Diversification Project
4. Approved cost with provincial share Total approved cost of the project is Rs.
4066.00 Million.
(Rs. In Million)
ADB’s Share: 1860.00
GOP Share: 414.00
Sp. Provinces Grant: 1,000.00
Private sector 792.00
Total : 4066.00
Page 1 of 3
/conversion/tmp/scratch/55070537.docx
6. Up to date progress both financial & Financial Progress = Rs. 903.651 Million
physical. Physical Progress up to December, 2010:
Component Progress
1. Agribusiness Support Services
Establishing an Agribusiness Support Fund ASF established under Section 42 of
(ASF) for Business Development Services Company’s Ordinance 1984 as non profit
(BDS) provision. organization and is fully functional.
Providing cost sharing grants for BDS and 3542 Matching Grants disbursed out of total
enhancing competitiveness. target of 3344 with following break up:
Agribusiness enterprise support grants: 345
Agribusiness enterprise start up grants: 96
BDS providers grants: 697
Private Sector Extension Services grants: 23
Demand Driven Research : 11
Farmer enterprises formation grants: 1250
BDSS Support grants: 1120
2. Capacity Building for Agribusiness
A. Curriculum development for Government Curricula for School Management Skills
Commerce Colleges (GCC) and Vocational Training Development and in operation.
Training Institutes (VTI). WTO and International Standards Compliance
Training Manual Developed and in operation.
Agribusiness Management Training Manual
Developed and is being practices.
Supply Chain Management and Export
procedures Training Manual Developed and in
operation.
Page 2 of 3
/conversion/tmp/scratch/55070537.docx
12. Identified ongoing projects with In Khyber Pakhtunkhwa three projects
sufficient expenditure which can be having same objects with a broader
taken in provincial ADP 2011-12 for spectrum are in progress. 3 Projects (serial
completion. No. I to iii below) have being completed
their planned period on June 2011.
14. Categories the new portfolio of scheme A scheme viz Rehabilitation of Orchards in
into crucial/less important. Conflict and Flood Affected Areas of
Khyber Pakhtunkhwa is proposed as new
project in forthcoming ADP 2011-12 have
extreme /crucial importance. It is
recommended that the proposal may be
approved / incorporated in the forthcoming
ADP 2011-12 on Top priority.
15. Justification / Remarks on weather to Project does not have share of Khyber
continued or discontinue this project in Pakhtunkhwa, therefore its continuation or
the province. taking in to account of provincial ADP does
not arise.