Name : ..........................................
PART – A
P.T.O.
2998 -2- *2998*
PART – B
Module – I
11. a) A business firm has recorded the demand for a particular product during the
past 6 weeks as shown below.
1st week 2nd week 3rd week 4th week 1st week 2nd week
Week
of January of January of January of January of February of February
Demand
in No. 19 17 22 27 29 33
of units
i) Calculate a 3-week moving average for the data to forecast demand for the
next week.
ii) Calculate the weighted average forecast for the data using a weight of 0.6 for
most recent data and weights of 0.3 and 0.1 for the previous weeks. 10
b) Define the terms ‘design capacity’ and ‘system capacity’. What are the different
long term capacity strategies that can be adopted for an Automobile Industry ?
10
12. a) What are the different types of plant layouts ? Explain them with examples. 10
b) Explain the steps in systematic layout planning. 10
Module – II
13. a) Explain the various pure strategies and mixed strategies in aggregate planning. 10
b) Determine the optimum sequence and makespan for the following 6 job
2 machines flow shop problem. Also determine the machine idle time.
Job i 1 2 3 4 5 6
M/c 1 5 2 13 10 8 12
10
M/c 2 4 3 14 1 9 11
*2998* -3- 2998
b) The demand for an item is 24,000 per year. Its production rate is 4000 per
month. The carrying cost is Re. 0.50/ unit/month and the set up cost is Rs. 800/-
per set-up. The shortage cost is Rs. 15/- per unit per year. Determine the Economic
Batch Quantity, maximum inventory and maximum stockout. 12
Module – III
––––––––––––––––