Escolar Documentos
Profissional Documentos
Cultura Documentos
Rev: A
SITE: JOB No: ANTICIPATED ACTIVITY
Start Date End Date
68 Tavistock Road
London TV001
W11 1AW June 2010 August 2010
NUMBER OF PERSONS INVOLVED IN
CONTRACTOR: PREPARED BY:
ACTIVITY:
CUBIC Design &
Quinton Schonknecht 1 Supervisor 2 Operatives
Development
Description:
Installation of the External Scaffold to facilitate the refurbishment works to the apartment block.
1
• Access ladders will be removed at the end of every shift and locked/stored to prevent access.
• Once scaffold struck out all fixing anchor points will be made good.
• Ensure site is clean and clear after works completed.
CUBIC PERMIT TO
LOAD TEMPORARY CSL to Tigon N/A Hat/gloves/goggles Yes
WORKS
2
ENVIRONMENTAL CONSIDERATION
(give details below and define the methods you wish to adopt to reduce impact and risk)
Reference should be made to the requirements of the construction phase Health Safety and Environmental
Management Plan where methods and techniques may be dictated to mitigate significant environmental
impact. These requirements must form part of the detailed method statement where activities form part of
these mitigation measures. Separate environmental risk assessments should be considered within this
method statement
• Welfare Facilities
• Names of appointed persons including qualified first aiders.
• Standard forms for such items as toolbox talks, risk assessment method statement inductions and
records
N/A
This method statement together with the risk assessment must be authorised by Cubic.
Once authorised by Cubic, the authorised method statement risk assessment is to be
registered and a copy kept in the site file.
3
OPERATIVES SIGNATURES:
Operatives who sign below hereby confirm that they fully understand the Works detailed
above:
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
4
In columns 3 and 8:
Probability 1 = extremely remote In columns 4 and 9: DIRECTIONS
Probability 2 = possible Severity 1 = negligible occurrence Complete cols 1-6
Probability 3 = likely Severity 2 = minor occurrence Eliminate hazard all together if reasonably practicable. For eliminated hazards enter 0 in column
Probability 4 = probable Severity 3 = significant occurrence 11. Reduce all other hazards if reasonably practicable.
Probability 5 = definite Severity 4 = major accident or injury Apply Control Measures to all greater than LOW in column 6
Probability levels 1 to 5 to be used in columns 3 and 8 Severity 5 = fatality Complete cols 7-11 and apply additional controls if Risk rating greater than LOW in col 11.
Severity levels 1 to 5 to be used in columns 4 and 9 Repeat until LOW.
ASSESSMENT OF RISK : H= High (risk rating 10-25), M =Medium (risk rating 5-10), L=Low (risk rating 1-5)
Risk rating = Probability x Severity
H, M, Lfor HarmPotential
1-5Severity
!-5Probability
1-5Severity
H, M, Lfor HarmPotential
= prob x sevRisk Rating
HAZARD Significant Risk CONTROL MEASURES
(H,M,L)H, M
Col Col Col Col Col Col Col Col
Column 1 Column 2 3 4 5 6 Column 7 8 9 10 11
5
Note: This risk assessment is an integral part of the Method Statement. Any revision to this risk assessment will require revision to the method statement in which it resides. Review and authorisation of this risk
assessment is an integral part of review and authorisation of this method statement. Risk assessments and assessments involving: noise, manual handling, COSHH, expectant and new mothers, display screen
equipment, young persons, PPE, should also be undertaken. For risk assessments involving lead, asbestos and radiological material the Project Manager should be immediately informed on their discovery and
consulted prior to any work taking place. This form can be used for risk assessments by groups which do not form part of a method statement in which case it must be authorised by CSL.