Escolar Documentos
Profissional Documentos
Cultura Documentos
Dr Wasoodev HOORPAH
Civil Engineer
Head of Bridges Dept.
OTUA, Paris, FRANCE
Summary
Steel has gradually made a come-back in the deck structure of medium and long span bridges in
France in the last twenty-five years. This trend started in the road bridges first and has now
reached the maximum share in the bridges for the new high-speed railway lines. Along with
economical structures like the twin girder decks, steel has kept on being used in innovative and
technically challenging design. This paper shows the recent trends and the new markets in bridge
design with steel taking place now in France.
Keywords: Steel, composite, aesthetics, high-speed railways, twin girder, tied arch, double box
section, construction, launching.
1. Introduction
Nowadays in France, above 80 % of bridges in the medium and long span range have a composite
steel concrete deck. This trend started in the 1980’s in the road bridges. Before that in the 1970’s
the development of prestressed concrete bridges in France had totally excluded steel from the
bridge market.
About ten years later, the same phenomenon was observed in the rail bridges for the high-speed
lines. The first two lines in the 1990’s had only pre-stressed concrete viaducts, but the share of
steel has gradually been increasing since that time.
The comeback started with the twin girder composite decks and gradually gave birth to other types
of structures. The new trends with steel can now be observed in all span ranges.
3. Road bridges
This basic form has undergone different variations : For very wide decks the slab is also supported
by the composite cross girders whose upper flanges are welded to the upper surface of the main
girders and these cross-girders sometimes extend under the cantilever parts of the deck as well.
Though this structure appears simple, it nevertheless incorporates the latest developpments from
the steel manufacturers :
- very thick plates reaching 150 mm, thus without flanges consisting of plates welded on
top of each other;
- longitudinally profiled plates, which alllows an optimal tailoring to the bending moment
diagram; ( Fig. 3)
- thermomechanical steel with a better weldability, not requiring preheating on site.
maximum variation in thickness (in maximum slope
type
mm) (in mm per metre)
55 8
55 8
40 8
Fig. 3 : Examples of longitudinally profiled plates
To enhance the aesthetic of the bridge, it is quite common to have girders of variable depth,
especially for long spans reaching 100 meters. The launching of such decks is possible, though a
bit more complicated than the constant depth girders.
The aesthetics of these sections are highly appreciated by bridge owners; for this reason they
have been chosen even for medium span crossings where the twin girders could have been
economical.
For large decks, up to now the cantilever on the outside was supported by crossbeams in the
alignment of the diaphragms. The recent examples of Verrières and Valence viaducts have
introduced diagonal tubular bracings which can also be inclined longitudinally. ( Fig.4)
Concrete bridge designers often find it interesting to use steel webs, for lightness and specially
for construction ease. For the 240 m. span Bras de la Plaine bridge opened in 2002 in Réunion
island, the deck consists of two prestressed concrete flanges connected to vertical tubes. These
were essential for the cantilever construction of the deck. Additional external prestressing cables
are also present .
Fig. 5 : Viaduct of Bras de la Plaine in Réunion
In the Meaux viaduct near Paris, the box section has the upper and lower flanges in prestressed
concrete and two ‘plano-tubular webs’ with additional tubular brackets. This 31 m wide bridge also
has the signal span prestressed with underside cables. ( Fig. 6) This design benefited from a
special innovation financing.
This comeback took place in the new TGV railway bridges only after 1990. The first high speed
railways in the eighties: South East and Atlantic lines had only pre-stressed concrete viaducts
while the North TGV line from Paris to Lille included some fifteen steel and composite bridges for a
total weight of 20000 tons.
This trend was confirmed in the new Mediterranean TGV with 44000 tons of steel in 23 bridges,
counting for nearly two thirds of the total large crossings. This exceeds the current annual steel
consumption in French bridges which reaches about 30 000 tons.
DECK TYPE TGV NORD INTER. IdF & LYON TGV MED
1993 - 1996 1994 - 1996 1997 -1999
Twin girder 2697 m 8000 t 1607 m 5115 t 7190 m 24959 t
Multi Girder 234 m 573 t 121 m 700 t 992 m 3554 t
RAPL 581 m 3350 t 300 m 2000 t 245 m 2040 t
Warren Truss 91 m 1000 t 0 0 0 0
Twin box section 0 0 0 0 290 m 1022 t
Tied arch 0 0 0 0 730 m 12900 t
Special tubular 0 0 0 0 300 m 1270 t
truss
Table 1 : Structural types of HSR steel bridges : total length and steel weight
The twin girder composite deck proved its highly competitive and economic value throughout all
the lines.The largest span built up to now is 63 m. at Viaduc d’Orgon; span of 75 m. will be seen in
the new TGV Est at Viaduc sur La Moselle. Its design has been optimised through easy to
fabricate structural details especially for the lower bracing. In some bridges this bracing is replaced
with concrete slabs, which are even more economical.
The conceptual design was carried with special attention to the dynamic behaviour of the deck
which had to be guaranteed under the high speed train. This is one of the main reason why the
high speed railway steel bridges systematically incorporate a concrete slab which takes part in the
global and local resistance as part of the composite deck structure. It also carries the ballast. The
concrete also brings supplementary mass and damping, thus decreasing the noise emission under
the TGV passing. High speed requires the steel deck to be very stiff and sufficiently heavy to limit
dynamic phenomena, which have to be mastered in order to ensure the safety and comfort of the
train passengers. The railway works regulations impose severe and precise criteria for these
points. This also has some important consequences on the detailed design regarding the fatigue
resistance.
In all these bridges, particular attention was given to the integration of architectural and structural
values in the engineer's work through a constant dialogue with the architect. This gave birth to the
spectacular steel superstructures in the large tied-arch viaducts with complex fabrication details
Mornas and Mondragon, La Garde Ahémar, South Avignon toll. And of course the Arc Viaduct
with its particular tubular truss girders.
In the new TGV Est line under construction, the lateral girder composite decks have been chosen
for skewed crossings over the A4 motorway. For the large viaducts like the Jaulny viaduct, a
composite deck on a double box sections with the outer web inclined has been chosen. This last
kind of deck had been introduced in fact in the TGV Méditerranée line for short skewed crossings.
The crossing of the Tarn valley represents a difficult obstacle for all crossings designed around
Millau. Lengthy studies carried since fifteen years ago had first analysed the gross itineraries in
order not to cut of the town from this new route, then the possible crossings of the Tarn Valley, with
all the bridges and tunnels required by each route chosen. Geological conditions excluded some
possibilities, also did the too steep alignments outside the motorway standards. ( Table 2)
Fig. 7 : The different types of bridges in the initial design ( Source AIOA )
For the final phase of these preliminary design steps, the following alternatives were proposed :
•Pre-stressed concrete deck with spans of 175m
•Steel box with orthotropic deck in 200m span
•Concrete arch viaduct 500m wide.
•Steel lattice deck with steel piers in 350m span
•Multi-span cable stayed viaduct with pre-stressed concrete deck in current span of 350m
From these proposals, an international jury led by the Road Director chose the cable-stayed
bridge.
The all steel deck consists of a 4m by 4.2m rectangular main box which forms the central spine of
the 32m deck and whose primary function is to anchor the stay cables. The whole deck is a
aerodynamic box section designed to resist the buffeting wind effects which are particularly strong
at this height over the mountain valley. The upper flange of the deck is an orthotropic plate with the
trapezoidal stiffeners designed to withstand also the axle loads of cars and heavy trucks on the
asphalt. The corrosion protection of the inside of the box section will be obtained by the use of a
drying system, which is more economical than a coating system. However the external surface of
the steel deck will be protected by a classical multi layer painting system which will also give the
final colour.
The Millau Viaduct also demonstrates that steel pylons can be economical by reducing the work
duration. The two pylons on the Tarn span will be used to retain the overhanging nose of the deck
during launching, while the other pylons will be slid on the deck and upraised directly over the
piers.
The steel deck of Millau Viaduct will be fabricated with high performance weldable steel. Many of
the steel elements such as the inner webs will have to resist complex stresses under the very high
reactions during launching or the pylons and the stay cable anchorages in service. For these
reasons most of the steel elements will be in S460 TM grade. On site welding of this grade can be
done without pre-heating. This steel grade was first used in France in 1994 at the Remoulins
Viaduct, and the Millau viaduct will be the first large scale utilisation : about 12000 tons on the total
of 36000 tons. The other steel grade mainly used will be S 355.
As for the steel pylons reaching 90m over the deck, they will be completely assembled in the
construction halls on the work platforms behind the abutments and slid horizontally on the
launched deck by a special carrier on multiple wheels, then raised at their final position over the
piers. For this raising, the steel contractor has designed a special rotating crane that will lift the
upper end of the pylon with jacks and cables. ( Fig. 11)
.
Fig 11: Construction sequences ( Source : OTUA)
Fig. 12 : Some construction sequences in April 2003
5.5 Fabrication
The foundation works have started at the beginning of 2002 on site. The steel fabrication has
started at nearly the same period in the steel contractor, EIFFEL’s shops at Lauterbourg. The
36000 tons of steel which will be mounted for this viaduct represents a year’s consumption of steel
in bridges in France. The inner box has web plates in thickness ranging from 40 to 90mm. The
lateral parts consists of 12 and 14 mm plates with stiffeners in 6 and 8 mm cold formed trapezoidal
section. The sections with an average length of 22m and breadth of 3.50m are fabricated with
automatic welding machines and a welding robot. ( Fig. 12- Fig. 13)
6. Conclusion
7. References
[1] G. LEBAILLY, B. PLU : Les ouvrages d’Art Métalliques sur LGV – JIS Dec. 2002
[2] Ph. RAMONDENC : The design of the steel and composite bridges of the TGV
Méditerranée. IABSE Conference, Madrid 12-14 June 2002
[3] OTUA : Ponts du TGV Méditerranée - Bulletin Ponts Métalliques N° 19 - 1999
[4] OTUA : Ponts du TGV Nord - Bulletin Ponts Métalliques N° 16 – 1996
[5] J. RAOUL : The design of common composite road bridges in France – ECCS Steel
Bridges Symposium - Barcelona March 2003