FRAMED STRUCTURES
FOUNDATIONS
SUPERSTRUCTURE
STAIRS
1.1 CONCRETE
Clause 1: Classification
Clause 5: Projections
• Small projections and cores such as nibs, fins, strings, cornices and kerbs
shall be included with the relevant item to which they apply.
1.2 FORMWORK
(c)Special: Smooth and fair: This class of finish requires the highest standard
of concrete work, formwork, accuracy and technique. The
standard of finish shall be straight, smooth and uniform finish of
good quality and consistent colour and texture, free of
honeycombing.
• Formwork to columns and walls separated into stages of n.e. 3,5 m high above
bearing level and thereafter in stages of 1,5 m.
• Formwork to circular columns measured in number and may include caps and
bases.
• Formwork to edges, risers, ends and reveals not exceeding 300 mm high or
wide all added together and measured in metres.
• Descriptions deemed to include bending, hooked ends and binding wire, cover
blocks and spacers, and maintaining in position during concreting.
• Bars in lengths exc. 13 m and n.e. 18 m kept separate and thereafter in stages
of 1 m lengths.
Filling
D
Stooling
A
Column
b
Order of Measurement:
Blinding
A - Column bases
B - Foundation columns
C - Foundation beams
D - Stooling under foundation beams
MEASURING LIST
A Columns bases
• Excavate for column bases m3
• Risk of collapse m2
• Unreinforced concrete (URC) in blinding under column bases m3
• Reinforced concrete (RC) in column bases m3
• Formwork to sides of column base (exceptional cases) m2
B Foundation Columns
• R.C. in foundation columns m3
• Formwork to sides of foundation columns m2
C Foundation beams
• Excavate for foundation beams m3
• Risk of collapse m2
• URC in blinding under foundation beams m3
• R.C. in foundation beams m3
• Formwork to sides of foundation beams m2
• Excavate for working space for formwork to sides of foundation beams m2
C B First floor
E
F Measure
each floor
from top of
floor level to
top of floor
level above
A
– all
inverted
beams part
of slab
Ground floor
Measuring procedure
Order of Measurement:
A Columns
• R.C. in columns m3
• rectangular columns m2
• L-shaped columns m2
• T-shaped columns m2
• circular columns No
• R C in columns m3
• R.C. in columns m3
• Formwork to soffit of slab propped up exc 1,5m and n.e. 3,5 m high m2
D Beams
F Isolated beams
• R.C. in walls m3
• Formwork to sides and walls with total height exceeding 3,5 m and n.e. 5 m
above bearing level m2
H Staircases
First floor
Landing
Ground floor
• Formwork to sloping and stepped outer edges of stairs ne. 300 mm high
extreme. m