Você está na página 1de 36

Final version, December, 1996

Voltage Collapse Mitigation

Report to IEEE Power System Relaying Committee


Prepared by IEEE Power System Relaying Committee, Substation Protection Subcommittee, Working
Group K12 - M. Begovic (Vice Chair), J. Bright, T. Domin, S. Easterday-McPadden, A. Girgis, W.
Hartmann, C. Henville (Chair), M. Ibrahim, K. Kozminski, R. Marttila, G. Michel, K. Mustaphi, D. Novosel, B.
Pettigrew, M. Sachdev, H. Shuh, P. Solanics, J. Williams.

Table of Contents
I. Introduction..............................................................................................................................................1
II. Voltage Collapse....................................................................................................................................1
A. Introduction 1
B. Modeling of Voltage Collapse 1
C. Voltage Collapse Proximity Indicators 2
D. Conventional Indicators 4
E. Future possibilities 5
F. Time Frame of Voltage Collapse 6
G. Load Types 7
III. Dynamic Sources of Reactive Power .................................................................................................9
A. Static Sources 9
B. Synchronous Machines 10
C. Measurement of Dynamic Reactive Power Reserve 12
D. Excitation Control Devices 14
E. Protection Issues 18
IV. Switched Capacitance .........................................................................................................................20
A. Long-term Time Frame. 20
B. Transient Time Frame 21
V. Automatic Reclosing .............................................................................................................................23
VI. Load Shedding......................................................................................................................................24
A. Manual Load Shedding 24
B. Load Shedding as Part of Energy Management Systems (EMS) 25
C. Automatic Load Shedding 25
VII. Distribution Voltage Control................................................................................................................28
A. General 28
B. LTC Blocking Schemes 28
C. Distribution Voltage Reduction 29
D. Comparison of Voltage Reduction and Blocking Schemes 30
VIII. Conclusion..........................................................................................................................................31
A. The fundamental principles of mitigation actions 31
B. Choice of action(s) depends to a large extent on dynamics 32
IX. Acknowledgments.................................................................................................................................33
X. References............................................................................................................................................33
Final version, December, 1996

This page left blank intentionally


Final version, December, 1996

I. Introduction proper diagnosis of the underlying factors


causing low voltage. Proper coordination of
protective schemes and system controls during
Proper application of protective relaying and
declining or low voltage conditions is essential.
control schemes and other remedial actions can
reduce the probability of voltage collapse. The
IEEE Power System Relaying Committee II. Voltage Collapse
(PSRC) decided to review the factors affecting
the choice and application of protection and A. Introduction
control schemes, to assist relay engineers in The main symptoms of voltage collapse are - low
making their contribution to the design of reliable voltage profiles, heavy reactive power flows,
power systems. inadequate reactive support, and heavily loaded
systems. The collapse is often precipitated by
In January 1994 the PSRC produced a special low-probability single or multiple contingencies.
publication [1] discussing the phenomenon and The consequences of collapse often require long
describing various automatic load shedding system restoration, while large groups of
schemes. During the preparation of that customers are left without supply for extended
publication it became apparent that there were a periods of time. Schemes which mitigate against
number of protection and control strategies that collapse need to use the symptoms to diagnose
could be applied to reduce the probability of the approach of the collapse in time to initiate
voltage collapse. This report discusses the corrective action.
protection aspects of the various schemes, and
factors affecting their application. By pointing out The following subsections will discuss the
relay highlights and concerns, it will supplement a modeling of the collapse (required in order to
more comprehensive reference [2]. determine the symptoms) and techniques to use
the symptoms to make the diagnosis. More
Voltage control problems are not new to the utility information on modeling systems subject to
industry but the problems in the past were voltage stability concerns are available in [3].
primarily associated with the transfer of power
from remote generation sites to load centers. B. Modeling of Voltage Collapse
These problems were addressed by specific Modeling techniques can be divided into two main
control and/or protection schemes dedicated to categories, static or dynamic. In determining the
the particular transmission systems. suitability of the different approaches, it is
important to distinguish between various events
More recently, the combined effects of inter-utility which affect the speed and probability of voltage
power transfers, wholesale wheeling, collapse:
interconnection of NUGs and difficulty in building
new transmission facilities have resulted in • disturbances of topology, which may involve
operating transmission systems closer to their equipment outages, or faults followed by
voltage/reactive limits. Voltage control problems equipment outages. Many of these
are now appearing in more tightly meshed disturbances are similar to those which are
transmission systems and over wide areas. traditionally associated with transient stability
Maintaining adequate network voltage with analysis, and sometimes the distinction is
reduced transmission margins has become a hard to make. For analysis of these events, a
major source of vulnerability for many dynamic system model is required.
interconnected systems.
• load disturbances; these are the fluctuations
The phenomenon of voltage collapse has created of load which may have dynamics of their
significant interest and much research. The own, which can be split into
major issue in dealing with voltage collapse is the

1
Final version, December, 1996

- slow load fluctuations (normal random load reactive support requirements and system
fluctuations) loading capability. However, time-domain
- fast load fluctuations (such as outages of simulations may also be used for voltage stability
large blocks of loads) analysis. Following is a brief account of proximity
Slow load fluctuations may be treated as indicators of steady state voltage instability.
inherently static. They cause the stable
equilibrium of the system to move slowly, Historically, early attempts to investigate voltage
which makes it possible to approximate unstable conditions were based on attempts to
voltage profile changes by a discrete improve the solution of static load flow programs
sequence of steady states rather than a applied to heavily loaded power systems having
dynamic model. low voltage profiles. It was difficult to arrive at
load flow solutions for such systems because at
The following table briefly summarizes the types the point of voltage collapse (and at higher loads)
of disturbances which may cause voltage there is no real steady state solution to the load
instability and the appropriate modeling approach: flow. Later, the dual solution (with two different
voltages for the same power delivered) were
Disturbance Description of Model observed to converge to a single point beyond
Disturbance which it became impossible to solve the power
Topological Equipment Outage Dynamic flow.
Fault Dynamic
Load Fast Dynamic Early indicators used the distance of the two
Fluctuation Slow Static solution points as an indicator of proximity to
collapse, since this distance decreases as the
point of maximum loadability approaches. Figure
While the three types of disturbances which
II-1 shows a VP diagram of a particular system at
require dynamic analysis are also known as the
a particular operating point, with the two solution
leading causes of other types of transient
points.
instability, they may cause voltage instability if
either one of the following happens:

• the post-disturbance equilibrium has a low 1


VU
voltage profile
• the transient voltage dips during the
disturbance are too long ∆V
• the post-disturbance equilibrium is voltage Voltage Pm
unstable (i.e., adding reactive power support (p.u.)
at any bus lowers the voltage at the same
VL
bus)

The best way to identify all the aspects of


transient and/or steady state performance of the
system before, during, and after the disturbance, 0 Power
as well as the effects of various contingencies, is
by time-domain simulation. This, unfortunately, is
sometimes a computationally expensive way. Figure II-1 VP Curve and Power Margin

C. Voltage Collapse Proximity Indicators The upper point VU is the normal operating point,
but a solution at VL is also possible. It can be
Presently, static simulations are still widely used seen that the distance between the two solutions
for planning and operating purposes to determine

2
Final version, December, 1996

∆V tends to zero as the margin of power Pm might occur. However, it is difficult to calculate
between the operating point and the point of the system condition and derive the parameters
maximum power approaches zero. in real time. Rapid derivation and analysis of
these parameters is important to initiate
VP curves do not take into account the reactive automatic corrective actions fast enough to avoid
power component of the load. To include the collapse under emergency conditions which arise
reactive component, a third dimension must be due to topological changes or very fast load
added, as shown in Figure II-2 following. changes.

trajectory (P,Q,V) It is much better if a few critical parameters that


V can be directly measured could be used in real
an operating point
time to quickly indicate proximity to collapse. An
point of voltage example of such indicator is the sensitivity of the
collapse generated reactive powers with respect to the
Q load parameters (active and reactive powers of
the loads). When the system is close to collapse,
small increases in load result in relatively large
active power increases in reactive power absorption in the
system. These increases in reactive power
P margin
absorption must be supplied by dynamic sources
reactive power margin of reactive power in the region. At the point of
collapse, the rate of change of generated
Figure II-2 VPQ Curve Representing a reactive power at key sources with respect to
Trajectory Where Both Active and Reactive load increases at key busses tends to infinity.
Power Can Change Arbitrarily
The sensitivity matrix of the generated reactive
powers with respect to loading parameters is
Figure II-2 represents a trajectory of the load relatively easy to calculate in off-line studies, but
increase when active and reactive power can could be a problem in real-time applications,
change independently, as well as the active and because of the need for system-wide
reactive power margins. The voltage stability measurement information. Large sensitivity
boundary is represented by a projection onto the factors reveal both critical generators (those
PQ plane (a bold curve). It can be observed that: required to supply most of the newly needed
(a) there may be many possible trajectories to reactive power), and critical loads (those whose
(and points of) voltage collapse; (b) active and location in the system topology imposes the
reactive power margins depend on the initial largest increase in reactive transmission losses,
operating point and the trajectory to collapse. even for the modest changes of their own load
parameters). The norm of such a sensitivity
There have been numerous later attempts to use matrix represents a useful proximity indicator, but
these initial observations and find more refined one that is still relatively difficult to interpret. It is
and accurate voltage collapse proximity not the generated reactive power, but its
indicators. They are usually based on derivatives with respect to loading parameters
measurement of the state of a given system which become infinite at the point of imminent
under stress and derivation of certain collapse.
parameters which indicate the stability or
closeness to instability of that system. Other useful indicators that can be directly
measured are the power margins themselves -
Parameters based on measurement of system they can be defined as margins of active, or
condition are useful for planning and operating reactive power on a single bus, or a collection of
purposes to avoid the situation where a collapse

3
Final version, December, 1996

busses in the system when a restricted number voltage in a specific area that may be subject to
of load parameters are allowed to freely change. voltage collapse. Power flow studies will show
how these sources respond to voltage
0.8
depressions in the region of interest. When
studies have defined the relationship of the Var
reserve in these specific sources, to total Var
P3 reserve in the region, it may be possible to use
P2 the Var reserve of these sources as an indicator
Q injected (p.u.)

0.4 P1
of total Var reserve in the region. Another
method may be to compute the significance of all
dynamic sources in the region, measure their
Qmissing
unused Var capability, and compute the amount
0
1.0 of Qreserve available to the region of interest.
Qreserve

Important aspects to consider in voltage stability


analyses:
-0.4
Voltage (p.u.)
• Operating limits, such as reactive power
Figure II-3 VQ Curve for Three Loads generation limits, are important factors in
voltage stability analysis. An example of the
application of such limits follows in the
For example, Figure II-3 shows a VQ diagram of discussion on conventional indicators.
a bus in a particular power system at three
different loads, P1, P2, and P3. The y axis • Many loads (especially the composite loads,
shows the amount of additional reactive power as viewed from the transmission network),
that must be injected into the bus to operate at a are sensitive to voltage, and the effects of
given voltage. The operating point is the their voltage-related behavior are to be
intersection of the power curve with the x axis, accounted for in accurate analysis of voltage
where no reactive power is required to be stability. Load characteristics are discussed
injected or absorbed. If the slope of the curve at later in this paper.
the intersection is positive, the system is stable,
because any additional reactive power will raise • Accurate short-term load forecasting
the voltage, and vice versa. It can be seen that techniques are to be used in order to assess
the system is voltage stable with the lightest load, the most likely direction of the load changes
P1. For this load, there is a reserve of reactive and corresponding margins.
power (Qreserve) that can be used to maintain
stability even if the load increases. The system D. Conventional Indicators
is only marginally stable with the medium load P2.
System planning static loadflow studies, can
The system is not stable with the heaviest load
define possible scenarios. For example, recent
P3, since an amount of reactive power
transmission network assessments conducted by
(Qmissing) must be injected into the bus to cause
the reliability regions which compose the North
an intersection with the x axis. Thus the measure
American Electric Reliability Council (NERC)
of Qreserve gives an indication of the margin
indicate that portions of the regional transmission
between stability and instability.
networks continue to be loaded to their limits
when accommodating power transfers. Special
Although Qreserve may be difficult or impossible
operating procedures are in place to coordinate
to measure directly, some means of estimating it
transfers and maintain system reliability during
are available. One method is to find dynamic
contingency conditions. In the Eastern
sources (or a single lumped source) of reactive
Interconnection, reliability of the transmission
power that play a significant role in supporting the

4
Final version, December, 1996

system will continue to be maintained through the there is no guarantee that low voltages persist
use of operating procedures such as the over a complete region. In spite of this, such
Reliability Coordination Plan (RCP). The RCP schemes have been operating reliably for many
was developed by utilities owning and operating years [1,5], in the sense that they have been
the transmission systems in various North secure against undesirable operation, and have
American regions. It is used to curtail or limit provided load relief under low voltage conditions.
transfers to insure adequate voltage profiles in However, it is a rare condition to be in danger of
that part of the Eastern Interconnection. imminent voltage collapse; so experience under a
wide variety of system conditions is not available.
Some common indicators of system conditions
that are presently measured to determine an When reactive power limiters on generators or
emergency system state, requiring voltage synchronous condensers operate to maintain the
collapse mitigation actions are machines within their capability, these machines
cannot do any more to support system voltages.
• Tie line status, generator status Thus the operation of the limiters may be good
• Voltage, time indicators of impending collapse. Such indicators
• Reactive power limiters in action are not yet widely used in North America, but are
• Reactive power reserves. more frequently used in Europe.

These indicators may be used individually, or Exhaustion of reactive power reserves is similar
together to determine the need for automatic to operation of reactive power limiters because
action. The status of tie lines or important local the result is an inability to maintain voltages.
generators can be a very good indicator, if their Exhaustion of such reserve means that one of
presence is required for stable operating the margins mentioned above as a direct
conditions. Such indicators cannot normally be indicator of the proximity of collapse has
used by themselves however, since voltage decreased to zero. When system studies define
collapse is a system wide phenomenon which the critical reserves, and levels, measurement of
cannot be described by knowledge of local remaining reserves can give a dependable
conditions alone. To allow use of a scheme warning of the approach of voltage instability. At
looking at the status of the critical equipment, least two utilities in North America (BC Hydro and
manual arming and disarming by system Florida Power and Light) use reactive power
operators may be required. This would place reserve as one factor in arriving at a decision to
extra burden on system operators however, and shed large blocks of load [1,4]. Measurement of
results in less than optimum arming of the reactive power reserve is discussed later in this
mitigation scheme. Thus the status of equipment paper.
can be considered as one part of the indication
of impending collapse. Other important factors E. Future possibilities
like tie line loads or reactive power source Some recently developed relaying techniques
outputs may be combined with equipment status may be useful in providing indication or control
to make the decision. The Florida Power and action in near voltage collapse conditions.
Light scheme [4] is one such scheme that uses a Following are some examples of these new
combination of equipment status and other developments.
factors.
• Adaptive relays can change settings as
Low voltages over a period of time are widely system conditions change. To cope with
used in undervoltage load shedding schemes and voltage problems, the shedding of load is
load tap changer control schemes (as will be based on voltage measurements, and is
discussed later in this report). A significant initiated when the local voltage falls below a
limitation of localized voltage measurement is that certain setting. The setting, location, and

5
Final version, December, 1996

amount of the load to be shed should be results in aperiodic decreasing (but sometimes
changed to adapt the load shedding scheme increasing) voltages. Figure II-4 shows some of
to the varying system conditions. The the time frames of the various phenomena
protection against voltage instability can be involved in loss of voltage stability. It can be
designed as a part of the hierarchical seen that several orders of magnitude of times
structure. Decentralized actions are are involved.
performed at substations with local
measurements which may be modified by Voltage stability phenomena in the transient
measurements or decisions from a wider region are often closely involved with angular
area, using a communications system. Better stability phenomena. Low voltages can result in
decisions can be made at a higher loss of angular stability, and loss of angular
hierarchical level, but larger number of stability will result in fluctuating voltages. Voltage
relevant system measurements are required. collapses in the longer-term time frames can also
result in loss of angular stability. Voltage
• Phasor measurements are useful to speed collapses do not always result in loss of angular
up state estimation to determine collapse in stability however. Even collapses in the transient
real time fast enough for automatic action. time frame, such as may be precipitated by slowly
Instead of using a relatively slow cleared short circuit faults do not necessarily
communication with conventional SCADA, result in loss of angular stability.
one can envision using faster communication
links with phasor measurement units which do Voltage collapses in the longer time frames are
not require much post-processing of the type that are attracting much of the attention
measurement data, and could possibly be and recent research in power system
used for real-time control of some transients phenomena. Tools to study time dependent
in power networks. Phasor measurement system response in longer time frames have only
units, and similar high-speed measurement been relatively recently developed, while tools for
devices are a predecessor of a new, faster, transient analysis of power systems are very
and more sophisticated generation of data mature and widely used. Advances in numerical
acquisition devices for system-wide algorithms and computer power have made it
monitoring in near real-time conditions for a possible to simulate systems of very large size
variety of disturbances, including voltage and with many types of equipment. Several
instabilities. software tools are now available to perform
simulation of power system responses over a
• User definable relays [6,7] may be useful for long period of time. Examples are the EPRI's
special applications where unique ETMSP [8], EUROSTAG, and PSS/E. Measures
measurements are required. For instance, to avoid collapses in all time frames will be
they may be set for specific rate of change of discussed in this paper. The time frame of the
voltage, if rate or shape of voltage collapse voltage instability phenomenon is an important
can be defined. User configured relays may factor in application of mitigation measures.
discriminate between collapse due to
instability and depression due to fault or Voltage collapses in the transient time frame are
motor starting. They may also be used in most often caused by slowly cleared faults, such
measurement of reactive power being used as the cascading collapse on 22 August, 1987
for voltage support, as a percentage of that TVA experienced [9], and the significant
maximum available reactive power. voltage depression that Philadelphia experienced
on July 1, 1992 [10].
F. Time Frame of Voltage Collapse
Voltage collapse can occur over a wide variety of
time frames. Loss of voltage stability generally

6
Final version, December, 1996

Transient Voltage Stability Longer-Term Voltage Stability

Induction Motor Dynamics Load/Power Transfer I n c r e a s e

Generator/Excitation Dynamics Load Tap Changers & Dist. Voltage Reg.

Prime Mover Control Load diversity/Thermostat

Mechanically Switched Capacitors Excitation Limiting Gas Turbine Start-up

Undervoltage Load Shedding Power Plant Operator

SVC Generator Change/AGC

Generator Inertial Dynamics Boiler Dynamics Line/Transformer Overload

DC DC Converter LTCs System Operator

Protective Relaying Including Overload Protection

1 Minute 10 Minutes 1 Hour

0.1 1 10 100 1000 10000


Time - Seconds

Figure II-4 - Time Frames for Voltage Stability Phenomena


(Reproduced from Reference 8, with permission)

Collapses in the longer term time frame may discussed in the following section). Thus a loss
result from loss of significant sources of local of a significant source of local generation or
generation or reactive support, or from loss of reactive support can precipitate a voltage
heavily loaded transmission capability. In such collapse in the transient, or long term time frame.
cases, transient overload capability may allow
nearby generators to maintain voltages for a G. Load Types
short time, until maximum excitation limiters come Load modeling is an essential, but often
into effect and local Var support is severely inadequately represented element in power
curtailed. However, loss of significant reactive system studies. Given a power system topology,
power support can also lead to loss of angular the behavior of the system following a
stability and voltage collapse in the transient time disturbance, or whether voltage collapse can
frame as was the case in the 13 March 1989 occur, depends to a great extent on how the load
collapse of the Hydro Quebec system due to loss is represented.
of several critical SVCs that were supporting the
transmission system voltages. Load admittances are a function of voltage and
frequency. The characteristics of load with
Collapses in the long term time frame may also respect to frequency are not critical for the
be caused by unusually fast load build up (such phenomena of voltage stability, but the
as the Tokyo 23 July, 1987, incident). They may characteristics with respect to voltage are critical.
also be caused by changing over time, of the Systems with “soft” loads which decrease sharply
characteristic of the load sensitivity to voltage (as

7
Final version, December, 1996

with voltage are much more likely to be voltage


stable than systems with “hard” loads that are
relatively independent of voltage. The
relationship of power to voltage may be
expressed as P = KpVα where P is the power
delivered to the load, Kp is a constant, V is the
magnitude of the supply voltage and the exponent
α, determines the sensitivity of the load to
voltage. “Hard” loads would have values of α
near 0, and “soft” loads would have values nearer
2.

Not only is the characteristic of the real power


component of load (with respect to voltage)
important, but also the reactive power component
characteristic is important. Voltage magnitude is Figure II-5 Variation of Voltage Dependency
much more sensitive to reactive power flow than with Time (Reproduced with permission, from
to real power flow. Similar to the case of real Reference 11)
power, the reactive power sensitivity may be
expressed as Q = KqVβ, where Q is the reactive
power supplied, Kq is a constant, V is the voltage In generating data for load models, there are two
magnitude and the exponent β determines the approaches: measurement-based, and
sensitivity to voltage. Investigations into the component-based. Measurement-based data are
sensitivity of load with respect to voltage must derived from curve fitting the field measurements
address both the real and reactive components [11,12,13,14]. Component-based methods are
(they must attempt to determine the values of α used when physical measurements are not
and β). available. EPRI has a program LOADSYN that
provides an automated means to generate
The values of α and β are not necessarily parameters for the mathematical load model. The
constant with time. Since voltage collapse is a user needs to specify load classes, such as
dynamic event, the dependence of α and β with percentages that are residential, commercial,
respect to time is also important. A common industrial, and components within each classes
method of investigating load characteristics is to such as heating, lighting, etc. More details can be
measure the response of load to small voltage found in [15,16].
changes. The studies often show that the
characteristics of α and β with respect to time Since customers require good power quality, it is
are different from each other. not usually possible to measure the response of
loads to large voltage changes (more than a few
Figure II-5 shows test results from a Swedish percent), such as may occur in a loss of voltage
study (at a substation designated FVK). For this stability event. The validity of load dependency
figure, the initial values of α and β vary from tests must therefore be estimated for larger
about 2 and 5 respectively, to 0.2 and 4 in the voltage fluctuations. That is, it is not certain that
steady state. the quantities for α and β are valid for voltage
variations outside tested levels.

The effectiveness of a type of control or


protective action to mitigate against voltage
collapse depends significantly on the load type.
For instance, a common control action (which will

8
Final version, December, 1996

be discussed later in this paper) is voltage mechanically switched capacitors can be


reduction by load tap changer blocking or set- provided by true dynamic sources of reactive
point change. Such a control action will be much power such as static Var compensators (SVCs),
less effective for hard loads than soft loads. The static condensers (STATCONs), synchronous
period of effectiveness will also depend to a large condensers, and generators.
extent on the variation of the exponents α and β
with respect to time. The application of SVCs and STATCONs in the
context of voltage stability is discussed in recent
III. Dynamic Sources of Reactive literature[2]. The main differences between
these two devices is that the SVC becomes a
Power shunt capacitor when it reaches the limit of its
control and all capacitance is fully switched in. Its
A. Static Sources reactive power output decreases as the square
Adequate Var support is critical to maintaining of the voltage when the maximum range of control
healthy system voltage and avoiding voltage is reached. The STATCON output is limited by
collapse. Within limits, static reactive sources its current carrying capability. Therefore, its
such as shunt capacitors, can assist in voltage reactive power output decreases linearly with the
support. However, unless they are converted to terminal voltage when the maximum range of
pseudo dynamic sources by being mechanically control is reached. Figure III-1 compares the
switched, they are not able to help support operating characteristics of the SVC and
voltages during emergencies, when more STATCON.
reactive power support is required. In fact, shunt
capacitors suffer a serious drawback of providing In respect to its capability to deliver more reactive
less reactive support at the very time that more power output than an SVC at lower voltages, the
support is needed, during a voltage depression STATCON behaves more like a synchronous
(Var output being proportional to the square of condenser than an SVC. Short time overload
the applied voltage). capacity of the STATCON is much lower, and of
shorter duration than that of a synchronous
Capacitors can be switched infrequently at high condenser however.
speed to provide dynamic voltage support, as
discussed in Section [IV]. However, the control It can be seen from this figure that in the case of
schemes can become rather complex, and large the SVC, after the voltage drops to a level where
blocks of capacitance must be switched at each maximum reactive capability of the equipment is
stage in a control scheme. More smoothly reached, any further decrease in voltage results
controlled, and faster reactive support than
Controlling Controlling Vterminal
range Vterminal range

Supplying vars Absorbing vars Supplying vars Absorbing vars

Current Current
SVC Operating Characteristic STATCON Operating Characteristic
Figure III-1 Comparison of SVC and STATCON operating characteristics

9
Final version, December, 1996

in severe decrease in supplied reactive current. the collapse-mitigation problem. Synchronous


However, the current supplied by the STATCON machines considered in this paper may be
remains at the maximum value, even in the generators or synchronous condensers. In
presence of continued voltage decline. The terms of reactive output capability, synchronous
slope of the characteristic in the controlling range condensers are treated similarly to static Var
is caused by deliberate droop in the control sources during commissioning and maintenance
characteristic for stability. The SVC will of in that rated output power must be demonstrated
course be limited by the short time current to be achieved.
capability of the reactors when the terminal
voltage rises above the controlling range. In Generators however are rated for specific real
practice excessively high voltage will not be power output, usually at a specific power factor.
allowed to persist on the power system for long During commissioning and maintenance, real
enough to damage the reactor (or reactor power output is carefully checked to meet
protection will operate to disconnect the SVC). specified requirements. Reactive power output
may be checked during commissioning, but may
SVCs and STATCONS are often operated in not be carefully checked after that. The reactive
conjunction with static sources of reactive power power capability may be required by the system,
such as reactors or capacitors. The SVC or but is not considered to be a revenue generator.
STATCON control equipment can be designed to Due to large impact on the system voltages, it
switch the static sources in such a manner as to may be difficult to operate large generators at
keep the dynamic source as close as possible to their reactive capability limits (for test purposes).
the middle of its operating range. By switching Therefore coordination of protection with control
static sources in this manner, as much as devices is not so frequently checked as with
possible of the full dynamic capability will be other reactive power sources[17]. Numerous
retained. An example of switched capacitors voltage collapse or near collapse incidents have
being used to maximize the availability of dynamic been aggravated by unexpected loss of healthy
power from a group of synchronous condensers generators due to lack of coordination of
is given in Section IV-A. protective equipment with generator capability.

Control of SVCs and STATCONs will normally be A typical generator capability diagram as supplied
achieved by use of digital control devices with by a manufacturer of a 165 MW, 0.9 pf turbo
almost unlimited flexibility to provide appropriate generator is shown in Figure III-2 following.
control of terminal voltage within the capability of 150 Mvar Rotor current limited
Unit supplies
the primary equipment. Protective devices vars region
(over-excited)
applied to this equipment will of course have to 100
coordinate with control settings and equipment
Stator current
capability. This coordination is normally 110% limited region
thoroughly checked at commissioning as the Gen. 105%
Terminal 100%
rated output of the device is measured as part of Voltage 95%
Real Power
acceptance testing, and at routine maintenance 90% 0 100 200 (MW)
intervals.
-50

B. Synchronous Machines
-100 Stator end winding
heating limited region
1. Capability Diagram Unit absorbs
vars
A synchronous machine is capable of generating (under-excited) -150

and supplying reactive power within its capability


limits to regulate system voltage. For this reason, Figure III-2 165 MW Generator Capability Diagram
it is an extremely valuable part of the solution to (at various percentages of terminal voltage)

10
Final version, December, 1996

Some interesting observations can be made from diagram. Reference[18] describes in more detail
Figure III-2. The reactive power capability the various other factors that can limit the
increases dramatically as real power output is generator capability.
limited. Further, the amount of reactive power Another significant limiter, which does not always
available from the generator is very dependent on coordinate with the generator capability or control
terminal voltage. In this respect, a generator equipment settings is the generator protection.
operating at low real power output can supply Rotor overload protection, loss of field protection,
significantly more reactive power at low voltages and backup protection are all systems that can
than at high voltages. cause unexpected and undesirable disconnection
of a generator in a voltage stressed system.
The increase in reactive power capability at lower Later sections in this paper will discuss some of
real power output means that system planners those protection aspects in more detail. A major
and operators may choose to generate less than reason for unexpected operation of protective
rated real power in order to have more reactive devices is the lack of routine exercising of the
power from generators at critical locations in generator at its capability limits [17].
voltage stability threatened systems. The choice
of operating point (Mw versus Mvar) for Excitation power is supplied by one of two types
generators at critical locations is predetermined, of exciters, rotating and static. As the term
and not usually subject to automatic control. It implies, a rotating exciter is one that mounts on
should be noted that when the generator reaches the machine shaft and rotates with the generator
the limit of its capability, particularly in the rotor producing main field current by induction. The
current limited region, it may not be controlling its exciter's field is energized by some independent
terminal voltage. The fact that it is at its limit of source, e.g., a permanent magnet generator
capability means that it is not able to raise the (PMG), station battery, etc., controlled by the
terminal voltage to the reference setting of the voltage regulator. A static exciter is comprised of
voltage regulator. Thus the reactive power limits a power transformer and power electronics
are to a certain extent, determined by the system utilizing generator terminal voltage as the source
conditions, and independent of the generator of field power. It would appear that a static
excitation system. exciter would be limited in its capability like
switched capacitors or an SVC because it is
The value of a generator as a source of reactive dependent upon the generator terminal voltage
power can be separated from its value as a for power; however, the transformer ratio is
source of real power, if it can be decoupled from selected so that the power electronics can deliver
the turbine and run as a synchronous condenser. a broad range of field current even with
In some plants where fuel or operating costs may depressed voltage. Generally speaking, static
make power generation uneconomic, it may be exciters are quicker in their response to voltage
possible to convert the generator to a disturbances than their rotating counterparts
synchronous condenser, and use it to support because of the latter's additional windings and
voltages in an area where real power has to be their associated time constants.
imported from a remote area.
2. Effect of Cooling Medium on Var
The generator capability diagram as supplied by Capability
the manufacturer is not necessarily the capability Generator capability may depend significantly on
of a given generator connected at a given point in the type and amount of cooling. This is
a system. Many other factors such as auxiliary particularly true of hydrogen cooled generators
equipment voltage limits, stator or transformer where cooling gas pressure affects both the real
winding voltage limits, cooling medium conditions, and reactive power capability. The curves
or over and under excitation controllers can limit shown in Figure III-2 are for an air cooled
a given generator’s capability to significantly less machine, operating at maximum ambient air
than that indicated by the manufacturer’s

11
Final version, December, 1996

temperature of 40 degrees C. Figure III-3 below the higher pressure. In addition to design
shows the variation in capability of a particular differences, the age of the unit, maintenance
306 MVA hydrogen cooled generator (at 100% cycles, and relative duty all affect the leakage
terminal voltage). The mechanical power supply rate at a given pressure.
capability is superimposed to show the limitations
of the steam supply system. The way in which Third, it is important that the generator's hot spot
reactive power capability increases with temperatures be somehow monitored, either
hydrogen pressure is easily seen. directly or indirectly. Average temperature, such
as hot gas temperature, average rotor winding
Mvar 200 60 temperature, etc., provide some information, but
45 H2 Pressure (PSIG) these are not hot spot temperatures. Operating
30
Unit Supplies Rotor Current Limit close to the rated capability curves necessitates
VARS
(Over excited) having this additional information because of the
100 Stator Current Limit potential for causing serious damage due to local
heating above rated temperature. Section III D b)
Real Power
(MW)
below discusses some techniques of rotor
0
0 100 200 300
temperature measurement presently being
investigated.

-100 Finally, if a generator has been derated in its


Stator end winding
output for hydrogen leakage problems, it is likely
Unit Absorbs
VARS heating limit that the control and protective devices have been
(under excited)
-200 reset accordingly. Settings of control and
Mechanical Power Limit
protective devices may have to be suitably
adjusted and tested to ensure coordination with
Figure III-3 306 MVA Generator Capability
each other and generator capability before the
Diagram (at various H2 pressures)
machine can be depended upon to provide
additional reactive capability.
There are some practical issues that warrant
serious consideration before increasing C. Measurement of Dynamic Reactive
hydrogen pressure to increase reactive power Power Reserve
supply capability. The outputs of dynamic sources of reactive
power such as synchronous condensers and
First, it is important to check with the generator generators are sometimes used in voltage
manufacturer to ensure that the capability curves collapse mitigation schemes. As discussed
furnished with the unit reflect that particular unit's earlier in this paper, when these sources are
design and are not "generic" for units of that type operating at, or near, their maximum capability,
and size. Although the generator itself may be the risk of voltage collapse is greatest. It may
capable of the heavier Var duty, the auxiliary present a challenge to the relay engineer to
systems supporting the generator and cooling measure the output of such sources as a
system may not be. percentage of their maximum capability. When
more than one source is involved, it is necessary
Second, higher hydrogen pressure generally to determine that only in-service sources, with
means increased hydrogen leakage. Depending automatic voltage regulation capabilities are used
upon the integrity of the hydrogen seals, this may in the calculation of percentage of dynamic
or may not be a problem. However, the risk of reactive capability.
explosion because of dangerous hydrogen
concentrations increases as leakage increases. One scheme described in reference 1 uses the
The seals, hydrogen pressure regulators, heat output of four strategically located synchronous
exchangers, etc. all need to be able to operate at

12
Final version, December, 1996

condensers (rated 2x100 Mvar and 2x50 Mvar) A PLC was used to calculate the average output
in conjunction with low voltages at more than one of the synchronous condensers as a percentage
key bus to initiate a load shedding scheme. The of maximum capability. A simplified logic diagram
simplified scheme logic diagram is shown in of the scheme implemented in the PLC is shown
Figure III-4 following. Staged load shedding will in Figure III-5. It should be noted that this figure
be initiated if the output of the synchronous has been simplified for clarity (as have all other
condensers at VIT is greater than a certain PLC logic diagrams in this paper). PLC logic
percentage of their maximum capability and the diagrams would normally include extensive error
voltage is low at least at two important busses checking routines, most of which are not shown in
(DMR and either SAT, or VIT) in the region. the diagrams.

It can be seen that the status of the synchronous


DMR
U/V condenser unit breaker and automatic voltage
regulator are both used to determine whether it’s
AND Shed Block 1 output should be considered as being available.
SAT The status of the voltage regulator also
U/V OR
AND t1 determines whether the output of the unit is
considered as part of the reactive power being
VIT AND Shed Block 2
delivered.
U/V t2
Shed Block 3 In Figure III-5, the quantity “Limit 1” is the rated
VIT capability of the synchronous condenser. This is
t3 shown as a fixed setting in the diagram.
MVAR
However, some of the units may be run with or
Figure III-4 - Simplified Logic diagram of an without hydrogen gas cooling. As discussed, in
automatic load shedding scheme using the previous section, the rating of the unit is
dynamic reactive power reserve as one higher when hydrogen cooling is available. A
parameter. status input for each unit is available to change
the setting of the limit depending on whether or
not hydrogen is present. However, the limit is not
Two factors complicate the determination of scaled with hydrogen pressure.
percentage of available capability that is being
generated by the synchronous condensers. For the synchronous condensers described
First, the units have different excitation systems above, the reactive output rating is relatively easy
with different gains, and different speeds of to define. However, the reactive capability of
response. They do not necessarily respond to generators is very variable. Measurement of
transmission system voltage depressions to the reactive power reserve available in a generator
same degree or in the same time frame as each can present challenges due this variation in
other. Secondly, some of the synchronous capability. Measurement of rotor current is one
condensers may not be in service, or may be indicator, since the reactive power output of the
operated in manual excitation mode, and cannot generator (operating at less than rated power
be considered as dynamic sources of reactive factor) is reached when the rotor current is at
power during any particular instant. It was continuously rated level. Conversion of
decided to consider only the output of in-service measured rotor current to generated Mvar
units, with automatic voltage regulators in service, presents a challenge however, due to the
and to use the average output of those units variation of Mvar output with real power and
expressed as a percentage of the maximum terminal voltage. Schemes can be designed
capability of all units being considered. which measure the real and reactive power
output and terminal voltage to determine how
much of the reactive capability is being used.

13
Final version, December, 1996

Start the scheme decreases. Extensive error


checking of the measuring device is important, as
Fail well as examination of failure modes and
Watchdog Alarm and block outputs
timer OK? consequences of failure.
OK

Yes
D. Excitation Control Devices
SC1 bkr
SC1 var capacity = 0 Mvar Since reactive power sources are so important to
or AVR off?
No voltage stability, then the control of these sources
is also critical. A discussion of various excitation
Set SC1
control features and their effects on voltage
Capacity = Limit 1 stability follows.

a) Manual vs. Automatic Control


Repeat for
SC2 - SC4 Modern excitation systems are controlled by one
Calc. total capacity = of two means: manual or automatic control
sum of individual systems. The term "manual control" means
capacities
direct control over the generator's main field
current with indirect regard to terminal voltage.
Measure var This is typically done by comparing the reference
inputs
field current level with a signal derived from a
var
current-sensing resistor, or current shunt, in the
Fail
measurements Alarm and block outputs leads to the generator's main field winding. Any
OK?
OK difference results in an adjustment to the
excitation until there is zero error between the
Yes
SC1
SC1 var output = 0 Mvar
two control signals. This is also sometimes
AVR off?
called current regulation.
No

The term "automatic control" means direct control


Repeat for SC2 - SC4 over the terminal voltage of the generator with
indirect regard for the field current. This is
Calculate Total output = typically done by comparing the reference level
= sum of individual
outputs with a signal derived from the generator terminal
vts. Any difference results in an adjustment to
Calculate% Total Reserve used = the excitation until there is zero error between the
(Total output / Total capacity) * 100% two control signals. This is also called voltage
regulation.
Total Yes
Time delay Enable Load
reserve used
>set point? Shedding A generator under manual control cannot
No automatically provide dynamic support to a power
system in need of more reactive power to
maintain normal voltage. In this mode the
generator is almost like a shunt capacitor bank in
Figure III-5 - Simplified Logic Diagram of providing an amount of reactive power which is
Reactive Power Output Measurement not varied continuously to regulate voltage. The
most significant difference being that the
Such schemes are complicated by the number of generator Var output may increase slightly as the
analogue inputs and calculation of limits. As system (and generator terminal) voltage declines,
complexity increases of course, the reliability of where as the shunt capacitor Var output
decreases as the square of the system voltage.

14
Final version, December, 1996

event, the time characteristic of the limiter is not


As for auxiliary control devices and regulators, changed.
there are typically only three active in manual
mode: the minimum and maximum field current Several techniques are available to measure the
limiters and a ceiling voltage limiter. The ceiling rotor temperature, including:
voltage limiter acts to limit the field current to a • Calculation of average winding temperature
level that corresponds to a safe terminal voltage by measuring the resistance (slip ring voltage
level in the event of a sudden load rejection (this divided by rotor current) This technique
field current level is typically much less than the requires special (low current) brushes to
maximum field current limit). measure the rotor voltage without being
affected by voltage drop across the brushes.
In the automatic, or voltage control, mode, As discussed earlier however, the average
minimum and maximum voltage limits are active rotor temperature is not necessarily a good
and are analogous to the minimum and maximum indicator of hot spot temperature. Thus use
current limits in current control mode. In addition, of the average temperature as a control
there are typically an overexcitation limiter (V/Hz device is limited.
limiter), a minimum excitation limiter (MEL) or
under excited reactive ampere limiter (URAL), • Measurement of winding temperature at
reactive droop control, reactive drop selected locations by resistance temperature
compensation (also called line drop or load detectors or thermocouples. This technique
compensation or LDC), Var limiter/regulator, requires a means of getting the measured
power factor limiter/regulator, and a power value off the rotating equipment to monitoring
system stabilizer. equipment. Special sliprings and brushes, or
radio transmission may be used for this
b) Overexcitation Limiter purpose. If the locations of temperature
An overexcitation limiter can take two forms: 1) a probes are carefully selected, it may be
device that limits the thermal duty of the rotor field possible to get a better indication of hot spot
circuit on a continuous current basis and 2) a temperatures than can be determined from
device that limits the effects of stator or average temperatures. However, close
transformer core iron saturation due to collaboration with the generator manufacturer
excessive generator terminal voltage, is required to ensure hottest locations are
underfrequency, or the combination of both. selected. It is also not usually economic to
retrofit temperature probes to existing
The overexcitation limiter protecting the rotor machines. Therefore use of such probes
from thermal overload is an important controller in would probably be limited to new machines.
system voltage stability. It usually is disabled in
the transient time frame to allow the excitation • On salient pole generators where large
system to force several times the rated voltage portions of the rotor windings are exposed, it
across the rotor winding and more than rated is possible to measure the temperature of the
continuous current, to help retain transient ends of the windings by infrared scanners
stability. After a few seconds, the limiter is mounted on the stator. These measurements
activated in an inverse time function - the higher will however give average temperatures of
the rotor current, the sooner the limiter is portions of the winding, and similar concerns
activated. The limiter brings the continuous rotor over lack of knowledge of hot spot
current down to, or just below, rated level to temperatures as for the winding resistance
ensure the rotor is not overheated by excessive measurement arise. The technique does
current. The limiter acts without regard as to however allow temperatures of individual
what the actual rotor temperature is. Even if the poles to be monitored.
rotor was very cool before the overexcitation

15
Final version, December, 1996

Rotor temperature measurement is not yet too-low a level of excitation. The MEL needs to
sufficiently reliable for widespread use in be carefully set, coordinating with the generator's
overexcitation control systems. Reference [2] reactive capability curve, the system's steady
describes one application. It is possible that as state stability limit, and the generator's loss of
measurement techniques mature, supplementary field relay. This control function is most important
temperature control may be feasible to extract under conditions of high system voltage, when the
more reactive power from a given generator. generator is operating at low excitation levels to
However, concerns over operating at the limits of absorb the maximum amount of reactive power.
a generator capability (as mentioned in sub-
section B.2 above) must always be weighed Since the MEL is only functional when the voltage
against possible marginal increases in reactive being regulated is higher than the reference
capability. It is likely that temperature monitoring setting, it may not be a critical function during a
will find its optimum application in short term voltage collapse scenario. However, when
overload capability. voltage stability is lost, it is possible for system
voltage to rise above acceptable levels. Such a
The V/Hz limiter is a device that protects the circumstance might happen if too much load is
generator stator and directly connected disconnected during a voltage depression, or too
transformers (main power transformer and unit much capacitance is added to try to boost system
auxiliary transformer) from excessive flux levels voltage. In such cases, proper operation of the
(with the high flux levels being indicated by high MEL, and its coordination with the loss of
ratio of volts to Hertz). When the windings of a excitation protection may be critical in restoring
generator or transformer are exposed to such a voltage stability.
condition, the core iron saturates and magnetic
flux escapes from the intended magnetic path to d) Reactive Droop Control and Load
penetrate the surrounding structural steel where Compensation (LDC)
induced currents can cause excessive I2R These are addressed together here because
heating which may result in failure of the they are closely related, but have opposite
generator or transformer. The V/Hz limiter effects. A control voltage that is proportional to
ensures that dangerously high levels of excitation the reactive power generated by the machine is
do not persist. For instance, it may be required applied to the sensed terminal voltage being
to operate to limit generator terminal voltage to a supplied to the voltage regulator. With reactive
safe level under conditions of depressed droop control, this control voltage is added to the
transmission system voltage when the generator sensed terminal voltage causing the regulator to
is producing a large amount of reactive power. sense too high a feedback voltage, resulting in a
The probability of overexcitation is more likely decrease in excitation. With load compensation,
when load compensation is being applied, as the this control voltage is subtracted from the sensed
automatic voltage regulator is not regulating terminal voltage causing the regulator to sense
terminal voltage under this condition. too low a feedback voltage, resulting in an
Coordination of this control device with the V/Hz increase in excitation.
protective relay (if installed) is necessary to avoid
unit trips for conditions that the limiter will safely With reactive droop control, the end result is a
respond to. sharing of the voltage regulation of a bus to which
multiple generators are connected in parallel.
c) Minimum Excitation Limiter Without droop, the voltage regulators would be
The MEL, or URAL, reduces the probability of a unstable as more than one regulator would
generator losing synchronism with the power attempt to control the same voltage. The
system due to too-low a level of excitation. It is machines would just circulate large quantities of
also intended to prevent generator core end iron Vars, and voltage regulation would be poor.
damage due to stator field fringing resulting from Droop is critical for generators bussed together,

16
Final version, December, 1996

but it needs to be set carefully so that adequate excitation as necessary to control voltage without
voltage levels are maintained. That is, too much regard to Var swings.
droop will result in voltage levels unacceptably
below nominal. The Var regulator is different from the limiter.
This control feature, rather than controlling the
With load compensation, the end result is better voltage to a set point, controls the Var output of
regulation of a point in the system somewhat the machine to a set point. Var regulation is well-
remote from the terminals of the machine. suited to a system that has a steady, baseload
Without load compensation, the controlled point is need for Var support.
the point where the terminal voltage is sensed -
the point where the generator vts tap into the Both of these devices have application with
isolated phase bus. Load compensation moves smaller machines ("small" relative to the
the controlled point out closer to the main power connected system) because of their inability to
transformer's high voltage terminals by significantly alter the transmission bus voltage,
compensating for a portion of the voltage drop regardless of their Var loading. However, it
that occurs across the transformer due to the should be recognized that when these limiters are
loading of the generator. This must be set in operation, the generator will not act to help
carefully to avoid wide reactive power swings on support system voltage during emergencies.
the machine that occur if it attempts to control
voltage at a point too far away in the system, f) Power Factor Limiter/Regulator
electrically speaking. The power factor limiter acts to keep the power
factor of a given machine within specified limits
A plant with more than one generator can be while on voltage control. This device is especially
made to control the voltage on the transmission useful in situations where economic penalties are
system some distance from the plant by the use imposed for operating with a power factor outside
of joint Var control (JVC) equipment. JVC allows of a published acceptable range.
several generators to control the voltage at a
single point without reactive power swings which The power factor regulator, like the Var regulator,
would result from independent voltage control controls to a specific power factor without regard
action on each of the generators. This for the voltage. This can be troublesome for the
equipment ensures that all generators take an bus voltage as the excitation will vary, and hence
equal share of reactive power as they attempt to the voltage will vary, with changes in generator
control the voltage at a common point. watt loading. Again, this is more typically used
with smaller generators or with large synchronous
Compensation for at least part of the reactive motors seeking to operate at or near unity power
drop in a generator step up transformer is one factor (for economic or other reasons).
way of allowing generators to more directly
control system voltage. In addition to the stability The increasing penetration of non utility
concerns, the voltage at the generator terminals generators in power systems results in
must also be controlled to within acceptable limits. increasing effect of their excitation control
Given the wide variation in generator reactive systems on power system voltage stability. Care
power capability, it may be necessary to depend is required to ensure their reactive power
on other controllers such as the volts/Hz limiter or capability is not incorrectly assumed to be
MEL for additional control. dynamic, when in fact they may be operating
under a power factor controller or Var limiter that
e) Var Limiter/Regulator restricts their reactive output to much less than
The Var limiter acts to limit the Var loading of a the units are capable of producing.
generator if the output reaches its threshold.
Otherwise, the regulator is free to adjust

17
Final version, December, 1996

g) Power System Stabilizer E. Protection Issues


Reference [19] quotes - “Modern generating
units equipped with high gain voltage regulators 1. Generator Protection Relays
enhance transient stability (the ability to recover It is important that generator and auxiliary
from large disturbances), but tend to detract from protection relays coordinate with excitation
steady-state stability (the ability to recover from control functions. Lack of such coordination has
small disturbances about the steady-state often been a factor in voltage collapse or near
operating condition). Power System Stabilizers collapse situations. Some critical protective
(PSS) improve steady-state stability by providing relays are loss-of-field, volts/Hz, rotor overload,
damping of power system modes of oscillation via excitation system overload, and auxiliary
modulation of generator excitation." So undervoltage protection.
described, the PSS is a device that reduces low-
frequency oscillations of a generator rotor The loss-of-field relay must coordinate with the
(typically in the range of 0.1 to 2.5 Hz). MEL on a dynamic basis as well as on a steady
Regardless of how it measures the speed state basis. The time delay in which an MEL can
changes (electrical frequency or mechanical act to limit under excitation may not be stated in
speed), the PSS is tuned to output a control exciter application guides. Under transient
voltage that is in phase with the speed changes conditions it is possible for the operating point of
that acts to increase excitation if the speed a generator to suddenly enter a region beyond
change is in the positive (speed-increasing) the MEL or loss of field protection
direction and decrease excitation if the speed characteristics. If the time delay of the loss of
change is in the negative (speed-decreasing) field relay is too short, or the MEL takes too long
direction. The increased excitation tightens the to operate, miscoordination and unnecessary
rotor's coupling with the power system, providing loss of the generator can occur. The lack of
a retarding torque that tends to slow the rotor, coordination can easily be missed if the exciter
bringing it back to nominal speed. Decreased gain or feedback settings are adjusted after
excitation loosens the rotor's coupling with the commissioning without subsequent check of the
power system, providing an accelerating torque speed of operation of the control function.
that tends to let the rotor accelerate back up to Regular exercising of the generator to its MEL
nominal speed. The purpose of the PSS is to control point will help minimize the risk of
minimize generator "hunting" and the attendant miscoordination.
low frequency power surges, thereby stabilizing
system voltage and enhancing system stability. Rotor and exciter overload protections must
As larger machines have far greater impact on coordinate with maximum excitation limiters,
the system and on each other in this regard, again on a dynamic basis as well as on a steady
PSS's are most effective on such large state basis. Since overload protection time
machines. PSS’s are presently being fitted on delays are often somewhat longer than loss-of-
many existing larger machines, and most new field protection delays, the speed of response of
machines which can significantly impact low the maximum excitation control is not of as great
frequency oscillations. a cause of concern as that of the MEL.
However, the possibility for miscoordination is still
PSS's must be correctly set with regard to their present. Exciter overcurrent protection settings
gain and phase lead parameters to avoid may be applied with more concern about short
exacerbating the oscillation problem. There are circuit sensitivity than with rotor overload
no protective elements that the PSS must capability. Further, if such protection is provided
coordinate with. by electromechanical relays, their accuracy
around the pickup current level may not be as
good as the accuracy of the overexcitation
limiter. Exercising of the generator at its

18
Final version, December, 1996

maximum excitation limit is the best way to distance and phase overcurrent relays, however,
ensure coordination is maintained. can be affected by excitation.

Dynamic coordination of the volts/Hz protection In the case of the phase distance relay,
with the volts/Hz controller is relatively easily depending upon its reach, the combination of low
achieved, because their time/flux characteristics system voltage (due to a collapse) and high load
are both well defined. A point of concern can (due to high Var output in response to the
arise when the volts/Hz protection is provided by collapsing voltage) could be interpreted as a low
one or two definite time relays set at specific magnitude three phase fault resulting in an
levels of volts/Hz. It may be difficult to coordinate undesirable trip. This is a problem especially if
the definite time characteristics with inverse time the generator is connected to a stiff system
characteristics of the control device. It is of because of the generator's relative inability to
course also important to coordinate the volts/Hz control the system voltage regardless of its
protection with the maximum voltage regulator excitation level.
control voltage. The maximum voltage regulator
setting may be very close to the maximum rated In the case of the phase overcurrent relays, they
continuous operating voltage, leaving little room are typically set with a pickup below rated load,
for the volts/Hz protection pick up point to fit relying on healthy voltage as a restraint. With the
between the two limits. same scenario as in the case above, if the
voltage falls below the set-point, the relay could
Auxiliary equipment may be protected by operate on load, again causing an undesirable
undervoltage relays to ensure the generator is trip. As with the distance relay, this is more likely
shut down safely before any essential auxiliary to occur when the generator is connected to a
equipment stalls or becomes disconnected due to stiff system.
low voltage. It is possible that low terminal
voltage could impose a limit in the underexcited It should be noted that undesirable trips could
region that the MEL must coordinate with. Since occur under low excitation conditions, as well,
the undervoltage protection would normally have because low excitation translates to low terminal
a significant time delay, dynamic coordination voltage, especially when the generator is
with the MEL may not be as much of a concern connected to a weak system. However, the
as static coordination. combination of low voltage due to
underexcitation, and heavy load is unlikely, so this
In spite of the difficulties in operating generators is seldom a problem.
at reactive power limits, regular testing of the
coordination of protection and control devices at The probability of undesirable trips of backup
those limits remains the best way of ensuring protection systems is reduced by detailed
important reactive power reserves are available application studies when applying such protection
when required during system emergencies. and when calculating settings. System
Reference [17] gives further details on benefits simulations for multiple or low probability
and difficulties of testing generators at reactive contingencies may be required to ensure the
power limits. backup devices are secure under such
conditions. If time delays of backup relays are
2. System Backup Relays short, dynamic system simulations may be
System backup relays are generally of three required as well as static simulations.
types: phase distance, phase overcurrent, and
ground overcurrent. Of these, the ground If reliable backup transmission protection exists
overcurrent is not affected by excitation levels, at the switching substation, backup phase
so it will not be addressed here. The phase distance relays may not be needed.
Consideration could be given to either removing
such relays, or reducing their reach such that

19
Final version, December, 1996

undesirable trippings under low voltage conditions nearby synchronous condensers, or static Var
are highly unlikely. compensators.

IV. Switched Capacitance BC Hydro uses a PLC to coordinate the


measurement of the output of synchronous
Switched capacitance is a method of providing condensers (rated 2x100 Mvar and 2x50 Mvar)
reactive power support to maintain voltages within and the switching of 2x50 Mvar capacitor banks.
tolerable limits. It is applied in different time Figure IV-1 shows the simplified logic diagram of
frames. Switching must be automatic to be the PLC used to control the capacitors.
effective in the transient time frames described in
Figure II-4 but may be manual or automatic for The capacitor banks are switched if the total
slower collapses. An important factor in the output exceeds 60% of the rating of units in
application of switched capacitors is that the service with automatic voltage regulators. The
voltage does not rise above tolerable limits in the PLC is used to calculate the output from all units.
post disturbance state. If the output is high, and system voltage is not too
high, one capacitor bank will be switched on. If
A. Long-term Time Frame. the output is very high, and the voltage is not too
Manual switching, or conventional voltage control high, both capacitors will be switched on. The
devices are often adequate for switching same device automatically switches the
capacitors in the longer time frame. Capacitors capacitors off if the output of the synchronous
are considered to be static reactive power condensers goes low, and if the system voltage
sources when applied for long term voltage is not also low. By this means, the utility can
control. Static capacitors may be switched control the system such that the synchronous
seasonally, weekly, or daily for this type of condenser is available for dynamic supply of
application, where the switching devices may be reactive power by keeping the condenser output
circuit breakers or circuit switchers. The design low under normal steady state conditions.
of the capacitor installation must consider the
possible speed and frequency of switching, as This is an example of using relatively slow speed
well as the voltage support requirements. Very switching of a capacitor to increase reactive
frequent switching would put a significant amount reserve earlier than required for an emergency
of wear on the switching device. situation. Early switching of static sources
means more dynamic power is available for quick
When the time frame of the voltage stability support during emergencies.
phenomena approaches the transient region,
automatic switching is almost always required. To minimize wear and tear on the switching
Capacitors are often switched by voltage relays equipment, the automatic control is sometimes
with time delays. To achieve the higher switching unidirectional. The reactive equipment is
speed, additional controls may be required to automatically switched on or off, to quickly
prevent excessive switching and wear on the regulate the voltage excursion, and operator
switching device. The voltage relays used for control is used to restore normal conditions when
switching may not be the conventional voltage the disturbance is over. This is a major
control relays. They may need higher accuracy, difference between special schemes and normal
or different techniques, similar to those used for voltage control devices which switch reactive
undervoltage load shedding. For instance, the equipment after very long time delays.
requirement for switching may need the three
phase voltages to be inside a certain window, or
the requirement may be controlled by the status
of other dynamic reactive power sources such as

20
Final version, December, 1996

Start

Watchdog Fail
OK?
Measure var
inputs
Measured vars Fail
OK?
Measure volt
Inputs
Find valid Fail
voltage Alarm and block outputs

Yes Yes
Mvar>20 & Time Delay Switch CX1 on
CX1 off?
V<141kV?
No No
Yes
CX2 off? Switch CX2 on

No

Yes Yes
Mva<-45 & Time Delay Switch CX1 off
CX1 on?
V>135kV?
No No
Yes
CX2 on? Switch CX2 off

No

Yes Yes
Mvar>70 & Time Delay Switch CX1 on
CX1 off?
V<141kV?
No No

Yes
CX2 off? Switch CX2 on

No

Yes Yes
Mvar<-95 & Time Delay Switch CX1 off
CX1 on?
V>135kV?
No No

Yes
CX2 on? Switch CX2 off

No

Figure IV-1 Logic Diagram for medium speed PLC capacitor control
device.

B. Transient Time Frame prevent unnecessary switching. Some control


The complexity and sophistication of the control schemes are described below, as examples of
device usually increases as the time frame of schemes used for capacitor switching in the
switching approaches transient levels. Since transient time frame.
voltage control is the objective, voltage sensing
devices are the prime tools used. However,
additional supervisory devices are required to

21
Final version, December, 1996

1. Capacitor Switching in 0.75 Seconds three phase voltages are below the threshold.
Reference [5] describes an undervoltage This reduces the probability of switching for
capacitor switching scheme installed by one utility unbalanced faults such as resistive single line to
which operates in conjunction with a load ground faults which might be cleared in longer
shedding scheme to avoid the possibility of than 12 cycles. A programmable logic controller
voltage collapse. This scheme is intended to (PLC) was selected to perform the measuring
insert a capacitor bank if the voltage drops due to and logical functions as shown in Figure IV-2
loss of a major system tie transformer. following.

The bank is connected in 0.75 seconds in an 3. Capacitor Switching in 0.15 Seconds


attempt to restore voltages before load has to be Mechanically switched capacitors can sometimes
shed. The 0.75 second delay is long enough to be applied for very fast voltage support. In such
override voltage depressions due to multi-phase cases, the control scheme increases in
faults on the 161 kV subtransmission system complexity. For instance, in some cases where
which are normally cleared in less than 0.5 DC transmission is an important source of
seconds. However the time delay is not long power, adequate reactive power is required to
enough to override voltage depressions due to support voltages at the receiving terminal after
single line to ground faults on the 161 kV system transient voltage depressions due to abnormally
or any type of fault on the 46 kV or 13 kV cleared faults.
distribution systems.
In one case, a very fast capacitor switching
Supervision elements are used to block capacitor scheme is applied to support the voltage at a
switching for faults which might be cleared in receiving terminal if the 345 kV (ac) system
longer than 0.75 seconds. A zero sequence suffers a fault with associated failure of a single
overvoltage detector is used as a supervision pole of the clearing breaker (with three phase
element for 161 kV ground faults, and breaker failure not being considered a credible
overcurrent fault detectors are used similarly, to contingency). In this case switching of the
block the switching scheme if the voltage is capacitor bank is required if the fault is not
depressed due to a distribution system multi- cleared within 9 cycles. Since the probable
phase or single line to ground fault. All measuring situation is a single line to ground fault, the
and logic functions are accomplished with capacitors must be switched for unbalanced
discrete electromechanical relays in this scheme. voltages. In this case, a directional negative
sequence overcurrent relay looking away from
2. Capacitor Switching in 0.2 Seconds the 345 kV system is used to block switching if
One utility uses fast capacitor switching to the unbalanced fault is not on that system.
maintain voltages on two 230 kV tie lines which Switching is also initiated for three phase faults
are overlaid by a 500 kV line. If the 500 kV line anywhere on the system (if clearing is not
trips out during high load conditions, there is a achieved within 14 cycles.
danger that low voltages on the underlying 230 kV
lines will result in loss of angular stability and/or
tripping by the line protection systems. Groups of
capacitors are located at different substations for
each of the two 230 kV lines. One substation has
12x40 Mvar capacitor banks, and the other has
6x30 Mvar banks. The capacitor banks are
switched by circuit breakers. Switching must be
accomplished very quickly, but not within normal
230 kV multiphase fault clearing times (less than
12 cycles). Switching is not initiated unless all

22
Final version, December, 1996

Start

Measure 3 Ph
Voltage
No No
No Any Yes Yes Yes
Voltage Capacitors Voltage Voltage
<98%? "on"? >107%? >110%?
Yes No

No Any Trip one Trip two


avail. caps capacitor capacitors
"off"?
Yes
Wait 12 cycles Wait 6 cycles

Reset No Voltage
Timer <98%?
Yes

Voltage No
<95%?
Yes
>1 No
Reset avail. caps
Timer "off"?
Yes
Switch on 2 Switch on 1
capacitors capacitor

Wait 12 cycles

No Voltage
<98%?
Yes
No Any
avail. caps
"off"?
Yes

Figure IV-2 Logic Diagram for PLC High Speed Capacitor Control Device

The above summarizes some of the stand alone V. Automatic Reclosing


applications of capacitor switching for voltage
control in different time frames. The application
Fast reclosure of high voltage transmission is
examples also illustrate the flexibility of PLCs in
used as the first attempt to restore lost
providing a means for complex control functions.
transmission as quickly as possible to minimize
As far as time frame is concerned, it is generally
exposure to excessive and unacceptable voltage
accepted that fast action requires more
declines and to enhance the stability of the
comprehensive control to coordinate with other
system. Ontario Hydro has implemented a
power system protection and control. However,
scheme using faster than normal automatic
time frame is not the only factor as location of
reclosure to prevent voltage collapse in the event
voltage sensing is also important. Furthermore,
of a transmission line outage coincident with
capacitor switching can also be a component part
outages on other parts of the transmission
of an overall scheme in which the capacitors are
system. The reclosure attempt must occur within
not used as the first resort to mitigate voltage
1.5 seconds after the initial loss of the
collapse (as per Section V).

23
Final version, December, 1996

transmission line. This time frame is dictated by VI. Load Shedding


the effectiveness of subsequent load shedding
should the reclosure not be successful. A
Load shedding is an option that is becoming more
reclosure time of 1.175 seconds can be
widely used as a final means of avoiding system
achieved with the slowest breakers in the region
wide voltage collapse. This option is only
(closing time 0.225 s). The total reclosure time
considered when all other effective means of
includes 0.5 s dead time before reclosing the
avoiding collapse are exhausted. This option
energizing breaker (lead terminal) and 0.1 s delay
may be the only effective option for various
for closing the follow terminal on restoration of
contingencies especially if the collapse is in the
potential from the lead terminal.
transient time frame, and if load characteristics
result in no effective load relief by transformer
If reclosure is unsuccessful, and the load is high,
load tap changer control. Load shedding results
load shedding is required to ensure an
in high costs to electricity suppliers and
acceptable voltage profile. Load shedding must
consumers, therefore, power systems should be
be initiated as soon as possible after
designed to require such actions only under very
unsuccessful reclose attempt if the voltage is
rare circumstances. Load may be shed either
lower than 85% of normal levels. A total of 504
manually or automatically depending on the rate
MW distributed at nine different stations is
of voltage drop.
available for shedding. Each block of load can be
armed by operator action and will be tripped when
A. Manual Load Shedding
the local station voltage drops below a preset
value for a preset time period. The scheme is If the time frame of collapse is long-term, manual
based on monitoring the transmission voltage load shedding can be implemented to stabilize the
with undervoltage relays on either side of the voltage. This mode of operation, normally applied
main or backup potential sources (automatic under inadequate generation conditions or
transfer for loss of the main source). The insufficient Var reserve, should have preplanned
undervoltage relays are duplicated, and both guidelines and procedures for the system
relays, set to 85% of the normal operating dispatchers to implement load shedding manually.
voltage, must operate to shed load. The load is System studies can provide load sensitivity
shed if the undervoltage condition persists for analyses from which the critical voltage can be
more than 1.5 seconds. Load shedding is determined to start load shedding. Another
blocked if both the main and alternate sources option to assist system operators for fast action
are lost (as detected by another undervoltage is to preprogram blocks of loads on the
relay). dispatcher control console of the SCADA
system. Dispatchers can select a particular
A total of 36 capacitor banks (both transmission block of load in a specific area requiring load
and distribution banks) in 17 transformer stations shedding to control the voltage drop. The blocks
in the region are equipped with automatic of load can also be divided into several
switching features that are voltage and time subgroups depending on sensitivity of the load,
dependent. The capacitors maintain the voltage so that execution of the manual load shedding
levels at or above the minimum acceptable level can be carried out in steps or in rolling sequence.
of about 90% of nominal. A predetermined
sequence of capacitor switching can occur up to A major disadvantage of relying on manual load
8 seconds after the initial loss of transmission. shedding is that it places a severe burden on
The effect of capacitor switching following load system operators to recognize an approaching
shedding is that of fine tuning the voltage levels to voltage stability problem and to act quickly
within the normal band. enough to avoid a major collapse. Even with the
most comprehensive preplanned guidelines,
there is a danger that the particular condition that
arises may not fall within the guidelines clearly

24
Final version, December, 1996

enough for prompt action. However, when short manual load shedding would be too slow to
term operational planning studies (time frame prevent a voltage collapse. Automatic load
less than a week) show the possibility of collapse shedding must be used to quickly arrest a fast
due to expected load and actual contingencies, voltage drop and allow the voltage to recover to
manual shedding can be applied with good an acceptable level before voltage collapse can
results. occur.

B. Load Shedding as Part of Energy Undervoltage detectors are often used to initiate
Management Systems (EMS) automatic load shedding. For low voltage events
Some utilities have installed remote controlled which do not lead to collapse (such as during a
devices to control the residential air conditioners, normally cleared system fault), these detectors
water heaters, and other loads as a part of must not operate in order to prevent nuisance
energy conservation effort to reduce system tripping of customer load. Security of the
peak demand. During the system peak load undervoltage detectors can be increased by
condition, a signal will be broadcasted to selected applying multiple phase detection, proper time
areas to cycle the interruptible loads off for 15- coordination between fault clearing and time
minute intervals. This short interruption will not delay for load shedding, and use of fault detection
drastically change the room or water temperature relays to inhibit load shedding. Reliability of load
to cause significant discomfort or inconvenience shedding to prevent voltage collapse can be
to customers. enhanced by use of other indicators than voltage
magnitude such as voltage and power sensitivity
This program is normally initiated by system factors or other forms of voltage stability indices.
dispatchers or by EMS based on the need of the
system. This same program can be used for Developing appropriate settings for the
load shedding either manually by dispatcher undervoltage detectors and time delays are
control or automatically from EMS if proper logic challenging problems. It might require intensive
can be programmed to detect a voltage instability. network analysis to find the desired values to
provide optimum coordination between load
To be effective, load shedding from this program shedding and voltage collapse. Generally, the
requires participation of large groups of settings are in the range of 85 to 95 percent of
customers. Such participation is unlikely to the operating voltages, with time delays ranging
materialize unless there is some sort of financial from tens of cycles to minutes [1,5,20]. The
incentive (such as reduced rates) for sensitivity of the load to the voltage level has a
participation. This type of action is most likely to great impact on the settings.
be considered when utilities can defer large
amounts of capital expenditure to reinforce For example, air-conditioning load is sensitive to
transmission if the program is implemented. In low voltage and can aggravate the system
order to get a reasonable return on the loss of voltage once the voltage drops below a level
revenue from financial incentives, operation of causing the air conditioners to stall [21]. The
this type of load shedding scheme would be aggregated locked rotor currents from stalled air-
expected much more often than the alternative of conditioners, which are almost entirely inductive,
disconnecting large blocks of load under extreme could drag the system voltage down if they
emergency conditions. remain connected to the system. Therefore, the
time delay for this type of load shedding may
C. Automatic Load Shedding need to be much shorter than others.
When the voltage instability is caused by sudden
loss of critical transmission equipment or Var On the other hand, if the system is capable of
generating equipment, the lead-time prior to a operating in the low voltage condition for long
voltage collapse will be very short. Therefore, enough, stalled motor load will disconnect itself by
it’s overload protection. Such disconnection was

25
Final version, December, 1996

observed in the Philadelphia Electric Company detectors are set very close to normal operating
low voltage incident [10]. The concern was voltages, it is sometimes necessary to ensure
expressed in analysis of that incident that if undervoltage relays sense voltages at very stiff
automatic load shedding had been applied, too busses. Stiff busses will be better regulated and
much load might have been disconnected, and subject to less disturbance (due to local transient
overvoltages could have resulted. conditions such as faults), than weaker busses.

Automatic load shedding to arrest frequency Use of multiple sensing relays can greatly
declines leading to possible blackout is widely increase reliability of underfrequency and
accepted and required in many interconnected undervoltage load shedding schemes. In some
systems. This type of protection system has cases, system studies may show that small
proven to be very reliable in not shedding load frequency changes are a necessary condition for
unnecessarily, and in shedding load when disturbances leading to voltage collapse. In such
required. Its success is due in part to the close cases, supervision of load shedding by
tolerances at which system frequency is normally underfrequency detectors can enhance security
maintained, and the reliability of deviation outside of the load shedding scheme. For example,
those tolerances as an indicator of serious Florida Power and Light supervise a load
generation/load mismatch. shedding scheme by underfrequency relays set
at 59.9 Hz. These relays trigger a latched relay
The comparison of settings of relays for that stays latched for up to a minute after the
underfrequency load shedding with those of frequency excursion. Load shedding is allowed if
relays for undervoltage load shedding is the latched relay is operated at the same time
interesting. In order for each member company that the reactive power deficiency decision is
of a coordinated council to shed the appropriate transmitted to the load supply point [4].
load, given the same frequency conditions, the
settings for the underfrequency relays and their Some relaying considerations associated with
associated timers are generally programmed to load shedding schemes:
trip essentially at the same time. Staged
shedding of load is achieved by programming the • Undervoltage detectors operate very close to
settings of various relays into different steps of normal operating voltages. Caution is
frequencies. However, undervoltage detectors required in setting and application to ensure
for automatic load shedding may be set at voltage reliability. Relays must be very accurate, and
levels close to each other, but spread into steps must be connected to accurate voltage
with different time delays (considerably longer transformers. The relay dropout ratio and
than underfrequency relay trip time). dropout time are important factors. If the
Underfrequency relays are often inhibited during voltage is depressed and restored due to a
undervoltage conditions to ensure response only transient event, the relays must reset before
to system wide frequency excursions. load shedding is initiated. To minimize the
response of relays to voltage depressions
Frequency decline due to generation/load due to unbalanced faults, three phase
mismatch is uniform over a wide area. measurement (all three phases must operate)
Underfrequency detectors with similar or identical or positive sequence voltage measurement
settings can be applied throughout a system. may be employed. To avoid load shedding
Voltage magnitude during a voltage instability for loss of potential supply, a window
incident is much more variable in the area under measuring principle may be employed. If the
consideration. Undervoltage detectors usually voltage is depressed to a very low level,
have to be installed in specific areas and (such as might occur for loss of potential
locations within a system, depending on system supply), no amount of load shedding is going
studies to identify the areas with a high probability to restore voltage to near normal, therefore
of voltage collapse. Since undervoltage

26
Final version, December, 1996

the voltage detector may be set to ignore near voltage collapse conditions. System
such voltages. simulations can produce sensitivity analyses
from which the critical blocks of load may be
• Steady state phase voltage unbalance due to determined.
heavy loading on untransposed lines is also a
factor in voltage measurement. Since • Unexpected loss of load (such as tripping of
undervoltage relay settings are very close to motor starters) in addition to intentional
normal operating levels, phase voltage disconnection of load, may result in
unbalance of only a few percent can be excessive loss of load. This excessive loss
significant. Measurement of all three phase of load, in addition to mitigation measures
voltages or use of positive sequence voltage such as switching on of shunt capacitors,
are techniques used to minimize the effects may result in unacceptably high voltages
of steady state phase voltage unbalance. during loss of voltage stability incidents.

• Interaction between manual and automatic • Automatic load restoration may be


load shedding schemes could be a problem. considered as a means of minimizing
It is preferable that there be no interaction excessively high voltages after load shedding.
between the two schemes. Such Load should be restored in stages, to prevent
independence can be assured by setting time subsequent secondary collapses. Automatic
delays of automatic schemes so short that load shedding and restoration was helpful in
manual actions might not reasonably be stabilizing voltages in an incident in the
expected to overlap. Figure II-4 shows Arizona Public Service and Salt River Project
system operator intervention may be (SRP) areas on 29 July, 1995. In this
expected after 1 minute; so automatic incident, an unusually slowly cleared fault led
schemes should have completed their action to air conditioner motor load stalling. A
by this time. severe and sustained region wide voltage
drop was arrested in part by undervoltage
• A combination of manual and automatic load initiated load shedding of 1400 MW of SRP
shedding is achieved by manually arming load. When voltages started to rise after load
automatic schemes when off-line studies or shedding, much of the load was automatically
on line indicators show that the possibility of restored within 20 seconds. Automatic load
voltage collapse is increasing. Manual restoration schemes must be carefully
control of automatic load shedding schemes applied to avoid causing widely fluctuating
is usually achieved by use of SCADA voltages during voltage instability.
systems. The advantage of manual
arming/disarming is that the security of the • Future implementation of automatic load
scheme is increased by blocking it during shedding schemes may involve more detailed
normal conditions. The disadvantage is that results of network analysis in line with recent
dependability is decreased under fast understanding of the voltage collapse
collapse scenarios by having the need for phenomenon. it may be coupled with faster
operator action before the scheme can monitoring systems, and setting points may
function. be calculated on sensitivity analysis of
reactive powers and voltages rather than
• Proper selection of blocks of load and isolated measurements of voltage, or
duration of shedding for the manual load frequency. The choice of loads to be shed in
shedding schemes is important. If manual such schemes may be dictated by the nature
load shedding is applied to remedy of active/reactive power imbalance in the
inadequate generation conditions, it should system, and should not interact with existing
have somewhat different objectives under schemes or priority loads.

27
Final version, December, 1996

VII. Distribution Voltage Control to this regulating effect, the LTC is an important
part of the overall voltage collapse scenario.
A. General
For the more frequent case, where the real
Electric utilities utilize load tapchangers (LTC) to power loads have some voltage dependency, the
maintain customer voltage levels as the system LTC can be utilized to reduce the severity of the
conditions change. Typically, as load increases, voltage collapse if appropriate control operation
the LTC will act to raise the tap position in order can be obtained. Blocking operation of the LTC
to maintain the voltage level. The LTC control has been widely offered as a method to reduce
relay will be set to operate in one of two modes - the negative effect on the system. Load voltage
bus voltage regulation or load center voltage reduction can be used to reduce the loading on
regulation using the line drop compensator. the system. This is similar to the peak shaving
systems widely used at many utilities. Therefore
Load Center voltage regulation requires a line the load tapchanger may be both a cause and a
drop compensator to regulate the voltage at the partial solution to the problem of voltage collapse.
load center. Transformers at distribution
substations are more likely to use load center B. LTC Blocking Schemes
voltage regulation than those at transmission
The simplest method to eliminate the LTC as a
substations. Therefore, it is important to know
contributor to voltage collapse is to block the
the mode of LTC control operation when
control’s automatic raise operation during any
modeling the effect of the tapchanging
period where voltage collapse appears to be a
transformer operation during voltage collapse.
concern. The decision to temporarily block the
tapchanger can be made using locally derived
During a period of voltage collapse, the LTC
information or can be made at a central location
control relays will detect a low voltage and begin
and the supervisory system can then send a
timing to raise the tap position of the transformer.
blocking signal to the unit. This action may result
When the voltage collapse occurs slowly, the
in a period of low voltage on the affected loads.
controls will time out and begin to raise the
The effect of the reduced supply voltages on
transformer tap position. Assuming no change in
power quality to customers in the whole service
the load on the transformer during this period, the
area must be weighed against the possible
LTC can often be considered a constant power
alternative of complete disconnection of some
load (i.e., α and β are near zero) as long as the
customers in a smaller area. Tap changer
tapchanger can maintain a constant load voltage.
blocking will be more effective for voltage decays
Since the primary voltage level drops, the current
slower than the transient time frame. It will also
flow in the transmission system is increased to
be more effective on loads that have a relatively
maintain the load power. This increasing current
high voltage dependency (i.e., α approaches 2
flow will further reduce the transmission system
and β is considerably higher). In cases where
voltage, making the voltage collapse more
the steady state value of β is high (such as the
severe.
value of 4 as seen in Figure II-5), the reduction of
reactive power demand due to reduced
In some cases, tap changers can also have a
distribution voltage will be very significant in
beneficial effect. Consider for instance, a case
helping keep transmission voltages up.
where a transformer is supplying predominantly
motor load with power factor correction
Local blocking schemes are implemented using
capacitors. The LTC keeps the supply voltage
voltage relays and timers to sense the voltage
high and hence does not affect the real power
level on the high voltage bus at the substation.
consumption (which is relatively independent of
The setpoint voltage is usually chosen to be a
voltage), and also maximizes the reactive support
level that is less than that which occurs during
from the power factor correction capacitors. Due
maximum acceptable overload conditions.

28
Final version, December, 1996

Blocking is initiated if the abnormal undervoltage transformer must be accurately estimated so that
condition exists longer than a predetermined the voltage calculation will be accurate. This
time. The time period may vary from 1 to several information can be derived via several methods
seconds. The LTC is unblocked when the and must be then utilized by the measuring relay.
voltage has recovered to an acceptable level for The transformer load current, series reactance,
a predetermined period of time, typically 5 and series resistance are also required to
seconds. Since the blocking action will be estimate the voltage drop due to load current. If
removed if the voltage recovers, usually a single load current is near unity power factor, the series
phase-phase voltage measurement is adequate resistance of the transformer will be the most
for this scheme. important factor in its impedance. If there is
significant reactive power flow through the
A coordinated blocking scheme can be utilized to transformer, the voltage drop across the series
block operation of LTC’s in an area where reactance will also be important. By combining
voltage instability is imminent. The coordinated the effects of the variable tap position of the
scheme can be accomplished with undervoltage transformer and the voltage drop caused by load
schemes acting independently (as described current, a reasonably accurate estimation of the
above) in a coordinated fashion at various high voltage level can be made.
stations within a region, or it can be a centralized
scheme that recognizes a pattern of low voltages C. Distribution Voltage Reduction
at key locations. In a centralized scheme, the Many utilities have implemented systems to
LTC blocking can be implemented in substations reduce distribution voltages during peak load
throughout the affected region, even if the voltage periods. The reduction in voltage is used to
at all locations is not yet below a specific reduce the system peak demand. In a similar
threshold. The key to operation of a centralized fashion the voltage reduction concept can be
system is the reliability of the communications used during periods where voltage stability
system. The data needed for decision making margins are insufficient.
must be collected at the central location for
analysis. Control decisions must then be sent to An example of voltage reductions for peak
each affected transformer location. shaving follows:

The effectiveness of an LTC blocking scheme at Voltage reductions represent an operating tool
the transmission level will largely depend on that may be included in load management
whether distribution transformers are LTC-type. programs. The Pennsylvania-New Jersey-
If the distribution transformers are LTC-type, Maryland Interconnection (PJM) utilizes 3%
additional measures are required to prevent their
and 5% voltage reductions to aid in curtailing
action from negating the effect of the LTC
peak load when required to provide sufficient
blocking scheme at the transmission level.
reserves to maintain tie flow schedules and
The blocking schemes described above require preserve limited energy sources. Voltage
an accurate measurement of the high voltage reductions are initiated for both capacity
level at each substation. When high side shortages and when reactive limits are
potential devices exist at the substation, this reached or exceeded. Experience has
voltage measurement can be made directly. In indicated that implementing a 5% voltage
substations that do not have potential devices on reduction on the PJM system will result in an
the high voltage, an estimation of the high voltage initial load reduction of approximately 2%.
level can be made from a voltage measurement
made on the low voltage side of the LTC The mechanics for implementing voltage
transformer. In order for this estimate to be reductions varies among the PJM member
accurate, several data items must be considered
companies since voltage control methods and
in the estimation. The tap position of the

29
Final version, December, 1996

facilities differ. In general, if load tap changing eliminating the delay typically present in the
facilities are available at distribution automatic control. In transformers, with static or
substations, tap changes or voltage schedule digital controls, voltage reduction inputs are
changes are initiated remotely by supervisory available that provide equivalent operation without
or radio control. If remote control facilities do the necessity of adding the fooler circuit. In
not exist, such action must be taken manually either case, the voltage reduction schemes
typically have one to three discrete steps
at the station. Some companies utilize load
available to the user. Typically steps of 2.5%,5%,
tap changing facilities at the subtransmission
and 7.5% of voltage reduction can be selected by
level rather than at the distribution level. In the system operator or SCADA system.
such cases, the subtransmission voltage is
reduced in order to lower the underlying During a period of potential voltage instability the
distribution voltages. In cases where voltage reduction scheme could be utilized to
automatic load tap changing is employed, reduce the system voltage to its minimum level so
control systems are used in which the tap as to reduce the load as much as possible. This
changer controller is fooled into thinking that step could be instituted prior to any load shedding
the controlled voltage is 3% or 5% high. The and could reduce the need for load shedding and
controller action subsequently automatically the corresponding load disruption. The voltage
provides the action to implement the desired reduction scheme could be implemented using a
voltage reduction. distributed or by a centralized measuring system
similar to the systems described above.
Voltage reductions during reactive D. Comparison of Voltage Reduction and
emergencies can provide the additional Blocking Schemes
benefit of increasing the connected reactive
These schemes are similar to each other in trying
support by forcing on capacitors which may to minimize the chance of complete
have not been switched into service by their disconnection of some customers by providing
associated voltage controllers. Localized slightly reduced voltage to most customers. Their
problems may occur during voltage effectiveness are both similarly dependent of
reductions due to the existence of voltage load characteristics and the time frame of voltage
sensitive customers in an area. In such decay.
cases, member companies are given the
flexibility to deviate from the voltage reduction The load characteristics are important in
directive in the specific problem areas. determining the amount of load relief that may be
expected for a given voltage depression. For
Voltage reduction schemes involve changing the loads that are predominantly motor loads, the real
setpoint of the systems distribution transformer power loss is minimal for a small voltage
LTC controls so that a lower distribution voltage depression. Thus load mix (ratio of residential,
is achieved. Several types of systems have commercial and industrial loads) is important as
been developed to implement voltage reduction. well as seasonal characteristics (air conditioning
Voltage fooler circuits are used to increase the loads for summer peaks). The time frame is
sensing voltage input to the LTC control relays. important because LTCs are effectively blocked
These circuits typically consist of a step-up in the transient time frame. As shown in Figure II-
transformer, with one or more taps, in series with 4, LTCs do not start to move until after the
the potential input to the control. Using SCADA transient time frame.
contacts the LTC control is fed a voltage that is
higher than the actual voltage, causing the control The voltage reduction scheme has an advantage
to act to lower the voltage. In some cases the over the blocking scheme in that the quality of
controls preset time delay is bypassed, power supplied to customers remains defined by

30
Final version, December, 1996

the new (reduced) set point. It has a potential Use appropriate diagnostic techniques to
disadvantage however, of providing less load provide early warning of the onset of voltage
relief than the blocking scheme which allows stability problems. Since voltage collapse is a
distribution supply voltages to drift down to wide area problem, these techniques often need
whatever levels the transmission voltage goes to. communications assistance. The
communications are not necessarily high speed,
A major point of concern in application of the but must be reliable. The techniques involve
blocking scheme using local voltage detectors is measurement of relevant factors such as voltage
that the LTC may have already moved to near it’s magnitude, status and output of sources of
full boost position by the time the primary voltage reactive power, rate of change of reactive power
has reduced to a level below the normal generation with respect to load, and magnitudes
maximum. Thus blocking the LTC may be too of real and reactive power flows.
late. Use of a centralized decision which could
be taken at an earlier time (since more Provide temporary reactive support until
information may be available to determine the operator action can stabilize system. This may
possible onset of collapse), may allow blocking require taking advantage of temporary overload
the LTC when it is in a near normal position. This capabilities of generators and synchronous
concern is not as important in a voltage reduction condensers in the affected area. To ensure full
scheme which retains control of the LTC. capability of all sources are available, they should
be operated from time to time at maximum and
With both schemes, the characteristics of the minimum reactive outputs to ensure all protective
distribution system is important. To minimize devices coordinate properly with control devices.
unacceptable power quality to some customers,
the voltage profile along the distribution feeder Provide permanent reactive support. Since it
should be fairly flat. If the profile is too steep, it is deficiency of reactive power sources that
will not be possible to reduce voltage levels at causes voltage to drop, provision of these
customers near the substation without reducing sources are an effective means of maintaining
voltage levels at distant customers to voltages. Switched capacitors are a popular
unacceptable levels. means of providing such support, but care must
be taken to avoid depending entirely on fixed
VIII. Conclusion support such as is provided by capacitors. Fixed
sources do not provide the control of system
A. The fundamental principles of voltage which is critical in near collapse
mitigation actions situations.
Anticipate the problem by using load flow and
stability studies to identify system conditions that Provide an appropriate mix of static and
may lead to voltage instability. Conditions that dynamic sources of reactive support.
lead to voltage collapse may be caused or Although dynamic sources of reactive power are
aggravated by heavy power transfer between much more expensive than fixed sources, they
regions; so coordination among the affected do have the advantage of being able to control
regions is essential to develop the appropriate voltages. Some relatively economical means of
mitigative action. Results of these studies can be providing dynamic support include use of LDC so
used to develop special operating procedures to that generators regulate voltages some distance
minimize the probability of collapse. Where from their terminals. Conversion of uneconomic
studies show that operating procedures alone are generators to synchronous condensers, and fast
not sufficient to ensure voltage stability, special switching of capacitors are sometimes options
control and protection schemes can be applied to for increasing the availability of sources of
mitigate the conditions leading to collapse. dynamic reactive support. Where possible,
dynamic sources of reactive power may be

31
Final version, December, 1996

operated as near to mid output as possible to Communications are required to ensure


maximize dynamic reactive reserve. Manual or coordination between different geographic
automatic switching of static sources (or sinks) locations. Test of coordination by regular
of reactive power is a better means of keeping exercising of control actions while the power
dynamic sources near the middle of their system is not stressed is the best way to ensure
operating range than adjusting their reference they will operate properly and coordinate with
voltage. each other and with protection systems under
stressed conditions.
Provide temporary load relief by blocking tap
changers or reducing distribution supply System dynamics in the voltage collapse time
voltage. The amount of load relief provided by frames depend on three factors, temporary
these means is determined entirely by the static overload capability of dynamic sources of
and dynamic characteristics of the real and reactive power, timing of control devices such as
reactive components of the load with respect to transformer load tap changers, and dynamic
voltage level. These characteristics vary widely, response of loads to voltage changes. Of these
and may need to be determined by test. The factors, it is usually the load characteristics that
reduction in reactive power demand with voltage are most difficult to determine. Even if load
is often larger than the reduction in real power characteristics are determined by test, mitigation
demand. It must be ensured that voltage quality actions based on these characteristics should be
is not degraded so much that the alternative of initiated in the region where the characteristics
load shedding would not have been preferable to are valid. For instance, if tests have determined
the customer. the characteristics within the range 0.95 to 1.05
p.u., the same characteristics cannot be
Shed load. This alternative is the ultimate short expected if the voltage drops to 0.85 p.u. At
term mitigation action. Since the cause of voltages less than 0.9 p.u., system response to
voltage collapse is an excess of load for the mitigation actions is very uncertain.
given transmission system, load shedding is a Operator training and response is very important.
clearly effective action. This action is likely to Operators must be able to recognize voltage
find increasing application as utilities balance the instability conditions and must be able to act
alternative of power supply reliability with power promptly and effectively to arrest collapse. The
supply cost. time frame of collapse is often longer than
operator response time. All automatic actions
B. Choice of action(s) depends to a large which are intended to provide temporary relief
extent on dynamics must be accompanied by clear indication of their
The speed of collapse can vary widely from a few action; so that operators can recognize the
seconds to tens of minutes. Since many of the conditions. Further, operator training must
mitigation actions offer temporary benefits, their include clear direction as to actions they are
effectiveness will vary widely with the dynamic required to take when voltage collapse is
characteristics of the collapse. Therefore, there imminent.
are no actions that are generally preferable for all
types of power systems. The study of voltage stability phenomena and
definition of alternatives is the system planner’s
Protection and control actions must be responsibility. Protection engineers can help in
coordinated with each other. As it becomes ensuring reliability of mitigation actions by proper
more difficult to provide new transmission and design, and by coordination with other protection
generation, utilities rely more on complex, and and control actions affecting system stability.
diverse protection and control systems. To
ensure coordination is achieved, two items
become important - communications and test.

32
Final version, December, 1996

IX. Acknowledgments 9 G. C. Bullock, “Cascading Voltage


Collapse in West Tennessee”, Proceedings,
The contributions and helpful comments during
Western Protective Relay Conference, 1990,
reviews of drafts of this document by Carson
Spokane, Washington
Taylor, Daniel Karlsson, and Stefan Arnborg, are
gratefully acknowledged.
10 North American Electric Reliability
Council (NERC), “1992 System Disturbances -
X. References Review of Selected Electric System
Disturbances in North America”, North American
1 IEEE Committee paper, "Summary of Electric Reliability Council, October, 1993 p.p.
System Protection and Voltage Stability", IEEE 18-32
WG on Voltage Stability, IEEE Transactions on
Power Delivery Vol. 10 No. 2, April, 1995 p.p. 11 D. Karlsson, et al., “Temporary Load-
631-638 Voltage Characteristics for Voltage Stability
Studies - Field and Laboratory Measurements”,
2 CIGRE Task Force 38.02.12, “Criteria CIGRE Paper No. 38-204, 30 August - 5
and Countermeasures for Voltage Collapse”, September, 1992.
Brochure No. 101, October, 1995 (summary in
Electra, October, 1995). 12 G. J. Berg, "System and Load behavior
Following Loss of Generation", Proc. IEE, Vol.
3 IEEE PES Publication 93TH0620-5PWR 199, No. 10, Oct. 1972, pp. 1483-1486.
"Suggested Techniques for Voltage Stability
Analysis" 13 S.A. Kalinowsy and M. M. Forte, "Steady
State Load-Voltage Characteristic Field Tests at
4 S.A. Nirenberg, D.S. McInnis, and K.D. Area Substations and Fluorescent Lighting
Sparks, “Fast Acting Load Shedding”, IEEE Component Characteristics", IEEE Trans. on
Transactions on Power Systems, Vol. 7 No. 2, PAS, June 1981, pp.3087-3094.
May 1992, p.p. 873-877.
14 T. Frantz et al., "Load Behavior Observed
5 H. M. Shuh and J. R. Cowan, in LILCO and RG & E Systems", IEEE Trans. on
“Undervoltage Load Shedding-An Ultimate PAS, April 1984, pp. 819-831.
Application for the Voltage Collapse,”
Proceedings Georgia Tech Protective Relay 15 IEEE Task Force, "Load representation
Conference, April 29 - May. 1, 1992 for Dynamic Performance Analysis", IEEE
Transactions on Power Systems, Vol. 8, No. 2,
6 P.G. McLaren, et. al., “”Open” Systems May 1993, p.p. 472-482.
Relaying”, IEEE Transactions on Power Delivery,
Vol. 9, No. 3, July 1994, p.p. 1316-1324. 16 IEEE Load Representation for Dynamic
Performance Task Force, "Standard Load
7 T. Newton, E. Lee, D. Rogers, “A New Models for Power Flow and Dynamic
Universal Protective Relay Architecture, its Performance Simulation", IEEE Trans. on Power
Philosophies, and Implementations”, Systems, Vol. 10, No. 3, pp. 1302-1313, August,
Proceedings, Western Protective Relay 1995
Conference, 1994, Spokane, Washington
17 N. E. Nilsson, and J. Mercurio,
“Synchronous Generator Capability Curve
8 C. W. Taylor, “Power System Voltage
Testing and Evaluation”, IEEE Trans on Power
Stability”, McGraw-Hill, 1994.
Delivery, Vol 9, N0. 1, January 1994, p.p.
414-424

33
Final version, December, 1996

18 M. M. Adibi and D. P. Milanicz, “Reactive


Capability Limitation of Synchronous Machines”,
IEEE Transactions on Power Delivery, Vol. 9 No.
1, February 1994, p.p. 29-40

19 Murdoch, Crenshaw, and Wright, "Power


System Stabilizer Application Guide", GE
Publication 84-EUE-207, 1984, p. II-1

20 C. W. Taylor, “Concepts of
Undervoltage Load Shedding for Voltage
Stability,” IEEE Transactions on Power
Delivery, Vol. 7, No. 2, p.p. 480-488, April
1992.

21 B. R. Williams, W. R. Schmus and


D. C. Dawson, “Transmission Voltage
Recovery Delayed by Stalled Air Conditioner
Compressors,” IEEE Trans. on Power
Systems, Volume 7, No. 3, August, 1992,
pp. 1173-1181

34

Você também pode gostar