Você está na página 1de 24

SYNTHESIS GAS CONVERSION OF METRO MANILA

MUNICIPAL SOLID WASTE THROUGH GASIFICATION


FOR 5MW GAS TURBINE ELECTRICAL ENERGY
PRODUCTION

Carillo, Renz Roe, Mationg


Hansel Paul, Penuela
Jasmine Helden Therese
Rosas, Leo Angelo
Advisers:
Jay R T. Adolacion
Dr. Rizalinda L. de Leon

Department of Chemical Engineering, College of Engineering


University of the Philippines, Diliman, Quezon, Philippines

Received and Accepted on April 5, 2011

Abstract
Turning trash into money is both an economic and environmental dream. But this dream has
already been slowly realized in Europe and in some parts of Asia through the chemical
engineering process of Gasification. This process not only converts coal and biomass into
useful Synthetic Gas (SynGas) but also handles Municipal Solid Wastes (MSW). This paper
showcases the conceptual and technical design of a gasification and energy plant that converts
MSW from Metro Manila into usable five Megawatts (5 MW) of electric energy. The plant design
is divided into four parts which corresponds to four major areas of the plant. The first area
manages the gathering and pre-treatment of raw MSW taken from Tanza, Navotas dumpsite.
The second part involves the gasification of MSW into syngas and the third part administers the
post treatment of the gas. Lastly, after post treatment, the syngas is fed into a gas turbine
generator which constitutes the fourth area of the plant. All major equipment comprising the
plant has in-depth technical specifications and analyses with information gathered from
numerous literatures. In addition to the technical aspects, the paper includes a market study and
economic breakdown of the plant in order to determine its feasibility once in operation.

Keywords: Municipal Solid Waste, Gasification, Synthetic Gas, Gas Turbine Generator, Waste
to Energy

I. Introduction municipal solid waste. The goal is to


develop an economically viable process
The proposed plant aims to generate in generating power by producing
electricity from synthetic gas, which will industrial grade synthetic gas from
be produced from the gasification of municipal solid waste. It is desired that

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 1 of 24


overall, the plant may not only be a these innovations require electrical
profitable business venture, but serve as energy in order to function, thus,
an environmentally friendly waste increasing the demand for energy
disposal method for municipal solid worldwide. In the Philippines, the
waste as well. demand for power is increasing with
The Philippine electrical power 20,000 Gigawatt-hour (GWh) in just a
industry is also analysed, so as to span of 9 years. Currently, the major
determine the potential of the industry in sources of energy in the country are the
the market in the country. Based on hydroelectric power and natural gas and
economic data from the previous years, coal combustion. (Department of
the demand for electrical power is Energy, 2009) This reliance on fossil
continually increasing through time, fuels is a huge disadvantage to our
majority of which are used for country economically and
residential, industrial and commercial environmentally. As more fossil fuels are
purposes. being burned, more carbon (and
The economics of synthetic gas as greenhouse gases as well) is released
source for the electrical power is also to the atmosphere, causing harmful
analysed based on the national data for effects to both health and the
natural gas. It was also found out that environment. Also, most of the world‟s
the main usage for natural gas in the oil reserves are monopolized by the
Philippines was for power, which is in Organization of Petroleum Exporting
line with the objectives of the proposed Countries (OPEC), which is highly
plant. unfavorable for the other OPEC-
The processes and equipment dependent countries as political and
involved are divided into four stages economic instability greatly affect the
namely the (1) pre-treatment of dynamics of the industry.
municipal solid waste, (2) gasification of Aside from our growing energy
municipal solid waste to synthetic gas, needs, another problem faced by our
(3) cleaning of synthetic gas, and (4) country is the disposal of municipal solid
generation of electrical energy from waste (MSW). Municipal solid waste
synthetic gas produced. There are a (MSW) refers to all non-hazardous solid
total of 11 processes used, majority of waste that includes household garbage,
which will be used for the pre-treatment, refuse (metal scrap, empty containers),
gasification and cleaning. The sludge from wastewater treatment
processes and their corresponding plants, and other discarded materials.
equipment are discussed in more detail, Here in the Philippines, the most
inclusive of the properties, calculations, common form of MSW disposal is
optimization and hazards of each. through landfilling. Landfilling is
considered a negative-income activity
II. Market Study since it consumes large areas of land
but fails to generate revenues.
a. The Design Problem Currently, controlled dumps in the
As the world becomes more outskirts of Metro Manila are
technologically advanced, more and responsible for the disposal of all of
more innovations and inventions are Metro Manila‟s MSW. The passing of
being developed. Most, if not all, of The Ecological Solid Waste

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 2 of 24


Management Act (RA 9003) in 2001 has •Provide sensitivity
already provided the legal framework for analysis and project profitability
the establishment of a systematic and of the proposed plant
ecological solid waste management
(SWM) program. RA 9003 also allows b. Energy Demand
the awarding of incentives to institutions Electric power has great global
that undertake effective SWM programs. demand as technological advancements
Despite the passing of R.A. 9003, there cause more and more devices to be
is still an impending garbage crisis in invented and manufactured. Most of
Metro Manila with the continuing these devices are usually run by
increase in MSW generation per capita, electrical energy – whether stored in
along with the increase of population in batteries, or transferred from electrical
the area. A study done by Navarro in sockets. With the continuous
2003 shows that the current SWM industrialization of our country, our
sector will not be able to sustain itself reliance of electric energy has
with the escalating prices of SWM. increased. As seen in the figure below,
(Navarro, 2003). the demand for power increases along
With this, we can see that there is with time, with the power consumption
a great need for a sustainable and increased by around 20,000 Gigawatt-
profitable MSW disposal system as well hour (GWh) in a span of 9 years, where
as an alternative power generation 1 watt is 1 joule of energy per second.
setup. The data below consists of the power
This study aims to develop an consumption for the past 9 years, with
economically viable process for the imports added and exports subtracted.
production of 5 MW of power from
municipal solid waste as a profitable
business venture and to serve as an
environmentally friendly waste disposal
method. Specifically, the study seeks
to:

•Design, simulate and optimize all


the equipments necessary in the
generation of electricity from
syngas made from MSW
•Provide an overview on
the current landscape of the
energy industry Figure 1. Power Consumption
•Analyze hazards and
risks involved in the equipments As seen in the figure above, the
and processes energy consumption for the Philippines
•Provide the piping layout has been projected to have an
and PID of the power plant increasing trend. For the span of time
•Explore the economic considered in the graph, Philippines has
feasibility of MSW gasification been consistently at the top 45 countries
and power production in electric consumption worldwide, three

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 3 of 24


of which are topped by United States of Waste Management Commission can
America, China and Japan, respectively. be made and approved. However, a
Furthermore, electric production in the major downside on the use of MSW as a
Philippines for 2011 was estimated in biomass feed for gasification is its
2009 to be 61, 9930 GWh the electric heterogeneity. Solid Waste could come
consumption to be around 54400 GWh. from a very wide range of sources and
Imports and exports are still non- thus the components present in the feed
existent for the Philippine industry could not be easily controlled. For this
(IndexMundi, 2010). reason, an elaborate pre-treatment must
be done accordingly to produce a more
c. Metro Manila Municipal uniform and homogeneous feed.
Solid Waste Designing the pre-treatment process
One major advantage of this would require strategies at which the
proposed project is the raw material at particle sizes of the feed that would be
which the production of electricity will entering the main reaction phase are
come from. Disposal of Municipal Solid consistent and the relative composition
Waste through landfill is in itself a is more or less steady. Furthermore,
resource spending activity and thus removal of unwanted components (i.e.
provides no positive financial gain. non-hydrocarbon wastes) should be
Additionally, adverse environmental employed in the design of the pre-
effect of landfilling generates risks that treatment process. The design of post-
could manifest in several ways such as treatment processes will also heavily
the „Payatas Tragedy‟ in 2000. For rely on the specifics and requirements of
those reason, this project would prove to the gas turbine that will be used to
be beneficial in a lot of ways. The produce the electricity. Aside from the
accessibility and procurement of the MSW, one other major raw material for
primary raw material in this project is this process is the catalyst that is to be
relatively easy and will come at almost used in the gasification stage. To further
no cost. Republic Act 9003, or otherwise minimize production costs, air will be the
known as the Ecological Solid Waste preferred material to be used. Again,
Management Act of 2000, strongly this raw material will come at a very little
encourages economic activity that would or almost no cost. Procurement of this
help curtail the problem on Solid Waste raw material therefore is not a major
Management and Section 45 of the said problem. The target amount of solid
act provides incentives “to individuals, waste to be processed every day will be
private organizations and entities, 100 metric tons. This will be the targeted
including non-government amount since most of the existing MSW
organizations, that have undertaken gasifiers in larger cities around the world
outstanding and innovative projects, process around 150 to 400 tons of MSW
technologies, processes and techniques per day.
or activities in re-use, recycling and
reduction” of Solid Waste. Thus, the d. Target Market and
cost of obtaining MSW would either be Competition
small and negligible or it could even be The electricity generated by the
a revenue generating activity if proposed plant will be the distributors for
coordination with the National Solid electric power, which are part of the

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 4 of 24


second sector of the electric power Sta. Rita and Napocor (NPC) are
industry in the Philippines. The current the largest sources of electric power of
largest distributor of electricity in Metro Meralco, as seen in the figure above.
Manila is Manila Electric Company Sta. Rita is a combined-cycle natural
(Meralco), which is among the top 5 gas power plant in Batangas owned by
largest companies in the country. It is, First Gas Power Corporation which is a
however, the only distributor of electric division of First Holdings. The plant
power in Metro Manila, dispensing produces 1,000 MW of power (First Gas
electrical energy to about 31 cities and Power Corporation, 2010). Similar to
80 municipalities in the region (Meralco, Sta. Rita is San Lorenzo CCGT which
2009). supplies 500MW power and has 13.06%
Possible competition will be market share (San Lorenzo CCGT
existing companies like National Power Power Plant, Batangas City, Philippines,
Corporation (Napocor) and the First 2010).
Philippine Holdings Corporation (First Napocor, on the other hand,
Holdings), which also produce power generates its own electricity, but the
and sell to electric power distributors same time also buys electricity from
such as Meralco. According to the Independent Power Producers (IPPs).
Computation of Generation Charge NPC used to have monopoly over power
document (2010) of Meralco, the other generation, until the generation sector of
power sources they distribute for are the industry was opened to private
Wholesale Electricity Spot Market investors by the effectivity of Executive
(WESM), Philippine Power Development Order No. 215 (DOE, 2005).
Corporation (Philpodeco), Montalban The smallest sources are
Methane Power Corporation (MMPC), Philpodeco and MMPC. Philpodeco is a
and other Independent Power power company that owns three mini-
Producers (IPP) such as Quality Power hydroelectric plants located in the
Products, Sta. Rita Gas Turbine Power Laguna areas (Miras, JC, 2006). The
Plant, and San Lorenzo Combined plants generate a sum of less than 2MW
Cycle Gas Turbine (CCGT) Power of power. On the other hand, MMPC is a
Plant. The energy share of these methane converting power plant that
sources is presented as a pie graph in derives energy from the Montalban
the figure below. Landfill. The plant is projected to
produce 8.19MW of power but only a
“very small level” is currently being used
due to technical problems (Añonuevo,
2009).
Existing power plants in Manila
are Duracom Unit 1 &2 and East Asia
Diesel, both diesel plants found in
Navotas, Philippines (DOE, 2006).
Based on the available data, the
proposed Gasification plant with
5.19MW output and operates
continuously, shall have a market share
of about 0.153%.
Figure 2 Energy Share

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 5 of 24


e. Plant Location f. Flowsheet Synthesis and
Electricity in Metro Manila is Development
generated by National Power In recent years, there have been
Corporation (Napocor), a government- numerous studies that involve the
owned and controlled corporation search for an alternative energy source.
(GOCC). It is currently ranked third This, in large part, is due to the
among 20 largest companies in the diminishing world supply of fossil fuels.
Philippines, “legislated into existence” One such alternative that is currently
by Commonwealth Act No. 120 on 1936 being explored is biomass as an energy
(Fay, 2010). source. There are several renewable
Independent power generators in biomass sources, (i.e. indigenous crops,
Luzon contribute to the total power woods) which makes it an attractive
generation as well. Electricity is alternative energy source. Hydrogen-
transmitted using high tension wires by rich gas can be produced from biomass
the National Grid Corporation of the after undergoing a process called
Philippines (NGPC), which is owned by gasification. Gasification is a process
private investors, and distributed by the that devolatilizes solid or liquid
Manila Electric Company (Meralco), the hydrocarbons, and converts them into a
only company allowed for electric gas with low to medium heating value.
distribution (DOE, 2005). The gas produced in gasification can
The plant will be located in have several applications such as raw
Tanza, Navotas, Metro Manila. The raw materials in various chemical industries
material for the proposed power plant is or as fuel to power gas turbines. This
municipal solid waste (MSW). It will, process will be discussed in further
thus, be physically and financially detail later on.
strategic to have the plant located within Today, Municipal Solid Waste
the immediate area of a dumpsite. This (MSW) is currently being explored as a
will ensure less cost for transportation of biomass feedstock for gasification
raw materials, ergo, maximizing the plants. These studies are aimed to
profit. Compared to the Payatas in provide knowledge on the utilization of
Quezon City, the location of another Municipal Solid Waste gasification to
dump site in Metro Manila, Navotas is serve both as an alternative process for
dense (more buildings per land area) energy recovery and a method for the
and has low coastal area, making it disposal of Solid Waste. These high
prone to calamities, especially of temperature energy recovery from MSW
storms. are known as Waste-to-Energy (WTE).
As of year 2000, a total of 49,450 A more common practice around the
exist in different barangays in Navotas, world regarding energy recovery from
around 8.49% of which are found in solid waste is the process of
Tanza, where the dumpsite is more combustion. Combustion of solid wastes
specifically located. As of December releases energy as the hydrocarbons
2010, 39.67 hectares is converted into reacts completely with oxygen and this
land fill, which is 3.71% of the total land energy that is being produced is utilized.
area (City of Navotas, 2007). However, one major downside of this
process is the formation of
dioxins/furans (PCDD/PCDFs) in the

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 6 of 24


flue gas which are proven to be harmful promotion for gasification and syngas
emissions to the environment. production.
Moreover, here in the Philippines, Dealing with the different risks in
Republic Act 8749, or more commonly health, safety and environment (HSE) is
known as the Clean Air Act, prohibits one of the major challenges for new
the incineration of solid wastes. technologies nowadays, usually
Therefore, gasification must be pursued because of the lack of awareness,
since it proves to be the better knowledge and concern of these issues.
commercially and environmentally viable Though biomass gasification is already
alternative. In line with this, our study is promoted as a better means for
aimed at designing a MSW gasification renewable energy production, many
plant that is to be built here in the HSE issues still remain to be addressed.
Philippines, specifically in Metro Manila, Systematic analysis, study and
one that would help reduce wastes that evaluation of different measures
ultimately end up in dumpsites/landfills, involving health, safety and environment
while at the same time the said process should be carefully done, so as to
would be economically feasible as a ensure proper handling and
commercial venture. This gasification performance for the municipal wastes,
plant will produce synthetic gas (syngas) the syngas as product and gasification
which is a gas composed mainly of as the major process.
hydrogen (H2) and carbon monoxide
(CO). The syngas is then subsequently b. Detailed Process
used as fuel to power a gas turbine that Synthesis
will produce electricity. Market demands Pretreatment
for electricity, which was discussed When the feed is delivered to the
previously, indicates a relatively easy plant, the pretreatment process begins.
market penetration due to increasing MSW, starting at stream 01 is fed into
demands in electricity. the hammer mill for size reduction. Next,
MSW is transferred to a trammel screen
III. Process Development for size discrimination. The oversize is
a. Health, Safety, and assumed to be composed big carton
Environmental boxes and the like, and shall be directly
Considerations fed to a rotary shredder. This shall be
Gasification is a vital process in done manually. On the other hand, the
the energy industry today, making a undersize is delivered back to the landfill
promising contribution to the while the medium size is fed to the
development of renewable energy conveyor installed with a magnetic head
worldwide. In this light, operational that separates iron from the feed. After
safety and environment compliance iron separation, it is then pass through
should be partnered with this an eddy current separator which takes
development in the energy industry, as it out aluminum. The feed then joins the
is currently and will continue to oversize earlier in the shredder. After
penetrate the energy market, therefore this second size reduction process,
appealing to investors and to common MSW is again discriminated through a
people as well. This can ensure vibrating screen. The fines shall enter
commercialization and improving

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 7 of 24


the gasifier hopper while the oversize assumptions are based on existing
shall go back to the shredder. literatures.
The basis for the material
Gasification balance is a daily operation that would
The gasifier hopper temporarily process 100 tons of MSW. This is the
stores the feed and delivers it at a basis used by the researchers in
steady rate to the fluidized bed gasifier. calculating all mass and energy
The MSW is converted into raw syngas balances, in preparing the process flow
through gasification in the equipment sheet, in designing equipments, and in
where air serves as the gasification calculating the economic feasibility of
medium. The gasification product the proposed power plant
composition is discussed in chapter 4 of MSW composition is an
this report. uncontrolled variable that could widely
alter the composition of the produced
Post-treatment and Cleaning gas. So for the purpose of this study, the
Raw syngas then undergoes known average compositions of Metro
post-treatment. It first undergoes Manila MSW were the basis used for the
catalytic cracking with dolomite which subsequent computations made,
transforms some unconverted product, specifically for the pre-treatment
or tar into more carbon monoxide and process.
hydrogen. The cracker has two columns Figure 3 shows the Process Flow
in order to accommodate dolomite Diagram of the proposed plant.
reloading to one of the columns while
the other is in operation. Particulates are IV. Equipment Design
then removed from the syngas by a a. Pre-treatment
candle filter after the cracking process.
HAMMER MILL
Electric Conversion and Heat The hammer mill was designed to
Recovery reduce the particle size of the MSW
When post-treatment is feed for easier classification in the nest
accomplished, the syngas is now fed processes. A low-speed, low-torque
into the gas turbine. The gas turbine hammer mill was chosen to avoid
converts syngas into electrical energy. explosions caused by undesired
The power output of the turbine is components in the feed stream and
6.42MW. About 1MW of this output is reduce the wear and tear caused by the
used for the plants energy requirement feed stream. The particle size of the
while the remaining is delivered to MSW feed will be reduced from 14.7 cm
electric distribution companies. (average) to -6m (average) in this
equipment.
c. Mass and Energy Untreated MSW is composed of
Balance different types of materials with different
The following paragraphs particle sizes. To homogenize the
describe the material flow in and out of particle size of the MSW, size reduction
the whole reactor. Several assumptions is necessary. A mechanical crusher,
were made so as to make the specifically a hammer mill, will be
calculation straightforward. These employed to perform the said task. The

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 8 of 24


Figure 3. Process Flow Diagram

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 9 of 24


crushing will also reduce the glass
component of the MSW stream to fines,
which will allow easier removal of glass
in the subsequent process. The particles
size distribution of the MSW feed was
assumed to be similar to that of New
York City (Nakamura, Castaldi, &
Themelis)
Figure 4. Hammer Mill
The MSW feed enters the
hammer mill through the hopper to the TROMMEL SCREEN
hammer circle. The rotating hammers in The trommel screen is designed
the circle crushes the feed by impacting to carry out size discrimination for the
it. The smaller particle is then allowed to crushed MSW. The design allows
pass through a series off grates where separation of the feed into three
only the material with the appropriate streams: X-3, X-4, and X-5 with particle
particle size is allowed to pass through. sizes of -2.54 cm, -6 cm, and +10.12
The rejected material is retained in the cm, respectively. The first stream is
hammer circle until it is reduced to the composed of crushed glass and other
desired particle size. (Tchobanoglous & undesired fines which will be disposed
Kreith, 2002) The specifications of the in landfills. The stream with the largest
selected hammer mill are shown below. particles size is assumed to be
composed mainly of cardboard boxes
Parameter Value Unit and this will be transported to the rotary
Actual Capacity 4.17 ton/hr shredder to be incorporated with the X-
Volumetric Capacity 6.683 m3/hr 7A stream.
Rotational Speed 1800 rpm After reducing the MSW into
smaller particle sizes, the stream must
Hammer length 25.00 cm
be classified into different streams. The
Hammer width 6.35 cm desired particle size for the next
Hammer Thickness 6.40 cm processes is -6 cm. Those particles with
Selected Hammer Mill sizes less than 1 inch are assumed to
MAXI PIG /10
Model be glass, which were effectively grinded
Feed mouth dimension 400x1490 Mm into fines during the processing in the
Power 250 kW(max hammer mill. The oversized
output) components of the feed stream, whose
H 1657 mm sizes exceed 10 cm, are assumed to be
D 1170 mm mostly cardboard because they are
W 2612 mm least likely to be reduced into smaller
Table 1. Hammer Mill Design specifications sizes by the hammer mill.
(Tchobanoglous & Kreith, 2002). For the
this plant‟s trommel mill, the equipment
is expected to completely separate the
crushed MSW into 3 streams, whose
particle sizes are -2.54 cm, -6 cm, and

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 10 of 24


+10.12 cm, respectively. To separate Parameter Value Unit
the feed stream more effectively, the Inclination angle 5 degrees
equipment will be designed with spikes Diameter 3.5 m
in its interior, which will serve as bag Mesh Size 1 5 cm
openers for those components trapped
Mesh Size 2 8 cm
in plastic bags.
Screen length 5 m
To design the trommel screen for this
plant, the efficiency of the equipment Rotational Speed 12 rpm
was assumed to be 99%, which means Table 2. Trommel Screen specifications
complete separation of MSW into the 3
desired streams. Since there is no MAGNETIC SEPARATOR
literature regarding the design of To remove the ferric components
trommel screens, literature values from of the MSW feed, a magnetic separator
Tchobanoglous et al and Robinson is installed in the pretreatment system.
adopted for this design. The power The equipment is expected to remove
consumption of the equipment was all the ferric materials, which constitute
extrapolated using the empirical data 4% of the untreated MSW. The removed
from Caputo et al‟s study. The sizes of ferric metal is then sent to a recovery
the openings for the trommel screen facility for recycling.
were estimated using the equation The magnetic separator for this
below. process is expected to remove the all
the ferric components of the screened
MSW. Since the amount of ferric
material to be recovered is just a small
fraction of the total MSW stream, a
magnetic head pulley will be
Where: appropriate. This type of magnetic
p = probability of the feed particle separator is the least expensive and
to pass through the screen easiest to operate. A permanent magnet
d = diameter of the feed particle was selected to reduce the electric
a = length of one side of the consumption of the plant.
square opening (or diameter of the To determine the appropriate size
circular opening) of the screen of the magnetic head pulley, empirical
Q = ratio of the area of the data from Perry‟s‟ Chemical Engineering
openings over the total screen area Handbook were used.
The head-pulley magnet will be
Material to be separated is fed installed at the end of the conveyor belt.
into one end of a tubular, rotating screen As the MSW stream arrives at the end
with a downward slope, so that the of the conveyor belt, the non-ferric
material will flow down the screen as it material falls off the belt while the ferric
is dropped and tumbled. Blades or waste is attracted to the head pulley and
prongs are located at the inlet end to is retained on the belt. Once the
open bags. (Tchobanoglous & Kreith, attracted material passes through the
2002) bottom of the belt, it falls off as soon as
it is moved away from the magnetic
pulley. The ferric materials separated
will be collected and transported to a

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 11 of 24


recycling facility. The computed The eddy current separator
specifications for the magnetic head produces a magnetic field that induces
pulley are shown below. an electric current in metallic
components of the MSW feed. The
Selected Pulley mm 914 induced electric current then generates
diameter a secondary magnetic field, which is
Belt velocity m/s 1.855 opposite to that of the primary magnetic
Belt width mm 457 field. This causes a physical repulsion of
Maximum depth of Mm 191 the metallic waste from the main stream.
material (Table Due to the low conductivity and density
19-18, Perry's) of aluminum, it is easily repelled and
Table 3. Magnetic Separator specifications separated by the equipment. Based on
the type of MSW feed and inlet flow
The head-pulley magnet is rate, the following specifications were
installed as an integral part of the belt determined.
conveyor. As material falls off the end of
the conveyor, the head-pulley magnetic ECS Model LC
forces hold magnetic material to the Magnetic Scalper CP and
belt, attracting the magnetic materials pulley
and changing their trajectory as they fall Actual Capacity ton/day 83
off the end of the belt. Under burden ton/hr 3.458
material, which is entrapped under the Capacity per ton/hr 20
magnetic metal, will be held onto the 1000mm Feed
belt by the magnetic material above it width (Shredded
and carried over into the magnetic refuse, 50-
product, resulting in contamination. 150mm)
Minimum feed mm 172.9
EDDY CURRENT SEPARATOR width
The eddy current separator
serves as a separator for non-ferric Separator
metal waste from the MSW stream. For Dimensions/Type
this process, all non-ferric metal waste ECS Model 12
is assumed to be aluminum. The Weight kg 450
aluminum waste will be collected and Total Power 6.25
sent to a recycle facility. Feed Width A 305
This process must remove all the Distance bet. B 1500
metal waste which was not removed Pulleys
from the previous process, which is length (w.out C1 2110
assumed to be aluminum. Aluminum hopper)
waste comprises 1% of the total MSW width E 899
feed. An eddy separator is appropriate System height G 1840
for this process since it allows easy System Length H 4120
separation of aluminum from MSW. To Table 4. Eddy current separator specifications
determine the appropriate specifications
for the said equipment, a selection table ROTARY SHEAR SHREDDER
from Eriez Magnetics Europe Ltd was
used.
MSW Gasification Carillo, Mationg, Penuela, Rosas Page 12 of 24
After removing the unwanted The specifications of the chosen shear
components of the MSW feed, the shredder are shown below. (Shredders
stream must be further homogenized & Grinders - TWIN SHAFT SHEAR
and its particle size must be reduced to TYPE)
less than 6 mm before entering the
fluidized bed gasifier. The rotary shear Model HT80-3526
shredder will allow size reduction of Motor Power 2 x 40 HP
streams X-8 and X-9, whose average Feed Size L x W 35" X 26"
particle sizes are -6 cm and +10 cm. Shaft Distance 12
In order to achieve the required
Rotor Thickness 1.2" / 2"
particle size for the fluidized bed
Rotor Diameter 13.6"
gasifier, a more uniform size reduction
process must be added to the Rotor Speed -rpm 22 / 20
pretreatment process. A rotary shredder Machine Weight 7700 lbs
is the most appropriate since it is able to Table 5. Shear shredder specification
cut the paper and plastic components of
the MSW into shreds effectively. The VIBRATING SCREEN
inlet MSW stream into this equipment is The vibrating screen allows
assumed to be of uniform size, with removal of particles with sizes greater
particles finer than 6 cm. The desired than 6 mm from the MSW stream. The
particle size is less than 6 mm, which is oversize is sent back to the rotary shear
the maximum allowable particle size for shredder where it is reduced to the
the fluidized bed gasifier. desired particle size.
To compute for the appropriate To separate the fraction of the
design for the rotary shear shredder, the MSW stream with the desired particle
density and volumetric flow rate of the size, a separator equipment is needed.
inlet stream were determined. The For this function, a vibrating screen is
particle size distribution of the resulting the most appropriate equipment due to
product from the shredder were adopted its high efficiency. The oversize stream
from the empirical data from is returned to the rotary shear shredder
Tchobanoglous et al. to reduce it to an admissible size while
The rotary shear shredder is the undersize is transported to the
essentially a continuous rotary shear or storage silo for gasification.
scissor. Material is fed into counter Vibratory screens are flat screens
rotating shafts with closely spaced mounted at an angle, which facilitates
cutters. This type of shredder tends to material movement. During operation,
cut feed material into strips, which are the screens vibrate up and down to
the same dimension as the cutter width allow undersize particles to pass
or spacing. The cutters are not circular, through it. (Tchobanoglous & Kreith,
but rather oblong. Material passes down 2002). The acquired specifications of
through openings that form between the the screen is shown below, as collected
tops of opposing cutters from opposite from the Shanghai Shibang Machinery
shafts. Hooks are positioned on each Catalogue. (SHANGHAI SHIBANG
cutter to grab material that enters the MACHINERY CO., LTD.)
mill and pull it into the shear where it is
cut. (Tchobanoglous & Kreith, 2002)

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 13 of 24


Type YA1237 Gasification of Municipal Solid
Screen Spec mm 1200x3700 Waste (MSW) is somehow complicated
Layers 1 due to its properties. Its kinetics has not
been studies extensively compared to
Sieve Pore mm 3-50
coal gasification. Yet it is possible to
Max Feed Size mm 200
design a MSW gasifier by considering
Capacity t/h 7.5-70 the feed as a form of biomass and
Power kW 5.5 obtaining the ultimate analysis
Vibrating composition of the MSW feed. Several
Hz 800-970
Frequency papers have been published that shows
Incline of Screen degrees 5 how gasifier design-specifications can
Table 6. Vibrating screen specification be calculated using ultimate analysis
data of any feed.
b. Gasification
Desired Product MWth 20.177142
FLUIDIZED BED GASIFIER Gas Power Output 9
The design of a MSW fluidized Desired LHV of MJ/Nm3 4.75
bed gasifier was performed which Product Gas
required the desired energy from the Biomass/Fuel LHV MJ/kg 22.181278
gas turbine and ultimate analysis of the 8
MSW feed. The ultimate analysis was Gasifier efficiency 0.89
approximated by utilizing the Metro Air Equivalence ER 0.2654979
Manila average compositions and an Ratio
older ultimate analysis study of MSW Stoichiometric kg/kg 7.3410483
from USA. The sizing and streams of amount of air dry fuel 8
the gasifier were obtained by an required
established process calculation. On the Fluidization m/s 35.417284
other hand, the composition of the Velocity 9
Maximum kg/m3.h 1120
product was estimated by using a
Volumetric
stoichiometric model. Lastly, the biomass capacity
controls for a gasifier and its of gasifier
corresponding HAZOP were presented. Product Gas Flow Nm3/s 4.2478195
The heart of the energy Rate
conversion plant is the gasification Biomass/Fuel kg/s 1.0220757
stage. This is where the pretreated Feed Rate
MSW is converted into usable Synthesis Air Flow Rate kg/s 0.0191727
Gas (Syngas). Gasification is basically Cross Sectional m2 0.4618645
heating with the presence of less Area
stoichiometric air requirement. This Volumetric Air m3/s 0.0630913
prevents complete combustion from Flow Rate @ 875 C
happening which is undesired since this Minimum Bed m 7.1130023
turns the feed into unusable products height
Diameter of m 0.7668534
instead. The basic compositions of
gasifier
syngas are Carbon Monoxide and
Table 7. Gasifier specification
Hydrogen gases with some amounts of
Carbon Dioxide and Nitrogen.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 14 of 24


c. Post treatment vital step in the utilization of the
synthesis gas for power production.
CATALYTIC TAR CRACKING Specifically for gas turbine use, the limit
Catalytic tar cracking is the first in for biomass gas tar concentration is
the series of gas clean up processes. within the range of 0.05 to 5 g/Nm3. In
This process is done to reduce tar order to attain this required
concentration on the synthesis gas concentration in our process, catalytic
produced from the gasification process. decomposition of the biomass tar is to
Tar is a complex mixture of condensable be done in a reactor, using dolomite as
hydrocarbons, including, among others, the catalyst.
oxygen-containing, 1- to 5-ring aromatic, The process undergoes
and complex polyaromatic hydrocarbons heterogeneous catalytic reaction. Using
(L. Devi et al., 2003). For Gas Turbine the rate constants calculated from the
applications, tar concentrations of the study by L. Devi et.al, a reactor will be
synthesis gas must be reduced to a designed assuming plug flow conditions,
tolerable level that the turbine can and utilizing the calculated apparent rate
withstand and accommodate. constant and activation energy
For our process, dolomite will be determined from the experiment in
used as the catalyst. Dolomite is a formulating a global rate expression for
cheap, non-metallic, disposable catalyst the reaction.
that performs well in reducing tar From the study mentioned above,
concentration of gasification product several considerations were made such
gas. as plug flow conditions. The apparent
One of the main obstacles faced value of the constants that were
by biomass gasification technologies is determined already accounts for the
the presence of considerable amount of effect on overall rate of transport (bulk to
tar and particulate matter in the interface and intraparticle) and
synthesis gas produced from the adsorption/desorption. Likewise, first
process. The typical level of tar order reaction mechanism were
concentration for fluidized bed biomass assumed for the global rate of the
gasifier is 10 g/Nm3. Tar is considered reaction.
to be an undesirable by-product of the From the apparent reaction
gasification process due to some kinetics constants, the space time,
potential problems that it could cause. catalyst amount, and catalyst-sand
Examples of these nuisances are (L. mixture amount were calculated.
Devi et.al, 2005): The reactor design for the lab
scale reactor used in the study will be
•Condensation and subsequent the basis for the industrial scale design.
plugging of downstream After performing the calculations, the
equipment results indicate the need for
•Formation of tar aerosols approximately 266 kg of dolomite or 1.2
•Polymerization into more tons of the catalyst-sand mixture per
complex structures reactor. Two 12 L stainless steel fixed
bed reactor (1 m diameter, 15 m height)
Therefore, reducing the tar will be used. These results are all based
concentration of the product gas is a on and in line with the study by L. Devi

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 15 of 24


et.al, thus the design method is highly Face Velocity 2.9 cm/s (5.8 ft/min)
dependent on the said study. The table Inlet Dust 18,400 ppm
below summarizes the result of the Loading
calculations. Outlet Dust Not Detectable
K0,app (m3/kg h) 7.2 x 1010 Loading
E (kJ/mol) 196 Table 9. Candle Filter specifications
R (J/mol K) 8.314
T (K) 1073.15 The result of the equipment
e-Eapp/RT 2.88089 x 10-10 design indicates the requirement for a
K (1/s) = K0,app x e-E/RT 20.74239642 Hot Gas Filtering Refractory Lined
Conversion Desired 95% Vessel diameter of 10 ft., with 64 candle
Space time (kgcat h/m3) 0.144425563 elements that are 1.5 m long. This
Flowrate (m3/h) 1845 design for the gas filtering is enough to
Amount of catalyst (kg) 266.4651631 reduce the biomass gas particulate in
Amount of mixture (kg) 1567.442136 the synthesis gas to allowable limits.
Table 8. Tar Cracker calculations This design method depends largely on
the reported performance of the SPPC
CANDLE FILTER Pinon Pine Hot Gas Filter in the tests
Following the initial gas clean up conducted.
step that reduces the tar concentration
through catalytic reaction with dolomite d. Gas Turbine
of the tar present in the produced
synthesis gas, the removal of dry solid GAS TURBINE
particulates will be done through candle The second most important component
barrier filters. Candle filters are porous, of the plant is the gas turbine package
ceramic, or metallic. (Basu, 2010) The which converts post-treated syngas into
porosity will depend on the size of the energy. The design of the turbine is
finest particles that must not be allowed simple since selection of a packaged
to pass through. These particles will product was done beforehand.
then deposit on the wall and form a The second key component of
layer of solids called a “filter cake.” the waste-to-energy plant is the
The candle filter design will be conversion of syngas to mechanical and
determined based on the results of the electrical energy by a gas turbine. The
study indicated on the report by T. gas turbine design process is simple
Lippert et.al for Westinghouse since the proponents have established a
Advanced Particle Filter System. The specific gas turbine package. The
specifications of the filter will be based specific package is the Allison (Rolls-
on the results of the biomass hot gas Royce) 501-KH5 Gas Turbine Package
filter tests conducted. which is currently available in the
market.
Gas Flow 1000 to 1700 ACFM
Filter 1.4 to 2.4 Mpa (200 to 350 Figure 4 shows the Gas Turbine
Pressure psig) equipment specification by a)
Filter Gas 1200 to 1900°F manufacturer and b) package dealer.
Temperature
No. of Candle 64
Elements

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 16 of 24


Figure 4a. Gas Turbine manufacturer specification

Figure 4b. Gas Turbine Package dealer specifications

In addition to the information stated The first major factor considered


above, syngas flow rate and energy in this chapter is the Total Capital
demand was sought. After the Investment. This is the amount in which
calculation process, the proponents the plant needs in order for it built. The
obtained the syngas flow rate and capital investment basically comprises
process energy demand to be at 3.3928 the total cost of equipment purchase
Nm3/s and 20.1771 MWth. and the site development. The second
major factor considered is the Total
V. Economic Analysis Product Cost. This is the amount
a. Cost Estimation needed to produce one unit of product.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 17 of 24


To complete the feasibility study, Conveyor Belt 2,660,530.36
all the costs shall be compared to how Feed Conveyor 1,375,234.19
much the plant will gain in revenue. Tar Reactor 956,958.14
Engineering Economics methods such Table 10. Summary of equipment cost
as Present Worth and IRR analysis shall
be done to effectively determine if the
proposal is an attractive venture or not. Amount %
Sensitivity analysis is also presented in (PhP)
the later part to determine which factors Purchased
of cost greatly affect the plant‟s 369,417,439.
Equipment
69
desirability. (Delivered E.C.) 20.53
We begin the calculation of TCI 144,072,801.
Installation
by determining how much all in all the 48 8.01
equipment are worth. The prices of each Instrumentation 48,024,267.1
of the equipment discussed in the Mass and Controls 6 2.67
and Energy Balance Chapter were 114,519,406.
Piping
already mentioned. Next, the other 30 6.37
36,941,743.9
factors for TCI were estimated using Electrical
7 2.05
Table 17 of Peters and Timmerhaus
Buildings and 107,131,057.
(1991). Assigning the total purchased Services 51 5.95
equipment as 100 over 487, the total Yard 36,941,743.9
capital investment can now be easily Improvements 7 2.05
determined. Using the total PhP 369 M, 203,179,591.
the total capital investment is calculated Service Facilities
83 11.29
by multiplying the amount to 487 over 22,165,046.3
Land
100. 8 1.23
Engineering and 118,213,580.
Equipment Equipment Cost Supervision 70 6.57
(PhP) Construction 125,601,929.
Expense 49 6.98
Hammer Mill 13,156,209.99
66,495,139.1
Trommel Screen 4,252,085.81 Contractor's Fee
4 3.70
Magnetic Separator 2,646,283.38 132,990,278.
Eddy Current 529,256.68 Contingency
29 7.39
Separator 273,368,905.
Rotary Shredder 3,804,328.78 Working Capital
37 15.20
Vibrating Screen 180,443.35
Vibrating Bottom - 1,020,381.33 Total Capital 1,799,062,93
Silo Investment 1.27 100.00
Centrifugal Air 2,583,554.68
Compressor Fixed Capital 1,525,694,02
Gas Turbine 43,830,813.10 Investment 5.90 85.00
Fluidized Bed Gasifier 233,081,114.43 Table 11. Breakdown of total capital investment
Pyrolysis 0.00
Candle Filter 45,101,906.68
Air Preheater Furnace 5,783,826.44
(for Gasifier)

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 18 of 24


% of Fixed PhP/year Notes: % from
Capital Taxable
Investment Product Cost
Raw Materials 0.00% 0.00 Raw material is MSW. It is 0.00%
assumed that the plant will
obtain MSW with no cost.
Operating Labor 0.08% 1,169,671.35 See Operating and Other 0.72%
Labor Cost Calculations
Direct 0.02% 303,828.55 See Operating and Other 0.19%
Supervisory and Labor Cost Calculations
clerical labor
Utilities 0.34% 5,212,892.76 Natural Gas and Dolomite. 3.19%
See Utilities Tab for NG and
Dolomite.
Maintenance 4.44% 67,808,623.37 See Maintenance and 41.54%
and Repairs Repairs Cost Calculations
Operating 0.67% 10,171,293.51 Assumed 15% of 6.23%
Supplies Maintenance and Repairs
Cost
Laboratory 0.01% 175,450.70 Assumed 15% of Operating 0.11%
Charges Labor Cost
Patents and 0.28% 4,258,811.77 0 to 6% of Product Cost 2.61%
Royalties
Depreciation 3.84% 58,614,233.76 Used Straight Line Method 35.90%
of Depreciation based on
MACRS-GDS Recovery
Period
Local Taxes
Insurance 1.00% 15,256,940.26 Assumed 1% of Fixed capital 9.35%
investment.
Rent 0.00% 0.00 Assumed land shall be 0.00%
bought and no buildings
shall be rented.
Plant Overhead 2.72% 41,569,273.96 Assumed 60% of Labor, and 25.46%
Costs Maintenance and Repairs
Costs
Administrative 0.02% 292,417.84 Assumed 25% of Operating 0.18%
costs Labor Cost
Distribution 0.19% 2,839,207.85 2 to 20% of product. (2%) 1.74%
and selling costs
Research and 0.93% 14,196,039.23 2 to 20% of product. (15%) 8.70%
development
costs
Total Product 163,254,451.14 Without Depreciation
Cost
104,640,217.38 With Depreciation

Table 12. Total Product Cost Breakdown

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 19 of 24


Total Product Cost All of the equipment purchased
As mentioned in the Mass and are assumed to depreciate after the
Energy Balance chapter, the cost of effective plant life of 22 years. This plant
obtaining raw materials is zero since it life is actually stated by the MACRS-
was assumed that the operators will GDS depreciation method which is used
acquire MSW for free. This scenario for this plant proposal. The MACRS
may be possible since it would be states that either Straight Line or
beneficial to local authorities if the Declining Balance with Switch can be
problem of MSW is shared by another used within the recovery period of the
company or group. plant. The recovery period for a typical
The Cost of Operating Labor was power plant is 15 years as instructed by
achieved by assigning appropriate this depreciation method. Straight Line
laborers for each process stage or method was used for 15 years. The
machine involved in the plant. In depreciable materials of the plant other
addition, control and chemical than the equipment include:
engineers, and mechanical and Instrumentation and Controls, Piping,
electrical engineers are also assigned to Electrical, Buildings and Services, and
take care of the specific work areas. The Service Facilities.
wage rate of the laborers for the plant is The other factors that should be
based on a 2006 survey by the considered for the Total Product Cost
Department of Labor and Employment. such as Insurance, and Research and
The consumable materials that Development Cost are estimated by
do not count as raw materials are giving percentages of various costs
placed as Utilities for the Plant. There already available.
are three consumables of the plant that Table 12 provides a breakdown
were categorized as Utilities. These are of the total product cost.
Natural Gas and Dolomite. Since the
plant is self-sustaining in energy, Economic Feasibility
electricity consumption is not considered For one year, the plant shall have
as a utility. projected gross revenue of about PhP
The cost of Maintenance and 198 M. This can now be used to assess
Repairs was estimated using table 25 of the plants economic feasibility, including
Peters and Timmerhaus (1991) Cost the total capital investment and total
Estimation Chapter. Each operation product cost.
stage is rated how much wage and Moreover, dividing the total
material should be allocated for its energy output to the total product cost
maintenance and repairs. calculated beforehand, the cost of
The Plant Overhead Cost which producing 1 kilowatt-hour of energy is
also takes care of the electric PhP 2.80/kWh. This value is smaller
consumption of the Gas Turbine than the selling price of Meralco which
Generator Station and of the plant such indicates that there will be positive
as lights and air-conditioning is revenue for the proposed plant.
assumed to be 70% of the sum of The initial revenue should be
Operating Labor, Supervision and deducted to the total product cost in
Clerical Labor, and Maintenance and order to determine the actual profitability
Repairs Costs. of the plant without any other charges.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 20 of 24


But tax laws of the country should be Using this value, we can
considered too. approximate how much it would cost to
Taxation should be considered throw garbage to a landfill. Using an
since it will greatly affect the net income inflation calculator provided by
of the project. The effective tax rate for a inflationdata.com, the price USD 10 is
production facility such as this is 35%. currently USD 13.13. And with a foreign
Tax is placed on the net income and exchange rate of PhP 43.83, the cost is
shall be paid by the future project 575.71 PhP/tonne.
owners. After this consideration, the Even though 100 tonnes/day of
final net income is now achieved. The MSW is delivered to the site, the actual
after-tax net income is about PhP 32.83 feed processed is about 90 tonnes/day
M. and the rest gets delivered back to
The payback period is calculated landfills or recycling facilities. The
by dividing the total capital investment amount of cost saved by putting up the
by the after-tax net revenue per year. proposed gasification plant is PhP 15.5
The result, which is also in years, is the M if the proposed gasification plant is
time it takes for the investment to realized. Hence, even if the plant is not
actually start earning profits and the profitable in terms of payback years, it is
capital already compensated. The possible to construct the gasification
payback period is 29.51 years, which is and power plant with the landfill benefit
more than the expected plant life. in mind. The revenues saved from the
Hence, this indicates that unfortunately, landfill may be used in order to shorten
the plant is not profitable and payback the payback period.
won‟t be attained unless plant is to have
a longer life span. VI. Conclusion and
Recommendations
Landfill Cost Savings The report proposes a municipal
An international study was made solid waste (MSW) conversion to usable
in 1999 by Johannessen and Boyer energy. Market study of this report
about the landfill status for most parts of points out the increasing demand of
the world. For the Philippines, the energy in recent years. Synthesis gas
Carmona and San Mateo landfills were was also shown to be increasingly used
investigated. They remark that as power since 1989 at a speedy rate.
municipalities charged a tipping fee for The current sources of syngas are coal
every truck of garbage delivered to their and petroleum. Several competitors
landfill. For San Mateo, the charge is have been mentioned in this section
about USD 1 per 4-wheeled truck including the several natural gas
delivered or about 10m3 of garbage and producers in the country. The proposed
USD 1.5 per 6-wheeled truck (15 m3). plant site is in Tanza, Navotas, located
On the other hand, Carmona landfill near the new landfill area.
charges a flat rate of about USD 5 per Technical discussion of the
truck delivered. There was no direct proposition suggests the utilization of a
source of how much it would cost for a fluidized bed gasifier, with air as its
landfill but they estimated that per tonne gasification medium. The process shall
of garbage, the landfill cost is USD 10. produce Synthesis Gas (SynGas) that
will be fed in a Gas Turbine Generator.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 21 of 24


The whole process is composed of The total capital investment
MSW pre-treatment, gasification, post- needed for the plant is PhP 1.80B while
treatment and cleaning, and electrical the total product cost per year is PhP
energy conversion and heat recovery. A 163M. The net income per year
complete process flowsheet and amounts to PhP 60M per year.
detailed streams were presented. In Economic analysis shows that the
addition, detailed design process plant‟s payback period is 29 years. This
sections for each significant process is greater than the expected plant life of
were also included. The projected power 22 years. However, considering the
output of the plant is 5.19MW with the savings of decreasing 90 tonnes/day of
amount needed to self-sustain the plant waste from landfill use, the plant may be
already considered. The report economically feasible if the savings are
concludes that the proposed method is used for the benefit of the plant.
feasible.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 22 of 24


VII. References

First Gas Power Corporation. (2010). Retrieved October 20, 2010, from First Gen Corporation:
http://www.firstgen.com.ph/OurAssets.php?id=17

San Lorenzo CCGT Power Plant, Batangas City, Philippines. (2010). Retrieved October 20, 2010, from
power-technology.com: http://www.power-technology.com/projects/sanlorenzo/

Añonuevo, E. P. (2009, August 19). Meralco draws power from first renewable energy source. Retrieved
October 20, 2010, from The Manila Times.net:
http://www.manilatimes.net/index.php/archives/444-meralco-draws-power-from-first-
renewable-energy-source

Department of Energy. (2009). Power Statistics. Retrieved April 1, 2011, from Department of Energy
Portal: http://www.doe.gov.ph/ep/Powerstat.htm

Miras, JC. (2006). First and Oldest (Hydroelectric) Power Plant in the Philippines. Retrieved October 20,
2010, from JcMiras.Net_02: http://www.jcmiras.net/surge/p77.htm

Navarro, R. A. (2003). A Systems Approach on Solid Waste Management of Metro Manila, Philippines.

Rodrigues, Monica, Arnaldo Walter, and Andre Faaij. "Performance evaluation of atmospheric biomass
integrated gasifier combined cycle systems under different strategies for the use of low calorific
gases." Energy Conversion and Management 48, 2007: 1289–1301.

(2004, January 16 ). SOLID WASTE INCINERATION. Washington: U.S. Army Corps of Engineers.
Basu, P. (2010). Biomass Gasification and Pyrolysis: Practical Design and Theory. Oxford: Elsevier.

Eriez Magnetics Europe Ltd. (2010, May 24). Product Fact Sheet: Eddy Current Separator Guide for
Preliminary Equipment Selection. Retrieved March 29, 2011, from Eriez Magnetics Europe Ltd:
http://eriez.com/Products/EddyCurrentSeparatorsRecycling/Documents/Brochure/

MANFREDINI & SCHIANCHI Srl. (n.d.). P.I.G. HAMMER MILL. Retrieved March 28, 2011, from
MANFREDINI & SCHIANCHI:
http://www.google.com.ph/url?sa=t&source=web&cd=1&ved=0CCIQFjAA&url=http%3A%2F%2
Fwww.manfredinieschianchi.com%2Fpdf%2F3-macchine%2F2-EN%2F301-02-2EN-hammer-
mills.pdf&rct=j&q=pdf%3A%20MANFREDINI%20%26%20SCHIANCHI%20hammer%20mill&ei=o4
KRTYLQCcWHcf31tYkH&usg

Nakamura, M., Castaldi, M., & Themelis, N. J. (n.d.). Numerical analysis of size reduction of municipal
solid waste particles on the traveling grate of a waste-to-energy combustion chamber.

Navarro, R. A. (2003). A Systems Approach on Solid Waste Management in Metro Manila, Philippines.
Sweden: Lund University International Master’s Programme in Environmental Science.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 23 of 24


Olsen, L., & Carnes, B. (2009). SCREEN CAPACITY CALCULATION. Retrieved March 28, 2011, from
VIBFEM:
http://vibfem.com.au/resources/vibrating_screens_and_feeders/Screen_Capacity_Paper.pdf

Perry, R. H. (1997). Perry’s Chemical Engineers’ Handbook. — 7th Ed. USA: The McGraw-Hill Companies,
Inc.

SHANGHAI SHIBANG MACHINERY CO., LTD. (n.d.). Vibrating Screens. Retrieved March 28, 2011, from
SHANGHAI SHIBANG MACHINERY CO., LTD.: http://www.shibang-
china.com/fr/Resources/crusher-pdf/download/vibrating-screen.pdf

Shredders & Grinders - TWIN SHAFT SHEAR TYPE. (n.d.). Retrieved March 21, 2011, from Wastecare
Corporation: http://www.wastecare.com/Products-Services/Shredders-Grinders/Grinders-
Shredders-2-Shaft-Shear-HT.htm

Tchobanoglous, G., & Kreith, F. (2002). Handbook of Solid Waste Management - Second Edition. U.S.A.:
The McGraw-Hill Companies, Inc.

MSW Gasification Carillo, Mationg, Penuela, Rosas Page 24 of 24

Você também pode gostar