Escolar Documentos
Profissional Documentos
Cultura Documentos
EXECUTIVE SUMMARY
Coal and Oil (C&O) Group – the Rs. 2500 cr integrated energy Group with
interests in coal trading, mining, shipping and logistics is implementing a
1200- MW coal fired thermal power station near Tuticorin, in the State of
Tamil Nadu. The proposed project shall be developed, financed, constructed,
commissioned, operated and maintained through a Special Purpose Vehicle
(SPV) titled – “Coastal Energen Private Ltd.” (ENERGEN) a C&O Group
Company.
2.0 PURPOSE
The purpose of this report is to establish the technical feasibility and project
cost estimates of the proposed 2x600MW capacity coal fired sub critical
thermal power plant near village Melamaruthur in the district of Tuticorin,
Tamil Nadu state.
This detailed project feasibility report highlights the details of the selected
site, availability and use of sea water to meet the water requirements,
technical features of the main plant equipment, coal and ash handling
systems, electrical systems, evacuation of power, environmental aspects,
estimates of project cost at power station bus, schedule for project
implementation of the proposed thermal power project.
3.0 SCOPE
b) Study of the selected site and establish the feasibility for the installation
of 2x600MW coal-based thermal power plant considering topography,
accessibility by rail and road, availability of sea water to meet the plant
water requirements, power evacuation plans, availability and transport
of fuel required for the plant, space availability for ash disposal and
general environmental aspects.
e) Environmental aspects.
(a) ENERGEN has identified the required land of about 1100 acres for the
proposed power plant. The proposed power plant site is located near village
Melamaruthur in the district of Tuticorin, Tamil Nadu state. The total available site area
of about 1100 acres is adequate for 2x600MW (and for further expansion) for main
plant, power house, transformer yard, switch yard, CW system, Coal handling plant,
water treatment plant, water reservoir, guard pond and ash disposal area as shown in
the Plot plan including green belt. However for coal stock yard for future units,
additional space needs to be identified along with ash disposal area.
(b) Out of the total of about 1100 acres of land, major portion of the land
belongs to private owners. The proposed land is barren, fallow land, single crop
cultivation in patches. There are no major settlements/ habitation / forestry. Hence no
rehabilitation and resettlement is envisaged.
5.2 WATER
Sea water would be pumped from sea to the power plant using sea
water intake pumps. The intake pump house will be located on the
shore and this pump house will receive water through a channel drawn
from the sea. Around 4.0 km pipe line is proposed to be laid from intake
pump house to plant site. ENERGEN has already applied to the
concerned authorities (like CRZ etc) for permission for withdrawal of 84
MGD sea water. Permission will have to be taken from appropriate
authorities for crossing National highway and railway lines if required.
Sea water will be directly used for condenser cooling and will be
treated in a desalination plant to be used for SG feed cycle make uo,
plant service water and potable water purposes. The cooling tower
blow down along with RO rejects will be led back to sea. through a
separate outfall channel arrangement.
5.3 COAL
Coal is imported to the plant through an external coal jetty. The coal will
further be transported through conveyors to site. Alternate provision of
transporting coal through railways will also be made available. Coal is
also proposed to be transported to site through trucks from the port.
The power generated will be sold through the Power Trading Agencies
using Inter-State transmission network
6.3 GENERATOR
The power plant is proposed to use imported coal with low Sulphur content.
Single Chimney with twin-flue of 275 meter high RCC stack is proposed to
be provided to meet the requirements of the environmental regulations. The
steam generators would be provided with low NOx burners and hence the
emission of oxides of Nitrogen from the steam generator would be minimum.
Adequate provisions are proposed for neutralizing the effluents from the
water treatment plant. Effluents from the entire power plant are proposed to
be treated and reused in the power plant to minimize the make-up water
requirement.
Total capital cost including the interest during construction for the proposed 2
x 600MW project is estimated to be Rs. 4297 Crores (Rs. 3.58 Crores/MW)
and the unit cost at 80% PLF is Rs 3.52 / kWh which has been calculated
considering 30 years of operation. Refer: Appendix 7.
10.0 CONCLUSIONS
The proposed power plant also has all the basic requirements essential for a
thermal power plant viz. land, water, fuel (coal) and power evacuation
facilities.
11.0 RECOMMENDATIONS
(b) Finalization of land lease agreement for power plant and ash disposal
area including additional area, corridors for coal conveyer and sea water
piping.
(f) Route survey and alignment studies for laying coal conveyers, sea water
pipes and electrical transmission lines.
(g) Securing allocation of use of sea water from the concerned authorities.
(h) Right of way for laying pipe line from sea to the power plant.
(i) Approval of Civil Aviation Authority for installing 275 m high chimney
(k) Discussion with Railway authority for constructing railway lines from
Milaviattan station up to proposed project site.
(m) Study for transportation of coal from external jetty to site including route
survey.