-off valves and Gate/Globe/Check valves
during the month. HP Heat Exchangers- Price opened, Cooling Towers-
final recommendation sent on 18.11.2006 Single vertical tender-
Recommendation for initial short listing sent for approval of IOCl on
07.11.2006.

BINA REFINERY PROJECT, (BORl), Cum. Physical Pro~ress-


Sch.:5.6%, Act.:5.8%

Process package for DCU received. MRs for Electric heater (ISOM),
Vaporiser & Reactors (MS Block) released TBA for CCR Reactors
released. Enquiry issued Civil/Strl. Works of MS Block, Electric Heater
for ISOM unit, Structured packing & associated internals. Order placed
for Reactors/separator (HCU), Cast and Glass preheater, Column &
Vessels (CDUNDU). Bids for Crude & Intermediate tank works at Bina
and Crude oil storage tanks at Vadinar are under evaluation Contract for
CDUNDU-Heater Works and Civil & Strl. Works, HCU/DHDT Civil/Stri
work and Consultancy services for Raw water intake awarded.
Construction of Boundary Wall, Site Grading, Site Office, Ware House,
Watch Tower, Control Room, SRR & S/S and Construction Water storage
& Distribution reservoir are in progress.

Pipe Line: Recommendation for placement of order for Line Pipe sent on
17.11.2006. Bids for line Pumps are due on 30.11.2006.

GREEN FUEL & EMMISSION CONTROL PROJECT AT MUMBAI


(HPCl)
Cum. Physical Proqress-Sch.:96.9%, Act.:81.0%

Order placed for 261 Nos MRs out of total 287 Nos. Balance ordering
pertains to Top-up piping MTO. All major equipment received except 1
vessel, 1 heat exchanger and 4 pumps for MS Block. Construction works
in progress for MS Block, Offsites, Control room, Sub-Station and Cooling
Tower. Substation -8 completed. OM plant and Nitrogen plant

4
I
.'

mechanically completed Hydrotested: SWS/SRU 52 out of 140 loops,


LPG Treating:71 out of 105 loops, Prime G+ 32 out of 205 loops. Act.
Constn. Progress for the month: 4.5% (Cum. Sch..92.6%, Cum.
Act.·61.7%) Progress of Construction is affected due to inadequate
mobilisation by contractors.

CLEAN FUEL PROJECT, VIZAG REFINERY, VIZAG (HPCL)


Cum. Physical Pro~ress- Sch.:97.7%, Act.:72.8%.

All drawings for all units including IBR package for NHT/CCR issued for
construction. Order placed for 12 MRs during the month Out of total 264
MRs, order placed for 242 Nos MRs Out of total 694 Nos Equipment. all
ordered and 564 Nos received at site Recommendation for award Issued
for FGD Package on 22.02.2006. Award is pending with HPCL for quite a
long period Recommendation for award of Instrumentation tender for MS
Block issued on 14.10.2006 and Offsite, Mech I Piping part - B issued on
25.09.2006. Delay in award of these contracts is affecting progress of
work. Contract for Electrical work of units and Tankages work part - II
awarded on 25.10.2006 and 14.11.2006 respectively Act Constn.
Progress for the month: 3.1% (Cum.Sch.95.4%, Cum. Act.452%)
Progress of Construction is affected due to inadequate mobilization of
resources by contractors and delay in award of contract for offsite Mech
IPiping (Part - B).

ESSAR OIL REFINERY PROJECT, VADINAR (EOL)


Cum. EI Services Proqress (for balance work after restart) -
Sch.:99.5%, Act.:70.9% (

CDUNDU/SGU Mechanically completed on 22.11.2006. Unit


commissioned on 27.11.2006. 1079 Nos Piping Isometrics out of
estimated total 1300 Nos released for construction in DHDS Unit HAZOP
completed for DHDS unit Construction is in progress for VBUlTreaters,
Sulphur Block, CCRlNHT and FCC/USGU, Rail &Truck Loading Gantries.
Progress of work affected due to non availability of piping materials and
Instrumentation Piping Loops: 596 Nos in VBUlTreaters out of total 682
Nos, 442 Nos in CCR/NHT out of total 526 Nos hydrotested. System

Mechanical Completion. FORMAT III: - CCR/NHT - 24 Nos raised for


Mechanical System out of total 41 Nos. VBU/ Treaters - 36 Nos raised for
Mechanical System out of total 54 Nos. Flare - Main flare & H2S Flare
completed. LPG Flare 8 Nos. raised for Mechanical system out of total 9
Nos. Fire Water System - All system completed. Format IV - Fire
Water System: All system completed.

5
!

CEIVIPPHASE - II PROJECT, KOCHI REFINERY, KOCHI (KRLI.


Schedule is under finalisation.

Selection of Licensor for VGO/HDS Unit and NHT/CCR completed.Kickoff


meeting held with licensor. Process data sheet s for CDUNDU being
issued. Design Basis for LPG Mounded bullets finalized and issued on
03.11.2006. NIT for GT/ HRSG package issued on 1511.2006. Purchase
& Tendering procedures approved. Enquiry for Boundary wall &
Construction power issued.

DHDT PROJECT, BONGAIGAON REFINERY, BONGAIGAON (BRPL)


C:UITl, Physical Proqress- Sch.:4.9%, Act.:4,5%.

Revised P&IDs released on 28.11.2006. MR released for Rotary


Compressor, Centrifugal Horizontal water pumps, Centrifugal pumps
SPP, HV Switch board, Vessels(>25mm), Neutral Ground resister. Piling
layout drawings for 1053 Nos of piles released Tender specs for
Civil/Str!. work for Sulphur Block/HGU and DHDT heater released. TBA
for GT based CPP released on 1411.2006. Tender for Civil & Str!. Works
of DHDT Unit including Control Room and Substation issued on
23.10.2006 with bid due on 27.11.2006. Recommendation sent for
ordering of Pipes-CS (Global), Fittings (Global) and award of the work of
DM plant Order placed for Cryogenic Nitrogen Plant, Makeup Gas
Compressor, Centrifugal Compressor (PII/A), Fittings (lndg) and Flanges.
Piling work commenced.

REFINERY EXPANSION and UP GRADATION PROJECT,


MANGALORE REFINERY, MANGALORE (MRPLl, Schedule is under
finalisation

Selection of Process Licensors in progress. Work on Process Package


for CDUNDU and Utilities & Offsites is in progre. Revised overall Plot
Plan issued for MRPL approval on 16.11.2006. Soil Investigation Work
awarded on 17.11.2006. Work on CPP feed package preparation
commenced. Land acquisition for Refinery facilities is in progress.

PUNJAB REFINERY PROJECT, GURU GOSIND SINGH REFINERIES


LTO, SATHINDA (GGSRL), Schedule is under finalisation.

Selection of Licensors for Process Unit is in progress. Process Design for


CDUNDU is in progress and Design Basis for SPM, Crude Pipeline &
COT under finalization. Finalisation of Plot Plan - Refinery is in progress.
Recommendation issued for award of work for restart of 4 Nos. tankages

6
(

work at site. Contract for construction of buildings awarded on


17.11.2006.

NEW VISAKH REFINERY PROJECT, VISAKH REFINERY, VISAKH


(HPC[J

~_chedule is under finalisation.

Finalisation of technical specs. for selection of Licensors is In progress


Process Design for CDUNDU is in progress. Plot Plan under finalisatlon.

P_ET_R_OC_H_E_M_IC_A_LS_D_IV_IS__IO_N

AROMATIC COMPLEX PROJECT AT KUWAIT (TECHNIMONT)


Cum. Engineering Progress- Sch.:39.5%, Act.:41.5%.

All Process data sheets issued to TCM. 474 Nos Architectural/Structural


drawings out of total 872 Nos, 102 Nos Electrical Drawings out of total
168 Nos and 70 Instrumentation drawings out of 187 Nos issued to rCM.
17 Nos MRs of Static Equipment out of total 21 Nos, 10 Nos MRs of
Electrical+CP System out of 27 Nos, 22 MRs of Instrumentation out of 59
NOs and all 4 pumps MRs issued to rCM. Vendor drawing review for
Compressors and other major equipment is in progress. Ordering of
Equipment is in progress at Milan, Italy.

UPPC EXPANSION PROJECT, (GAIL)


Cum. Physical Progress- Sch.:94.9%, Act.:B9.0% (Schedule
Revised).

Out of total 213 Nos eqpt., 212 Nos ordered, 145 Nos received at site and
130 Nos erected. Rotary Dryer erected during the month. Civil Works:
RCC - 14,786 m3 completed out of total 15,550 m3. A1G Piping welding
59,793 10 completed out of total 125;150 10. Erection 67,035 1M
completed out of total 140,107 1M.

PANIPAT NAPHTHA CRACKER PROJECTS, (IOCL):Cum. Physical


Progress: Sch.: 11.9%, Act.:13.4%.

EPCC Package - 1(Naphtha Cracker Unit - Mis. Toyo Engg. Corpn. &
L&T): - P&IO review completed. Out of 626 Nos, 343 equipments
ordered. HAZOP Study in progress. Site activities commenced for Site
office/Ware house & pilling work. EPCC Package - 2(PP+HOPE): - PP:
Work awarded to Mis Technimont ASPA Italy on 14.11.2006. HOPE:
Tender annulled. IOCL have issued enquiry for appointing EPCM
Contractor. EPCC Package - 3(LLDPE + HOPE Swing): Tender

7
,
annulled 10CL have asked ElL to submit proposal for the package on
LSTK basis. ElL proposal submitted on 02.11.2006. EPCC Package -
4(Captive Power Plant-Mis. L&T): Utility Boiler. GTG and HRSG ordered.
EPCC Package - 5(Cooling Water Pkg.): Layout, design Basis and U/G
pipe thk. Approved. CW pumps (23 Nos) ordered. EPCC Package -
6(RO based OM Water Plant & Condensate Polishing Unit-Mis. VA Tech
Wabag Ltd.): Plot plan approved. Clarifier, Pressure Vessels & pressure
tubes ordered. EPCC Package - 7(ET Plant Mis NICCO Corporation)
Revised BEP expected by end Nov.'06. Inspection categorization
approved. EPCC Package - 8 (Offsites & Storage Mis 10TL) RFO
issued for LP/HP Compressors, Pumps, Benzene recovery system, HT
Cables, RCC Pipes Site mobilisation is In progress Soil Investigation
report reviewed. Site mobilization is in progress. EPCC Package - 9
(Balance Utilities, Water Block, Interconnection to Panipat refinery,
Marketing Terminal and Flare- Mis Naftogaz) P & IDs for flare package,
Process data sheet for MOVsIPRDs, updates data sheets for
PMT/Refinery transfer pumps and Water pumps completed Survey for
flyover completed. EPCC Package - 10 (MEG Unit) Bids received on
16.102006, Evaluation is in progress. EO Reactors (FIM) Mis L&T- Sub-
ordering of boughtout items is in progress. EPCC Package - 11 (N202 -
BOO): TBA approved by 10CL on 03.11.2006 Condition of agreement is
under finalization by IOPCL. EPCC Package - 12 (Non Plant Buildings)
Feed package under finalization. NIT expected to be released by 1st week
of Dec. '06. EPCC Package - 13(Spent Caustic Treatment): Licensor
selection is in progress. EPCC Package - 14(PSU Revamp)' NIT issued
with bid due date of 11.12.2006.

PIPELINE PROJECTS DIVISION

NUMALIGARH SILIGURI PIPELINE PROJECT, (OIL)


Cum. Physical Progress- Sch.:87.0%, Act.:62.3%.

Ordering of all items completed. All 322 KM Line Pipe coated and
dispatched to dump sites. Micro tunneling Work (Mis. Ludwig-Pfieffer &
Gypsum Structural JV): Mobilisation is in progress Composite Works of
terminals: - Numaligarh despatch Terminal: Site grading work is in
progress. Siliguri despatch Terminal: Site grading and excavation work
started. Laying of 143.7 KM Pipe out of total 397 KM Completed.

MUNDRA DELHI PIPELINE PROJECT, (HPCL)


Cum. Physical Progress- Sch.:100%, Act.:82.9%.

Manufacturing of bare Line Pipe and Coating of 1050 KM completed.


Line Pipe Laying work of 846 KM completed out of total 1050 Km. Civil

8
l
Works and Composite works in progress for all the terminals except for
Jaipur Terminal Land yet to be acquired for Jaipur terminal

VADINAR~IN~JPELINE PROJECT, (BORL)


Cum.£hysical Prggress- Sch.:3.3%, Act.:2.8%.

Revised P&IDs, Equipment list & Eqpt Data sheet for balance eqpt
released Pipeline schematics released. MR for control valves released
on 07.11.2006. Final recommendation for linepipes sent on 17 11.2006
Bids due date for Main line & Booster pumps extended to 1512.2006

DHABOL-PANVELj='IPELINE PROJECTS, (GAIlJ


~um. Physicalj'roMess-: Sch.:37.8%, Act. :26.7%

PHASE-I:- Coated Line Pipes (30" - 187 KM). 5321 KM pipe


despatched. EPC Package Awarded to 2 parties on 03072006
Manufacturing activities for critical items are in progress. Trenching,
Welding of Joints and Lowering is in progress. PHASE - 11- Coated Line
Pipes (30" - 118 Km, 4" & 8"-19 KM): NIT published on 25.11.2006 for
ICB Tender EPC Package 3 Offers received and TBA IS targeted to be
issued by 06.12.2006

METALLURGY PROJECTS DIVISION

ALUMINA REFINERY PROJECT AT MURI, (HINDALCO)


Cum. EI Services Progress- Sch.:100.0%, Act.:86.3%.

All Piping GADs issued, Major engineering work completed. Piling, Civil
& Structural, Tankages, Piping and Equipment Erection. Electrical works
in progress. Construction work for Alumina Calciner Package and
Evaporation Package are in advance stage of completion. Construction of
Raw water Intake Well and Pipeline Package, Raw Water Treatment
Package, Effluent treatment Plant and Cooling Tower is in progress.

IInd PHASE EXPANSION ALUMINA SMELTER PROJECT AT ANGUL,


(NALCO), Cum. Physical Proqress- Sch.:38.3%, Act.:19.0%.

MR for EOT crane 160T issued. Order placed for Stratified material
insulator, End panel tightness joint panel, BRO Bricks & Grouting
compound and Dry and wet air receivers. NIT issued for CS Strl section
and hot rolled tubes for PSS and enquiries issued for EOT crane
(refloated), Insulating hoses, Local isolation cabinets, flanges, HV cables,
Battery & battery charger. Priced recommendation sent for Pot super
structure, Crust breaker and feeder Assembly, Cathode bars, pot room
liquid bath bins, Crust bath transport bins and heat insulated boxes, CS

9
welded pipes, KUB concrete, Micaveer insulators and Fibro cement
insulators Civil/strl works tender refloated on 07.11.2006 with bid due
date 30.11.2006 and Cooling tower tender floated on 07.11.2006 with bid
due date 07.12.2006. 47 Nos Pot Shells received at site out of total 242
Nos. RCC work of Pot Line, Civil & Structural Work of Pot Room A & B.
Central Duplex Building, are in progress. Piling Work completed
Construction water & Drinking water line completed and charged at pot
line

~~~~~~~~~_.u
MINES and ALUMINA __
REFINERY EXPANSION .
PROJECT ,_
AT
[JAMANJODI, (NALCO), Cum. Physical. Progress,. ~ch.:36..6°&,
Act.:14.2%.

101 Nos AFC Drgs issued out of estimated total of 659 nos. 64 Nos MRs
Issued out of total 150 Nos. Recommendation issued for 12 and order
placed for 9 out of estimated total 150 MRs 3,679MT of BO Plates
received out of total requirement of 3,793MT for Precipitati on Tanks Civil
& Structural Works - RCC work in progress for Precipitation Tanks
Foundation of first tank (No 1122) handed over to tankage contractor
Evaporation Package: Civil and Structural Work is in progress. 1131 MT
Strl Steel received out of 1400 MT and Fabrication of 200MT completed.
Site Grading and Piling work is in progress.

OVERSEAS PROJECTS DIVISION

REHABILITATION AND ADAPTATION OF SKIKDA REFINERY


(NAFTEC, ALGERIA), Phase - I (Feed Phase): Cum. Physical
Progress: Sch.: 52.1%. Act.:58.0%.

EPCC - 1(OSBL Electrical Works): NAFTEC confirmed change overto


200 KV grid input to refinery on 07. J 1.2006. Compilation of Tech
Amendment NO.2 has been takenup accordingly. EPCC - 2(DCS and
Instrumentation Modernisation Works): NAFTEC reissued the tender on
restricted enquiry basis to 5 bidders. Bids due date extended upto
04.12.2006. EPCC - 3(CDU I Gas Plant I Rehabilitation of utilities and
Offsites): Bids due has been extended to 08.12.2006. Process Package
for Utilities & Offsites under advance stage of finalisation. EPCC-
4(Aromatic Block): FEED Package has been compiled and is in process
of dispatch. Evaluation of bids for Prequalification of bidder is in progress.
EPCC - 5 (LNISOM and adaptation Utilities and Offsites) & 6 (DHDS):
Due date for receipt of priced bids from LNISOM Process Licensor
extended to 05.12.2006. EPCC - 6 (DHDS incl. Sulphur Recovery
Unit): Due date for receipt of priced bids from DHDS Process Licensor
extended to 05.12.2006. EPCC - 7(Adaptation Area Site Grading):

10
EPCC Contarctor mobilized and Area cleaning and site grading work is in
progress. EPCC - 8(Dismantling of existing Paraxylene Recovery Unit):
Contractor mobilised and commenced the work w.e.f 1811.2006.
EPCC - 9 (Fire Water network): Fire water layout, P&IDs, Tanks and
Pump data sheets prepared EPCC - 10(pipelines to Port) Preparation
of Design Basis, Survey and Soil Investigation Layout have been
completed

ALGJERS .. REFINERY REHABILITATION PROJECI, (NAFTEC,


ALC3J;RI~1_J)has~ - I (Feed Phase): Cum. Physical Progress: Sch. &
Actual: 100.0 **%.
-- ._--- .. -----

EPC Package1 (Modernisation of Instrumentation and New Central


Control Room) Technical Recommendation issued NAFTEC. Finalisation
of Draft Contract (Commercial terms & conditions) by NAFTEC is in
progress EPCC - 02 (Electrical System Revamp): (** In view of non
receipt of offers for EPCC-02, this package has been split into 3 new
smaller packages EPCC-02, 03 & 04) After split tender published in
Baosem on 06.11.2006 with bid due date of 13.01.2007.

ADDITIONAL WORK: - EPCC Package 3 (Heater Revamp) Response


from NAFTEC awaited on proposed implementation philosophy to take up
the preparation of FEED Package. EPC Package 4 (New OWS I CRWS
Network In OSBL and New ETP) ) Tender published in Baosem on
20.11.2006 with bid due date of 2201.2007.