Escolar Documentos
Profissional Documentos
Cultura Documentos
Introduction to
MS Project 2007
Contents
Page
1 Getting Started 2
2 Using the Task Pane List 3
2.1 Set a date to schedule from 3
2.2 Define general working times 3
2.3 List the tasks in the project 5
2.3.1 Create the plan task list 5
2.3.2 See task properties 6
2.3.3 Recurring tasks 6
2.3.4 Put task names on chart 7
2.4 Organize tasks into phases 7
2.5 Schedule tasks 8
2.5.1 Establish links between tasks 8
2.5.2 Specify or change task start and end 8
dates
3 External tasks and using colour 9
4 Essential finishing touches 9
5 Recording progress 10
6 Printing your plan 10
6.1 Selecting dates to print 10
6.2 Putting task details on each page 11
6.3 Adjusting details to fit the page 11
Appendices 12
A Print previews of DemoPlan.mpp 12
B Checklist of essential items for project and assignment plans 14
1. Getting Started
Being able to plan your workload is a valuable skill, needed not only for your studies at University, but also for your future career, even for organising possible future
personal activities such household DIY.
Project planning may be a directly assessed component of a module that you will be required to do as part of your studies. It is also indirectly assessed; students who do
not plan their work often find that they cannot complete their assignments to time and may get poor marks!
MS Project is a project planning tool that students are required to use for some modules. The skills gained in planning these projects can then be transferred to other
projects and even to planning your full study/leisure/employment activities (should you so wish!).
This document will take you though the creation and customising of a simple project plan.
The information here should be sufficient for most module plans that you will create for your courses.
There is extensive help within MS Project if you wish to find out more.
If you close your file while part-way through this list, it will reopen at the point you were at before.
If you want to change any of the settings in an existing document, one way is to click on the Task icon on the toolbar, then go to the required item in the list and make the
changes.
All tasks have a start date, so choose a suitable date from the dialog provided. A date of the start of the academic year may be suitable for a year-long project module.
The default date is the current system date.
The dates at the head of your plan will adjust to start from your plan start date if you choose a date other than the system date.
The date for this example is the first day of term for the 2006/2007 academic year.
Click on the Save icon to save your file, giving it a suitable name (DemoPlan, for example). Note that the file will have an .mpp file extension. As with all files that you
create or amend, it is good practice to keep saving after every few changes.
Here you can say what days of the week you will work and what hours of each working day are to be classed as working hours. You may want to make one (or both!) of
the weekend days into working days, or designate some other day as a regular non-working day, or extend the hours that you will work each day. For simple plans for
assignments and project work the hour’s element is probably not needed, but you may want to give yourself a day off each week.
There are five steps to doing this, and you will be guided by a wizard. Look at the bottom of the task pane to see the step numbers.
Click on the Change working time…link, choose the month, click on the required day, and set it to the required value. Unfortunately, there does not seem to be any way
of setting a comment to indicate why the day setting has been changed.
Use default
Sets the date to the default calendar
that you set in Step 2. This option is
useful if you had arranged a day off
then want to reinstate it.
Nonworking time
Use this to notify the day as a day off.
When you confirm the details (press
the OK button) the day will show in the
plan as a non-working day (it will be
highlighted on the plan, as shown
here).
Now we come to the content of the plan – the tasks that are to be scheduled and tracked. Read the More Information link (bottom of Task Pane). A task is “An activity
that has a beginning and an end. Project plans are made up of tasks.” Ref: MS Project Help.
For your assignment or project you should already know some of the tasks and deliverable dates. Let’s suppose that the plan is to be for a project module and that you
already have the following information for the first few weeks:
• Introductory lecture on Thursday of week 1
• Meeting with supervisor on Tuesday of week 2, at which you are to discuss your ideas for the project
• D#1 Terms of Reference (TOR) and Human Research Ethics (HRE) form – deadline Friday week 3.
Some tasks naturally break down into sub tasks, as shown above.
Other tasks (lectures, meetings, and submitting work) are pretty small in duration and may be better designated as ‘milestones’. To do this, select the required task and
click the task pane check box for milestones (see screenprint below).
Enter the task list shown here, and change durations to match. Note
the blue ‘task bars’ showing task durations.
Task numbers occur automatically
If you click on a task bar) you will see the properties for that task.
You can use this property box to change task details. It is especially useful for recording
progress (see section 6).
Some tasks may occur several times throughout the project. If these occur at irregular
intervals, then enter them as separate tasks.
Other tasks may occur at regular intervals, so can be entered as ‘recurring tasks’. An example is a regular review of progress, perhaps on a Friday of each week.
Highlight task 2 and insert a recurring task via the menu: InsertRecurring Task. You
will get the dialog box shown below.
The ‘End by’ date chosen here is the Friday before Easter on the DMU 2006/2007
academic calendar.
The task will now show with task bars for every Friday throughout the project, all on the same line as the task for ‘review progress’.
Note also that the task numbers after this recurring task will have changed to allow for task 2 actually being many tasks (one per week for 20-odd weeks). See
screenprints in section 2.3.4 and Appendix A.
Your chart will cover many weeks and it can be difficult on printouts to see what task each task bar refers to. If you want to put the task names on each bar, then use the
menu FormatBar Styles to do this:
The screenprint here shows how to set the task name to appear on the left of all milestones.
Highlight tasks 30 and 31 and press the green ‘indent’ arrow (pointing to the right) on the toolbar.
These two items are now designated as subtasks of task 29. The duration of task 29 has been changed and is calculated from information from the sub tasks. It now has
a black summary task bar. There is a +/- sign to the side of task 29; clicking on this will expand/contract the task.
In the same way, you can designate tasks 34-36 as subtasks of task 33.
If you want to ‘outdent’ an item, simply choose the other green arrow icon (pointing to the left).
Here you will specify which tasks link to other tasks. In a project, this means “establishing a dependency between tasks. Linking tasks defines a dependency between
their start and finish dates”. Ref: MS Project Help.
Extract from MS Project Help: Link tasks in a project or across projects
After tasks are created in a project, they need to be linked to show relationships between them.
Link tasks within the same project
1. On the View menu, click Gantt Chart.
2. In the Task Name field, select two or more tasks you want to link in the order you want to link them.
• To select nonadjacent tasks, hold down CTRL, and then click the tasks you want to link.
• To select adjacent tasks, hold down SHIFT, and then click the first and last tasks you want to link.
59719426.doc Page 10 of 18 Stuart Korova / 7th.May2010
3. Click Link Tasks .
Microsoft Office Project 2003 creates a finish-to-start task link by default. You can change this task link
to start-to-start, finish-to-finish, or start-to-finish.
Introduction to MS Project 2007.
For example, tasks 30 and 31 could be linked; you can’t write up research unless you have done the research first.
If you follow the MS Office Help shown above you will see that the tasks are now moved so that task 31 starts when task 30 finishes.
However, you may want to start the write-up part-way through the research (tasks frequently overlap – a ‘waterfall’ approach to all tasks is normally not a good one!).
This is simple to arrange. Double-click on the dependency line and change the properties as shown below.
This states that the second task (31) is to start 2 days before the first one (30) finishes.
With MS Project the idea is that you link all your tasks together and that this will automatically adjust, and thus specify the start and end dates for each task.
However, you can specify the dates separately for unlinked tasks, or change dates to reflect changes to your plan (and there will be changes), by several methods:
• Via the task properties; see section 2.3.2.
o Set the required dates. You may need to reset duration back to 0 (zero) for milestones.
• By changing the dates in the Gantt chart date columns.
• By clicking and dragging the task bar.
See Appendix A for plan printouts showing tasks with various start and end dates.
All text by default is in black font, but colour is useful to identify external tasks. To do this, highlight the task, and then use:
• FormatFont to change the font colour for the selected task details
• FormatBar to change the colour for the selected task bar.
Red font has been used for the external task and the task bar.
5. Recording progress
Your plan has now been started and is ready to use.
When you see your supervisor for progress meetings you will need to take your plan and show progress to date.
Progress can be added via the General tab on task properties; see section 2.3.2.
Click on the +/- by the side of a recurring task to expand the task to see the specific subtask you want to change, then click on +/- again to contract the task afterwards.
• To record progress, simply set the ‘percentage complete’ to an appropriate value.
• The task bar will have a solid line added to indicate the proportion complete.
• Tasks that are 100% complete are indicated by a tick in the indicator column.
• If all tasks in a group are complete then setting the group task as 100% complete will also set the subtasks as 100% complete – and vice versa.
The screenprint below shows that task 1 (the introductory lecture) has been attended (is 100% complete) and that task 30 (research ideas) is 50% complete.
You should also adjust task start and finish dates, add
additional tasks, etc. to reflect what you actually did. It is
normal, indeed expected, for plan details to change in the light of what actually happened (‘best laid plans…’ and all that).
If you look at the plan in print preview, you will see that…
• …there are four pages to be printed, from the plan start date to the plan end date – you may not want to print the whole lot each time, especially as the project
progresses.
• …the task details only appear on the first page – this can make making sense of later pages difficult.
If you print via FilePrint the dialog box will give you the usual option of printing specific pages only, plus the option
of printing between specific dates.
By using this second option you can ensure that you print only the relevant part of the plan.
Use the View tab of the FilePage Setup dialog box to specify the number of columns you want to
appear on each page. Set the appropriate number then tick the box.
The plan created here has only a very few tasks. Your project plan will end up much larger, and the task list may go over to a second (or third!) page. You can reduce the
number of pages that will print by choosing the ‘fit to page’ option on the Page tab of the FilePage Setup dialog box.
Page 2 of 2
Symptoms
A task in your project starts earlier than the project start date.
CAUSE
You might have set a date constraint, such as Start No Earlier Than (SNET) or Must Start On (MSO),
which ties the task to a date earlier than the project's start date. These constraints can cause the task to be
The task might have an external dependency to a task in another project. That dependency might be
causing the task to start earlier than the project start date.
The task might have an actual start date recorded before the project start date.
Resolution
If your task has a date constraint to begin no earlier than the project's start date, reset the constraint.
Select the task, click Task Information , and then click the Advanced tab. In the Constraint type list,
If your task requires an external dependency, change the project start date to match the external
dependency date. On the Project menu, click Project Information. In the Start date box, enter the new
date.
If your task has an incorrect actual start date, select the task, and then on the Tools menu, point to
Tracking and then click Update Tasks. Under Actual, change the date in the Start box.
Make sure that all your tasks and notes are spelled correctly!