Escolar Documentos
Profissional Documentos
Cultura Documentos
!"
!"#$% &'&()% *#$+,$$($% '-*% #..,$/)'/($% /01% '2'#.'3.(%
&,3.#$"(*% /($/% $4$/(5$% 61)% )(.#'3#.#/4% '-*% '*(7,'+4%
(2'.,'81-% 16% (.(+/)#+% &10()% $4$/(5$9% !"(4% ')(% /"(%
:;!<=>>?*(2(.1&(*%'/%/"(%@-#2()$#/4%16%<'$A'/+"(0'-%
'-*% /"(% BCCCD:!<=>E?*(2(.1&(*% 34% /"(% BCCCDFC<%
G&&.#+'81-% 16% F)13'3#.#/4% H(/"1*$% <,3+155#I((9%
!"(% &'&()% #..,$/)'/($% /"(% 3'$#+% $4$/(5% +1-JK,)'81-$%
'-*% $15(% 16% /"(% &,3.#$"(*% *'/'% ,$(*% /1% +1-*,+/%
)(.#'3#.#/4%'-*%'*(7,'+4%$/,*#($%1-%/"($(%$4$/(5$9%
Introduction
#"
<#-K.(%.#-(%*#'K)'5%16%/"(%:;!<
$"
Introduction
The IEEE-RTS is a 24 bus system with 10
generator buses, 17 load buses, 33
transmission lines, 5 transformers and 32
generating units. The total installed capacity is
3405 MW and the system peak load is 2850 MW.
The IEEE-RTS was developed by a Task Force
of the Application of Probability Methods
Subcommittee of the IEEE Power System
Engineering Committee. It was developed to
satisfy the need for a standard database to test
and compare results from different power
system reliability evaluation methodologies.%%
%"
<#-K.(%.#-(%*#'K)'5%16%/"(%BCCCD:!<
&"
B-/)1*,+81-%
'"
Introduction
Hierarchical levels
("
RBTS Data
• Generation Data
)"
RBTS Data
*"
RBTS-Generation Data
Reference 11 includes the relevant cost data on
each generating unit including fuel costs,
operating costs and capital costs. Two loading
orders are provided. The first loading order is
on a purely economic basis, in which the hydro
units are loaded before the thermal units, due
to their low operating costs. The second
loading order allocates some hydro units as
peaking capacity, which could reflect limited
energy considerations.
+!"
RBTS-Generation Data
++"
RBTS-Transmission Data
+#"
RBTS-Transmission Data
The basic transmission outage data for the system in
Fig. 1 is augmented in [11] by providing the necessary
impedance, susceptance and current rating data to
conduct AC load flow studies. Load bus data is
provided in the form of peak load MW and MVAr values.
Reference 11 suggests that the load at each bus should
be classified in the two categories of firm load and
curtailable load and that in the case of a relevant
system problem, curtailable load should be curtailed
first followed by curtailment of firm load if necessary.
+$"
Single line diagram of the RBTS
+%"
Extended single line
diagram of the RBTS
+&"
RBTS-Distribution Data
+*"
IEEE-RTS Data
#!"
IEEE-RTS Data
#+"
IEEE-RTS Data
The Generating Unit Reliability Data for
the IEEE-RTS
##"
<#-K.(%.#-(%*#'K)'5%16%/"(%BCCCD:!<
#$"
IEEE-RTS Data
The Generating Unit Reliability Data for
the IEEE-RTS
#%"
IEEE-RTS Data
#&"
IEEE-RTS Data
#'"
IEEE-RTS Data
#("
IEEE-RTS Data
#)"
IEEE-RTS Data
#*"
IEEE-RTS Data
$!"
IEEE-RTS Data
The RTS-79 transmission system was enhanced by
including a phase shifter, a two terminal DC
transmission line and five inter-area ties. The
transmission branch data for each area is described in
tabular form. A DC interconnection between Area A and
B is proposed based on a procedure and data
presented in [18].
Figure 8 shows a single line diagram of the One Area
RTS-96 including substations. The relevant circuit
breaker failure data are given in [17]. Figure 8 was
originally published in [19].
<#-K.(%.#-(%*#'K)'5%16%/"(%BCCCD:!<
$#"
Single line diagram of the IEEE One Area RTS-96
$$"
with substations
IEEE-RTS Data
$%"
IEEE-RTS Data
$&"
IEEE-RTS Data
$'"
Conclusion
This paper presents a general overview of the RBTS
and the IEEE-RTS, and a brief summary of the
evolution of these test systems. The paper does not
attempt to provide a compilation of the test systems
data contained in the references. As noted in the
paper, the IEEE Reliability Test System Task Force was
motivated to expand and enhance the IEEE-RTS in
1996 by the changes that had occurred in the electric
utility industry. Considerable changes have occurred
since 1996, which suggests that both the RBTS and the
IEEE-RTS should be studied and enhanced to include
data that would allow these changes to be incorporated
and applied in basic electric power system reliability
assessment.
$("