UN P

EXPLICANDO GRAFICAMENTE REPROGRAMACI


01. Proyecto atrasado

HH PLAN HH REAL
HH % Avance
Semana acumulada HH Real Acumulada % Avance real
planificada planificado
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 10 15 0.24% 5 10 0.16%
Sem.3 20 35 0.56% 15 25 0.40%
Sem.4 30 65 1.05% 30 55 0.88%
Sem.5 50 115 1.85% 50 105 1.69%
Sem.6 70 185 2.98% 70 175 2.82%
Sem.7 80 265 4.26% 80 255 4.10%
Sem.8 150 415 6.68% 100 355 5.71%
Sem.9 200 615 9.90% 100 455 7.32%
Sem.10 450 1065 17.14% 150 605 9.73%
Sem.11 550 1615 25.99% 300 905 14.56%
Sem.12 750 2365 38.05% 200 1105 17.78%
Sem.13 800 3165 50.93% 1105 17.78%
Sem.14 850 4015 64.60% 1105 17.78%
Sem.15 700 4715 75.86% 1105 17.78%
Sem.16 650 5365 86.32% 1105 17.78%
Sem.17 400 5765 92.76% 1105 17.78%
Sem.18 200 5965 95.98% 1105 17.78%
Sem.19 200 6165 99.20% 1105 17.78%
Sem.20 50 6215 100.00% 1105 17.78%
6215

02. CURVA S DE PROYECTO REPROGRAMADO MISMO PLAZO DE EJECUCION


Saldo a la fecha de reprogramación : 5110 HH

HH PLAN HH REAL
HH
Semana acumulada % Avance HH Real Acumulada % Avance
planificada
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 5 10 0.16% 5 10 0.16%
Sem.3 15 25 0.40% 15 25 0.40%
Sem.4 30 55 0.88% 30 55 0.88%
Sem.5 50 105 1.69% 50 105 1.69%
Sem.6 70 175 2.82% 70 175 2.82%
Sem.7 80 255 4.10% 80 255 4.10%
Sem.8 100 355 5.71% 100 355 5.71%
Sem.9 100 455 7.32% 100 455 7.32%
Sem.10 150 605 9.73% 150 605 9.73%
Sem.11 300 905 14.56% 300 905 14.56%
Sem.12 200 1105 17.78% 200 1105 17.78%
Sem.13 900 2005 32.26% 700 1805 29.04%
Sem.14 1000 3005 48.35% 1805 29.04%
Sem.15 1100 4105 66.05% 1805 29.04%
Sem.16 850 4955 79.73% 1805 29.04%
Sem.17 450 5405 86.97% 1805 29.04%
Sem.18 360 5765 92.76% 1805 29.04%
Sem.19 365 6130 98.63% 1805 29.04%
Sem.20 85 6215 100.00% 1805 29.04%
6215
UN PROYECTO DIFERENTES CURVAS S
ROGRAMACIONES MAYORES METRADOS , AMPLIACIONES DE PLAZ

% Variación SPI (EV/PV) Curva S control y


110.00%
0.00% -
0.00% 1.00 100.00%
0.08% 0.67
0.16% 0.71 90.00%
0.16% 0.85
0.16% 0.91 80.00%
0.16% 0.95
0.16% 0.96 70.00%
0.97% 0.86
2.57% 0.74 60.00%
7.40% 0.57
50.00%
11.42% 0.56
20.27% 0.47
40.00%

30.00%

20.00%

10.00%

0.00%
Sem.0 Sem.1 Sem.2 Sem.3 Sem.4 Sem.5 Sem.6 Sem.7 Sem.8 Sem.9 Sem.1

% Variación SPI (EV/PV) Curva S control y Seguimiento LB Repro


110.00%
0.00% -
0.00% 1.00
100.00%
0.00% 1.00
0.00% 1.00 90.00%
0.00% 1.00
80.00%

70.00%
100.00%

90.00%

0.00% 1.00 80.00%


0.00% 1.00
0.00% 1.00 70.00%
0.00% 1.00
0.00% 1.00 60.00%
0.00% 1.00
0.00% 1.00 50.00%

0.00% 1.00
40.00%
3.22% 0.90

30.00%

20.00%

10.00%

0.00%
Sem.0 Sem.1 Sem.2 Sem.3 Sem.4 Sem.5 Sem.6 Sem.7 Sem.8 Sem.9 Sem.10
NES DE PLAZO , RETIRO DE ALCANCE

Curva S control y Seguimiento

100.00%

38.05%

17.78%

em.7 Sem.8 Sem.9 Sem.10 Sem.11 Sem.12 Sem.13 Sem.14 Sem.15 Sem.16 Sem.17 Sem.18 Sem.19 Sem.20

guimiento LB Reprogramada sin ampliacion de plazo

100.00%
100.00%

32.26%
29.04%

17.78%

em.7 Sem.8 Sem.9 Sem.10 Sem.11 Sem.12 Sem.13 Sem.14 Sem.15 Sem.16 Sem.17 Sem.18 Sem.19 Sem.20
EXPLICANDO GRAFICAMENTE REPROG
01. Proyecto atrasado

HH PLAN HH REAL
HH % Avance
Semana acumulada HH Real Acumulada % Avance real
planificada planificado
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 10 15 0.24% 5 10 0.16%
Sem.3 20 35 0.56% 15 25 0.40%
Sem.4 30 65 1.05% 30 55 0.88%
Sem.5 50 115 1.85% 50 105 1.69%
Sem.6 70 185 2.98% 70 175 2.82%
Sem.7 80 265 4.26% 80 255 4.10%
Sem.8 150 415 6.68% 100 355 5.71%
Sem.9 200 615 9.90% 100 455 7.32%
Sem.10 450 1065 17.14% 150 605 9.73%
Sem.11 550 1615 25.99% 300 905 14.56%
Sem.12 750 2365 38.05% 200 1105 17.78%
Sem.13 800 3165 50.93% 1105 17.78%
Sem.14 850 4015 64.60% 1105 17.78%
Sem.15 700 4715 75.86% 1105 17.78%
Sem.16 650 5365 86.32% 1105 17.78%
Sem.17 400 5765 92.76% 1105 17.78%
Sem.18 200 5965 95.98% 1105 17.78%
Sem.19 200 6165 99.20% 1105 17.78%
Sem.20 50 6215 100.00% 1105 17.78%
6215

02. CURVA S DE PROYECTO REPROGRAMADO CON AMPLIACION DE PLAZO DE EJECUCION


Saldo a la fecha de reprogramación : 5110 HH

HH PLAN HH REAL
HH
Semana acumulada % Avance HH Real Acumulada % Avance
planificada
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 5 10 0.16% 5 10 0.16%
Sem.3 15 25 0.40% 15 25 0.40%
Sem.4 30 55 0.88% 30 55 0.88%
Sem.5 50 105 1.69% 50 105 1.69%
Sem.6 70 175 2.82% 70 175 2.82%
Sem.7 80 255 4.10% 80 255 4.10%
Sem.8 100 355 5.71% 100 355 5.71%
Sem.9 100 455 7.32% 100 455 7.32%
Sem.10 150 605 9.73% 150 605 9.73%
Sem.11 300 905 14.56% 300 905 14.56%
Sem.12 200 1105 17.78% 200 1105 17.78%
Sem.13 300 1405 22.61% 150 1255 20.19%
Sem.14 405 1810 29.12% 1255 20.19%
Sem.15 400 2210 35.56% 1255 20.19%
Sem.16 380 2590 41.67% 1255 20.19%
Sem.17 450 3040 48.91% 1255 20.19%
Sem.18 325 3365 54.14% 1255 20.19%
Sem.19 330 3695 59.45% 1255 20.19%
Sem.20 420 4115 66.21% 1255 20.19%
Sem.21 400 4515 72.65% 1255 20.19%
Sem.22 410 4925 79.24% 1255 20.19%
Sem.23 390 5315 85.52% 1255 20.19%
Sem.24 395 5710 91.87% 1255 20.19%
Sem.25 180 5890 94.77% 1255 20.19%
Sem.26 140 6030 97.02% 1255 20.19%
Sem.27 130 6160 99.12% 1255 20.19%
Sem.28 55 6215 100.00% 1255 20.19%
6215
UN PROYECTO DIFERENTES CURVAS S
NTE REPROGRAMACIONES MAYORES METRADOS , AMPLIACIONES

% Variación SPI (EV/PV) Cur


110.00%
0.00% -
0.00% 1.00 100.00%
0.08% 0.67
0.16% 0.71 90.00%
0.16% 0.85
0.16% 0.91 80.00%
0.16% 0.95
0.16% 0.96 70.00%
0.97% 0.86
2.57% 0.74 60.00%
7.40% 0.57
11.42% 0.56 50.00%

20.27% 0.47
40.00%

30.00%

20.00%

10.00%

0.00%
Sem.0 Sem.1 Sem.2 Sem.3 Sem.4 Sem.5 Sem.6 Sem.7 Sem

% Variación SPI (EV/PV) Curva S control y Seguim


110.00%
0.00% -
0.00% 1.00
0.00% 1.00 100.00%
0.00% 1.00
0.00% 1.00 90.00%

80.00%
100.00%

90.00%
0.00% 1.00
0.00% 1.00
80.00%
0.00% 1.00
0.00% 1.00
0.00% 1.00 70.00%
0.00% 1.00
0.00% 1.00
60.00%
0.00% 1.00
2.41% 0.89
50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
.0 .1 .2 .3 .4 .5 .6 .7 .8 .9 .1
0
.1
1
m m m m m m m m m m
S e Se Se Se Se Se Se Se Se Se S em S em
AS S
PLIACIONES DE PLAZO , RETIRO DE ALCANCE

Curva S control y Seguimiento

100.00%

38.05%

17.78%

Sem.6 Sem.7 Sem.8 Sem.9 Sem.10 Sem.11 Sem.12 Sem.13 Sem.14 Sem.15 Sem.16 Sem.17 Sem.18 Sem.19 Sem.20

S control y Seguimiento LB reprogramada con ampliacion de plazo

100.00%
100.00%
100.00%
100.00%

22.61%
20.19%
17.78%

.8 .9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8
m m .1 .1 .1 .1 .1 .1 .1 .1 .1 .1 .2 .2 .2 .2 .2 .2 .2 .2 .2
Se Se S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em
100.00%

m.18 Sem.19 Sem.20

100.00%
100.00%

25 .2
6
.2
7
.2
8
S em S em S em
EXPLICANDO GRAFICAMENTE R
01. Proyecto atrasado

HH PLAN HH REAL
HH % Avance
Semana acumulada HH Real Acumulada % Avance real
planificada planificado
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 10 15 0.24% 5 10 0.16%
Sem.3 20 35 0.56% 15 25 0.40%
Sem.4 30 65 1.05% 30 55 0.88%
Sem.5 50 115 1.85% 50 105 1.69%
Sem.6 70 185 2.98% 70 175 2.82%
Sem.7 80 265 4.26% 80 255 4.10%
Sem.8 150 415 6.68% 100 355 5.71%
Sem.9 200 615 9.90% 100 455 7.32%
Sem.10 450 1065 17.14% 150 605 9.73%
Sem.11 550 1615 25.99% 300 905 14.56%
Sem.12 750 2365 38.05% 200 1105 17.78%
Sem.13 800 3165 50.93% 1105 17.78%
Sem.14 850 4015 64.60% 1105 17.78%
Sem.15 700 4715 75.86% 1105 17.78%
Sem.16 650 5365 86.32% 1105 17.78%
Sem.17 400 5765 92.76% 1105 17.78%
Sem.18 200 5965 95.98% 1105 17.78%
Sem.19 200 6165 99.20% 1105 17.78%
Sem.20 50 6215 100.00% 1105 17.78%
6215

02. CURVA S DE PROYECTO REPROGRAMADO CON AMPLIACION DE PLAZO DE EJECUCION


Saldo a la fecha de reprogramación : 5110 HH
Mayor metrado 1450 HH

HH PLAN HH REAL
HH
Semana acumulada % Avance HH Real Acumulada % Avance
planificada
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 5 10 0.16% 5 10 0.16%
Sem.3 15 25 0.40% 15 25 0.40%
Sem.4 30 55 0.88% 30 55 0.88%
Sem.5 50 105 1.69% 50 105 1.69%
Sem.6 70 175 2.82% 70 175 2.82%
Sem.7 80 255 4.10% 80 255 4.10%
Sem.8 100 355 5.71% 100 355 5.71%
Sem.9 100 455 7.32% 100 455 7.32%
Sem.10 150 605 9.73% 150 605 9.73%
Sem.11 300 905 14.56% 300 905 14.56%
Sem.12 200 1105 17.78% 200 1105 17.78%
Sem.12 0 1105 14.42% 0 1105 14.42%
Sem.13 700 1805 23.55% 400 1505 19.63%
Sem.14 800 2605 33.99% 1505 19.63%
Sem.15 900 3505 45.73% 1505 19.63%
Sem.16 750 4255 55.51% 1505 19.63%
Sem.17 450 4705 61.38% 1505 19.63%
Sem.18 550 5255 68.56% 1505 19.63%
Sem.19 580 5835 76.13% 1505 19.63%
Sem.20 600 6435 83.95% 1505 19.63%
Sem.21 335 6770 88.32% 1505 19.63%
Sem.22 200 6970 90.93% 1505 19.63%
Sem.23 205 7175 93.61% 1505 19.63%
Sem.24 170 7345 95.83% 1505 19.63%
Sem.25 140 7485 97.65% 1505 19.63%
Sem.26 130 7615 99.35% 1505 19.63%
Sem.27 40 7655 99.87% 1505 19.63%
Sem.28 10 7665 100.00% 1505 19.63%
7665
UN PROYECTO DIFERENTES CURVAS S
CAMENTE REPROGRAMACIONES MAYORES METRADOS , AMPLIAC

% Variación SPI (EV/PV)

110.00%
0.00% -
0.00% 1.00 100.00%
0.08% 0.67
0.16% 0.71 90.00%
0.16% 0.85
0.16% 0.91 80.00%
0.16% 0.95
0.16% 0.96 70.00%
0.97% 0.86
2.57% 0.74 60.00%
7.40% 0.57
11.42% 0.56 50.00%

20.27% 0.47
40.00%

30.00%

20.00%

10.00%

0.00%
Sem.0 Sem.1 Sem.2 Sem.3 Sem.4 Sem.5 Sem.6 Sem

7665

% Variación SPI (EV/PV) Curva S control y


0.00% - 110.00%

0.00% 1.00
0.00% 1.00
0.00% 1.00 100.00%

90.00%
110.00%

100.00%

0.00% 1.00
0.00% 1.00
90.00%
0.00% 1.00
0.00% 1.00
0.00% 1.00
80.00%
0.00% 1.00
0.00% 1.00
0.00% 1.00
70.00%
0.00% 1.00
0.00% 1.00
3.91% 0.83
60.00%

50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
.0 .1 .2 .3 .4 .5 .6 .7 .8 .9
m m m m m m m m m m
Se Se Se Se Se Se Se Se Se Se Se
m
CURVAS S
OS , AMPLIACIONES DE PLAZO , RETIRO DE ALCANCE

Curva S control y Seguimiento

38.05%

17.78%

Sem.5 Sem.6 Sem.7 Sem.8 Sem.9 Sem.10 Sem.11 Sem.12 Sem.13 Sem.14 Sem.15 Sem.16 Sem.17 Sem.18

Curva S control y Seguimiento LB REPROGRAMADA POR MAYOR METRADO

100.00%
100.00%

38.05%

23.55%
19.63%
14.41%
17.78 %

.7 .8 .9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5
m m m .1 .1 .1 .1 .1 .1 .1 .1 .1 .1 .2 .2 .2 .2 .2 .2
Se Se Se m m m m m m m m m m m m m m m m
Se Se Se Se Se Se Se Se Se Se Se Se Se Se Se Se S
100.00%

Sem.16 Sem.17 Sem.18 Sem.19 Sem.20

100.00%
100.00%

2 3 4 5 6 7 8
.2 .2 .2 .2 .2 .2 .2
m m m m m m m
Se Se Se Se Se Se
EXPLICANDO GRAFICAMENTE REPR
01. Proyecto atrasado

HH PLAN HH REAL
HH % Avance
Semana acumulada HH Real Acumulada % Avance real
planificada planificado
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 10 15 0.24% 5 10 0.16%
Sem.3 20 35 0.56% 15 25 0.40%
Sem.4 30 65 1.05% 30 55 0.88%
Sem.5 50 115 1.85% 50 105 1.69%
Sem.6 70 185 2.98% 70 175 2.82%
Sem.7 80 265 4.26% 80 255 4.10%
Sem.8 150 415 6.68% 100 355 5.71%
Sem.9 200 615 9.90% 100 455 7.32%
Sem.10 450 1065 17.14% 150 605 9.73%
Sem.11 550 1615 25.99% 300 905 14.56%
Sem.12 750 2365 38.05% 200 1105 17.78%
Sem.13 800 3165 50.93% 1105 17.78%
Sem.14 850 4015 64.60% 1105 17.78%
Sem.15 700 4715 75.86% 1105 17.78%
Sem.16 650 5365 86.32% 1105 17.78%
Sem.17 400 5765 92.76% 1105 17.78%
Sem.18 200 5965 95.98% 1105 17.78%
Sem.19 200 6165 99.20% 1105 17.78%
Sem.20 50 6215 100.00% 1105 17.78%
6215

02. CURVA S DE PROYECTO REPROGRAMADO CON AMPLIACION DE PLAZO DE EJECUCION


Saldo a la fecha de reprogramación : 4310 HH
Menor metrado 800 HH

HH PLAN HH REAL
HH
Semana acumulada % Avance HH Real Acumulada % Avance
planificada
(PV) (EV)
Sem.0 0 0 0.00% 0 0 0.00%
Sem.1 5 5 0.08% 5 5 0.08%
Sem.2 5 10 0.16% 5 10 0.16%
Sem.3 15 25 0.40% 15 25 0.40%
Sem.4 30 55 0.88% 30 55 0.88%
Sem.5 50 105 1.69% 50 105 1.69%
Sem.6 70 175 2.82% 70 175 2.82%
Sem.7 80 255 4.10% 80 255 4.10%
Sem.8 100 355 5.71% 100 355 5.71%
Sem.9 100 455 7.32% 100 455 7.32%
Sem.10 150 605 9.73% 150 605 9.73%
Sem.11 300 905 14.56% 300 905 14.56%
Sem.12 200 1105 17.78% 200 1105 17.78%
Sem.12 0 1105 20.41% 0 1105 20.41%
Sem.13 405 1510 27.89% 300 1405 25.95%
Sem.14 400 1910 35.27% 1405 25.95%
Sem.15 380 2290 42.29% 1405 25.95%
Sem.16 450 2740 50.60% 1405 25.95%
Sem.17 325 3065 56.60% 1405 25.95%
Sem.18 330 3395 62.70% 1405 25.95%
Sem.19 420 3815 70.45% 1405 25.95%
Sem.20 400 4215 77.84% 1405 25.95%
Sem.21 300 4515 83.38% 1405 25.95%
Sem.22 200 4715 87.07% 1405 25.95%
Sem.23 205 4920 90.86% 1405 25.95%
Sem.24 170 5090 94.00% 1405 25.95%
Sem.25 140 5230 96.58% 1405 25.95%
Sem.26 130 5360 98.98% 1405 25.95%
Sem.27 45 5405 99.82% 1405 25.95%
Sem.28 10 5415 100.00% 1405 25.95%
5415
UN PROYECTO DIFERENTES CURVAS S
MENTE REPROGRAMACIONES MAYORES METRADOS , AMPLIACION

% Variación SPI (EV/PV)

110.00%
0.00% -
0.00% 1.00 100.00%
0.08% 0.67
0.16% 0.71 90.00%
0.16% 0.85
0.16% 0.91 80.00%
0.16% 0.95
0.16% 0.96 70.00%
0.97% 0.86
2.57% 0.74 60.00%

7.40% 0.57
50.00%
11.42% 0.56
20.27% 0.47
40.00%

30.00%

20.00%

10.00%

0.00%
Sem.0 Sem.1 Sem.2 Sem.3 Sem.4 Sem.5 Sem.6 Sem.7

% Variación SPI (EV/PV) Curva S control y


110.00%
0.00% -
0.00% 1.00
0.00% 1.00 100.00%
0.00% 1.00

90.00%

80.00%
100.00%

0.00% 1.00
90.00%
0.00% 1.00
0.00% 1.00
0.00% 1.00 80.00%
0.00% 1.00
0.00% 1.00
70.00%
0.00% 1.00
0.00% 1.00
0.00% 1.00 60.00%
0.00% 1.00
1.94% 0.93
50.00%

40.00%

30.00%

20.00%

10.00%

0.00%
.0 .1 .2 .3 .4 .5 .6 .7 .8 .9 .1
0
m m m m m m m m m m
S e Se Se Se Se Se Se Se Se Se S em
RVAS S
AMPLIACIONES DE PLAZO , RETIRO DE ALCANCE

Curva S control y Seguimiento

38.05%

17.78%

em.5 Sem.6 Sem.7 Sem.8 Sem.9 Sem.10 Sem.11 Sem.12 Sem.13 Sem.14 Sem.15 Sem.16 Sem.17 Sem.18 Sem.19

Curva S control y Seguimiento LB reprogramada por menor metrado

100.00%
100.00%

27.89%
25.95%
20.41%
17.78%

.7 .8 .9 .1
0
.1
1
.1
2
.1
3
.1
4
.1
5
.1
6
.1
7
.1
8
.1
9
.2
0
.2
1
.2
2
.2
3
.2
4
.2
5
.2
6
.2
7
m m m
Se Se S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em S em
100.00%

Sem.17 Sem.18 Sem.19 Sem.20

100.00%
100.00%

4 5 6 7 8
.2 .2 .2 .2 .2
S em S em S em S em S em