Escolar Documentos
Profissional Documentos
Cultura Documentos
MIL001 ZERO DATE - PROJECT START 0 18MAR08 ZERO DATE - PROJECT START
BASIC ENGINEERING
Subtotal 138 02MAY08 16SEP08
EN260 PREP & APPRL OF DBR - CIVIL 20 02MAY08 21MAY08 PREP & APPRL OF DBR - CIVIL
EN250 PREP & APPRL OF DBR - CHIMNEY 25 27MAY08 20JUN08 PREP & APPRL OF DBR - CHIMNEY
EN230 PREP & APPRL OF DBR - FUEL OIL SYSTEM 25 16JUN08 10JUL08 PREP & APPRL OF DBR - FUEL OIL SYSTEM
EN100 PLOT PLAN RELEASE FOR CONSTR. 50 04JUL08 22AUG08 PLOT PLAN RELEASE FOR CONSTR.
EN110 LOAD LIST FINALISATION 25 04JUL08 28JUL08 LOAD LIST FINALISATION
EN140 PREP & APPRL OF DBR - ELECTRICAL SYS 45 09JUL08 22AUG08 PREP & APPRL OF DBR - ELECTRICAL SYS
EN130 PREP & APPRL OF DBR - WATER SYSTEM 35 14JUL08 17AUG08 PREP & APPRL OF DBR - WATER SYSTEM
EN150 PREP & APPRL OF DBR - COMPRESSED AIR SYS 25 14JUL08 07AUG08 PREP & APPRL OF DBR - COMPRESSED AIR SYS
EN200 PREP & APPRL OF DBR - FIRE PROT. & DETECT SYS 45 14JUL08 27AUG08 PREP & APPRL OF DBR - FIRE PROT. & DETECT SYS
EN190 PREP & APPRL OF DBR - COAL HANDLING SYS 30 19JUL08 17AUG08 PREP & APPRL OF DBR - COAL HANDLING SYS
EN240 PREP & APPRL OF DBR - C&I 45 03AUG08 16SEP08 PREP & APPRL OF DBR - C&I
EN210 PREP & APPRL OF DBR - AC & VENTILATION 25 18AUG08 11SEP08
EN220 PREP & APPRL OF DBR - AHP 25 18AUG08 11SEP08
INTERFACE
Subtotal 652 12MAY08 22FEB10
TPL TO BHEL
TB001 UNIT #1 - BOILER FOUNDATION COMPLETION 0 25NOV08
TB002 UNIT #1 - ESP FOUNDATION COMPLETION 0 25JAN09
U2TB001 UNIT #2 - BOILER FOUNDATION COMPLETION 0 23FEB09
TB025 U#1 LP / HP HEATERS, DRAIN COOLER FOUND. COMPLN. 0 13MAR09
TB012 FUEL OIL PUMP SKID FOUNDATION READINESS 0 01APR09
U2TB002 UNIT #2 - ESP FOUNDATION COMPLETION 0 25APR09
TB020 EOT CRANE READINESS FOR EQUIPMENTS' ERECTION 0 21MAY09
TB014 UNIT #1 - BFP & CEP FOUNDATION COMPLETION 0 26MAY09
TB015 U#1 - AOP, JOP & EOP FOUNDATION COMPLETION 0 26MAY09
GENERAL
Subtotal 467 02MAY08 11AUG09
SITE PREPAREDNESS
SSP100 SITE CLEARENCE TO START WORK 0 01MAY08
UNIT I - BTG
Subtotal 739 18MAR08 26MAR10
STEAM GENERATION
BOILER FOUNDATION
ENGINEERING
EN450 BOILER FOUNDATION DRG 20 22MAY08 10JUN08 BOILER FOUNDATION DRG
BBE001 BOILER FOUNDATION ENGG 30 16JUN08 15JUL08 BOILER FOUNDATION ENGG
PROCUREMENT
BBP001 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler 15 16JUL08 30JUL08 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler
BBP002 MFG & DISPATCH OF FOUNDATION MATLS 28 31JUL08 27AUG08 MFG & DISPATCH OF FOUNDATION MATLS
CIVIL
BA100 FOUND FOR BOILER MAIN COLUMN 60 28AUG08 26OCT08
BA110 FOUND FOR BOILER AUXILIARY COLUMN 50 02OCT08 20NOV08
BA150 READINESS OF BOILER FOUNDATION 5 21NOV08 25NOV08
BOILER STRUCTURE
ENGINEERING
BSE001 ENGINEERING- BOILER STR. 30 21JUN08 20JUL08 ENGINEERING- BOILER STR.
PROCUREMENT
BSP001 RECEIPT OF BOILER STR. MATERIAL AT WORKS 10 21JUL08 30JUL08 RECEIPT OF BOILER STR. MATERIAL AT WORKS
BSP002 MANUFACTURING - BOILER STRUCTURE 128 22JUL08 26NOV08 MANUFACTURING - BOILER STRUCTURE
BSP003 DESPATCH MAIN BOILER STRUCTURE 120 29AUG08 26DEC08
BSP004 DESPATCH AUXILIARY STRUCTURE 180 31AUG08 26FEB09
ERECTION/COMMISSIONING
BSEC001 ERCN. OF MAIN BOILER STR. 90 15JAN09 14APR09
BSEC002 ERECTION OF AUX STR. 50 01MAR09 19APR09
BSEC003 STR. ERECTION BEFORE DRUM LIFTING 5 26MAR09 30MAR09
BOILER DRUM
ENGINEERING
BDE001 ENGINEERING- BOILER DRUM 30 02MAY08 31MAY08 ENGINEERING- BOILER DRUM
PROCUREMENT
BDP001 INTEND. & RECEIPT OF BOILER DRUM MTRL. AT WORKS 156 10MAY08 12OCT08
BDP002 MANUFACTURING & DISPATCH- BOILER DRUM 170 13OCT08 31MAR09
ERECTION/COMMISSIONING
BDEC001 BOILER DRUM LIFTING 0 30APR09
BOILER PRESSURE PARTS
ENGINEERING
BPE001 ENGINEERING- BOILER PRESS PARTS 30 16JUL08 14AUG08 ENGINEERING- BOILER PRESS PARTS
PROCUREMENT
BPP001 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS 85 06AUG08 29OCT08 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS
UNIT II - BTG
Subtotal 761 18MAR08 17APR10
STEAM GENERATION
BOILER FOUNDATION
ENGINEERING
U2EN500 BOILER FOUNDATION DRG 20 22MAY08 10JUN08 BOILER FOUNDATION DRG
U2BBE011 BOILER FOUNDATION ENGG 30 16JUN08 15JUL08 BOILER FOUNDATION ENGG
PROCUREMENT
U2BBP011 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler 15 16JUL08 30JUL08 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler
U2BBP012 MFG & DISPATCH OF FOUNDATION MATLS 28 29OCT08 25NOV08
CIVIL
U2BA200 FOUND FOR BOILER MAIN COLUMN 60 26NOV08 24JAN09
U2BA210 FOUND FOR BOILER AUXILIARY COLUMN 50 31DEC08 18FEB09
U2BA250 READINESS OF BOILER FOUNDATION 5 19FEB09 23FEB09
BOILER STRUCTURE
ENGINEERING
U2BSE011 ENGINEERING- BOILER STR. 30 21JUN08 20JUL08 ENGINEERING- BOILER STR.
PROCUREMENT
U2BSP011 RECEIPT OF BOILER STR. MATERIAL AT WORKS 10 21JUL08 30JUL08 RECEIPT OF BOILER STR. MATERIAL AT WORKS
U2BSP012 MANUFACTURING - BOILER STRUCTURE 128 19OCT08 23FEB09
U2BSP013 DESPATCH MAIN BOILER STRUCTURE 120 26NOV08 25MAR09
U2BSP014 DESPATCH AUXILIARY STRUCTURE 180 28NOV08 26MAY09
ERECTION/COMMISSIONING
U2BSEC011 ERCN. OF MAIN BOILER STR. 90 15APR09 13JUL09
U2BSEC012 ERECTION OF AUX STR. 50 30MAY09 18JUL09
U2BSEC013 STR. ERECTION BEFORE DRUM LIFTING 5 24JUN09 28JUN09
BOILER DRUM
ENGINEERING
U2BDE011 ENGINEERING- BOILER DRUM 30 02MAY08 31MAY08 ENGINEERING- BOILER DRUM
PROCUREMENT
U2BDP011 INTEND. & RECEIPT OF BOILER DRUM MTRL. AT WORKS 156 10MAY08 12OCT08
U2BDP012 MANUFACTURING & DISPATCH- BOILER DRUM 170 11JAN09 29JUN09
COMMON BOP
Subtotal 689 12MAY08 31MAR10
TG BUILDING
ENGINEERING
EN310 SPECIFICATION- EOT CRANE 25 17JUL08 10AUG08 SPECIFICATION- EOT CRANE
EN300 CIVIL DRG FOR STG BUILDING 45 03AUG08 16SEP08 CIVIL DRG FOR STG BUILDING
PROCUREMENT
PR230 ORDERING - AGGREGATE PRODUCTION CRUSHER 30 01JUN08 30JUN08 ORDER
PR240 MOBILIZATION & SET-UP OF AGGRERATE PRODN CRUSHER 60 01JUL08 29AUG08 MOBILIZATION & SET-UP OF AGGRERATE PRODN CRUSHER
PR200 ORDERING- EOT CRANE 35 11AUG08 14SEP08 ORDERING- EOT CRANE
PR210 MANUFACTURING- EOT CRANE 190 15SEP08 23MAR09
PR220 DISPATCH- EOT CRANE 25 24MAR09 17APR09
CIVIL
TG010 MAIN COLUMN FOUND 180 02SEP08 28FEB09
TG020 FABRICATION - STG BUILD STRUCTURE 240 14SEP08 11MAY09
TG110 TG FOUNDATION WORKS - UNIT #1 180 27SEP08 25MAR09
TG030 ERECTION OF STG BUILD STRUCTURE 300 24OCT08 19AUG09
TG040 CONCRETING OF BC BAY 3.5m FLOOR 60 23DEC08 20FEB09
U2TG110 TG FOUNDATION WORKS - UNIT #2 180 26DEC08 23JUN09
TG060 CONCRETING OF BC BAY 8m FLOOR 60 07JAN09 07MAR09
TG065 CONCRETING OF BC BAY 11m FLOOR 60 22JAN09 22MAR09
TG080 CONCRETING OF BC BAY 0.00m FLOOR 90 22JAN09 21APR09
TG075 CONCRETING OF BC BAY 16.5 m FLOOR 60 06FEB09 06APR09
TG125 READINESS FOR SWITCH GEAR ERECT @ 3.5 M 40 21FEB09 01APR09
TG120 UNIT BATTERY ROOM READINESS - UNIT #1 35 11MAR09 14APR09
TG100 ROOF & SIDE SHEETING 140 23MAR09 09AUG09
TG190 STATION BATTERY ROOM READINESS 45 23MAR09 06MAY09
U2TG120 UNIT BATTERY ROOM READINESS - UNIT #2 35 07APR09 11MAY09
TG015 AUX COLUMN FOUND 270 15APR09 09JAN10
TG135 READINESS FOR EOT ERECT 0 21APR09
TG050 CONCRETING OF AB BAY 5m FLOOR- PART 45 15MAY09 28JUN09
Start Date 01MAR08 DAR7 Sheet 42 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity