Escolar Documentos
Profissional Documentos
Cultura Documentos
Sample Problem
¾ Plan and Profile Design
¾ Design Software
¾ Station Calculations
Standard Details
Factory
F t Collection
C ll ti Stations
St ti
Questions and Answers
Schematic of Typical Vacuum System
General Guidelines for Vacuum
System
y Design
g
Determine the geographical limits of
th service
the i area
THRUST
Vacuum Line Thrust
E T
T
LV LE
PI
VA IN
M E
O AG
FR EW
AIR SPACE LIQUID
HIGH VELOCITY
S
D UID AT REST
OPEN FROM EN CONTACTS LIQ
OF LINE TO & PROPELS THE
MASS
BACKSURGE
MAIN FLOW N
VACUUM STATIO DOWNSTREAM
0.2% FALL
0+00
6+00
21+40 B
Example
p of
BRANCH B
Flow Path
26+50
BUFFER
TANK
0+00 BRANCH C (10GPM)
30+15 C 12+95
34+15 16+50
36+00 18+10
38+95
0+00 D 44+40
22+50
BRANCH D
TYPICAL
HOMES
2+80
48+00
B
F 30+30
G
E 53+95
8+30
Explanation of Q (MEAN)
Vacuum Main Profile Design Example
AIRVAC - STANDARD
SLOPES
¾ Use natural ground slope if greater than 0.2%
¾ Use 00.2%
% sslope
ope for
o flat
at te
terrain
a
¾ Use saw tooth profile for uphill transport
¾ Use 00.2%
2% slope at 50’
50 minimum prior to first lift in any
series
Summary of Vacuum Piping Design
F d
Fundamentals
t l
FLOW LIMITS
¾ Maximum Friction Loss not to exceed 5 feet
3” = 4 homes or equivalent
44” = 38 GPM
6” = 106 GPM
88” = 210 GPM
10”= 375 GPM
Summary of Vacuum Piping Design
F d
Fundamentals
t l
FLOW
SERIES OF
LIFTS
ELEV
FLOW FLOW
45° ELBOW
VACUUM SEWER MAIN VACUUM SEWER BRANCH
2' MINIMUM
45º ELBOW
Branch
VACUUM BRANCH TO MAIN CONNECTION
20' MINIMUM
FROM A LIFT
FLOW
(2)
B
BASED ON SPEARS MFG.
Connections
(1) 45° WYE, SOCKET x SOCKET x SOCKET
A
(2) 45° ELL, SOCKET x SOCKET C
D
(1)
WYE SIZE A B C D - INVERT
4x4x4 8 3/4" 3 5/16" 8.53" 0.71'
10 x 10 x 10 22 3/8"
3/8 8 19/32" 21 90"
21.90 1 89'
1.89
Gravityy
4" GRAVITY LINE STUBBED OUT
AND CAPPED OFF (MAY BE AS
MANY AS FOUR CONNECTIONS)
FIGURE 3
3-2
2 VALVE PIT PRIOR TO HOME CONNNECTION
0+00
6+00
21+40 B
BRANCH B
26+50
BUFFER
TANK
Design Example
Layout
0+00 BRANCH C (10GPM)
30+15 C 12+95
34+15 16+50
36+00 18+10
38+95
0+00 D 44+40
22+50
BRANCH D
TYPICAL
HOMES
2+80
48+00
F 30+30
G
E 53+95
8+30
Design
g Example
p
Consider vacuum sewer layout
¾ Locations of collection station, sewers and AIRVAC
valves selected in accordance with requirements of
AIRVAC 2005 Design Manual
Locate sewers to
- Minimize lift
- Minimize length
- Equalize flows on each sewer (where possible)
¾ Locate AIRVAC valves to serve two or more homes
per valve
See Chapter 5
Design
g Example
p
Assumptions
p
¾ Each AIRVAC valve to serve two (2) homes
¾ Peak flow pper home .64 GPM or 1.28 GPM /
AIRVAC valve installation
To efficiently serve the areas in the design
example layout
¾ Three (3) main sewers required
¾ Each main connected directly to vacuum tank at
collection station
¾ Sewers are not joined together into bus main outside
the station
Design
g Example
p
Division
Di i i valves
l llocated
t d tto iisolate
l t areas off
sewer network for troubleshooting purposes
Profiles prepared for Main #2
¾ Profiles for Branches, Main #1 and Main #3 would be
similar
Design
g Example
p
3051 lf 4” 600 lf
8” v.s. 0+00
6+00
Design
21+40 B
BRANCH B
Example 8”
26+50
1030 lf 6” v.s.
0+00 BRANCH C
6” 4”
BUFFER
TANK
(10GPM)
Layout
30+15 C 12+95
6” 10 + 30
880 lf
34+15 6” v.s. 16+50
36+00 18+10
38+95
0+00 D 44+40
22+50
BRANCH D
TYPICAL
HOMES
2+80
48+00
830 lf 1500 lf
4” v.s. 6” v.s.
F 30+30
G
E 53+95
8+30
Figure F4-
F4-17 – Piping Calculation Sheet
PROJECT: Design
PROJECT D i Example
E l STATION NUMBER:
NUMBER 1
DATE: 6/25/03 Peak Flow Rate per Home = .64 gpm
LINE 4” PIPE 6” PIPE 8” PIPE 10” PIPE PEAK # SVCE # AIRVAC HOMES
LATERALS VALVES (or EDUS)
1 2400 1400 79.4 62 62 124
2
3 3700 2200 49.9 10 32 78
TOTALS
Average Service
Lateral Length
Total 3” Pipe
VOLUME OF PIPEWORK (BASED ON SDR-21 PVC PIPE)
Vp = (.0547 x Length 3”) + (.0904 x Length 4”) + (.1959 x Length 6”) + (.3321 x Length 8”) = (.5095 x QTY
10”) FT3
Vp = ( + + + + ) FT3
Vp = 7.5 ( ) GALLONS
Vp = GALLONS
2/ Vp = GALLONS
3
Figure F4-
F4-17 – Piping Calculation Sheet
PROJECT: Design
PROJECT D i Example
E l STATION NUMBER:
NUMBER 1
DATE: 6/25/03 Peak Flow Rate per Home = .64 gpm
LINE 4” PIPE 6” PIPE 8” PIPE 10” PIPE PEAK # SVCE # AIRVAC HOMES
LATERALS VALVES (or EDUS)
1 2400 1400 79.4 62 62 124
2 3430 3410 3015 145.9 114 114 228
3 3700 2200 49.9 10 32 78
TOTALS 9530 7010 3015 275.2 186 208 430
Average Service 20’
20
Lateral Length
Total 3” Pipe 3720
VOLUME OF PIPEWORK (BASED ON SDR-21 PVC PIPE)
Vp = (.0547 x Length 3”) + (.0904 x Length 4”) + (.1959 x Length 6”) + (.3321 x Length 8”) = (.5095 x QTY
10”) FT3
Vp = ( + + + + ) FT3
Vp = 7.5 ( ) GALLONS
Vp = GALLONS
2/ Vp = GALLONS
3
Figure F4-
F4-17 – Piping Calculation Sheet
PROJECT:
O C Design Example STATION
S O NUMBER: 1
DATE: 6/25/03 Peak Flow Rate per Home = .64 gpm
LINE 4” PIPE 6” PIPE 8” PIPE 10” PIPE PEAK # SVCE # AIRVAC HOMES
LATERALS VALVES (or EDUS)
1 2400 1400 79.4 62 62 124
2 3430 3410 3015 145.9 114 114 228
3 3700 2200 49.9 10 32 78
TOTALS 9530 7010 3015 275.2 186 208 430
Average Service 20’
Lateral Length
Total 3” Pipe 3720
VOLUME OF PIPEWORK (BASED ON SDR-21 PVC PIPE)
Vp = (.0547 x Length 3”) + (.0904 x Length 4”) + (.1959 x Length 6”) + (.3321 x Length 8”) = (.5095 x QTY
10”) FT3
Vp = ( 203 + 861 + 1373 + 1001 + -- ) FT3 = 3438 FT3
Vp = 7.5 ( 3438 ) GALLONS ( 7.5 gal / FT3 )
Vp = 25,785 GALLONS TOTAL PIPE VOLUME (Sewage & Vacuum)
2/ Vp = 17,018 GALLONS VACUUM ONLY
3
E
PROJECT: Example Problem Project No.: 951075
x
a
Peak Flow (Qmax) Qmax = gpm
Qmax
Average Flow (Qa) = = Qa = gpm
Peak Factor 3.5
l
*Longest Line Length (A)
0' - 5,000' 6
e
5001' - 7 000'
7.000' 7
7001' - 10,000' 8
10,001' 12,000' 9
12,001' 15,000' 11
Di scharge Pump Capacity (Qdp) = Qmax Qmax = gpm
o
Total Volume Collection Tank (Vct)
= ____Vo = 3 Vo Vct = gal
g
*INCLUDE 400 GGallons
ll ffor R
Reserve T
Tank*
k*
b
Vacuum Reservoir/Moi sture Removal Tank
gal
(Vrt) (If separate vessel is desired) Vrt =
(include in Vct)
(Rec ommended Volum e Vrt-= 400 gal)
l System Pump Down Time for Operating Range (0.045 cfm min) (2/3 Vp+ (Vct-Vo)+Vrt) gal
e
=
of 16" to 20" Hg Vacuum (t) gal Qvp cfm
"t" should be 1 to 3 mins. (0.045 ( )+( - )+( )
m
= t = mins.
if over 3, increase Qvp / if under 1, increase Vrt cfm
PROJECT: Example Problem PROJECT #: 951075
E
x STATION #: 1 DATE: 6/25/03
e 7,001’
10,001’
-
-
10,000’
12,000’
8
9
m 12,001’ - 15,000’ 11
PROJECT: Example Problem PROJECT #: 951075
E
x STATION #: 1 DATE: 6/25/03
b Tank (Vrt)
(if separate vessel is desired) 1519 + 400 = 1919 use 2000 gal
l
e
* Vo
= 1.84 Qmax for 3.5 Peak Factor
m = 1.64 Qmax for 4.0 Peak Factor
PROJECT: Example Problem PROJECT #: 951075
E
x STATION #: 1 DATE: 6/25/03
a
m System
y Pump p Down ((0.045 cfm min)) (2/3
( Vp p +(Vct-Vo)
( ) +Vrt)) gal
g
Time for Operating
p Range
gal Qvp cfm
x
a
Peak Flow (Qmax) Qmax = gpm
Qmax
Average Flow (Qa) = = Qa = gpm
Peak Factor 3.5
l
*Longest Line Length (A)
0' - 5,000' 6
e
5001' - 7 000'
7.000' 7
7001' - 10,000' 8
10,001' 12,000' 9
12,001' 15,000' 11
Di scharge Pump Capacity (Qdp) = Qmax Qmax = gpm
o
Total Volume Collection Tank (Vct)
= ____Vo = 3 Vo Vct = gal
g
*INCLUDE 400 GGallons
ll ffor R
Reserve T
Tank*
k*
b
Vacuum Reservoir/Moi sture Removal Tank
gal
(Vrt) (If separate vessel is desired) Vrt =
(include in Vct)
(Rec ommended Volum e Vrt-= 400 gal)
l System Pump Down Time for Operating Range (0.045 cfm min) (2/3 Vp+ (Vct-Vo)+Vrt) gal
e
=
of 16" to 20" Hg Vacuum (t) gal Qvp cfm
"t" should be 1 to 3 mins. (0.045 ( )+( - )+( )
m
= t = mins.
if over 3, increase Qvp / if under 1, increase Vrt cfm
E
PROJECT: Example Problem Project No.: 951075
x
a
Peak Flow (Qmax) Qmax = 275.2 gpm
Qmax Qmax
Average Flow (Qa) = = Qa = 78.6 gpm
m
Peak Factor 3.5
Qa 78.6
Minimum Flow (Qmin) = = Qmin = 39 3 gpm
39.3
2 2
e
5001' - 7 000'
7.000' 7 ----- 6045
7001' - 10,000' 8
10,001' 12,000' 9
12,001' 15,000' 11
Discharge Pump Capacity (Qdp) = Qmax Qmax = 275.2 gpm
b
Vacuum Reservoir/Moisture Removal Tank
0 gal
(Vrt) (If separate vessel is desired) Vrt =
(include in Vct)
(Recommended Volume Vrt-= 400 gal)
e
System Pump Down Time for Operating Range (0.045 cfm min) (2/3 Vp+(Vct-Vo)+Vrt) gal
=
of 16" to 20" Hg Vacuum (t) gal Qvp cfm
"t" should be 1 to 3 mins. (0.045 ( 17,018 ) + ( 2000 - 506 ) + ( 0 )
m
= t = 1.83 mins.
if over 3, increase Qvp / if under 1, increase Vrt 455 cfm
E
PROJECT: Example Problem Project No.: 951075
x
a
Peak Flow (Qmax) Qmax = 275.2 gpm
Qmax Qmax
Average Flow (Qa) = = Qa = 78.6 gpm
m
Peak Factor 3.5
Qa 78.6
Minimum Flow (Qmin) = = Qmin = 39 3 gpm
39.3
2 2
e
5001' - 7 000'
7.000' 7 ----- 6045
7001' - 10,000' 8
10,001' 12,000' 9
12,001' 15,000' 11
Discharge Pump Capacity (Qdp) = Qmax Qmax = 275.2 gpm
b
Vacuum Reservoir/Moisture Removal Tank
0 gal
(Vrt) (If separate vessel is desired) Vrt =
(include in Vct)
(Recommended Volume Vrt-= 400 gal)
e
System Pump Down Time for Operating Range (0.045 cfm min) (2/3 Vp+(Vct-Vo)+Vrt) gal
=
of 16" to 20" Hg Vacuum (t) gal Qvp cfm
"t" should be 1 to 3 mins. (0.045 ( 17,018 ) + ( 2000 - 506 ) + ( 0 )
m
= t = 1.83 mins.
if over 3, increase Qvp / if under 1, increase Vrt 455 cfm
E
PROJECT: Example Problem Project No.: 951075
x
a
Peak Flow (Qmax) Qmax = 275.2 gpm
Qmax Qmax
Average Flow (Qa) = = Qa = 78.6 gpm
m
Peak Factor 3.5
Qa 78.6
Minimum Flow (Qmin) = = Qmin = 39 3 gpm
39.3
2 2
e
5001' - 7 000'
7.000' 7 ----- 6045
7001' - 10,000' 8
10,001' 12,000' 9
12,001' 15,000' 11
Discharge Pump Capacity (Qdp) = Qmax Qmax = 275.2 gpm
b
Vacuum Reservoir/Moisture Removal Tank
0 gal
(Vrt) (If separate vessel is desired) Vrt =
(include in Vct)
(Recommended Volume Vrt-= 400 gal)
e
System Pump Down Time for Operating Range (0.045 cfm min) (2/3 Vp+(Vct-Vo)+Vrt) gal
=
of 16" to 20" Hg Vacuum (t) gal Qvp cfm
"t" should be 1 to 3 mins. (0.045 ( 17,018 ) + ( 2000 - 506 ) + ( 0 )
m
= t = 1.83 mins.
if over 3, increase Qvp / if under 1, increase Vrt 455 cfm
Design
g Example:
p Hydloss
y Sp
Spreadsheet
Microsoft Excel
Worksheet
520 520
VACUUM MAIN #2
FLOW
515 515
510 510
505 505
EL=502.60
EL 501 70
EL=501.70
EL=503.51
EL=501.10 EL=501.00 500
500
@3+00 EL=500.20 @10+00
EL=502.00
CONNECT TO @6+00
VACUUM STATION
@0 00
@0+00
0+00 2+00 4+00 6+00 8+00 10+00 12+00 14+00 16+00 18+00
520 520
VACUUM MAIN #2
FLOW
515 515
510 510
CONNECT LINE "C"
@30 1
@30+15
CONNECT LINE "B" EL=505.91
@21+40
505 EL=504.71 505
EL=504.41
@32+00 EL=503.41
EL=503.21
@33+50
EL=503.51 EL=502.41
@34+50
500 500
18+00 20+00 22+00 24+00 26+00 28+00 30+00 32+00 34+00 36+00
520 520
515 515
END OF LINE
EL=513.91
510 @53+95 510
CONNECT LINE "D"
@38+95
CHANGE TO 4"
EL=507.08
@44+40
POINT "F"
505 505
EL=503.20
EL=502.60
EL=502.71
EL=502 71
EL=502.20 EL=502.00
@36+00 EL=501.60
@38+45 @42+45
@40+45
500 500
POINT "D"
36+00 38+00 40+00 42+00 44+00 46+00 48+00 50+00 52+00 54+00
Existing Manhole
Vacuum
Station
12.0 Ft
((L)) Equiv
q for station
fittings = 10.0’
ROB
MAT
11/11/96 1/4" = 1'-0" 1-S
Standard Valve Pit – Breather Details
STANDARD DETAILS
Standard Detail 2-S VALVE PIT - BREATHER DETAILS
2-S
Standard Line Details
1/2" = 1'-0" 3
Standard Line Connection Details