Agri-business Development and

Diversification Project

1. Executing Agency DALPMG, MINFA, PHDEC, FSC&RD,


LDDB

2. Whether the project is implemented in Yes, the project is implemented in Khyber


province or not. Pakhtunkhwa as well.

3. Date of approval Planned for 5 years i.e. July 2005 to June


2010.

4. Approved cost with provincial share Total approved cost of the project is Rs.
4066.00 Million.

(Rs. In Million)
ADB’s Share: 1860.00
GOP Share: 414.00
Sp. Provinces Grant: 1,000.00
Private sector 792.00
Total : 4066.00

5. Release & Expenditure since


commencement.
Name of component Total Planned AmountExpenditure incurred
up to June 2010
ADB GOP ADB GOP
PMU/PIO’s 165.92 150.750 165.92 150.750
Agribusiness Support Fund 307.97 80.620 307.97 80.620
Pakistan Horticulture Development & Export Company 16.048 72.919 16.048 72.919
along with 4 Training components.
Livestock & Dairy Development Board 4.591 15.731 4.591 15.731
Department of Agricultural Livestock Products 6.800 15.680 6.800 15.680
Marketing & Grading (DALPMG Export Certification.
Federal Seed Certification & Registration Deptt. 14.100 28.200 14.100 28.200
Consultancy 112.100 0.000 112.100 0.000
Block Allocation to Provinces/Special Areas 0.000 457.973 0.000 457.973
Total : 0 0 0 0

Page 1 of 3
/conversion/tmp/scratch/55070537.docx
6. Up to date progress both financial & Financial Progress = Rs. 903.651 Million
physical. Physical Progress up to December, 2010:

Component Progress
1. Agribusiness Support Services
 Establishing an Agribusiness Support Fund  ASF established under Section 42 of
(ASF) for Business Development Services Company’s Ordinance 1984 as non profit
(BDS) provision. organization and is fully functional.
 Providing cost sharing grants for BDS and  3542 Matching Grants disbursed out of total
enhancing competitiveness. target of 3344 with following break up:
 Agribusiness enterprise support grants: 345
 Agribusiness enterprise start up grants: 96
 BDS providers grants: 697
 Private Sector Extension Services grants: 23
 Demand Driven Research : 11
 Farmer enterprises formation grants: 1250
 BDSS Support grants: 1120
2. Capacity Building for Agribusiness
A. Curriculum development for Government  Curricula for School Management Skills
Commerce Colleges (GCC) and Vocational Training Development and in operation.
Training Institutes (VTI).  WTO and International Standards Compliance
Training Manual Developed and in operation.
 Agribusiness Management Training Manual
Developed and is being practices.
 Supply Chain Management and Export
procedures Training Manual Developed and in
operation.

i. 29000 plants have been purchased and plantation completed.


ii. Bench mark data recorded and soil analysis have been completed.
iii. Layout maps and digging of pits for plantation were completed.
iv. Pear plants (cv.Lecont) purchased.

7. Funds available for 2010-11 Rs. 8.231 Million.

8. Funds released by the provincial finance Not applicable


department during 2011-12.

9. Anticipated Expdt. By June 2011. Rs. 8.231 Million.

10. Overall releases and expenditure by June Rs. 16.459 Million


2011.

11. Funds still available with provincial Rs. 7.186 Million


finance department.

Page 2 of 3
/conversion/tmp/scratch/55070537.docx
12. Identified ongoing projects with In Khyber Pakhtunkhwa three projects
sufficient expenditure which can be having same objects with a broader
taken in provincial ADP 2011-12 for spectrum are in progress. 3 Projects (serial
completion. No. I to iii below) have being completed
their planned period on June 2011.

i. Establishment of Model Fruit Orchards


in NWFP according to Ecological Zones.
ii. Establishment of Date Progeny Gardens
in DIKhan, Bannu Lakki Marwat and
Tank Districts of N.W.F.P.
iii. Block Plantation & Acelerated
Promotion of Fruits (Ber, Dates and
Pomegranates) in Districts Lakki
Marwat, Karak & Tank.
iv. Exploitation of Area Specific potential
of various crops in the province.

13. Identifying scheme with a nominal Not applicable.


expenditure which could be dropped.

14. Categories the new portfolio of scheme A scheme viz Rehabilitation of Orchards in
into crucial/less important. Conflict and Flood Affected Areas of
Khyber Pakhtunkhwa is proposed as new
project in forthcoming ADP 2011-12 have
extreme /crucial importance. It is
recommended that the proposal may be
approved / incorporated in the forthcoming
ADP 2011-12 on Top priority.

15. Justification / Remarks on weather to Project does not have share of Khyber
continued or discontinue this project in Pakhtunkhwa, therefore its continuation or
the province. taking in to account of provincial ADP does
not arise.