CRONOGRAMA DE IMPLANTAÇÃO

Gerência de Implantação de Projetos Correntes Corredor Sudeste


Adequação do CAIS Secundário TIG
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023 2024 2025
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Jun
Finish Date
Adequação do CAIS Secundário TIG 1.24% 1344.00 05-May-21 07-Jan-25 0.2% 1344.00 05-May-21 A 07-Jan-25 0.00

Engenharia 12.77% 508.00 05-May-21 24-Sep-22 10.64% 508.00 05-May-21 A 24-Sep-22 0.00

Inicial 14.29% 251.00 14-Jun-21 19-Feb-22 0% 216.00 19-Jul-21 A 19-Feb-22 0.00

E1000 TAP 100% 15.00 14-Jun-21 28-Jun-21 0% 150.00 19-Jul-21 A 15-Dec-21 -170.00

E1010 Aprovação da declaração de escopo 100% 15.00 29-Jun-21 13-Jul-21 0% 15.00 16-Dec-21 30-Dec-21 -170.00

E1020 Emissão de solicitação de Autorização de Desenv olvimento de Projeto 0% 1.00 04-Jan-22 04-Jan-22 0% 1.00 04-Jan-22 04-Jan-22 0.00

E1030 Elaboração / Aprovação do Plano de Trabalho 0% 10.00 05-Jan-22 14-Jan-22 0% 10.00 05-Jan-22 14-Jan-22 0.00

E1040 Elaboração / Aprovação da ADP 0% 10.00 15-Jan-22 24-Jan-22 0% 10.00 15-Jan-22 24-Jan-22 0.00

E2000 Topografia 0% 10.00 25-Jan-22 03-Feb-22 0% 10.00 25-Jan-22 03-Feb-22 0.00

E2100 ADP Sondagem 0% 10.00 01-Jan-22 10-Jan-22 0% 10.00 01-Jan-22 10-Jan-22 0.00

E3000 Sondagem 0% 40.00 11-Jan-22 19-Feb-22 0% 40.00 11-Jan-22 19-Feb-22 0.00

Conceitual 100% 0.00 05-May-21 05-May-21 100% 0.00 05-May-21 A 05-May-21 A 0.00

EC1000 Projeto Conceitual - Handover - Engenharia Ana Barbara 100% 0.00 05-May-21 05-May-21 100% 0.00 05-May-21 A 05-May-21 A 0.00

Basico 0% 1.00 01-Dec-21 01-Dec-21 0% 1.00 01-Dec-21 01-Dec-21 0.00

EB1000 Projeto Básico - Handover - Engenharia Ana Barbara 0% 1.00 01-Dec-21 01-Dec-21 0% 1.00 01-Dec-21* 01-Dec-21 0.00

Detalhado 0% 201.00 20-Feb-22 08-Sep-22 0% 201.00 20-Feb-22 08-Sep-22 0.00

ED1000 Projeto detalhado Mecânica (processo, tubulação) 0% 180.00 20-Feb-22 18-Aug-22 0% 180.00 20-Feb-22 18-Aug-22 0.00

ED1010 Projeto detalhado Civil (arquitetura, infraestrutura, metálica) 0% 180.00 20-Feb-22 18-Aug-22 0% 180.00 20-Feb-22 18-Aug-22 0.00

ED1020 Projeto detalhado Elérica (automação, instrumentação, telecom) 0% 180.00 20-Feb-22 18-Aug-22 0% 180.00 20-Feb-22 18-Aug-22 0.00

EP1000 PQ 0% 7.00 19-Aug-22 25-Aug-22 0% 7.00 19-Aug-22 25-Aug-22 0.00

ER1000 Construtibilidade 0% 7.00 26-Aug-22 01-Sep-22 0% 7.00 26-Aug-22 01-Sep-22 0.00

ER1005 Documentação para contratação 0% 5.00 02-Sep-22 06-Sep-22 0% 5.00 02-Sep-22 06-Sep-22 0.00

ER1010 CAPEX 0% 7.00 02-Sep-22 08-Sep-22 0% 7.00 02-Sep-22 08-Sep-22 0.00

Requisição de Compra 0% 16.00 09-Sep-22 24-Sep-22 0% 16.00 09-Sep-22 24-Sep-22 0.00

C0010 Preparação do processo de contratação 0% 7.00 09-Sep-22 15-Sep-22 0% 7.00 09-Sep-22 15-Sep-22 0.00

C0020 Emissão / Aprovação RT Físic a 0% 3.00 16-Sep-22 18-Sep-22 0% 3.00 16-Sep-22 18-Sep-22 0.00

C1000 Emissão / Aprovação RC no S AP 0% 2.00 23-Sep-22 24-Sep-22 0% 2.00 23-Sep-22 24-Sep-22 0.00

Comitê Orçamentário 0% 295.00 02-Dec-21 22-Sep-22 0% 295.00 02-Dec-21 22-Sep-22 0.00

Engenharia 0% 23.00 02-Dec-21 24-Dec-21 0% 23.00 02-Dec-21 24-Dec-21 0.00

CO0010 Cadastro / liberação do projeto na Ferramenta de captura / Criação do PEP 0% 3.00 02-Dec-21 04-Dec-21 0% 3.00 02-Dec-21 04-Dec-21 0.00

CO0020 Submissão da documentação no Sharepoint 0% 5.00 05-Dec-21 09-Dec-21 0% 5.00 05-Dec-21 09-Dec-21 0.00

CO0030 Aprovação da documentação no Sharepoint 0% 9.00 10-Dec-21 18-Dec-21 0% 9.00 10-Dec-21 18-Dec-21 0.00

CO0040 Aprovação do projeto pelo controladoria (email de acordo da Gestão 0% 3.00 19-Dec-21 21-Dec-21 0% 3.00 19-Dec-21 21-Dec-21 0.00
Econômica)
CO1000 Liberação orçamentária / Apro vação no SAP (controladoria) 0% 3.00 22-Dec-21 24-Dec-21 0% 3.00 22-Dec-21 24-Dec-21 0.00

Obra 0% 14.00 09-Sep-22 22-Sep-22 0% 14.00 09-Sep-22 22-Sep-22 0.00

CO1010 Submissão da documentação no Sharepoint 0% 5.00 09-Sep-22 13-Sep-22 0% 5.00 09-Sep-22 13-Sep-22 0.00

CO2000 Aprovação da documentação no Sharepoint / liberação orçamentária 0% 9.00 14-Sep-22 22-Sep-22 0% 9.00 14-Sep-22 22-Sep-22 0.00

Licenciamento 100% 75.00 08-Sep-21 21-Nov-21 0% 159.00 08-Sep-21 A 13-Feb-22 -84.00

Licenciamento ambiental 100% 75.00 08-Sep-21 21-Nov-21 0% 159.00 08-Sep-21 A 13-Feb-22 -84.00

L0010 Elaboração e emissão da RIPLA 100% 7.00 08-Sep-21 14-Sep-21 0% 91.00 08-Sep-21 A 07-Dec-21 -84.00

L0020 Avaliação e retorno da RIPLA 100% 38.00 15-Sep-21 22-Oct-21 0% 38.00 08-Dec-21 14-Jan-22 -84.00

L1000 Licenciamento 100% 30.00 23-Oct-21 21-Nov-21 0% 30.00 15-Jan-22 13-Feb-22 -84.00

Contratação Obras e Serviços 0% 64.00 25-Sep-22 27-Nov-22 0% 64.00 25-Sep-22 27-Nov-22 0.00

Obra 0% 64.00 25-Sep-22 27-Nov-22 0% 64.00 25-Sep-22 27-Nov-22 0.00

Contratação 0% 64.00 25-Sep-22 27-Nov-22 0% 64.00 25-Sep-22 27-Nov-22 0.00

C1010 Visita técnica 0% 7.00 25-Sep-22 01-Oct-22 0% 7.00 25-Sep-22 01-Oct-22 0.00

Primary Baseline Remaining Work Milestone Page 1 of 2 Data Atualização: 01-Dec-21

Actual Work Critical Remaining Work Summary © Primavera Systems, Inc.


CRONOGRAMA DE IMPLANTAÇÃO
Gerência de Implantação de Projetos Correntes Corredor Sudeste
Adequação do CAIS Secundário TIG
Activity ID Activity Name % Prev. Dur. BL In. BL Térm. BL % Real Dur. In. Corr. Térm. Corr. Variance - BL 2018 2019 2020 2021 2022 2023 2024 2025
BL Corr. Project May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Jun
Finish Date
C1020 Esclarecimento técnico / Recebimento de propostas 0% 15.00 02-Oct-22 16-Oct-22 0% 15.00 02-Oct-22 16-Oct-22 0.00

C1030 Análise técnica de propostas e aprovação 0% 15.00 17-Oct-22 31-Oct-22 0% 15.00 17-Oct-22 31-Oct-22 0.00

C1040 Análise comercial / Negociação 0% 20.00 01-Nov-22 20-Nov-22 0% 20.00 01-Nov-22 20-Nov-22 0.00

CT1000 Assinatura do contrato 0% 7.00 21-Nov-22 27-Nov-22 0% 7.00 21-Nov-22 27-Nov-22 0.00

Obras 0% 766.00 03-Dec-22 07-Jan-25 0% 766.00 03-Dec-22 07-Jan-25 0.00

Obra 0% 766.00 03-Dec-22 07-Jan-25 0% 766.00 03-Dec-22 07-Jan-25 0.00

Mobilização 0% 60.00 03-Dec-22 01-Feb-23 0% 60.00 03-Dec-22 01-Feb-23 0.00

O1000 Emissão da OS 0% 0.00 03-Dec-22 0% 0.00 03-Dec-22 0.00

O1110 Mobilização de recursos 0% 30.00 04-Dec-22 02-Jan-23 0% 30.00 04-Dec-22 02-Jan-23 0.00

O1120 Montagem / Aprovaç ão do canteiro final de obras c onforme E PS-519 0% 30.00 03-Jan-23 01-Feb-23 0% 30.00 03-Jan-23 01-Feb-23 0.00

O1200 Apresentação / Apro vação da estratégia de mobiliz ação 0% 7.00 04-Dec-22 10-Dec-22 0% 7.00 04-Dec-22 10-Dec-22 0.00

O1210 Elaboração / Aprovação do Plano de Trabalho da Obra (PTO) 0% 30.00 04-Dec-22 02-Jan-23 0% 30.00 04-Dec-22 02-Jan-23 0.00

Construção 0% 691.00 02-Feb-23 23-Dec-24 0% 691.00 02-Feb-23 23-Dec-24 0.00

O2000 Atividades da OBRA 0% 0.00 02-Feb-23 02-Feb-23 0% 0.00 02-Feb-23 02-Feb-23 0.00

TO1000 Conclusão de todo o escopo 0% 1.00 23-Dec-24 23-Dec-24 0% 1.00 23-Dec-24 23-Dec-24 0.00

Estaca prancha e estacas nova ponte e píer 0% 360.00 02-Feb-23 27-Jan-24 0% 360.00 02-Feb-23 27-Jan-24 0.00

A1000 Preparar local para cravação das estacas (Locação, limpeza e retirada de 0% 120.00 02-Feb-23 01-Jun-23 0% 120.00 02-Feb-23 01-Jun-23 0.00
rochas se necessário)
A1010 Execução do estaqueamento 0% 270.00 03-May-23 27-Jan-24 0% 270.00 03-May-23 27-Jan-24 0.00

Realizar aterro/nivelamento do piso de toda a área 0% 280.00 09-Nov-23 14-Aug-24 0% 280.00 09-Nov-23 14-Aug-24 0.00

A1020 Aterro compactado 0% 120.00 09-Nov-23 07-Mar-24 0% 120.00 09-Nov-23 07-Mar-24 0.00

A1030 Execução de piso de concreto 0% 90.00 28-Jan-24 26-Apr-24 0% 90.00 28-Jan-24 26-Apr-24 0.00

A1070 Execução Urbanização 0% 90.00 17-Apr-24 15-Jul-24 0% 90.00 17-Apr-24 15-Jul-24 0.00

A1080 Execução Elétrica 0% 60.00 16-Jun-24 14-Aug-24 0% 60.00 16-Jun-24 14-Aug-24 0.00

A1090 Execução Mecânica 0% 60.00 16-Jun-24 14-Aug-24 0% 60.00 16-Jun-24 14-Aug-24 0.00

Supraestrutura da nova ponte e novo píer 0% 310.00 17-Feb-24 22-Dec-24 0% 310.00 17-Feb-24 22-Dec-24 0.00

A1040 Execução formas, armação e concretagem dos blocos de coroamento 0% 180.00 17-Feb-24 14-Aug-24 0% 180.00 17-Feb-24 14-Aug-24 0.00

A1050 Construção de passarela em estrutura metálica - nova ponte e novo píer 0% 90.00 16-Jun-24 13-Sep-24 0% 90.00 16-Jun-24 13-Sep-24 0.00

A1060 Adequação de Flutuante 0% 60.00 15-Aug-24 13-Oct-24 0% 60.00 15-Aug-24 13-Oct-24 0.00

A1100 Execução de drenagem 0% 60.00 14-Sep-24 12-Nov-24 0% 60.00 14-Sep-24 12-Nov-24 0.00

A1110 Execução Elétrica 0% 90.00 24-Sep-24 22-Dec-24 0% 90.00 24-Sep-24 22-Dec-24 0.00

A1120 Execução Mecânica 0% 90.00 24-Sep-24 22-Dec-24 0% 90.00 24-Sep-24 22-Dec-24 0.00

Desmobilização 0% 15.00 24-Dec-24 07-Jan-25 0% 15.00 24-Dec-24 07-Jan-25 0.00

O3000 Desmobilização do Canteiro de Obras e de Todos os Recurso 0% 15.00 24-Dec-24 07-Jan-25 0% 15.00 24-Dec-24 07-Jan-25 0.00

Primary Baseline Remaining Work Milestone Page 2 of 2 Data Atualização: 01-Dec-21

Actual Work Critical Remaining Work Summary © Primavera Systems, Inc.