COMPLETION OF BALANCE WORK & COMISSIONING OF SEWARAGE SUMP Such as (1)

INTERNAL & EXTERNAL ELECTRIFICATION (II) INSTALATION OF PUMP & MOTOR ETC
AT 4-R & 5-R STAFF QUARTER, M.K.C.G. MEDICAL, BERHAMPUR.[ 13 - 2215 :
Maintenance of Urban Ewarage system ( N.P.) ]

[A] INTERNAL & EXTERNAL ELECTRIFICATION :

[1] 100Amp T.P.N Main switch ( Sunder ) = 1 nos.


at the rate Rs. 4500.00 per each. = Rs. 4,500.00
32Amp Main DP switch( Sunder ) = 1 nos.
at the rate Rs. 860.00 per each. = Rs. 860.00
100Amp Kit-Cat switch( Sunder ) = 3 nos.
at the rate Rs. 330.00 per each. = Rs. 990.00
100Amp Bus bar ( Sunder ) = 1 nos.
at the rate Rs. 1975.00 per set. = Rs. 1,975.00
Earthing = 2 nos.
at the rate Rs. 1700.00 per each. = Rs. 3,400.00
3 x ½ core Armod cable = 30.0 mtr.
at the rate Rs. 365.00 per mtr. = Rs. 10,950.00
320 copper wire( Finolex ) = 60.0 mtr.
at the rate Rs. 250.00 per mtr. = Rs. 15,000.00
716 copper wire( Rico ) = 20.0 mtr.
at the rate Rs. 85.00 per mtr. = Rs. 1,700.00
Kit-Cat Clamp = 1 nos.
at the rate Rs. 700.00 per each. = Rs. 700.00
T.P.N Clamp = 1 nos.
at the rate Rs. 700.00 per each. = Rs. 700.00
Bus Bar Clamp = 1 nos.
at the rate Rs. 700.00 per each. = Rs. 700.00
Rs. 41475.00
Add 12% Labour charges = Rs. 4977.00

[ 2 ] Provision for Security deposite, Processing fees & Inspection


charges for 3 phase line to South-co. L.S. Rs. 20000.00
66,452.00
[ B ] INSTALATION OF PUMP & MOTOR :

1
Supplying all materials, labour and T&P for fittng and fixing of 3 phase
vertical open well 7.50 H.P. Submerssible Pump and motor( Any reputed
make ) for discharge of solid soft fibre PH value -7.5 and temperature -
ABIENT at head10 / 12.0mtr. and discharge 1250 / 860 LPM-Suction dia for
solid-80mm and delivery is 100mm , etc all complete as per direction of
Engineer-in-charge.
= 1 nos. @ Rs. 90000.00 per each = Rs. 90,000.00

2
Supplying all materials, labour and T&P for fitting of suitable Panel board for
7.50 HP vertical sewage lifting Pumpset with single phase preventor, inside
cought-out , Volt meter , Ampere meter, Three phase indicator lamp etc all
complete as per the specification and direction of Engineer-in-charge
i.] Pump set = 1 nos. @ Rs. 20000.00 per each = Rs. 20,000.00
ii.] 10mm² 3 core copper flat cable( ISI Marked ) = 30.0 mtr.
at the rate Rs. 413.10 per mtr. = Rs. 12,393.00
3 Supplying all materials,labour and T&P for Lowering of Open well pump set
into the sump, providing suction & delivery line including all cost,
conveyance and taxes of G.I. pipe & P.V.C. pipe 6mm 3 core copper flat
cable all fitting etc all complete.
1.] 100mm.φ G.I. flange pipe [medium class ]= 20 mtr.
at the rate Rs. 876.00 per mtr. = Rs. 17,520.00
2.] 100 mm dia G.I. socket ( ISI ) = 1 Nos
at the rate Rs. 800.00 per each. = Rs. 800.00
3.] 100mm. x 90° dia. G.I. flange bend ( ISI ) = 2 nos.
at the rate Rs. 1200.00 per each = Rs. 2,400.00
[C] CONSTRUCTION OF APPROACH ROAD :

1 Supplying all labour and T&P for earth work in all kinds of soil within 50mtr
initial lead and 1.5mtr initial lift including rough dressing and breaking of
clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3mtr in
depth as per direction of Engineer-in-charge.
2 x 1.30 x 0.60 x 1.25mtr. = 1.95 cum.
@ Rs. 5626.40 per % cum= Rs 110.00

2 Supplying all materials , labour and T&P and providing C.C (1:4:8) using 40
mm bhg metal including watering for curing, cost and conveyance, taxes and
royalities etc. all complete as per direction of Er-in-charge.
2 x 1.30 x 0.60 x 0.15mtr. = 0.23 cum.
@ Rs. 2384.60 per cum. = Rs 548.00

3 Supplying all materials , labour and T&P for providing 0.10m thick R.C.C
work in roof slab with C.C. ( 1:2:4 ) using 12 mm size b.h.g. chips with cost,
conveyance & royalty etc. complete including watering and curing with
proper centering & shuttering and false work, laying & hoisting, dismentalling
the false work after completion, site cleaning & disposal of debris to suitable
place away from locality complete as per direction of Engineer-in-charge.

i] In roofslab = 1 x 7.0 x 1.20 x 0.15 mtr. = 1.26 cum.


ii] Pillar = 2nos x 1.20 x 0.30 x 1.0 mtr. = 0.72 cum.
1.98 cum.
@ Rs. 3580.40
per cum.=Rs. 7,089.00

4 Supplying all materials, labour and T&P for providing timber centering and
shuttering as per direction of Engineer-in-charge.
i] Roof slab = 1 no x 7.0 x 1.20 mtr. = 8.40 sqm
@ Rs. 221.30
per cum.=Rs. 1,859.00

ii] Beam = 2 x 2 x 1.20 x 1.0 mtr. = 4.80 sqm


2 x 2 x 1.0 x 0.30 mtr. = 1.20 sqm
6.00 sqm
@ Rs. 302.10
per cum.=Rs. 1,813.00

5 Supplying all materials , labour and T&P for providing M.S. Reinforcement
for R.C.C. works including cutting, bending, binding and tying the grills and
placing in position including cost of M.S. rod , binding wire 18 to 20 gauge,
all complete as per direction of Engineer-in-charge.
Qnty. = at the rate of 0.90 Qntl. / cum of R.C.C.
i.e. 1.98 cum x 0.90 Q = 1.78 qntl.
@ Rs. 4801.20
per cum.=Rs. 8,556.00
[ D ] RENOVATION OF FOUL SEWER LINE

1
Supplying all materials,labour and T&P for laying in trenches unplasticized
PVC pipes and specials of the following outside dia. for all classes including
jointing with approved solvent cement by non-heat application method
including testing as per specification and direction of Engineer-in-charge etc.
all complete. [excluding earth work and cost of pipes and fittings] [per mtr.]
i.] Laying of 160 mm. dia. PVC pipe = 25.0 Mtr
at the rate Rs. 662.90
per cum.=Rs. 16,573.00

2
Supplying all materials,labour and T&P for constructing Man-hole chamber
with R.C.C. top slab in (1:1.5:3 ) mix with foundation concrete (1:2:4 ) inside
plaster 12mm. thick with cement mortar (1:3) finished with neat cement
punning, 12mm. thick out side plaster (1:3),brick work with K.B. bricks with
crushing strength not less than 75kg/sqcm. in cement mortar (1:3) finished
smooth complete as per specification. [IS-4111(part-1) 1967.] (excluding
earth work )
i.] Rectangular Man-hole size (0.90x0.90x0.90 mtr ) type-B =
6 nos. at the rate Rs. 7156.20 per each = Rs. 42,937.00
Extra for every additional depth of 0.10mtr. or part there of Man-hole size
ii.] (0.90x0.90x0.90mtr) from 0.90mtr to 1.65mtr depth.[data for 0.10mtr.]

Additionsl depth of Man-hole = 12 nos.


at the rate Rs. 358.10 per each = Rs. 4,297.00

293,347.00

Add 1% contingency = Rs. 2933.00


Add 1% Labour Cess = Rs. 2933.00
Rs. 299,213.00

Or say Rs. 299,200.00

Junior Engineer Assistant Engineer, Executive Engineer,


P.H.Section No-I, M.K.C.G. P.H.Sub-Division No-I, P.H.Division,Berhampur.
Medical Campus,Berhampur. Berhampur.
i.] 110mm. dia. [O.D.] PVC. Pipe ( 6kg / cm² ) = 40.00 mtr.
at the rate Rs. 439.30 per mtr. = Rs. 17,572.00
145113
COMPLETION F BALANCE WORK & COMISSIONING OF SEWARAGE SUMP Ssuch as (1)
INTERNAL & EXTERNAL ELECTRIFICATION (II) INSTALATION OF PUMP & MOTOR ETC AT 4-
R & 5-R STAFF QUARTER, M.K.C.G. MEDICAL, BERHAMPUR.[ 13 - 2215 : Maintenance of Urb
an Ewarage system ( N.P.) ]

[B] INSTALATION OF PUMP & MOTOR :

1
Supplying all materials, labour and T&P for fittng and fixing of 3 phase vertical
open well 7.50 H.P. Submerssible Pump and motor( Any reputed make ) for
discharge of solid soft fibre PH value -7.5 and temperature - ABIENT at
head10 / 12.0mtr. and discharge 1250 / 860 LPM-Suction dia for solid-80mm
and delivery is 100mm , etc all complete as per direction of Engineer-in-charge.
= 1 nos. @ Rs. 90000.00 per each = Rs. 90,000.00

2
Supplying all materials, labour and T&P for fitting of suitable Panel board for
7.50 HP vertical sewage lifting Pumpset with single phase preventor, inside
cought-out , Volt meter , Ampere meter, Three phase indicator lamp etc all
complete as per the specification and direction of Engineer-in-charge
i.] Pump set = 1 nos. @ Rs. 20000.00 per each = Rs. 20,000.00
ii.] 10mm² 3 core copper flat cable( ISI Marked ) = 30.0 mtr.
at the rate Rs. 413.10 per mtr. = Rs. 12,393.00
Supplying all materials,labour and T&P for Lowering of Open well pump set into
3 the sump, providing suction & delivery line including all cost, conveyance and
taxes of G.I. pipe & P.V.C. pipe 6mm 3 core copper flat cable all fitting etc all
complete.
1.] 100mm.φ G.I. flange pipe [medium class ]= 20 mtr.
at the rate Rs. 876.00 per mtr. = Rs. 17,520.00
2.] 100 mm dia G.I. socket ( ISI ) = 2 Nos
at the rate Rs. 800.00 per each. = Rs. 1,600.00
3.] 100mm. x 90° dia. G.I. flange bend ( ISI ) = 2 nos.
at the rate Rs. 1800.00 per each = Rs. 3,600.00

Rs. 145113.00
66,452.00
145113.00
211,565.00
19975

231,540.00

55434

286,974.00

5739.48

292,713.48
REPORT

This estimate has been framed by the Executive Engineer.Berhampur P.H.Division,


Berhampur to meet the probable expenditure for the work " COMPLETION F BALANCE WORK &
COMISSIONING OF SEWARAGE SUMP Ssuch as (1) INTERNAL & EXTERNAL ELECTRIFICATION
(II) INSTALATION OF PUMP & MOTOR ETC AT 4-R & 5-R STAFF QUARTER, M.K.C.G. MEDICAL,
BERHAMPUR.[ 13 - 2215 : Maintenance of Urb an Ewarage system ( N.P.) ]

The Sewarage system for 4-R and 5-R Staff Quarter of M.K.C.G. Medical College campus
is not functioning properly as there is no pumping system from Sewarage sump as a result all the Man-
holts are getting chock frequently , for which staffs including the boardings are suffering a lot &
environment becomes unhealthy and unhygienic..In order to prevent such problems the pumping of
sewarage water from sump is urgently required.

In this estimate following provisions are kept. :

1.] Provision for external & Internal electrification

2.] Provision for external & Internal electrification

3.] Laying of 160 mm. dia. PVC pipe = 25.0 mtr.

4.] Rectangular Man-hole size (0.90x0.90x0.90 mtr ) type-B = 6 Nos.

ESTIMATED COST:-

The cost estimate stands at Rs. 300,000.00 Lakh. including 1% contigency

and 1% labour Cess charges. While framing this estimate current schedule of rates, DGS & D/EPM
rates and local market prices have been taken into account.

SPECIFICATION:-

During execution of the above work the P.W.D./P.H. and I.S. specification will be strictly
followed.

TIME SCHEDULE:-

It is proposed to complete the work within 30 working days provided funds and materials
are available in time.

Junior Engineer, Assistant Engineer, Executive Engineer,


P.H.Section No.I, M.K.C.G P.H.Sub-Division No-I, Public Health Division,
Medical Campus, Berhampur. Berhampur. Berhampur.
COMPLETION F BALANCE WORK & COMISSIONING OF SEWARAGE SUMP Ssuch as
(1) INTERNAL & EXTERNAL ELECTRIFICATION (II) INSTALATION OF PUMP & MOTOR
ETC AT 4-R & 5-R STAFF QUARTER, M.K.C.G. MEDICAL, BERHAMPUR.[ 13 - 2215 :
Maintenance of Urb an Ewarage system ( N.P.) ]

1 Supplying all labour and T&P for earth work in all kinds of soil within 50mtr
initial lead and 1.5mtr initial lift including rough dressing and breaking of
clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3mtr
in depth as per direction of Engineer-in-charge.
2 x 1.30 x 0.60 x 1.25mtr. = 1.95 cum.
@ Rs. 5626.40 per % cum= Rs 110.00
Supplying all materials , labour and T&P and providing C.C (1:4:8) using
2 40 mm bhg metal including watering for curing, cost and conveyance,
taxes and royalities etc. all complete as per direction of Engineer-in-
charge.
2 x 1.30 x 0.60 x 0.15mtr. = 0.23 cum.
@ Rs. 2384.60 per cum. = Rs 548.00

3 Supplying all materials , labour and T&P for providing 0.10m thick R.C.C
work in roof slab with C.C. ( 1:2:4 ) using 12 mm size b.h.g. chips with
cost, conveyance & royalty etc. complete including watering and curing
with proper centering & shuttering and false work, laying & hoisting,
dismentalling the false work after completion, site cleaning & disposal of
debris to suitable place away from locality complete as per direction of
Engineer-in-charge.
i] In roofslab = 1 x 7.0 x 1.20 x 0.15 mtr. = 1.26 cum.
ii] Pillar = 2nos x 1.20 x 0.30 x 1.0 mtr. = 0.72 cum.
1.98 cum.
@ Rs. 3580.40
per cum.=Rs. 7,089.00

4 Supplying all materials, labour and T&P for providing timber centering and
shuttering as per direction of Engineer-in-charge.
i] Roof slab = 1 no x 7.0 x 1.20 mtr. = 8.40 sqm
@ Rs. 221.30
per cum.=Rs. 1,859.00

ii] Beam = 2 x 2 x 1.20 x 1.0 mtr. = 4.80 sqm


2 x 2 x 1.0 x 0.30 mtr. = 1.20 sqm
6.00 sqm
@ Rs. 302.10
per cum.=Rs. 1,813.00

5 Supplying all materials , labour and T&P for providing M.S. Reinforcement
for R.C.C. works including cutting, bending, binding and tying the grills
and placing in position including cost of M.S. rod , binding wire 18 to 20
gauge, all complete as per direction of Engineer-in-charge.
Qnty. = at the rate of 0.90 Qntl. / cum of R.C.C.
i.e. 1.98 cum x 0.90 Q = 1.78 qntl.
@ Rs. 4801.20per cum.=Rs. 8,556.00

###
[C ] RENOVATION OF FOUL SEWER LINE

1
Supplying all materials,labour and T&P for laying in trenches unplasticized
PVC pipes and specials of the following outside dia. for all classes
including jointing with approved solvent cement by non-heat application
method including testing as per specification and direction of Engineer-in-
charge etc. all complete. [excluding earth work and cost of pipes and
fittings] [per mtr.]
i.] Laying of 160 mm. dia. PVC pipe = 45.0 Mtr
at the rate Rs. 780.00
per cum.=Rs. 35,100.00
Additional depth per 0.10 mtr depth or part thre of from 1.0 mtr to 1.50
i.] mtr
75.0 mtr at the rate Rs. 3.10 per each. = Rs. 233.00
Additional depth per 0.10 mtr depth or part thre of from 1.50 mtr to 3.0
ii.] mtr
30 No at the rate Rs. 4.20 per each. = Rs. 126.00

###