Activity Activity Orig Rem % Predecessors Cal Early Early JAN

2 3 4 5 6 7 8 9
ID Description Dur Dur ID Start Finish 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0
Heat Exchanger Cleaning and Inspection
Pre-Shutdown Work
Subtotal 4 4 0 1 03JAN11 03JAN11
08:00 11:59

HE10 Scaffold erection 4 4 0 1 03JAN11 03JAN11 Scaffold erection


08:00 11:59

Shutdown Work
Subtotal 52 52 0 2 04JAN11 06JAN11
09:00 12:59

Piping
HE20 Remove insulation for blinding work 2 2 0 HE10* 2 04JAN11 04JAN11 Remove insulation for blinding work
09:00 10:59
HE30 Isolate line, drain & purge system 2 2 0 HE20* 2 04JAN11 04JAN11 Isolate line, drain & purge system
11:00 12:59
HE40 Blinding 4 4 0 HE30* 2 04JAN11 04JAN11 Blinding
13:00 16:59
HE50 Remove channel spls & shell side 1 1 0 HE40* 2 04JAN11 04JAN11 Remove channel spls & shell side spls
spls 17:00 17:59
HE220 Reinstate pipe spools 1 1 0 HE210* 2 06JAN11 06JAN11 Reinstate pipe spools
00:00 00:59
HE230 De-blinding and sign off flange check 4 4 0 HE250* 2 06JAN11 06JAN11 De-blinding and sign off flange check list
list 05:00 08:59
HE240 Conduct the overall tightness test 2 2 0 HE230* 2 06JAN11 06JAN11 Conduct the overall tightness test (OATT)
(OATT) 09:00 10:59
HE260 Reinstate piping insulation 2 2 0 HE240* 2 06JAN11 06JAN11 Reinstate piping insulation
11:00 12:59

Mechanical
HE60 Remove channel cover, channel head 2 2 0 HE50* 2 04JAN11 04JAN11 Remove channel cover, channel head
18:00 19:59
HE70 Remove shell cover, floating head 2 2 0 HE60* 2 04JAN11 04JAN11 Remove shell cover, floating head
20:00 21:59
HE110 Dis-assemble backing device 1 1 0 HE70* 2 04JAN11 04JAN11 Dis-assemble backing device
22:00 22:59
HE80 Pull out tube bundle 1 1 0 HE110* 2 04JAN11 04JAN11 Pull out tube bundle
23:00 23:59
HE120 Shell side internal cleaning at site 2 2 0 HE80* 2 05JAN11 05JAN11 Shell side internal cleaning at site
00:00 01:59
HE90 Send to cleaning yart at site 1 1 0 HE80* 2 05JAN11 05JAN11 Send to cleaning yart at site
00:00 00:59

Start Date 02JAN11 00:00 HESD Sheet 1 of 2


Early Bar
Finish Date 06JAN11 13:59 Date Revision Checked Approved
Float Bar
Data Date 03JAN11 08:00
Run Date 02JAN11 17:34 Progress Bar
Shell & Tue HE cleaning/Inspection
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Rem % Predecessors Cal Early Early JAN
2 3 4 5 6 7 8 9
ID Description Dur Dur ID Start Finish 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0
Mechanical
HE160 Send tube bundle back to site 1 1 0 HE150* 2 05JAN11 05JAN11 Send tube bundle back to site
09:00 09:59
HE170 Reinstate tube bundle 2 2 0 HE130, 2 05JAN11 05JAN11 Reinstate tube bundle
HE160* 10:00 11:59
HE180 Reinstate CH head, channel cover, 2 2 0 HE170* 2 05JAN11 05JAN11 Reinstate CH head, channel cover, backing device
backing device 12:00 13:59
HE200 Install floating head, shell cover 2 2 0 HE190* 2 05JAN11 05JAN11 Install floating head, shell cover
18:00 19:59
HE250 Bolt Torqueing on Shell & Tue side 4 4 0 HE220* 2 06JAN11 06JAN11 Bolt Torqueing on Shell & Tue side flanges
flanges 01:00 04:59

Inspection
HE100 Cleaning tube bundle by hydrojecting 4 4 0 HE90* 2 05JAN11 05JAN11 Cleaning tube bundle by hydrojecting
01:00 04:59
HE130 Shell side visual inspection 1 1 0 HE120* 2 05JAN11 05JAN11 Shell side visual inspection
02:00 02:59
HE140 IRIS inspection on tubes 2 2 0 HE100* 2 05JAN11 05JAN11 IRIS inspection on tubes
05:00 06:59
HE150 Repair tubes (if found damages) 2 2 0 HE140* 2 05JAN11 05JAN11 Repair tubes (if found damages)
07:00 08:59
HE190 Perform tube side leak test 4 4 0 HE180* 2 05JAN11 05JAN11 Perform tube side leak test
14:00 17:59
HE210 Conduct shell side leak test 4 4 0 HE200* 2 05JAN11 05JAN11 Conduct shell side leak test
20:00 23:59

Post-Shutdown Work
Subtotal 1 1 0 1 06JAN11 06JAN11
13:00 13:59

HE270 Dismantle Scaffold & House keeping 1 1 0 HE260* 1 06JAN11 06JAN11 Dismantle Scaffold & House keeping
13:00 13:59

Start Date 02JAN11 00:00 HESD Sheet 2 of 2


Early Bar
Finish Date 06JAN11 13:59 Date Revision Checked Approved
Float Bar
Data Date 03JAN11 08:00
Run Date 02JAN11 17:34 Progress Bar
Shell & Tue HE cleaning/Inspection
Critical Activity

Classic Schedule Layout