Escolar Documentos
Profissional Documentos
Cultura Documentos
Section A
£180,000
2 B OAR/machine hour = = £18/machine hour
10,000
4 D The trend is the general upward or downward movement of the variable over time.
The additive model assumes independence, not the multiplicative model.
Regression analysis can be used to predict the trend but adjustments still need to be made regarding variations.
5 A Cost accounting can be used for stock valuation to meet the requirements of both internal and external reporting.
130
6 B 325,000 x = 340,726 adjusted year 7 sales figure
124
435,000
% = 127·7% 100% = 27·7%
340,726
7 A
( )
8 B Working conditions, pension provisions and welfare are all costs relating to retaining, not replacing, labour.
10 C Since the company has an objective of minimising costs the potential optimal solutions will be the points closest to the origin i.e.
D and E.
é 3,664 ù
11 A IRR = 15% + êêê úúú x (20% 15%)
ë 3,664 + 21,451 û
= 15·7%
17
12 C S = 6,300 + 0·05M
M = 8,450 + 0·1S
S = 6,300 + 0·05 x (8,450 + 0·1S)
= 6,300 + 422·5 + 0·005S
0·995S = 6,722·5
\ S = £6,756
\ M = £9,126
For production department 1, the total overheads are
= 17,500 + 6,756 x 60% + 9,126 x 75%
= £28,398
Ö Ö
2ChD 2 x (50 + 5) x 4,000
13 D EOQ = = = 509 units
Co (15 x 0·1) + 0·2
135,000
18 B OAR/labour hour = = £15/labour hour
9,000
Capacity variance:
Actual 9,750 hours
Budget 9,000 hours
750 hours
x £15 = £11,250 favourable
20 C Process account
Units £ Units £
Materials 3,500 52,000 Normal loss 875 7,000
Labour 9,625
Abnormal gain 175 Output 2,800
3,675 3,675
18
21 B Specific fixed overheads per division = 262,500 x 60%
157,500
= = 52,500
3
23 A Higher level management could be involved with all level of decision making within a business.
12
25 D Ö1·1268 = 1·01
50 x 1·0113x12 1 = £18,610
1·01 1
19
Section B
2 (a) £
Budgeted prime cost (30 + 24) x 12,000 (648,000)
Cost volume variance (500 x 54) 27,000
(621,000)
Materials
Price: Did cost £345,000
Should cost (37,250 x £10) £372,500
27,500F
Usage: Did use 37,250 kg
Should use (11,500 x 3) 34,500 kg
2,750 kg
x £10 (27,500)A
Labour
Rate: Did cost £300,000
Should cost (45,350 x £6) £272,100
(27,900)A
Efficiency: Did take 45,350 hours
Should take (11,500 x 4 hours) 46,000 hours
650 hours
x £6 3,900F
Actual prime cost (£300,000 + £345,000) (645,000)
(b) Labour rate variance this shows that labour were paid at a higher rate
Labour efficiency variance this shows that labour worked harder than expected as they made more in less time
Interdependence since labour were paid more they were motivated to work harder
20
3 (a) (i) Total cost for 30,000 units or less = 50,000 + 5 x Q
(ii) Total cost for more than 30,000 units = 100,000 + 5 x Q
(b)
(c) Implications of having two breakeven points: the product is only profitable between 20,000 and 30,000 units and above
40,000 units, so the production plan should be set accordingly.
21
5 (a)
£000 £000
Sales 48·6
Cost of sales:
Opening stock (150 x 22) 3·3
Production costs
Variable costs 36·0
Fixed costs (1,800 x 2) 3·6
42·9
Closing stock (350 x 22) (7·7)
Under absorption (W2) 0·4
(35·6)
Gross profit 12·4
Administration (3·6)
Selling (1·2 + 3·2) (4·4)
Net profit 4·4
Workings
1. Standard cost per unit
£
Direct variable costs 20
£4,000
Fixed overheads = 2
2,000 units
22
(b) £
Profit under absorption costing 4,400
Add fixed costs in opening stock (150 x 2) 300
Less fixed costs in closing stock (350 x 2) (700)
Profit under marginal costing 4,000
A business may prefer marginal costing as it only includes costs that are relevant for decision making i.e. variable ones. Also the
business may not have significant fixed overheads and so marginal costing could be more appropriate.
22
Part 1 Examination Paper 1.2
Financial Information for Management Marking Scheme
Marks
Section A
Each question within this section is worth 2 marks 25 x 2
50
Section B
1 (a) Calculation of marginal cost plus 1
Advantage of marginal cost plus 1
Disadvantage of marginal cost plus 1
Calculation of fixed cost plus 1
Advantage of fixed cost plus 1
Disadvantage of fixed cost plus 1
6
23
Marks
4 (a) Production budget
Sales units for both products ½
Opening stock figures for both products ½
Closing stock figure for product A ½
Closing stock figure for product B ½
2
(b) Materials usage budget
Figure for material X 1
Figure for material Y 1
2
(c) Material purchases budget
Opening stock figures for both materials ½
Closing stock figure for material X 1
Closing stock figure for material Y 1
Showing material costs per kg or litre ½
3
(d) Labour budget
Total hours for skilled labour 1
Total hours for semi skilled labour 1
Showing labour cost per hour ½
2½
Presentation ½
10
24