Sarawak Shell Bhd

MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

FABRICATION OF SCDR-A TOPSIDES AND E11K-A PROJECT


CONTRACT No. 591397

CLOSE OUT REPORT

0 05-Oct-07 Issue for approval


R. Khairul Ardani Othman Sabran Felixberto Clerigo

Prepared by Reviewed by Approved by


REV DATE DESCRIPTION
Planning Eng’r PM CSR

This document contains information that has been prepared by MMHE SDN BHD and all information contained
herein shall be held in confidence. Disclosure, reproduction, or other use of this document is prohibited without
the prior written consent of MMHE SDN BHD
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

TABLE OF CONTENTS

No. CHAPTER PAGE

A. CONSTRUCTION 1 - 13

PROJECT OVERVIEW 1

1. Overall Project Schedule 1


1.1 Overall Schedule 1
1.2 Overall S-curve 1

2. Contract Summary 2

3. Contract Representative 2
3.1 SSB Representative 2
3.2 MMHE Representative 2

4. Contract Cost Summary 2

5. Organization 2
5.1 Project Organizational Chart 2

6. Manpower 2
6.1 Manpower Histogram 2

7. Subcontractor 3

8. Fabrication 3
8.1 Introduction 3
8.2 Fabrication Yard 3
8.3 Structural Works 4-5
8.4 Piping Works 5
8.5 Mechanical Works 6
8.6 Electrical & Instrumentation Works 7
8.7 Blasting & Painting Works 8

9. Statistics 8
10. Testing & Pre-Commissioning 9 -10
11. Inter-Departmental Assessment 11-12
12. Lesson Learnt 13
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

B. QHSE 14 - 20

1. Health, Safety and Environment 14

1.1 Overall HSE Statistics 14


1.2 HSE Targets 15
1.3 Induction Training 15
1.4 Fabrication Yard Orientation and Security 15
1.5 Housekeeping 15
1.6 Drills 15
1.7 Project HSE Meeting 16
1.8 Daily Toolbox Meeting 16
1.9 Weekly HSE Talk 16-17
1.10 HSE Walkabout 17-18
1.11 Friday HSE Video Show 18
1.12 QHSE Day Celebration 18
1.13 HSE Incentives 18
1.14 HSE Violation 18
1.15 D&A Program 18
1.16 Safety Campaigns 19
1.17 HSE Workshop 19
1.18 Incident / Injury 19

2. Inter-Departmental Assessment 20

C. PROCUREMENT 21 - 23

1.0 Statistics 21-23


2.0 Lesson Learnt 23

D. ENGINEERING 24 - 26

1.0 Statistics 24
2.0 Inter-Departmental Assessment 25
3.0 Lesson Learnt 26
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

E. QA/QC 26 - 27

1.0 Statistics 27
2.0 Lesson Learnt 27

F. COST CONTROLLER 28 - 31

1.0 Statistics 28
2.0 Change Orders 29
3.0 Budget Cost Over-run, Reasons and mitigating Action 29
4.0 Project Cash Flow Status & Lesson Learnt 30
5.0 Inter-Departmental Assessment 30
6.0 Lesson Learnt 31

G. APPENDIXES

™ Appendix 1 - Schedule Bar Chart


™ Appendix 2 - Overall S-Curve
™ Appendix 3 - Manpower Histogram
™ Appendix 4 - Progress Calculation Level-IV
™ Appendix 5 - Project Organizational Chart
™ Appendix 6 - Subcontractor Evaluation Sheet
™ Appendix 7 - Fabrication Yard
™ Appendix 8 - RFQ / CO / VOP Log
™ Appendix 9 - Erection Sequence
™ Appendix 10 - Progress Photographs
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

Project : Fabrication of SCDR-A Topsides & Pre-fabrication for E11K-A Tie-ins

Department: Construction

Scope: SCDR-A Topsides: The scope of work consists of Construction, Engineering, Procurement
and supply of materials, Fabrication, Inspection, Testing, and On-Shore Commissioning,
Loadout & Seafastening of the SCDR-A Topsides and Associated Appurtenances.

E11K-A TIE-INS: The scope of work consists of Construction, Engineering, Procurement,


Supply of Materials, Fabrication, Inspection, Testing, and Packing, Loadout &
Seafastening of ship loose items for SCDR-A pipeline tie-in works at the existing E11K-A
Platform.

Project Background: The Shallow Clastics field covers an area of ca. 600km.sq., (40-km x 15-km)
consisting of alternating sand shale sequences in which eight-gas bearing intervals have been
identified to date. The field comprises two en-enchelon ENE-WSW trending culminations that
overlie the F13 and E11 carbonate fields in the northern and mid part of the field, respectively.

SCDR-A will be place on the SW area of the Shallow Clastics field with four highly deviated wells
and one back-up well and tied back to the E11K-A Platform via a single 6.4-km, 14-inch (0.35-m)
carbon steel pipeline. The gas and condensate from the SW area of the reservoir will be
transported wet as a multiphase mixture to the E11K-A facilities, where the fluids will be
separated, dehydrated and re-combined prior to export to MLNG DUA.

The SCDR-A is an unmanned drilling riser topsides design for a “minimum facilities” concept. The
minimum facilities consists of Flow lines, Wet Gas System, Wellhead Desander System, Vents and
Drains Systems, Fresh Water System, Pedestal Crane, Process Control System, IPS, Fire and Gas
System, Telecommunication System, etc.

1.0 OVERALL PROJECT SCHEDULE

1.1 Overall Schedule


See Appendix 1 - Schedule Bar Chart

1.2 Overall S-Curve


See Appendix 2 – Overall S-Curve

1 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


2.0 CONTRACT SUMMARY

2.1 Contract No. : 591397


2.2 Contract Title : Fabrication of SCDR-A Topsides
2.3 Scope of Work : The Scope of work consists of Construction,
Engineering, Procurement and supply of materials,
Fabrication, Inspection, Testing, & On-Shore Pre-
Commissioning, Loadout & Seafastening of the SCDR-
A Topsides and Associated Appurtenances.
2.4 Contract Duration
Contractual Start Date : 12 October 2006
Contractual Duration : 58 weeks
MCD : 28 August 2007
Sailaway : 05 Sept 2007 (Planned), 27 Sept 07 (Actual)
2.5 Type of Contract : Lump Sump
2.6 Contract Value : RM 75,667,000.00

3.0 CONTRACT REPRESENTATIVE

3.1 SARAWAK SHELL BERHAD (SSB)


Company Representative : Tjitske Monster
Designation : Project Manager
Company Site Representative : Felixberto Clerigo
Designation : Client Site Representative

3.2 MALAYSIA MARINE & HEAVY ENGINEERING SDN BHD (MMHE)


Contractor Representative : Mohamed Za’aba Abbas
Designation : General Manager, Engineering & Construction
Contractor Site Representative : Othman Bin Sabran
Designation : Project Manager

4.0 CONTRACT COST SUMMARY

4.1 Original Contract Value : RM 75,667,000.00


4.2 Change Order : RM ……………….
4.3 Final Contract Price : RM ……………….

5.0 MANPOWER

5.1 Manpower Histogram


See Appendix 3 – Manpower Histogram

6.0 PROGRESS CALCULATION

6.1 Progress Calculation Sheet Level-IV


See Appendix 4 – Progress Calculation Level-IV

7.0 ORGANIZATION CHART

7.1 Project Organizational Chart


See Appendix 5 – Project Organizational Chart

2 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

8.0 SUBCONTRACTOR

Actual
Planned Planned Actual
Discipline Company Award
Award Date Mob Date Mob Date
Date

Structural Kejuruteraan Wijaya Sdn Bhd 11-Oct-06 03-Nov-06 12-Oct-06 09-Nov-06

Blasting/Painting BB Tech Services Sdn Bhd 05-Dec-06 22-Feb-07 06-Dec-06 02-Mar-07

HVAC Dynac 15-Nov-06 15-Dec-06 16-Nov-06 21-Dec-06

Piping Jurunature Sdn Bhd 05-Jan-07 07-Feb-07 06-Jan-07 12-Feb-07

Mechanical Jurunature Sdn Bhd 13-Jan-07 07-Feb-07 14-Jan-07 12-Feb-07

Electrical Asadra (M) Sdn Bhd 20-Feb-07 26-Feb-07 21-Feb-07 02-Mar-07

Instrument Asadra (M) Sdn Bhd 20-Feb-07 26-Feb-07 21-Feb-07 02-Mar-07

Architectural Arrow Platform (M) Sdn Bhd 16-Mar-07 26-Feb-07 17-Mar-07 08-Mar-07

GRE Piping Amerstrand Engineering 17-Mar-07 08-Feb-07 18-Mar-07 14-Feb-07

PFP Jurunature Sdn Bhd 24-May-07 15-May-07 28-May-07 19-May-07

Weighing UES Logistics (M) Sdn Bhd 25-Jun-07 25-June-07 26-Jun-07 07-Jun-07

Load Out Asian Lift PTE Ltd. 10-Aug-07 30-July-07 11-Aug-07 09-Sep-07

See Appendix 6 - Subcontractors Evaluation Sheets

9.0 Fabrication

9.1 Introduction
The SCDR-A Topsides Project structure was consists of Cellar Deck, Mezzanine Deck, Main
Deck, Wellhead Platform, Intermediate Platform and Flare Boom. The total weight is
approximately 1,700 metric tons. In additional to that, there is fabrication of ship loose
items for SCDR-A pipeline tie-in works at existing E11K-A Platform.

9.2 Fabrication Yard


See Appendix 7 - Fabrication Area.

3 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


9.3 Structural Works
9.3.1 All structural steel materials were sweep blast and apply primer prior to delivery
to the fabrication shop. Upon completion of pre-fabrication, these materials
were blasted again and applied approved epoxy or main coating/ primer
epoxy glass flake prime prior to erection in situ. These materials were segregated
color coded according to material types and components for easy issuance to
sub-contractor. This segregation of materials also applied to surplus materials
whether pre-issued by SSB or by MMHE.
9.3.2 Prepared, fabricated skidding beams, skid shoes w/ weighing beam and cast
additional concrete block supports. Checked also in consideration soil bearing
pressure of place where it was erected if enough to resist / bare total weight of
the structure.
9.3.3 After preparation of skidding beam and concrete block supports, concrete
blocks, skid beams and skid shoes were installed by using crawler crane.
Erection and final assembly on top of skid beams was done using crawler or
hydraulic cranes.
9.3.4 All pre-fabrication of haunches, plate girders, primary beams & secondary
beams, and structural out fittings i.e. handrails, stairways and service platform
was done @ Engineering workshop no.8, All the pre-fabricated were blasted and
applied main coat prior to erection to minimized blasting works at site and
minimize the working time for all discipline without disturbance of blasting works.
9.3.5 During assembly of Cellar deck one (1) trailer was utilized. Haunches and girders
were transported from fabrication area to erection site by using trailer & forklifts.
Fabricated and assembled the cellar deck in-situ by providing temporary
skidding support frame. Installed equipment / vessel if available else hold some
braces.
9.3.6 Fabricated truss rows and braces for mezzanine deck / main deck erection.
Column and braces in row A and row B are erected/welded in cellar deck
panel. Installed all outfitting items including equipments before erection of
wellhead access platform, mezzanine deck and main deck.
9.3.7 Fabricated Mezzanine Deck building walls / panels and roof, Wellhead access
platform and Intermediate Platform. Fabricated primary and secondary beams
@ Engineering Workshop no.8. Sub-assemble was done @ fabrication no. 1.
9.3.8 Fabricated and assembled Main Deck. Fabricated haunches, plate girders
including primary and secondary beams @ Engineering workshop no. 8.
Assembled Main Deck in-situ at the rear side of cellar deck. Erected Mezzanine
Deck ( 5 parts ) building wall / panel and roof and followed by erection of
Wellhead Access Platform. All these said erection sequence was carried out
before the erection of Main Deck ( 2 parts ).
9.3.9 Fabricated and assembled pedestal crane diesel storage tank @ fabrication # 1.
Assembled pedestal crane was lifted and transported to a designated up-
righting area not far from assembly area by using two (1) no. of crawler crane
and (1) no. of 45 toner mobile crane. After up righting, the assembled pedestal
column was transported and installed using one (1) crawler crane. The height of
the pedestal crane was considered on the capacity of the crane to be used.
9.3.10 After the erection of Main Deck and Pedestal Crane was completed, the
Intermediate Deck ( 3 part ) was erected.

4 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


9.3.11 Fabricated and assembled Vent Boom at designated area also in fabrication #
1. Diagonal and horizontal braces were lifted and transported from assembly
area and installed to its final location, using two ( 2 ) cranes.

8.4 PIPING WORKS


8.4.1 Fabrication: All spools fabrication was done inside the workshops and full
tractability of the piping materials including off-cut was maintained. Welding
was done by qualified welders and in accordance with the WPS. Visual
inspection of the elements was done prior to NDE test as per the NDT procedure
(RT was performed at night). Pipe spools that required Post Weld Heat Treatment
was done as per the PWHT procedure. After the NDE clearance, the spools were
hydrotested or sent to the Blasting & Painting area.
8.4.2 Installation: Prior to spools installations, all NDE were cleared, all spools internals
were hydro-jetted and blown dry and the entire opening have temporary covers
to prevent the ingress of foreign materials. Lifting belts were utilized instead of
wire slings during installation. Flange or field welded joints were one progressively
away from the equipment nozzle connections. Final bolt tightening on
equipment tie-in was done after equipment alignments have been accepted.
8.4.3 Hydro Test
The following were address before hydro test commenced:
All pipe supports installed.
All NDE & PWHT accepted.
All valves permitted to be included on the package were in full open
position.
Flushing completed.
Valve greasing was carried out.

The test pressure of each package was as shown in the hydro test packages.
The extent of the package that hydrotested was barricaded and with warning
signboard during hydro test.
Hydro test results were recorded on pressure recorders and all data/charts were
clearly marked and compiled at the completion of the Flushing and Hydro-
testing activities. A Flushing and Hydro-Test Procedure was developed. After
hydrostatic testing, the piping systems was thoroughly drained to remove all the
water and following by air-drying.
8.4.4 Reinstatement Test
Reinstatement test was carried out after hydro-test. The following activities were
completed before the reinstatement test commenced:
All temporary components used during the hydro test were removed.
All piping, valves, instrument, equipment and line elements were installed.
The piping system within the reinstatement package was made up to the
final operating condition.

All reinstatement packages was developed and line checks was carried out
prior to reinstatement testing, which include sequence of building up test
pressure up to the specific test pressure and the sequence for depressurizing
including safety requirement was observed during the actual testing.

5 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

8.5 MECHANICAL WORKS

8.5.1 MMHE subcontracted or purchased the equipment from approved vendors.

8.5.2 All mechanical supports/sitting fabrication works was done inside the workshop
taking into account the as-built measurement of the equipment skid supports
and the deck levelness. Specific installation heavy lift procedure for major
equipment was developed.

8.5.3 Prior to delivery, MMHE ensured that the equipment was inspected and tested
either at vendor premises or upon delivery at MMHE.

8.5.4 MMHE completed all required testing & inspection prior to installation.

8.5.5 Major equipment, which required PTW or special permit for lifting, were erected
to location pending its availability.

8.5.6 Equipments, which are sensitive to moist, humidity, extreme heat or duct, MMHE
provided adequate protection. The preservation covered throughout the
fabrication period.

8.5.7 Major Mechanical equipments installed are, but not limited to the following:

8.5.7.1 Pedestal Crane


8.5.7.2 Centrifugal Pumps (4 nos.)
8.5.7.3 CO2 Vent Snuffing Unit
8.5.7.4 Corrosion Inhibitor Injection Skid
8.5.7.5 Close Drain Vessel
8.5.7.6 Condensate Pod
8.5.7.7 Fresh Water Tank
8.5.7.8 Flush Water Tank
8.5.7.9 Swing Jib Cranes (2 nos.)
8.5.7.10 Launcher / Receiver
8.5.7.11 Sand Bins (2 nos.)
8.5.7.12 Desander Skids (5 nos.)
8.5.7.13 Wellhead (5 nos.)

Major HVAC equipments installed are, but not limited to the following:

8.5.7.14 Air handling Unit (2 nos.)


8.5.7.15 Air Cooled Condensate Unit (4 nos.)
8.5.7.16 Fan Coil Unit (Battery Room 2 nos.)
8.5.7.17 Electric Duct Heater (3 nos.)
8.5.7.18 Exhaust Fan (4 nos.)
8.5.7.19 External & Internal Ducting

6 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

8.6 ELECTRICAL & INSTRUMENTATION WORKS

8.6.1 MMHE subcontracted or purchased the equipment from approved vendors.

8.6.2 Prior to delivery, MMHE ensured that the equipments and devices were inspected
and tested either at vendor premises or upon delivery at MMHE.

8.6.3 MMHE completed all required testing & inspection prior to installation.

8.6.4 Equipments and devices with sensitive control devices and electronic devices
were stored in an enclosed air condition storage area prior to installation. The
preservation covered throughout the fabrication period.

8.6.5 All E&I supports, brackets and stands were fabricated inside the workshop as per
approved IFC dwgs. All supports, brackets & stands were full seal welded and
painted in accordance with SSB specifications unless shown otherwise on the IFC
dwgs.

8.6.6 All fabricated E&I supports, brackets & stands accepted by SSB were installed in
accordance with latest IFC dwgs. Full welding was done only after confirmation if
no obstruction/alteration within the areas concerned.

8.6.7 All E&I equipment were installed strictly on accordance with manufacturer’s
instruction and specification. Specific installation heavy lift procedure for major
equipment was developed.

8.6.8 The major E&I equipments installed are, but not limited to the following:

Electrical
• Power Transformer
• 6.6KV Ring Main Unit
• LV Distribution Board (8 nos.)
• AC Uninterruptible Power Supply (UPS)
• Interposing Relay Panels (2 nos.) – (1 no. ship loose for E11-KA)
• 400V Switchboard
• Splitter Box

Instrumentation

• Wellhead Control Panel


• Distributed Control System (DCS)
• AVA System
• GPA/PA System Cabinet
• Sand Monitoring System
• Hydraulic Actuated Valves
• Wet Gas Metering System
• IPS System

7 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

8.7 BLASTING & PAINTING WORKS

8.7.1 All raw fabricated materials (i.e. supports, brackets, stands, etc) were blasted
and applied approved Epoxy or Main Coating / Primer Epoxy Glass Flake prior to
erection.

8.7.2 For tubular, diagonal braces and columns were blasted and applied main coat
prior to erection.

8.7.3 All main steel assembled at ground level were spot blast on the welded
connection and welded attachment area and painted by the main coating
prior to lifting of the deck to its position.

8.7.4 The finished coat was applied right after the primary steel box-up and damage
portion thereafter was repaired and cosmetic painted during and after all
interdisciplinary components are installed, prior to MCD.

9.0 STATISTICS

9.1 PMT Evaluation

Risk Change
Site Technical
No Discipline Notification
Query Issued
Identified De-risked Issued

1 Mechanical 11 11 8 31

2 Structural 6 6 33 67

3 E&I 20 12 5 38

4 Architectural 2 2 6 14

5 Piping 9 9 9 23

6 HVAC 2 2 2 2

7 B&P 3 7

8 QA 1 1 4 8

9 T&C 1

8 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

10.0 TESTING & PRE-COMMISSIONING

10.1 Testing & Pre-commissioning outline the final inspection and onshore pre-commissioning
of the package system including the equipment installation works on SCDR-A Topsides
Project.
Onshore pre-commissioning proved that all equipment available have been installed
and connected in accordance with IFC drawings and operation is in line with the
design concept.
All inspection and test results are recorded on the SSB format of check sheets, Shell EP
Asia Pacific (EPA) format. The check sheet overview for each system is provided in the
detailed procedure. MMHE assigned personnel that performed the testing, inspection &
onshore pre-commissioning of various types of system and equipment, followed the
approved detailed procedure.
MMHE requested all tests and witnessed by SSB Commissioning Team. MMHE recorded
all test and counter signed by SSB Representative after testing was completed.
Original copy of check sheets were handed over progressively throughout the pre-
commissioning period and were kept in accordance with the commissioning system
numbering for final documentation.

10.2 General Scopes of Testing & Pre-commissioning are the following:

10.2.1 Bench calibration of instrument items upon deliver prior to installation.

10.2.2 Function test of electrical protection relays such as earth fault relays, overload
relays and etc.

10.2.3 Cable continuity check and megger testing.

10.2.4 Loop checking and static function test of all control panels.

10.2.5 Cleaning the package during and after the pre-commissioning.

10.2.6 System function test inclusive of over-all testing and shutdown matrices.

10.2.7 Alignment check for rotating equipment.

10.2.8 Preparation of pre-commissioning check sheets and test reports for


compilation and final documentation.

10.2.9 Flushing and reinstatement leak testing for system.

10.2.10 Full commissioning of HVAC, Pedestal Crane, etc. and maximize the
commissioning works onshore wherever possible.

9 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

10.3 Testing & Pre-commissioning Systems are the following:


10.3.1 System 01 : Gas and Condensate Production
10.3.2 System 12 : HVAC and Pressurization
10.3.3 System 13 : Diesel Fuel
10.3.4 System 18 : Drains
10.3.5 System 19 : Vents
10.3.6 System 20 : Material Handling
10.3.7 System 22 : Portable Emergency Equipment
10.3.8 System 23 : Fire Water
10.3.9 System 24 : Fresh Water
10.3.10 System 25 : Flush Water
10.3.11 System 27 : Electrical Generation and Distribution
10.3.12 System 28 : Uninterruptible Power Supplies
10.3.13 System 29 : Lighting and Small Power
10.3.14 System 30 : Navigational Aids
10.3.15 System 32 : Bonding, Earthing and Lighting Protection
10.3.16 System 33 : Distributed Control System (DCS)
10.3.17 System 34 : Fire and Gas Detection
10.3.18 System 35 : GPA
10.3.19 System 36 : AVA
10.3.20 System 37 : Telecommunications
10.3.21 System 39 : Instrument Protective System

10 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


11.0 Inter-departmental Assessment

Assessment
No Item
Excellent Good Fair Poor
1 Procurement

Remarks/ Improvement Opportunity:

No. Remarks Improvement Opportunity

1. Longer duration taken for PO awarding. Reduce the red tape.

2. Materials delivery beyond the planned To firm up the PO earlier and closely
schedule, as a result Fabrication and Testing & monitor the delivery of materials.
Commissioning works has been delayed (e.g. :
Launcher Receiver End Closure, E&I materials).
Prior to this also delivery of those
materials/equipment need to accelerate,
resulting cost increase.

3. Some of materials/equipment delivered not To revisit the vendor list and technical
meet targeted quality (e.g.: Closed Drain person / PMT should evaluate the proposed
Vessel & Condensate Pod – Too many punch vendor/supplier before award PO.
list and affecting others disciplines activities).

4. Materials specification changes not highlighted Should consult with design team, PMT and
to PMT and Client. As results too many re-test client before conclude to deviate from
conducted & time consumed & cost impact original specification.
(e.g.: Piping Duplex 8” seamless changes to
welded type).

5. The quality of procurement reporting is poor. To provide a detail and correct information
on the procurement report.

2 Design & Engineering

Remarks/ Improvement Opportunity:

No. Remarks Improvement Opportunity

1. TBE response is slow, resulting PO awarding To improve the evaluating period.


delayed.

2. Design quality is poor. Inter clash check in Design should improve in quality of
between designs disciplines is almost nil, designing & be very strong in justifying
resulting too many major clashing at site. related queries and should work as a team
among design team when finalizing the
drawings.
Design team should be the frontline in

11 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


advising the project team at beginning
stage for any materials shortage or clashes
or any related activities, which are not
highlighted by the client’s consultant.

3. Too many unplanned PR. Cost and time To improve the quality on justifying the
impact. details drawings.

3 Cost Controller

Remarks/ Improvement Opportunity:

No. Remarks Improvement Opportunity

1. Cost controller has a very structured


administration and procedures. All related site
changes and contractual requirement is well
monitored and organized.

4 Planner

Remarks/ Improvement Opportunity:

No. Remarks Improvement Opportunity

1. Package planning details week. Package planning should be in detail and


incorporate all the activities related to the
project. Also to be more proactive in
determining the impact of the schedule
delivered.

12 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

C. Lessons Learnt

1) Design team should be the frontline in advising the project team at beginning stage for any
materials shortage or clashes or any related activities that are not highlighted by the client’s
consultant. The time frame for justification and advising the project team also should be at a
high-speed mode. Not to copy and paste only the client’s entire only consultant drawing
details.
Design should improve in quality of designing & be very strong in justifying related queries
and should work as a team among design team when finalizing the drawings.
2) Procurement department should improve in delivery the PO and should transparent in
reporting the delivery of materials.
3) Material Control should tally the information materials delivery to project team to avoid too
many urgent releases given during project implemented.
4) Planning should detail out all activities and proactive in advising the impact of planned work
delivered.

13 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

Department: QHSE

Project HSE Targets:


It is MMHE committed desire to continually improve the overall Health Safety and environmental
performance and to further enhance a proactive safety culture and consciousness at all levels
involved in this Project.
Since beginning of the project on 21st July, 2006 through first cut of steel on 12th October, 2006 until
the Mechanical Completion Day (MCD) date on 28th August 2007, Loadout on 12th September,
2007 and Sail away of SCDR-A Topsides on 27th September, 2007, has achieved 462,640 man-hours,
405 days without Incident.

1.0 HEALTH, SAFETY AND ENVIRONMENT

1.1 Overall HSE Statistic as of 27/09/07

Category Accumulative
Total Man-hours without LTI 462,640
Near Miss 0
First Aid 0
Occupational Health 0
MTC 0
RWC 0
No. of Fire/Explosion Incident 0
Property/Equipment Damage 0
LTI 0
Permanent Total Disability 0
Fatality 0
Total Recordable Occupational Illness 0
TRCF 0
Cost of Accidents 0
No. of Days LTI Free 405
No. of Unsafe Act walkabout findings 1364
No. of Unsafe Condition walkabout findings 1162
Total UCUX submission 2257

Legend:
TRCF : Total Recordable Case Frequency
MTC : Medical Treatment Case
RWC : Restricted Work Case
LTI : Lost Time Injury

14 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

1.2 Project HSE Targets


The HSE Targets for the project were:
1.2.1 Carry out all works during the project so as to achieve the highest standards in HSE
with a zero LTI.
1.2.2 Maintain the TRCF below 1.35 throughout the project.
1.2.3 Eliminate any occupational related diseases while carrying out all works during the
project.
1.2.4 Generate less waste / scrap and to eliminate chemical spillage.
1.2.5 Proper handling and management of hazardous waste as ISO 14001 and SSB
requirement.
1.2.6 Carry out remedial action promptly for all identified hazards so as to reduce the risk
of injury to personnel and damage to environment, plant and equipment.
1.2.7 Establish and maintain a safe and healthy working environment.
1.2.8 Establish a pro-active system in HSE Management System as OHSAS 18001.
1.2.9 Identify and record all hazards including near miss by utilizing the SSB System.

1.3 Induction Training


All employees and subcontractors were required to attend NOSP (NIOSH OSFAM Safety
Passport) induction training to familiarize themselves with the HSE requirements of the
project. The induction program covered topics such as the safe work procedures, work
instructions, emergency procedures and assembly points were aim to make personnel
aware of the HSE regulations and system to assist them in carrying out their work in a safe
manner at all times regarding their own safety, that of their colleagues, the environment
and SSB personnel. The number trained is 325 personnel.

1.4 Fabrication Yard Orientations and Security


All PMT, Subcontractors and Client project personnel were required to attend work site
safety orientation programs, which lasted for three and a half hours. The orientation
covered topics like sites rules, emergency response procedures, assembly points, security
procedures and the safety culture expected of each personnel. At the SCDR-A project site
we adopted the Proactive Intervention Culture (PIC) ‘Budaya Tegur Menegur’ safety culture
where anyone can intervene and stop work or advise anyone seen doing unsafe practices.
So far project has inducted 1046 personnel.

1.5 Housekeeping
The project workforce carried out daily housekeeping and cleaning activities at site
before/after work and weekly “Gotong Royong” on Saturday. These programs were aimed
at increasing job efficiency, improving safety performance, reducing risks of fire / explosion
and preventing trip / fall accidents

1.6 Drills
The project executed two drills, the first on 14th February 2007 for First Aid, Rescue and
Evacuation Drill and on 17th July 2007, and the second one on Rescue, Evacuation and Fire
Drill. Both exercises successfully done as per our expectation.

15 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

1.7 Project HSE Meeting


MMHE together with SSB and subcontractors convene an HSE meeting once a week on
every Monday at 0930hrs. The number is 49. The following items were discussed at each
meeting:
1.7.1 Review incident injury reports lessoned learnt and discuss recommended
appropriate controls and interventions.
1.7.2 Review any issue raised by the HSE Management Committee.
1.7.3 Review the progress towards achieving key performance indicators.
1.7.4 Discuss health, safety and environment issues.
1.7.5 Update HSE Plan/programmed.

1.8 Daily Toolbox Meeting


Toolbox meeting were held at site on a daily basis and all MMHE personnel, subcontractors
and vendors attended it. The Toolbox Meetings lasted for about twenty minutes and usually
included items such as:
1.8.1 Pre job discussion.
1.8.2 Hazard identification at work site.
1.8.3 PTW briefing.
1.8.4 Areas of safety concern to the workers.
1.8.5 Project safety rules and policies.
1.8.6 Systems and procedures.
1.8.7 Reviews of injury and incident reports.

Toolbox Meetings were also being used as an educational forum to improve employee’s
knowledge and understanding of health and safety systems, rules and requirement.

1.9 Weekly HSE Talk


MMHE PMT, Subcontractor’s Management and HSE take turns to conduct the HSE Talk every
Monday. The duration of the HSE talk will take approximately 15-30 minutes depending on
the contents of the safety topic.

The topic of the HSE Talk are predominantly focused on the risks, known hazards, unsafe
acts or practices related to the daily activities. The HSE talk also acted as a tool for
management and workers inter communication to convey information and to mobilize
action on current aspect of health safety and the protection of the environment.

All MMHE employees and subcontractors who are involved with the fabrication of SCDR-A
were required to attend the talk and attendance was taken. Any absenteeism without
good reason is considered non-compliance to HSE Plan. To ensure sufficient space to
accommodate all the workers and to protect the place from rain and sun, we erected a
zinc roof shed with a staged podium to ensure this important gathering is always carried out
despite the weather conditions.

16 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

The following are the topics discussed during HSE Talk:


No TOPIC PRESENTER DATE
01 WORKSITE HAZARDS ABD. MANAN A. BAKAR, HSE EXEC. 16/10/06
02 HSE PLAN BRIEFING ABD. MANAN A. BAKAR, HSE EXEC. 23/10/06
03 WORKER HSE RESPONSIBILITY RAHIM MOHAMAD,HSE SUPV. 30/10/06
04 PREJOB HSE SITEPREPARATION MOHAMMAD ABDULLAH, HSE COOR. 06/11/06
05 TOOL & EQUIPMENT INSP. YAHYA ABU, TOOLCENTRE, MMHE 13/11/06
06 WORKSITE HOUSEKEEPNG ANDY DARING, SP, KWSB, 20/11/06
07 HOTWORKS HAZARDS NADARAJAN, HSE SUPV. 27/11/06
08 SCAFFOLDING SAFETY ROSLI SHAHUDIN, SCAFFOLDING FORE. 04/12/06
09 ELECTRICALSAFETY ZUBAIRI, CHARGEMAN,TSD, 11/12/06
10 ELECTRICALSAFETY SITI SYAKIRA & YUNUS, E&I SUPV. 18/12/06
11 WORKING AT HEIGHT TAY SIN YING, PRO. ENGINEER, KWSB. 27/12/06
12 P.P.E. MD. SALLEHUDDIN SAMIUN, E&I TE MMHE 04/01/07
13 HEARING PROTECTION AMIRUSHAM ABD.RAHIM, PIPING TE, MMHE 08/01/07
14 GENERAL WORKSITE SAFETY ABD. MANAN ABU BAKAR, HSE EXEC. 15/01/07
15 RADIOGRAPHY SAFETY IBRAHIM AWANG, PM , ESCON 22/01/07
16 AAA PROGRAM W. M. FARIS W. MAHMUD, MECH. SUPV. PMT 29/02/07
17 RESPIRATORY PROTECTION MAZLINA ABD. HAMID, HEALTH EXEC., QHSE 5/02/07
18 DRIVING SAFETY ABD. MANAN ABU BAKAR, HSE EXEC. 12/02/07
19 HOTWORK SAFETY M. YUSAA M. NOOR, SSB, HSE ADVISOR 21/02/07
20 PIPING INSTALLATION MOHD TAIB HASSAN, JN SAFETY PROMOTER 26/02/07
21 AVIAN FLU KHAIRUL AFFENDI, HE LEAD, QHSE 05/03/07
22 B&P SAFETY HUSAINI HUSSIN, PM, BB TECH 12/03/07
23 THINK BEFORE YOU THROW LIZA RAMLI, ENVI. EXEC., QHSE 19/03/07
24 ELECTRICAL HAZARDS SHAIFUDDIN ABDULLAH, PM, ASADRA 26/03/07
25 B&P HAZARDS ZOL MAHDON, SUPV, BB TECH. 2/04/07
26 HOUSEKEEPING AT SITE AHMAD RAMIZU, PRO. MANAGER, KWSB 11/04/07
27 LIFTING HAZARDS. KRISHNAN PONNAN, LIFTING SUPV. WSD, 16/04/07
28 EFFECT OF CHEMICALS NOOR FARHANA, SAFETY PRO. ASADRA. 23/04/07
29 HSE PENALTY & VIOLATION MD. IBRAHIM MUSTAFA, QHSE, MMHE 30/04/07
30 GENERAL H/KEEPING NORAZLI ASAAD, PE,SSB 07/05/07
31 MECH. & EQUIPMENT SAFETY MD HAZWAN MD DIN, IPT, MMHE 14/05/07
32 GRE SHAVING SAMSUDDIN BANDOG, AESB SAFETY 21/05/07
33 LOTO & SYSTEM HAZARDS ABD HALIM BAJURI, T&C LEAD 28/05/07
34 GRATING MANAGEMENT YUNUS, E&I, PMT 4/06/07
35 GENERAL SAFETY ABD MANAN ABU BAKAR, QHSE 11/06/07
36 SCAFFOLDING ABD JALAL, WSD, MMHE 18/06/07
37 E&I SAFEYY SAIFUDDIN ABDULLAH, PM, ASADRA 25/06/07
38 PFP PROCEDURE ALIAS A. BAKAR, PFP, JURUNATURE 2/7/07
39 HYDROTEST SOP FAUZI ISHAK,PIPING SUPV. MMHE 9/7/07
40 HOTWORK SAFETY ANDY DARING, SP, KWSB, 16/07/07
41 QUALITY & SAFETY JUMIATUL IKLAS, QA ENGINEER 23/07/07
42 HEAT STRESS ABD MANAN ABU BAKAR, HSE EXECUTIVE 30/07/07
43 NOISE INDUCEMENT HAZARDS MAZLINA ABD. HAMID, HEALTH EXEC., QHSE 06/08/07
44 DENGUE & AEDES MD. IBRAHIM MUSTAFA, QHSE, MMHE 13/08/07
45 LUNG DISEASES ABD MANAN ABU BAKAR, HSE EXECUTIVE 20/08/07
46 WORKING ON BARGE/LOADOUT MOHD RIDZUAN HASSAN, CON. SUPT. PMT 27/08/07
47 PROJECT CLOSING REPORT BRIEFING OTHMAN SABRAN, PROJECT MANAGER, PMT 03/09/07
48 SSB CLOSING REPORT BRIEFING FELIXBERTO CLERIGO, CSR, SSB 10/09/07

1.10 HSE Walkabout

Safety Audits / “Walkabout” were conducted on every Monday at 8:30 a.m. It was
participated by a group of personnel, which consists of SSB Company Site Representative
(CSR), MMHE Project Manager, Subcontractor Project Managers, Discipline Superintendent,
HSE Executive, HSE Supervisor, Discipline Engineers, Discipline Supervisors and Subcontractors
Supervisors. Any hazards or unsafe act/conditions will be highlighted and action will be
taken to eliminate or rectify immediately, unresolved findings will be discussed during the
HSE meeting for further action.

17 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

The purpose of the Walkabout is to ensure the work site is safe and in compliance with HSE
rules and regulations. The findings will be discussed in the HSE Weekly meeting.
Apart from the regular Monday Safety Walkabout, we have also implemented a twice-daily
safety task force walkabout among the subcontractors which was conducted by the MMHE
and subcontractor safety promoters at all work locations. The findings and action taken
were discussed in daily safety promoters meeting and submitted on a daily basis for records.

1.11 Friday HSE Video Show

HSE education for all personnel involved in the project plays an important role in
promoting safety work practices, Although the HSE plan only requires once every two weeks
but we conducted on a weekly basis, however we have exceeded this requirement. We
were able to screen the 30 minutes safety video shows every Friday, 520 personnel have
attended. This was made possible by having our own TV and VCD player specifically
dedicated for the SCDR-A project. SSB staff generously lent the audiovisual items.

1.12 QHSE DAY Celebrations

Two QHSE day celebrations were held during the onshore fabrication. The first milestone
achievement was celebrated on 10/05/07.after achieving 250,000 man-hours while the
375,000 milestone was recorded on 14/07/07.

1.13 HSE Incentives

HSE incentives in both cash vouchers and non monetary form such as t-shirts, caps and
mugs were handed out to the workforce on every Monday morning talk for the most
number of U-See, U-Act submitted during the week or month, HSE quiz. Apart from that we
also hand out tokens to those who were selected on the spot for good HSE practices where
PMT and clients top management were making their visits to site. The number of tokens
given is 215.

1.14 HSE Violations

So far we have issued 51 SAC and 7 SVC to non-compliant at site. The objective is to
discourage workforce not to commit un-safe work practices.

1.15 D&A Programmed

The objective is to maintain a safe, healthy and productive work environment, the use and
abuse (sales, possession, trafficking & influence) of drug and alcohol. The number tested so
far, 341 all negative.

18 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

1.16 SAFETY CAMPAIGNS

Two campaigns the first one PPE Awareness Campaign was launched on 10//05//07
and the second, PTW Management Campaign on 25/06/07. A unique feature towards a
pro-active HSE management was the launch of “HSE Commitment by Contractors and
PMT Signing Ceremony”. we were serious about Safety and would ensure that they would
carry out their work in safe manner and complete it on time. Beside the campaigns, all
SCDR-A Project workforces have to wear coverall at all time as per the contract.

1.17 HSE Workshops

HSE workshops were held during the course of the project for supervisors, workers and HSE
personnel. The workshops focused on the Hazard Identification (HIRAC), proactive
interventions (PIC) and refocusing on the HSE objectives for the project with an eye on
Improving HSE performances. MMHE HSE Executive and SSB HSE Advisor jointly animated
the workshop.

1.19 Incident / Injury

All types of incident and injuries, including LTI, MTC, RWC, first aid, near miss, property and
environmental damage were required to be promptly reported within 24 hours to
MMHE/SSB representative verbally and writing.

Since the project commenced on the First Cut of Steel, 12th September 2006 until MCD
date on 28th August 2007 and Sailaway on 27th September, 2007, SCDR-A Topsides has
achieved our vision of “Nobody Gets Hurt” and the target of ZERO INCIDENT.

19 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


2.0 Inter-Departmental Assessment

Assessment
No Item
Excellent Good Fair Poor

1 Procurement

Remarks/ Improvement Opportunity:


1. Attended PIC course as per project requirements.
2. Comply with cover-all & PPE issue @ site.
3. No safety non-compliance.

2 Design & Engineering

Remarks/ Improvement Opportunity:


1. Attended PIC course as per project requirements.
2. Comply with cover-all & PPE issue @ site.
3. No safety non-compliance.

3 Cost Controller

Remarks/ Improvement Opportunity:


1. Attended PIC course as per project requirements.
2. Comply with cover-all & PPE issue @ site.
3. No safety non-compliance.

4 Construction

Remarks/ Improvement Opportunity:


To improve mindset and behavior of PMT and to achieve the objective of world-class safety
performance, as per strategy to support MMHE corporate agenda. To upgrade submission of
UCUX, SAC/SVC, PTW management, active participation in daily Tool Box Talk, HSE meeting and
pro-active site safety intervention & immediate rectification.
PMT have contributed great teamwork to enhance the project housekeeping programmed.

5 Planner

Remarks/ Improvement Opportunity:


1. Attended PIC course as per project requirements.
2. Comply with cover-all & PPE issue @ site.
3. No safety non-compliance.

20 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

Department: Procurement

Overview: Project is an EPCC and a lump sum procurement contract by MMHE. Client Sarawak
Shell Berhad. Target MCD is on 28 August 2007. Sail away by 5 September 2007. This
project is a Topside Drilling Flatform and Satellite Tie-in Flatform. Location is 200
Kilometers offshore Miri-Sarawak. The Design consultant is MMC Oil & Gas Engineering
Sdn. Bhd.

1.0 Long Lead Items

Actual
No Item PR Date PO Date FRD Delivery Reason for Delay
Date
Technical clarification from
Design delay due to
External Door Type D1
1 25/08/06 23/01/07 22/12/06 18/04/07 engineer’s transition. PA was
and D2 and D3
hold. Manage to capture
installation on site
Technical clarification from
Design delay due to
External Door Type D4
2 25/08/07 23/01/07 22/12/06 05/02/07 engineer’s transition. PA was
,D4A,D5, and D6
hold. Manage to capture
installation on site.
Delay on delivery of package
due technical queries /
procurement of materials to
Pedestal Crane engine
3 05/08/06 19/10/06 15/05/07 10/07/07 proceed on production by
driven
vendor. Manage to coup up
schedule for installation on
site.
Delay cutting of Po’s &
delivery due to budgetary
4 Flush / Closed water Tank 5/8/06 19/10/06 15/05/07 10/06/07
issue. Still manage to meet
schedule on site installation
Delay cutting of Po’s &
Open Drain Caisson delivery due to budgetary
5 05/08/06 19/10/06 15/05/07 01/06/07
Pump issue. Still manage to meet
schedule on site installation
Delay cutting of Po’s &
delivery due to budgetary
6 Diesel Transfer Pump 05/08/06 19/10/06 15/05/07 10/06/07
issue. Still manage to meet
schedule on site installation
Delayed of cutting of PO’s
due to budgetary issue /
7 Sonic Vent Tip Package 07/08/06 23/01/07 07/05/07 10/07/07 technical clarification by
design. Still managed to install
as per site schedule.
Delayed of cutting of PO’s
due to budgetary issue /
Corrosion Inhibitor
8. 07/08/06 18/10/06 08/03/07 03/05/07 technical clarification by
Injection Skids
design. Still managed to install
as per site schedule.
Delayed of cutting of PO’s
due to budgetary issue /
9 Closed Drain Vessel 07/08/06 21/11/06 22/01/07 26/04/07 technical clarification by
design. Still managed to install
as per site schedule.

21 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


Managed to capture
10 Condensate POD 07/08/06 21/11/06 22/01/07 26/04/07
installation on site.
Managed to capture
11 Fresh Water Tank 07/08/06 06/11/06 20/12/06 10/05/07
installation on site.
Managed to capture
12 Flush Water Tank 07/08/06 06/11/06 20/12/06 24/04/07
installation on site.
Managed to capture
13 Swing Jib Crane 07/08/06 13/10/06 10/05/07 15/05/07
installation on site.
Due late production from
14 Pig Trap Enclosure 16/08/06 06/02/07 26/03/07 13/08/07
vendor principal

15 Pig Receiver 18/08/06 23/01/07 20/06/07 01/10/07 E11K-A ship loose material.

Globe/ Check / Gate Managed to capture


16 17/08/06 29/01/07 11/12/06 14/07/07
Valve installation on site.
Managed to capture
17 Gate Valve 17/08/06 29/01/07 11/12/06 14/07/07
installation on site.
Managed to capture
18 Check Valve 17/08/06 29/01/07 11/12/06 14/07/07
installation on site.
Staggered delivery by Vendor
(Metronet). Remaining to
19 Check Valve 17/08/06 26/01/07 11/12/06
complete the delivery by 30
August 2007
Managed to capture
20 PipeWld. Dn300 23/08/06 29/12/06 11/12/06
installation on site.
Delayed on delivery.
21 Wellhead Control Panel 10/08/06 26/02/06 18/03/07 10/07/07 Managed to capture
installation on site.
Delayed on delivery.
22 Sand Monitoring Systems 11/08/06 29/01/07 18/03/07 22/05/07 Managed to capture
installation on site.
Delayed on delivery.
23 Choke Valve Hydraulic 15/08/06 04/12/06 01/03/07 16/06/07 Managed to capture
installation on site.

24 Ultrasonic Gas Flow meter 15/08/06 01/03/07 To deliver by 30 August 2007

Delayed on delivery.
25 GPA/PA System Cabinet 23/08/06 29/12/06 01/03/07 06/05/07 Managed to capture
installation on site.
Delayed on delivery.
26 Flame Detector (IR Point) 23/08/06 31/01/07 01/03/07 06/05/07 Managed to capture
installation on site.
Delayed on delivery.
27 ESD Break glass Station 23/08/06 22/12/06 01/03/07 15/04/07 Managed to capture
installation on site.
Delayed on delivery.
28 Restriction Orifice Plate 29/08/06 29/01/07 01/03/07 30/07/07 Managed to capture
installation on site.
Delayed on delivery.
Level Gauge (using
29 30/08/06 27/03/07 01/02/07 15/08/07 Managed to capture
pressure gauge)
installation on site.

30 Pig Signaler 14/09/06 19/04/06 01/02/07 15/11/ 07 To install Offshore

Delayed on delivery.
31 Pressure Gauges 14/09/06 05/04/07 01/02/07 07/08/07 Managed to capture
installation on site.
Delayed on delivery.
32 Level Gauges Reflex 14/09/06 16/04/07 01/02/06 08/08/07 Managed to capture
installation on site.
Delayed on delivery. Manage
33 Instrument Junction Boxes 18/11/06 12/04/07 30/04/07 11/07/07
to capture installation on site

22 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.


Delayed on delivery.
34 Fire & Gas Junction Box 18/11/06 12/04/07 30/;04/07 11/07/07 Managed to capture
installation on site.
Delayed for some qty. due
35 Cable Glands Instrument 23/11/06 01/ 06/07 08/02/07 21/06/07 additional requirement on
site.
Delayed for some qty. due
Cable Ladders & Trays
36 02/11/06 15/06/07 08/02/07 25/06/07 additional requirement on
Instrument
site.
Managed to capture
37 Multi Cable Transit 25/11/06 03/04/07 15/04/07 25/04/07
installation on site.
Delayed for some qty. due
38 Power Transformer 10/08/06 09/11/06 01/11/06 05/05/07 additional requirement on
site.
Delayed for some qty. due
39 Ring Main Unit 10/08/06 28/12/06 01/04/07 18/06/07 additional requirement on
site.
Delayed for some qty. due
40 Interposing Relay Panel 11/08/06 26/02/07 16/11/06 19/05/07 additional requirement on
site.
Delayed on PO cut due
Power Distribution Board budgetary issue & tech
41 11/08/06 06/12/06 16/11/06 05/04/07
(small) clarification. Managed to
capture installation on site.
Delayed on PO cut due
budgetary issue & tech
42 Ring Main Unit 10/08/06 28/12/06 01/04/07 18/06/07
clarification. Managed to
capture installation on site.
Delayed on PO cut due
budgetary issue & tech
43 Navigational Aids System 12/08/06 07/12/06 01/11/06 05/05/07
clarification. Managed to
capture installation on site.
Delayed on PO cut due
Normal Fluorescent budgetary issue & tech
44 230/8/06 31/01/06 15/1/2007 07/06/07
Lighting Fixture clarification. Managed to
capture installation on site.
Emergency florescent Managed to capture
45 23/08/06 31/01/06 15/01/07 09/06/07
Lighting Fixture installation on site.
Plan PR captured delivery on
46 Electrical Cable 24/08/06 23/01/07 16/04/07 14/04/07 site. Delay due to additional
requirement on site.
Plan PR captured delivery on
Cable ladders & Trays
47 30/08/06 07/12/06 30/01/07 06/02/07 site. Delay due to additional
electrical
requirement on site.
Plan PR captured delivery on
48 Electrical Cable Glands 07/09/06 09/12/06 16/04/07 14/04/07 site. Delay due to additional
requirement on site.
Plan PR captured delivery on
49 Junction Boxes Electrical 08/09/06 26/03/07 12/02/06 29/06/07 site. Delay due to additional
requirement on site.

2.0 Lessons Learnt


Fifty percent (50%) of the long lead items did not meet the field requirement date from PR. Due
to long process on technical clarification from Design, Budgetary issues, holding the circulation
of PA’s / PO’s. Hence Procurement and PMT managed to capture installation of items in the
project. To avoid happening again, need to shorten period on TBE’s and PA’s circulation for
approval. Additional items / Shortfall materials, which nearly capture the total quantity of Plan
PR’s, should be avoided. Procurement is facing a difficulties on ordering as wells as capturing the
delivery timing of items.

23 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

Department: Design & Engineering

Scope: D & E scope include, but not limited to, review and checking of Client-supplied AFC drawings,
PDMS and ACADD models, MTO’s, COG, Structural analysis and other calculations related to
the execution and final completion of the project. Scope also covers procurement and
technical evaluation of contractual scope of supply such as Structural steel, Piping bulk
materials, manual valves except ball valves 2” and above and other materials required in the
Contracts; deliverables such as fabrication drawings for all disciplines and reference drawings
from Client-supplied AFC drawings and soft copies.

Overview: The Shallow Clastics field, located 140-km NW of Bintulu, was discovered in 1969 by wells
F13-1 and E11-1. The field is one of the eleven fields under the MLNG-DUA PSC, which took effect on
30 June 1993. Under the terms of this PSC, Sarawak Shell Berhad as a joint venture arrangement with
PETRONAS Carigali Sendirian Berhad will operate the Shallow Clastics field until PSC expiry on 26 May
2015. Shallow Clastics Phase 3 is the development of the SW area of the Shallow Clastics field. SCDR-
A will be placed on the SW area of the Shallow Clastics field with four highly deviated wells and one
back up well and tied back to the E11K-A platform via a single 6.4-km, 14” carbon steel pipeline. The
gas and condensate from the SW area reservoir will be transported wet as a multiphase mixture to the
E11K-A facilities, where the fluids will be separated and re-combined prior to export to MLNG-DUA.

1.0 Statistics

Instrumentation

Architectural
Mechanical

Structural

Electrical

Piping
No Subject

1 No. of shop drawing original estimation 100 174 365 684 11 598

No. of shop drawing additional from


2 6 nil nil nil nil 3
Original estimate due to change order
No. of shop drawing additional from
3 nil nil nil 278 nil 2
original due to MMHE

4 Man-hour 27648 8112 10900 7152 2700 10818

5 No. drawing days delay nil nil nil nil nil nil

6 No. of site-clash nil nil nil 50 nil 8

7 No. of client deliverable delay nil nil nil nil nil nil

8 No. of PR issued on time 50 26 45 43 7 33

9 No. of Change Notifications issued nil nil nil nil nil 1

10 No. of Site Technical Query issued 31 61 29 9 13 19

24 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

2.0 Inter-departmental Assessment

Assessment
No Item
Excellent Good Fair Poor

2.1 Procurement

Remarks/ Improvement Opportunity:


PR’s raised from various disciplines should be acted upon promptly, thus ensuring a window
wherein delivery of long-lead items will be captured within the project time frame. Queries to
Vendors should be expedited judiciously so as to enhance early completion of Technical
Evaluations and issuance of Purchase Orders, thus giving vendors lead time to meet delivery
schedules.
2.2 Construction

Remarks/ Improvement Opportunity


1. PMT to inform of any clash, material shortfall, rejected purchased items and other problems
involving D & E before giving information to Client in order to resolve these problems
internally so as not to create unnecessary remarks and reprimands from the Client.
2. QC to expedite issuance of “Red-line” mark-ups so as not to rush D & E in the generation of
“AS-BUILTS” in the dying days of the project.
3. PR’s for additional materials required by the Project not covered by the MTO should be
raised by PMT to expedite speedy processing.
4. Close interaction between PMT and D & E is a must to avoid confusion, finger-pointing and
blaming once problems arise.

2.3 Cost Controller

Remarks/ Improvement Opportunity


D & E to inform Cost Control Engineer of any addition or deletion of materials in the form
Material Change Notice (MCN) to keep him updated of any V.O.’s.

2.4 Planner

Remarks/ Improvement Opportunity


Planner to furnish D & E updated planning package every now and then.

25 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

3.0 Lessons Learnt

3.1 PDMS model should be clash- checked after exportation of BOCAD to ensure a clash-
free piping configuration.
3.2 Thorough review and checking of Client and Yard supplied materials to avoid last
minute procurement of shortfall materials.
3.3 Close interaction between PMT and D & E to ensure the capturing of potential
problems at site such as shortage of construction materials, clashes, obstructions and
tripping hazards, etc.
3.4 Inter-disciplinary coordination should be encourage to avoid inter-disciplinary clashes
at site during installation of piping, supports, cable trays, pad eyes, etc.
3.5 Early issuance by QC of “RED-LINES” to avoid cramming on document preparation
during project close-out preparations.

Department: QA/QC

Project Quality Target:


• Zero LTI (Lost Time Injury)
• Piping repair rate less than 0.5 %
• Structural repair rate less than 1 %

Objective of Project Quality Plan:


1. To maintain a comprehensive Quality Management System which control such as project
management, design engineering, procurement, fabrication process and pre-commissioning.
2. Ensuring that project quality meets total Sarawak Shell Berhad (SSB) satisfaction and statutory
requirements
3. Minimizing potential quality problem areas, thus improving cost effectiveness and efficiency.
4. Ensure regular monitoring, reviews, inspections and audits to verify the implementation
compliance to the contractual requirements.

26 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

1.0 Statistics

No Subject Status

1 Project Specific Procedures Total : 54, Approved: 54 , Outstanding: 0

2 Quality Action Note (QAN) issued Total: 106, Close: 106, Outstanding: 0

3 Non-conformance report (NCR) issued Total: 15, Close: 15, Outstanding; 0

Structural:
Length Tested (RT+UT) : 1,376,332 mm.
Defect length : 4,413 mm.
Defect rate : 0.32 %
Major Type of Defect : Slag, Lack of Fusion, & Porosity
4 Weld Repair Rate
Piping:
Length Tested (RT+UT) : 579051 mm
Defect length : 206 mm.
Defect rate : 0.04 %
Major Type of Defect : Porosity and Lack of Fusion

2.0 Lessons Learnt

Vendor supplied and delivered the equipments (Closed drain vessel and Condensate Pod)
to MMHE yard without completion of Non Destructive Test and improper compilation of
Manufacturer Data Record. Rectification should be done by Project Team in order to fulfill
the Code requirements and Client specifications. The repair activities such as re-alignment
on nozzle, re-Radiography, re-Hydro test and repainted. These kinds of repairs consume a lot
material, consumables, schedule and cost as well.

Recommendation:
• Site visit for ensuring capability and performance of the selected vendor / supplier for
the project critical equipment /mechanical package
• To conduct pre-execution audit prior to fabrication commencement to give more
confidence on availability and readiness of drawing, material, project
personnel/manpower, tools and yard facilities.
• Procurement to update vendor data monitoring registry to achieve final
documentation compilation in schedule.
• To increase the frequency of inspection to vendor yard for earlier detection if any
malfunction or non-conformances occurred during fabrication phase.

27 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

Department: Cost Controller

Project Overview: Generally SCDR-A Topsides is a profitable project but the project was largely hit
by the price escalation on Stainless Steel and Duplex Stainless Steel related
materials/equipment.
Few materials and equipment delayed of delivery due some prolonged
settlement on over-budgeted issues thus contribute to most of negative
progress of the project and catch-up progress by means of acceleration is
inevitable.

Massive repetitive works as a result of clashing/obstruction is the “ugly” side of


the project.

1.0 Statistics

No Subject Value (RM)

1 Original Contract Value 75,667,000.00


2 Adjusted Contract Value (incl. variations and re-measurement) 76,859,000.00
3 Total Project Profit 2,240,000.00
4 Liquidation Damages to Vendors and 3rd Party Consultants (If any) Nil
5 Liquidation Damages by Client (If any) Nil
6 Project Job Cost Summary
i. Mechanical 9,954,000.00
ii. E&I 11,890,000.00
iii. Structural 3,190,000.00
Blasting/Corrosion Protection 183,000.00
Architectural 800,000.00
Pressure Vessel/Tank 898,000.00
iv. Piping/Valves 11,740,000.00
Testing/Commissioning 200,000.00
Sea fastening/Grillage 27,000.00
Service to Client 103,000.00
v. Project Management Team 649,000.00
Grating 545,000.00
Fire Fighting & Safety Equipment 37,000.00
Ship loose 100,000.00
Handling Client Supplied Materials 100,000.00
Documentations 100,000.00
Consumables/miscellaneous 253,000.00
vi. Subcontractor 22,330,000.00
vii. Direct Expenses 4,128,000.00

28 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

2.0 Change Orders

• To attach the following reports from the COP Register


See Appendix 8 - RFQ/CO/VOP Log

3.0 Budget Cost Overran, Reasons and Mitigating Action

3.1 Material/ disciplines

3.1.1 Material procured last minutes to cater miss-out and modification works
entails ex-stock material is secured at higher price.
Design MTO to be doubled check by Construction to cater for potential
unavoidable clashing/modification, site routing etc

3.1.2 Procured materials from VDP – Price to be concluded based on bidding


price (price that had been used for submission of ITB to Client) as long as the
price is still valid. No re tendering is necessary.

3.1.3 Price escalation especially SS and DSS based materials. Further negotiation.

3.1.4 Delayed delivery project materials i.e. DSS pipe materials entails project to
be accelerated to regain the progress would cost extra money to the
project in terms of acceleration.

3.2 Subcontract Works/ disciplines

3.2.1 Procure project materials thru CO mechanism for faster delivery to catch-up
the schedule. Procurement, Design and Construction to double-checked
actual materials and to cater potential site routing/re-routing, clashing or site
obstruction.

3.2.2 Repetitive/Modification
To officially highlights Client of any hindrance at site fabrication with regard
to final location etc. so as to minimize the repetitive works. PDMS review to
be conducted regularly.

3.2.3 VO to the contractor for additional work of punch list clearance of vendor
package i.e. Pedestal Crane, Vessel/ Procurement Dept. to ensure recovery
prior VO to be executed.

29 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

4.0 Project Cash flow Status and lesson learnt

4.1 Payment Certificate accorded with massive materials documentation i.e. GRIN,
MAC, and PO.

Material Control Coordinator to promptly extend a copy of duly approved material


documentation i.e. GRIN, MAC to Quantity Surveyor to ensure expeditious
preparation of Payment Certificate.

5.0 Inter-departmental Assessment

Assessment
No Item
Excellent Good Fair Poor

1 Procurement

Remarks/ Improvement Opportunity:


1. VDP: Price imposed by vendor is expensive/to further negotiate.
2. Package equipment delivered with punch list: Procurement to ensure the cost recovery
of punch list cleared by subcontractor / to monitor closely to ensure the completion of
equipment package prior to the delivery.
3. Delayed of materials delivery i.e. DSS entails the project progress delayed.

2 Design & Engineering

Remarks/ Improvement Opportunity:


Plenty of material purchase at last minutes to cater for shortage of materials due to miss-out,
site routing, clashing and modifications. / MTO provided by Design to be doubled check by
Construction to ensure sufficiency prior to issue PR.

3 Construction

Remarks/ Improvement Opportunity:


1) To check detail drawing provided by design against the site condition for which items to
be installed/erected just to minimize the potential clashing prior to fabrication and
installation.
2) To double checked MTO provided by design prior to issue PR as to ensure that the
materials be secured sufficiently. Material ordered on urgent basis entails materials be
obtained ex-stock and expensive.
3) .To officially highlights Client of any hindrance at site fabrication with regard to final
location etc. to minimize the repetitive works on regular basis
4) Site Instruction (SI) issued to sub-contractor to be substantiated with technical justification
i.e. mark-up drawing, STQ, e-mail etc. to ensure the change control and monitoring
being facilitated.

30 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report

Sarawak Shell Bhd.

6.0 Lessons Learnt

6.1 To regularly conduct PDMS review against AFC document issued by Client to at least
minimize site clashing/obstruction

6.2 To double-checked MTO provided by design prior to issue PR as to ensure that the
materials be secured sufficiently. Material ordered on urgent basis entails materials
be obtained ex-stock and expensive

6.3 To check detail drawing provided by design against the site condition for which items
to be installed/erected just to minimize the potential clashing prior to fabrication and
installation.

6.4 To officially highlights Client of any hindrance at site fabrication with regard to final
location etc. to minimize the repetitive works on regular basis

6.5 Site Instruction (SI) issued to sub-contractor to be substantiated with technical


justification i.e. drawing, STQ, e-mail etc. to ensure the change control and
monitoring being facilitated.

6.6 Material Control Coordinator to promptly extend a copy of duly approved material
documentation i.e. GRIN, MAC to Quantity Surveyor to ensure expeditious
preparation of Payment Certificate.

FABRICATION ERECTION SEQUENCE

See Appendix 9 – Erection Sequence

PROGRESS PHOTOGRAPHS

See Appendix 10 - Progress Photographs

31 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 1 - SCHEDULE BARCHART


Contract No : 591397 Page 1 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov

Fabrication of SCDR-A
SCD Topsides & Existing E11K-A Platform 0 19-Jul-06 05-Sep-07 19-Jul-06 A 05-Oct-07 A 0

PROJECT MILESTONE
MILEST 0 19-Jul-06 05-Sep-07 19-Jul-06 A 05-Oct-07 A 0

MIL1000 Contract Award 0 100% 19-Jul-06 19-Jul-06 A


MIL1010 Client to Issue AFC Dwgs & MTO 0 100% 04-Aug-06 04-Aug-06 A
MIL1020 Start of Fabrication Works (1st Cut of Steel) 0 100% 12-Oct-06 12-Oct-06 A
MIL1060 Latest Box-Up 0 0% 27-Apr-07 04-May-07 A
MIL1030 MCD for Topsides 0 0% 28-Aug-07 03-Sep-07 A
MIL1040 SCDR-A Topsides Ready for Sailaway 0 0% 05-Sep-07 27-Sep-07 A
MIL1070 MCD for Shiploose Items 0 0% 07-Aug-07 01-Oct-07 A
MIL1050 E11K-A Ready for Sailaway (Shiploose Items) 0 0% 11-Aug-07 05-Oct-07 A
PRELIMINARIES 0 19-Jul-06 23-Aug-07 19-Jul-06 A 05-Oct-07 A 0

Construction Facilities
Facilitie 0 19-Jul-06 05-Jul-07 19-Jul-06 A 11-Jul-07 A 0
PRE1130 Set-up Contractor's Facilities 0 100% 19-Jul-06 06-Dec-06 19-Jul-06 A 20-Dec-06 A
PRE1180 Set-up SSB's site Office and Facilities 0 100% 19-Jul-06 18-Dec-06 19-Jul-06 A 29-Dec-06 A
PRE1210 Set-up EDMS system, including lease line. 0 100% 07-Oct-06 12-Jan-07 07-Oct-06 A 19-Jan-07 A
PRE1220 Set-up Completion Management System 0 100% 07-Oct-06 09-Mar-07 07-Oct-06 A 02-Mar-07 A
PRE1430 Set-up Video conferencing Facilities 0 100% 07-Oct-06 06-Nov-06 01-Nov-06 A 24-Nov-06 A
PRE1440 Welder Qualification Test 0 100% 12-Oct-06 28-Dec-06 08-Nov-06 A 26-Jan-07 A
PRE1170 Facilities for 3rd Parties 0 100% 07-Feb-07 05-Jul-07 12-Feb-07 A 11-Jul-07 A
Project Management 0 01-Aug-06 15-May-07 01-Aug-06 A 18-May-07 A 0
PRE1450 Mobilise Project Management Team, Supervision and Staff 0 100% 01-Aug-06 20-Dec-06 01-Aug-06 A 16-Mar-07 A
PRE1690 Mobilise Pre-Commissioning Team 0 100% 07-Apr-07 15-May-07 07-Apr-07 A 18-May-07 A
Procedures Preparation
Preparat 0 01-Aug-06 06-Jul-07 01-Aug-06 A 06-Jul-07 A 0
PRE1480 Prepare/Submit/Approve Planning Package 0 100% 01-Aug-06 31-Oct-06 01-Aug-06 A 18-Oct-06 A
PRE1490 Prepare/Submit/Approve HSE Procedures 0 100% 01-Aug-06 06-Nov-06 01-Aug-06 A 01-Nov-06 A
PRE1500 Prepare/Submit/Approve QA/QC Procedures 0 100% 01-Aug-06 06-Nov-06 01-Aug-06 A 04-Dec-06 A
PRE1510 Prepare/Submit/Approve Engineering Procedures 0 100% 01-Aug-06 02-Jan-07 01-Aug-06 A 06-Jul-07 A
PRE1670 Prepare/Submit/Approve Fabrication Procedures 0 100% 01-Aug-06 25-Jan-07 01-Aug-06 A 30-Mar-07 A
PRE1680 Prepare/Submit/Approve Precomm Procedures 0 100% 24-Apr-07 06-Jul-07 14-Nov-06 A 19-Feb-07 A
PRE1520 Prepare/Submit/Approve Weighing Procedures 0 100% 25-Jan-07 05-Apr-07 29-Jan-07 A 06-Jul-07 A
Insurance & Bond 0 21-Sep-06 21-Feb-07 21-Sep-06 A 29-Jun-07 A 0
PRE1530 Submit/Accept Performance Bond 0 100% 21-Sep-06 18-Nov-06 21-Sep-06 A 16-Oct-06 A
PRE1540 Submit/Accept Insurances 0 100% 21-Sep-06 16-Oct-06 21-Sep-06 A 20-Feb-07 A
PRE1550 Submit/Accept CIDB Tax 0 100% 21-Sep-06 21-Feb-07 11-Jun-07 A 29-Jun-07 A
Final Documentations 0 07-May-07 23-Aug-07 07-May-07 A 05-Oct-07 A 0
PRE1560 Prepare & Submit Final Documentation (Manual/Closeout R... 0 100% 07-May-07 23-Aug-07 07-May-07 A 05-Oct-07 A
Sub-Contractors Selection
Sele 0 01-Aug-06 10-Aug-07 01-Aug-06 A 29-Jun-07 A 0
PRE1260 Prepare Tender/Evaluate for STRUCTURAL Subcontractor 0 100% 01-Aug-06 11-Oct-06 01-Aug-06 A 01-Nov-06 A
PRE1270 Prepare Tender/Evaluate for BLASTING & PAINTING Subcontr... 0 100% 26-Sep-06 05-Dec-06 02-Oct-06 A 21-Feb-07 A
PRE1280 Prepare Tender/Evaluate for PIPING Subcontractor 0 100% 06-Oct-06 05-Jan-07 06-Oct-06 A 06-Feb-07 A
PRE1330 Prepare Tender/Evaluate for HVAC Subcontractor 0 100% 06-Oct-06 15-Nov-06 11-Oct-06 A 15-Dec-06 A
PRE1290 Prepare Tender/Evaluate for MECHANICAL Subcontractor 0 100% 23-Oct-06 13-Jan-07 30-Oct-06 A 06-Feb-07 A
PRE1300 Prepare Tender/Evaluate for ELECTRICAL Subcontractor 0 100% 17-Nov-06 20-Feb-07 27-Nov-06 A 24-Feb-07 A
PRE1310 Prepare Tender/Evaluate for INSTRUMENT Subcontractor 0 100% 17-Nov-06 20-Feb-07 27-Nov-06 A 24-Feb-07 A
PRE1320 Prepare Tender/Evaluate for ARCHITECTURAL Subcontractor 0 100% 02-Jan-07 16-Mar-07 06-Jan-07 A 26-Feb-07 A

Primary Baseline Job No : #2006351C / Planning Ref : PN5103-0A     Date Revision Checked Approved
Actual Work 04-Sep-06 Rev. A0 - For Reviewed and Approval
SCHEDULE OF SCDR-A TOPSIDES AND E11K-A 18-Oct-06 Rev. 0 - For Approval
Remaining Work
SHIPLOOSE ITEMS
Critical Remaining Work
Milestone Closeout Report
Contract No : 591397 Page 2 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
PRE1405 Prepare Tender/Evaluate for GRE PIPING Subcontractor 0 100% 27-Jan-07 17-Mar-07 22-Jan-07 A 07-Feb-07 A
PRE1505 Prepare Tender/Evaluate for WEIGHING Subcontractor 0 100% 27-Apr-07 25-Jun-07 07-May-07 A 25-Jun-07 A
PRE1605 Prepare Tender/Evaluate for LOAD-OUT Subcontractor 0 100% 18-Jun-07 10-Aug-07 04-Jun-07 A 29-Jun-07 A
Award Sub-Contractor
Sub-Contracto & Mobilization 0 11-Oct-06 18-Aug-07 03-Nov-06 A 10-Sep-07 A 0
PRE1265 Award & Mobilization of STRUCTURAL Subcontractor 0 100% 11-Oct-06 19-Oct-06 03-Nov-06 A 09-Nov-06 A
PRE1335 Award & Mobilization of HVAC Subcontractor 0 100% 15-Nov-06 23-Nov-06 15-Dec-06 A 22-Dec-06 A
PRE1285 Award & Mobilization of PIPING Subcontractor 0 100% 05-Jan-07 13-Jan-07 07-Feb-07 A 12-Feb-07 A
PRE1295 Award & Mobilization of MECHANICAL Subcontractor 0 100% 13-Jan-07 22-Jan-07 07-Feb-07 A 13-Feb-07 A
PRE1355 Award & Mobilization of GRE PIPING Subcontractor 0 100% 17-Mar-07 26-Mar-07 08-Feb-07 A 14-Feb-07 A
PRE1275 Award & Mobilization of BLASTING & PAINTING Subcontractor 0 100% 05-Dec-06 13-Dec-06 22-Feb-07 A 02-Mar-07 A
PRE1305 Award & Mobilization of ELECTRICAL Subcontractor 0 100% 20-Feb-07 28-Feb-07 26-Feb-07 A 02-Mar-07 A
PRE1315 Award & Mobilization of INSTRUMENT Subcontractor 0 100% 20-Feb-07 28-Feb-07 26-Feb-07 A 02-Mar-07 A
PRE1325 Award & Mobilization of ARCHITECTURAL Subcontractor 0 100% 16-Mar-07 24-Mar-07 27-Feb-07 A 08-Mar-07 A
PRE1365 Award & Mobilization of WEIGHING Subcontractor 0 100% 25-Jun-07 02-Jul-07 25-Jun-07 A 05-Jul-07 A
PRE1375 Award & Mobilization of LOAD-OUT Subcontractor 0 100% 10-Aug-07 18-Aug-07 29-Jun-07 A 10-Sep-07 A
ENGINEERING 0 04-Aug-06 06-Aug-07 04-Aug-06 A 05-Oct-07 A 0

Review Materials 0 04-Aug-06 02-Jan-07 04-Aug-06 A 02-Mar-07 A 0


PRE1340 Prepare/Submit/Approve of STRUCTURAL MTO 0 100% 04-Aug-06 08-Nov-06 04-Aug-06 A 27-Nov-06 A
PRE1341 Prepare/Submit/Approve of PIPING MTO 0 100% 04-Aug-06 02-Dec-06 04-Aug-06 A 13-Dec-06 A
PRE1342 Prepare/Submit/Approve of MECHANICAL MTO 0 100% 04-Aug-06 27-Oct-06 04-Aug-06 A 28-Nov-06 A
PRE1343 Prepare/Submit/Approve of ELECTRICAL MTO 0 100% 04-Aug-06 27-Nov-06 04-Aug-06 A 29-Nov-06 A
PRE1344 Prepare/Submit/Approve of INSTRUMENT MTO 0 100% 04-Aug-06 27-Nov-06 04-Aug-06 A 29-Nov-06 A
PRE1345 Prepare/Submit/Approve of ARCHITECTURAL MTO 0 100% 18-Oct-06 18-Dec-06 18-Oct-06 A 22-Dec-06 A
PRE1346 Prepare/Submit/Approve of HVAC MTO 0 100% 23-Nov-06 02-Jan-07 15-Dec-06 A 02-Mar-07 A
Construction Drawings
Drawin 0 04-Aug-06 06-Aug-07 04-Aug-06 A 05-Oct-07 A 0
PRE1350 Prepare/Submit/Approve STRUCTURAL Shop Drawings 0 100% 04-Aug-06 23-Feb-07 04-Aug-06 A 02-Mar-07 A
PRE1360 Prepare/Submit/Approve PIPING Shop Drawings 0 100% 04-Aug-06 13-Mar-07 04-Aug-06 A 09-Mar-07 A
PRE1370 Prepare/Submit/Approve MECHANICAL Shop Drawings 0 100% 02-Oct-06 02-Mar-07 02-Oct-06 A 07-Mar-07 A
PRE1380 Prepare/Submit/Approve ELECTRICAL Shop Drawings 0 100% 18-Oct-06 02-Apr-07 18-Oct-06 A 11-May-07 A
PRE1390 Prepare/Submit/Approve INSTRUMENT Shop Drawings 0 100% 18-Oct-06 07-Apr-07 18-Oct-06 A 27-Apr-07 A
PRE1410 Prepare/Submit/Approve HVAC Shop Drawings 0 100% 13-Dec-06 17-Mar-07 18-Dec-06 A 30-Mar-07 A
PRE1400 Prepare/Submit/Approve ARCHITECTURAL Shop Drawings 0 100% 30-Dec-06 23-Apr-07 22-Dec-06 A 20-Apr-07 A
PRE1420 Prepare/Submit/Approve AS-BUILT Drawings 0 100% 29-Mar-07 06-Aug-07 02-Apr-07 A 05-Oct-07 A
PRE1720 Prepare/Submit/Approve SEAFASTENING Drawings 0 100% 01-Mar-07 28-May-07 06-Aug-07 A 27-Aug-07 A
PROCUREMENT 0 07-Aug-06 23-Aug-07 07-Aug-06 A 05-Oct-07 A 0

Client Supply Materils 0 17-Aug-06 23-Aug-07 13-Sep-06 A 10-Sep-07 A 0


PRO1000 Rec'v/Accept Structural Steel : Type I and II Plates 0 100% 17-Aug-06 05-Sep-06 13-Sep-06 A 30-Sep-06 A
PRO1010 Rec'v/Accept Structural Steel : Type I and II Beams 0 100% 17-Aug-06 05-Sep-06 13-Sep-06 A 30-Sep-06 A
PRO1020 Rec'v/Accept Structural Steel : Type I and II Round Tubulars 0 100% 17-Aug-06 05-Sep-06 13-Sep-06 A 30-Sep-06 A
PRO1110 Rec'v/Accept Wet Gas Metering Skid (Operational Metering) 0 100% 01-Jun-07 19-Jun-07 29-Nov-06 A 15-Dec-06 A
PRO1090 Rec'v/Accept Telecommunication Equipment 0 100% 18-Apr-07 05-May-07 13-Dec-06 A 27-Dec-06 A
PRO1120 Rec'v/Accept 14" CS Pipeline (pipeline spools, bends, major ... 0 100% 30-Jun-07 17-Jul-07 23-Dec-06 A 08-Jan-07 A
PRO1070 Rec'v/Accept AC Uninterruptible Power Supply (UPS) 0 100% 09-Apr-07 25-Apr-07 30-Dec-06 A 15-Jan-07 A
PRO1140 Rec'v/Accept Fittings & Accessories for Subsea Cable Cone... 0 100% 03-Jul-07 20-Jul-07 27-Jan-07 A 16-Feb-07 A
PRO1030 Rec'v/Accept All Ball Valves : Manual & Actuated Valves 2" (... 0 100% 02-Apr-07 19-Apr-07 16-Feb-07 A 15-May-07 A
PRO1100 Rec'v/Accept Wellhead Desander Skids 0 100% 18-May-07 05-Jun-07 03-Mar-07 A 16-Mar-07 A
PRO1060 Rec'v/Accept IPS, FGS and Wellhead Control System (WHCS) 0 100% 04-Apr-07 21-Apr-07 06-Mar-07 A 18-May-07 A
PRO1040 Rec'v/Accept Motor Operated Valves 0 100% 02-Apr-07 19-Apr-07 30-Mar-07 A 13-Apr-07 A
PRO1050 Rec'v/Accept Distributed Control System (DCS) & Audio Visu... 0 100% 04-Apr-07 21-Apr-07 31-Mar-07 A 06-Apr-07 A
PRO1080 Rec'v/Accept 400V Switchboard 0 100% 09-Apr-07 25-Apr-07 14-May-07 A 18-May-07 A
PRO1130 Rec'v/Accept Seafastening Mat'l, Lifting Slings and Shackles 0 100% 07-Aug-07 23-Aug-07 07-Aug-07 A 10-Sep-07 A
MMHE Supply Materials
Materi 0 07-Aug-06 08-Aug-07 07-Aug-06 A 05-Oct-07 A 0
Contract No : 591397 Page 3 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
Purchase Request to Purchase Order 0 07-Aug-06 08-Feb-07 07-Aug-06 A 25-May-07 A 0
Structural 0 11-Sep-06 19-Dec-06 11-Sep-06 A 20-Apr-07 A 0
PRO1600 PR/PO of Structural Tubulars 0 100% 11-Sep-06 30-Oct-06 11-Sep-06 A 08-Nov-06 A
PRO1610 PR/PO of Structural Beams 0 100% 15-Sep-06 06-Nov-06 15-Sep-06 A 21-Nov-06 A
PRO1620 PR/PO of Structural Plates 0 100% 22-Sep-06 15-Nov-06 02-Oct-06 A 08-Jan-07 A
PRO1640 PR/PO of Miscellaneous Sections (angles, chanels, SHS etc.) 0 100% 29-Sep-06 24-Nov-06 04-Oct-06 A 29-Dec-06 A
PRO1630 PR/PO of Ancillary Steel (grating, stair tread, etc.) 0 100% 07-Oct-06 30-Nov-06 07-Oct-06 A 12-Jan-07 A
PRO1650 PR/PO of Fire/Blast Walls 0 100% 16-Oct-06 11-Dec-06 16-Oct-06 A 09-Mar-07 A
PRO1670 PR/PO of All Remaining Structural Mat'l 0 100% 23-Oct-06 19-Dec-06 30-Oct-06 A 02-Mar-07 A
PRO1660 PR/PO of Passive Fire Projection (PFP) 0 100% 19-Oct-06 16-Dec-06 13-Nov-06 A 20-Apr-07 A
Piping 0 07-Sep-06 27-Dec-06 07-Sep-06 A 02-Mar-07 A 0
PRO1690 PR/PO of Carbon Steel (CS) Pipes & Fitting 0 100% 07-Sep-06 04-Nov-06 07-Sep-06 A 23-Oct-06 A
PRO1700 PR/PO of Stainless Steel (SS) Pipes & Fitting 0 100% 11-Sep-06 11-Nov-06 11-Sep-06 A 27-Dec-06 A
PRO1710 PR/PO of Duplex Stainless Steel (DSS) Pipes & Fitting 0 100% 13-Sep-06 22-Nov-06 13-Sep-06 A 19-Dec-06 A
PRO1730 PR/PO of Valves 0 100% 16-Sep-06 05-Dec-06 16-Sep-06 A 02-Feb-07 A
PRO1720 PR/PO of GRE Pipes & Fitting 0 100% 22-Sep-06 11-Nov-06 22-Sep-06 A 28-Nov-06 A
PRO1750 PR/PO of Pipe Bends & Barred Tees 0 100% 03-Oct-06 28-Nov-06 02-Oct-06 A 08-Dec-06 A
PRO1740 PR/PO of Piping Specialty Items 0 100% 03-Oct-06 23-Nov-06 03-Oct-06 A 05-Dec-06 A
PRO1760 PR/PO of Associated Fittings & Acc. for Launcher 0 100% 18-Oct-06 18-Dec-06 10-Oct-06 A 09-Feb-07 A
PRO1770 PR/PO of All Remaining Piping Mat'l 0 100% 27-Oct-06 27-Dec-06 13-Nov-06 A 02-Mar-07 A
Mechanical 0 07-Aug-06 16-Nov-06 07-Aug-06 A 31-Jan-07 A 0
PRO1910 PR/PO of Padestal Crane 0 100% 07-Aug-06 02-Oct-06 07-Aug-06 A 16-Oct-06 A
PRO1780 PR/PO of Flush Water Tank 0 100% 12-Aug-06 30-Oct-06 12-Aug-06 A 08-Nov-06 A
PRO1790 PR/PO of Fresh Water Tank 0 100% 12-Aug-06 30-Oct-06 12-Aug-06 A 08-Nov-06 A
PRO1800 PR/PO of Closed Drain Vessel 0 100% 15-Aug-06 13-Oct-06 15-Aug-06 A 21-Nov-06 A
PRO1810 PR/PO of Condensate Pod 0 100% 15-Aug-06 11-Oct-06 15-Aug-06 A 21-Nov-06 A
PRO1880 PR/PO of HP Vent Tip 0 100% 17-Aug-06 03-Nov-06 17-Aug-06 A 23-Jan-07 A
PRO1890 PR/PO of CO2 Vent Snuffing System 0 100% 17-Aug-06 03-Nov-06 17-Aug-06 A 23-Jan-07 A
PRO1930 PR/PO of Corrosion Inhibitor Injection Package 0 100% 18-Aug-06 17-Oct-06 18-Aug-06 A 18-Oct-06 A
PRO1900 PR/PO of Manual Operated Trolley Hoists 0 100% 21-Aug-06 07-Oct-06 21-Aug-06 A 06-Nov-06 A
PRO1920 PR/PO of Swing Jib Cranes with Manual Operated Hoist 0 100% 21-Aug-06 17-Oct-06 21-Aug-06 A 18-Oct-06 A
PRO1840 PR/PO of Flush Water Pump 0 100% 22-Aug-06 20-Oct-06 22-Aug-06 A 31-Oct-06 A
PRO1850 PR/PO of Fresh Water Pump 0 100% 22-Aug-06 20-Oct-06 22-Aug-06 A 31-Oct-06 A
PRO1830 PR/PO of Open Drain Caisson Pump 0 100% 23-Aug-06 19-Oct-06 23-Aug-06 A 30-Oct-06 A
PRO1860 PR/PO of Closed Drain Transfer Pump 0 100% 23-Aug-06 19-Oct-06 23-Aug-06 A 30-Oct-06 A
PRO1820 PR/PO of Diesel Transfer Pump 0 100% 24-Aug-06 28-Oct-06 24-Aug-06 A 01-Nov-06 A
PRO1870 PR/PO of All Remaining Pumps 0 100% 26-Aug-06 06-Nov-06 26-Aug-06 A 05-Dec-06 A
PRO1940 PR/PO of All Remaining Mechanical Items 0 100% 29-Aug-06 16-Nov-06 29-Aug-06 A 31-Jan-07 A
Electrical 0 12-Aug-06 09-Jan-07 12-Aug-06 A 24-Apr-07 A 0
PRO1960 PR/PO of Power Transformer 0 100% 12-Aug-06 30-Oct-06 12-Aug-06 A 06-Nov-06 A
PRO1970 PR/PO of 6.6KV Ring Main Unit 0 100% 18-Aug-06 14-Nov-06 18-Aug-06 A 27-Dec-06 A
PRO1980 PR/PO of LV Distribution Board 0 100% 18-Aug-06 14-Nov-06 18-Aug-06 A 05-Dec-06 A
PRO2010 PR/PO of Electrical / Control Cables, Fitting & MCT's 0 100% 29-Aug-06 08-Nov-06 29-Aug-06 A 06-Mar-07 A
PRO2000 PR/PO of Cable Trays, Ladder & Accessories 0 100% 11-Sep-06 14-Nov-06 11-Sep-06 A 06-Dec-06 A
PRO2020 PR/PO of Junction Boxes and Control Panels 0 100% 22-Sep-06 15-Dec-06 22-Sep-06 A 09-Feb-07 A
PRO2040 PR/PO of Light Fitting, Photocells Mounting and Accessories 0 100% 29-Sep-06 21-Dec-06 29-Sep-06 A 08-Mar-07 A
PRO2030 PR/PO of Remote Control Units and Safety Switches 0 100% 14-Oct-06 30-Dec-06 14-Oct-06 A 24-Apr-07 A
PRO1990 PR/PO of Powered Navigational Aids System 0 100% 18-Oct-06 29-Dec-06 18-Oct-06 A 08-Dec-06 A
PRO2050 PR/PO of Earthing Accessories 0 100% 02-Nov-06 15-Dec-06 19-Oct-06 A 09-Mar-07 A
PRO2060 PR/PO of All Other Electrical Items 0 100% 10-Nov-06 09-Jan-07 22-Nov-06 A 09-Mar-07 A
Instrument 0 21-Aug-06 19-Dec-06 21-Aug-06 A 20-Apr-07 A 0
PRO2260 PR/PO of Control, Ball and Operated Valves 0 100% 21-Aug-06 07-Nov-06 21-Aug-06 A 04-Jan-07 A
PRO2270 PR/PO of Ultra Sonic Flare Gas Meter 0 100% 23-Aug-06 02-Nov-06 23-Aug-06 A 07-Feb-07 A
Contract No : 591397 Page 4 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
PRO2070 PR/PO of Wellhead Control Panel 0 100% 24-Aug-06 11-Nov-06 24-Aug-06 A 06-Feb-07 A
PRO2120 PR/PO of Ultrasonic Flowmeters 0 100% 26-Aug-06 28-Oct-06 26-Aug-06 A 01-Dec-06 A
PRO2160 PR/PO of Choke Valves 0 100% 29-Aug-06 08-Nov-06 29-Aug-06 A 21-Nov-06 A
PRO2090 PR/PO of GPA/PAPA 0 100% 07-Sep-06 11-Nov-06 07-Sep-06 A 03-Jan-07 A
PRO2080 PR/PO of Sand Monitoring System 0 100% 13-Sep-06 17-Nov-06 13-Sep-06 A 27-Dec-06 A
PRO2150 PR/PO of Pressure Gauges 0 100% 20-Sep-06 14-Nov-06 20-Sep-06 A 10-Apr-07 A
PRO2170 PR/PO of Pig Signallers 0 100% 28-Oct-06 04-Dec-06 11-Oct-06 A 20-Apr-07 A
PRO2130 PR/PO of Level Gauges (Reflex Type) 0 100% 14-Oct-06 29-Nov-06 14-Oct-06 A 04-Apr-07 A
PRO2140 PR/PO of Level Gauges (Using Pressure Gauge) 0 100% 14-Oct-06 29-Nov-06 14-Oct-06 A 04-Apr-07 A
PRO2100 PR/PO of Restriction Orifice Plates 0 100% 31-Oct-06 12-Dec-06 16-Oct-06 A 06-Apr-07 A
PRO2110 PR/PO of Orifice Plates 0 100% 31-Oct-06 12-Dec-06 16-Oct-06 A 09-Feb-07 A
PRO2180 PR/PO of IR Flame Detector 0 100% 02-Nov-06 12-Dec-06 16-Oct-06 A 10-Jan-07 A
PRO2190 PR/PO of IR Point Gas Detector 0 100% 02-Nov-06 08-Dec-06 16-Oct-06 A 09-Feb-07 A
PRO2200 PR/PO of IR Open Path Gas Detector 0 100% 02-Nov-06 08-Dec-06 16-Oct-06 A 19-Jan-07 A
PRO2210 PR/PO of Smoke Detector 0 100% 02-Nov-06 08-Dec-06 16-Oct-06 A 22-Dec-06 A
PRO2220 PR/PO of Hydrogen Gas Detector 0 100% 02-Nov-06 08-Dec-06 16-Oct-06 A 22-Dec-06 A
PRO2240 PR/PO of Acoustic Leak Detector 0 100% 02-Nov-06 11-Dec-06 16-Oct-06 A 22-Dec-06 A
PRO2250 PR/PO of Heat Detector 0 100% 02-Nov-06 08-Dec-06 16-Oct-06 A 22-Dec-06 A
PRO2230 PR/PO of ESD Break Glass Station 0 100% 08-Nov-06 11-Dec-06 18-Oct-06 A 22-Dec-06 A
PRO2300 PR/PO of Instrument Cable, Junction Boxes & MCT's 0 100% 19-Sep-06 14-Nov-06 30-Oct-06 A 20-Apr-07 A
PRO2280 PR/PO of Field Instrument & Mounting Stands & Supports etc. 0 100% 16-Sep-06 08-Nov-06 13-Nov-06 A 02-Mar-07 A
PRO2290 PR/PO of Cable Tray & Ladders 0 100% 22-Sep-06 18-Nov-06 13-Nov-06 A 15-Jan-07 A
PRO2310 PR/PO of Instrument Tubing, Fittings & Valves 0 100% 28-Sep-06 22-Nov-06 13-Nov-06 A 12-Feb-07 A
PRO2320 PR/PO of All Remaining Instrumentation Items 0 100% 10-Nov-06 19-Dec-06 22-Nov-06 A 16-Mar-07 A
Architectural 0 24-Nov-06 06-Jan-07 03-Oct-06 A 23-Jan-07 A 0
PRO1680 PR/PO of Architectural Mat'l (floor/wall/ceiling panels, doors ... 0 100% 24-Nov-06 06-Jan-07 03-Oct-06 A 23-Jan-07 A
HVAC 0 11-Dec-06 15-Jan-07 20-Dec-06 A 26-Feb-07 A 0
PRO1950 PR/PO of HVAC System Package 0 100% 11-Dec-06 15-Jan-07 20-Dec-06 A 26-Feb-07 A
Safety 0 29-Nov-06 29-Jan-07 10-Oct-06 A 11-May-07 A 0
PRO2340 PR/PO of Safety Signs 0 100% 29-Nov-06 04-Jan-07 10-Oct-06 A 11-May-07 A
PRO2330 PR/PO of Safety Equipment and Fire Protection Equipment 0 100% 02-Dec-06 29-Jan-07 12-Oct-06 A 02-Feb-07 A
Others Materials 0 02-Dec-06 08-Feb-07 25-Dec-06 A 25-May-07 A 0
PRO2350 PR/PO of Any Other Materials not included above 0 100% 02-Dec-06 08-Feb-07 25-Dec-06 A 25-May-07 A
Purchase Order to D
Delivery 0 03-Oct-06 23-Jul-07 17-Oct-06 A 05-Oct-07 A 0
Structural 0 30-Oct-06 04-Apr-07 09-Nov-06 A 10-May-07 A 0
PRO2360 PO to Del of Structural Tubulars 0 100% 30-Oct-06 29-Nov-06 09-Nov-06 A 01-Dec-06 A
PRO2370 PO to Del of Structural Beams 0 100% 07-Nov-06 12-Dec-06 22-Nov-06 A 16-Jan-07 A
PRO2400 PO to Del of Miscellaneous Sections (angles, chanels, SHS etc.) 0 100% 24-Nov-06 10-Jan-07 18-Dec-06 A 12-Jan-07 A
PRO2390 PO to Del of Ancillary Steel (grating, stair tread, etc.) 0 100% 30-Nov-06 27-Jan-07 20-Dec-06 A 26-Jan-07 A
PRO2380 PO to Del of Structural Plates 0 100% 15-Nov-06 30-Dec-06 02-Jan-07 A 02-Feb-07 A
PRO2410 PO to Del of Fire/Blast Walls 0 100% 11-Dec-06 13-Mar-07 07-Feb-07 A 10-May-07 A
PRO2420 PO to Del of Passive Fire Projection (PFP) 0 100% 16-Dec-06 04-Apr-07 21-Feb-07 A 28-Apr-07 A
PRO2430 PO to Del of All Remaining Structural Mat'l 0 100% 19-Dec-06 14-Feb-07 02-Mar-07 A 22-Mar-07 A
Piping 0 06-Nov-06 30-May-07 24-Oct-06 A 10-Sep-07 A 0
PRO2450 PO to Del of Carbon Steel (CS) Pipes & Fitting 0 100% 06-Nov-06 15-Jan-07 24-Oct-06 A 04-Jan-07 A
PRO2480 PO to Del of GRE Pipes & Fitting 0 100% 11-Nov-06 28-Feb-07 29-Nov-06 A 03-Apr-07 A
PRO2500 PO to Del of Piping Specialty Items 0 100% 11-Dec-06 23-Mar-07 06-Dec-06 A 02-Apr-07 A
PRO2510 PO to Del of Pipe Bends & Barred Tees 0 100% 19-Dec-06 30-May-07 09-Dec-06 A 25-Apr-07 A
PRO2470 PO to Del of Duplex Stainless Steel (DSS) Pipes & Fitting 0 100% 22-Nov-06 26-May-07 20-Dec-06 A 10-Sep-07 A
PRO2460 PO to Del of Stainless Steel (SS) Pipes & Fitting 0 100% 11-Nov-06 13-Feb-07 28-Dec-06 A 06-Feb-07 A
PRO2490 PO to Del of Valves 0 100% 18-Dec-06 04-May-07 02-Feb-07 A 27-Apr-07 A
PRO2520 PO to Del of Associated Fittings & Acc. for Launcher 0 100% 05-Jan-07 27-Apr-07 10-Feb-07 A 04-May-07 A
PRO2530 PO to Del of All Remaining Piping Mat'l 0 100% 27-Dec-06 12-Apr-07 02-Mar-07 A 06-Jul-07 A
Contract No : 591397 Page 5 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
Mechanical 0 03-Oct-06 23-Jul-07 17-Oct-06 A 06-Aug-07 A 0
PRO2670 PO to Del of Padestal Crane 0 100% 03-Oct-06 12-Jul-07 17-Oct-06 A 07-Jul-07 A
PRO2680 PO to Del of Swing Jib Cranes with Manual Operated Hoist 0 100% 17-Oct-06 30-Apr-07 19-Oct-06 A 16-May-07 A
PRO2690 PO to Del of Corrosion Inhibitor Injection Package 0 100% 17-Oct-06 14-Jun-07 19-Oct-06 A 30-Apr-07 A
PRO2590 PO to Del of Open Drain Caisson Pump 0 100% 19-Oct-06 30-May-07 31-Oct-06 A 31-May-07 A
PRO2600 PO to Del of Flush Water Pump 0 100% 20-Oct-06 21-Jun-07 01-Nov-06 A 18-Jun-07 A
PRO2610 PO to Del of Fresh Water Pump 0 100% 20-Oct-06 21-Jun-07 01-Nov-06 A 18-Jun-07 A
PRO2620 PO to Del of Closed Drain Transfer Pump 0 100% 19-Oct-06 09-Jun-07 01-Nov-06 A 02-Apr-07 A
PRO2580 PO to Del of Diesel Transfer Pump 0 100% 28-Oct-06 26-Jun-07 02-Nov-06 A 18-Jun-07 A
PRO2660 PO to Del of Manual Operated Trolley Hoists 0 100% 07-Oct-06 22-May-07 07-Nov-06 A 05-May-07 A
PRO2540 PO to Del of Flush Water Tank 0 100% 30-Oct-06 17-May-07 09-Nov-06 A 21-Apr-07 A
PRO2550 PO to Del of Fresh Water Tank 0 100% 30-Oct-06 28-Apr-07 09-Nov-06 A 14-May-07 A
PRO2560 PO to Del of Closed Drain Vessel 0 100% 13-Oct-06 04-Jul-07 22-Nov-06 A 23-Apr-07 A
PRO2570 PO to Del of Condensate Pod 0 100% 11-Oct-06 04-Jun-07 22-Nov-06 A 22-Apr-07 A
PRO2630 PO to Del of All Remaining Pumps 0 100% 07-Nov-06 13-Jul-07 06-Dec-06 A 06-Jul-07 A
PRO2640 PO to Del of HP Vent Tip 0 100% 03-Nov-06 01-Jul-07 24-Jan-07 A 10-Jul-07 A
PRO2650 PO to Del of CO2 Vent Snuffing System 0 100% 03-Nov-06 01-Jul-07 24-Jan-07 A 10-Jul-07 A
PRO2700 PO to Del of All Remaining Mechanical Items 0 100% 16-Nov-06 23-Jul-07 02-Feb-07 A 06-Aug-07 A
Electrical 0 30-Oct-06 10-Jul-07 07-Nov-06 A 06-Jul-07 A 0
PRO2720 PO to Del of Power Transformer 0 100% 30-Oct-06 10-Jul-07 07-Nov-06 A 28-Apr-07 A
PRO2740 PO to Del of LV Distribution Board 0 100% 14-Nov-06 04-Apr-07 06-Dec-06 A 14-Apr-07 A
PRO2760 PO to Del of Cable Trays, Ladder & Accessories 0 100% 14-Nov-06 15-Feb-07 07-Dec-06 A 06-Feb-07 A
PRO2750 PO to Del of Powered Navigational Aids System 0 100% 29-Dec-06 18-May-07 09-Dec-06 A 14-Apr-07 A
PRO2730 PO to Del of 6.6KV Ring Main Unit 0 100% 14-Nov-06 14-Jun-07 28-Dec-06 A 11-Jun-07 A
PRO2780 PO to Del of Junction Boxes and Control Panels 0 100% 15-Dec-06 07-Apr-07 10-Feb-07 A 29-Jun-07 A
PRO2810 PO to Del of Earthing Accessories 0 100% 15-Dec-06 13-Mar-07 23-Feb-07 A 05-Mar-07 A
PRO2770 PO to Del of Electrical / Control Cables, Fitting & MCT's 0 100% 09-Nov-06 28-Mar-07 07-Mar-07 A 02-Apr-07 A
PRO2800 PO to Del of Light Fitting, Photocells Mounting and Accessories 0 100% 21-Dec-06 26-Mar-07 09-Mar-07 A 08-Jun-07 A
PRO2820 PO to Del of All Other Electrical Items 0 100% 10-Jan-07 22-May-07 09-Mar-07 A 06-Jul-07 A
PRO2790 PO to Del of Remote Control Units and Safety Switches 0 100% 30-Dec-06 25-Apr-07 24-Apr-07 A 14-May-07 A
Instrument 0 28-Oct-06 29-Jun-07 22-Nov-06 A 05-Oct-07 A 0
PRO2920 PO to Del of Choke Valves 0 100% 09-Nov-06 29-Jun-07 22-Nov-06 A 16-Jun-07 A
PRO2880 PO to Del of Ultrasonic Flowmeters 0 100% 28-Oct-06 27-Feb-07 01-Dec-06 A 28-Feb-07 A
PRO2970 PO to Del of Smoke Detector 0 100% 09-Dec-06 26-Apr-07 23-Dec-06 A 17-Mar-07 A
PRO2980 PO to Del of Hydrogen Gas Detector 0 100% 09-Dec-06 26-Apr-07 23-Dec-06 A 08-Feb-07 A
PRO2990 PO to Del of ESD Break Glass Station 0 100% 11-Dec-06 10-May-07 23-Dec-06 A 14-Apr-07 A
PRO3000 PO to Del of Acoustic Leak Detector 0 100% 11-Dec-06 27-Apr-07 23-Dec-06 A 27-Apr-07 A
PRO3010 PO to Del of Heat Detector 0 100% 09-Dec-06 26-Apr-07 23-Dec-06 A 17-Mar-07 A
PRO2840 PO to Del of Sand Monitoring System 0 100% 17-Nov-06 20-Apr-07 28-Dec-06 A 28-May-07 A
PRO2850 PO to Del of GPA/PAPA 0 100% 11-Nov-06 21-Mar-07 04-Jan-07 A 26-Mar-07 A
PRO3020 PO to Del of Control, Ball and Operated Valves 0 100% 08-Nov-06 04-May-07 05-Jan-07 A 15-Jun-07 A
PRO2940 PO to Del of IR Flame Detector 0 100% 12-Dec-06 28-Apr-07 11-Jan-07 A 05-May-07 A
PRO3050 PO to Del of Cable Tray & Ladders 0 100% 18-Nov-06 07-Feb-07 15-Jan-07 A 08-Feb-07 A
PRO2960 PO to Del of IR Open Path Gas Detector 0 100% 09-Dec-06 26-Apr-07 20-Jan-07 A 11-Jun-07 A
PRO2830 PO to Del of Wellhead Control Panel 0 100% 11-Nov-06 03-Apr-07 07-Feb-07 A 10-Jul-07 A
PRO3030 PO to Del of Ultra Sonic Flare Gas Meter 0 100% 02-Nov-06 26-Apr-07 08-Feb-07 A 18-Sep-07 A
PRO2870 PO to Del of Orifice Plates 0 100% 12-Dec-06 23-May-07 10-Feb-07 A 21-Apr-07 A
PRO2950 PO to Del of IR Point Gas Detector 0 100% 09-Dec-06 26-Apr-07 10-Feb-07 A 04-Jun-07 A
PRO3070 PO to Del of Instrument Tubing, Fittings & Valves 0 100% 22-Nov-06 20-Mar-07 13-Feb-07 A 01-Mar-07 A
PRO3060 PO to Del of Instrument Cable, Junction Boxes & MCT's 0 100% 14-Nov-06 16-Feb-07 17-Feb-07 A 06-Jul-07 A
PRO3040 PO to Del of Field Instrument & Mounting Stands & Supports ... 0 100% 09-Nov-06 26-Mar-07 02-Mar-07 A 02-Apr-07 A
PRO2910 PO to Del of Pressure Gauges 0 100% 14-Nov-06 06-Mar-07 28-May-07 A 04-Sep-07 A
PRO2860 PO to Del of Restriction Orifice Plates 0 100% 12-Dec-06 17-May-07 27-Jul-07 A 23-Aug-07 A
Contract No : 591397 Page 6 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
PRO2900 PO to Del of Level Gauges (Using Pressure Gauge) 0 100% 29-Nov-06 09-Apr-07 30-Jul-07 A 28-Aug-07 A
PRO2890 PO to Del of Level Gauges (Reflex Type) 0 100% 29-Nov-06 09-Apr-07 07-Aug-07 A 27-Aug-07 A
PRO3080 PO to Del of All Remaining Instrumentation Items 0 100% 19-Dec-06 13-Jun-07 11-Aug-07 A 24-Aug-07 A
PRO2930 PO to Del of Pig Signallers 0 100% 04-Dec-06 14-Mar-07 01-Oct-07 A 05-Oct-07 A
Architectural 0 08-Jan-07 12-Mar-07 26-Jan-07 A 12-Jul-07 A 0
PRO2440 PO to Del of Architectural Mat'l (floor/wall/ceiling panels, do... 0 100% 08-Jan-07 12-Mar-07 26-Jan-07 A 12-Jul-07 A
HVAC 0 15-Jan-07 12-Mar-07 26-Feb-07 A 30-Mar-07 A 0
PRO2710 PO to Del of HVAC System Package 0 100% 15-Jan-07 12-Mar-07 26-Feb-07 A 30-Mar-07 A
Safety 0 04-Jan-07 09-Jul-07 02-Feb-07 A 10-Aug-07 A 0
PRO3090 PO to Del of Safety Equipment and Fire Protection Equipment 0 100% 29-Jan-07 09-Jul-07 02-Feb-07 A 30-Jul-07 A
PRO3100 PO to Del of Safety Signs 0 100% 04-Jan-07 21-May-07 30-Jul-07 A 10-Aug-07 A
Others Materials 0 08-Feb-07 16-Jul-07 06-Aug-07 A 24-Aug-07 A 0
PRO3110 PO to Del of Any Other Materials not included above 0 100% 08-Feb-07 16-Jul-07 06-Aug-07 A 24-Aug-07 A
Materials Receiving Inspection 0 29-Nov-06 08-Aug-07 01-Dec-06 A 05-Oct-07 A 0
Structural 0 29-Nov-06 20-Apr-07 01-Dec-06 A 10-May-07 A 0
PRO3120 Receive/Accept of Structural Tubulars 0 100% 29-Nov-06 14-Dec-06 01-Dec-06 A 12-Jan-07 A
PRO3130 Receive/Accept of Structural Beams 0 100% 12-Dec-06 03-Jan-07 08-Jan-07 A 26-Jan-07 A
PRO3140 Receive/Accept of Structural Plates 0 100% 30-Dec-06 20-Jan-07 09-Jan-07 A 23-Feb-07 A
PRO3160 Receive/Accept of Miscellaneous Sections (angles, chanels,... 0 100% 11-Jan-07 31-Jan-07 10-Jan-07 A 30-Jan-07 A
PRO3150 Receive/Accept of Ancillary Steel (grating, stair tread, etc.) 0 100% 27-Jan-07 15-Feb-07 17-Jan-07 A 02-Mar-07 A
PRO3190 Receive/Accept of All Remaining Structural Mat'l 0 100% 14-Feb-07 09-Mar-07 12-Feb-07 A 23-Mar-07 A
PRO3170 Receive/Accept of Fire/Blast Walls 0 100% 13-Mar-07 03-Apr-07 01-Mar-07 A 10-May-07 A
PRO3180 Receive/Accept of Passive Fire Projection (PFP) 0 100% 04-Apr-07 20-Apr-07 28-Apr-07 A 04-May-07 A
Piping 0 15-Jan-07 18-Jun-07 05-Jan-07 A 28-Sep-07 A 0
PRO3210 Receive/Accept of Carbon Steel (CS) Pipes & Fitting 0 100% 15-Jan-07 14-Feb-07 05-Jan-07 A 28-Feb-07 A
PRO3220 Receive/Accept of Stainless Steel (SS) Pipes & Fitting 0 100% 13-Feb-07 10-Mar-07 06-Feb-07 A 23-Mar-07 A
PRO3260 Receive/Accept of Piping Specialty Items 0 100% 23-Mar-07 14-Apr-07 26-Mar-07 A 09-Apr-07 A
PRO3240 Receive/Accept of GRE Pipes & Fitting 0 100% 28-Feb-07 26-Mar-07 04-Apr-07 A 13-Apr-07 A
PRO3280 Receive/Accept of Associated Fittings & Acc. for Launcher 0 100% 27-Apr-07 17-May-07 09-Apr-07 A 11-May-07 A
PRO3250 Receive/Accept of Valves 0 100% 04-May-07 31-May-07 18-Apr-07 A 28-Sep-07 A
PRO3270 Receive/Accept of Pipe Bends & Barred Tees 0 100% 30-May-07 18-Jun-07 25-Apr-07 A 04-May-07 A
PRO3230 Receive/Accept of Duplex Stainless Steel (DSS) Pipes & Fitting 0 100% 17-May-07 07-Jun-07 27-Apr-07 A 03-Aug-07 A
PRO3290 Receive/Accept of All Remaining Piping Mat'l 0 100% 12-Apr-07 09-May-07 01-May-07 A 29-Jun-07 A
Mechanical 0 28-Apr-07 08-Aug-07 02-Apr-07 A 24-Aug-07 A 0
PRO3380 Receive/Accept of Closed Drain Transfer Pump 0 100% 09-Jun-07 25-Jun-07 02-Apr-07 A 13-Apr-07 A
PRO3300 Receive/Accept of Flush Water Tank 0 100% 17-May-07 01-Jun-07 21-Apr-07 A 27-Apr-07 A
PRO3330 Receive/Accept of Condensate Pod 0 100% 04-Jun-07 16-Jun-07 22-Apr-07 A 27-Apr-07 A
PRO3320 Receive/Accept of Closed Drain Vessel 0 100% 04-Jul-07 17-Jul-07 23-Apr-07 A 27-Apr-07 A
PRO3450 Receive/Accept of Corrosion Inhibitor Injection Package 0 100% 14-Jun-07 28-Jun-07 30-Apr-07 A 04-May-07 A
PRO3420 Receive/Accept of Manual Operated Trolley Hoists 0 100% 23-May-07 09-Jun-07 05-May-07 A 11-May-07 A
PRO3310 Receive/Accept of Fresh Water Tank 0 100% 28-Apr-07 12-May-07 14-May-07 A 18-May-07 A
PRO3440 Receive/Accept of Swing Jib Cranes with Manual Operated... 0 100% 30-Apr-07 17-May-07 16-May-07 A 25-May-07 A
PRO3350 Receive/Accept of Open Drain Caisson Pump 0 100% 30-May-07 13-Jun-07 31-May-07 A 08-Jun-07 A
PRO3390 Receive/Accept of All Remaining Pumps 0 100% 13-Jul-07 28-Jul-07 04-Jun-07 A 15-Jun-07 A
PRO3340 Receive/Accept of Diesel Transfer Pump 0 100% 26-Jun-07 07-Jul-07 10-Jun-07 A 14-Jun-07 A
PRO3360 Receive/Accept of Flush Water Pump 0 100% 21-Jun-07 03-Jul-07 10-Jun-07 A 14-Jun-07 A
PRO3370 Receive/Accept of Fresh Water Pump 0 100% 21-Jun-07 03-Jul-07 10-Jun-07 A 14-Jun-07 A
PRO3430 Receive/Accept of Padestal Crane 0 100% 12-Jul-07 25-Jul-07 07-Jul-07 A 11-Jul-07 A
PRO3400 Receive/Accept of HP Vent Tip 0 100% 01-Jul-07 14-Jul-07 10-Jul-07 A 11-Jul-07 A
PRO3410 Receive/Accept of CO2 Vent Snuffing System 0 100% 01-Jul-07 13-Jul-07 10-Jul-07 A 11-Jul-07 A
PRO3460 Receive/Accept of All Remaining Mechanical Items 0 100% 23-Jul-07 08-Aug-07 27-Jul-07 A 24-Aug-07 A
Electrical 0 15-Feb-07 19-Jul-07 07-Feb-07 A 30-Jun-07 A 0
PRO3520 Receive/Accept of Cable Trays, Ladder & Accessories 0 100% 15-Feb-07 05-Mar-07 07-Feb-07 A 13-Apr-07 A
Contract No : 591397 Page 7 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
PRO3570 Receive/Accept of Earthing Accessories 0 100% 13-Mar-07 03-Apr-07 05-Mar-07 A 09-Mar-07 A
PRO3530 Receive/Accept of Electrical / Control Cables, Fitting & MCT's 0 100% 28-Mar-07 14-Apr-07 19-Mar-07 A 13-Apr-07 A
PRO3500 Receive/Accept of LV Distribution Board 0 100% 04-Apr-07 23-Apr-07 14-Apr-07 A 27-Apr-07 A
PRO3510 Receive/Accept of Powered Navigational Aids System 0 100% 18-May-07 01-Jun-07 14-Apr-07 A 20-Apr-07 A
PRO3480 Receive/Accept of Power Transformer 0 100% 10-Jul-07 19-Jul-07 28-Apr-07 A 04-May-07 A
PRO3560 Receive/Accept of Light Fitting, Photocells Mounting and Ac... 0 100% 30-Mar-07 26-Apr-07 09-May-07 A 22-Jun-07 A
PRO3550 Receive/Accept of Remote Control Units and Safety Switches 0 100% 25-Apr-07 14-May-07 14-May-07 A 15-Jun-07 A
PRO3540 Receive/Accept of Junction Boxes and Control Panels 0 100% 07-Apr-07 25-Apr-07 21-May-07 A 30-Jun-07 A
PRO3580 Receive/Accept of All Other Electrical Items 0 100% 23-May-07 13-Jun-07 08-Jun-07 A 29-Jun-07 A
PRO3490 Receive/Accept of 6.6KV Ring Main Unit 0 100% 14-Jun-07 01-Jul-07 12-Jun-07 A 29-Jun-07 A
Instrument 0 07-Feb-07 18-Jul-07 08-Feb-07 A 05-Oct-07 A 0
PRO3740 Receive/Accept of Hydrogen Gas Detector 0 100% 26-Apr-07 12-May-07 08-Feb-07 A 23-Feb-07 A
PRO3810 Receive/Accept of Cable Tray & Ladders 0 100% 07-Feb-07 28-Feb-07 09-Feb-07 A 02-Mar-07 A
PRO3820 Receive/Accept of Instrument Cable, Junction Boxes & MCT's 0 100% 16-Feb-07 14-Mar-07 22-Feb-07 A 20-Jul-07 A
PRO3640 Receive/Accept of Ultrasonic Flowmeters 0 100% 27-Feb-07 19-Mar-07 28-Feb-07 A 16-Mar-07 A
PRO3830 Receive/Accept of Instrument Tubing, Fittings & Valves 0 100% 20-Mar-07 11-Apr-07 01-Mar-07 A 09-Mar-07 A
PRO3730 Receive/Accept of Smoke Detector 0 100% 26-Apr-07 09-May-07 17-Mar-07 A 23-Mar-07 A
PRO3770 Receive/Accept of Heat Detector 0 100% 26-Apr-07 11-May-07 17-Mar-07 A 23-Mar-07 A
PRO3610 Receive/Accept of GPA/PAPA 0 100% 21-Mar-07 16-Apr-07 26-Mar-07 A 20-Apr-07 A
PRO3800 Receive/Accept of Field Instrument & Mounting Stands & Su... 0 100% 26-Mar-07 19-Apr-07 31-Mar-07 A 06-Apr-07 A
PRO3750 Receive/Accept of ESD Break Glass Station 0 100% 10-May-07 24-May-07 14-Apr-07 A 20-Apr-07 A
PRO3630 Receive/Accept of Orifice Plates 0 100% 24-May-07 09-Jun-07 21-Apr-07 A 27-Apr-07 A
PRO3760 Receive/Accept of Acoustic Leak Detector 0 100% 27-Apr-07 12-May-07 27-Apr-07 A 15-May-07 A
PRO3780 Receive/Accept of Control, Ball and Operated Valves 0 100% 04-May-07 24-May-07 01-May-07 A 29-Jun-07 A
PRO3700 Receive/Accept of IR Flame Detector 0 100% 28-Apr-07 12-May-07 05-May-07 A 11-May-07 A
PRO3600 Receive/Accept of Sand Monitoring System 0 100% 21-Apr-07 08-May-07 28-May-07 A 05-Jun-07 A
PRO3710 Receive/Accept of IR Point Gas Detector 0 100% 26-Apr-07 10-May-07 04-Jun-07 A 08-Jun-07 A
PRO3720 Receive/Accept of IR Open Path Gas Detector 0 100% 26-Apr-07 10-May-07 12-Jun-07 A 22-Jun-07 A
PRO3680 Receive/Accept of Choke Valves 0 100% 29-Jun-07 18-Jul-07 16-Jun-07 A 29-Jun-07 A
PRO3670 Receive/Accept of Pressure Gauges 0 100% 06-Mar-07 24-Mar-07 25-Jun-07 A 04-Sep-07 A
PRO3590 Receive/Accept of Wellhead Control Panel 0 100% 03-Apr-07 25-Apr-07 10-Jul-07 A 12-Jul-07 A
PRO3840 Receive/Accept of All Remaining Instrumentation Items 0 100% 13-Jun-07 03-Jul-07 03-Aug-07 A 24-Aug-07 A
PRO3650 Receive/Accept of Level Gauges (Reflex Type) 0 100% 09-Apr-07 27-Apr-07 17-Aug-07 A 27-Aug-07 A
PRO3660 Receive/Accept of Level Gauges (Using Pressure Gauge) 0 100% 09-Apr-07 26-Apr-07 17-Aug-07 A 27-Aug-07 A
PRO3620 Receive/Accept of Restriction Orifice Plates 0 100% 17-May-07 02-Jun-07 23-Aug-07 A 27-Aug-07 A
PRO3790 Receive/Accept of Ultra Sonic Flare Gas Meter 0 100% 26-Apr-07 11-May-07 17-Sep-07 A 18-Sep-07 A
PRO3690 Receive/Accept of Pig Signallers 0 100% 14-Mar-07 02-Apr-07 02-Oct-07 A 05-Oct-07 A
Architectural 0 12-Mar-07 07-Apr-07 26-Mar-07 A 13-Jul-07 A 0
PRO3200 Receive/Accept of Architectural Mat'l (floor/wall/ceiling pa... 0 100% 12-Mar-07 07-Apr-07 26-Mar-07 A 13-Jul-07 A
HVAC 0 12-Mar-07 02-Apr-07 05-Mar-07 A 13-Apr-07 A 0
PRO3470 Receive/Accept of HVAC System Package 0 100% 12-Mar-07 02-Apr-07 05-Mar-07 A 13-Apr-07 A
Safety 0 22-May-07 30-Jul-07 02-Apr-07 A 17-Aug-07 A 0
PRO3850 Receive/Accept of Safety Equipment and Fire Protection Eq... 0 100% 09-Jul-07 30-Jul-07 02-Apr-07 A 10-Aug-07 A
PRO3860 Receive/Accept of Safety Signs 0 100% 22-May-07 04-Jun-07 06-Aug-07 A 17-Aug-07 A
Others Materials 0 16-Jul-07 31-Jul-07 16-Jul-07 A 31-Jul-07 A 0
PRO3870 Receive/Accept of Any Other Materials not included above 0 100% 16-Jul-07 31-Jul-07 16-Jul-07 A 31-Jul-07 A
FABRICATION OF SCDR-A TOPSIDES 0 22-Sep-06 20-Aug-07 22-Sep-06 A 05-Oct-07 A 0

Structural 0 12-Oct-06 18-Jun-07 08-Nov-06 A 10-Sep-07 A 0


Fabrication 0 12-Oct-06 23-May-07 08-Nov-06 A 31-Aug-07 A 0
FAB1370 Fabricate and Arrange Temp. Supports 0 100% 12-Oct-06 06-Dec-06 08-Nov-06 A 22-Dec-06 A
FAB1380 Fab/Assem Cellar Deck (In-Situ) 0 100% 14-Nov-06 21-Feb-07 10-Nov-06 A 27-Mar-07 A
FAB1390 Fabricate Columns, Diagonals & Braces 0 100% 22-Dec-06 27-Feb-07 18-Dec-06 A 02-Mar-07 A
FAB1400 Fabricate Main Deck 0 100% 29-Dec-06 27-Mar-07 26-Dec-06 A 07-May-07 A
Contract No : 591397 Page 8 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
FAB1410 Fabricate Mezzanine Deck 0 100% 10-Jan-07 10-Mar-07 08-Jan-07 A 30-Mar-07 A
FAB1540 Fabricate Wellhead Access Platform 0 100% 18-Jan-07 06-Mar-07 18-Jan-07 A 15-Mar-07 A
FAB1440 Fabricate Framing for Switchgear, ILE Rooms, W.Shelter & W... 0 100% 24-Jan-07 15-Mar-07 27-Jan-07 A 18-May-07 A
FAB1430 Fabricate Handrails 0 100% 05-Feb-07 29-Mar-07 30-Jan-07 A 06-Apr-07 A
FAB1470 Fabricate Intermediate Platform 0 100% 31-Jan-07 12-Mar-07 06-Feb-07 A 30-Mar-07 A
FAB1420 Fabricate Stairways & Ladder 0 100% 15-Feb-07 07-Apr-07 21-Feb-07 A 25-May-07 A
FAB1450 Fabricate Gratings 0 100% 24-Feb-07 17-Apr-07 26-Feb-07 A 15-Jun-07 A
FAB1760 Fabricate Crane Padestal and Boom Rest 0 100% 02-Apr-07 02-May-07 05-Mar-07 A 15-May-07 A
FAB1460 Fabricate Vent Boom 0 100% 09-Mar-07 10-May-07 12-Mar-07 A 18-May-07 A
FAB1510 Fabricate Lifting Padeyes 0 100% 02-May-07 23-May-07 25-Jun-07 A 31-Aug-07 A
Installation 0 05-Feb-07 18-Jun-07 29-Jan-07 A 10-Sep-07 A 0
FAB1480 Erect Column and Braces (on Cellar Deck) 0 100% 05-Feb-07 27-Mar-07 29-Jan-07 A 11-May-07 A
FAB1740 Erect Wellhead Access Platform 0 100% 20-Mar-07 11-Apr-07 16-Mar-07 A 13-Apr-07 A
FAB1490 Erect Mezzanine Deck 0 100% 27-Mar-07 23-Apr-07 21-Mar-07 A 07-May-07 A
FAB1560 Install Framing for Switchgear, ILE Rooms, W.Shelter & Worksh... 0 100% 29-Mar-07 28-Apr-07 23-Mar-07 A 05-Jun-07 A
FAB1570 Erect Intermediate Platform 0 100% 26-Mar-07 14-Apr-07 12-Apr-07 A 04-May-07 A
FAB1530 Install Gratings 0 100% 05-Apr-07 02-May-07 21-Apr-07 A 10-Aug-07 A
FAB1520 Install Handrails 0 100% 10-Apr-07 09-May-07 23-Apr-07 A 03-Aug-07 A
FAB1550 Install Stairways & Ladder 0 100% 18-Apr-07 16-May-07 25-Apr-07 A 24-Aug-07 A
FAB1500 Erect Main Deck 0 100% 28-Apr-07 22-May-07 04-May-07 A 22-Jun-07 A
FAB1750 Install Crane Padestal and Boom Rest 0 100% 16-May-07 07-Jun-07 14-May-07 A 29-Jun-07 A
FAB1580 Install Vent Boom 0 100% 01-Jun-07 18-Jun-07 22-Jun-07 A 06-Jul-07 A
FAB1590 Install Lifting Padeyes 0 100% 24-May-07 14-Jun-07 17-Aug-07 A 10-Sep-07 A
Blasting/Painting 0 22-Sep-06 31-Jul-07 22-Sep-06 A 25-Sep-07 A 0
FAB1600 Auto Blast/Prime Structural Mat'l Type I and II 0 100% 22-Sep-06 17-Nov-06 22-Sep-06 A 28-Nov-06 A
FAB1620 Blast/Prime Structural Mat'l Type III 0 100% 14-Dec-06 14-Mar-07 12-Dec-06 A 16-Mar-07 A
FAB1630 Blast/Paint Pipe Supports 0 100% 31-Jan-07 27-Mar-07 01-Mar-07 A 25-May-07 A
FAB1640 Blast/Paint Mezzanine Deck 0 100% 10-Mar-07 27-Mar-07 04-Mar-07 A 20-Apr-07 A
FAB1660 Blast/Paint Electrical Supports 0 100% 15-Mar-07 02-Apr-07 05-Mar-07 A 20-Apr-07 A
FAB1680 Blast/Paint Instrument Supports 0 100% 15-Mar-07 02-Apr-07 05-Mar-07 A 20-Apr-07 A
FAB1710 Blast/Paint Pipe Spools 0 100% 28-Feb-07 11-Apr-07 05-Mar-07 A 27-Jul-07 A
FAB1780 Blast/Paint Wellhead Access Platform 0 100% 06-Mar-07 20-Mar-07 07-Mar-07 A 23-Mar-07 A
FAB1700 Blast/Paint Handrails 0 100% 02-Apr-07 19-Apr-07 10-Mar-07 A 15-Jun-07 A
FAB1790 Blast/Paint Intermediate Platform 0 100% 12-Mar-07 26-Mar-07 15-Mar-07 A 18-May-07 A
FAB1610 Blast/Paint Cellar Deck 0 100% 27-Mar-07 28-Apr-07 26-Mar-07 A 22-Jun-07 A
FAB1650 Blast/Paint Main Deck 0 100% 27-Mar-07 26-Apr-07 02-Apr-07 A 25-May-07 A
FAB1690 Blast/Paint Stairways & Ladder 0 100% 07-Apr-07 24-Apr-07 09-Apr-07 A 22-May-07 A
FAB1670 Blast/Paint Framing for Switchgear, ILE Rooms, W.Shelter & W... 0 100% 15-Mar-07 29-Mar-07 13-Apr-07 A 23-May-07 A
FAB2110 Touch-Up Painting 0 100% 11-Apr-07 31-Jul-07 14-Apr-07 A 25-Sep-07 A
FAB1770 Blast/Paint Crane Padestal and Boom Rest 0 100% 02-May-07 16-May-07 24-Apr-07 A 24-May-07 A
FAB2130 Apply Fire/Blast Walls 0 100% 10-May-07 01-Jun-07 14-May-07 A 01-Jun-07 A
FAB1720 Blast/Paint Vent Boom 0 100% 10-May-07 01-Jun-07 21-May-07 A 25-May-07 A
FAB2120 Apply Passive Fire Proofing 0 100% 01-Jun-07 15-Jun-07 18-Jun-07 A 06-Jul-07 A
FAB1730 Blast/Paint Lifting Padeyes 0 100% 14-Jun-07 27-Jun-07 24-Aug-07 A 08-Sep-07 A
Piping 0 13-Jan-07 15-Aug-07 12-Feb-07 A 21-Sep-07 A 0
Fabrication 0 13-Jan-07 31-Jul-07 12-Feb-07 A 10-Aug-07 A 0
FAB2100 Fabricate Pipe Supports 0 100% 13-Jan-07 28-Mar-07 12-Feb-07 A 30-Mar-07 A
FAB2630 Fabricate CS Pipe Spools 0 100% 14-Feb-07 25-Apr-07 26-Feb-07 A 15-May-07 A
FAB2840 Fabricate SS Pipe Spools 0 100% 10-Mar-07 03-May-07 07-Mar-07 A 18-May-07 A
FAB2860 Fabricate GRE Pipe Spools 0 100% 26-Mar-07 15-May-07 05-Apr-07 A 15-Jun-07 A
FAB2870 Fabricate Piping Specialty Items 0 100% 14-Apr-07 28-May-07 14-Apr-07 A 18-May-07 A
FAB2850 Fabricate DSS Pipe Spools 0 100% 07-Jun-07 31-Jul-07 23-Apr-07 A 10-Aug-07 A
Installation 0 24-Jan-07 15-Aug-07 01-Mar-07 A 21-Sep-07 A 0
Contract No : 591397 Page 9 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
FAB2820 Install Pipe Supports Below Cellar Deck 0 100% 24-Jan-07 12-Mar-07 01-Mar-07 A 25-May-07 A
FAB2990 Install Pipe Supports Below Main Deck 0 100% 27-Feb-07 25-Apr-07 06-Mar-07 A 08-Jun-07 A
FAB2830 Install CS Pipe Spools 0 100% 08-Mar-07 22-May-07 05-Apr-07 A 06-Jul-07 A
FAB2880 Install SS Pipe Spools 0 100% 06-Apr-07 14-May-07 06-Apr-07 A 06-Jul-07 A
FAB2900 Install GRE Pipe Spools 0 100% 16-Apr-07 12-Jun-07 23-Apr-07 A 27-Jul-07 A
FAB2910 Install Piping Specialty Items 0 100% 10-May-07 01-Jul-07 07-May-07 A 25-May-07 A
FAB2930 Install Associated Fitting & Acc for Launcher 0 100% 17-May-07 13-Jun-07 14-May-07 A 15-Jun-07 A
FAB2950 Hydrotest/Reinstatement 0 100% 09-Jun-07 15-Aug-07 16-May-07 A 21-Sep-07 A
FAB2920 Install Pipe Bends & Barred Tees 0 100% 17-Jul-07 06-Aug-07 21-May-07 A 25-May-07 A
FAB2940 Valve Installation 0 100% 21-May-07 13-Jul-07 21-May-07 A 14-Sep-07 A
FAB2890 Install DSS Pipe Spools 0 100% 30-Jun-07 11-Aug-07 25-Jun-07 A 15-Aug-07 A
FAB2960 Pipe Insulation 0 100% 09-Jul-07 06-Aug-07 10-Jul-07 A 07-Aug-07 A
Mechanical 0 15-Feb-07 20-Aug-07 22-Feb-07 A 04-Sep-07 A 0
FAB2415 Fabricate Equipment Supports 0 100% 15-Feb-07 06-Apr-07 22-Feb-07 A 27-Apr-07 A
FAB3070 Install Equipment Supports 0 100% 28-Mar-07 23-May-07 26-Mar-07 A 12-Jun-07 A
FAB3300 Install Wellhead Desander Skids 0 100% 05-Jun-07 28-Jun-07 26-Mar-07 A 13-Apr-07 A
FAB3110 Install Corrosion Inhibitor Injection Package 0 100% 28-Jun-07 13-Jul-07 04-May-07 A 11-May-07 A
FAB3190 Install Flush Water Tank 0 100% 01-Jun-07 18-Jun-07 14-May-07 A 25-May-07 A
FAB3210 Install Closed Drain Vessel 0 100% 17-Jul-07 07-Aug-07 16-May-07 A 08-Jun-07 A
FAB3180 Install Swing Jib Cranes with Manual Operated Hoist 0 100% 23-May-07 14-Jun-07 28-May-07 A 08-Jun-07 A
FAB3130 Install Condensate Pod 0 100% 16-Jun-07 03-Jul-07 29-May-07 A 08-Jun-07 A
FAB3200 Install Fresh Water Tank 0 100% 21-May-07 07-Jun-07 31-May-07 A 08-Jun-07 A
FAB3120 Install Diesel Transfer Pump 0 100% 07-Jul-07 31-Jul-07 11-Jun-07 A 02-Jul-07 A
FAB3140 Install Open Drain Caisson Pump 0 100% 13-Jun-07 01-Jul-07 15-Jun-07 A 29-Jun-07 A
FAB3090 Install Flush Water Pump 0 100% 03-Jul-07 28-Jul-07 18-Jun-07 A 22-Jun-07 A
FAB3100 Install Fresh Water Pump 0 100% 03-Jul-07 28-Jul-07 18-Jun-07 A 22-Jun-07 A
FAB3220 Install All Remaining Pumps 0 100% 28-Jul-07 11-Aug-07 18-Jun-07 A 29-Jun-07 A
FAB3160 Install Manual Operated Trolley Hoists 0 100% 09-Jun-07 25-Jun-07 25-Jun-07 A 06-Jul-07 A
FAB3150 Install Closed Drain Transfer Pump 0 100% 25-Jun-07 13-Jul-07 27-Jun-07 A 13-Jul-07 A
FAB3080 Install HP Vent Tip 0 100% 14-Jul-07 02-Aug-07 12-Jul-07 A 10-Aug-07 A
FAB3170 Install CO2 Vent Snuffing System 0 100% 13-Jul-07 02-Aug-07 12-Jul-07 A 13-Jul-07 A
FAB3230 Install Padestal Crane 0 100% 25-Jul-07 10-Aug-07 12-Jul-07 A 27-Jul-07 A
FAB3240 Install All Remaining Mechanical Items 0 100% 08-Aug-07 20-Aug-07 11-Aug-07 A 04-Sep-07 A
Electrical 0 28-Feb-07 03-Aug-07 02-Mar-07 A 07-Sep-07 A 0
FAB2970 Fabricate Electrical Supports 0 100% 28-Feb-07 06-Apr-07 02-Mar-07 A 11-May-07 A
FAB2980 Install Electrical Supports 0 100% 26-Mar-07 05-May-07 15-Mar-07 A 15-Jun-07 A
FAB3250 Install Cable Trays, Ladder & Accessories 0 100% 13-Apr-07 04-Jun-07 16-Apr-07 A 29-Jun-07 A
FAB3260 Install Electrical / Control Cables, Fitting & MCT's 0 100% 14-Apr-07 24-May-07 16-Apr-07 A 08-Jun-07 A
FAB3370 Install Earthing Accessories 0 100% 23-Apr-07 05-Jul-07 23-Apr-07 A 10-Aug-07 A
FAB3340 Install LV Distribution Board 0 100% 27-Apr-07 23-May-07 14-May-07 A 25-May-07 A
FAB3280 Cable Pulling 0 100% 02-May-07 15-Jun-07 21-May-07 A 27-Jul-07 A
FAB3400 Install AC Uninterruptible Power Supply (UPS) 0 100% 03-May-07 23-May-07 22-May-07 A 05-Jun-07 A
FAB3750 Install 400V Switchboard 0 100% 07-May-07 30-May-07 22-May-07 A 06-Jun-07 A
FAB3310 Install Power Transformer 0 100% 19-Jul-07 03-Aug-07 28-May-07 A 15-Jun-07 A
FAB3350 Install Powered Navigational Aids System 0 100% 27-Jun-07 17-Jul-07 02-Jun-07 A 08-Jun-07 A
FAB3360 Glanding & Termination 0 100% 22-May-07 28-Jun-07 04-Jun-07 A 07-Aug-07 A
FAB3270 Install Light Fitting, Photocells Mounting and Accessories 0 100% 14-May-07 20-Jun-07 11-Jun-07 A 29-Jun-07 A
FAB3320 Install 6.6KV Ring Main Unit 0 100% 04-Jul-07 25-Jul-07 29-Jun-07 A 13-Jul-07 A
FAB3290 Install Junction Boxes and Control Panels 0 100% 11-May-07 14-Jun-07 30-Jun-07 A 13-Jul-07 A
FAB3330 Install Remote Control Units and Safety Switches 0 100% 01-Jun-07 30-Jun-07 02-Jul-07 A 07-Sep-07 A
FAB3380 Install All Other Electrical Items 0 100% 13-Jun-07 20-Jul-07 02-Jul-07 A 13-Jul-07 A
Instrument 0 28-Feb-07 08-Aug-07 02-Mar-07 A 05-Oct-07 A 0
FAB3020 Fabricate Instrument Supports 0 100% 28-Feb-07 03-Apr-07 02-Mar-07 A 11-May-07 A
Contract No : 591397 Page 10 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
FAB3030 Install Instrument Supports 0 100% 27-Mar-07 02-May-07 09-Mar-07 A 22-Jun-07 A
FAB3390 Install Cable Tray & Ladders 0 100% 05-Apr-07 22-May-07 16-Apr-07 A 24-Aug-07 A
FAB3040 Instrument Calibration 0 100% 10-May-07 26-Jun-07 07-May-07 A 03-Aug-07 A
FAB3410 Install Instrument Cable, Junction Boxes & MCT's 0 100% 16-May-07 27-Jun-07 09-May-07 A 09-May-07 A
FAB3450 Install Ultrasonic Flowmeters 0 100% 18-May-07 05-Jun-07 14-May-07 A 25-May-07 A
FAB3550 Install Smoke Detector 0 100% 30-May-07 14-Jun-07 14-May-07 A 03-Aug-07 A
FAB3710 Install F&G System 0 100% 21-Apr-07 12-May-07 14-May-07 A 18-May-07 A
FAB3430 Install Field Instrument & Mounting Stands & Supports etc. 0 100% 08-May-07 28-May-07 15-May-07 A 10-Aug-07 A
FAB3050 Cable pulling 0 100% 04-May-07 16-Jun-07 22-May-07 A 19-Sep-07 A
FAB3520 Install IR Flame Detector 0 100% 26-May-07 12-Jun-07 28-May-07 A 10-Aug-07 A
FAB3500 Install Distributed Control System (DCS) and (AVA) 0 100% 21-Apr-07 22-May-07 28-May-07 A 15-Jun-07 A
FAB3480 Install GPA/PAPA 0 100% 24-May-07 23-Jun-07 31-May-07 A 03-Aug-07 A
FAB3560 Install Hydrogen Gas Detector 0 100% 30-May-07 12-Jun-07 31-May-07 A 08-Jun-07 A
FAB3600 Install IPS System 0 100% 21-Apr-07 14-May-07 02-Jun-07 A 15-Jun-07 A
FAB3530 Install IR Point Gas Detector 0 100% 26-May-07 13-Jun-07 04-Jun-07 A 10-Aug-07 A
FAB3510 Install ESD Break Glass Station 0 100% 12-Jun-07 25-Jun-07 04-Jun-07 A 22-Jun-07 A
FAB3570 Install Acoustic Leak Detector 0 100% 28-May-07 15-Jun-07 04-Jun-07 A 08-Jun-07 A
FAB3440 Install Sand Monitoring System 0 100% 05-Jun-07 25-Jun-07 06-Jun-07 A 29-Jun-07 A
FAB3580 Install Heat Detector 0 100% 31-May-07 15-Jun-07 11-Jun-07 A 22-Jun-07 A
FAB3540 Install IR Open Path Gas Detector 0 100% 26-May-07 12-Jun-07 18-Jun-07 A 03-Aug-07 A
FAB3730 Install Telecommunication Equipment 0 100% 07-May-07 07-Jun-07 18-Jun-07 A 03-Aug-07 A
FAB3490 Install Control, Ball and Operated Valves 0 100% 25-May-07 29-Jun-07 25-Jun-07 A 17-Aug-07 A
FAB3060 Glanding & Termination 0 100% 07-Jun-07 02-Jul-07 25-Jun-07 A 20-Sep-07 A
FAB3720 Install Wellhead Control System (WHCS) 0 100% 21-Apr-07 19-May-07 29-Jun-07 A 13-Jul-07 A
FAB3630 Install Instrument Tubing, Fittings & Valves 0 100% 10-May-07 05-Jun-07 02-Jul-07 A 10-Aug-07 A
FAB3420 Install Wellhead Control Panel 0 100% 25-Apr-07 24-May-07 13-Jul-07 A 20-Jul-07 A
FAB3660 Install Pressure Gauges 0 100% 19-May-07 06-Jun-07 16-Jul-07 A 27-Jul-07 A
FAB3740 Install Wet Gas Metering Skid (Operational Metering) 0 100% 19-Jun-07 09-Jul-07 16-Jul-07 A 10-Aug-07 A
FAB3650 Install Level Gauges (Using Pressure Gauge) 0 100% 18-May-07 04-Jun-07 27-Jul-07 A 06-Aug-07 A
FAB3620 Install Orifice Plates 0 100% 18-Jun-07 01-Jul-07 27-Jul-07 A 03-Aug-07 A
FAB3640 Install Level Gauges (Reflex Type) 0 100% 21-May-07 06-Jun-07 30-Jul-07 A 06-Aug-07 A
FAB3610 Install Restriction Orifice Plates 0 100% 11-Jun-07 25-Jun-07 03-Aug-07 A 10-Aug-07 A
FAB3670 Install All Remaining Instrumentation Items 0 100% 03-Jul-07 04-Aug-07 03-Aug-07 A 31-Aug-07 A
FAB3470 Install Choke Valves 0 100% 18-Jul-07 08-Aug-07 06-Aug-07 A 18-Aug-07 A
FAB3590 Install Ultra Sonic Flare Gas Meter 0 100% 22-May-07 12-Jun-07 19-Sep-07 A 22-Sep-07 A
FAB3460 Install Pig Signallers 0 100% 24-May-07 12-Jun-07 02-Oct-07 A 05-Oct-07 A
Architectural 0 24-Mar-07 26-Jul-07 15-Mar-07 A 24-Aug-07 A 0
FAB2760 Switchgear, Transformer & Battery Room 0 100% 24-Mar-07 07-May-07 15-Mar-07 A 03-Aug-07 A
FAB2770 Instrument Local Equipment Room 0 100% 21-Apr-07 04-Jul-07 21-Apr-07 A 10-Aug-07 A
FAB2780 Weather Shelter & Workshop 0 100% 21-Jun-07 26-Jul-07 21-May-07 A 24-Aug-07 A
HVAC 0 02-Apr-07 19-Jul-07 12-Mar-07 A 03-Aug-07 A 0
FAB2790 Switchgear, Transformer & Battery Room 0 100% 02-Apr-07 12-May-07 12-Mar-07 A 03-Aug-07 A
FAB2800 Instrument Local Equipment Room 0 100% 30-Apr-07 26-Jun-07 01-May-07 A 27-Jul-07 A
FAB2810 Weather Shelter & Workshop 0 100% 12-Jun-07 19-Jul-07 21-May-07 A 27-Jul-07 A
Safety 0 04-Jun-07 15-Aug-07 11-Jun-07 A 31-Aug-07 A 0
FAB3680 Install of Safety Equipment and Fire Protection Equipment 0 100% 30-Jul-07 15-Aug-07 11-Jun-07 A 24-Aug-07 A
FAB3690 Install of Safety Signs 0 100% 04-Jun-07 20-Jun-07 17-Aug-07 A 31-Aug-07 A
Others Materials 0 31-Jul-07 16-Aug-07 03-Aug-07 A 17-Aug-07 A 0
FAB3700 Install of Any Other Materials not included above 0 100% 31-Jul-07 16-Aug-07 03-Aug-07 A 17-Aug-07 A
ONSHORE PRE-COMMISSIONING
PRE-CO 0 21-May-07 28-Aug-07 23-May-07 A 28-Sep-07 A 0

COM1020 Precom UPS System 0 100% 08-Jun-07 06-Jul-07 23-May-07 A 20-Jul-07 A


COM1010 Precom Lighting and Small Power 0 100% 30-Jun-07 28-Jul-07 04-Jun-07 A 28-Sep-07 A
COM1130 Precom Earthing and Bonding System 0 100% 21-May-07 22-Jun-07 11-Jun-07 A 03-Aug-07 A
Contract No : 591397 Page 11 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
COM1160 Precom Navigation Aid System 0 100% 17-Jul-07 02-Aug-07 18-Jun-07 A 27-Jul-07 A
COM1040 Precom Materials Handling 0 100% 10-Aug-07 28-Aug-07 02-Jul-07 A 17-Aug-07 A
COM1060 Precom HVAC 0 100% 26-Jun-07 28-Jul-07 09-Jul-07 A 28-Sep-07 A
COM1190 Precom Gas and Condensate System 0 100% 28-Jul-07 28-Aug-07 09-Jul-07 A 28-Sep-07 A
COM1030 Precom Fresh Water System 0 100% 28-Jul-07 17-Aug-07 23-Jul-07 A 28-Sep-07 A
COM1050 Precom Electrical Power Generation & Distribution (EDG) 0 100% 25-Jul-07 18-Aug-07 23-Jul-07 A 28-Sep-07 A
COM1140 Precom Drain System 0 100% 23-Jul-07 16-Aug-07 23-Jul-07 A 17-Aug-07 A
COM1170 Precom Diesel Fuel System 0 100% 31-Jul-07 16-Aug-07 23-Jul-07 A 28-Sep-07 A
COM1210 Precom Flush Water System 0 100% 28-Jul-07 16-Aug-07 23-Jul-07 A 17-Aug-07 A
COM1070 Precom IPS System 0 100% 04-Jul-07 30-Jul-07 27-Jul-07 A 28-Sep-07 A
COM1090 Precom Fire and Gas System (F&G) 0 100% 30-Jun-07 01-Aug-07 27-Jul-07 A 28-Sep-07 A
COM1110 Precom GPA System 0 100% 23-Jun-07 17-Jul-07 27-Jul-07 A 28-Sep-07 A
COM1200 Precom Sand Monitoring System 0 100% 11-Jul-07 30-Jul-07 30-Jul-07 A 17-Aug-07 A
COM1080 Precom DCS and AVA System 0 100% 30-Jul-07 28-Aug-07 03-Aug-07 A 28-Sep-07 A
COM1120 Precom Telecomunication System 0 100% 16-Jun-07 14-Jul-07 03-Aug-07 A 24-Aug-07 A
COM1150 Precom Vent System 0 100% 02-Aug-07 18-Aug-07 03-Aug-07 A 28-Sep-07 A
COM1180 Precom Corrosion Inhibitor Injection System 0 100% 13-Jul-07 03-Aug-07 03-Aug-07 A 24-Aug-07 A
COM1100 Precom Wellhead Control System (WHCS) 0 100% 28-Jun-07 30-Jul-07 17-Aug-07 A 28-Sep-07 A
WEIGHING, LOADOUT
LOAD & SEAFASTENING 0 02-Jul-07 04-Sep-07 02-Jul-07 A 18-Sep-07 A 0

CVE1000 Civil Engineering and Infrastructure Works 0 100% 02-Jul-07 16-Aug-07 02-Jul-07 A 16-Aug-07 A
WGH1000 1st Weighing of Topsides 0 100% 02-Jul-07 06-Jul-07 04-Jul-07 A 06-Jul-07 A
WGH1010 Final Weighing of Topsides 0 100% 10-Aug-07 15-Aug-07 22-Aug-07 A 23-Aug-07 A
LOA1000 Loadout Topsides 0 100% 29-Aug-07 31-Aug-07 11-Sep-07 A 11-Sep-07 A
LOA1010 Seafastening Topsides 0 100% 31-Aug-07 04-Sep-07 11-Sep-07 A 18-Sep-07 A
E11K-A SHIPLOOSE
SHIPLOOS ITEMS 0 21-Aug-06 24-Jul-07 21-Aug-06 A 31-Aug-07 A 0

ENGINEERING 0 21-Aug-06 25-Jan-07 21-Aug-06 A 06-Apr-07 A 0


PRE1700 Prepare/Submit/Approve of MTO 0 100% 21-Aug-06 25-Nov-06 21-Aug-06 A 06-Apr-07 A
PRE1710 Prepare/Submit/Approve of Shop Drawings 0 100% 03-Oct-06 25-Jan-07 06-Nov-06 A 30-Mar-07 A
PROCUREMENT 0 05-Oct-06 05-Jun-07 03-Oct-06 A 24-Aug-07 A 0
Purchase Request to Purchase Order 0 05-Oct-06 22-Jan-07 03-Oct-06 A 27-Apr-07 A 0
PRO4450 PR/PO of Pipe Matl's 0 100% 05-Oct-06 30-Nov-06 03-Oct-06 A 23-Feb-07 A
PRO4470 PR/PO of Mechanical Matl's 0 100% 26-Oct-06 20-Dec-06 10-Oct-06 A 23-Feb-07 A
PRO4490 PR/PO of Electrical Matl's 0 100% 25-Nov-06 22-Jan-07 16-Oct-06 A 09-Mar-07 A
PRO4500 PR/PO of Instrument Matl's 0 100% 25-Nov-06 22-Jan-07 20-Oct-06 A 27-Apr-07 A
PRO4440 PR/PO of Structural Matl's 0 100% 08-Nov-06 03-Jan-07 25-Dec-06 A 06-Apr-07 A
Purchase Order to D
Delivery 0 30-Nov-06 24-May-07 08-Jan-07 A 24-May-07 A 0
PRO4510 PO to Del Pipe Matl's 0 100% 30-Nov-06 14-Apr-07 08-Jan-07 A 20-Apr-07 A
PRO4520 PO to Del Electrical Matl's 0 100% 22-Jan-07 23-May-07 29-Jan-07 A 24-May-07 A
PRO4530 PO to Del Instrument Matl's 0 100% 22-Jan-07 24-May-07 29-Jan-07 A 24-May-07 A
PRO4460 PO to Del Structural Matl's 0 100% 03-Jan-07 15-May-07 22-Feb-07 A 15-May-07 A
PRO4540 PO to Del Mechanical Matl's 0 100% 20-Dec-06 19-May-07 22-Feb-07 A 18-May-07 A
Materials Receiving Inspection 0 14-Apr-07 05-Jun-07 09-Apr-07 A 24-Aug-07 A 0
PRO4590 Receive/Accept of Pipe Matl's 0 100% 14-Apr-07 04-May-07 09-Apr-07 A 24-Aug-07 A
PRO4600 Receive/Accept of Electrical Matl's 0 100% 24-May-07 05-Jun-07 16-Apr-07 A 17-Aug-07 A
PRO4610 Receive/Accept of Instrument Matl's 0 100% 25-May-07 05-Jun-07 16-Apr-07 A 24-Aug-07 A
PRO4620 Receive/Accept of Mechanical Matl's 0 100% 21-May-07 30-May-07 08-May-07 A 01-Jun-07 A
PRO4580 Receive/Accept of Structural Matl's 0 100% 15-May-07 23-May-07 16-May-07 A 25-May-07 A
FABRICATION 0 04-May-07 24-Jul-07 07-May-07 A 31-Aug-07 A 0
Structural 0 24-May-07 05-Jul-07 24-May-07 A 06-Jul-07 A 0
SHP1000 Fab. Misc Structural Members E11K-A 0 100% 24-May-07 05-Jul-07 24-May-07 A 06-Jul-07 A
Mechanical 0 30-May-07 04-Jul-07 31-May-07 A 08-Jun-07 A 0
SHP1120 Fab. Mechanical Items 0 100% 30-May-07 04-Jul-07 31-May-07 A 08-Jun-07 A
Contract No : 591397 Page 12 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
Piping 0 04-May-07 13-Jul-07 07-May-07 A 24-Aug-07 A 0
SHP1010 Fabricate Pipe Supports 0 100% 04-May-07 11-Jun-07 07-May-07 A 29-Jun-07 A
SHP1030 Fabricate CS Pipe Spools 0 100% 04-May-07 07-Jun-07 07-May-07 A 06-Jul-07 A
SHP1160 Fabricate Duplex Pipe Spools 0 100% 26-May-07 21-Jun-07 21-May-07 A 17-Aug-07 A
SHP1040 Testing & Preservation of Pipe Spools 0 100% 16-Jun-07 06-Jul-07 22-May-07 A 24-Aug-07 A
SHP1170 Fabricate SS Pipe Spools 0 100% 13-Jun-07 01-Jul-07 18-Jun-07 A 02-Jul-07 A
SHP1180 Fabricate GRE Pipe Spools 0 100% 26-Jun-07 13-Jul-07 28-Jun-07 A 14-Jul-07 A
Electrical 0 05-Jun-07 11-Jul-07 30-May-07 A 31-Aug-07 A 0
SHP1050 Fabricate Electrical Supports 0 100% 05-Jun-07 29-Jun-07 30-May-07 A 22-Jun-07 A
SHP1140 Electrical Shiploose Items 0 100% 21-Jun-07 11-Jul-07 25-Jun-07 A 31-Aug-07 A
Instrument 0 05-Jun-07 11-Jul-07 09-Jun-07 A 31-Aug-07 A 0
SHP1060 Fabricate Instrument Supports 0 100% 05-Jun-07 29-Jun-07 09-Jun-07 A 06-Jul-07 A
SHP1150 Instrument Shiploose Items 0 100% 21-Jun-07 11-Jul-07 25-Jun-07 A 31-Aug-07 A
Blasting/Painting 0 11-Jun-07 24-Jul-07 12-Jun-07 A 03-Aug-07 A 0
SHP1070 Blasting/Painting Pipe Supports 0 100% 11-Jun-07 28-Jun-07 12-Jun-07 A 29-Jun-07 A
SHP1090 Blasting/Painting Electrical Supports 0 100% 29-Jun-07 09-Jul-07 23-Jun-07 A 29-Jun-07 A
SHP1080 Blasting/Painting Pipe Spools 0 100% 06-Jul-07 24-Jul-07 25-Jun-07 A 03-Aug-07 A
SHP1100 Blasting/Painting Instrument Supports 0 100% 29-Jun-07 09-Jul-07 25-Jun-07 A 29-Jun-07 A
SHP1130 Blasting/Painting Mechanical Items 0 100% 04-Jul-07 13-Jul-07 04-Jul-07 A 13-Jul-07 A
SHP1110 Blasting/Painting Structural Members 0 100% 05-Jul-07 17-Jul-07 05-Jul-07 A 20-Jul-07 A
LOADOUT & SEAFASTENING
SEAF SHIPLOOSE 0 08-Aug-07 11-Aug-07 04-Oct-07 A 05-Oct-07 A 0
LOA1020 Loadout & Seafastening Shiploose Items 0 100% 08-Aug-07 11-Aug-07 04-Oct-07 A 05-Oct-07 A
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 2 - OVERALL S-CURVE


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.01 0.01 0.01 0.00 0.01
21-Jul-06
0.02 0.03 0.03 0.00 0.04 28-Jul-06
0.08 0.08 0.11 0.00 0.11 04-Aug-06
0.27 0.30 0.39 0.02 0.41 11-Aug-06
0.34 0.32 0.72 0.08 0.73 18-Aug-06
0.42 0.42 1.15 0.21 1.14 25-Aug-06
1.24 0.38 2.39 0.34 1.52 01-Sep-06
0.53 0.45 2.92 0.55 1.97 08-Sep-06
0.31 0.47 3.23 0.88 2.44 15-Sep-06
0.28 0.53 3.51 1.28 2.97 22-Sep-06
0.28 0.55 3.79 1.65 3.52 29-Sep-06
0.51 0.72 4.30 2.10 4.24 06-Oct-06
0.71 0.79 5.01 2.59 5.04 13-Oct-06
1.21 0.88 6.22 3.14 5.91 20-Oct-06
0.29 0.46 6.51 3.42 6.38 27-Oct-06
0.73 0.90 7.24 4.02 7.28 03-Nov-06
0.79 0.87 8.03 4.69 8.15 10-Nov-06
0.66 0.93 8.69 5.42 9.08 17-Nov-06
1.02 1.08 9.71 6.17 10.16 24-Nov-06
0.89 1.03 10.60 6.90 11.19 01-Dec-06
0.93 1.00 11.53 7.81 12.19 08-Dec-06
0.83 0.94 12.36 8.90 13.13 15-Dec-06

Early Plan (Rev. 0)


0.95 0.89 13.31 9.96 14.02 22-Dec-06
0.92 0.78 14.23 10.83 14.80 29-Dec-06
1.14 1.08 15.37 11.65 15.88 05-Jan-07
1.15 1.37 16.52 12.58 17.26 12-Jan-07
1.50 1.67 18.02 13.57 18.93 19-Jan-07
1.94 1.93 19.96 14.79 20.86 26-Jan-07
1.92 2.20 21.88 16.21 23.06 02-Feb-07
3.14 2.43 25.02 17.71 25.49 09-Feb-07
FABRICATION OF

2.37 2.63 27.39 19.39 28.12 16-Feb-07

( Manhrs Based )
1.72 2.30 29.11 20.94 30.42 23-Feb-07
Late Plan (Rev. 0)

2.62 2.48 31.73 22.95 32.90 02-Mar-07

OVERALL S-CURVE
3.36 2.54 35.09 25.46 35.44 09-Mar-07
2.65 2.49 37.74 28.10 37.93 16-Mar-07
SCDR-A TOPSIDES & E11K-A SHIPLOOSE

1.66 2.48 39.40 30.60 40.41 23-Mar-07


2.90 2.73 42.30 33.29 43.14 30-Mar-07
2.67 2.46 44.97 35.83 45.60 06-Apr-07
2.45 3.15 47.42 38.68 48.75 13-Apr-07
2.49 3.22 49.91 41.44 51.98 20-Apr-07
2.04 3.21 51.95 44.01 55.19 27-Apr-07
2.68 2.55 54.63 46.59 57.74
Actual (Rev.0)

04-May-07
2.12 3.44 56.75 49.66 61.18 11-May-07
3.71 3.36 60.46 52.80 64.53 18-May-07
3.81 3.46 64.27 55.67 68.00 25-May-07
2.85 2.69 67.12 58.03 70.68 01-Jun-07
3.38 3.34 70.50 61.07 74.03 08-Jun-07
3.02 3.24 73.52 64.02 77.26 15-Jun-07
2.26 2.73 75.78 66.91 80.00 22-Jun-07
2.90 2.42 78.68 70.36 82.42 29-Jun-07
3.62 2.81 82.30 74.86 85.23 06-Jul-07
3.02 2.29 85.32 78.57 87.52 13-Jul-07
1.83 2.32 87.15 82.33 89.84 20-Jul-07
2.01 2.41 89.16 85.70 92.24 27-Jul-07
2.27 2.57 91.43 88.82 94.82 03-Aug-07
2.20 2.15 93.63 91.83 96.97 10-Aug-07
2.13 1.77 95.76 94.69 98.74 17-Aug-07
1.43 0.40 97.19 97.55 99.14 24-Aug-07
0.63 0.34 97.82 99.30 99.47 31-Aug-07
0.30 0.53 98.12 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.92 0.00 99.04 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.20 0.00 99.24 100.00 100.00 21-Sep-07


0.38 0.00 99.62 100.00 100.00 28-Sep-07

0.38 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.01 0.01 0.01 0.00 0.01
21-Jul-06
0.03 0.03 0.04 0.00 0.04 28-Jul-06
0.08 0.08 0.12 0.00 0.12 04-Aug-06
0.30 0.30 0.42 0.02 0.42 11-Aug-06
0.32 0.32 0.74 0.09 0.74 18-Aug-06
0.42 0.42 1.16 0.21 1.16 25-Aug-06
1.30 0.38 2.46 0.34 1.55 01-Sep-06
0.54 0.46 3.00 0.56 2.01 08-Sep-06
0.30 0.47 3.30 0.90 2.48 15-Sep-06
0.25 0.54 3.55 1.30 3.02 22-Sep-06
0.31 0.56 3.86 1.68 3.57 29-Sep-06
0.53 0.73 4.39 2.13 4.31 06-Oct-06
0.67 0.80 5.06 2.63 5.10 13-Oct-06
1.23 0.88 6.29 3.18 5.99 20-Oct-06
0.30 0.47 6.59 3.47 6.45 27-Oct-06
0.73 0.91 7.32 4.07 7.36 03-Nov-06
0.81 0.88 8.13 4.75 8.24 10-Nov-06
0.66 0.94 8.79 5.50 9.18 17-Nov-06
1.03 1.08 9.82 6.25 10.26 24-Nov-06
0.89 1.03 10.71 6.99 11.29 01-Dec-06
0.92 1.01 11.63 7.91 12.30 08-Dec-06
0.85 0.94 12.48 9.02 13.25 15-Dec-06

Early Plan (Rev. 0)


0.95 0.90 13.43 10.09 14.15 22-Dec-06
0.94 0.78 14.37 10.97 14.93 29-Dec-06
1.15 1.09 15.52 11.81 16.02 05-Jan-07
1.17 1.39 16.69 12.74 17.41 12-Jan-07
1.52 1.69 18.21 13.74 19.10 19-Jan-07
1.97 1.96 20.18 14.98 21.06 26-Jan-07
1.95 2.24 22.13 16.42 23.31 02-Feb-07
3.19 2.47 25.32 17.94 25.78 09-Feb-07
2.40 2.68 27.72 19.64 28.46 16-Feb-07

( Manhrs Based )
1.76 2.34 29.48 21.21 30.80 23-Feb-07
Late Plan (Rev. 0)

2.65 2.52 32.13 23.25 33.33 02-Mar-07


3.43 2.59 35.56 25.80 35.92 09-Mar-07
FABRICATION OF SCDR-A TOPSIDES

2.70 2.54 38.26 28.48 38.46 16-Mar-07


1.68 2.52 39.94 31.03 40.98

Overall SCDR-A S-CURVE


23-Mar-07
2.95 2.78 42.89 33.76 43.76 30-Mar-07
2.72 2.51 45.61 36.35 46.27 06-Apr-07
2.49 3.21 48.10 39.25 49.48 13-Apr-07
2.52 3.28 50.62 42.05 52.76 20-Apr-07
2.07 3.27 52.69 44.66 56.02 27-Apr-07
2.73 2.59 55.42 47.28 58.61
Actual (Rev.0)

04-May-07
2.00 3.41 57.42 50.40 62.02 11-May-07
3.76 3.32 61.18 53.58 65.34 18-May-07
3.77 3.41 64.95 56.45 68.76 25-May-07
2.84 2.55 67.79 58.80 71.31 01-Jun-07
3.26 3.15 71.05 61.83 74.46 08-Jun-07
2.91 3.09 73.96 64.70 77.55 15-Jun-07
2.17 2.54 76.13 67.43 80.09 22-Jun-07
2.69 2.27 78.82 70.75 82.37 29-Jun-07
3.50 2.71 82.32 75.13 85.07 06-Jul-07
3.04 2.26 85.36 78.71 87.34 13-Jul-07
1.85 2.35 87.21 82.35 89.69 20-Jul-07
2.03 2.45 89.24 85.60 92.14 27-Jul-07
2.32 2.62 91.56 88.69 94.76 03-Aug-07
2.23 2.16 93.79 91.70 96.92 10-Aug-07
2.18 1.79 95.97 94.59 98.71 17-Aug-07
1.23 0.41 97.20 97.50 99.12 24-Aug-07
0.60 0.34 97.80 99.29 99.46 31-Aug-07
0.30 0.54 98.10 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.94 0.00 99.04 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.20 0.00 99.24 100.00 100.00 21-Sep-07


0.39 0.00 99.63 100.00 100.00 28-Sep-07

0.37 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.00 0.00 0.00 0.00 0.00
21-Jul-06
0.00 0.00 0.00 0.00 0.00 28-Jul-06
0.00 0.00 0.00 0.00 0.00 04-Aug-06
0.00 0.00 0.00 0.00 0.00 11-Aug-06
0.00 0.00 0.00 0.00 0.00 18-Aug-06
0.00 0.00 0.00 0.00 0.00 25-Aug-06
0.00 0.00 0.00 0.00 0.00 01-Sep-06
0.00 0.00 0.00 0.00 0.00 08-Sep-06
0.00 0.00 0.00 0.00 0.00 15-Sep-06
0.00 0.00 0.00 0.00 0.00 22-Sep-06
0.00 0.00 0.00 0.00 0.00 29-Sep-06
0.00 0.00 0.00 0.00 0.00 06-Oct-06
0.00 0.00 0.00 0.00 0.00 13-Oct-06
0.00 0.00 0.00 0.00 0.00 20-Oct-06
0.00 0.00 0.00 0.00 0.00 27-Oct-06
0.00 0.00 0.00 0.00 0.00 03-Nov-06
0.00 0.00 0.00 0.00 0.00 10-Nov-06
0.00 0.00 0.00 0.00 0.00 17-Nov-06
0.00 0.00 0.00 0.00 0.00 24-Nov-06
0.00 0.00 0.00 0.00 0.00 01-Dec-06
0.00 0.00 0.00 0.00 0.00 08-Dec-06
0.00 0.00 0.00 0.00 0.00 15-Dec-06

Early Plan (Rev. 0)


0.00 0.00 0.00 0.00 0.00 22-Dec-06
0.00 0.00 0.00 0.00 0.00 29-Dec-06
0.00 0.00 0.00 0.00 0.00 05-Jan-07
0.00 0.00 0.00 0.00 0.00 12-Jan-07
0.00 0.00 0.00 0.00 0.00 19-Jan-07
0.00 0.00 0.00 0.00 0.00 26-Jan-07
0.00 0.00 0.00 0.00 0.00 02-Feb-07
0.00 0.00 0.00 0.00 0.00 09-Feb-07
0.00 0.00 0.00 0.00 0.00 16-Feb-07

( Manhrs Based )
0.00 0.00 0.00 0.00 0.00 23-Feb-07
Late Plan (Rev. 0)

0.00 0.00 0.00 0.00 0.00 02-Mar-07


0.00 0.00 0.00 0.00 0.00 09-Mar-07
FABRICATION OF SCDR-A TOPSIDES

0.00 0.00 0.00 0.00 0.00 16-Mar-07


0.00 0.00 0.00 0.00 0.00 23-Mar-07
0.00 0.00 0.00 0.00 0.00 30-Mar-07
0.00 0.00 0.00 0.00 0.00 06-Apr-07

Weighing, Loadout & Seafastening S-CURVE


0.00 0.00 0.00 0.00 0.00 13-Apr-07
0.00 0.00 0.00 0.00 0.00 20-Apr-07
0.00 0.00 0.00 0.00 0.00 27-Apr-07
Actual (Rev.0)

0.00 0.00 0.00 0.00 0.00 04-May-07


0.00 0.00 0.00 0.00 0.00 11-May-07
0.00 0.00 0.00 0.00 0.00 18-May-07
0.00 0.00 0.00 0.00 0.00 25-May-07
0.00 0.00 0.00 0.00 0.00 01-Jun-07
0.00 0.00 0.00 0.00 0.00 08-Jun-07
0.00 0.00 0.00 0.00 0.00 15-Jun-07
0.00 0.00 0.00 0.00 0.00 22-Jun-07
0.00 0.00 0.00 0.00 0.00 29-Jun-07
0.00 14.73 0.00 0.00 14.73 06-Jul-07
21.81 7.09 21.81 1.78 21.81 13-Jul-07
6.11 6.10 27.92 18.42 27.92 20-Jul-07
6.09 6.09 34.01 24.52 34.01 27-Jul-07
6.11 6.10 40.12 30.61 40.12 03-Aug-07
6.10 6.10 46.22 36.72 46.22 10-Aug-07
5.74 17.59 51.96 42.81 63.81 17-Aug-07
0.00 0.00 51.96 48.92 63.81 24-Aug-07
11.85 11.01 63.81 70.70 74.83 31-Aug-07
0.00 25.17 63.81 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

33.81 0.00 97.62 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

2.38 0.00 100.00 100.00 100.00 21-Sep-07


0.00 0.00 100.00 100.00 100.00 28-Sep-07

0.00 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.00 0.00 0.00 0.00 0.00
21-Jul-06
0.00 0.00 0.00 0.00 0.00 28-Jul-06
0.00 0.00 0.00 0.00 0.00 04-Aug-06
0.00 0.00 0.00 0.00 0.00 11-Aug-06
0.00 0.00 0.00 0.00 0.00 18-Aug-06
0.00 0.00 0.00 0.00 0.00 25-Aug-06
0.00 0.00 0.00 0.00 0.00 01-Sep-06
0.00 0.00 0.00 0.00 0.00 08-Sep-06
0.00 0.00 0.00 0.00 0.00 15-Sep-06
0.00 0.00 0.00 0.00 0.00 22-Sep-06
0.00 0.00 0.00 0.00 0.00 29-Sep-06
0.00 0.00 0.00 0.00 0.00 06-Oct-06
0.00 0.00 0.00 0.00 0.00 13-Oct-06
0.00 0.00 0.00 0.00 0.00 20-Oct-06
0.00 0.00 0.00 0.00 0.00 27-Oct-06
0.00 0.00 0.00 0.00 0.00 03-Nov-06
0.00 0.00 0.00 0.00 0.00 10-Nov-06
0.00 0.00 0.00 0.00 0.00 17-Nov-06
0.00 0.00 0.00 0.00 0.00 24-Nov-06
0.00 0.00 0.00 0.00 0.00 01-Dec-06
0.00 0.00 0.00 0.00 0.00 08-Dec-06
0.00 0.00 0.00 0.00 0.00 15-Dec-06

Early Plan (Rev. 0)


0.00 0.00 0.00 0.00 0.00 22-Dec-06
0.00 0.00 0.00 0.00 0.00 29-Dec-06
0.00 0.00 0.00 0.00 0.00 05-Jan-07
0.00 0.00 0.00 0.00 0.00 12-Jan-07
0.00 0.00 0.00 0.00 0.00 19-Jan-07
0.00 0.00 0.00 0.00 0.00 26-Jan-07
0.00 0.00 0.00 0.00 0.00 02-Feb-07
0.00 0.00 0.00 0.00 0.00 09-Feb-07
0.00 0.00 0.00 0.00 0.00 16-Feb-07

( Manhrs Based )
0.00 0.00 0.00 0.00 0.00 23-Feb-07
Late Plan (Rev. 0)

0.00 0.00 0.00 0.00 0.00 02-Mar-07


0.00 0.00 0.00 0.00 0.00 09-Mar-07
FABRICATION OF SCDR-A TOPSIDES

0.00 0.00 0.00 0.00 0.00 16-Mar-07


0.00 0.00 0.00 0.00 0.00 23-Mar-07
0.00 0.00 0.00 0.00 0.00 30-Mar-07

Pre-Commissioning S-CURVE
0.00 0.00 0.00 0.00 0.00 06-Apr-07
0.00 0.00 0.00 0.00 0.00 13-Apr-07
0.00 0.00 0.00 0.00 0.00 20-Apr-07
0.00 0.00 0.00 0.00 0.00 27-Apr-07
Actual (Rev.0)

0.00 0.00 0.00 0.00 0.00 04-May-07


0.00 0.00 0.00 0.00 0.00 11-May-07
0.00 0.00 0.00 0.00 0.00 18-May-07
0.59 0.88 0.59 0.00 0.88 25-May-07
0.00 1.06 0.59 0.00 1.94 01-Jun-07
0.44 1.27 1.03 0.00 3.22 08-Jun-07
0.00 2.65 1.03 0.00 5.87 15-Jun-07
0.00 3.83 1.03 0.00 9.70 22-Jun-07
9.22 4.61 10.25 0.00 14.31 29-Jun-07
6.41 10.47 16.66 0.37 24.78 06-Jul-07
1.68 9.67 18.34 2.50 34.45 13-Jul-07
2.75 9.98 21.09 5.26 44.43 20-Jul-07
7.51 10.90 28.60 10.16 55.33 27-Jul-07
9.58 12.55 38.18 22.61 67.89 03-Aug-07
12.98 11.17 51.16 40.48 79.06 10-Aug-07
23.60 12.54 74.76 65.02 91.60 17-Aug-07
15.14 5.97 89.90 89.50 97.56 24-Aug-07
2.60 2.44 92.50 100.00 100.00 31-Aug-07
2.93 0.00 95.43 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.00 0.00 95.43 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

1.41 0.00 96.84 100.00 100.00 21-Sep-07


2.20 0.00 99.04 100.00 100.00 28-Sep-07

0.96 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.00 0.00 0.00 0.00 0.00
21-Jul-06
0.00 0.00 0.00 0.00 0.00 28-Jul-06
0.00 0.00 0.00 0.00 0.00 04-Aug-06
0.00 0.00 0.00 0.00 0.00 11-Aug-06
0.00 0.00 0.00 0.00 0.00 18-Aug-06
0.00 0.00 0.00 0.00 0.00 25-Aug-06
0.00 0.00 0.00 0.00 0.00 01-Sep-06
0.00 0.00 0.00 0.00 0.00 08-Sep-06
0.00 0.00 0.00 0.00 0.00 15-Sep-06
0.00 0.00 0.00 0.00 0.00 22-Sep-06
0.03 0.07 0.03 0.00 0.07 29-Sep-06
0.01 0.09 0.04 0.00 0.16 06-Oct-06
0.10 0.09 0.14 0.00 0.25 13-Oct-06
0.21 0.15 0.35 0.07 0.41 20-Oct-06
0.04 0.08 0.39 0.12 0.48 27-Oct-06
0.16 0.15 0.55 0.20 0.63 03-Nov-06
0.19 0.15 0.74 0.33 0.79 10-Nov-06
0.38 0.37 1.12 0.48 1.15 17-Nov-06
0.67 0.61 1.79 0.63 1.76 24-Nov-06
0.40 0.60 2.19 0.78 2.35 01-Dec-06
0.47 0.58 2.66 1.14 2.93 08-Dec-06
0.47 0.54 3.13 1.75 3.47 15-Dec-06

Early Plan (Rev. 0)


0.70 0.59 3.83 2.34 4.06 22-Dec-06
0.74 0.63 4.57 2.83 4.68 29-Dec-06
1.01 1.06 5.58 3.27 5.75 05-Jan-07
1.15 1.41 6.73 3.80 7.16 12-Jan-07
1.56 1.83 8.29 4.42 8.98 19-Jan-07
2.15 2.26 10.44 5.40 11.24 26-Jan-07
2.13 2.66 12.57 6.68 13.90 02-Feb-07
3.45 2.97 16.02 8.14 16.88 09-Feb-07
2.96 3.17 18.98 9.92 20.05 16-Feb-07

( Manhrs Based )
1.85 2.76 20.83 11.62 22.81 23-Feb-07
Late Plan (Rev. 0)

2.94 2.96 23.77 13.98 25.77 02-Mar-07


3.95 3.12 27.72 17.08 28.89 09-Mar-07

Fabrication S-CURVE
FABRICATION OF SCDR-A TOPSIDES

3.43 3.08 31.15 20.34 31.97 16-Mar-07


2.08 3.05 33.23 23.40 35.02 23-Mar-07
3.53 3.43 36.76 26.78 38.45 30-Mar-07
3.50 3.07 40.26 30.04 41.53 06-Apr-07
2.93 3.84 43.19 33.71 45.37 13-Apr-07
3.24 3.93 46.43 37.28 49.31 20-Apr-07
2.27 4.12 48.70 40.51 53.42 27-Apr-07
Actual (Rev.0)

3.20 3.25 51.90 43.84 56.68 04-May-07


2.46 4.21 54.36 47.79 60.89 11-May-07
4.72 4.23 59.08 51.77 65.12 18-May-07
4.94 4.24 64.02 55.10 69.36 25-May-07
3.85 3.12 67.87 57.76 72.48 01-Jun-07
4.23 3.92 72.10 61.15 76.40 08-Jun-07
3.66 3.81 75.76 64.48 80.21 15-Jun-07
2.69 2.91 78.45 67.79 83.12 22-Jun-07
2.79 2.47 81.24 71.89 85.59 29-Jun-07
3.93 2.22 85.17 77.38 87.81 06-Jul-07
3.09 1.97 88.26 81.67 89.78 13-Jul-07
2.16 2.02 90.42 85.47 91.80 20-Jul-07
2.17 2.33 92.59 89.13 94.13 27-Jul-07
2.40 2.59 94.99 92.23 96.72 03-Aug-07
2.04 2.06 97.03 94.77 98.78 10-Aug-07
1.38 1.11 98.41 96.84 99.89 17-Aug-07
0.71 0.11 99.12 99.01 100.00 24-Aug-07
0.16 0.00 99.28 100.00 100.00 31-Aug-07
0.21 0.00 99.49 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.17 0.00 99.66 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.03 0.00 99.69 100.00 100.00 21-Sep-07


0.31 0.00 100.00 100.00 100.00 28-Sep-07

0.00 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.00 0.00 0.00 0.00 0.00
21-Jul-06
0.00 0.00 0.00 0.00 0.00 28-Jul-06
0.00 0.00 0.00 0.00 0.00 04-Aug-06
0.07 0.07 0.07 0.07 0.07 11-Aug-06
0.31 0.31 0.38 0.17 0.38 18-Aug-06
1.48 1.48 1.86 0.29 1.86 25-Aug-06
4.05 1.61 5.91 0.54 3.47 01-Sep-06
6.67 1.91 12.58 1.15 5.38 08-Sep-06
1.12 2.08 13.70 2.60 7.46 15-Sep-06
1.88 2.81 15.58 4.57 10.27 22-Sep-06
0.61 2.76 16.19 6.26 13.04 29-Sep-06
5.93 3.75 22.12 8.16 16.78 06-Oct-06
1.19 3.92 23.31 10.50 20.70 13-Oct-06
2.47 4.04 25.78 12.93 24.74 20-Oct-06
2.11 2.06 27.89 14.22 26.80 27-Oct-06
1.31 4.03 29.20 17.16 30.83 03-Nov-06
3.25 4.03 32.45 20.51 34.86 10-Nov-06
2.49 3.24 34.94 23.84 38.10 17-Nov-06
2.29 2.66 37.23 27.01 40.76 24-Nov-06
3.14 2.38 40.37 29.73 43.14 01-Dec-06
1.03 2.51 41.40 32.69 45.65 08-Dec-06
1.96 2.08 43.36 35.91 47.72 15-Dec-06

Early Plan (Rev. 0)


1.50 1.33 44.86 38.97 49.05 22-Dec-06
1.07 0.91 45.93 41.51 49.96 29-Dec-06
1.48 0.89 47.41 43.67 50.84 05-Jan-07
0.86 0.73 48.27 45.74 51.57 12-Jan-07
1.51 0.93 49.78 47.26 52.50 19-Jan-07
1.21 0.70 50.99 48.77 53.20 26-Jan-07
0.42 0.76 51.41 50.43 53.96 02-Feb-07
1.12 0.63 52.53 51.85 54.59 09-Feb-07
1.65 0.83 54.18 52.90 55.42 16-Feb-07

( Manhrs Based )
1.63 0.83 55.81 53.74 56.25 23-Feb-07
Late Plan (Rev. 0)

1.48 1.05 57.29 54.44 57.30 02-Mar-07


2.44 1.05 59.73 55.01 58.35 09-Mar-07
FABRICATION OF SCDR-A TOPSIDES

2.05 1.06 61.78 55.81 59.41

Procurement S-CURVE
16-Mar-07
0.78 1.40 62.56 56.64 60.81 23-Mar-07
3.26 1.58 65.82 57.41 62.39 30-Mar-07
1.87 1.93 67.69 57.69 64.32 06-Apr-07
2.16 3.49 69.85 57.98 67.81 13-Apr-07
0.93 3.50 70.78 58.34 71.31 20-Apr-07
3.88 2.06 74.66 59.08 73.37 27-Apr-07
Actual (Rev.0)

4.35 1.69 79.01 60.08 75.06 04-May-07


0.94 2.61 79.95 61.96 77.67 11-May-07
3.10 1.46 83.05 64.84 79.13 18-May-07
1.43 2.33 84.48 68.81 81.46 25-May-07
0.07 1.93 84.55 72.29 83.39 01-Jun-07
0.93 2.00 85.48 77.10 85.40 08-Jun-07
2.88 1.48 88.36 80.57 86.88 15-Jun-07
1.40 1.77 89.76 82.40 88.65 22-Jun-07
0.61 1.76 90.37 84.86 90.41 29-Jun-07
3.07 2.00 93.44 87.83 92.41 06-Jul-07
3.63 2.40 97.07 90.72 94.81 13-Jul-07
0.16 3.20 97.23 94.46 98.01 20-Jul-07
0.33 1.22 97.56 96.35 99.24 27-Jul-07
0.39 0.32 97.95 97.07 99.55 03-Aug-07
0.69 0.18 98.64 98.59 99.73 10-Aug-07
0.31 0.14 98.95 99.23 99.87 17-Aug-07
0.17 0.13 99.12 99.53 100.00 24-Aug-07
0.18 0.00 99.30 99.86 100.00 31-Aug-07
0.16 0.00 99.46 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.26 0.00 99.72 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.04 0.00 99.76 100.00 100.00 21-Sep-07


0.00 0.00 99.76 100.00 100.00 28-Sep-07

0.24 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.00 0.00 0.00 0.00 0.00
21-Jul-06
0.00 0.00 0.00 0.00 0.00 28-Jul-06
0.00 0.00 0.00 0.00 0.00 04-Aug-06
1.94 1.94 1.94 0.12 1.94 11-Aug-06
3.94 1.94 5.88 0.56 3.88 18-Aug-06
2.93 1.94 8.81 1.35 5.81 25-Aug-06
4.82 1.60 13.63 2.11 7.42 01-Sep-06
1.28 1.94 14.91 3.50 9.36 08-Sep-06
1.86 1.94 16.77 4.94 11.29 15-Sep-06
0.93 1.94 17.70 6.53 13.23 22-Sep-06
2.23 1.60 19.93 8.14 14.83 29-Sep-06
1.25 2.22 21.18 10.08 17.06 06-Oct-06
4.30 2.35 25.48 12.01 19.40 13-Oct-06
0.60 2.66 26.08 13.95 22.06 20-Oct-06
0.79 1.75 26.87 14.92 23.82 27-Oct-06
2.45 3.34 29.32 16.76 27.16 03-Nov-06
3.08 3.29 32.40 18.51 30.45 10-Nov-06
0.54 3.14 32.94 20.79 33.59 17-Nov-06
2.68 3.14 35.62 23.42 36.73 24-Nov-06
2.41 3.21 38.03 26.28 39.94 01-Dec-06
4.77 2.93 42.80 29.23 42.87 08-Dec-06
2.64 2.98 45.44 32.03 45.85 15-Dec-06

Early Plan (Rev. 0)


2.94 3.20 48.38 34.81 49.05 22-Dec-06
2.95 2.59 51.33 37.19 51.64 29-Dec-06
2.83 2.70 54.16 39.56 54.33 05-Jan-07
2.76 3.29 56.92 42.69 57.62 12-Jan-07
3.47 3.29 60.39 46.39 60.91 19-Jan-07
4.13 3.29 64.52 50.11 64.20 26-Jan-07
4.57 3.29 69.09 53.58 67.48 02-Feb-07
5.80 3.29 74.89 56.88 70.77 09-Feb-07
1.46 3.29 76.35 60.17 74.05 16-Feb-07

( Manhrs Based )
2.36 2.78 78.71 62.95 76.84 23-Feb-07
Late Plan (Rev. 0)

2.89 2.84 81.60 66.24 79.67 02-Mar-07


4.59 2.69 86.19 69.52 82.37 09-Mar-07
FABRICATION OF SCDR-A TOPSIDES

Engineering S-CURVE
0.43 2.47 86.62 72.81 84.84 16-Mar-07
0.78 1.81 87.40 76.10 86.64 23-Mar-07
1.09 1.75 88.49 79.43 88.39 30-Mar-07
0.49 1.47 88.98 82.45 89.86 06-Apr-07
1.02 1.25 90.00 85.60 91.11 13-Apr-07
0.88 1.13 90.88 87.70 92.24 20-Apr-07
0.37 0.83 91.25 89.81 93.07 27-Apr-07
Actual (Rev.0)

0.17 0.57 91.42 91.41 93.64 04-May-07


0.17 0.69 91.59 92.55 94.33 11-May-07
0.24 0.69 91.83 93.23 95.01 18-May-07
0.19 0.69 92.02 93.92 95.70 25-May-07
0.09 0.43 92.11 94.49 96.14 01-Jun-07
0.84 0.40 92.95 95.17 96.54 08-Jun-07
0.09 0.40 93.04 95.86 96.94 15-Jun-07
0.48 0.40 93.52 96.55 97.35 22-Jun-07
0.07 0.41 93.59 97.07 97.75 29-Jun-07
0.11 0.47 93.70 97.54 98.22 06-Jul-07
0.18 0.40 93.88 97.95 98.62 13-Jul-07
0.21 0.40 94.09 98.35 99.03 20-Jul-07
0.19 0.41 94.28 98.75 99.43 27-Jul-07
0.47 0.40 94.75 99.16 99.84 03-Aug-07
0.33 0.16 95.08 99.56 100.00 10-Aug-07

0.09 0.00 95.17 99.97 100.00 17-Aug-07


0.65 0.00 95.82 100.00 100.00 24-Aug-07
1.35 0.00 97.17 100.00 100.00 31-Aug-07
0.07 0.00 97.24 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.98 0.00 98.22 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.86 0.00 99.08 100.00 100.00 21-Sep-07


0.00 0.00 99.08 100.00 100.00 28-Sep-07

0.92 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.15 0.15 0.15 0.00 0.15
21-Jul-06
0.43 0.43 0.58 0.00 0.58 28-Jul-06
1.14 1.14 1.72 0.00 1.72 04-Aug-06
2.20 2.20 3.92 0.00 3.92 11-Aug-06
3.20 2.20 7.12 0.43 6.12 18-Aug-06
3.20 2.20 10.32 1.22 8.32 25-Aug-06
3.34 1.82 13.66 1.99 10.13 01-Sep-06
1.55 2.20 15.21 2.92 12.33 08-Sep-06
1.44 2.20 16.65 4.44 14.53 15-Sep-06
1.08 2.26 17.73 6.08 16.80 22-Sep-06
1.37 2.20 19.10 7.74 19.00 29-Sep-06
1.56 2.71 20.66 9.94 21.71 06-Oct-06
1.95 3.29 22.61 12.14 25.00 13-Oct-06
5.06 3.42 27.67 14.34 28.42 20-Oct-06
0.37 1.53 28.04 15.44 29.94 27-Oct-06
4.82 3.00 32.86 17.66 32.95 03-Nov-06
2.31 2.59 35.17 20.26 35.53 10-Nov-06
2.11 2.44 37.28 22.91 37.97 17-Nov-06
2.39 2.80 39.67 25.59 40.77 24-Nov-06
2.22 2.47 41.89 28.27 43.24 01-Dec-06
2.15 2.49 44.04 31.01 45.72 08-Dec-06
2.18 2.35 46.22 33.92 48.07 15-Dec-06

Early Plan (Rev. 0)


1.45 1.85 47.67 36.58 49.92 22-Dec-06
1.57 1.00 49.24 38.69 50.92 29-Dec-06
1.38 0.91 50.62 41.05 51.83 05-Jan-07
1.12 1.23 51.74 43.23 53.06 12-Jan-07
0.33 1.03 52.07 45.48 54.09 19-Jan-07
0.44 0.81 52.51 47.49 54.90 26-Jan-07
1.04 0.74 53.55 49.28 55.64 02-Feb-07
3.14 1.04 56.69 50.99 56.68 09-Feb-07
0.95 1.74 57.64 52.58 58.42 16-Feb-07

( Manhrs Based )
1.86 1.62 59.50 53.85 60.04 23-Feb-07
Late Plan (Rev. 0)

3.53 1.94 63.03 54.81 61.97 02-Mar-07


1.17 1.36 64.20 55.68 63.33 09-Mar-07
FABRICATION OF SCDR-A TOPSIDES

1.04 1.32 65.24 56.72 64.65

Preliminaries S-CURVE
16-Mar-07
1.42 1.68 66.66 57.54 66.33 23-Mar-07
1.36 1.32 68.02 57.98 67.65 30-Mar-07
0.82 0.92 68.84 58.43 68.57 06-Apr-07
2.44 1.64 71.28 59.15 70.21 13-Apr-07
1.33 1.75 72.61 60.49 71.96 20-Apr-07
1.67 1.82 74.28 61.99 73.78 27-Apr-07
Actual (Rev.0)

1.39 1.63 75.67 62.97 75.41 04-May-07


2.51 2.41 78.18 64.18 77.83 11-May-07
2.16 2.34 80.34 65.40 80.17 18-May-07
1.83 1.94 82.17 67.28 82.11 25-May-07
1.61 1.60 83.78 69.26 83.71 01-Jun-07
1.73 1.94 85.51 71.93 85.66 08-Jun-07
0.99 1.94 86.50 74.60 87.60 15-Jun-07
1.80 1.99 88.30 77.31 89.59 22-Jun-07
3.72 2.16 92.02 80.02 91.75 29-Jun-07
2.70 2.37 94.72 82.93 94.12 06-Jul-07
0.00 0.83 94.72 85.14 94.95 13-Jul-07
0.68 0.81 95.40 87.08 95.76 20-Jul-07
0.00 0.81 95.40 89.02 96.56 27-Jul-07
0.00 0.81 95.40 90.96 97.37 03-Aug-07
0.00 0.81 95.40 92.89 98.17 10-Aug-07
0.00 1.01 95.40 94.83 99.18 17-Aug-07
0.00 0.82 95.40 96.86 100.00 24-Aug-07
0.00 0.00 95.40 98.84 100.00 31-Aug-07
0.04 0.00 95.44 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.00 0.00 95.44 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.00 0.00 95.44 100.00 100.00 21-Sep-07


1.14 0.00 96.58 100.00 100.00 28-Sep-07

3.42 0.00 100.00 100.00 100.00 05-Oct-07


Percentage

Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100

Actual (Rev.0)

Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)

Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06

Planning Ref : PN5103-0 (M)


0.00 0.00 0.00 0.00 0.00
21-Jul-06
0.00 0.00 0.00 0.00 0.00 28-Jul-06
0.00 0.00 0.00 0.00 0.00 04-Aug-06
0.00 0.00 0.00 0.00 0.00 11-Aug-06
0.00 0.00 0.00 0.00 0.00 18-Aug-06
0.00 0.07 0.00 0.00 0.07 25-Aug-06
0.66 0.11 0.66 0.00 0.18 01-Sep-06
0.21 0.13 0.87 0.05 0.32 08-Sep-06
0.01 0.13 0.88 0.18 0.45 15-Sep-06
0.01 0.12 0.89 0.32 0.58 22-Sep-06
0.01 0.11 0.90 0.43 0.69 29-Sep-06
0.02 0.32 0.92 0.56 1.00 06-Oct-06
0.15 0.56 1.07 0.69 1.57 13-Oct-06
1.38 0.56 2.45 0.85 2.13 20-Oct-06
0.22 0.29 2.67 0.98 2.43 27-Oct-06
0.21 0.64 2.88 1.25 3.06 03-Nov-06
0.40 0.65 3.28 1.52 3.71 10-Nov-06
0.34 0.69 3.62 1.78 4.40 17-Nov-06
0.32 0.69 3.94 2.10 5.08 24-Nov-06
1.39 0.75 5.33 2.46 5.83 01-Dec-06
0.86 0.67 6.19 2.85 6.51 08-Dec-06
0.31 0.67 6.50 3.14 7.18 15-Dec-06

Early Plan (Rev. 0)


0.49 0.65 6.99 3.28 7.83 22-Dec-06
0.38 0.50 7.37 3.59 8.33 29-Dec-06
0.11 0.51 7.48 3.90 8.85 05-Jan-07
0.17 0.58 7.65 4.28 9.42 12-Jan-07
0.75 0.59 8.40 4.61 10.01 19-Jan-07
0.36 0.45 8.76 4.91 10.46 26-Jan-07
0.17 0.12 8.93 5.50 10.59 02-Feb-07
0.78 0.11 9.71 6.09 10.70 09-Feb-07
0.41 0.12 10.12 6.68 10.82 16-Feb-07

( Manhrs Based )
0.45 0.10 10.57 7.04 10.92 23-Feb-07
Late Plan (Rev. 0)

0.50 0.11 11.07 7.46 11.03 02-Mar-07


0.20 0.12 11.27 7.88 11.15 09-Mar-07
0.26 0.11 11.53 8.29 11.26 16-Mar-07
0.12 0.12 11.65 8.71 11.38 23-Mar-07
FABRICATION OF E11K-A SHIPLOOSE ITEMS

0.47 0.11 12.12 9.13 11.49 30-Mar-07

OverAll S-Curve E11K-A Shiploose Items


0.39 0.10 12.51 9.47 11.59 06-Apr-07
0.12 0.12 12.63 9.89 11.71 13-Apr-07
1.13 0.43 13.76 10.30 12.14 20-Apr-07
0.10 0.54 13.86 10.72 12.68 27-Apr-07
Actual (Rev.0)

0.08 0.45 13.94 11.30 13.13 04-May-07


8.21 4.74 22.15 12.14 17.88 11-May-07
1.64 5.23 23.79 12.99 23.11 18-May-07
5.77 6.02 29.56 16.09 29.12 25-May-07
3.81 9.74 33.37 18.76 38.86 01-Jun-07
9.10 13.02 42.47 22.20 51.89 08-Jun-07
8.59 10.55 51.06 29.27 62.44 15-Jun-07
6.76 12.53 57.82 40.65 74.97 22-Jun-07
13.77 10.18 71.59 50.39 85.15 29-Jun-07
9.51 7.90 81.10 61.49 93.05 06-Jul-07
2.03 3.69 83.13 70.98 96.74 13-Jul-07
1.02 0.74 84.15 81.48 97.48 20-Jul-07
0.50 0.17 84.65 90.65 97.65 27-Jul-07
0.22 0.00 84.87 95.32 97.65 03-Aug-07
0.53 1.48 85.40 98.77 99.13 10-Aug-07
0.00 0.87 85.40 100.00 100.00 17-Aug-07
11.16 0.00 96.56 100.00 100.00 24-Aug-07
2.11 0.00 98.67 100.00 100.00 31-Aug-07
0.34 0.00 99.01 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.

0.00 0.00 99.01 100.00 100.00 14-Sep-07


MALAYSIA MARINE AND HEAVY

0.05 0.00 99.06 100.00 100.00 21-Sep-07


0.13 0.00 99.19 100.00 100.00 28-Sep-07

0.81 0.00 100.00 100.00 100.00 05-Oct-07


SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 3 - MANPOWER HISTOGRAM


HVAC
Rigger
Painter

Electrical
Pipe Fitter

Rev. No : 0
Scaffolder
Instrument
Struct Fitter
Proc Coord

Pipe Welder

Electrical (F)

Architectural
Struct Welder

Instrument (F)

Total Direct Manhrs

Legend
Manpower Direct

Mechanical Fitter
Mechanical Tech

Total Overall Manhrs


Hydrotest/Leaktest

Total Indirect Manhrs


Manpower Indirect
MANPOWER PER WEEK

Corrd+Designer+etc

Job No : #2006351C
Weighing Technician

Contract No : 591397
Project Management

Total Wkly Manpower


Helper (Marker/Grinder)

LoadOut and Seafastening


Testing & PreCommissioning

Planning Ref : PN5103-0 (M)


Plan 42 - 42 1 1 1
21-Jul-06
Actual 108 - 108 2 2 2
Plan 121 - 121 3 3 3
28-Jul-06

100
150
200
250
300
350

50

0
Actual 432 - 432 8 1 1 6 8 21-Jul-06
Plan 319 - 319 7 7 7
4-Aug-06
Actual 540 - 540 10 1 1 8 10 28-Jul-06

Plan 1,260 - 1,260 28 14 1 14 28


11-Aug-06
Actual 1,026 - 1,026 19 5 5 9 19 4-Aug-06

Plan 1,347 - 1,347 30 14 2 14 30


18-Aug-06
Actual 1,350 - 1,350 25 7 8 10 25 11-Aug-06

Plan 1,765 - 1,765 39 14 12 14 39


25-Aug-06
Actual 1,620 - 1,620 30 9 8 13 30 18-Aug-06

Plan 1,596 - 1,596 35 12 13 11 35


1-Sep-06
Actual 1,890 - 1,890 35 11 10 14 35 25-Aug-06

Plan 1,920 - 1,920 43 14 15 14 43


8-Sep-06
Actual 1,944 - 1,944 36 11 10 15 36 1-Sep-06

Plan 1,981 - 1,981 44 14 16 14 44


15-Sep-06
Actual 2,214 - 2,214 41 14 10 17 41 8-Sep-06

Plan 2,253 - 2,253 50 14 22 14 50


22-Sep-06
2,322 - 2,322 14 10 19 15-Sep-06
Actual 43 43
Plan 2,324 214 2,110 52 5 5 12 22 14 47
29-Sep-06 22-Sep-06
Actual 2,700 162 2,538 50 3 3 15 10 22 47
Plan 3,073 259 2,814 68 6 6 16 29 17 63
6-Oct-06 29-Sep-06
Actual 3,024 378 2,646 56 5 2 7 15 10 24 49
Plan 3,367 269 3,098 75 0 6 0 0 0 6 17 31 21 69
13-Oct-06 6-Oct-06
Actual 3,456 702 2,754 64 9 4 13 15 10 26 51
Plan 3,725 448 3,277 83 0 6 1 1 2 10 20 32 21 73
20-Oct-06 13-Oct-06
Actual 3,888 918 2,970 72 1 10 5 1 17 15 10 30 55
Plan 1,961 224 1,737 44 0 3 0 1 1 5 13 16 10 39

Scaffolder
Pipe Fitter
27-Oct-06 20-Oct-06
Actual 1,710 450 1,260 38 1 5 3 1 10 8 9 11 28
Plan 3,827 448 3,379 85 0 6 1 1 2 10 25 32 19 75
Project Management

3-Nov-06 27-Oct-06
Actual 3,015 585 2,430 67 2 6 4 1 13 15 10 29 54
Plan 3,698 448 3,250 82 0 6 1 1 2 10 24 32 16 72
10-Nov-06 3-Nov-06
Actual 3,240 765 2,475 72 3 5 4 1 4 17 15 10 30 55
Plan 3,957 1,076 2,881 88 2 1 6 3 5 7 24 23 26 15 64
17-Nov-06 10-Nov-06
Actual 3,645 1,125 2,520 81 6 4 3 2 10 25 15 10 31 56
Proc Coord
Pipe Welder

Plan 4,562 1,778 2,784 101 4 2 1 6 12 16 40 23 21 17 62


17-Nov-06
24-Nov-06
Actual 4,815 2,295 2,520 107 12 10 2 5 7 15 51 15 10 31 56
Helper (Marker/Grinder)

Plan 4,365 1,748 2,617 97 4 2 6 12 16 39 23 19 15 58 24-Nov-06


1-Dec-06
Actual 4,950 2,430 2,520 110 13 12 1 5 8 15 54 15 10 31 56
Plan 4,261 1,693 2,568 95 4 2 6 11 15 38 21 20 15 57 1-Dec-06
8-Dec-06
Actual 4,815 2,295 2,520 107 10 9 6 10 16 51 15 10 31 56
Plan 3,984 1,586 2,398 89 3 2 1 5 10 14 35 22 17 15 53 8-Dec-06
15-Dec-06
Actual 5,040 2,610 2,430 112 12 7 5 6 11 17 58 14 10 30 54
Hydrotest/Leaktest
Corrd+Designer+etc

Plan 3,789 1,729 2,060 84 3 2 4 5 10 14 38 23 11 12 46 15-Dec-06


22-Dec-06
Actual 4,486 2,416 2,070 100 12 6 5 6 10 15 54 12 9 25 46
Testing & PreCommissioning

Plan 3,303 1,836 1,467 73 4 1 3 6 11 15 41 19 8 6 33 22-Dec-06


29-Dec-06
Actual 3,915 2,070 1,845 87 10 5 4 5 10 12 46 11 9 21 41
Plan 4,593 3,122 1,471 102 7 3 3 10 20 27 69 20 7 6 33 29-Dec-06
5-Jan-07
Electrical

Actual 4,725 2,745 1,980 105 11 5 4 7 12 22 61 13 9 22 44


Struct Fitter

Plan 5,923 4,133 1,790 132 9 4 4 14 26 35 92 24 8 8 40 5-Jan-07


12-Jan-07
Weighing Technician

Actual 6,435 3,825 2,610 143 18 5 5 7 20 30 85 21 10 27 58


Plan 7,129 5,369 1,760 158 12 5 1 2 4 18 33 44 119 24 9 6 39 12-Jan-07
19-Jan-07
Actual 7,200 4,590 2,610 160 17 5 7 8 27 38 102 20 10 28 58
8,324 6,628 1,696 14 6 2 3 4 9 5 19-Jan-07
Plan 185 23 41 54 147 24 38
26-Jan-07
Actual 7,695 4,995 2,700 171 21 7 7 8 29 39 111 20 10 30 60
26-Jan-07
Plan 9,487 7,818 1,669 211 16 8 5 5 5 27 46 61 174 23 9 5 37
Electrical (F)
Struct Welder

2-Feb-07
Actual 8,145 5,445 2,700 181 23 10 8 8 32 40 121 20 10 30 60
2-Feb-07
Plan 10,488 8,734 1,754 233 17 9 5 5 8 29 52 68 194 23 9 6 39
9-Feb-07
LoadOut and Seafastening

Actual 8,775 6,165 2,610 195 25 9 7 8 46 42 137 20 10 28 58


9-Feb-07
Plan 11,283 9,308 1,975 251 18 10 7 7 0 0 8 32 55 70 207 23 10 11 44

OVERALL MANPOWER HISTOGRAM


16-Feb-07
Actual 9,675 7,155 2,520 215 24 12 2 6 7 12 49 47 159 20 10 26 56
16-Feb-07
Rigger

Plan 9,892 8,116 1,776 220 16 8 9 10 1 1 7 28 44 57 180 20 10 10 39


23-Feb-07
Instrument

Actual 8,370 6,300 2,070 186 22 10 7 9 3 6 19 30 34 140 17 8 21 46


23-Feb-07
Plan 10,600 8,681 1,919 236 16 8 1 0 1 0 12 13 2 1 10 29 44 56 193 20 10 12 43
2-Mar-07
Actual 9,315 7,065 2,250 207 24 7 8 10 3 11 22 40 32 157 18 10 22 50
2-Mar-07
Plan 10,868 9,156 1,712 242 14 8 5 2 6 3 14 15 2 1 19 27 39 49 203 19 10 9 38
9-Mar-07
Actual 10,935 8,775 2,160 243 26 12 4 1 5 2 9 12 3 20 29 42 30 195 18 10 20 48
9-Mar-07
FABRICATION OF SCDR-A TOPSIDES

Plan 10,668 9,036 1,632 237 12 7 5 2 6 3 20 20 2 1 36 25 28 35 201 18 11 8 36


16-Mar-07
Painter

Actual 11,115 8,865 2,250 247 29 15 2 4 1 5 2 10 11 3 26 27 34 28 197 17 10 23 50


16-Mar-07
Plan 10,559 8,966 1,593 235 10 7 5 2 6 3 19 20 2 1 51 22 24 27 199 13 12 10 35
Instrument (F)

23-Mar-07
Actual 11,250 9,090 2,160 250 32 14 2 2 4 2 5 2 10 12 3 1 35 24 32 22 202 15 11 22 48
23-Mar-07
Plan 11,568 10,072 1,496 257 9 8 10 7 3 9 4 21 22 2 1 47 25 28 28 224 12 13 8 33
30-Mar-07
Actual 11,565 9,450 2,115 257 30 14 3 4 5 2 6 2 11 12 3 1 37 27 31 22 210 14 11 22 47 30-Mar-07
Plan 10,442 9,025 1,417 232 8 7 7 11 7 4 9 5 17 19 2 2 29 22 27 23 201 10 15 6 31
6-Apr-07
Actual 12,060 10,035 2,025 268 31 17 5 5 7 2 8 2 12 14 2 1 40 25 31 21 223 13 11 21 45 6-Apr-07

Plan 13,020 11,285 1,735 289 10 10 13 13 7 11 6 4 27 27 1 2 33 29 31 28 251 9 19 10 39


13-Apr-07
Architectural

Actual 12,915 11,025 1,890 287 29 22 11 6 8 5 10 3 14 17 4 2 41 24 29 20 245 11 10 21 42 13-Apr-07


Mechanical Tech

Plan 13,311 11,550 1,761 296 11 8 13 13 7 11 9 18 31 31 1 1 30 27 24 22 257 8 20 11 39


20-Apr-07
Actual 13,500 11,430 2,070 300 32 20 11 6 10 6 10 5 17 20 3 2 42 22 28 20 254 10 11 25 46 20-Apr-07

Plan 13,630 12,087 1,543 303 11 7 13 20 12 27 10 22 30 29 1 1 24 24 19 18 269 6 17 11 34


27-Apr-07
Actual 13,005 10,980 2,025 289 34 18 12 5 10 6 10 5 17 20 3 2 41 20 22 19 244 10 11 24 45 27-Apr-07

Plan 10,821 9,549 1,272 240 7 6 16 18 10 29 10 26 19 18 1 1 4 17 15 14 212 4 14 10 28


HVAC

4-May-07
Actual 11,565 9,765 1,800 257 30 20 13 5 8 4 9 5 15 17 3 2 34 19 16 17 217 9 10 21 40 4-May-07

Plan 14,350 12,751 1,599 319 6 7 25 15 12 47 13 47 24 23 1 1 5 21 19 17 283 5 16 15 36


Mechanical Fitter

11-May-07
Actual 11,205 9,405 1,800 249 27 22 13 8 8 4 9 5 16 17 3 2 21 20 20 14 209 9 10 21 40 11-May-07

Plan 14,234 12,821 1,413 316 4 7 14 9 14 58 15 61 22 20 1 1 7 17 14 11 285 5 12 15 31


18-May-07
Actual 11,340 9,495 1,845 252 24 21 13 7 9 8 9 10 17 18 3 2 17 16 21 16 211 9 10 22 41 18-May-07

Plan 14,698 13,048 1,650 327 4 4 5 12 9 16 62 16 63 23 21 3 5 5 16 10 8 290 5 20 12 37


25-May-07
11,835 2,025 2 23 25 12 9 9 14 9 17 5 18 25 10 7 9 10 26 25-May-07
Actual 13,860 308 17 20 23 18 263 45
Plan 11,410 10,050 1,360 254 4 2 2 10 8 14 57 9 37 18 18 5 8 4 12 5 4 223 3 17 10 30
1-Jun-07 1-Jun-07
Actual 13,770 11,790 1,980 306 4 27 23 12 8 9 13 9 16 5 19 24 11 7 15 21 22 17 262 9 10 25 44
Plan 14,184 12,751 1,433 315 5 3 3 12 9 18 69 11 41 21 22 14 17 2 18 6 6 283 3 17 12 32
8-Jun-07 8-Jun-07
Actual 13,320 11,430 1,890 296 6 24 20 12 8 10 14 9 16 6 18 23 11 7 15 22 20 13 254 9 10 23 42
Plan 13,818 12,622 1,196 307 13 3 2 16 9 14 48 11 37 6 20 22 21 23 2 21 4 4 280 3 12 12 27
15-Jun-07 15-Jun-07
Actual 13,770 11,835 1,935 306 6 25 22 12 10 10 16 9 16 6 18 25 11 7 15 22 20 13 263 9 10 24 43
Plan 11,723 10,415 1,308 261 19 2 1 20 10 10 31 6 18 9 16 20 20 24 5 18 2 2 231 3 14 12 29
22-Jun-07 22-Jun-07
Actual 14,130 12,240 1,890 314 6 24 24 12 10 10 17 9 16 8 17 24 11 8 19 23 20 14 272 9 10 23 42
Plan 10,507 9,149 1,358 233 24 2 1 15 18 9 23 6 13 9 13 16 12 21 4 16 1 2 203 3 14 13 30
29-Jun-07 29-Jun-07
Actual 13,860 12,060 1,800 308 6 21 23 12 11 10 18 9 17 8 17 24 11 8 17 22 20 14 268 9 10 21 40
Plan 11,457 9,940 1,517 255 8 21 33 3 2 9 19 3 8 4 11 10 20 21 10 16 3 17 1 2 221 3 16 15 34
6-Jul-07 6-Jul-07
Actual 13,905 12,105 1,800 309 7 6 22 22 11 10 10 17 9 18 8 16 22 11 8 17 21 20 14 269 9 10 21 40
Plan 9,712 8,507 1,205 216 12 2 40 2 2 8 9 2 3 4 12 8 17 18 10 16 4 14 189 3 19 5 27
13-Jul-07 13-Jul-07
Actual 13,680 11,925 1,755 304 2 5 7 21 22 11 10 9 18 10 20 8 16 21 10 9 12 21 19 14 265 9 10 20 39
Plan 9,621 8,364 1,257 214 12 41 3 3 7 9 1 3 3 10 8 15 14 11 18 2 14 186 3 20 5 28
20-Jul-07 20-Jul-07
Actual 12,915 11,160 1,755 287 2 13 20 20 11 10 9 18 10 20 8 14 19 12 9 9 18 16 10 248 9 10 20 39
Plan 10,204 9,418 786 227 12 45 3 4 8 2 6 3 13 8 18 16 15 25 2 18 209 3 10 5 17 27-Jul-07
27-Jul-07
Actual 12,870 11,205 1,665 286 4 14 19 18 9 8 10 17 12 21 9 14 17 17 10 8 17 15 10 249 8 9 20 37
Plan 10,914 10,448 466 243 12 51 2 4 2 6 2 8 8 16 13 43 31 1 19 232 3 2 5 10 3-Aug-07
3-Aug-07
Actual 11,745 10,080 1,665 261 4 20 17 12 3 4 7 17 8 16 9 13 16 17 12 8 17 14 10 224 8 9 20 37
Plan 9,124 8,783 341 203 15 46 1 3 1 4 0 0 8 11 8 59 21 13 195 1 1 5 8 10-Aug-07
BHD.

10-Aug-07
Actual 10,350 8,775 1,575 230 4 20 17 12 2 2 7 16 6 11 9 12 14 14 7 8 14 12 8 195 7 8 20 35
Plan 7,524 7,191 333 167 13 23 51 0 1 6 2 2 47 10 5 160 1 6 7 17-Aug-07
17-Aug-07
Actual 8,955 7,470 1,485 199 4 20 15 10 1 1 6 12 5 9 7 9 10 12 7 8 10 12 8 166 6 7 20 33
Plan 1,690 1,416 274 38 24 2 4 1 31 1 5 6 24-Aug-07
24-Aug-07
Actual 8,235 6,885 1,350 183 4 18 14 12 1 1 6 12 5 9 7 9 10 7 4 6 8 12 8 153 6 4 20 30
Plan 1,425 1,425 - 32 22 10 32 31-Aug-07
31-Aug-07
Actual 7,515 6,300 1,215 167 16 16 12 12 5 10 5 6 6 7 8 5 4 6 6 10 6 140 4 3 20 27
MALAYSIA MARINE AND HEAVY ENGINEERING SDN.

Plan 2,231 2,231 - 50 50 50 7-Sep-07


7-Sep-07
Actual 5,850 5,085 765 130 20 12 10 12 4 6 4 5 4 4 3 3 2 4 4 10 6 113 2 1 14 17
Plan - - - 14-Sep-07
14-Sep-07
Actual 4,455 3,780 675 99 25 4 8 6 2 4 2 4 2 4 3 1 1 4 4 6 4 84 2 1 12 15
Plan - - - 21-Sep-07
21-Sep-07
Actual 2,520 1,845 675 56 4 6 2 1 3 1 3 2 2 2 1 1 4 2 4 3 41 2 1 12 15
28-Sep-07
28-Sep-07
Actual 1,440 765 675 32 4 3 1 1 1 1 2 1 2 1 17 2 1 12 15
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 4 - PROGRESS CALCULATION LEVEL-IV


SCDR-A TOPSIDES ##### ###### 12-Oct-07
Activity Break Down Level IV
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN
g g j p
p
p
Fabrication of SCDR-A Topsides & Existing E11K-A Platform 100.00 19-Jul-06 04-Sep-07 424,227 100.00 100.00 100.00 100.00 0.00
PRELIMINARIES 6.61 19-Jul-06 23-Aug-07 28,043 100.00 100.00 100.00 100.00 0.00
Construction Facilities 2.17 19-Jul-06 05-Jul-07 9,209 % Comp 100.00 100.00 100.00 100.00 0.00
PRE1130 Set-up Contractor's Facilities 0.28 19-Jul-06 06-Dec-06 1,200 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
PRE1170 Facilities for 3rd Parties 1.36 07-Feb-07 05-Jul-07 5,760 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
PRE1180 Set-up SSB's site Office and Facilities 0.28 19-Jul-06 18-Dec-06 1,200 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
PRE1210 Set-up EDMS system, including lease line. 0.08 07-Oct-06 12-Jan-07 320 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
PRE1220 Set-up Completion Management System 0.07 07-Oct-06 09-Mar-07 285 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
PRE1430 Set-up Video conferencing Facilities 0.03 07-Oct-06 06-Nov-06 134 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
PRE1440 Welder Qualification Test 0.07 12-Oct-06 28-Dec-06 310 Physical 100% 0 100.00 100.00 100.00 100.00 100.00 0.00
No. of Personel
Project Management 1.13 01-Aug-06 15-May-07 4,789 Mobilized 100.00 100.00 100.00 100.00 0.00
100%
PRE1450 Mobilise Project Management Team, Supervision and Staff 0.87 01-Aug-06 20-Dec-06 3,675 Nos. 100% 40 40 100.00 100.00 100.00 100.00 0.00
PRE1690 Mobilise Pre-Commissioning Team 0.26 07-Apr-07 15-May-07 1,114 Nos. 100% 35 35 100.00 100.00 100.00 100.00 0.00
Procedures Preparation 1.03 01-Aug-06 06-Jul-07 4,365 Prepare Submitted Approved 100.00 100.00 100.00 100.00 0.00
30% 60% 10%
PRE1480 Prepare/Submit/Approve Planning Package 0.15 01-Aug-06 31-Oct-06 649 % Compl 100% 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRE1490 Prepare/Submit/Approve HSE Procedures 0.16 01-Aug-06 06-Nov-06 695 % Compl 100% 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- HSE Manual % Compl 50% 1 1 1 1 100.00
- Project HSE Plan % Compl 50% 1 1 1 1 100.00
PRE1500 Prepare/Submit/Approve QA/QC Procedures 0.16 01-Aug-06 06-Nov-06 695 % Compl 100% 21 21 21 21 100.00 100.00 100.00 100.00 0.00
- Site Project Quality Plan % Compl 5% 1 1 1 1 100.00
- Welder Qualification & Testing Procedure % Compl 5% 1 1 1 1 100.00
- Post Weld Heat Treatment (PWHT) Procedure % Compl 5% 1 1 1 1 100.00
- Weld Distortion Control Procedure % Compl 5% 1 1 1 1 100.00
- Weld Repair & Buttering Procedure % Compl 5% 1 1 1 1 100.00
- Welding Consumable Control Procedure % Compl 5% 1 1 1 1 100.00
- WPS Procedure for Structural % Compl 5% 1 1 1 1 100.00
- WPS Procedure for Piping % Compl 5% 1 1 1 1 100.00
- Standard NDT Procedure % Compl 5% 1 1 1 1 100.00
- Fairing Procedure % Compl 5% 1 1 1 1 100.00
- Leveling & Dimensional Control Proc. % Compl 5% 1 1 1 1 100.00
- Control of Non Conformance Product Procedure % Compl 5% 1 1 1 1 100.00
- Document Control Procedure % Compl 5% 1 1 1 1 100.00
- ITP for Structural % Compl 5% 1 1 1 1 100.00
- ITP for Piping % Compl 5% 1 1 1 1 100.00
- ITP for Blasting & Painting % Compl 5% 1 1 1 1 100.00
- ITP for Mechanical % Compl 5% 1 1 1 1 100.00
- ITP for Instrumentation % Compl 5% 1 1 1 1 100.00
- ITP for Electrical % Compl 5% 1 1 1 1 100.00
- Radiograph Safety and Emergency Procedure % Compl 5% 1 1 1 1 100.00
- Positive Material Identification % Compl 5% 1 1 1 1 100.00
PRE1510 Prepare/Submit/Approve Engineering Procedures 0.19 01-Aug-06 02-Jan-07 797 % Compl 100% 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Engineering Control Procedure % Compl 25% 1 1 1 1 100.00
- Weight Control Procedure % Compl 25% 1 1 1 1 100.00
- General Lifting Procedure % Compl 25% 1 1 1 1 100.00
- Loadout and Seafastening Procedure % Compl 25% 1 1 1 1 100.00
PRE1520 Prepare/Submit/Approve Weighing Procedures 0.07 25-Jan-07 05-Apr-07 278 % Compl 100% 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRE1670 Prepare/Submit/Approve Fabrication Procedures 0.20 01-Aug-06 25-Jan-07 834 % Compl 100% 18 18 18 18 100.00 100.00 100.00 100.00 0.00
- Project Execution Plan % Compl 6% 1 1 1 1 100.00
- Planning & Control Procedure % Compl 6% 1 1 1 1 100.00
- Structural Fabrication & Erection Procedure % Compl 6% 1 1 1 1 100.00
- Piping Fabrication & Erection Procedure % Compl 6% 1 1 1 1 100.00
- Electrical And Instrumentation Installation Procedure % Compl 6% 1 1 1 1 100.00
- Mechanical Equipment Installation Procedure % Compl 6% 1 1 1 1 100.00
- Surface Preparation, Painting and Repair/B/P Procedure % Compl 6% 1 1 1 1 100.00
- Hydrotest / Flushing & Reinstatement Procedure % Compl 6% 1 1 1 1 100.00
- Valve Leak Test Procedure % Compl 6% 1 1 1 1 100.00
- Chemical Cleaning Procedure % Compl 6% 1 1 1 1 100.00
- Contract Administration & Change Order Procedure % Compl 6% 1 1 1 1 100.00
- Fabrication and Installation of GRE Piping % Compl 6% 1 1 1 1 100.00
- Bolt Tensioning Procedure % Compl 6% 1 1 1 1 100.00
- Inspection & Maintenance of Lifting Equipment Procedure % Compl 6% 1 1 1 1 100.00
- Insulation Procedure % Compl 6% 1 1 1 1 100.00
- Scaffolding Installation Procedure % Compl 6% 1 1 1 1 100.00
- Duplex Fabrication Procedure % Compl 6% 1 1 1 1 100.00

1 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

- Coating System Qualification Test Procedure % Compl 6% 1 1 1 1 100.00


PRE1680 Prepare/Submit/Approve Precomm Procedures 0.10 24-Apr-07 06-Jul-07 417 % Compl 100% 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Instrument Calibration Procedure % Compl 25% 1 1 1 1 100.00
- Lube Oil Flushing Procedure % Compl 25% 1 1 1 1 100.00
- Reinstatement Leak Test Procedure % Compl 25% 1 1 1 1 100.00
- Testing and Precommissioning Procedure % Compl 25% 1 1 1 1 100.00
Insurance & Bond 0.16 21-Sep-06 21-Feb-07 695 Submitted Accepted 100.00 100.00 100.00 100.00 0.00
90% 10%
PRE1530 Submit/Accept Performance Bond 0.05 21-Sep-06 18-Nov-06 218 % Compl 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRE1540 Submit/Accept Insurances 0.05 21-Sep-06 16-Oct-06 227 % Compl 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRE1550 Submit/Accept CIDB Tax 0.06 21-Sep-06 21-Feb-07 250 % Compl 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
Final Documentations 0.75 07-May-07 23-Aug-07 3,200 Prepare Submitted Approved 100.00 100.00 100.00 100.00 0.00
70% 20% 10%
PRE1560 Prepare & Submit Final Documentation (Manual/Closeout Report/ 0.75 07-May-07 23-Aug-07 3,200 % Compl 100% 1 1 1 1 100.00 100.00 100.00 100.00 0.00
Sub-Contractors Selection 1.07 01-Aug-06 10-Aug-07 4,545 Prepare Subcon Pkg Tender Evaluation Approved 100.00 100.00 100.00 100.00 0.00
50% 40% 10%
PRE1260 Prepare Tender/Evaluate for STRUCTURAL Subcontractor 0.17 01-Aug-06 11-Oct-06 720 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1270 Prepare Tender/Evaluate for BLASTING & PAINTING Subcontractor 0.08 26-Sep-06 05-Dec-06 360 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1280 Prepare Tender/Evaluate for PIPING Subcontractor 0.17 06-Oct-06 05-Jan-07 710 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1290 Prepare Tender/Evaluate for MECHANICAL Subcontractor 0.10 23-Oct-06 13-Jan-07 420 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1300 Prepare Tender/Evaluate for ELECTRICAL Subcontractor 0.14 17-Nov-06 20-Feb-07 610 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1310 Prepare Tender/Evaluate for INSTRUMENT Subcontractor 0.14 17-Nov-06 20-Feb-07 610 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1320 Prepare Tender/Evaluate for ARCHITECTURAL Subcontractor 0.08 02-Jan-07 16-Mar-07 325 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1330 Prepare Tender/Evaluate for HVAC Subcontractor 0.06 06-Oct-06 15-Nov-06 235 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1405 Prepare Tender/Evaluate for GRE PIPING Subcontractor 0.05 27-Jan-07 17-Mar-07 220 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1505 Prepare Tender/Evaluate for WEIGHING Subcontractor 0.04 27-Apr-07 25-Jun-07 175 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1605 Prepare Tender/Evaluate for LOAD-OUT Subcontractor 0.04 18-Jun-07 10-Aug-07 160 % Compl 100% 1 100% 100% 100% 100.00 100.00 100.00 100.00 0.00
Award Sub-Contractor & Mobilization 0.29 11-Oct-06 18-Aug-07 1,240 Award Mobilized 100.00 100.00 100.00 100.00 0.00
90% 10%
PRE1265 Award & Mobilization of STRUCTURAL Subcontractor 0.03 11-Oct-06 19-Oct-06 120 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1275 Award & Mobilization of BLASTING & PAINTING Subcontractor 0.03 05-Dec-06 13-Dec-06 110 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1285 Award & Mobilization of PIPING Subcontractor 0.03 05-Jan-07 13-Jan-07 120 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1295 Award & Mobilization of MECHANICAL Subcontractor 0.03 13-Jan-07 22-Jan-07 110 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1305 Award & Mobilization of ELECTRICAL Subcontractor 0.03 20-Feb-07 28-Feb-07 120 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1315 Award & Mobilization of INSTRUMENT Subcontractor 0.03 20-Feb-07 28-Feb-07 120 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1325 Award & Mobilization of ARCHITECTURAL Subcontractor 0.03 16-Mar-07 24-Mar-07 110 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1335 Award & Mobilization of HVAC Subcontractor 0.03 15-Nov-06 23-Nov-06 120 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1355 Award & Mobilization of GRE PIPING Subcontractor 0.03 17-Mar-07 26-Mar-07 110 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1365 Award & Mobilization of WEIGHING Subcontractor 0.02 25-Jun-07 02-Jul-07 100 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
PRE1375 Award & Mobilization of LOAD-OUT Subcontractor 0.02 10-Aug-07 18-Aug-07 100 % Compl 100% 1 100% 100% 100.00 100.00 100.00 100.00 0.00
ENGINEERING 7.53 04-Aug-06 06-Aug-07 31,954 100.00 100.00 100.00 100.00 0.00
Review Materials 1.22 04-Aug-06 02-Jan-07 5,183 Prepare MTO Submitted Approved 100.00 100.00 100.00 100.00 0.00
60% 20% 20%
PRE1340 Prepare/Submit/Approve of STRUCTURAL MTO 0.18 04-Aug-06 08-Nov-06 762 Nos. 100% 15 15 15 15 100.00 100.00 100.00 100.00 0.00
PRE1341 Prepare/Submit/Approve of PIPING MTO 0.23 04-Aug-06 02-Dec-06 967 Nos. 100% 15 15 15 15 100.00 100.00 100.00 100.00 0.00
PRE1342 Prepare/Submit/Approve of MECHANICAL MTO 0.16 04-Aug-06 27-Oct-06 660 Nos. 100% 35 35 35 35 100.00 100.00 100.00 100.00 0.00
PRE1343 Prepare/Submit/Approve of ELECTRICAL MTO 0.22 04-Aug-06 27-Nov-06 920 Nos. 100% 19 19 19 19 100.00 100.00 100.00 100.00 0.00
PRE1344 Prepare/Submit/Approve of INSTRUMENT MTO 0.22 04-Aug-06 27-Nov-06 920 Nos. 100% 29 29 29 29 100.00 100.00 100.00 100.00 0.00
PRE1345 Prepare/Submit/Approve of ARCHITECTURAL MTO 0.11 18-Oct-06 18-Dec-06 477 Nos. 100% 2 2 2 2 100.00 100.00 100.00 100.00 0.00
PRE1346 Prepare/Submit/Approve of HVAC MTO 0.11 23-Nov-06 02-Jan-07 477 Nos. 100% 25 25 25 25 100.00 100.00 100.00 100.00 0.00
Construction Drawings 6.31 04-Aug-06 06-Aug-07 26,771 Prepare Shop Dwg Submitted Approved 100.00 100.00 100.00 100.00 0.00
60% 20% 20%
PRE1350 Prepare/Submit/Approve STRUCTURAL Shop Drawings 1.04 04-Aug-06 23-Feb-07 4,393 Nos. 100% 234 234 234 234 100.00 100.00 100.00 100.00 0.00
- IFA Shop Drawings Nos. 25% 24 24 24 24 100.00
- IFC Shop Drawings Nos. 25% 138 138 138 138 100.00
- IFA Shop Drawings (NDT) Nos. 25% 36 36 36 36 100.00
- IFC Shop Drawings (NDT) Nos. 25% 36 36 36 36 100.00
PRE1360 Prepare/Submit/Approve PIPING Shop Drawings 1.19 04-Aug-06 13-Mar-07 5,040 Nos. 100% 989 989 989 989 100.00 100.00 100.00 100.00 0.00
- IFA Shop Drawings Nos. 50% 391 391 391 391 100.00
- IFC Shop Drawings Nos. 50% 598 598 598 598 100.00
PRE1370 Prepare/Submit/Approve MECHANICAL Shop Drawings 0.64 02-Oct-06 02-Mar-07 2,717 Nos. 100% 107 107 107 107 100.00 100.00 100.00 100.00 0.00
- IFA Shop Drawings Nos. 50% 40 40 40 40 100.00
- IFC Shop Drawings Nos. 50% 67 67 67 67 100.00
PRE1380 Prepare/Submit/Approve ELECTRICAL Shop Drawings 0.86 18-Oct-06 02-Apr-07 3,650 Nos. 100% 694 694 694 694 100.00 100.00 100.00 100.00 0.00
- IFA Shop Drawings Nos. 50% 347 347 347 347 100.00
- IFC Shop Drawings Nos. 50% 347 347 347 347 100.00
PRE1390 Prepare/Submit/Approve INSTRUMENT Shop Drawings 0.82 18-Oct-06 07-Apr-07 3,491 Nos. 100% 1798 1798 1798 1798 100.00 100.00 100.00 100.00 0.00
- IFA Shop Drawings Nos. 50% 899 899 899 899 100.00
- IFC Shop Drawings Nos. 50% 899 899 899 899 100.00
PRE1400 Prepare/Submit/Approve ARCHITECTURAL Shop Drawings 0.52 30-Dec-06 23-Apr-07 2,215 Nos. 100% 22 22 22 22 100.00 100.00 100.00 100.00 0.00
- IFA Shop Drawings Nos. 50% 11 11 11 11 100.00

2 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

- IFC Shop Drawings Nos. 50% 11 11 11 11 100.00


PRE1410 Prepare/Submit/Approve HVAC Shop Drawings 0.43 13-Dec-06 17-Mar-07 1,824 Nos. 100% 59 59 59 59 100.00 100.00 100.00 100.00 0.00
PRE1420 Prepare/Submit/Approve AS-BUILT Drawings 0.55 29-Mar-07 06-Aug-07 2,349 Nos. 100% 2186 2186 2186 2186 100.00 100.00 100.00 100.00 0.00
- As-built drawings for Structural + NDT Nos. 26% 174 174 174 174 100.00
- As-built drawings for Piping Nos. 20% 598 598 598 598 100.00
- As-built drawings for Mechanical Nos. 12% 90 90 90 90 100.00
- As-built drawings for Electrical Nos. 15% 355 355 355 355 100.00
- As-built drawings for Instrument Nos. 15% 899 899 899 899 100.00
- As-built drawings for Architectural Nos. 5% 11 11 11 11 100.00
- As-built drawings for HVAC Nos. 7% 59 59 59 59 100.00
PRE1720 Prepare/Submit/Approve SEAFASTENING Drawings 0.26 01-Mar-07 28-May-07 1,092 Nos. 100% 12 12 12 12 100.00 100.00 100.00 100.00 0.00
PROCUREMENT 8.30 07-Aug-06 23-Aug-07 35,196 100.00 100.00 100.00 100.00 0.00
Client Supply Materils 0.71 17-Aug-06 23-Aug-07 3,017 Delivered to Site Accepted 100.00 100.00 100.00 100.00 0.00
80% 20%
PRO1000 Rec'v/Accept Structural Steel : Type I and II Plates 0.04 17-Aug-06 05-Sep-06 180 Nos. 100% 34 34 34 100.00 100.00 100.00 100.00 0.00
PRO1010 Rec'v/Accept Structural Steel : Type I and II Beams 0.04 17-Aug-06 05-Sep-06 180 Nos. 100% 175 175 175 100.00 100.00 100.00 100.00 0.00
PRO1020 Rec'v/Accept Structural Steel : Type I and II Round Tubulars 0.04 17-Aug-06 05-Sep-06 180 Nos. 100% 71 71 71 100.00 100.00 100.00 100.00 0.00
PRO1030 Rec'v/Accept All Ball Valves : Manual & Actuated Valves 2" (CS,Du 0.04 02-Apr-07 19-Apr-07 190 Nos. 100% 207 207 207 100.00 100.00 100.00 100.00 0.00
PRO1040 Rec'v/Accept Motor Operated Valves 0.03 02-Apr-07 19-Apr-07 140 Nos. 100% 3 3 3 100.00 100.00 100.00 100.00 0.00
PRO1050 Rec'v/Accept Distributed Control System (DCS) & Audio Visual Aid 0.05 04-Apr-07 21-Apr-07 200 Nos. 100% 90 90 90 100.00 100.00 100.00 100.00 0.00
PRO1060 Rec'v/Accept IPS, FGS and Wellhead Control System (WHCS) 0.07 04-Apr-07 21-Apr-07 300 Nos. 100% 9 9 9 100.00 100.00 100.00 100.00 0.00
PRO1070 Rec'v/Accept AC Uninterruptible Power Supply (UPS) 0.05 09-Apr-07 25-Apr-07 220 Nos. 100% 22 22 22 100.00 100.00 100.00 100.00 0.00
PRO1080 Rec'v/Accept 400V Switchboard 0.05 09-Apr-07 25-Apr-07 200 Nos. 100% 8 8 8 100.00 100.00 100.00 100.00 0.00
PRO1090 Rec'v/Accept Telecommunication Equipment 0.04 18-Apr-07 05-May-07 180 Nos. 100% 31 31 31 100.00 100.00 100.00 100.00 0.00
PRO1100 Rec'v/Accept Wellhead Desander Skids 0.09 18-May-07 05-Jun-07 400 Nos. 100% 5 5 5 100.00 100.00 100.00 100.00 0.00
PRO1110 Rec'v/Accept Wet Gas Metering Skid (Operational Metering) 0.05 01-Jun-07 19-Jun-07 200 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO1120 Rec'v/Accept 14" CS Pipeline (pipeline spools, bends, major & min 0.03 30-Jun-07 17-Jul-07 147 Nos. 100% 8 8 8 100.00 100.00 100.00 100.00 0.00
PRO1130 Rec'v/Accept Seafastening Mat'l, Lifting Slings and Shackles 0.03 07-Aug-07 23-Aug-07 120 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO1140 Rec'v/Accept Fittings & Accessories for Subsea Cable Conection 0.04 03-Jul-07 20-Jul-07 180 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
MMHE Supply Materials 7.59 07-Aug-06 08-Aug-07 32,179 100.00 100.00 100.00 100.00 0.00
Purchase Request to Purchase Order 3.96 07-Aug-06 08-Feb-07 16,796 PR RFQ BCD TBE PO 100.00 100.00 100.00 100.00 0.00
Structural 0.75 11-Sep-06 19-Dec-06 3,167 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1600 PR/PO of Structural Tubulars 0.11 11-Sep-06 30-Oct-06 475 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Secondary Pipes (Type III) Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO1610 PR/PO of Structural Beams 0.11 15-Sep-06 06-Nov-06 470 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Secondary Beam (Type III) Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Monorail Beam Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO1620 PR/PO of Structural Plates 0.11 22-Sep-06 15-Nov-06 460 Comt'd Qty 50% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Deck Plating Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO1630 PR/PO of Ancillary Steel (grating, stair tread, etc.) 0.11 07-Oct-06 30-Nov-06 451 Comt'd Qty 100% 5 5 5 5 5 5 100.00 100.00 100.00 100.00 0.00
- Grating Materials Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Handrail Materials Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Flatbars and Kickplates Round Bar Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Stair Materials Comt'd Qty 20% 1 1 1 1 1 1 100.00
- T-6700 Structural Scope Materials Comt'd Qty 20% 1 1 1 1 1 1 100.00
PRO1640 PR/PO of Miscellaneous Sections (angles, chanels, SHS etc.) 0.12 29-Sep-06 24-Nov-06 526 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Angles and Channels (Type III) Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Deck Drain Materials Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO1650 PR/PO of Fire/Blast Walls 0.07 16-Oct-06 11-Dec-06 300 Comt'd Qty 100% 3 3 3 3 3 3 100.00 100.00 100.00 100.00 0.00
- Wall Platings & Wall Angular Support Comt'd Qty 33% 1 1 1 1 1 1 100.00
- Wall Cladding Comt'd Qty 33% 1 1 1 1 1 1 100.00
- Fire/Blast Walls Comt'd Qty 33% 1 1 1 1 1 1 100.00
PRO1660 PR/PO of Passive Fire Projection (PFP) 0.06 19-Oct-06 16-Dec-06 270 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1670 PR/PO of All Remaining Structural Mat'l 0.05 23-Oct-06 19-Dec-06 215 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Temp. Support Materials Comt'd Qty 100% 2 2 2 2 2 2 100.00
Piping 0.84 07-Sep-06 27-Dec-06 3,544 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1690 PR/PO of Carbon Steel (CS) Pipes & Fitting 0.12 07-Sep-06 04-Nov-06 500 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Carbon Steel Pipes Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO1700 PR/PO of Stainless Steel (SS) Pipes & Fitting 0.10 11-Sep-06 11-Nov-06 420 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- SS and DSS Pipes Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO1710 PR/PO of Duplex Stainless Steel (DSS) Pipes & Fitting 0.17 13-Sep-06 22-Nov-06 704 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Flange CS / Duplex / SS Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Fitting CS / Duplex / SS Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO1720 PR/PO of GRE Pipes & Fitting 0.08 22-Sep-06 11-Nov-06 360 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- GRE Pipes & Fittings Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO1730 PR/PO of Valves 0.14 16-Sep-06 05-Dec-06 580 Comt'd Qty 100% 5 5 5 5 5 5 100.00 100.00 100.00 100.00 0.00
- Ball Valves Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Ball Valves for GRE lines Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Globe, Gate & Check Valves Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Check Valves for GRE lines Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Double Block & Bleed Valve Comt'd Qty 20% 1 1 1 1 1 1 100.00

3 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

PRO1740 PR/PO of Piping Specialty Items 0.06 03-Oct-06 23-Nov-06 260 Comt'd Qty 80% 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Gasket Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Studbolt with Nuts Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Pipe Support Mat'l Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Pipe Support - U-Bolts/Clamps Comt'd Qty 20% 1 1 1 1 1 1 100.00
PRO1750 PR/PO of Pipe Bends & Barred Tees 0.07 03-Oct-06 28-Nov-06 280 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Reduced Barred Tee Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO1760 PR/PO of Associated Fittings & Acc. for Launcher 0.06 18-Oct-06 18-Dec-06 260 Comt'd Qty 100% 5 5 5 5 5 5 100.00 100.00 100.00 100.00 0.00
- Launcher (L-2900) & Receiver (L-2960) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Pig Trap End Closure (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Eccentric Reducer (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Weldolet (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Welding Neck Flanges (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
PRO1770 PR/PO of All Remaining Piping Mat'l 0.04 27-Oct-06 27-Dec-06 180 Comt'd Qty 100% 5 5 5 5 5 5 100.00 100.00 100.00 100.00 0.00
- All Remaining Materials Comt'd Qty 100% 5 5 5 5 5 5 100.00
Mechanical 0.62 07-Aug-06 16-Nov-06 2,615 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1780 PR/PO of Flush Water Tank 0.04 12-Aug-06 30-Oct-06 160 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1790 PR/PO of Fresh Water Tank 0.04 12-Aug-06 30-Oct-06 160 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1800 PR/PO of Closed Drain Vessel 0.04 15-Aug-06 13-Oct-06 175 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1810 PR/PO of Condensate Pod 0.04 15-Aug-06 11-Oct-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1820 PR/PO of Diesel Transfer Pump 0.03 24-Aug-06 28-Oct-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1830 PR/PO of Open Drain Caisson Pump 0.03 23-Aug-06 19-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1840 PR/PO of Flush Water Pump 0.03 22-Aug-06 20-Oct-06 130 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1850 PR/PO of Fresh Water Pump 0.03 22-Aug-06 20-Oct-06 130 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1860 PR/PO of Closed Drain Transfer Pump 0.03 23-Aug-06 19-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1870 PR/PO of All Remaining Pumps 0.03 26-Aug-06 06-Nov-06 120 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1880 PR/PO of HP Vent Tip 0.03 17-Aug-06 03-Nov-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1890 PR/PO of CO2 Vent Snuffing System 0.03 17-Aug-06 03-Nov-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1900 PR/PO of Manual Operated Trolley Hoists 0.03 21-Aug-06 07-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1910 PR/PO of Padestal Crane 0.07 07-Aug-06 02-Oct-06 280 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1920 PR/PO of Swing Jib Cranes with Manual Operated Hoist 0.03 21-Aug-06 17-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1930 PR/PO of Corrosion Inhibitor Injection Package 0.05 18-Aug-06 17-Oct-06 200 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1940 PR/PO of All Remaining Mechanical Items 0.04 29-Aug-06 16-Nov-06 150 Comt'd Qty 100% 6 6 6 6 6 6 100.00 100.00 100.00 100.00 0.00
- Corrosion Probe and Coupon Assembly Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Chemical Injection and Sampling Conection Fitting Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Y-Type Strainers Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Spring Hangers Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Bird Screens Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Sight Glasses Comt'd Qty 17% 1 1 1 1 1 1 100.00
Electrical 0.60 12-Aug-06 09-Jan-07 2,530 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1960 PR/PO of Power Transformer 0.08 12-Aug-06 30-Oct-06 340 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1970 PR/PO of 6.6KV Ring Main Unit 0.07 18-Aug-06 14-Nov-06 300 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1980 PR/PO of LV Distribution Board 0.07 18-Aug-06 14-Nov-06 300 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1990 PR/PO of Powered Navigational Aids System 0.04 18-Oct-06 29-Dec-06 160 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2000 PR/PO of Cable Trays, Ladder & Accessories 0.05 11-Sep-06 14-Nov-06 200 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Cable Ladder / Tray & Accessories Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO2010 PR/PO of Electrical / Control Cables, Fitting & MCT's 0.07 29-Aug-06 08-Nov-06 300 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Cables (Power & Control, AC/DC UPS, Lighting & Small Power). Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Multicable Transit (MCT) & Accessories Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO2020 PR/PO of Junction Boxes and Control Panels 0.04 22-Sep-06 15-Dec-06 180 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Interposing Relay Panel Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO2030 PR/PO of Remote Control Units and Safety Switches 0.05 14-Oct-06 30-Dec-06 210 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Socket, Plug & Switches Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Remote Control Station Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO2040 PR/PO of Light Fitting, Photocells Mounting and Accessories 0.07 29-Sep-06 21-Dec-06 300 Comt'd Qty 100% 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Fluorescent, Exit Light & Floodlights Lighting Fixture Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Power & Lighting Junction Boxes Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Lighting Poles Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Beacon AOL Photocell Comt'd Qty 25% 1 1 1 1 1 1 100.00
PRO2050 PR/PO of Earthing Accessories 0.03 02-Nov-06 15-Dec-06 120 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2060 PR/PO of All Other Electrical Items 0.03 10-Nov-06 09-Jan-07 120 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Electrical Steel Mat'l Comt'd Qty 100% 2 2 2 2 2 2 100.00
Instrument 0.90 21-Aug-06 19-Dec-06 3,837 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO2070 PR/PO of Wellhead Control Panel 0.05 24-Aug-06 11-Nov-06 200 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2080 PR/PO of Sand Monitoring System 0.03 13-Sep-06 17-Nov-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2090 PR/PO of GPA/PAPA 0.04 07-Sep-06 11-Nov-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2100 PR/PO of Restriction Orifice Plates 0.03 31-Oct-06 12-Dec-06 128 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2110 PR/PO of Orifice Plates 0.03 31-Oct-06 12-Dec-06 128 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2120 PR/PO of Ultrasonic Flowmeters 0.04 26-Aug-06 28-Oct-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2130 PR/PO of Level Gauges (Reflex Type) 0.03 14-Oct-06 29-Nov-06 138 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2140 PR/PO of Level Gauges (Using Pressure Gauge) 0.03 14-Oct-06 29-Nov-06 138 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00

4 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

PRO2150 PR/PO of Pressure Gauges 0.03 20-Sep-06 14-Nov-06 145 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2160 PR/PO of Choke Valves 0.07 29-Aug-06 08-Nov-06 300 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2170 PR/PO of Pig Signallers 0.03 28-Oct-06 04-Dec-06 130 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2180 PR/PO of IR Flame Detector 0.03 02-Nov-06 12-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2190 PR/PO of IR Point Gas Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2200 PR/PO of IR Open Path Gas Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2210 PR/PO of Smoke Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2220 PR/PO of Hydrogen Gas Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2230 PR/PO of ESD Break Glass Station 0.03 08-Nov-06 11-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2240 PR/PO of Acoustic Leak Detector 0.03 02-Nov-06 11-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2250 PR/PO of Heat Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2260 PR/PO of Control, Ball and Operated Valves 0.05 21-Aug-06 07-Nov-06 220 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2270 PR/PO of Ultra Sonic Flare Gas Meter 0.04 23-Aug-06 02-Nov-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2280 PR/PO of Field Instrument & Mounting Stands & Supports etc. 0.03 16-Sep-06 08-Nov-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2290 PR/PO of Cable Tray & Ladders 0.04 22-Sep-06 18-Nov-06 151 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2300 PR/PO of Instrument Cable, Junction Boxes & MCT's 0.03 19-Sep-06 14-Nov-06 140 Comt'd Qty 100% 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Instrument Cables Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Cable Glands Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Junction Boxes Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Multicable Transit (MCT) & Accessories Comt'd Qty 25% 1 1 1 1 1 1 100.00
PRO2310 PR/PO of Instrument Tubing, Fittings & Valves 0.03 28-Sep-06 22-Nov-06 148 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2320 PR/PO of All Remaining Instrumentation Items 0.04 10-Nov-06 19-Dec-06 183 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
Architectural 0.08 24-Nov-06 06-Jan-07 352 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1680 PR/PO of Architectural Mat'l (floor/wall/ceiling panels, doors and w 0.08 24-Nov-06 06-Jan-07 352 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Doors, Frames and Accessories Comt'd Qty 100% 1 1 1 1 1 1 100.00
HVAC 0.08 11-Dec-06 15-Jan-07 321 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1950 PR/PO of HVAC System Package 0.08 11-Dec-06 15-Jan-07 321 Comt'd Qty 100% 10 10 10 10 10 10 100.00 100.00 100.00 100.00 0.00
Safety 0.07 29-Nov-06 29-Jan-07 300 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO2330 PR/PO of Safety Equipment and Fire Protection Equipment 0.05 02-Dec-06 29-Jan-07 200 Comt'd Qty 100% 15 15 15 15 15 15 100.00 100.00 100.00 100.00 0.00
- Flexible Hose and Hose Coupling Conection Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Hosereels Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Fire Extinguishers Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Liftraft Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Lifejackets Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Lifejacket Containers Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Knotted Rope Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Ring Life Buoy Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Safety Shower & Self-Contained Eyewash Station Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Helicopter Crash Box & Cabinet Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Fireman's Equipment Comt'd Qty 7% 1 1 1 1 1 1 100.00
- First Aid Kit Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Smoke Hoods and Container Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Breathing Apparatus Set and Cabinet Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Firewater Monitor Comt'd Qty 7% 1 1 1 1 1 1 100.00
PRO2340 PR/PO of Safety Signs 0.02 29-Nov-06 04-Jan-07 100 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Safety Signs Comt'd Qty 100% 1 1 1 1 1 1 100.00
Others Materials 0.03 02-Dec-06 08-Feb-07 130 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO2350 PR/PO of Any Other Materials not included above 0.03 02-Dec-06 08-Feb-07 130 Comt'd Qty 100% 10 10 10 10 10 10 100.00 100.00 100.00 100.00 0.00
Purchase Order to Delivery 0.00 03-Oct-06 23-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
Structural 0.00 30-Oct-06 04-Apr-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2360 PO to Del of Structural Tubulars 0.00 30-Oct-06 29-Nov-06 - Linear 100% 0.00 0.00 0.00 0.00
PRO2370 PO to Del of Structural Beams 0.00 07-Nov-06 12-Dec-06 - Linear 100% 0.00 0.00 0.00 0.00
PRO2380 PO to Del of Structural Plates 0.00 15-Nov-06 30-Dec-06 - Linear 100% 0.00 0.00 0.00 0.00
PRO2390 PO to Del of Ancillary Steel (grating, stair tread, etc.) 0.00 30-Nov-06 27-Jan-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2400 PO to Del of Miscellaneous Sections (angles, chanels, SHS etc.) 0.00 24-Nov-06 10-Jan-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2410 PO to Del of Fire/Blast Walls 0.00 11-Dec-06 13-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2420 PO to Del of Passive Fire Projection (PFP) 0.00 16-Dec-06 04-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2430 PO to Del of All Remaining Structural Mat'l 0.00 19-Dec-06 14-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
Piping 0.00 06-Nov-06 30-May-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2450 PO to Del of Carbon Steel (CS) Pipes & Fitting 0.00 06-Nov-06 15-Jan-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2460 PO to Del of Stainless Steel (SS) Pipes & Fitting 0.00 11-Nov-06 13-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2470 PO to Del of Duplex Stainless Steel (DSS) Pipes & Fitting 0.00 22-Nov-06 26-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2480 PO to Del of GRE Pipes & Fitting 0.00 11-Nov-06 28-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2490 PO to Del of Valves 0.00 18-Dec-06 04-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2500 PO to Del of Piping Specialty Items 0.00 11-Dec-06 23-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2510 PO to Del of Pipe Bends & Barred Tees 0.00 19-Dec-06 30-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2520 PO to Del of Associated Fittings & Acc. for Launcher 0.00 05-Jan-07 27-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2530 PO to Del of All Remaining Piping Mat'l 0.00 27-Dec-06 12-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
Mechanical 0.00 03-Oct-06 23-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2540 PO to Del of Flush Water Tank 0.00 30-Oct-06 17-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2550 PO to Del of Fresh Water Tank 0.00 30-Oct-06 28-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00

5 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

PRO2560 PO to Del of Closed Drain Vessel 0.00 13-Oct-06 04-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2570 PO to Del of Condensate Pod 0.00 11-Oct-06 04-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2580 PO to Del of Diesel Transfer Pump 0.00 28-Oct-06 26-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2590 PO to Del of Open Drain Caisson Pump 0.00 19-Oct-06 30-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2600 PO to Del of Flush Water Pump 0.00 20-Oct-06 21-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2610 PO to Del of Fresh Water Pump 0.00 20-Oct-06 21-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2620 PO to Del of Closed Drain Transfer Pump 0.00 19-Oct-06 09-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2630 PO to Del of All Remaining Pumps 0.00 07-Nov-06 13-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2640 PO to Del of HP Vent Tip 0.00 03-Nov-06 01-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2650 PO to Del of CO2 Vent Snuffing System 0.00 03-Nov-06 01-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2660 PO to Del of Manual Operated Trolley Hoists 0.00 07-Oct-06 22-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2670 PO to Del of Padestal Crane 0.00 03-Oct-06 12-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2680 PO to Del of Swing Jib Cranes with Manual Operated Hoist 0.00 17-Oct-06 30-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2690 PO to Del of Corrosion Inhibitor Injection Package 0.00 17-Oct-06 14-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2700 PO to Del of All Remaining Mechanical Items 0.00 16-Nov-06 23-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
Electrical 0.00 30-Oct-06 10-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2720 PO to Del of Power Transformer 0.00 30-Oct-06 10-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2730 PO to Del of 6.6KV Ring Main Unit 0.00 14-Nov-06 14-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2740 PO to Del of LV Distribution Board 0.00 14-Nov-06 04-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2750 PO to Del of Powered Navigational Aids System 0.00 29-Dec-06 18-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2760 PO to Del of Cable Trays, Ladder & Accessories 0.00 14-Nov-06 15-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2770 PO to Del of Electrical / Control Cables, Fitting & MCT's 0.00 09-Nov-06 28-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2780 PO to Del of Junction Boxes and Control Panels 0.00 15-Dec-06 07-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2790 PO to Del of Remote Control Units and Safety Switches 0.00 30-Dec-06 25-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2800 PO to Del of Light Fitting, Photocells Mounting and Accessories 0.00 21-Dec-06 26-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2810 PO to Del of Earthing Accessories 0.00 15-Dec-06 13-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2820 PO to Del of All Other Electrical Items 0.00 10-Jan-07 22-May-07 - Linear 100% 0.00 0.00 0.00 0.00
Instrument 0.00 28-Oct-06 29-Jun-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2830 PO to Del of Wellhead Control Panel 0.00 11-Nov-06 03-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2840 PO to Del of Sand Monitoring System 0.00 17-Nov-06 20-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2850 PO to Del of GPA/PAPA 0.00 11-Nov-06 21-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2860 PO to Del of Restriction Orifice Plates 0.00 12-Dec-06 17-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2870 PO to Del of Orifice Plates 0.00 12-Dec-06 23-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2880 PO to Del of Ultrasonic Flowmeters 0.00 28-Oct-06 27-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2890 PO to Del of Level Gauges (Reflex Type) 0.00 29-Nov-06 09-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2900 PO to Del of Level Gauges (Using Pressure Gauge) 0.00 29-Nov-06 09-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2910 PO to Del of Pressure Gauges 0.00 14-Nov-06 06-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2920 PO to Del of Choke Valves 0.00 09-Nov-06 29-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2930 PO to Del of Pig Signallers 0.00 04-Dec-06 14-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2940 PO to Del of IR Flame Detector 0.00 12-Dec-06 28-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2950 PO to Del of IR Point Gas Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2960 PO to Del of IR Open Path Gas Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2970 PO to Del of Smoke Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2980 PO to Del of Hydrogen Gas Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2990 PO to Del of ESD Break Glass Station 0.00 11-Dec-06 10-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3000 PO to Del of Acoustic Leak Detector 0.00 11-Dec-06 27-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3010 PO to Del of Heat Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3020 PO to Del of Control, Ball and Operated Valves 0.00 08-Nov-06 04-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3030 PO to Del of Ultra Sonic Flare Gas Meter 0.00 02-Nov-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3040 PO to Del of Field Instrument & Mounting Stands & Supports etc. 0.00 09-Nov-06 26-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3050 PO to Del of Cable Tray & Ladders 0.00 18-Nov-06 07-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3060 PO to Del of Instrument Cable, Junction Boxes & MCT's 0.00 14-Nov-06 16-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3070 PO to Del of Instrument Tubing, Fittings & Valves 0.00 22-Nov-06 20-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3080 PO to Del of All Remaining Instrumentation Items 0.00 19-Dec-06 13-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
Architectural 0.00 08-Jan-07 12-Mar-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2440 PO to Del of Architectural Mat'l (floor/wall/ceiling panels, doors an 0.00 08-Jan-07 12-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
HVAC 0.00 15-Jan-07 12-Mar-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2710 PO to Del of HVAC System Package 0.00 15-Jan-07 12-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
Safety 0.00 04-Jan-07 09-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO3090 PO to Del of Safety Equipment and Fire Protection Equipment 0.00 29-Jan-07 09-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3100 PO to Del of Safety Signs 0.00 04-Jan-07 21-May-07 - Linear 100% 0.00 0.00 0.00 0.00
Others Materials 0.00 08-Feb-07 16-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO3110 PO to Del of Any Other Materials not included above 0.00 08-Feb-07 16-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
Materials Receiving Inspection 3.63 29-Nov-06 08-Aug-07 15,383 Delivered to Site Accepted 100.00 100.00 100.00 100.00 0.00
Structural 0.55 29-Nov-06 20-Apr-07 2,322 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3120 Receive/Accept of Structural Tubulars 0.09 29-Nov-06 14-Dec-06 400 Nos. 100% 111 111 111 100.00 100.00 100.00 100.00 0.00
- Secondary Pipes Type III (PR #68) Nos. 100% 111 111 111 100.00
PRO3130 Receive/Accept of Structural Beams 0.09 12-Dec-06 03-Jan-07 384 Nos. 100% 335 335 335 100.00 100.00 100.00 100.00 0.00
- Secondary Beam Type III (PR #66) Nos. 90% 329 329 329 100.00
- Monorail Beam Type III (PR #67) Nos. 10% 6 6 6 100.00
PRO3140 Receive/Accept of Structural Plates 0.07 30-Dec-06 20-Jan-07 288 Nos. 100% 168 168 168 100.00 100.00 100.00 100.00 0.00
- Deck Plating (PR #121) Nos. 100% 168 168 168 100.00

6 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

PRO3150 Receive/Accept of Ancillary Steel (grating, stair tread, etc.) 0.06 27-Jan-07 15-Feb-07 270 Nos. 100% 9449 9449 9449 100.00 100.00 100.00 100.00 0.00
- Grating and Clips Materials (PR #112) Nos. 17% 7722 7722 7722 100.00
- Handrail Materials (PR #129) Nos. 17% 554 554 554 100.00
- Flatbars and Kickplates Round Bar (PR #130) Nos. 17% 143 143 143 100.00
- Stair Tread (PR #131) Nos. 17% 716 716 716 100.00
- T-6700 Structural Scope Materials (PR #134) Nos. 17% 34 34 34 100.00
- Hex Bolt and Nuts (PR #129) Nos. 17% 280 280 280 100.00
PRO3160 Receive/Accept of Miscellaneous Sections (angles, chanels, SHS e 0.06 11-Jan-07 31-Jan-07 275 Nos. 100% 216 216 216 100.00 100.00 100.00 100.00 0.00
- Channels Type III (PR #111) Nos. 25% 4 4 4 100.00
- Angles Type III (PR #111) Nos. 25% 129 129 129 100.00
- SHS (PR #111) Nos. 25% 15 15 15 100.00
- Deck Drain Materials (PR #139) Nos. 25% 68 68 68 100.00
PRO3170 Receive/Accept of Fire/Blast Walls 0.06 13-Mar-07 03-Apr-07 240 Nos. 100% 423 423 423 100.00 100.00 100.00 100.00 0.00
- Wall Platings & Angular Support CHL & AGL (PR #117) Nos. 40% 209 209 209 100.00
- Wall Cladding (PR #197) Nos. 30% 140 140 140 100.00
- Fire/Blast Walls (PR #179) Nos. 30% 74 74 74 100.00
PRO3180 Receive/Accept of Passive Fire Projection (PFP) 0.05 04-Apr-07 20-Apr-07 220 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3190 Receive/Accept of All Remaining Structural Mat'l (PR #98/166/151/ 0.06 14-Feb-07 09-Mar-07 245 Nos. 100% 27 27 27 100.00 100.00 100.00 100.00 0.00
Piping 0.59 15-Jan-07 18-Jun-07 2,517 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3210 Receive/Accept of Carbon Steel (CS) Pipes & Fitting 0.09 15-Jan-07 14-Feb-07 400 Nos. 100% 475 475 475 100.00 100.00 100.00 100.00 0.00
- Carbon Steel Pipes (PR #42) Nos. 60% 58 58 58 100.00
- Flange CS (PR #56) Nos. 20% 168 168 168 100.00
- Fitting CS (PR #59) Nos. 20% 249 249 249 100.00
PRO3220 Receive/Accept of Stainless Steel (SS) Pipes & Fitting 0.07 13-Feb-07 10-Mar-07 288 Nos. 100% 10034 10034 10034 100.00 100.00 100.00 100.00 0.00
- SS Pipes (PR #52) Nos. 60% 93 93 93 100.00
- Flange SS (PR #56) Nos. 10% 227 227 227 100.00
- Fitting SS (PR #59) Nos. 10% 341 341 341 100.00
- Gasket (PR #71) Nos. 5% 1166 1166 1166 100.00
- Studbolt with Nuts (PR #78) Nos. 5% 7339 7339 7339 100.00
- Pipe Support Mat'l (PR #79) Nos. 5% 155 155 155 100.00
- Pipe Support - U-Bolts/Clamps (PR #142) Nos. 5% 713 713 713 100.00
PRO3230 Receive/Accept of Duplex Stainless Steel (DSS) Pipes & Fitting 0.10 17-May-07 07-Jun-07 410 Nos. 50% 1955 1955 1955 100.00 100.00 100.00 100.00 0.00
- DSS Pipes (PR #52) Nos. 50% 904 904 904 100.00
- Flange Duplex SS (PR #56) Nos. 25% 411 411 411 100.00
- Fitting Duplex SS (PR #59) Nos. 25% 640 640 640 100.00
PRO3240 Receive/Accept of GRE Pipes & Fitting 0.06 28-Feb-07 26-Mar-07 270 Nos. 100% 1626 1626 1626 100.00 100.00 100.00 100.00 0.00
- GRE Pipes & Fittings (PR #65) Nos. 100% 1626 1626 1626 100.00
PRO3250 Receive/Accept of Valves 0.10 04-May-07 31-May-07 420 Nos. 100% 116 116 116 100.00 100.00 100.00 100.00 0.00
- Ball Valves (PR #32) Nos. 20% 5 5 5 100.00
- Ball Valves for GRE lines (PR #33) Nos. 20% 3 3 3 100.00
- Globe, Gate & Check Valves (PR #38) Nos. 20% 74 74 74 100.00
- Check Valves for GRE lines (PR #39) Nos. 20% 3 3 3 100.00
- Double Block & Bleed Valve (PR #41) Nos. 20% 31 31 31 100.00
PRO3260 Receive/Accept of Piping Specialty Items (PR #20&23) 0.04 23-Mar-07 14-Apr-07 154 Nos. 100% 45 45 45 100.00 100.00 100.00 100.00 0.00
PRO3270 Receive/Accept of Pipe Bends & Barred Tees 0.04 30-May-07 18-Jun-07 175 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
- Reduced Barred Tee (PR #10) Nos. 100% 1 1 1 100.00
PRO3280 Receive/Accept of Associated Fittings & Acc. for Launcher 0.04 27-Apr-07 17-May-07 190 Nos. 100% 45 45 45 100.00 100.00 100.00 100.00 0.00
- Pig Launcher & Receiver (PR #40) Nos. 20% 1 1 1 100.00
- Pig Trap End Closure (Launcher Material) (PR #34) Nos. 20% 2 2 2 100.00
- Eccentric Reducer (Launcher Material) (PR #35) Nos. 20% 2 2 2 100.00
- Weldolet (Launcher Material) (PR #36) Nos. 20% 19 19 19 100.00
- Welding Neck Flanges (Launcher Material) (PR #37) Nos. 20% 21 21 21 100.00
PRO3290 Receive/Accept of All Remaining Piping Mat'l 0.05 12-Apr-07 09-May-07 210 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Mechanical 0.94 28-Apr-07 08-Aug-07 3,967 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3300 Receive/Accept of Flush Water Tank 0.05 17-May-07 01-Jun-07 220 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3310 Receive/Accept of Fresh Water Tank 0.06 28-Apr-07 12-May-07 240 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3320 Receive/Accept of Closed Drain Vessel 0.10 04-Jul-07 17-Jul-07 420 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3330 Receive/Accept of Condensate Pod 0.08 04-Jun-07 16-Jun-07 320 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3340 Receive/Accept of Diesel Transfer Pump 0.04 26-Jun-07 07-Jul-07 175 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3350 Receive/Accept of Open Drain Caisson Pump 0.04 30-May-07 13-Jun-07 180 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3360 Receive/Accept of Flush Water Pump 0.04 21-Jun-07 03-Jul-07 150 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3370 Receive/Accept of Fresh Water Pump 0.04 21-Jun-07 03-Jul-07 150 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3380 Receive/Accept of Closed Drain Transfer Pump 0.04 09-Jun-07 25-Jun-07 180 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3390 Receive/Accept of All Remaining Pumps 0.03 13-Jul-07 28-Jul-07 142 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3400 Receive/Accept of HP Vent Tip 0.05 01-Jul-07 14-Jul-07 200 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3410 Receive/Accept of CO2 Vent Snuffing System 0.04 01-Jul-07 13-Jul-07 150 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3420 Receive/Accept of Manual Operated Trolley Hoists 0.03 23-May-07 09-Jun-07 120 Nos. 100% 4 4 4 100.00 100.00 100.00 100.00 0.00
PRO3430 Receive/Accept of Padestal Crane 0.13 12-Jul-07 25-Jul-07 540 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3440 Receive/Accept of Swing Jib Cranes with Manual Operated Hoist 0.05 30-Apr-07 17-May-07 210 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3450 Receive/Accept of Corrosion Inhibitor Injection Package 0.11 14-Jun-07 28-Jun-07 450 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00

7 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

PRO3460 Receive/Accept of All Remaining Mechanical Items 0.03 23-Jul-07 08-Aug-07 120 Nos. 100% 32 32 32 100.00 100.00 100.00 100.00 0.00
- Corrosion Probe and Coupon Assembly (PR #25) Nos. 17% 4 4 4 100.00
- Chemical Injection and Sampling Conection Fitting (PR #21) Nos. 17% 14 14 14 100.00
- Y-Type Strainers (PR #23) Nos. 17% 5 5 5 100.00
- Spring Hangers (PR #26) Nos. 17% 5 5 5 100.00
- Bug Screens (PR #27) Nos. 17% 3 3 3 100.00
- Sight Glasses (PR #24) Nos. 17% 1 1 1 100.00
Electrical 0.51 15-Feb-07 19-Jul-07 2,147 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3480 Receive/Accept of Power Transformer 0.09 10-Jul-07 19-Jul-07 400 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3490 Receive/Accept of 6.6KV Ring Main Unit 0.08 14-Jun-07 01-Jul-07 360 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3500 Receive/Accept of LV Distribution Board 0.04 04-Apr-07 23-Apr-07 175 Nos. 100% 8 8 8 100.00 100.00 100.00 100.00 0.00
PRO3510 Receive/Accept of Powered Navigational Aids System 0.03 18-May-07 01-Jun-07 110 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3520 Receive/Accept of Cable Trays, Ladder & Accessories 0.05 15-Feb-07 05-Mar-07 200 Nos. 100% 2669 2669 2669 100.00 100.00 100.00 100.00 0.00
- Cable Ladder & Accessories (PR #58 & #80) Nos. 35% 1711 1711 1711 100.00
- Cable Tray & Accessories (PR #58) Nos. 35% 940 940 940 100.00
- Cable Gland & Accessories (PR #53) Nos. 30% 18 18 18 100.00
PRO3530 Receive/Accept of Electrical / Control Cables, Fitting & MCT's 0.05 28-Mar-07 14-Apr-07 210 Nos. 100% 862 862 862 100.00 100.00 100.00 100.00 0.00
- Cables (Pwr & Ctrl, AC/DC UPS, Lighting & Small Power) (PR #18) Nos. 50% 8 8 8 100.00
- Multicable Transit (MCT) & Accessories (PR #116) Nos. 50% 854 854 854 100.00
PRO3540 Receive/Accept of Junction Boxes and Control Panels 0.03 07-Apr-07 25-Apr-07 140 Nos. 100% 3 3 3 100.00 100.00 100.00 100.00 0.00
- Interposing Relay Panel (PR #17) Nos. 75% 2 2 2 100.00
- Power Junction Boxes (PR #76) Nos. 25% 1 1 1 100.00
PRO3550 Receive/Accept of Remote Control Units and Safety Switches 0.03 25-Apr-07 14-May-07 130 Nos. 100% 68 68 68 100.00 100.00 100.00 100.00 0.00
- Socket, Plug & Switches (PR #75) Nos. 50% 61 61 61 100.00
- Remote Control Units (PR #114) Nos. 50% 7 7 7 100.00
PRO3560 Receive/Accept of Light Fitting, Photocells Mounting and Accesso 0.05 30-Mar-07 26-Apr-07 210 Nos. 100% 331 331 331 100.00 100.00 100.00 100.00 0.00
- Fluorescent, Exit Light & Floodlights Lighting Fixture (PR #51) Nos. 50% 197 197 197 100.00
- Lighting Junction Boxes (PR #76) Nos. 50% 134 134 134 100.00
PRO3570 Receive/Accept of Earthing Accessories 0.02 13-Mar-07 03-Apr-07 100 Nos. 100% 183 183 183 100.00 100.00 100.00 100.00 0.00
- Earthing Cable & Cable Lug (PR #74) Nos. 100% 183 183 183 100.00
PRO3580 Receive/Accept of All Other Electrical Items 0.03 23-May-07 13-Jun-07 112 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Instrument 0.82 07-Feb-07 18-Jul-07 3,460 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3590 Receive/Accept of Wellhead Control Panel 0.14 03-Apr-07 25-Apr-07 600 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3600 Receive/Accept of Sand Monitoring System 0.02 21-Apr-07 08-May-07 90 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3610 Receive/Accept of GPA/PAPA 0.03 21-Mar-07 16-Apr-07 140 Nos. 100% 88 88 88 100.00 100.00 100.00 100.00 0.00
PRO3620 Receive/Accept of Restriction Orifice Plates 0.01 17-May-07 02-Jun-07 60 Nos. 100% 13 13 13 100.00 100.00 100.00 100.00 0.00
PRO3630 Receive/Accept of Orifice Plates 0.01 24-May-07 09-Jun-07 60 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3640 Receive/Accept of Ultrasonic Flowmeters 0.03 27-Feb-07 19-Mar-07 140 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3650 Receive/Accept of Level Gauges (Reflex Type) 0.02 09-Apr-07 27-Apr-07 100 Nos. 100% 5 5 5 100.00 100.00 100.00 100.00 0.00
PRO3660 Receive/Accept of Level Gauges (Using Pressure Gauge) 0.02 09-Apr-07 26-Apr-07 100 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3670 Receive/Accept of Pressure Gauges 0.02 06-Mar-07 24-Mar-07 70 Nos. 100% 18 18 18 100.00 100.00 100.00 100.00 0.00
PRO3680 Receive/Accept of Choke Valves 0.08 29-Jun-07 18-Jul-07 320 Nos. 100% 5 5 5 100.00 100.00 100.00 100.00 0.00
PRO3690 Receive/Accept of Pig Signallers 0.02 14-Mar-07 02-Apr-07 80 Nos. 100% 4 4 4 100.00 100.00 100.00 100.00 0.00
PRO3700 Receive/Accept of IR Flame Detector 0.02 28-Apr-07 12-May-07 75 Nos. 100% 23 23 23 100.00 100.00 100.00 100.00 0.00
PRO3710 Receive/Accept of IR Point Gas Detector 0.02 26-Apr-07 10-May-07 70 Nos. 100% 6 6 6 100.00 100.00 100.00 100.00 0.00
PRO3720 Receive/Accept of IR Open Path Gas Detector 0.02 26-Apr-07 10-May-07 70 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
PRO3730 Receive/Accept of Smoke Detector 0.02 26-Apr-07 09-May-07 70 Nos. 100% 27 27 27 100.00 100.00 100.00 100.00 0.00
PRO3740 Receive/Accept of Hydrogen Gas Detector 0.02 26-Apr-07 12-May-07 70 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3750 Receive/Accept of ESD Break Glass Station 0.01 10-May-07 24-May-07 60 Nos. 100% 9 9 9 100.00 100.00 100.00 100.00 0.00
PRO3760 Receive/Accept of Acoustic Leak Detector 0.02 27-Apr-07 12-May-07 80 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3770 Receive/Accept of Heat Detector 0.02 26-Apr-07 11-May-07 70 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3780 Receive/Accept of Control, Ball and Operated Valves 0.08 04-May-07 24-May-07 340 Nos. 100% 16 16 16 100.00 100.00 100.00 100.00 0.00
- Ball Valves (PR #32 & 33) Nos. 50% 8 8 8 100.00
- Operated Valves (PR #145) Nos. 50% 8 8 8 100.00
PRO3790 Receive/Accept of Ultra Sonic Flare Gas Meter 0.02 26-Apr-07 11-May-07 80 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3800 Receive/Accept of Field Instrument & Mounting Stands & Supports 0.03 26-Mar-07 19-Apr-07 140 Nos. 100% 106 106 106 100.00 100.00 100.00 100.00 0.00
PRO3810 Receive/Accept of Cable Tray & Ladders 0.04 07-Feb-07 28-Feb-07 180 Nos. 100% 2449 2449 2449 100.00 100.00 100.00 100.00 0.00
- Cable Ladder & Accessories (PR #58) Nos. 50% 1509 1509 1509 100.00
- Cable Tray & Accessories (PR #58) Nos. 50% 940 940 940 100.00
PRO3820 Receive/Accept of Instrument Cable, Junction Boxes & MCT's 0.04 16-Feb-07 14-Mar-07 160 Nos. 100% 22774 22774 22774 100.00 100.00 100.00 100.00 0.00
- Instrument Cables (PR #101) Nos. 26% 21647 21647 21647 100.00
- Cable Glands (PR #148) Nos. 20% 568 568 568 100.00
- Junction Boxes (PR #146) Nos. 20% 15 15 15 100.00
- Multicable Transit (MCT) & Accessories (PR #153) Nos. 15% 259 259 259 100.00
- Earthing Materials (PR #155) Nos. 19% 285 285 285 100.00
PRO3830 Receive/Accept of Instrument Tubing, Fittings & Valves 0.04 20-Mar-07 11-Apr-07 160 Nos. 100% 52 52 52 100.00 100.00 100.00 100.00 0.00
- Instrument Materials (PR #144) Nos. 100% 52 52 52 100.00
PRO3840 Receive/Accept of All Remaining Instrumentation Items 0.02 13-Jun-07 03-Jul-07 75 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Architectural 0.09 12-Mar-07 07-Apr-07 380 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3200 Receive/Accept of Architectural Mat'l (floor/wall/ceiling panels, d 0.09 12-Mar-07 07-Apr-07 380 Nos. 100% 47129 47129 47129 100.00 100.00 100.00 100.00 0.00
- Doors, Frames and Accessories (PR #54) Nos. 18% 9 9 9 100.00

8 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

- Ceiling & TNF Panel Nos. 18% 750 750 750 100.00
- Raise Floor Nos. 20% 400 400 400 100.00
- Copper Coated Pin Nos. 5% 22000 22000 22000 100.00
- Rockwool Nos. 16% 1200 1200 1200 100.00
- Aluminium Foil Rolls 10% 20 20 20 100.00
- Galvanize Speed Clip Nos. 4% 22000 22000 22000 100.00
- Anti Skid Paint Nos. 9% 750 750 750 100.00
HVAC 0.05 12-Mar-07 02-Apr-07 220 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3470 Receive/Accept of HVAC System Package 0.05 12-Mar-07 02-Apr-07 220 Unit 100% 60 60 60 100.00 100.00 100.00 100.00 0.00
- Condenser Fan & Motor Unit 12% 6 6 6 100.00
- DX Coil Unit 10% 4 4 4 100.00
- Compressor Unit 12% 6 6 6 100.00
- Condenser Coil Unit 12% 6 6 6 100.00
- Exhaust Fan & Motor Unit 11% 4 4 4 100.00
- Motorized Damper Unit 11% 8 8 8 100.00
- Duct Heater Unit 10% 3 3 3 100.00
- HVAC Control Panel Unit 12% 3 3 3 100.00
- Support Unit 10% 20 20 20 100.00
Safety 0.07 22-May-07 30-Jul-07 300 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3850 Receive/Accept of Safety Equipment and Fire Protection Equipme 0.06 09-Jul-07 30-Jul-07 240 Nos. 100% 131 131 131 100.00 100.00 100.00 100.00 0.00
- Flexible Hose and Hose Coupling Conection (PR #20) Nos. 8% 40 40 40 100.00
- Hosereels (PR #22) Nos. 8% 10 10 10 100.00
- Fire Extinguishers (PR #88) Nos. 8% 33 33 33 100.00
- David Liferaft and Safety Equipment (PR #93) Nos. 8% 3 3 3 100.00
- Lifejacket (PR #92) Nos. 8% 3 3 3 100.00
- Lifejacket Container (PR #92) Nos. 8% 3 3 3 100.00
- Knotted Rope (PR #91) Nos. 8% 3 3 3 100.00
- Ring Life Buoy (PR #94) Nos. 8% 20 20 20 100.00
- Safety Shower & Self-Contained Eyewash Station (PR #95) Nos. 8% 9 9 9 100.00
- First Aid Kit (PR #90) Nos. 8% 3 3 3 100.00
- Smoke Hoods and Container (PR #97) Nos. 8% 2 2 2 100.00
- Breathing Apparatus Set and Cabinet (PR #96) Nos. 8% 1 1 1 100.00
- Firewater Monitor (PR #89) Nos. 7% 1 1 1 100.00
PRO3860 Receive/Accept of Safety Signs 0.01 22-May-07 04-Jun-07 60 Nos. 100% 120 120 120 100.00 100.00 100.00 100.00 0.00
- Safety Signs (PR #107) Nos. 100% 120 120 120 100.00
Others Materials 0.02 16-Jul-07 31-Jul-07 70 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3870 Receive/Accept of Any Other Materials not included above 0.02 16-Jul-07 31-Jul-07 70 Nos. 100 100 100 100.00 100.00 100.00 100.00 0.00
FABRICATION OF SCDR-A TOPSIDES 69.20 22-Sep-06 20-Aug-07 293,578 100.00 100.00 100.00 100.00 0.00
Structural 24.10 12-Oct-06 18-Jun-07 102,218 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Fabrication 19.16 12-Oct-06 23-May-07 81,284 Pieces Joints 100.00 100.00 100.00 100.00 0.00
FAB1370 Fabricate and Arrange Temp. Supports 0.32 12-Oct-06 06-Dec-06 1,370 No. of Pcs 100% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00 100.00 100.00 100.00 0.00
- Fab. Skid Shoes W 30 x 132 Nos. 23% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Fab. Jacking Beam W 30 x 132 Nos. 23% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Fab. Transverse Jacking Beam W 36 x 210 Nos. 19% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Fab. Column 752 dia x 12.7 wt Nos. 15% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Fab. Temp. Column Support 1498 dia x 25.4 wt Nos. 10% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Fab. Temp. Column Support 1193.6 dia x 25.4 wt Nos. 10% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
FAB1380 Fab/Assem Cellar Deck (In-Situ) 5.03 14-Nov-06 21-Feb-07 21,319 No. of Pcs 100% 1646 1646 100.00 2390 2390 100.00 2390 100.00 2390 100.00 100.00 100.00 100.00 100.00 0.00
- Top Ring Plate 50mm Nos. 2% 7 7 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Bottom Ring Plate 50mm Nos. 2% 7 7 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Top Flange Plate Nos. 2% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Bottom Flange Plate Nos. 1% 1 1 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Top Insert Plate Nos. 2% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- W 36 x 210 Nos. 15% 28 28 100.00 67 67 100.00 67 100.00 67 100.00 100.00
- W 24 x 94 Nos. 13% 15 15 100.00 32 32 100.00 32 100.00 32 100.00 100.00
- W 24 x 68 Nos. 13% 99 99 100.00 200 200 100.00 200 100.00 200 100.00 100.00
- W 18 x 50 Nos. 9% 36 36 100.00 72 72 100.00 72 100.00 72 100.00 100.00
- W 12 x 35 Nos. 8% 82 82 100.00 164 164 100.00 164 100.00 164 100.00 100.00
- W 8 x 15 Nos. 10% 424 424 100.00 848 848 100.00 848 100.00 848 100.00 100.00
- Pipe 457 x 20.6 Nos. 2% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Ins. Plates / Gratings Nos. 7% 570 570 100.00 570 570 100.00 570 100.00 570 100.00 100.00
- Stiffeners Nos. 5% 347 347 100.00 347 347 100.00 347 100.00 347 100.00 100.00
- Transition Pieces (Cone 1219 x 1524 x 40 wt) Nos. 2% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Stabbing Guide (Cone 1444 x 500 x 30 wt) Nos. 3% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Stabbing Guide (Cone 1139 x 500 x 30 wt) Nos. 3% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Closure Plate 20mm x 480 dia Nos. 2% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- Spacer Plate 3mm to 1444 dia Nos. 1% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Spacer Plate 3mm to 1139 dia Nos. 1% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00

9 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

FAB1390 Fabricate Columns, Diagonals & Braces 1.12 22-Dec-06 27-Feb-07 4,748 No. of Pcs 100% 97 97 100.00 194 194 100.00 194 100.00 194 100.00 100.00 100.00 100.00 100.00 0.00
Column - 1524 dia. x 50 wt Nos. 6% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Column - 1524 dia. x 40 wt Nos. 8% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
Column - 1219 dia. x 40 wt Nos. 14% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Column - 1219 dia. x 25 wt Nos. 10% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Column - 813 dia. x 23 wt Nos. 5% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Column - 457 dia. x 16 wt Nos. 6% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
Column - 356 dia. x 13 wt Nos. 5% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
Column - 273 dia. x 13 wt Nos. 5% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
Column - 219 dia. x 13 wt Nos. 3% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Column - 168 dia. x 08 wt Nos. 4% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
Diagonal braces - 660 dia. x 25 wt Nos. 6% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
Diagonal braces - 610 dia. x 25 wt Nos. 12% 26 26 100.00 52 52 100.00 52 100.00 52 100.00 100.00
Diagonal braces - 610 dia. x 20 wt Nos. 8% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
Diagonal braces - 356 dia. x 13 wt Nos. 5% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
Diagonal braces - 219 dia. x 13 wt Nos. 3% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
FAB1400 Fabricate Main Deck 4.40 29-Dec-06 27-Mar-07 18,671 No. of Pcs 100% 1104 1030 93.30 1705 1626 95.37 1626 95.37 1626 95.37 100.00 100.00 100.00 100.00 0.00
- Top Ring Plate 50mm Nos. 2% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Bottom Ring Plate 50mm Nos. 3% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- Top Flange Plate Nos. 2% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Bottom Flange Plate Nos. 3% 7 7 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Top Insert Plate Nos. 3% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- W 36 x 210 Nos. 12% 29 29 100.00 58 58 100.00 58 100.00 58 100.00 100.00
- W 24 x 94 Nos. 13% 39 39 100.00 78 78 100.00 78 100.00 78 100.00 100.00
- W 24 x 68 Nos. 11% 70 70 100.00 140 140 100.00 140 100.00 140 100.00 100.00
- W 18 x 50 Nos. 8% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- W 12 x 35 Nos. 8% 23 23 100.00 46 46 100.00 46 100.00 46 100.00 100.00
- W 10 x 45 Nos. 7% 9 9 100.00 18 18 100.00 18 100.00 18 100.00 100.00
- W 10 x 22 Nos. 3% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- W 8 x 15 Nos. 8% 240 240 100.00 480 480 100.00 480 100.00 480 100.00 100.00
- Ins. Plates / Gratings Nos. 7% 87 87 100.00 87 87 100.00 87 100.00 87 100.00 100.00
- Stiffeners Nos. 4% 347 347 100.00 347 347 100.00 347 100.00 347 100.00 100.00
- Fab. Skid Beams Nos. 8% 196 122 62.24 323 244 75.54 244 75.54 244 75.54 100.00
- Flange Plate Nos. 1.5% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- Stopper Plate Nos. 1.0% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Web Plate 38mm Nos. 1.5% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Ring Plate 50mm Nos. 1.5% 12 12 100.00 24 24 100.00 24 100.00 24 100.00 100.00
- End Plate 38mm Nos. 0.5% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Cap Plate 38mm Nos. 0.5% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Pipe 1219 x 12 wt Nos. 0.5% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Stiffeners Plate Nos. 1.0% 64 64 100.00 128 128 100.00 128 100.00 128 100.00 100.00
FAB1410 Fabricate Mezzanine Deck 2.60 10-Jan-07 10-Mar-07 11,047 No. of Pcs 100% 878 878 100.00 1257 1257 100.00 1257 100.00 1257 100.00 100.00 100.00 100.00 100.00 0.00
- W 24 x 68 Nos. 24% 56 56 100.00 112 112 100.00 112 100.00 112 100.00 100.00
- W 18 x 50 Nos. 17% 30 30 100.00 60 60 100.00 60 100.00 60 100.00 100.00
- W 12 x 35 Nos. 18% 43 43 100.00 86 86 100.00 86 100.00 86 100.00 100.00
- W 8 x 15 Nos. 20% 150 150 100.00 300 300 100.00 300 100.00 300 100.00 100.00
- Ins. Plates / Gratings Nos. 12% 499 499 100.00 499 499 100.00 499 100.00 499 100.00 100.00
- Stiffeners Nos. 9% 100 100 100.00 200 200 100.00 200 100.00 200 100.00 100.00
FAB1420 Fabricate Stairways & Ladder 0.19 15-Feb-07 07-Apr-07 822 No. of Pcs 100% 29 29 100.00 29 29 100.00 29 100.00 29 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 30% 8 8 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Cellar Deck Nos. 40% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- Mezzanine Deck Nos. 16% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Wellhead Access Platform Nos. 9% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Intermediate Platform Nos. 5% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
FAB1430 Fabricate Handrails 0.27 05-Feb-07 29-Mar-07 1,140 No. of Pcs 100% 187 187 100.00 187 187 100.00 187 100.00 187 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 35% 51 51 100.00 51 51 100.00 51 100.00 51 100.00 100.00
- Cellar Deck Nos. 36% 70 70 100.00 70 70 100.00 70 100.00 70 100.00 100.00
- Mezzanine Deck Nos. 13% 40 40 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- Wellhead Access Platform / Wing Deck Nos. 9% 14 14 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Intermediate Platform Nos. 7% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
FAB1440 Fabricate Framing for Switchgear, ILE Rooms, W.Shelter & Worksho 1.21 24-Jan-07 15-Mar-07 5,149 No. of Pcs 100% 152 152 100.00 197 197 100.00 197 100.00 197 100.00 100.00 100.00 100.00 100.00 0.00
Roof Framing and Plating Nos. 40% 45 45 100.00 90 90 100.00 90 100.00 90 100.00 100.00
- W 18 x 50 Nos. 14% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
- W 14 x 38 Nos. 12% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- W 12 x 35 Nos. 9% 5 5 100.00 10 10 100.00 10 100.00 10 100.00 100.00
- Roof Plate 6mm Nos. 5% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Wall Framing and Plating Nos. 60% 107 107 100.00 107 107 100.00 107 100.00 107 100.00 100.00
- W 8 x 28 Nos. 17% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
- Pipe 219 x 8 wt Nos. 9% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00

10 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

- Channel 6 x 12 Nos. 11% 25 25 100.00 25 25 100.00 25 100.00 25 100.00 100.00


- Angle 75 x 75 x 8 mm Nos. 10% 30 30 100.00 30 30 100.00 30 100.00 30 100.00 100.00
- Wall Plt 4.5 mm & Blast Wall Nos. 13% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
FAB1450 Fabricate Gratings 0.19 24-Feb-07 17-Apr-07 800 No. of Pcs 100% 187 187 100.00 187 187 100.00 187 100.00 187 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 17% 51 51 100.00 51 51 100.00 51 100.00 51 100.00 100.00
- Cellar Deck Nos. 32% 70 70 100.00 70 70 100.00 70 100.00 70 100.00 100.00
- Mezzanine Deck Nos. 16% 40 40 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- Wellhead Access Platform / Wing Deck Nos. 25% 14 14 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Intermediate Platform Nos. 10% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
FAB1460 Fabricate Vent Boom 1.12 09-Mar-07 10-May-07 4,747 No. of Pcs 100% 33 33 100.00 66 66 100.00 66 100.00 66 100.00 100.00 100.00 100.00 100.00 0.00
- Pipe 406 dia x 13 wt Nos. 24% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Pipe 324 dia x 25.4 wt Nos. 20% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Pipe 324 dia x 10 wt Nos. 17% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Pipe 324 dia x 6 wt Nos. 15% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Pipe 273 dia x 6 wt Nos. 12% 12 12 100.00 24 24 100.00 24 100.00 24 100.00 100.00
- Pipe 219 dia x 6 wt Nos. 12% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
FAB1470 Fabricate Intermediate Platform 0.81 31-Jan-07 12-Mar-07 3,422 No. of Pcs 100% 153 153 100.00 306 306 100.00 306 100.00 306 100.00 100.00 100.00 100.00 100.00 0.00
- W 12 x 35 Nos. 35% 43 43 100.00 86 86 100.00 86 100.00 86 100.00 100.00
- W 8 x 15 Nos. 30% 60 60 100.00 120 120 100.00 120 100.00 120 100.00 100.00
- Plt 10 mm / Grating Nos. 15% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Pipe Braces 141 x 7 wt Nos. 20% 46 46 100.00 92 92 100.00 92 100.00 92 100.00 100.00
FAB1510 Fabricate Lifting Padeyes 0.10 02-May-07 23-May-07 433 No. of Pcs 100% 52 52 100.00 72 72 100.00 72 100.00 72 100.00 100.00 100.00 100.00 100.00 0.00
- Fab. Main Plate Nos. 47% 16 16 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Fab. Check Plate Nos. 38% 16 16 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Fab. Stiffener Plate Nos. 15% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
FAB1540 Fabricate Wellhead Access Platform 1.56 18-Jan-07 06-Mar-07 6,609 No. of Pcs 100% 159 159 100.00 318 318 100.00 318 100.00 318 100.00 100.00 100.00 100.00 100.00 0.00
- W 12 x 26 Nos. 45% 85 85 100.00 170 170 100.00 170 100.00 170 100.00 100.00
- Channel 8 x 18.75 Nos. 33% 36 36 100.00 72 72 100.00 72 100.00 72 100.00 100.00
- Pipe 114 x 6 wt Nos. 22% 38 38 100.00 76 76 100.00 76 100.00 76 100.00 100.00
FAB1760 Fabricate Crane Padestal and Boom Rest 0.24 02-Apr-07 02-May-07 1,004 No. of Pcs 100% 24 24 100.00 46 46 100.00 46 100.00 46 100.00 100.00 100.00 100.00 100.00 0.00
- Pipe 1524 dia x 50 wt (Pedestal Clumn) Nos. 28% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Pipe 610 dia x 20 wt Nos. 17% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Pipe 60 dia x 4 wt Nos. 15% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- W 12 x 53 Nos. 17% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- W 8 x 15 Nos. 10% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Plt 12 mm (Closure) Nos. 13% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Total
Done % Done % Done % Done %
Installation 4.93 05-Feb-07 18-Jun-07 20,934 Pieces Joints 100.00 100.00 100.00 100.00 0.00
FAB1480 Erect Column and Braces (on Cellar Deck) 0.83 05-Feb-07 27-Mar-07 3,520 No. of Pcs 100% 36 36 100.00 36 36 100.00 36 100.00 36 100.00 100.00 100.00 100.00 100.00 0.00
- Erect Vertical Column Deck Leg at Row A1 Nos. 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Erect Vertical Column Deck Leg at Row A2 Nos. 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Erect Vertical Column Deck Leg at Row A3 Nos. 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Erect Vertical Column Deck Leg at Row B1 Nos. 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Erect Vertical Column Deck Leg at Row B2 Nos. 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Erect Vertical Column Deck Leg at Row B3 Nos. 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Erect Vertical & Herizontal Braces at Row A Nos. 13% 10 10 100.00 10 10 100.00 10 100.00 10 100.00 100.00
- Erect Vertical & Herizontal Braces at Row B Nos. 13% 10 10 100.00 10 10 100.00 10 100.00 10 100.00 100.00
- Erect Herizontal Braces at Row 1 Nos. 5% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Erect Herizontal Braces at Row 3 Nos. 5% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Erect Vertical & Herizontal Braces at Row 3a & 4 Nos. 4% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
FAB1490 Erect Mezzanine Deck 0.79 27-Mar-07 23-Apr-07 3,342 Portion 100% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00 100.00 100.00 100.00 0.00
FAB1500 Erect Main Deck 0.90 28-Apr-07 22-May-07 3,837 No. of Pcs 100% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB1520 Install Handrails 0.21 10-Apr-07 09-May-07 890 No. of Pcs 100% 209 209 100.00 209 209 100.00 209 100.00 209 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 33% 70 70 100.00 70 70 100.00 70 100.00 70 100.00 100.00
- Cellar Deck Nos. 27% 51 51 100.00 51 51 100.00 51 100.00 51 100.00 100.00
- Mezzanine Deck Nos. 21% 40 40 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- Wellhead Access Platform / Wing Deck Nos. 11% 28 28 100.00 28 28 100.00 28 100.00 28 100.00 100.00
- Intermediate Platform Nos. 8% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
FAB1530 Install Gratings 0.16 05-Apr-07 02-May-07 658 No. of Pcs 100% 1500 1500 100.00 1500 1500 100.00 1500 100.00 1500 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 5% 50 50 100.00 50 50 100.00 50 100.00 50 100.00 100.00
- Cellar Deck Nos. 33% 514 514 100.00 514 514 100.00 514 100.00 514 100.00 100.00
- Mezzanine Deck Nos. 28% 494 494 100.00 494 494 100.00 494 100.00 494 100.00 100.00
- Wellhead Access Platform / Wing Deck Nos. 24% 369 369 100.00 369 369 100.00 369 100.00 369 100.00 100.00
- Intermediate Platform Nos. 10% 73 73 100.00 73 73 100.00 73 100.00 73 100.00 100.00
FAB1550 Install Stairways & Ladder 0.19 18-Apr-07 16-May-07 786 No. of Pcs 100% 18 18 100.00 18 18 100.00 18 100.00 18 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 10% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Cellar Deck Nos. 45% 8 8 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Mezzanine Deck Nos. 20% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Wellhead Access Platform / Wing Deck Nos. 15% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00

11 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

- Intermediate Platform Nos. 10% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00


FAB1560 Install Framing for Switchgear, ILE Rooms, W.Shelter & Workshop 0.57 29-Mar-07 28-Apr-07 2,409 Rooms 100% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00 100.00 100.00 100.00 0.00
- Battery Room Room 22% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Switchgear Room Room 38% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Instrument Local Equipment Room 30% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Weather Shelter, Workshop and Blast Wall Room 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
FAB1570 Erect Intermediate Platform 0.32 26-Mar-07 14-Apr-07 1,370 No. of Pcs 100% 3 3 100.00 3 3 100.00 3 100.00 3 100.00 100.00 100.00 100.00 100.00 0.00
FAB1580 Install Vent Boom 0.08 01-Jun-07 18-Jun-07 342 No. of Pcs 100% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB1590 Install Lifting Padeyes 0.14 24-May-07 14-Jun-07 606 No. of Pcs 100% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00 100.00 100.00 100.00 0.00
FAB1740 Erect Wellhead Access Platform 0.54 20-Mar-07 11-Apr-07 2,283 No. of Pcs 100% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB1750 Install Crane Padestal and Boom Rest 0.21 16-May-07 07-Jun-07 891 No. of Pcs 100% 3 3 100.00 3 3 100.00 3 100.00 3 100.00 100.00 100.00 100.00 100.00 0.00
- Install Crane Padestal Column Nos. 45% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Install Crane Adaptor Nos. 40% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
- Install Boom Rest Nos. 15% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Blasting/Painting 4.76 22-Sep-06 31-Jul-07 20,182 Prep B/P Accept 100.00 100.00 100.00 100.00 0.00
10% 80% 10%
FAB1600 Auto Blast/Prime Structural Mat'l Type I and II 0.45 22-Sep-06 17-Nov-06 1,928 Nos 100% 280 280 280 280 100.00 100.00 100.00 100.00 0.00
- Beam 36 Nos 5% 45 45 45 45 100.00
- Beam 24 Nos 5% 105 105 105 105 100.00
- Beam 18 Nos 5% 25 25 25 25 100.00
- Pipe 1524 (Type I & II) Nos 5% 9 9 9 9 100.00
- Pipe 1219 (Type I & II) Nos 5% 13 13 13 13 100.00
- Pipe 610 (Type I) Nos 5% 24 24 24 24 100.00
- Pipe 457 (Type I) Nos 5% 4 4 4 4 100.00
- Pipe 356 (Type I) Nos 5% 5 5 5 5 100.00
- Pipe 273 (Type I) Nos 5% 10 10 10 10 100.00
- Pipe 660 (Type I) Nos 5% 6 6 6 6 100.00
- Plate 60 x 10 x 3.05 (Grade 355EMZ) Nos 5% 1 1 1 1 100.00
- Plate 50 x 10 x 3.05 (Grade 355EMZ) Nos 5% 5 5 5 5 100.00
- Plate 38 x 10 x 3.05 (Grade 355CZ) Nos 5% 1 1 1 1 100.00
- Plate 35 x 10 x 3.05 (Grade 355CZ) Nos 5% 2 2 2 2 100.00
- Plate 25 x 10 x 3.05 (Grade 355CZ) Nos 5% 1 1 1 1 100.00
- Plate 50 x 10 x 3.05 (Grade 355C) Nos 5% 3 3 3 3 100.00
- Plate 38 x 10 x 3.05 (Grade 355C) Nos 5% 5 5 5 5 100.00
- Plate 25 x 10 x 3.05 (Grade 355C) Nos 5% 6 6 6 6 100.00
- Plate 20 x 10 x 3.05 (Grade 355C) Nos 5% 5 5 5 5 100.00
- Plate 16 x 10 x 3.05 (Grade 355C) Nos 5% 4 4 4 4 100.00
- Plate 40 x 10 x 3.05 (Grade 355C) Nos 5% 1 1 1 1 100.00
Prep B/P 1st Coat 2nd Coat 3rd Coad Accept
10% 20% 20% 20% 20% 10%
FAB1610 Blast/Paint Cellar Deck 0.54 27-Mar-07 28-Apr-07 2,279 SM 100% 5125 5125 5125 5125 5125 5125 5125 100.00 100.00 100.00 100.00 0.00
Prep B/P Accept
10% 80% 10%
FAB1620 Blast/Prime Structural Mat'l Type III 0.50 14-Dec-06 14-Mar-07 2,103 Nos. 100% 1693 1693 1693 1693 100.00 100.00 100.00 100.00 0.00
- Secondary Pipes (Type III) Nos. 17% 129 129 129 129 100.00
- Secondary Beam (Type III) Nos. 21% 373 373 373 373 100.00
- Monorail Beam Nos. 3% 6 6 6 6 100.00
- Deck Plating Nos. 15% 121 121 121 121 100.00
- Handrail Materials Nos. 4% 187 187 187 187 100.00
- Flatbars and Kickplates Round Bar Nos. 5% 129 129 129 129 100.00
- Stair Tread Nos. 5% 338 338 338 338 100.00
- Channels (Type III) Nos. 10% 108 108 108 108 100.00
- Angles (Type III) Nos. 12% 202 202 202 202 100.00
- SHS Nos. 8% 100 100 100 100 100.00
Prep B/P 1st Coat 2nd Coat Final Coat Accept
10% 20% 20% 20% 20% 10%
FAB1630 Blast/Paint Pipe Supports 0.39 31-Jan-07 27-Mar-07 1,643 Nos. 100% 510 510 510 510 510 510 510 100.00 100.00 100.00 100.00 0.00
FAB1640 Blast/Paint Mezzanine Deck 0.25 10-Mar-07 27-Mar-07 1,074 SM 100% 1297 1297 1297 1297 1297 1297 1297 100.00 100.00 100.00 100.00 0.00
FAB1650 Blast/Paint Main Deck 0.44 27-Mar-07 26-Apr-07 1,855 SM 100% 4114 4114 4114 4114 4114 4114 4114 100.00 100.00 100.00 100.00 0.00
FAB1660 Blast/Paint Electrical Supports 0.14 15-Mar-07 02-Apr-07 614 Nos. 100% 348 348 348 348 348 348 348 100.00 100.00 100.00 100.00 0.00
FAB1670 Blast/Paint Framing for Switchgear, ILE Rooms, W.Shelter & Worksho 0.19 15-Mar-07 29-Mar-07 818 SM 100% 720 720 720 720 720 720 720 100.00 100.00 100.00 100.00 0.00
FAB1680 Blast/Paint Instrument Supports 0.14 15-Mar-07 02-Apr-07 614 Nos. 100% 280 280 280 280 280 280 280 100.00 100.00 100.00 100.00 0.00
FAB1690 Blast/Paint Stairways & Ladder 0.09 07-Apr-07 24-Apr-07 380 Nos. 100% 17 17 17 17 17 17 17 100.00 100.00 100.00 100.00 0.00
FAB1700 Blast/Paint Handrails 0.10 02-Apr-07 19-Apr-07 409 Nos. 100% 175 175 175 175 175 175 175 100.00 100.00 100.00 100.00 0.00
FAB1710 Blast/Paint Pipe Spools 0.41 28-Feb-07 11-Apr-07 1,738 Nos. 100% 137 137 137 137 137 137 137 100.00 100.00 100.00 100.00 0.00
FAB1720 Blast/Paint Vent Boom 0.12 10-May-07 01-Jun-07 497 SM 100% 784 784 784 784 784 784 784 100.00 100.00 100.00 100.00 0.00
FAB1730 Blast/Paint Lifting Padeyes 0.05 14-Jun-07 27-Jun-07 219 Nos. 100% 4 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
FAB1770 Blast/Paint Crane Padestal and Boom Rest 0.06 02-May-07 16-May-07 263 SM 100% 180 180 180 180 180 180 180 100.00 100.00 100.00 100.00 0.00
FAB1780 Blast/Paint Wellhead Access Platform 0.18 06-Mar-07 20-Mar-07 745 SM 100% 331 331 331 331 331 331 331 100.00 100.00 100.00 100.00 0.00
FAB1790 Blast/Paint Intermediate Platform 0.12 12-Mar-07 26-Mar-07 511 SM 100% 481 481 481 481 481 481 481 100.00 100.00 100.00 100.00 0.00

12 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

Touch-Up Accept
90% 10%
FAB2110 Touch-Up Painting 0.23 11-Apr-07 31-Jul-07 986 SM 100% 2600 2600 2600 100.00 100.00 100.00 100.00 0.00
PFP/BW Accept
90% 10%
FAB2120 Apply Passive Fire Proofing 0.12 01-Jun-07 15-Jun-07 526 Pcs 100% 100 100 100 100.00 100.00 100.00 100.00 0.00
FAB2130 Apply Fire/Blast Walls 0.23 10-May-07 01-Jun-07 980 Pcs 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Piping 15.04 13-Jan-07 15-Aug-07 63,793 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Dia Total Dia
Done % Done % Done % Done %
Fabrication 5.38 13-Jan-07 31-Jul-07 22,831 Inch Inch 100.00 100.00 100.00 100.00 0.00
FAB2100 Fabricate Pipe Supports 0.67 13-Jan-07 28-Mar-07 2,830 Dia Inch 100% 510 510 100.00 555 555 100.00 555 100.00 555 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 11% 110 110 100.00 110 110 100.00 110 100.00 110 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 19% 90 90 100.00 90 90 100.00 90 100.00 90 100.00 100.00
- Mezzanine Deck Dia Inch 48% 200 200 100.00 245 245 100.00 245 100.00 245 100.00 100.00
- Main Deck Dia Inch 22% 110 110 100.00 110 110 100.00 110 100.00 110 100.00 100.00
FAB2630 Fabricate CS Pipe Spools 1.69 14-Feb-07 25-Apr-07 7,163 Dia Inch 100% 1796 1796 100.00 1796 1796 100.00 1796 100.00 1796 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 18% 330 330 100.00 330 330 100.00 330 100.00 330 100.00 100.00
- Mezzanine Deck Dia Inch 68% 1214 1214 100.00 1214 1214 100.00 1214 100.00 1214 100.00 100.00
- Cellar Deck Dia Inch 11% 198 198 100.00 198 198 100.00 198 100.00 198 100.00 100.00
- Main Deck Dia Inch 3% 54 54 100.00 54 54 100.00 54 100.00 54 100.00 100.00
FAB2840 Fabricate SS Pipe Spools 0.81 10-Mar-07 03-May-07 3,423 Dia Inch 100% 1300 1300 100.00 1300 1300 100.00 1300 100.00 1300 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 28% 357 357 100.00 357 357 100.00 357 100.00 357 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 21% 285 285 100.00 285 285 100.00 285 100.00 285 100.00 100.00
- Mezzanine Deck Dia Inch 31% 400 400 100.00 400 400 100.00 400 100.00 400 100.00 100.00
- Main Deck Dia Inch 20% 258 258 100.00 258 258 100.00 258 100.00 258 100.00 100.00
FAB2850 Fabricate DSS Pipe Spools 1.02 07-Jun-07 31-Jul-07 4,337 Dia Inch 100% 5985 5985 100.00 5985 5985 100.00 5985 100.00 5985 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 5% 477 477 100.00 477 477 100.00 477 100.00 477 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 17% 1027 1027 100.00 1027 1027 100.00 1027 100.00 1027 100.00 100.00
- Mezzanine Deck Dia Inch 78% 4481 4481 100.00 4481 4481 100.00 4481 100.00 4481 100.00 100.00
FAB2860 Fabricate GRE Pipe Spools 0.73 26-Mar-07 15-May-07 3,104 Dia Inch 100% 5876 5876 100.00 5876 5876 100.00 5876 100.00 5876 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 22% 1388 1388 100.00 1388 1388 100.00 1388 100.00 1388 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 20% 1137 1137 100.00 1137 1137 100.00 1137 100.00 1137 100.00 100.00
- Mezzanine Deck Dia Inch 40% 2326 2326 100.00 2326 2326 100.00 2326 100.00 2326 100.00 100.00
- Main Deck Dia Inch 18% 1025 1025 100.00 1025 1025 100.00 1025 100.00 1025 100.00 100.00
FAB2870 Fabricate Piping Specialty Items 0.47 14-Apr-07 28-May-07 1,974 Dia Inch 100% 620 620 100.00 620 620 100.00 620 100.00 620 100.00 100.00 100.00 100.00 100.00 0.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Dia Total Dia
Done % Done % Done % Done %
Installation 9.66 24-Jan-07 15-Aug-07 40,964 Inch Inch 100.00 100.00 100.00 100.00 0.00
FAB2820 Install Pipe Supports Below Cellar Deck 0.59 24-Jan-07 12-Mar-07 2,510 Nos. 100% 203 203 100.00 203 203 100.00 203 100.00 203 100.00 100.00 100.00 100.00 100.00 0.00
FAB2830 Install CS Pipe Spools 1.56 08-Mar-07 22-May-07 6,627 Nos. 100% 412 412 100.00 412 412 100.00 412 100.00 412 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 14% 57 57 100.00 57 57 100.00 57 100.00 57 100.00 100.00
- Mezzanine Deck Nos. 79% 325 325 100.00 325 325 100.00 325 100.00 325 100.00 100.00
- Cellar Deck Nos. 7% 30 30 100.00 30 30 100.00 30 100.00 30 100.00 100.00
FAB2880 Install SS Pipe Spools 0.90 06-Apr-07 14-May-07 3,798 Nos. 100% 302 302 100.00 302 302 100.00 302 100.00 302 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 12% 54 54 100.00 54 54 100.00 54 100.00 54 100.00 100.00
- Cellar Deck & Switchgear/LER Nos. 17% 65 65 100.00 65 65 100.00 65 100.00 65 100.00 100.00
- Mezzanine Deck Nos. 36% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00
- Main Deck Nos. 35% 83 83 100.00 83 83 100.00 83 100.00 83 100.00 100.00
FAB2890 Install DSS Pipe Spools 1.38 30-Jun-07 11-Aug-07 5,861 Nos. 100% 1150 1150 100.00 1150 1150 100.00 1150 100.00 1150 100.00 100.00 100.00 100.00 100.00 0.00
- Cellar Deck & Switchgear/LER Nos. 47% 193 193 100.00 193 193 100.00 193 100.00 193 100.00 100.00
- Mezzanine Deck Nos. 53% 957 957 100.00 957 957 100.00 957 100.00 957 100.00 100.00
FAB2900 Install GRE Pipe Spools 0.69 16-Apr-07 12-Jun-07 2,931 Nos. 100% 1762 1762 100.00 1762 1762 100.00 1762 100.00 1762 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 17% 293 293 100.00 293 293 100.00 293 100.00 293 100.00 100.00
- Cellar Deck & Switchgear/LER Nos. 21% 379 379 100.00 379 379 100.00 379 100.00 379 100.00 100.00
- Mezzanine Deck Nos. 44% 789 789 100.00 789 789 100.00 789 100.00 789 100.00 100.00
- Main Deck Nos. 18% 301 301 100.00 301 301 100.00 301 100.00 301 100.00 100.00
FAB2910 Install Piping Specialty Items 0.58 10-May-07 01-Jul-07 2,444 Nos. 100% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB2920 Install Pipe Bends & Barred Tees 0.45 17-Jul-07 06-Aug-07 1,926 Nos. 100% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB2930 Install Associated Fitting & Acc for Launcher 0.38 17-May-07 13-Jun-07 1,631 Nos. 100% 15 15 100.00 15 15 100.00 15 100.00 15 100.00 100.00 100.00 100.00 100.00 0.00
Install 90% Accept 10%
Done % Done %
FAB2940 Valve Installation 0.92 21-May-07 13-Jul-07 3,896 Nos. 100% 187 Note; o/s 4 nos. Glove Valve (Monitor under punchlist ite 187 100.00 187 100.00 100.00 100.00 100.00 100.00 0.00
LC / Flush 20% Hydrotest 60% Reinstate 10% Accept 10%
Total
Done % Done % Done % Done %
Pack
FAB2950 Hydrotest/Reinstatement 0.81 09-Jun-07 15-Aug-07 3,423 Lines 100% 102 102 100.00 102 100.00 102 100.00 102 100.00 100.00 100.00 100.00 100.00 0.00
Insulation 90% Accept 10%
Total
Done % Done %
Lines
FAB2960 Pipe Insulation 0.58 09-Jul-07 06-Aug-07 2,445 Lines 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00

13 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%


Total Total
Done % Done % Done % Done %
Pieces Joints
FAB2990 Install Pipe Supports Below Main Deck 0.82 27-Feb-07 25-Apr-07 3,470 Pcs 100% 307 307 100.00 307 307 100.00 307 100.00 307 100.00 100.00 100.00 100.00 100.00 0.00
Mechanical 5.48 15-Feb-07 20-Aug-07 23,253 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB2415 Fabricate Equipment Supports 0.20 15-Feb-07 06-Apr-07 858 Nos. 100% 58 58 100.00 58 58 100.00 58 100.00 58 100.00 100.00 100.00 100.00 100.00 0.00
- Flush Water Pump Nos. 10% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Fresh Water Pump Nos. 10% 5 5 100.00 5 5 100.00 5 100.00 5 100.00 100.00
- Diesel Transfer Pump Nos. 12% 5 5 100.00 5 5 100.00 5 100.00 5 100.00 100.00
- Swing Jib Crane Nos. 23% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Launcher & Receiver Nos. 21% 10 10 100.00 10 10 100.00 10 100.00 10 100.00 100.00
- Safety Shower & Eyewash Station Nos. 10% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Fire Extinguisher Nos. 14% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB3070 Install Equipment Supports 0.27 28-Mar-07 23-May-07 1,140 Nos. 100% 76 76 100.00 76 76 100.00 76 100.00 76 100.00 100.00 100.00 100.00 100.00 0.00
- Flush Water Pump Nos. 10% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Fresh Water Pump Nos. 10% 5 5 100.00 5 5 100.00 5 100.00 5 100.00 100.00
- Diesel Transfer Pump Nos. 12% 5 5 100.00 5 5 100.00 5 100.00 5 100.00 100.00
- Swing Jib Crane Nos. 23% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Launcher & Receiver Nos. 21% 10 10 100.00 10 10 100.00 10 100.00 10 100.00 100.00
- Safety Shower & Eyewash Station Nos. 10% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Fire Extinguisher Nos. 14% 42 42 100.00 42 42 100.00 42 100.00 42 100.00 100.00
Set Equip 60% Lvl & Fit 30% Accept 10%
Done % Done % Done %
FAB3080 Install HP Vent Tip 0.21 14-Jul-07 02-Aug-07 912 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3090 Install Flush Water Pump 0.16 03-Jul-07 28-Jul-07 684 Unit 100% 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3100 Install Fresh Water Pump 0.16 03-Jul-07 28-Jul-07 684 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3110 Install Corrosion Inhibitor Injection Package 0.31 28-Jun-07 13-Jul-07 1,300 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3120 Install Diesel Transfer Pump 0.29 07-Jul-07 31-Jul-07 1,233 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3130 Install Condensate Pod 0.24 16-Jun-07 03-Jul-07 1,031 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3140 Install Open Drain Caisson Pump 0.16 13-Jun-07 01-Jul-07 684 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3150 Install Closed Drain Transfer Pump 0.16 25-Jun-07 13-Jul-07 684 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3160 Install Manual Operated Trolley Hoists 0.32 09-Jun-07 25-Jun-07 1,367 Unit 100% 4 4 100.00 4 100.00 4 100.00 100.00 100.00 100.00 100.00 0.00
FAB3170 Install CO2 Vent Snuffing System 0.27 13-Jul-07 02-Aug-07 1,130 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3180 Install Swing Jib Cranes with Manual Operated Hoist 0.32 23-May-07 14-Jun-07 1,368 Unit 100% 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3190 Install Flush Water Tank 0.23 01-Jun-07 18-Jun-07 960 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3200 Install Fresh Water Tank 0.22 21-May-07 07-Jun-07 924 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3210 Install Closed Drain Vessel 0.26 17-Jul-07 07-Aug-07 1,106 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3220 Install All Remaining Pumps 0.24 28-Jul-07 11-Aug-07 1,034 Unit 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3230 Install Padestal Crane 0.59 25-Jul-07 10-Aug-07 2,507 Unit 100% 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
- Mechinery Deck Unit 80% 1 1 100.00 1 100.00 1 100.00 100.00
- Crane Boom & Mast Frame Unit 20% 1 1 100.00 1 100.00 1 100.00 100.00
FAB3240 Install All Remaining Mechanical Items 0.27 08-Aug-07 20-Aug-07 1,140 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
- Install Pig Launcher & Receiver Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00
FAB3300 Install Wellhead Desander Skids 0.59 05-Jun-07 28-Jun-07 2,507 Unit 100% 5 5 100.00 5 100.00 5 100.00 100.00 100.00 100.00 100.00 0.00
Electrical 6.61 28-Feb-07 03-Aug-07 28,038 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB2970 Fabricate Electrical Supports 0.47 28-Feb-07 06-Apr-07 1,996 Pcs 100% 592 592 100.00 592 592 100.00 592 100.00 592 100.00 100.00 100.00 100.00 100.00 0.00
- Cable Ladder Support Pcs 36% 199 199 100.00 199 199 100.00 199 100.00 199 100.00 100.00
- Lighting Support Pcs 30% 200 200 100.00 200 200 100.00 200 100.00 200 100.00 100.00
- Coaming/Plinth Support Pcs 12% 29 29 100.00 29 29 100.00 29 100.00 29 100.00 100.00
- JB/Socket/RCU Support Pcs 22% 164 164 100.00 164 164 100.00 164 100.00 164 100.00 100.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB2980 Install Electrical Supports 0.48 26-Mar-07 05-May-07 2,040 Pcs 100% 582 582 100.00 582 582 100.00 582 100.00 582 100.00 100.00 100.00 100.00 100.00 0.00
- Cable Ladder Support Pcs 36% 199 199 100.00 199 199 100.00 199 100.00 199 100.00 100.00
- Lighting Support Pcs 30% 190 190 100.00 190 190 100.00 190 100.00 190 100.00 100.00
- RCU/MCT/Coaming/Saddles Support Pcs 12% 29 29 100.00 29 29 100.00 29 100.00 29 100.00 100.00
- Outlet Support Pcs 22% 164 164 100.00 164 164 100.00 164 100.00 164 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3250 Install Cable Trays, Ladder & Accessories 0.74 13-Apr-07 04-Jun-07 3,135 Mtrs 100% 785 785 100.00 785 100.00 100.00 100.00 100.00 100.00 0.00
Install Cable Ladder Mtrs 47% 329 329 100.00 329 100.00 100.00
- Cellar Deck Mtrs 3% 20 20 100.00 20 100.00 100.00
- Mezzanine Deck Mtrs 16% 111 111 100.00 111 100.00 100.00
- Switchgear,LER,Battery,Welter Shelter & Transfomer Rooms Mtrs 28% 198 198 100.00 198 100.00 100.00

14 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

Install Cable Tray Mtrs 53% 456 456 100.00 456 100.00 100.00
- Main Deck Mtrs 9% 78 78 100.00 78 100.00 100.00
- Cellar Deck Mtrs 19% 165 165 100.00 165 100.00 100.00
- Mezzanine Deck Mtrs 15% 132 132 100.00 132 100.00 100.00
- Switchgear,LER,Battery,Welter Shelter & Transfomer Rooms Mtrs 10% 81 81 100.00 81 100.00 100.00
FAB3260 Install Electrical / Control Cables, Fitting & MCT's 0.74 14-Apr-07 24-May-07 3,140 Mtrs 100% 22 22 100.00 22 100.00 100.00 100.00 100.00 100.00 0.00
Install Electrical Coaming Mtrs 60% 13 13 100.00 13 100.00 100.00
- Cellar Deck Mtrs 32% 8 8 100.00 8 100.00 100.00
- Mezzanine Deck Mtrs 24% 4 4 100.00 4 100.00 100.00
- Main Deck Mtrs 4% 1 1 100.00 1 100.00 100.00
Install Electrical MCT's Nos. 40% 9 9 100.00 9 100.00 100.00
- Switchgear,LER,Battery,Welter Shelter & Transfomer Rooms Nos. 40% 9 9 100.00 9 100.00 100.00
FAB3270 Install Light Fitting, Photocells Mounting and Accessories 0.56 14-May-07 20-Jun-07 2,394 Nos. 100% 190 190 100.00 170 89.47 100.00 100.00 100.00 100.00 0.00
Install Light Fitting Nos. 100% 190 190 100.00 170 89.47 100.00
- Intermediate Platform Nos. 10% 9 9 100.00 9 100.00 100.00
- Cellar Deck Nos. 56% 111 111 100.00 111 100.00 100.00
- Mezzanine Deck Nos. 27% 54 54 100.00 54 100.00 100.00
- Main Deck Nos. 7% 16 16 100.00 16 100.00 100.00
Pull/Lay 90% Accept 10%
Done % Done %
FAB3280 Cable Pulling 0.92 02-May-07 15-Jun-07 3,907 Runs 100% 605 605 100.00 605 100.00 100.00 100.00 100.00 100.00 0.00
Power Cable Runs 16% 12 12 100.00 12 100.00 100.00
- Cable @ RMU (RMU-7505) Runs 9% 8 8 100.00 8 100.00 100.00
- Cable @ 6.6 kv Transformer (TF-7501) Runs 7% 4 4 100.00 4 100.00 100.00
Control Cable Runs 51% 215 215 100.00 215 100.00 100.00
- Cable 400v @ Switchgear (SB-7505) Runs 11% 113 113 100.00 113 100.00 100.00
- Cable 230v @ AC UPS (LCPA-8955) Runs 9% 5 5 100.00 5 100.00 100.00
- Cable 230v @ AC UPS (UPS-7805) Runs 9% 33 33 100.00 33 100.00 100.00
- Cable 230v @ AC UPS (DB-7815) Runs 9% 53 53 100.00 53 100.00 100.00
- Cable HVAC @ Control Panel Runs 6% 7 7 100.00 7 100.00 100.00
- Cable MOV @ Distribution Board (DB-7745) Runs 7% 4 4 100.00 4 100.00 100.00
DC Runs 10% 20 20 100.00 20 100.00 100.00
- Cable 24V DC @ Distribution Board (DB-7925) Runs 10% 20 20 100.00 20 100.00 100.00
Lighting/small power cables Runs 23% 358 358 100.00 358 100.00 100.00
- Cable @ Indoor Lighting Distribution Board (Normal/Emergency DB-7725) Runs 6% 48 48 100.00 48 100.00 100.00
- Cable @ Outdoor Lighting Distribution Board (Normal DB-7735) Runs 6% 50 50 100.00 50 100.00 100.00
- Cable @ Small Power Distribution Board (DB-7715) Runs 7% 153 153 100.00 153 100.00 100.00
- Cable @ Outdoor Lighting Emergency (DB-7845) Runs 4% 107 107 100.00 107 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3290 Install Junction Boxes and Control Panels 0.49 11-May-07 14-Jun-07 2,096 Nos. 100% 119 119 100.00 119 100.00 100.00 100.00 100.00 100.00 0.00
- JB's Sump Deck Nos. 11% 13 13 100.00 13 100.00 100.00
- JB's Cellar Deck & Switchgear/LER Nos. 53% 63 63 100.00 63 100.00 100.00
- JB's Mezzanine Deck Nos. 26% 31 31 100.00 31 100.00 100.00
- JB's Main Deck Nos. 10% 12 12 100.00 12 100.00 100.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3310 Install Power Transformer 0.23 19-Jul-07 03-Aug-07 984 Nos. 100% 1 1 100 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3320 Install 6.6KV Ring Main Unit 0.22 04-Jul-07 25-Jul-07 946 Nos. 100% 4 4 100 4 100.00 4 100.00 100.00 100.00 100.00 100.00 0.00
Install 90% Accept 10%
Done % Done %
FAB3330 Install Remote Control Units and Safety Switches 0.27 01-Jun-07 30-Jun-07 1,140 Nos. 100% 17 17 100.00 17 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 5% 2 Note : 2 100.00 2 100.00 100.00
- Cellar Deck & Switchgear/LER Nos. 18% 8 34 pcs RCU will plan to be install at Offshore due to late 8 100.00 8 100.00 100.00
- Mezzanine Deck Nos. 67% 3 delivery. Tentative arrive at PG ETA 31/09/07 (Consider 3 100.00 3 100.00 100.00
under punclist monitoring)
- Main Deck Nos. 10% 4 4 100.00 4 100.00 100.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3340 Install LV Distribution Board 0.23 27-Apr-07 23-May-07 957 Nos. 100% 7 7 100 7 100.00 7 100.00 100.00 100.00 100.00 100.00 0.00
- Install Indoor Lighting Distribution Board (Normal/Emergency DB-7725) Nos. 10% 1 1 100 1 100.00 1 100.00 100.00
- Install Outdoor Lighting Distribution Board (Normal DB-7735) Nos. 12% 1 1 100 1 100.00 1 100.00 100.00
- Install Outdoor Lighting Emergency (DB-7845) Nos. 12% 1 1 100 1 100.00 1 100.00 100.00
- Install Small Power Distribution Board (DB-7715) Nos. 18% 1 1 100 1 100.00 1 100.00 100.00
- Install 24V DC Distribution Board (DB-7925) Nos. 17% 1 1 100 1 100.00 1 100.00 100.00
- Install 230V AC UPS Distribution Board (DB-7815) Nos. 17% 1 1 100 1 100.00 1 100.00 100.00
- Install MOV Distribution Board (DB-7745) Nos. 14% 1 1 100 1 100.00 1 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3350 Install Powered Navigational Aids System 0.17 27-Jun-07 17-Jul-07 717 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Glnd/Trmt 90% Accept 10%

15 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

Done % Done %
FAB3360 Glanding & Termination 0.25 22-May-07 28-Jun-07 1,074 Nos. 100% 1210 1210 100.00 1210 100.00 100.00 100.00 100.00 100.00 0.00
Power Cable Nos. 16% 24 24 100.00 24 100.00 100.00
- Cable @ RMU (RMU-7505) Nos. 9% 16 16 100.00 16 100.00 100.00
- Cable @ 6.6 kv Transformer (TF-7501) Nos. 7% 8 8 100.00 8 100.00 100.00
Control Cable Nos. 51% 430 430 100.00 430 100.00 100.00
- Cable 400v @ Switchgear (SB-7505) Nos. 11% 226 226 100.00 226 100.00 100.00
- Cable 230v @ AC UPS (LCPA-8955) Nos. 9% 10 10 100.00 10 100.00 100.00
- Cable 230v @ AC UPS (UPS-7805) Nos. 9% 66 66 100.00 66 100.00 100.00
- Cable 230v @ AC UPS (DB-7815) Nos. 9% 106 106 100.00 106 100.00 100.00
- Cable HVAC @ Control Panel Nos. 6% 14 14 100.00 14 100.00 100.00
- Cable MOV @ Distribution Board (DB-7745) Nos. 7% 8 8 100.00 8 100.00 100.00
DC Nos. 10% 40 40 100.00 40 100.00 100.00
- Cable 24V DC @ Distribution Board (DB-7925) Nos. 10% 40 40 100.00 40 100.00 100.00
Lighting/small power cables Nos. 23% 716 716 100.00 716 100.00 100.00
- Cable @ Indoor Lighting Distribution Board (Normal/Emergency DB-7725) Nos. 6% 96 96 100.00 96 100.00 100.00
- Cable @ Outdoor Lighting Distribution Board (Normal DB-7735) Nos. 6% 100 100 100.00 100 100.00 100.00
- Cable @ Small Power Distribution Board (DB-7715) Nos. 7% 306 306 100.00 306 100.00 100.00
- Cable @ Outdoor Lighting Emergency (Normal DB-7845) Nos. 4% 214 214 100.00 214 100.00 100.00
Earthing 90% Accept 10%
Done % Done %
FAB3370 Install Earthing Accessories 0.20 23-Apr-07 05-Jul-07 855 Nos. 100% 950 950 100.00 950 100.00 100.00 100.00 100.00 100.00 0.00
Install 90% Accept 10%
Done % Done %
FAB3380 Install All Other Electrical Items 0.13 13-Jun-07 20-Jul-07 569 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3400 Install AC Uninterruptible Power Supply (UPS) 0.24 03-May-07 23-May-07 1,038 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3750 Install 400V Switchboard 0.25 07-May-07 30-May-07 1,051 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
Instrument 7.32 28-Feb-07 08-Aug-07 31,040 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB3020 Fabricate Instrument Supports 0.33 28-Feb-07 03-Apr-07 1,404 Nos. 100% 523 523 100.00 523 523 100.00 523 100.00 523 100.00 100.00 100.00 100.00 100.00 0.00
- Cable Tray Support Nos. 64% 320 320 100.00 320 320 100.00 320 100.00 320 100.00 100.00
- Major Equipment / JB Nos. 3% 21 21 100.00 21 21 100.00 21 100.00 21 100.00 100.00
- Instrument Support Nos. 4% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
- Fire & Gas Nos. 13% 73 73 100.00 73 73 100.00 73 100.00 73 100.00 100.00
- Telecom Nos. 2% 7 7 100.00 7 7 100.00 7 100.00 7 100.00 100.00
- AVA Nos. 2% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- GPA / PA Nos. 9% 48 48 100.00 48 48 100.00 48 100.00 48 100.00 100.00
- MCT / Coaming Nos. 3% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB3030 Install Instrument Supports 0.48 27-Mar-07 02-May-07 2,043 Nos. 100% 523 523 100.00 523 523 100.00 523 100.00 523 100.00 100.00 100.00 100.00 100.00 0.00
- Cable Ladder/Tray Support Nos. 64% 323 323 100.00 323 323 100.00 323 100.00 323 100.00 100.00
- Plint / JB Nos. 4% 21 21 100.00 21 21 100.00 21 100.00 21 100.00 100.00
- Fire & Gas Nos. 13% 66 66 100.00 66 66 100.00 66 100.00 66 100.00 100.00
- Telecom Nos. 1% 7 7 100.00 7 7 100.00 7 100.00 7 100.00 100.00
- AVA Nos. 2% 11 11 100.00 11 11 100.00 11 100.00 11 100.00 100.00
- GPA / PA Nos. 7% 43 43 100.00 43 43 100.00 43 100.00 43 100.00 100.00
- MCT / Coaming Nos. 4% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00
- Fusible Plug Nos. 5% 30 30 100.00 30 30 100.00 30 100.00 30 100.00 100.00
Calib'n 80% Accept 20%
Done % Done %
FAB3040 Instrument Calibration 0.20 10-May-07 26-Jun-07 845 Nos. 100% 126 126 100.00 126 100.00 100.00 100.00 100.00 100.00 0.00
- Flow Transmitter (FT) Nos. 10% 10 10 100.00 10 100.00 100.00
- Level Transmitter (LT) Nos. 3% 5 5 100.00 5 100.00 100.00
- IRCD (MOV) Nos. 8% 6 6 100.00 6 100.00 100.00
- Pressure Regulator (PCV) Nos. 3% 1 1 100.00 1 100.00 100.00
- Diff Pressure Transmitter (PDT) Nos. 4% 5 5 100.00 5 100.00 100.00
- Pressure Gauge (PG) Nos. 21% 47 47 100.00 47 100.00 100.00
- Pressure Relief Valve (PSV) Nos. 12% 12 12 100.00 12 100.00 100.00
- Pressure Transmitter (PT) Nos. 6% 7 7 100.00 7 100.00 100.00
- Pressure Vacuum Relief Valve (PVSV) Nos. 7% 4 4 100.00 4 100.00 100.00
- Pressure Transmitter (PZT) Nos. 14% 13 13 100.00 13 100.00 100.00
- Temperature Transmitter (TT) Nos. 4% 7 7 100.00 7 100.00 100.00
- Actuated Ball Valve (UZV) Nos. 8% 9 9 100.00 9 100.00 100.00
Pull/Lay 90% Accept 10%
Done % Done %

16 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

FAB3050 Cable pulling 0.31 04-May-07 16-Jun-07 1,335 Mtrs 100% 13859 13859 100.00 13859 100.00 100.00 100.00 100.00 100.00 0.00
- DCS & IPS Mtrs 55% 7755 7755 100.00 7755 100.00 100.00
- GPA / PA Mtrs 13% 1860 1860 100.00 1860 100.00 100.00
- Telecom Mtrs 5% 665 665 100.00 665 100.00 100.00
- AVA Mtrs 7% 750 750 100.00 750 100.00 100.00
- FGS Mtrs 20% 2829 2829 100.00 2829 100.00 100.00
Glnd/Trmt 90% Accept 10%
Done % Done %
FAB3060 Glanding & Termination 0.19 07-Jun-07 02-Jul-07 799 Nos. 100% 954 954 100.00 954 100.00 100.00 100.00 100.00 100.00 0.00
- DCS & IPS Nos. 48% 390 390 100.00 390 100.00 100.00
- GPA / PA Nos. 22% 196 196 100.00 196 100.00 100.00
- Telecom Nos. 2% 38 38 100.00 38 100.00 100.00
- AVA Nos. 4% 56 56 100.00 56 100.00 100.00
- FGS Nos. 24% 274 274 100.00 274 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3390 Install Cable Tray & Ladders 0.59 05-Apr-07 22-May-07 2,507 Mtrs 100% 467 467 100.00 467 100.00 100.00 100.00 100.00 100.00 0.00
- Install Cable Tray & Ladder Mtrs 85% 326 Note ; 15mtr under shiploose item will be instl at offshore 326 100.00 326 100.00 100.00
- Install Tubing Tray Mtrs 15% 141 141 100.00 141 100.00 100.00
FAB3410 Install Instrument Cable Junction Boxes & MCT's 0.39 16-May-07 27-Jun-07 1,675 Mtrs 100% 75 75 100.00 75 100.00 100.00 100.00 100.00 100.00 0.00
Junction Boxes Nos. 80% 70 70 100.00 70 100.00 100.00
- Fire & Gas Nos. 12% 4 4 100.00 4 100.00 100.00
- Telephone Nos. 10% 3 3 100.00 3 100.00 100.00
- Instrument JB Nos. 20% 22 22 100.00 22 100.00 100.00
- GPA / PA Nos. 33% 40 40 100.00 40 100.00 100.00
- Fibre Optic Nos. 5% 1 1 100.00 1 100.00 100.00
MCT Nos. 20% 5 5 100.00 5 100.00 100.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3420 Install Wellhead Control Panel 0.31 25-Apr-07 24-May-07 1,335 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
Fit-Up 50% Weld 40% Accept 10%
Done % Done % Done %
FAB3430 Install Field Instrument & Mounting Stands & Supports etc. 0.44 08-May-07 28-May-07 1,880 Nos. 100% 184 184 100.00 184 100.00 184 100.00 100.00 100.00 100.00 100.00 0.00
- Impulse Line Nos. 50% 26 Note ; 2 nos of Pig Signaller ETA 26 100.00 26 100.00 26 100.00 100.00
- Instrument Devices Nos. 50% 158 06/11/07, plan to install offshore. 158 100.00 158 100.00 158 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3440 Install Sand Monitoring System 0.10 05-Jun-07 25-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3450 Install Ultrasonic Flowmeters 0.10 18-May-07 05-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3460 Install Pig Signallers 0.10 24-May-07 12-Jun-07 420 Nos. 100% 2 Note ; 2 nos of Pig Signaller ETA 06/11/07, plan to install 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3470 Install Choke Valves 0.16 18-Jul-07 08-Aug-07 694 Nos. 100% 5 offshore. 5 100.00 5 100.00 100.00 100.00 100.00 100.00 0.00
FAB3480 Install GPA/PAPA 0.10 24-May-07 23-Jun-07 420 Nos. 100% 49 49 100.00 49 100.00 100.00 100.00 100.00 100.00 0.00
- Install Strobe Light Nos. 28% 16 16 100.00 16 100.00 100.00
- Install Outdoor Speaker Nos. 27% 18 18 100.00 18 100.00 100.00
- Install Indoor Speaker Nos. 14% 4 4 100.00 4 100.00 100.00
- Install Pushbutton Station Nos. 21% 9 9 100.00 9 100.00 100.00
- Install Sounder Nos. 10% 2 2 100.00 2 100.00 100.00
FAB3490 Install Control, Ball and Operated Valves 0.31 25-May-07 29-Jun-07 1,310 Nos. 100% 8 Note ; 1 no ball valve under shiploose items. 8 100.00 8 100.00 100.00 100.00 100.00 100.00 0.00
FAB3500 Install Distributed Control System (DCS) and (AVA) 0.17 21-Apr-07 22-May-07 711 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3510 Install ESD Break Glass Station 0.10 12-Jun-07 25-Jun-07 413 Nos. 100% 9 9 100.00 9 100.00 100.00 100.00 100.00 100.00 0.00
FAB3520 Install IR Flame Detector 0.10 26-May-07 12-Jun-07 420 Nos. 100% 23 23 100.00 23 100.00 100.00 100.00 100.00 100.00 0.00
FAB3530 Install IR Point Gas Detector 0.10 26-May-07 13-Jun-07 420 Nos. 100% 16 16 100.00 16 100.00 100.00 100.00 100.00 100.00 0.00
FAB3540 Install IR Open Path Gas Detector 0.10 26-May-07 12-Jun-07 420 Nos. 100% 20 20 100.00 20 100.00 100.00 100.00 100.00 100.00 0.00
FAB3550 Install Smoke Detector 0.10 30-May-07 14-Jun-07 420 Nos. 100% 27 27 100.00 27 100.00 100.00 100.00 100.00 100.00 0.00
FAB3560 Install Hydrogen Gas Detector 0.10 30-May-07 12-Jun-07 420 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3570 Install Acoustic Leak Detector 0.10 28-May-07 15-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3580 Install Heat Detector 0.10 31-May-07 15-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3590 Install Ultra Sonic Flare Gas Meter 0.10 22-May-07 12-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3600 Install IPS System 0.20 21-Apr-07 14-May-07 858 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3610 Install Restriction Orifice Plates 0.07 11-Jun-07 25-Jun-07 291 Nos. 100% 13 13 100.00 13 100.00 100.00 100.00 100.00 100.00 0.00
FAB3620 Install Orifice Plates 0.07 18-Jun-07 01-Jul-07 291 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3630 Install Instrument Tubing, Fittings & Valves 0.47 10-May-07 05-Jun-07 1,993 Mtrs. 100% 2073 2073 100.00 2073 100.00 100.00 100.00 100.00 100.00 0.00
FAB3640 Install Level Gauges (Reflex Type) 0.10 21-May-07 06-Jun-07 420 Nos. 100% 5 5 100.00 5 100.00 100.00 100.00 100.00 100.00 0.00
FAB3650 Install Level Gauges (Using Pressure Gauge) 0.10 18-May-07 04-Jun-07 420 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3660 Install Pressure Gauges 0.10 19-May-07 06-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3670 Install All Remaining Instrumentation Items 0.14 03-Jul-07 04-Aug-07 585 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3710 Install F&G System 0.20 21-Apr-07 12-May-07 858 Nos. 100% 11 11 100.00 11 100.00 100.00 100.00 100.00 100.00 0.00
FAB3720 Install Wellhead Control System (WHCS) 0.27 21-Apr-07 19-May-07 1,151 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3730 Install Telecommunication Equipment 0.30 07-May-07 07-Jun-07 1,278 Nos. 100% 23 23 100.00 23 100.00 100.00 100.00 100.00 100.00 0.00
- Install Antena Nos. 40% 3 Note ; 1no antena under shiploose items. 3 100.00 3 100.00 100.00
- Install Outdoor Telephone Nos. 12% 3 3 100.00 3 100.00 100.00

17 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

- Install Indoor Telephone Nos. 12% 5 5 100.00 5 100.00 100.00


- Install CCTV Nos. 36% 12 12 100.00 12 100.00 100.00
FAB3740 Install Wet Gas Metering Skid & Panel (Operational Metering) 0.11 19-Jun-07 09-Jul-07 484 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Architectural 2.33 24-Mar-07 26-Jul-07 9,881 Mark&Cut 30% Install 60% Accept 10% 100.00 100.00 100.00 100.00 0.00
Done % Done % Done %
FAB2760 Switchgear, Transformer Room & Battery Room 0.82 24-Mar-07 07-May-07 3,477 Pcs 100% 5110 5110 100.00 5110 100.00 5110 100.00 100.00 100.00 100.00 100.00 0.00
Fire Rated Doors Pcs 11% 10 10 100.00 10 100.00 10 100.00 100.00
- Door Panels (Single & Double) Pcs 6% 5 5 100.00 5 100.00 5 100.00 100.00
- Door Frame (Single & Double) Pcs 5% 5 5 100.00 5 100.00 5 100.00 100.00
Wall Finish (H15 Wall) Pcs 74% 4800 4800 100.00 4800 100.00 4800 100.00 100.00
- 3mm dia. x 95 L.G. Copper Coated Pin Pcs 25% 2100 2100 100.00 2100 100.00 2100 100.00 100.00
- Insulation Rockwool Pcs 16% 250 250 100.00 250 100.00 250 100.00 100.00
- Aluminium Foil Pcs 10% 250 250 100.00 250 100.00 250 100.00 100.00
- Galvanize M.S. Speed Clip Pcs 9% 2100 2100 100.00 2100 100.00 2100 100.00 100.00
- 25mm TNF Wall Panel Pcs 14% 100 100 100.00 100 100.00 100 100.00 100.00
Floor and Cailing Finish Pcs 15% 300 300 100.00 300 100.00 300 100.00 100.00
- Cailing Pcs 10% 100 100 100.00 100 100.00 100 100.00 100.00
- Floor Pcs 5% 200 200 100.00 200 100.00 200 100.00 100.00
FAB2770 Instrument Local Equipment Room 1.01 21-Apr-07 04-Jul-07 4,273 Pcs 100% 4914 4914 100.00 4914 100.00 4914 100.00 100.00 100.00 100.00 100.00 0.00
Fire Rated Doors Pcs 11% 4 4 100.00 4 100.00 4 100.00 100.00
- Door Panels (Single & Double) Pcs 6% 2 2 100.00 2 100.00 2 100.00 100.00
- Door Frame (Single & Double) Pcs 5% 2 2 100.00 2 100.00 2 100.00 100.00
Wall Finish (AO Wall) Pcs 69% 4800 4800 100.00 4800 100.00 4800 100.00 100.00
- 3mm dia. x 95 L.G. Copper Coated Pin Pcs 25% 2100 2100 100.00 2100 100.00 2100 100.00 100.00
- Insulation Rockwool Pcs 16% 250 250 100.00 250 100.00 250 100.00 100.00
- Aluminium Foil Pcs 10% 250 250 100.00 250 100.00 250 100.00 100.00
- Galvanize M.S. Speed Clip Pcs 9% 2100 2100 100.00 2100 100.00 2100 100.00 100.00
- 25mm TNF Wall Panel Pcs 9% 100 100 100.00 100 100.00 100 100.00 100.00
Cailing & Floor Finish Pcs 15% 100 100 100.00 100 100.00 100 100.00 100.00
- Cailing & Steel Rise Floor Pcs 15% 100 100 100.00 100 100.00 100 100.00 100.00
Furnitures Pcs 5% 10 10 100.00 10 100.00 10 100.00 100.00
- Computer Table Pcs 3% 5 5 100.00 5 100.00 5 100.00 100.00
- Sitting Chair Pcs 2% 5 5 100.00 5 100.00 5 100.00 100.00
FAB2780 Weather Shelter & Workshop 0.50 21-Jun-07 26-Jul-07 2,131 Pcs 100% 2708 2708 100.00 2708 100.00 2708 100.00 100.00 100.00 100.00 100.00 0.00
Fire Rated Doors Pcs 11% 4 4 100.00 4 100.00 4 100.00 100.00
- Door Panels (Double) Pcs 6% 2 2 100.00 2 100.00 2 100.00 100.00
- Door Frame (Double) Pcs 5% 2 2 100.00 2 100.00 2 100.00 100.00
Wall Finish (H15 Wall) Pcs 69% 2600 2600 100.00 2600 100.00 2600 100.00 100.00
- 3mm dia. x 95 L.G. Copper Coated Pin Pcs 15% 1100 1100 100.00 1100 100.00 1100 100.00 100.00
- Insulation Rockwool Pcs 19% 150 150 100.00 150 100.00 150 100.00 100.00
- Aluminium Foil Pcs 14% 150 150 100.00 150 100.00 150 100.00 100.00
- Galvanize M.S. Speed Clip Pcs 12% 1100 1100 100.00 1100 100.00 1100 100.00 100.00
- 25mm TNF Wall Panel Pcs 9% 100 100 100.00 100 100.00 100 100.00 100.00
Cailing & Floor Finish Pcs 15% 100 100 100.00 100 100.00 100 100.00 100.00
- Cailing & Flooring w/ anti skid paint Pcs 15% 100 100 100.00 100 100.00 100 100.00 100.00
Furnitures Pcs 5% 4 4 100.00 4 100.00 4 100.00 100.00
- Computer Table Pcs 3% 2 2 100.00 2 100.00 2 100.00 100.00
- Sitting Chair Pcs 2% 2 2 100.00 2 100.00 2 100.00 100.00
HVAC 2.23 02-Apr-07 19-Jul-07 9,461 M&C / Lift Position 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB2790 Switchgear, Transformer Room & Battery Room 0.78 02-Apr-07 12-May-07 3,295 Pcs 100% 615 615 100.00 615 615 100.00 615 100.00 615 100.00 100.00 100.00 100.00 100.00 0.00
Fabrication Pcs 40% 363 363 100.00 363 363 100.00 363 100.00 363 100.00 100.00
Fab. Ducting Supports Pcs 4% 80 80 100.00 80 80 100.00 80 100.00 80 100.00 100.00
Fab. Duct Penetration Pcs 2% 13 13 100.00 13 13 100.00 13 100.00 13 100.00 100.00
Fab. Internal Duct Pcs 10% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00
Fab. External Duct Pcs 2% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00
Fab. AHU Pcs 4% 16 16 100.00 16 16 100.00 16 100.00 16 100.00 100.00
Fab. ACCU Pcs 4% 16 16 100.00 16 16 100.00 16 100.00 16 100.00 100.00
Fab. Duct Heater Pcs 2% 3 3 100.00 3 3 100.00 3 100.00 3 100.00 100.00
Fab. Dumpers Pcs 2% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Fab. Exhauts Fan Pcs 4% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Fab. Control Panel Pcs 2% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Fab. FAT Pcs 4% 10 10 100.00 10 10 100.00 10 100.00 10 100.00 100.00
Installation Pcs 60% 252 252 100.00 252 252 100.00 252 100.00 252 100.00 100.00
Install Ducting Supports Pcs 6% 80 80 100.00 80 80 100.00 80 100.00 80 100.00 100.00
Install Duct Penetration Pcs 6% 9 9 100.00 9 9 100.00 9 100.00 9 100.00 100.00
Install Internal Duct Pcs 7% 37 37 100.00 37 37 100.00 37 100.00 37 100.00 100.00
Install External Duct Pcs 7% 90 90 100.00 90 90 100.00 90 100.00 90 100.00 100.00

18 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

Install AHU Pcs 8% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00


Install ACCU Pcs 8% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
Install Duct Heater Pcs 4% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Install Dumpers Pcs 4% 18 18 100.00 18 18 100.00 18 100.00 18 100.00 100.00
Install Exhauts Fan Pcs 4% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Install Control Panel Pcs 3% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Install SS Drain Pipe Pcs 2% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
Install Jacketing Copper Pipe Pcs 1% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
FAB2800 Instrument Local Equipment Room 1.01 30-Apr-07 26-Jun-07 4,273 Pcs 100% 111 111 100.00 111 111 100.00 111 100.00 111 100.00 100.00 100.00 100.00 100.00 0.00
Install Ducting Supports Pcs 20% 80 80 100.00 80 80 100.00 80 100.00 80 100.00 100.00
Install Duct Penetration Pcs 10% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
Install Internal Duct Pcs 20% 24 24 100.00 24 24 100.00 24 100.00 24 100.00 100.00
Install External Duct Pcs 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Install ACCU Pcs 20% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
Install Duct Heater Pcs 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Install Dumpers Pcs 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
FAB2810 Weather Shelter & Workshop 0.45 12-Jun-07 19-Jul-07 1,893 Pcs 100% 33 33 100.00 33 33 100.00 33 100.00 33 100.00 100.00 100.00 100.00 100.00 0.00
Install Ducting Supports Pcs 20% 10 10 100.00 10 10 100.00 10 100.00 10 100.00 100.00
Install Duct Penetration Pcs 20% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
Install Internal Duct Pcs 20% 14 14 100.00 14 14 100.00 14 100.00 14 100.00 100.00
Install External Duct Pcs 20% 5 5 100.00 5 5 100.00 5 100.00 5 100.00 100.00
Install Duct Heater Pcs 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Install Dumpers Pcs 10% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
Safety 0.67 04-Jun-07 15-Aug-07 2,850 Install 90% Accept 10% 100.00 100.00 100.00 100.00 0.00
Done % Done %
FAB3680 Install of Safety Equipment and Fire Protection Equipment 0.50 30-Jul-07 15-Aug-07 2,138 Nos. 100% 186 186 100.00 186 100.00 100.00 100.00 100.00 100.00 0.00
- Flexible Hose and Hose Coupling Conection Nos. 9% 40 40 100.00 40 100.00 100.00
- Hosereels Nos. 8% 10 10 100.00 10 100.00 100.00
- Fire Extinguishers Nos. 7% 33 33 100.00 33 100.00 100.00
- Liftraft and Safety Equipment Nos. 18% 3 3 100.00 3 100.00 100.00
- Lifejacket Nos. 7% 36 36 100.00 36 100.00 100.00
- Lifejacket Container Nos. 7% 3 3 100.00 3 100.00 100.00
- Knotted Rope Nos. 7% 3 3 100.00 3 100.00 100.00
- Ring Life Buoy Nos. 7% 21 21 100.00 21 100.00 100.00
- Safety Shower & Self-Contained Eyewash Station Nos. 10% 9 9 100.00 9 100.00 100.00
- First Aid Kit Nos. 8% 3 3 100.00 3 100.00 100.00
- Smoke Hoods and Container Nos. 7% 24 24 100.00 24 100.00 100.00
- Breathing Apparatus Set and Cabinet Nos. 7% 1 1 100.00 1 100.00 100.00
FAB3690 Install of Safety Signs 0.17 04-Jun-07 20-Jun-07 712 Nos. 100% 95 Note ; 18 nos under shiploose items. 95 100.00 95 100.00 100.00 100.00 100.00 100.00 0.00
Others Materials 0.67 31-Jul-07 16-Aug-07 2,850 Install 90% Accept 10% 100.00 100.00 100.00 100.00 0.00
Done % Done %
FAB3700 Install of Any Other Materials not included above 0.67 31-Jul-07 16-Aug-07 2,850 Nos. 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
ONSHORE PRE-COMMISSIONING 4.34 21-May-07 28-Aug-07 18,430 PreComm 90% Accept 10% 100.00 100.00 100.00 100.00 0.00
Done % Done %
COM1010 Precom Lighting and Small Power 0.19 30-Jun-07 28-Jul-07 824 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1020 Precom UPS System 0.26 08-Jun-07 06-Jul-07 1,094 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1030 Precom Fresh Water System 0.10 28-Jul-07 17-Aug-07 426 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1040 Precom Materials Handling 0.18 10-Aug-07 28-Aug-07 776 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1050 Precom Electrical Power Generation & Distribution (EDG) 0.34 25-Jul-07 18-Aug-07 1,461 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1060 Precom HVAC 0.31 26-Jun-07 28-Jul-07 1,327 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1070 Precom IPS System 0.25 04-Jul-07 30-Jul-07 1,049 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1080 Precom DCS and AVA System (Control System) 0.31 30-Jul-07 28-Aug-07 1,324 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1090 Precom Fire and Gas System (F&G) 0.26 30-Jun-07 01-Aug-07 1,083 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1100 Precom Wellhead Control System (WHCS) 0.29 28-Jun-07 30-Jul-07 1,223 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1110 Precom GPA System 0.17 23-Jun-07 17-Jul-07 713 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1120 Precom Telecomunication System 0.25 16-Jun-07 14-Jul-07 1,065 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1130 Precom Earthing and Bonding System 0.26 21-May-07 22-Jun-07 1,100 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1140 Precom Drain System 0.13 23-Jul-07 16-Aug-07 539 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1150 Precom Vent System 0.17 02-Aug-07 18-Aug-07 731 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1160 Precom Navigation Aid System 0.08 17-Jul-07 02-Aug-07 335 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1170 Precom Diesel Fuel System 0.20 31-Jul-07 16-Aug-07 852 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1180 Precom Corrosion Inhibitor Injection System 0.15 13-Jul-07 03-Aug-07 639 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1190 Precom Gas and Condensate System 0.23 28-Jul-07 28-Aug-07 974 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1200 Precom Sand Monitoring System 0.11 11-Jul-07 30-Jul-07 469 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
COM1210 Precom Flush Water System 0.10 28-Jul-07 16-Aug-07 426 Sys 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
WEIGHING, LOADOUT & SEAFASTENING 2.09 02-Jul-07 04-Sep-07 8,862 Prep. 80% Accept 20% 100.00 100.00 100.00 100.00 0.00
Done % Done %
CVE1000 Civil Engineering and Infrastructure Works 0.84 02-Jul-07 16-Aug-07 3,555 Comp. 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
LOA1000 Loadout Topsides 0.26 29-Aug-07 31-Aug-07 1,098 Comp. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
LOA1010 Seafastening Topsides 0.50 31-Aug-07 04-Sep-07 2,109 Comp. 100% 4 4 100.00 4 100.00 100.00 100.00 100.00 100.00 0.00

19 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

WGH1000 1st Weighing of Topsides 0.25 02-Jul-07 06-Jul-07 1,050 Comp. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
WGH1010 Final Weighing of Topsides 0.25 10-Aug-07 15-Aug-07 1,050 Comp. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
E11K-A SHIPLOOSE ITEMS 1.88 21-Aug-06 24-Jul-07 7,972 100.00 100.00 100.00 100.00 0.00
ENGINEERING 0.12 21-Aug-06 25-Jan-07 520 Prep MTO / ShpDwg Submitted Approved 100.00 100.00 100.00 100.00 0.00
60% 20% 20%
PRE1700 Prepare/Submit/Approve of MTO 0.03 21-Aug-06 25-Nov-06 140 Nos. 100% 26 26 26 26 100.00 100.00 100.00 100.00 0.00
- Structural Nos. 18% 1 1 1 1 100.00
- Piping Nos. 27% 7 7 7 7 100.00
- Mechanical Nos. 19% 2 2 2 2 100.00
- Electrical Nos. 19% 8 8 8 8 100.00
- Instrument Nos. 17% 8 8 8 8 100.00
PRE1710 Prepare/Submit/Approve of Shop Drawings 0.09 03-Oct-06 25-Jan-07 380 Nos. 100% 934 934 934 934 100.00 100.00 100.00 100.00 0.00
Structural Nos. 17% 20 20 20 20 100.00
- IFA Shop Drawings Nos. 6 6 6 6 100.00
- IFC Shop Drawings Nos. 14 14 14 14 100.00
Piping Nos. 27% 254 254 254 254 100.00
- IFA Shop Drawings Nos. 127 127 127 127 100.00
- IFC Shop Drawings Nos. 127 127 127 127 100.00
Mechanical Nos. 16% 16 16 16 16 100.00
- IFA Shop Drawings Nos. 3 3 3 3 100.00
- IFC Shop Drawings Nos. 13 13 13 13 100.00
Electrical Nos. 19% 82 82 82 82 100.00
- IFA Shop Drawings Nos. 41 41 41 41 100.00
- IFC Shop Drawings Nos. 41 41 41 41 100.00
Instrument Nos. 21% 190 190 190 190 100.00
- IFA Shop Drawings Nos. 95 95 95 95 100.00
- IFC Shop Drawings Nos. 95 95 95 95 100.00
PROCUREMENT 0.19 05-Oct-06 05-Jun-07 798 PR RFQ BCD TBE PO 100.00 100.00 100.00 100.00 0.00
Purchase Request to Purchase Order 0.07 05-Oct-06 22-Jan-07 300 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO4440 PR/PO of Structural Matl's 0.01 08-Nov-06 03-Jan-07 30 Comp. Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO4450 PR/PO of Pipe Matl's 0.02 05-Oct-06 30-Nov-06 84 Comp. Qty 100% 6 6 6 6 6 6 100.00 100.00 100.00 100.00 0.00
- Ball, Globe, Gate & Check Valves (PR No.#62) Comp. Qty 21% 1 1 1 1 1 1 100.00
- Pipes (PR No.#63) Comp. Qty 29% 1 1 1 1 1 1 100.00
- Flange and Pipe Fitting (PR No.#64) Comp. Qty 19% 1 1 1 1 1 1 100.00
- Gasket (PR No.#83) Comp. Qty 9% 1 1 1 1 1 1 100.00
- Stud Bolt with Nuts (PR No.#136) Comp. Qty 8% 1 1 1 1 1 1 100.00
- Pipe Supports Matl's (PR No.#103) Comp. Qty 14% 1 1 1 1 1 1 100.00
PRO4470 PR/PO of Mechanical Matl's 0.01 26-Oct-06 20-Dec-06 46 Comp. Qty 100% 6 6 6 6 6 6 100.00 100.00 100.00 100.00 0.00
- Pig trap end closure Comp. Qty 22% 1 1 1 1 1 1 100.00
- Eccentric Reducer Comp. Qty 17% 1 1 1 1 1 1 100.00
- Weldolet Comp. Qty 12% 1 1 1 1 1 1 100.00
- Welding Neck Flanges Comp. Qty 15% 1 1 1 1 1 1 100.00
- Equal Barred Tee (PR No.#11) Comp. Qty 24% 1 1 1 1 1 1 100.00
- Corrosion Monitoring System (PR No.#13) Comp. Qty 10% 1 1 1 1 1 1 100.00
PRO4490 PR/PO of Electrical Matl's 0.02 25-Nov-06 22-Jan-07 70 Comp. Qty 100% 7 7 7 7 7 7 100.00 100.00 100.00 100.00 0.00
- Electrical Cables (PR No.#70) Comp. Qty 24% 1 1 1 1 1 1 100.00
- Electrical Cable Gland (PR No.#73) Comp. Qty 20% 1 1 1 1 1 1 100.00
- Electrical Earthing Matl's (PR No.#74) Comp. Qty 7% 1 1 1 1 1 1 100.00
- Electrical Cable Ladder (PR No.#80) Comp. Qty 14% 1 1 1 1 1 1 100.00
- Electrical HV Cable Termination (PR No.#69) Comp. Qty 12% 1 1 1 1 1 1 100.00
- Electrical Cable Power (PR No.#72) Comp. Qty 14% 1 1 1 1 1 1 100.00
- Electrical Steel Mat'l (PR No.#77) Comp. Qty 9% 1 1 1 1 1 1 100.00
PRO4500 PR/PO of Instrument Matl's 0.02 25-Nov-06 22-Jan-07 70 Comp. Qty 90% 7 7 7 7 7 7 100.00 100.00 100.00 100.00 0.00
- Control Valve (PR No.#29) Comp. Qty 21% 1 1 1 1 1 1 100.00
- Instrument Cables (PR No.#102) Comp. Qty 19% 1 1 1 1 1 1 100.00
- Instrument Cables Glands (PR No.#149) Comp. Qty 15% 1 1 1 1 1 1 100.00
- Instrument Hook-Up Matl's (PR No.#144) Comp. Qty 14% 1 1 1 1 1 1 100.00
- Instrument Earthing Matl's (PR No.#156) Comp. Qty 7% 1 1 1 1 1 1 100.00
- Instrument Steel Matl's (PR No.#158) Comp. Qty 9% 1 1 1 1 1 1 100.00
- Instrument MCT & Misc. Items (PR No.#154) Comp. Qty 5% 1 1 1 1 1 1 100.00
Purchase Order to Delivery 0.04 30-Nov-06 24-May-07 174 Expedite 100.00 100.00 100.00 100.00 0.00
100%
PRO4460 PO to Del Structural Matl's 0.01 03-Jan-07 15-May-07 26 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4510 PO to Del Pipe Matl's 0.01 30-Nov-06 14-Apr-07 48 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4520 PO to Del Electrical Matl's 0.01 22-Jan-07 23-May-07 35 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4530 PO to Del Instrument Matl's 0.01 22-Jan-07 24-May-07 35 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4540 PO to Del Mechanical Matl's 0.01 20-Dec-06 19-May-07 30 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
Materials Receiving Inspection 0.08 14-Apr-07 05-Jun-07 324 Delivered to Site Accepted 100.00 100.00 100.00 100.00 0.00
80% 20%
PRO4580 Receive/Accept of Structural Matl's 0.01 15-May-07 23-May-07 60 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00

20 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

PRO4590 Receive/Accept of Pipe Matl's 0.02 14-Apr-07 04-May-07 98 Nos. 100% 1648 1648 1648 100.00 100.00 100.00 100.00 0.00
- Ball, Globe, Gate & Check Valves (PR No.#62) Nos. 23% 25 25 25 100.00
- Pipes (PR No.#63) Nos. 27% 108 108 108 100.00
- Flange and Pipe Fitting (PR No.#64) Nos. 19% 212 212 212 100.00
- Gasket (PR No.#83) Nos. 10% 128 128 128 100.00
- Stud Bolt with Nuts (PR No.#136) Nos. 8% 1164 1164 1164 100.00
- Pipe Supports Matl's (PR No.#103) Nos. 13% 11 11 11 100.00
PRO4600 Receive/Accept of Electrical Matl's 0.02 24-May-07 05-Jun-07 72 Nos. 100% 1012 1012 1012 100.00 100.00 100.00 100.00 0.00
- Electrical Cables (PR No.#70) Nos. 24% 250 250 250 100.00
- Electrical Cable Gland (PR No.#73) Nos. 20% 18 18 18 100.00
- Electrical Earthing Matl's (PR No.#74) Nos. 7% 183 183 183 100.00
- Electrical Cable Ladder (PR No.#80) Nos. 14% 222 222 222 100.00
- Electrical HV Cable Termination (PR No.#69) Nos. 12% 2 2 2 100.00
- Electrical Cable Power (PR No.#72) Nos. 14% 310 310 310 100.00
- Electrical Steel Mat'l (PR No.#77) Nos. 9% 27 27 27 100.00
PRO4610 Receive/Accept of Instrument Matl's 0.02 25-May-07 05-Jun-07 70 Nos. 100% 1711 1711 1711 100.00 100.00 100.00 100.00 0.00
- Control Valve (PR No.#29) Nos. 24% 1 1 1 100.00
- Instrument Cables (PR No.#102) Nos. 20% 1478 1478 1478 100.00
- Instrument Cables Glands (PR No.#149) Nos. 15% 54 54 54 100.00
- Instrument Hook-Up Matl's (PR No.#144) Nos. 16% 52 52 52 100.00
- Instrument Earthing Matl's (PR No.#156) Nos. 14% 10 10 10 100.00
- Instrument Steel Matl's (PR No.#158) Nos. 7% 106 106 106 100.00
- Instrument MCT & Misc. Items (PR No.#154) Nos. 4% 10 10 10 100.00
PRO4620 Receive/Accept of Mechanical Matl's 0.01 21-May-07 30-May-07 24 Nos. 100% 3 3 3 100.00 100.00 100.00 100.00 0.00
- Equal Barred Tee (PR No.#11) Nos. 60% 1 1 1 100.00
- Corrosion Monitoring System (PR No.#13) Nos. 40% 2 2 2 100.00
FABRICATION SHIPLOOSE ITEMS 1.57 04-May-07 24-Jul-07 6,654 100.00 100.00 100.00 100.00 0.00
Structural 0.19 24-May-07 05-Jul-07 801 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1000 Fab. Misc Structural Members E11K-A 0.19 24-May-07 05-Jul-07 801 No. of Pcs 100% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
Mechanical 0.05 30-May-07 04-Jul-07 200 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1120 Fab. Mechanical Items 0.05 30-May-07 04-Jul-07 200 Pcs 100% 3 3 100.00 3 3 100.00 3 100.00 3 100.00 100.00 100.00 100.00 100.00 0.00
Piping 1.04 04-May-07 13-Jul-07 4,411 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Dia Total Dia
Done % Done % Done % Done %
Inch Inch
SHP1010 Fabricate Pipe Supports 0.18 04-May-07 11-Jun-07 751 Dia Inch 100% 33 33 100.00 33 33 100.00 33 100.00 33 100.00 100.00 100.00 100.00 100.00 0.00
SHP1030 Fabricate CS Pipe Spools 0.28 04-May-07 07-Jun-07 1,200 Dia Inch 100% 495 495 100.00 495 495 100.00 495 100.00 495 100.00 100.00 100.00 100.00 100.00 0.00
SHP1040 Testing & Preservation of Pipe Spools 0.04 16-Jun-07 06-Jul-07 160 Dia Inch 100% 11 11 100.00 11 11 100.00 11 100.00 11 100.00 100.00 100.00 100.00 100.00 0.00
SHP1160 Fabricate Duplex Pipe Spools 0.33 26-May-07 21-Jun-07 1,401 Dia Inch 100% 803 803 100.00 803 803 100.00 803 100.00 803 100.00 100.00 100.00 100.00 100.00 0.00
SHP1170 Fabricate SS Pipe Spools 0.14 13-Jun-07 01-Jul-07 599 Dia Inch 100% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
SHP1180 Fabricate GRE Pipe Spools 0.07 26-Jun-07 13-Jul-07 300 Dia Inch 100% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
Electrical 0.11 05-Jun-07 11-Jul-07 480 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1050 Fabricate Electrical Supports 0.07 05-Jun-07 29-Jun-07 300 Pcs 100% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Handling 90% Accept 10%
Done % Done %
SHP1140 Electrical Shiploose Items 0.04 21-Jun-07 11-Jul-07 180 Pcs 100% 7 7 100.00 7 100.00 100.00 100.00 100.00 100.00 0.00
Instrument 0.11 05-Jun-07 11-Jul-07 480 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1060 Fabricate Instrument Supports 0.07 05-Jun-07 29-Jun-07 300 Pcs 100% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Handling 90% Accept 10%
Done % Done %
SHP1150 Instrument Shiploose Items 0.04 21-Jun-07 11-Jul-07 180 Pcs 100% 7 7 100.00 7 100.00 100.00 100.00 100.00 100.00 0.00
Blasting/Painting 0.07 11-Jun-07 24-Jul-07 282 Prep B/P 1st Coat 2nd Coat Accept 100.00 100.00 100.00 100.00 0.00
10% 30% 25% 25% 10%
SHP1070 Blasting/Painting Pipe Supports 0.02 11-Jun-07 28-Jun-07 72 Pcs 100% 33 33 33 33 33 33 100.00 100.00 100.00 100.00 0.00
SHP1080 Blasting/Painting Pipe Spools 0.02 06-Jul-07 24-Jul-07 70 Pcs 100% 100 100 100 100 100 100 100.00 100.00 100.00 100.00 0.00
SHP1090 Blasting/Painting Electrical Supports 0.01 29-Jun-07 09-Jul-07 30 Pcs 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
SHP1100 Blasting/Painting Instrument Supports 0.01 29-Jun-07 09-Jul-07 30 Pcs 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
SHP1110 Blasting/Painting Structural Members 0.01 05-Jul-07 17-Jul-07 40 Pcs 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
SHP1130 Blasting/Painting Mechanical Items 0.01 04-Jul-07 13-Jul-07 40 Pcs 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
LOADOUT & SEAFASTENING SHIPLOOSE 0.05 08-Aug-07 11-Aug-07 192 100.00 100.00 100.00 100.00 0.00
Prep/Chk Packing LO SF Accept
30% 40% 10% 10% 10%
LOA1020 Loadout & Seafastening Shiploose Items 0.05 08-Aug-07 11-Aug-07 192 Compl 100% 100 100 100 100 100 100 100.00 100.00 100.00 100.00 0.00

21 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK

MHRS PLANNED PLANNED BASIS OF LVL 4 EARLY


ACT ID ACTIVITY NAME MHRS EST QTY PROGRESS MEASUREMENT MID PLAN LATE PLAN ACTUAL VAR
WTG START FINISH QTY (UNIT) WTG PLAN

SUMMARY of SCDR-A Topsides OALL WTG


PRELIMINARIES 6.74 19-Jul-06 23-Aug-07 28,043 100.00 100.00 100.00 100.00 0.00
ENGINEERING 7.68 4-Aug-06 6-Aug-07 31,954 100.00 100.00 100.00 100.00 0.00
PROCUREMENT 8.46 7-Aug-06 23-Aug-07 35,196 100.00 100.00 100.00 100.00 0.00
FABRICATION OF SCDR-A TOPSIDES 70.56 22-Sep-06 20-Aug-07 293,578 100.00 100.00 100.00 100.00 0.00
ONSHORE PRE-COMMISSIONING 4.43 21-May-07 28-Aug-07 18,430 100.00 100.00 100.00 100.00 0.00
WEIGHING, LOADOUT & SEAFASTENING 2.13 2-Jul-07 4-Sep-07 8,862 100.00 100.00 100.00 100.00 0.00
OVERALL SCDR-A PROGRESS 100.00 416,065 100.00 100.00 100.00 100.00 0.00

SUMMARY of ENGINEERING
Review Materials 16.22 4-Aug-06 2-Jan-07 5,183 100.00 100.00 100.00 100.00 0.00
Construction Drawings 83.78 4-Aug-06 6-Aug-07 26,771 100.00 100.00 100.00 100.00 0.00
Overall ENGINEERING Progress 100.00 4-Aug-06 6-Aug-07 31,954 100.00 100.00 100.00 100.00 0.00

SUMMARY of PROCUREMENT
Client Supply Materils 8.57 17-Aug-06 23-Aug-07 3,017 100.00 100.00 100.00 100.00 0.00
MMHE Supply Materials 91.43 7-Aug-06 8-Aug-07 32,179 100.00 100.00 100.00 100.00 0.00
Purchase Request to Purchase Order 52.20 7-Aug-06 8-Feb-07 16,796 100.00 100.00 100.00 100.00 0.00
Purchase Order to Delivery 0.00 3-Oct-06 23-Jul-07 - 0.00 0.00 0.00 0.00 0.00
Materials Receiving Inspection 47.80 29-Nov-06 8-Aug-07 15,383 100.00 100.00 100.00 100.00 0.00
Overall PROCUREMENT Progress 100.00 7-Aug-06 23-Aug-07 35,196 100.00 100.00 100.00 100.00 0.00

SUMMARY of Fabrication SCDR-A Topsides


Structural 34.82 12-Oct-06 18-Jun-07 102,218 100.00 100.00 100.00 100.00 0.00
Blasting/Painting 6.87 22-Sep-06 31-Jul-07 20,182 100.00 100.00 100.00 100.00 0.00
Piping 21.73 13-Jan-07 15-Aug-07 63,797 100.00 100.00 100.00 100.00 0.00
Mechanical 7.92 15-Feb-07 20-Aug-07 23,256 100.00 100.00 100.00 100.00 0.00
Electrical 9.55 28-Feb-07 3-Aug-07 28,038 100.00 100.00 100.00 100.00 0.00
Instrument 10.57 28-Feb-07 8-Aug-07 31,045 100.00 100.00 100.00 100.00 0.00
Architectural 3.37 24-Mar-07 26-Jul-07 9,882 100.00 100.00 100.00 100.00 0.00
HVAC 3.22 2-Apr-07 19-Jul-07 9,461 100.00 100.00 100.00 100.00 0.00
Safety 0.97 4-Jun-07 15-Aug-07 2,850 100.00 100.00 100.00 100.00 0.00
Others Materials 0.97 31-Jul-07 16-Aug-07 2,850 100.00 100.00 100.00 100.00 0.00
Overall Fabrication Progress 100.00 22-Sep-06 20-Aug-07 293,578 100.00 100.00 100.00 100.00 0.00

SUMMARY of E11K-A SHIPLOOSE ITEMS


ENGINEERING 6.37 21-Aug-06 25-Jan-07 520 100.00 100.00 100.00 100.00 0.00
PROCUREMENT 9.78 5-Oct-06 5-Jun-07 798 100.00 100.00 100.00 100.00 0.00
FABRICATION 81.50 4-May-07 24-Jul-07 6,652 100.00 100.00 100.00 100.00 0.00
LOADOUT & SEAFASTENING SHIPLOOSE 2.35 8-Aug-07 11-Aug-07 192 100.00 100.00 100.00 100.00 0.00
Overall E11K-A SHIPLOOSE ITEMS Progress 100.00 30-Mar-14 5-Mar-15 8,164 100.00 100.00 100.00 100.00 0.00

22 of 22
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 5 - PROJECT ORGANIZATION CHART


SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 6 - SUBCONTRACTOR EVALUATION SHEET


MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36006607
WORK DESCRIPTION : STRUCTURAL WORKS @ SCDR-A TOPSIDES
SUB-CONTRACTOR : KEJUYUTERAAN WIJAYA SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : ARNEL MENDOZA
DESIGNATION : SCTRUCTURAL/ACHITECTURAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 13, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


FAMILIARITY/ COMPLIANCE WITH
I 4 Average
MMHE’S BASIC PRACTICES
FAMILIARITY/ COMPLIANCE WITH JOB
II 4 Average
SPECIFICATIONS
III DETAILED ENGINEERING
Economy of Design 3 Meets the desired standard of performance.
Efficiency/ Correctness of Techniques 3 Meets the desired standard of performance.
Technical Acceptability of Result 4 Average
Quality of Personnel/ Supervisor 4 Average
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 4 Average
Coordination of Various Disciplines
4 Average
and Phases of Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 3 Meets the desired standard of performance.

VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average

Sharpness of Buying 4 Average

VII SUBCONTRACTS
Selection of Subcontractors 4 Average
Personnel/ Supervision 4 Average
VIII EXPEDITING 4 Average
IX BULK MATERIAL CONTROL 4 Average
ESTIMATING, COST REPORTING & COST
X 4 Average
CONTROL.
XI PLANNING/ SCHEDULING IN WORK 4 Average
XII PROCESSING OF CHANGES IN WORK 4 Average
XIII FIELD EFFICIENCY 4 Average
OVERALL RATING 4 Average, Few weaknesses.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ Management is short of comments that leads to unpleasant discussion..
2. Any special factors that affected subcontractor’s performance on this project.
™ Submitted plan were just for compliance but not workable.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36007629
WORK DESCRIPTION : ARCHITECTURAL WORKS
SUB-CONTRACTOR : ARROW PLATFORM (M) SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : ARNEL MENDOZA
DESIGNATION : SCTRUCTURAL/ACHITECTURAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 17, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


FAMILIARITY/ COMPLIANCE WITH MMHE’S BASIC
I 4 Average, with few weaknesses.
PRACTICES
II FAMILIARITY/ COMPLIANCE WITH JOB SPECIFICATIONS 4 Average, with few weaknesses.
III DETAILED ENGINEERING
Economy of Design 4 Average, with few weaknesses.
Efficiency/ Correctness of Techniques 4 Average, with few weaknesses.
Technical Acceptability of Result 4 Average, with few weaknesses.
Quality of Personnel/ Supervisor 4 Average, with few weaknesses.
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 4 Average, with few weaknesses.
Coordination of Various Disciplines and Phases of
4 Average, with few weaknesses.
Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 4 Average, with few weaknesses.

VI MATERIAL PURCHASING
Knowledge of Vendors 5 Low Average, with some weaknesses

Sharpness of Buying 5 Low Average, with some weaknesses

VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
OVERALL RATING 4 Average, Few weaknesses.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ They can perform the work but unable to meet the desired MMHE standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
™ Expediting effort on submission of Vendor Data or on delivery of materials, failed to
expedite successfully.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36007625
WORK DESCRIPTION : FABRICATION & INSTALLATION OF PIPING WORKS
SUB-CONTRACTOR : JURUNATURE SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : MOHD SUBHA B. RI
DESIGNATION : PIPING SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 18, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


FAMILIARITY/ COMPLIANCE WITH
I 3 Generally meets desired standard of performance.
MMHE’S BASIC PRACTICES
FAMILIARITY/ COMPLIANCE WITH JOB
II 3 Generally meets desired standard of performance.
SPECIFICATIONS
III DETAILED ENGINEERING
Economy of Design 3 Generally meets desired standard of performance.
Efficiency/ Correctness of Techniques 3 Generally meets desired standard of performance.
Technical Acceptability of Result 3 Generally meets desired standard of performance.
Quality of Personnel/ Supervisor 3 Generally meets desired standard of performance.
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 2 Always meets desired standard of performance.
Coordination of Various Disciplines and
2 Always meets desired standard of performance.
Phases of Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 2 Always meets desired standard of performance.

VI MATERIAL PURCHASING
Knowledge of Vendors 3 Generally meets desired standard of performance.

Sharpness of Buying 3 Generally meets desired standard of performance.

VII SUBCONTRACTS
Selection of Subcontractors 3 Generally meets desired standard of performance.
Personnel/ Supervision 4 Average, low of supervision & monitoring.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses of monitoring.
ESTIMATING, COST REPORTING & COST
X 3 Generally meets desired standard of performance.
CONTROL.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 3 Generally meets desired standard of performance.
XIII FIELD EFFICIENCY 3 Generally meets desired standard of performance.
OVERALL RATING 3 Generally meets desired standard of performance.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ They can perform the work & meet the desired MMHE standard of performance.
2. Any special factors that affected subcontractor’s performance on this project.
™ Strong support to the Project Team.
™ Meet the project schedule.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36007624
WORK DESCRIPTION : FABRICATION & INSTALLATION OF GRE PIPES
SUB-CONTRACTOR : AMERSTARND ENGINEERING SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : MOHD SUBHA B. RI
DESIGNATION : PIPING SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 18, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


FAMILIARITY/ COMPLIANCE WITH MMHE’S BASIC
I 4 Average, with few weaknesses.
PRACTICES
II FAMILIARITY/ COMPLIANCE WITH JOB SPECIFICATIONS 4 Average, with few weaknesses.
III DETAILED ENGINEERING
Economy of Design 4 Average, with few weaknesses.
Efficiency/ Correctness of Techniques 4 Average, with few weaknesses.
Technical Acceptability of Result 4 Average, with few weaknesses.
Quality of Personnel/ Supervisor 4 Average, with few weaknesses.
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 4 Average, with few weaknesses.
Coordination of Various Disciplines and Phases of
4 Average, with few weaknesses.
Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 4 Average, with few weaknesses.

VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average, with few weaknesses.

Sharpness of Buying 4 Average, with few weaknesses.

VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
Average, with few weaknesses of
IX BULK MATERIAL CONTROL 4
monitoring.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
OVERALL RATING 4 Average, with few weaknesses.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ They can perform the work but cannot meet the desired MMHE standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
™ Strong support to the Project team.
™ Meet the project schedule.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36007625
WORK DESCRIPTION : MECHANICAL INSTALLATION WORKS
SUB-CONTRACTOR : JURUNATURE SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351
NAME OF RATER : ABD RAZAK ABU BAKAR
DESIGNATION : MECHANICAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 17, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS

FAMILIARITY/ COMPLIANCE WITH MMHE’S BASIC


I 3 Meets the desired standard of performance.
PRACTICES
FAMILIARITY/ COMPLIANCE WITH JOB
II 3 Performed work with less outside support.
SPECIFICATIONS
III DETAILED ENGINEERING
Economy of Design 3 Meets the desired standard of performance.
Efficiency/ Correctness of Techniques 3 Meets the desired standard of performance.
Technical Acceptability of Result 3 Meets the desired standard of performance.
Quality of Personnel/ Supervisor 3 Meets the desired standard of performance.
IV ENGINEERING PRODUCTIVITY
Always exceed the desired standard of
Work Output of Personal 2
performance.
Coordination of Various Disciplines and Phases of Always exceed the desired standard of
2
Project Execution performance.
V PROCUREMENT ENGINEERING
Selection of Materials/ Equipment 3 Meets the desired standard of performance.
VI MATERIAL PURCHASING

Knowledge of Vendors 3 Meets the desired standard of performance.


Sharpness of Buying 3 Meets the desired standard of performance.
VII SUBCONTRACTS
Selection of Subcontractors 3 Meets the desired standard of performance.
Personnel/ Supervision 3 Meets the desired standard of performance.
VIII EXPEDITING 4 Average
IX BULK MATERIAL CONTROL 3 Meets the desired standard of performance.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average
XI PLANNING/ SCHEDULING IN WORK 3 Meets the desired standard of performance.
XII PROCESSING OF CHANGES IN WORK 3 Meets the desired standard of performance.
Always exceed the desired standard of
XIII FIELD EFFICIENCY 2
performance.
OVERALL RATING 3 Meets the desired standard of performance.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ Performed works and meet the desired standard of performance.
2. Any special factors that affected subcontractor’s performance on this project.
™ Strong team personnel/supervision at site.
™ All materials meet the delivery target/schedule.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36007628
WORK DESCRIPTION : ELECTRICAL & INSTRUMENTATION WORKS
SUB-CONTRACTOR : ASADRA (M) SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : TEODORO D. FLORES
DESIGNATION : ELECTRICAL / INSTRUMENTATION SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 10, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


Few weaknesses, can perform work but
FAMILIARITY/ COMPLIANCE WITH MMHE’S BASIC
I 4 cannot meet the desired standard of
PRACTICES
performance.
Cannot perform work without outside
II FAMILIARITY/ COMPLIANCE WITH JOB SPECIFICATIONS 7
support.
III DETAILED ENGINEERING
Economy of Design 7 Unsatisfactory performance.
Efficiency/ Correctness of Techniques 7 Unsatisfactory performance.
Technical Acceptability of Result 6 Below average.
Quality of Personnel/ Supervisor 4 Average, with few weaknesses.
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 5 Low average, with some weaknesses.
Coordination of Various Disciplines and Phases of
4 Average, with few weaknesses.
Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 4 Average, with few weaknesses.

VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average, with few weaknesses.

Sharpness of Buying 4 Average, with few weaknesses.

VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
Many weaknesses. Can perform work
OVERALL RATING 6 but cannot meet the desired standard
of performance.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ Many weaknesses. Can perform work but cannot meet the desired standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
™ Delay in delivery of materials.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36007627
WORK DESCRIPTION : BLASTING & PAINTING WORKS
SUB-CONTRACTOR : BB TECH SERVICES SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : SANUSI HANAFI
DESIGNATION : BLASTING & PAINTING SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 18, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


FAMILIARITY/ COMPLIANCE WITH MMHE’S BASIC
I 4 Average, with few weaknesses.
PRACTICES
II FAMILIARITY/ COMPLIANCE WITH JOB SPECIFICATIONS 4 Average, with few weaknesses.
III DETAILED ENGINEERING
Economy of Design 4 Average, with few weaknesses.
Efficiency/ Correctness of Techniques 4 Average, with few weaknesses.
Technical Acceptability of Result 4 Average, with few weaknesses.
Quality of Personnel/ Supervisor 4 Average, with few weaknesses.
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 4 Average, with few weaknesses.
Coordination of Various Disciplines and Phases of
4 Average, with few weaknesses.
Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 4 Average, with few weaknesses.

VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average, with few weaknesses.

Sharpness of Buying 4 Average, with few weaknesses.

VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
OVERALL RATING 4 Average, Few weaknesses.

GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ They can perform the work but unable to meet the desired MMHE standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
™ Sometimes lack of manpower & equipment.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.

Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

SUBCONTRACTOR PERFORMANCE EVALUATION

SUB-CONTRACT NO : 36006616
WORK DESCRIPTION : HVAC SYSTEM FABRICATION & INSTALLATION
SUB-CONTRACTOR : DYNAC SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : ABD RAZAK ABU BAKAR
DESIGNATION : MECHANICAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 17, 2007

NO. CRITERIA FOR EVALUATION RATING REMARKS


FAMILIARITY/ COMPLIANCE WITH MMHE’S BASIC Few weaknesses by meets the desired
I 4
PRACTICES standard of performance.
Performed work with less outside
II FAMILIARITY/ COMPLIANCE WITH JOB SPECIFICATIONS 3
support.
III DETAILED ENGINEERING
Meets the desired standard of
Economy of Design 3
performance.
Efficiency/ Correctness of Techniques 4 Average.
Technical Acceptability of Result 4 Average.
Meets the desired standard of
Quality of Personnel/ Supervisor 3
performance.
IV ENGINEERING PRODUCTIVITY
Work Output of Personal 4 Average.
Coordination of Various Disciplines and Phases of
4 Average.
Project Execution
V PROCUREMENT ENGINEERING

Selection of Materials/ Equipment 4 Average.

VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average.

Sharpness of Buying 4 Average.

VII SUBCONTRACTS
Meets the desired standard of
Selection of Subcontractors 3
performance.
Meets the desired standard of
Personnel/ Supervision 3
performance.
VIII EXPEDITING 4 Average
IX BULK MATERIAL CONTROL 4 Average.
Meets the desired standard of
X ESTIMATING, COST REPORTING & COST CONTROL. 3
performance.
XI PLANNING/ SCHEDULING IN WORK 4 Average
XII PROCESSING OF CHANGES IN WORK 4 Average
Meets the desired standard of
XIII FIELD EFFICIENCY 3
performance.
OVERALL RATING 4 Average
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
™ Meet the desired standard of performance, but needs to improve planning work schedule.
2. Any special factors that affected subcontractor’s performance on this project.
™ Shortage / less manpower working direct at site.
™ Improve procurement of material schedule.
™ Need improvement on Planning, Procurement & key personnel at site.
3. Any reservation on this subcontractor getting future MMHE work.
™ Recommend for future MMHE work.
Page 1 / 1
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 7 - FABRICATION YARD


SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 8 - RFQ / CO / VOP Log


MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
CHANGE ORDER (CO)/VARIATION ORDER (VO) REGISTER Date: 6-Nov-07

NO RFQ VOP CO VO DESCRIPTION CO AMOUNT VO AMOUNT REMARKS


NO NO NO NO
1 NA 001 001 001 PPE For Fabrication : Use of Coverall 65,049.60 65,049.60 Closed
2 NA NA 002 Training for SSB personnel 11,610.00 SSB to issue VO
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
TOTAL 76,659.60 65,049.60
Appendix 7
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
REQUEST FOR QUOTATION /VARIATION ORDER PROPOSAL /CHANGE ORDER/VARIATION ORDER REGISTER
CONTRACT SUM (RM) 75,167,286.00
Date : 0-Jan-00
Approved VARIATION ORDER
STATUS
REQUEST FOR QUOTATION (RFQ) RFQ REPLY FROM MMHE Amount Pending Amount Rejected Amount CHANGE ORDER (C.O) (V.O)
RM Estimated % to Amount RM INVOICING OTHER REMARKS
RFQ COST ESTIMATE RFQ OR VO PHYSICAL
DESCRIPTION REV. DATE ISSUED REV. DATE ISSUED recognize CO NO RM VO NO RM
NO (RM) PROCESSING WORK STATUS
RM as sales RM NO. DATE

A) PROVISIONAL SUM (PS)

01
PROVISIONAL SUM-PART 3;SCHEDULE OF PRICES AND RATES;ITEM 9 - SUPPLY ADDITIONAL HOOK-UP MATERIALS, OFFSHORE COMMISSIONING SPARES, START-UP SPARES and 1 Year OPERATING SPARES

1st Order 12/04/2006 161,372.68 161,372.68 In Progress Approved


2nd Order 03/08/2007 407,855.71 407,855.71 In Progress Approved
3rd Order 04/11/2007 107,395.70 107,395.70 In Progress Approved
Transportation charges 25/8/07 39,210.71 0.00 39,210.71 50% 19,605.36

SUB-TOTAL PS - ITEM (9)


715,834.80 676,624.09 19,605.36

PROVISIONAL SUM - PART 3:SCHEDULE OF PRICE AND RATES;ITEM 5- AFB-AFC CHANGES

Structural
12/12/06 175,066.45 175,066.45 In Progress Approved

Electrical (Except for Cables)


06/02/07 161,436.00 161,436.00 In Progress Approved

Electrical ( for Cables)


18/05/07 60,480.00 60,480.00 In Progress Approved

Piping (includes Post AFC


Rev. A1) 12/03/07 104,615.00 104,615.00 In Progress Approved

Pipe Supports
27/03/07 1,793.22 1,793.22 In Progress Approved

Instrument 12/05/07 -40,709.00 -40,709.00 In Progress Approved


Mechanical 31/05/07 15,306.85 15,306.85 In Progress Approved

SUB-TOTAL PS - ITEM (5)


477,988.52 477,988.52 0.00
TOTAL PS
1,193,823.32 1,154,612.61 19,605.36
Appendix 7
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
REQUEST FOR QUOTATION /VARIATION ORDER PROPOSAL /CHANGE ORDER/VARIATION ORDER REGISTER
CONTRACT SUM (RM) 75,167,286.00
Date : 0-Jan-00
Approved VARIATION ORDER
STATUS
REQUEST FOR QUOTATION (RFQ) RFQ REPLY FROM MMHE Amount Pending Amount Rejected Amount CHANGE ORDER (C.O) (V.O)
RM Estimated % to Amount RM INVOICING OTHER REMARKS
RFQ COST ESTIMATE RFQ OR VO PHYSICAL
DESCRIPTION REV. DATE ISSUED REV. DATE ISSUED recognize CO NO RM VO NO RM
NO (RM) PROCESSING WORK STATUS
RM as sales RM NO. DATE

B) REQUEST FOR QUOTATION (RFQ)


02 40' Porta Cabin for Company Completed MMHE to Reply
Commissioning Team

03 2 nos of Antenna Mounting Refer to Completed


Stands Incoporated in
19/4/07 Instrument AFB- AFB/AFC change Approved
for Instrument
AFC changes
04 Supply 14" Hanger Flange & 25/5/07 229,696.39 229,696.39 Under
Flange below SDV for SCDR- Procurement
A to E11K-A Pipeline 29/9/07 100% 229,696.39 SSB to Reply

05 Offshore Pre-Drilled Scope of 10/08/07 On progress


Works MMHE to Reply

06 Supply Fire Fighting 22/8/07 Under


Equipment Procurement MMHE to Reply

07 Temporary Lighting 09/04/2007 Under


Procurement MMHE to Reply

08 Supply and install quick 4/9/07 Under


release exhaust valve Procurement
complete with tubings and MMHE to Reply
fittings
09 Instrument materials for Under
offshore Hook-up Procurement MMHE to Reply

10 Rigging Gear for Sand Bin V- Under


0410A/B Procurement MMHE to Reply

NA Training for SSB personnel 02 On-going WGO pending


11,610.00 11,610.00
issuance

TOTAL RFQ 229,696.39 11,610.00 229,696.39 229,696.39 0.00 11,610.00 0.00

C) VARIATION ORDER PROPOAL (VOP)

VOP 1: PPE For Fabrication : Completed Approved


Use of Coverall 02/06/07 65,049.60 65,049.60 01 65,049.60 01 65,049.60

VOP 2:Red Color Painting For Completed


08/05/07 23,662.62 23,662.62 Rejected
Firewater Lines
VOP 3:Revised Sand Bin Leg Refer VOP Incoporated in Incoporated in Completed
Connection AFB/AFC AFB/AFC
16/05/07 Approved
remeasurement remeasurement
Register for Mechanical for Mechanical
Appendix 7
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
REQUEST FOR QUOTATION /VARIATION ORDER PROPOSAL /CHANGE ORDER/VARIATION ORDER REGISTER
CONTRACT SUM (RM) 75,167,286.00
Date : 0-Jan-00
Approved VARIATION ORDER
STATUS
REQUEST FOR QUOTATION (RFQ) RFQ REPLY FROM MMHE Amount Pending Amount Rejected Amount CHANGE ORDER (C.O) (V.O)
RM Estimated % to Amount RM INVOICING OTHER REMARKS
RFQ COST ESTIMATE RFQ OR VO PHYSICAL
DESCRIPTION REV. DATE ISSUED REV. DATE ISSUED recognize CO NO RM VO NO RM
NO (RM) PROCESSING WORK STATUS
RM as sales RM NO. DATE
On-going
VOP 4:WHCP Accumulator
Material Substitution From 16/05/07 278,351.00 278,351.00 70% 194,845.70 SSB to Reply
Bladder Type To Piston

VOP 5:Vessel Vendor Change Completed


12/05/07 15,091.00 15,091.00 Rejected
To VDP
VOP 6:Wellhead Control Completed
Panel - Additional ball Valve & 12/05/07 77,641.88 77,641.88 90% 69,877.69 SSB to Reply
Check
Completed
VOP 7:Additional Cantilever
Beam for Blastwall support
(STQ no. A-008),Additional
Amount agreed by
steel works to infill the gaps
25/05/07 25,534.90 25,534.90 100% 25,534.90 SSB. SSB to issue
(STQ no A-009),Additional
CO
wings plates (STQ no-
045),Wiremesh Material
Proposal

Completed Amount agreed by


VOP 8 :Additional AFC Rev A
09/06/07 24,309.74 24,309.74 100% 24,309.74 SSB. SSB to issue
due to VDI(Desender)
CO
VOP 9 :STQ-S-50;material Completed SSB to Reply
substitution from 50mm thk to 15/06/07 12,483.87 12,483.87 50% 6,241.94
60mm thk. (SSB supply)
VOP 10 :First Fill - Chemical On-going SSB to Reply
For Corrosion Inhibitor Skid 21/06/07 166,603.50 166,603.50 50% 83,301.75

VOP 11 :Additional Flanges On-going SSB to Reply


(as per STQ No. P-013 & P- 29/06/07 22,977.00 80% 18,381.60
019) 22,977.00
VOP 12 : Additional Switches On-going SSB to Reply
1,473.00 50% 736.50
for toilet, STQ-E-013 18/07/07 1,473.00
VOP 13 :Additional Beacon, On-going SSB to Reply
21,288.88 80% 17,031.10
STQ-E-008 & E-012 19/07/07 21,288.88
VOP 14 :Fabricate and Install Completed MMHE to resubmit
16,127.56 80% 12,902.05
Cageladder and Handrail 24/07/07 14,339.18
VOP 15 :Additional 10mm Completed SSB to Reply
Thick Plate (S-055), Additional
Structural Support for Lift Raft
28/07/07 4,937.46 4,937.46 90% 4,443.71
Along Platform (S-062), and
Fabricate and Install Deck
Drain (S-065)
VOP 16:Re-routing and On-going SSB to Reply

Change of Piping Material of 1/8/07 3,191.48 3,191.48 90% 2,872.33

Portable Water Line to Toilet


VOP 17: Supply Ball Valves On-going SSB to Reply
13/8/2007 225,341.50 225,341.50 100% 225,341.50
on behalf of COMPANY
Appendix 7
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
REQUEST FOR QUOTATION /VARIATION ORDER PROPOSAL /CHANGE ORDER/VARIATION ORDER REGISTER
CONTRACT SUM (RM) 75,167,286.00
Date : 0-Jan-00
Approved VARIATION ORDER
STATUS
REQUEST FOR QUOTATION (RFQ) RFQ REPLY FROM MMHE Amount Pending Amount Rejected Amount CHANGE ORDER (C.O) (V.O)
RM Estimated % to Amount RM INVOICING OTHER REMARKS
RFQ COST ESTIMATE RFQ OR VO PHYSICAL
DESCRIPTION REV. DATE ISSUED REV. DATE ISSUED recognize CO NO RM VO NO RM
NO (RM) PROCESSING WORK STATUS
RM as sales RM NO. DATE
VOP 18 :Lifebuoy Quantity On-going SSB to Reply
15/8/2007 1,397.50 1,397.50 90% 1,257.75
(STQ No. M-027)
VOP 19 :IRP-7875 and IRP- On-going SSB to Reply
7802 Rewiring - New Scope 22/8/2007 6,450.00 6,450.00 90% 5,805.00
(STQ-E-031)
VOP 20 :Change of On-going SSB to Reply
specification for Washdown 25/8/2007 7,839.98 7,839.98 90% 7,055.98
Hose Reel
VOP 21 ;Storage of SSB Completed SSB to Reply
22/8/2007 29,095.00 29,095.00 90% 26,185.50
Surplus Material
VOP 22)Cost Impact for STQ SSB to Reply
No. M-032 and STQ No. M- 28/8/2007 38,524.94 38,524.94 90% 34,672.45
033
VOP 23) SCDR-A Flame SSB to Reply
7/9/07 28,487.50 28,487.50 90% 25,638.75
Detector - Isolator
VOP 24)AUX Power Supply SSB to Reply

From UPS DB-7815 to TF- 7/9/07 750.00 750.00 90% 675.00

7505 (STQ No. E-030)


VOP 25)Additional Portable SSB to Reply
Eyewash Station (STQ No. E- 11/9/07 1,483.50 1,483.50 90% 1,335.15
035)
VOP 26) Additional 2 nos of SSB to Reply
MCT and cable ladders due to
14/9/2007 7,012.50 7,012.50 90% 6,311.25
reroute of cable from RMU to
Transformer (STQ No. E-019)
VOP 27)Supply and Install SSB to Reply
10/04/2007 21,983.51 21,983.51 70% 15,388.46
Sunshade
VOP 28)Cost Impact for STQ SSB to Reply
10/05/2007 19,413.16 19,413.16 90% 17,471.84
P-023 and S-069

TOTAL VOP 1,144,714.20 65,049.60 1,042,699.36 79% 827,617.64 38,753.62 65,049.60 65,049.60

TOTAL PS+VOP + RFQ 1,374,410.59 76,659.60 1,272,395.75 85% 1,076,919.39 38,753.62 76,659.60 65,049.60
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
REQUEST FOR QUOTATION REGISTER

Date : 20-Oct-2007

NO DESCRIPTION AMOUNT (RM) REMARKS

1 CONTRACT SUM 75,167,286.00


2 APPROVED PS 1,154,612.61
3 APPROVED RFQ/VOP 76,659.60
4 PS/RFQ/VOP pending approval 1,076,919.39
5 REVISED CONTRACT SUM(RM) 77,475,477.60
Appendix 6
VARIATION ORDER PROPOSAL (VOP) REGISTER

CONTRACT NO. : 591397


CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES Date 0-Jan-00

VARIATION ORDER PROPOSAL


AMOUNT VOP PROCESSING
VOP No. DESCRIPTION DATE SUBMITTED APPROVED REMARKS
ISSUED RM RM

001 PPE For Fabrication : Use of Coverall 20/12/06 65,049.60 65,049.60 Aproved CO-1/VO-1
002 Red Color Painting For Firewater Lines 08/05/07 23,662.62 Rejected
Revised Sand Bin Leg Connection
Incoporated in AFB/AFC
003 16/05/07 1,312.00 1,312.00
remeasurement for Mechanical
Approved

004 WHCP Accumulator Material Substitution From Bladder Type To Piston 16/05/07 278,351.00 SSB to Reply

005 Vessel Vendor Change To VDP 12/05/07 15,091.00 Rejected


006 Wellhead Control Panel - Additional ball Valve & Check 12/05/07 77,641.88 SSB to Reply

Additional Cantilever Beam for Blastwall support (STQ no. A- Amount agreed in
007 008),Additional steel works to infill the gaps (STQ no A-009),Additional 25/05/07 25,534.90 25,534.90 principle.SSB to issue SSB to issue CO
wings plates (STQ no-045),Wiremesh Material Proposal CO

Amount agreed in
008 Additional AFC Rev A due to VDI(Desender) 09/06/07 24,309.74 24,309.74 principle.SSB to issue SSB to issue CO
CO
STQ-S-50;material substitution from 50mm thk to 60mm thk. (SSB
009 15/06/07 12,483.87 SSB to Reply
supply)
010 First Fill - Chemical For Corrosion Inhibitor Skid 21/06/07 166,603.50 SSB to Reply
011 Additional Flanges (as per STQ No. P-013 & P-019) 29/06/07 22,977.00 SSB to Reply
012 Additional Switches for toilet, STQ-E-013 18/07/07 1,473.00 SSB to Reply
013 Additional Beacon, STQ-E-008 & E-012 19/07/07 21,288.88 SSB to Reply
Fabricate and Install Cageladder and Handrail @battery Room, STQ-S-
SSB to Reply
014 058 24/07/07 16,127.56
Additional 10mm Thick Plate (S-055), Additional Structural Support for
015 Lift Raft Along Platform (S-062), and Fabricate and Install Deck Drain (S- 28/07/07 4,937.46 SSB to Reply
065)
Re-routing and Change of Piping Material of Portable Water Line to
016 08/01/2007 3,191.48 SSB to Reply
Toilet,STQ-P-21
017 Supply Ball Valves on behalf of COMPANY 13/8/2007 225,341.50 SSB to Reply

018 Lifebuoy Quantity (STQ No. M-027) 15/8/2007 1,397.50 SSB to Reply
019 IRP-7875 and IRP-7802 Rewiring - New Scope (STQ-E-031) 22/8/2007 6,450.00 MMHE to resubmit
VARIATION ORDER PROPOSAL
AMOUNT VOP PROCESSING
VOP No. DESCRIPTION DATE SUBMITTED APPROVED REMARKS
ISSUED RM RM
020 Change of specification for Washdown Hose Reel 25/8/2007 7,839.98 SSB to Reply

021 Storage of SSB Surplus Material 22/8/2007 29,095.00 SSB to Reply

022 Cost Impact for STQ No. M-032 and STQ No. M-033 28/8/2007 38,524.94 SSB to Reply

023 SCDR-A Flame Detector - Isolator 09/07/2007 28,487.50 SSB to Reply

024 AUX Power Supply From UPS DB-7815 to TF-7505 (STQ No. E-030) 09/07/2007 750.00 SSB to Reply

025 Additional Portable Eyewash Station (STQ No. E-035) 09/11/2007 1,483.50 SSB to Reply
026 Additional 2 nos of MCT and cable ladders due to reroute of cable from
14/9/2007 7,012.50 SSB to Reply
RMU to Transformer (STQ No. E-019)
027 Supply and Install Sunshade 10/04/2007 21,983.51 SSB to Reply
028 Cost Impact for STQ P-023 and S-069 10/05/2007 19,413.16 SSB to Reply

TOTAL 1,147,814.58 116,206.24

MALAYSIA MARINE AND HEAVY ENGINEERING SDN. BHD.


ENGINEERING AND CONSTRUCTION DIVISION

Note :
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 9 - ERECTION SEQUENCE


SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.

APPENDIX 10 - PROGRESS PHOTOGRAPHS


13-09-06 CLIENT SUPPLIED MATERIALS (‘I’ BEAM)

14-09-06 CLIENT SUPPLIED MATERIAL (STEEL PLATES)

15-09-06 CLIENT SUPPLIED MATERIALS ( TUBULARS)


02-10-06 ‘I’ BEAM AUTO BLASTING

03-10-06 ‘I’ BEAM AFTER AUTO BLAST

04-10-06 ‘I’ BEAM SPRAY WITH DECK PRIMIER COATING


08-10-06 STEEL PLATE COMPLETED BLAST & COATED WITH
DECK PRIMIER

12-10-06 WITNESS THE FIRST CUT CEREMONY

14-10-06 AUTO BLASTING PAINTING OF TUBULAR IN


PROGRESS
01-11-06 DISPLAY PPE SIGN BOARD & FIRE FIGHTING
EQUIPMENT @ SITE

09-11-06 GROUND BREAKING @ FAB.1

13-11-06 CELLAR DECK FRAMING MARKING CUTTING


18-11-06 LAY SKID BASE ON PENNY WEIGHT @ SITE

20-11-06 ERECT TEMPORARY VERTICAL BRACES ON


PENNY WEIGHTS @ SITE

27-11-06 ARRANGE MAIN DECK PANEL TEMP.


SUPPORTS & PENNY WEIGHTS @ SITE IN PROGRESS
01-12-06 LEG ROW A1 MARKING ON ELECTRICAL
OPERATED ROLLER

02-12-06 WELDING ROW 3A,2A,B1 & A1 STABBING


CONES IN PROGRESS

03-12-06 MAIN DECK PANEL SITE ASSEMBLY


PREPARATION IN PROGRESS
04-12-06 ERECT SCUFFOLDING ON MAIN DECK PANEL
TEMPORARY SUPPORT

05-12-06 CELLAR DECK PANEL TEMPORARY SUPPORTS


LEVELLING CHECK

06-12-06 CELLAR DECK PANEL 1ST PRIMARY FRAME


LAYING
07-12-06 MAIN DECK PRIMARY FRAME MARKING IN
PROGRESS

08-12-06 TOP/BOTTOM FLANGE PLATES FITTING

09-12-06 STABBING COLUMN INTERNAL WELDING


10-12-06 CELLAR DECK PANEL PRIMARY FRAMES
ASSEMBLY

11-12-06 WELDING ROW B1 STABBING COLUMN IN


PROGRESS

12-12-06 CELLAR DECK PANEL PRIMARY FRAMES


ASSEMBLY
13-12-06 CELLAR DECK PANEL PRIMARY FRAMES
ASSEMBLY

14-12-06 ‘SAW’ STABBING COLUMN ROW B1

15-12-06 MAIN DECK PANEL ASSEMBLY SITE


PREPARATION
16-12-06 LEVELLING CHECK ON MAIN DECK PANEL
TEMPORARY SUPPORTS

17-12-06 CELLAR DECK PANEL TOP & BOTTOM FLANGE


PLATES FITTING IN SITU

18-12-06 MAIN DECK PRIMARY FRAME CUTTING


19-12-06 COLUMN FIT-UP

20-12-06 CELLAR DECK PANEL ASSEMBLY IN


PROGRESS

21-12-06 STUBBING CONE LINER FITTING


22-12-06 CELLAR DECK PANEL ASSEMBLY

23-12-06 FIT-UP MAIN DECK PANEL PRIMARY FRAME

24-12-06 ‘UT’ & ‘MPI’ STUBBING COLUMN WELDING


JOINT
26-12-06 GAUGE STUBBING CONE COATING

27-12-06 CELLAR DECK PANEL ASSEMBLY IN


PROGRESS

28-12-06 INSTALL STUBBING LEG @ ROW A3 ON CELLAR


DECK
29-12-06 INSTALL STUBBING LEG @ ROW A1

30-12-06 FABRICATING MAIN DECK SKID BEAMS

31-12-06 WELDING & VISUAL INSPECTION MAIN DECK


PRIMARY FRAME
01-01-07 AERIAL VIEW OF CELLAR DECK PANEL
ASSEMBLY

02-01-07 FIT-UP MAIN DECK SKID BEAM TOP & BOTTOM


FLANGE PLATE

03-01-07 MAIN COLUMN ROW A1 LIFTING LUG VISUAL


INSPECTION
04-01-07 MEZZAININE DECK PANEL FRAMINGS
ASSEMBLY

05-01-07 MAIN DECK PANEL FRAMINGS ASSEMBLY

06-01-07 MAIN COLUMN ROW B2 LIFTING LUG


COMPLETED GRINDING
07-01-07 CELLAR DECK PANEL FRAME JOINTS WELDING
IN PREPARATION

08-01-07 MAIN DECK SKID BEAM FLANGE PLATE


STRONG BACK FITTING

09-01-07 ‘UT’ & ‘MPI’ ROW 2A STABBING COLUMN


WELDING JOINT
10-01-07 MAIN DECK PANEL ASSEMBLY IN PROGRESS

11-01-07 WELDING CELLAR DECK PANEL FRAME


JOINTS IN PROGRESS

12-01-07 ‘SAW’ MAIN DECK SKID BEAM WELDING JOINT


13-01-07 MAIN DECK PANEL PRIMARY/SECONDARY
FRAME FITTING

14-01-07 ERECT VERTICAL BRACES ON CELLAR DECK


@ ROW A4 & B4

15-01-07 DIAGONAL BRACE PROFILE MARKING &


CUTTING
16-01-07 HANDRAIL FABRICATION

17-01-07 CELLAR DECK PRIMARY FRAME WELDING JOINT


VISUAL & ‘MPI’

18-01-07 ERECT STABBING COLUMN @ ROW A2


19-01-07 ERECT MAIN COLUMN @ ROW A1

20-01-07 FABRICATED HANDRAILS

21-01-07 HANDRAILS JOINTS WELDING


22-01-07 ERECT STABBING COLUMN @ ROW B2

23-01-07 ERECT 6 NOS. OF STABBING COLUMNS ON


CELLAR DECK COMPLETED

24-01-07 ERECT CELLAR DECK FIRST DIAGONAL


BRACE @ ROW A4
25-01-07 CELLAR DECK VERTICAL BRACE FITTING

26-01-07 ERECT OTHERS DIAGONAL BRACES ON


CELLAR DECK

27-01-07 CELLAR DECK SECONDARY FRAMES FITTING


IN PROGRESS
28-01-07 WELDING OF MEZZANINE DECK FRAMING IN
PROGRESS

29-01-07 ERECT DIAGONAL BRACES BETWEEN ROW B1


& B2

30-01-07 ERECT DIAGONAL BRACES @ BETWEEN ROW


A1 & A2
02-02-07 SUB ASSEMBLE DIAGONAL BRACES

03-02-07 ERECT CELLAR DECK DIAGONAL BRACES @


BETWEEN ROW A2 & A3

05-02-07 ERECT CELLAR DECK DIAGONAL & VERTICAL


BRACES IN PROGRESS
06-02-07 CELLAR DECK DIAGONAL BRACES FITTING

07-02-07 ASSEMBLE SKID BEAM @ SITE

08-02-07 ERECT DIAGONAL BRACES BETWEEN ROW A3 &


B3 COMPLETED
10-02-07 LIFTING & INSTALL CELLAR DECK PLATE

11-02-07 WELDING CELLAR DECK TOP FLANGE PLATE

12-02-07 CELLAR DECK DIAGONAL BRACES WELDING IN


PROGRESS
13-02-07 WELLHEAD PLATFORM ASSEMBLY

14-02-07 RESCUE DRILL (HEAD COUNTING)

14-02-07 RESCUE DRILL (SAFETY PERSONNEL @ SITE)


14-02-07 RESCUE DRILL
(VICTIM BRING DOWN FROM CELLAR DECK)

14-02-07 VICTIM ATTEND BY MEDICAL PESSONEL

14-02-07 REPORT TO CLIENT REPRESENTATIVES (SSB)


14-02-07 BRIEFING BY CLIENT & MMHE SAFETY
PERSONNEL

15-02-07 MEZZANINE DECK PANEL ASSEMBLY

16-02-07 MEZZANINE DECK PANEL FRAMINGS FITTING


17-02-07 MAIN DECK SKID BEAM FITTING @ ROW B

18-02-07 MAIN DECK SKID BEAM FITTING @ ROW A

19-02-07 INSTALLING WELLHEAD PRATFORM VERTICAL


BRACES
20-02-07 MAIN DECK PANEL ROW B SKID BEAM FITTING

21-02-07 MAIN DECK PANEL ROW A SKID BEAM FITTING

22-02-07 MAIN DECK PANEL TOP FLANGE PLATE


WELDING
23-02-07 PIPE SUPPORTS MARKING

24-02-07 PIPE SUPPORT STRUCTURE GAS CUTTING

25-02-07 PIPE SUPPORT FABRICATION


26-02-07 AN AERIAL VIEW OF CELLAR DECK PANEL

27-02-07 WELDING & GRINDING WELLHEAD PLTFORM


STRUCTURE IN PROGRESS

28-02-07 STAIRWAY FABRICATION


01-03-07 PIPE SUPPORTS MARKING (MECHANICAL)

02-03-07 INSTALLING DIAGONAL BRACES TRANVERSE


BEAM @ BETWEEN ROW A2 & A3 ON CELLAR DECK

03-03-07 WELLHEAD FRAMING JOINTS WELDING IN


PROGRESS
04-03-07 MAIN DECK PANEL FRAMMING JOINTS

05-03-07 ‘MPI’ WELLHEAD PLATFORM FRAMING JOINTS

06-03-07 WELLHEAD GRATING CLIP SEATING


(STAINLESS STEEL)
07-03-07 MAZZAININE DECK PANEL BLASTING IN
PROGRESS

08-03-07 ASSEMBLY INTERMEDIATE PLATFORM IN-SITU

09-03-07 INSTALL MEZZANINE DECK GRATING CLIP


SEATINGS
10-03-07 FABRICATING MEZZAININE DECK GRATINGS

11-03-07 BLASTING & PAINTING WELLHEAD PANEL IN

12-03-07 ERECT SWITCHGEAR & INSTRUMENT LER


STRUCTURE ON CELLAR DECK
13-03-07 MEZZANINE DECK FRAMING (PARTIAL)
COMPLETED WITH FINAL COATING

14-03-07 FIT & WELD CELLAR DECK GRATING GRIP


SCREW BOSS (STAINLESS STEEL)

15-03-07 MARKING & CUTTING OF E&I SUPPORT SUB


STRUCTURES IN PROGRESS
16-03-07 LIFTING & ERECT WELLHEAD PANEL

17-03-07 ASSEMBLE INTERMEDIATE PLATFORM IN


PROGRESS

18-03-07 ERECT SWITCHGEAR & INSTRUMENT LOCAL


EQUIPMENT ROOM FRAME STRUCTURE
19-03-07 FIT & WELD SWITCHGEAR & INSTRUMENT LER
ROOM WALL PANEL IN PROGRESS

20-03-07 INSTALLING DECK PLATE ON MAIN DECK


PANEL

21-03-07 PRECOATING FOR DESANDER &


ACCUMULATOR
22-03-07 ERECT THE 1ST PANEL OF MEZZANINE DECK

23-03-07 INTERMEDIATE PLATFORM FRAMING


COMPLETED SPRAY WITH 2ND COATING

24-03-07 LIFTING & INSTALL DESANDER &


INCCUMULATOR
25-03-07 CELLAR DECK PANEL BETWEEN 2 & 3
COMPLETE FIT-UP

26-03-07 INSTALL 4 UNITS OF DESANDER &


ACCUMULATIR ON CELLAR DECK

27-03-07 ERECT MEZZANINE DECK SUB PANEL @


BETWEEN ROW A2 & A3
28-03-07 INSTALLING FINAL DIAGONAL BRACES ON
ROW B

29-03-07 FABRICATING INTERMEDIATE HANDRAILS

30-03-07 INSTALLING HALF CUT PIPE ON SKID BEAM @


ROW B
01-04-07 FABRICATING INTERMEDIATE PLATFORM
GRATINGS

02-4-07 AERIAL VIEW OF SCDR-A PROJECT CELLAR &


MEZZANINE DECK

03-04-07 ERECT MEZZANINE DECK PANEL @ BETWEEN


ROW B2 & B3
04-04-07 5 SETS OF DESANDER & ACCUMULATOR IN-
PLACE ON CELLAR DECK

05-04-07 CELLAR DECK BETWEEN ROW 2 & 3 BLASTING


& PAINTING TO 2ND COAT

06-04-07 WELDING DESANDER & ACCUMULATOR


BASEMENT
07-04-07 ‘TIG’ WELDING ON 14 INCHES RISER PIPE

09-03-07 WELDING SWITHGEAR & INSTRUMENT LOCAL


ELECTRICAL ROOM WALL PANEL IN PROGRESS

10-04-07 ASSEMBLE ROW 3C VENT BOOM


11-04-07 AERIAL VIEW OF SCDR-A TOPSIDES

12-04-07 FABRICATING E&I STANDS IN PROGRESS

13-04-07 BATTERY ROOM WALL PANEL FITTING &


WELDING
26-04-07 ‘MPI’ 2 INCHES CLOSED DRAIN PIPE SPOOL
FLANGE WELDING JOINT

27-04-07 INSTALL ELECTRICAL CABLE TRAYS @ BELOW


CELLAR DECK IN PROGRESS

28-04-07 INSTALLING 2 INCHES DIESEL FLUID & 3


INCHES PORATABLE WATER (SS) PIPELINE @ BELOW
CELLAR DECK
29-04-07 INSTALLING 8 & 6 INCHES HAZARDOUS DRAIN
(GRE) PIPELINES @ BELOW CELLAR DECK IN
PROGRESS

29-04-07 INSTALLING CELLAR DECK HANDRAILS,


GRATINGS & STAIRWAYS

30-04-07 AIR HANDLING UNIT IN-PLACE


14-04-07 MACHINING GLASSFLAKE REINFORCE EPOXY
(GRE) PIPE SPOOL

15-04-07 GLASSFLAKE REINFORCE EPOXY (GRE) PIPE


& ELBOW FITTING

16-04-07 GLASSFLAKE REIINFORCE EPOXY (GRE) PIPE


SPOOL SUB ASSEMBLY
17-04-07 INSTALLING 4 INCHES OPEN DRAIN @ BELOW
CELLAR DECK IN PROGRESS

18-04-07 INSTRUMENT LOCAL ELECTRICAL ROOM


EQUIPMENT SEATING

19-04-07 MARKING/CUTTING & GRINDING GRE PIPE


SUPPORT SUB STRUCTURE
20-04-07 FABRICATED 8 INCHES FIREWATER &
HAZARDOUS DRAIN PIPE SPOOLS (GRE)

21-04-07 MAIN DECK PANEL BLASTING & PAINTING IN


PROGRESS

22-04-07 ERECT VENT BOOM VERTICAL & DIAGONAL


BRACES
23-04-07 BATTERY ROOM EXTERNAL COAING

24-04-07 FABRICATED GRE PIPE CLAMPS

25-04-07 FABRICATING 6 x 5’’ HAZARDOUS DRAIN PIPE


SPOOL (GRE)
01-05-07 AN AERIAL VIEW OF SCDR-A PROJECT @
ERECTION SITE

02-05-07 MAIN DECK PANEL BALSTING & PAINTING IN


PROGRESS

03-05-07 CRANE PEDESTAL COMPLETED WITH FINAL


COAT
04-05-07 ERECT MAIN DECK PANEL @ BETWEEN
ROW 3 & 4

05-05-07 ERECT MAIN DECK PANELS COMPLETED

06-05-07 RELOCATE VENT BOOM


07-05-07 FABRICATING 8 INCHES PROCESS GAS PIPE
SPOOLS

08-05-07 INSTALL CORROSIVE INHABITOR INJECTION


PACKAGE IN-PLACE ON CELLAR DECK

09-05-07 INSTALLING 8 INCHES HARZARDOUS DRAIN


(GRE) @ BELOW CELLAR DECK
10-05-07 SCDR-A PROJECT 1ST QHSE DAY ADDRESS BY
En’ MOHAMMAD ZAABA ABBAS (MMHE E&C GM)

10-05-07 ADDRESSING BY MISS TJITSKE MONSTER


(SSB TEAM LEADER)

10-05-07 LAUNCHING OF SCDR-A TOPSIDES PROJECT


FIRST QSHE DAY SLOGAN ‘NOBODY GET HURT’ BY
MMHE CEO EN’ WAN YUSOFF
10-05-07 SIGN ON THE PPE AWARENESS CAMPAIGN BY
RESPECTIVE SUB CONTRACTORS

10-05-07 ROAD SAFETY CAMPAIGN & PPE SALE

10-05-07 SOUVENIR FOR SUB CONTRACTOR


REPRESENTATIVE & INDIVIDUAL PARTICIPANT
11-05-07 INSTALLING 8 INCHES HAZARDOUS VENT
PIPELINE @ BELOW CELLAR DECK

12-05-07 VALVE BODY LEAKAGE HYDROTESTING

13-05-07 BATTERY ROOM EXTERNAL WALL COATING


14-05-07 INSUALTION WORK @ BELOW SWITCHGEAR
ROOM IN PROGRESS

15-05-07 GALVANISED DECK MOUNTED LIGHTING


STANDS

16-05-07 ERECT CRANE PEDESTAL


17-05-07 INSTALLING HANDRAILS ON MAIN DECK IN
PROGRESS

18-05-07 INSTALL 2 INCHES CORROSIVE INHABITOR


EXPANDABLE PIPE SUPPORT @ BELOW CELLAR DECK

19-05-07 INSTALL BATTERY RACKS & FLOOR TILE


20-05-07 MAIN DECK FLUSH WATER TANK IN-PLACE

21-05-07 SWITCHGEAR ROOM DB-7815 (230 V AC UPS


DISTRUTION BOARD) IN-PLACE

22-05-07 SWITCHGEAR ROOM AIR DUCTING WORK IN


PROGRESS
23-05-07 VENT BOOM BLASTING & PAINTING IN
PROGRESS

24-05-07 INSTALLING 8 INCHES FIREWATER PIPELINES 2


BELOW CELLAR DECK

25-05-07 SWITCHGEAR ROOM IN/OUT DOOR LIGHTS


SAMALL POWER DISTRIBUTION BOARD IN-PLACE
26-05-07 VENT BOOM FIRST COATING

27-05-07 SWITCHGEAR ROOM EMERGENCY OUTDOOR


LIGHTING DISTRIBUTION BOARD

28-05-07 SPRAY VENT BOOM FINAL COAT COMPLETED


29-05-07 SPRAY FINAL COATING ON PEDESTAL CRANE
BOOM REST IN PROGRESS

30-05-07 INSTALLING 6 INCHES HP FLARE PIPELINES ON


VENT BOOM

31-05-07 PEDESTAL CRANE INTERMEDIATE LANDING


01-06-07 CABLE PULLING @ BELOW CELLAR DECK IN
PROGRESS

02-06-07 CABLE PULLING IN SWITCHGEAR ROOM

03-06-07 CABLE PULLING IN INSTRUMENT LOCAL


EQUIPMENT ROOM
04-06-07 CABLE PULLING @ BELOW MEZANINE DECK
AHU AREA

05-06-07 INSTALLING CELLAR DECK GRATING

06-06-07 INSTALLING MAIN DECK INSTRUMENT


EQUIPMENT
07-06-07 ERECT PEDESTAL CRANE CONE ADAPTOR

08-06-07 INSTALL SAND BIN ON MAIN DECK IN-PLACE

09-06-07 ERECT PEDESTAL CRANE BOOM REST


10-06-07 INSTALLING VENT BOOM PIPELINES

11-06-07 INSTALL AIR CONDITIONAL UNITS

12-06-07 INSTALLING CLOSED DRAIN VESSEL


PIPELINES
13-06-07 GAS LAUNCHER TO E-11K-A & PIPELINE

14-06-07 INSTALL DECK MOUNTED FLORESCENT


LIGHTING STAND

15-06-07 INSTALLING SUSPENDED LIGHTING @ BELOW


MEZZAININE DECK
16-07-07 AN AERIAL VIEW OF VENT BOOM

17-06-07 INSTALL 8 INCHES OPEN DRAIN HAZARDOUS


ON CLOSE DRAIN VESSEL

18-06-07 SWITCHGEAR ROOM CONTROL PANEL AOL


(LCPA-8955) CABLE TERMINATION
19-06-07 INSTALL SCDR-A TOPSIDES NAME PLATE

20-06-07 TRAIL-FIT MAIN DECK REMOVEABLE HATCHS

21-06-07 FLUSH WATER PUMPS (2 SETS) IN-PLACE ON


MAIN DECK
22-06-07 ERECT VENT BOOM

23-06-07 FABRICATED 8 INCHES PROCESS GAS PIPE


SPOOLS (SS)

24-06-07 FABRICATED 2 INCHES VENT HP PIPE SPOOLS


(SS)
25-06-07 INSTALLING CRANE SERVICE PLATFORM

26-06-07 INSTALL BATTERY PACKAGES

27-06-07 SWITCHGEAR ROOM 230V AC UPS


DISTRIBUTION BOARD CABLE TERMINATION
28-06-07 INSTRUMENT LOCAL ELECTRICAL ROOM
CABLE PULLING IN PROGRESS

29-06-07 INSTALLING 2 TON MONORAIL HOIST FOR


LAUNCHER USAGE

30-06-07 SWITCHGEAR ROOM UPS TESTING &


COMMISSIONING IN PROGRESS
01-07-07 CABLE TRAYS EARTHING

02-07-07 BLAST WALL C/W PASSIVE FIRE PROTECTION


COATING

03-07-07 RELOCATE PEDESTAL CRANE BOOM REST


04-07-07 12 INCHES HARZARDOUS DRAIN & 4 INCHES
FRESH WETER PIPE END BLINDS (GRE)

05-07-07 12 INCHES HARZARDOUS DRAIN & 4 INCHES


FRESH WATER PIPELINE C/W EXPANABLE SUPPORTS

06-07-07 TRANSFORMER ROOM ENTRANCE WORK IN


PROGRESS
07-07-07 CELLAR DECK TOILET SPACE

08-07-07 MAIN DECK NAVIGATION LIGHTING

09-07-07 ERECT TEMPORARY SUPPORT FOR PEDESTAL


CRANE BOOM
10-07-07 INSTALL PEDESTAL CRANE CONTROL TOWER
IN-PLACE

11-07-07 INSTALLING FRESH WATER PUMP PIPELINES

12-07-07 CEMENTING WORK ON SWITCHGEAR ROOM IN


PROGRESS
13-07-07 TOILET SPACE FLOORING

14-07-07 INSTALLING DIESEL TRANSFER PUMP


PIPELINES

15-07-07 PASSIVE FIRE PROTECTION (PFP) BULKHEAD


@ INSTRUMENT LOCAL ROOM,WEATHER SHELTER &
WORKSHOP AREA
16-07-07 INSTALL CO2 VENT SNUFFING UNIT ON MAIN
DECK IN-PLACE

17-07-07 PEDESTAL CRANE BOOM ASSEMBLY

18-07-07 ERECT PEDESTAL CRANE BOOM COMPLETED


19-07-07 WELLHEAD PLATFORM & GRATING

20-07-07 PORTABLE WATER PIPELINE HYDROTESTING


24 BAR IN PROGRESS

21-07-07 ‘MPI’ TRANSFORMER & SWITCHGEAR AIR


TIGHT DOOR WELDING JOINT
22-07-07 INSTALL PEDESTAL CRANE STRING WIRE

23-07-07 INSTALLING WELLHEAD CONTROL PANEL


HYDRAULIC TUBINGS

24-07-07 MAIN DECK BEACON LIGHTING &


GENERALPLATFORM ALARM
25-07-07 CABLE FASTENING

26-07-07 DECK TOILET BOWL FITTING

27-07-07 PEDESTAL CRANE BOOM ON TRIAL


28-07-07 HYDROTESTING PORTABLE WATER PIPELINE
TO 28 BAR PRESSURE @ BELOW CELLAR DECK

30-07-07 INSTALLING PIPELINE & VALVES BETWEEN


FLUSH TANK & PUMP

31-07-07 WELLHEAD SERVICE PLATFORM MUD WALL


01-08-07 ROW B MAIN COLUMNS FINAL COATING IN
PROGRESS

02-08-07 INTERMEDIATE DECK POWER BLAST

03-08-07 CABLE GLANDING WORK ON INTERMEDIATE


DECK JUNCTION BOX JB-FF-008 & SCDR-AZJBi-4510
04-08-07 SWITCHGEAR ROOM PRE COMMISSIONING IN
PROGRESS

05-08-07 MAIN DECK JUNCTION BOX SCDR-A ZJBI-4515


CABLE TERMINATION

06-08-08 WELDING LOADOUT LIFTING PADEYE


07-08-08 DECK TOILET BOWL & WASH BASIN

08-08-07 WELLHEAD CONTROL PANEL PRE


COMMISSIONING TEST

09-08-08 INSTALLING VENT TIP


10-08-07 MAIN DECK FLUSH WATER PUMP
TEMPERATURE & SPEED TEST

11-08-07 MUD WALL ENTRANCE

12-08-07 INSTALL FIRE DRILL HOSE ON MAIN DECK


13-08-07 INSTALLING EQUIPMENT TRANSMITTERS ON
PROCESS GAS PIPELINES

14-08-07 SWITCHGEAR ROOM SWITCH BOARD


PRECOM.

15-08-07 SWITCHGEAR ROOM VCB POWER


DISTRIBUTION CABLE TERMINATION
16-08-07 INSTRUMENT LOCAL ELECTRICAL ROOM
MULTI CABLE TRANSIT

17-08-07 WELDING LOAD OUT LIFTING PADEYE

18-08-07 SWITCHGEAR ROOM PRECOMMISSIONING IN


PROGRESS
19-08-07 INSTRUMENT LOCAL ELECTRICAL ROOM
EQUIPMENT PRECOMMISSIONING

20-08-07 SC PRODUCTION MANIFOLD REINSTALLMENT


20 BAR HYDROTEST

21-08-07 FRESH WATER PUMP SUCTION STRAINER


22-08-07 INSTRUMENT LOCAL ELECTRICAL ROOM
PRECOM.

23-08-07 HVAC TESTING & COMMISSIONING

24-08-07 DESCUFFOLDING IN PROGRESS


25-08-07 FRESH WATER PUMP ALIGNMENT WORK IN
PROGRESS

26-08-07 MAIN DECK SAFETY APPLIANCES

27-08-07 SC PRODUCTION MANIFOLD PACKAGE (TP-PG-


019A) HYDROTESTING 190 BAR
28-08-07 MUSTER AREA SIGNBOARD @ CELLAR DECK

29-08-07 WELDING LOADOUT LIFTING PADEYE @ ROW 3A

30-08-07 BELOW CELLAR DECK DESCUFFOLDING IN


PROGRESS
01-09-08 LOADOUT PREPARATION (LIFTIG SHACKLES)

02-09-07 LOADOUT PREPARATION


(LIFTIG STRING WIRE)

03-09-07 INTERMEDIATE PLATFORM RADIATION SHIELD


04-09-07 CELLAR DECK SC PRODUCTION MANIFOLD

05-09-07 CELLAR DECK 0.5 TON SWING JIG CRANE

06-09-07 ‘MPI’ LOADOUT LIFTING PADEYE WELDING


JOINTS
07-09-07 MEZZAININE DECK WELLHEAD MUD WALL

08-09-07 EASTERN KINGDOM ‘FLAT TOP BARGE’


ARRIVED @ QUAY-1

09-09-07 ASIAN HERCULES ARRIVED @ QUAY 1


10-09-07 INSTALLING GRILLEAGES ON EASTERN KINGDOM
(FTB)

11-09-07 SCDR-A TOPSIDES MODULE COMPLETELY LIFT


UP BY ASIAN HERCULES II (3200 MT)

11-09-07 SCDR-A TOPSIDES LOADOUT ONTO EASTERN


KINGDOM (FLAT TOP BARGE)
12-09-07 SEAFASTENING WORKS IN PROGRESS

13-09-07 WELDING SEAFASTENING STRUCTURES

14-09-07 PACK SHIPLOOSE ITEMS


15-09-07 TEMPORARY WELD UP GRILLAGE & TOPSIDE
STABBING CONE

16-09-07 ‘UT’ & ‘MPI’ SEAFASTENING STRUCTURE


WELDING JOINTS

17-09-07 SHIPLOOSE (GRE PIPE SPOOLS) PACK IN


CONTAINER
18-09-07 SHIPLOOSE
(HANDRAILS & CONDUCTOR PILES)

19-09-07 SHIPLOOSE
(8’’ x 150’ x 5 LENGTHS/PACK x PP ROPE x BOTH END
CANVAS EYE)

20-09-07 SEAFASTENING SWITCHGEAR ROOM


EQUIPMENTS
21-09-07 W/SHOP & SHELTER ROMM SEAFASTENING

22-09-07 DECK TOILET DECORATIONS

23-09-07 WING DECK SAFETY PASSAGE


24-09-07 SHIPLOOSE IN CONTAINER ONBOARD OF THE
BARGE

25-09-07 SHIPLOOSE
(PART OF INTERMEDIATE PLATFORM STRUCTURE)

26-09-07 OFF SHORE CONTAINER 4 NOS.


27-09-07 SCDR-A TOPSIDES ON THE BARGE BEFORE
SAILAWAY

27-09-07 SCDR-A TOPSIDES SAILAWAY