June 22, 2011 Manila, Philippines 6th Asia Clean Energy Forum 2011
History
Hyderabad Milk Requirement 25 Laks /Day. Currently
Established in Nov. 2009. 21 Acre Farm - 2 Acres Dairy.
Current Cost of milk Rs 35-50/Liter and increasing Distribution 3000 ltrs/per day
IECC 2
Activity
Power plant for all electrical needs 30 Kw 4-6
Hrs per day major power cuts in India Milk Processing plant (Paneer, Yogurt, Skim Milk, Ghee) Use heat from wood fired boiler for pasturization C30 Generates electricity Supplements Boiler with hot water. Output 30 65 C saves approximately 50 Kg of wood per day Decrease use of wood convert fully to biogas in 2012 by increasing animals
IECC 3
IECC
IECC
Animal Waste
Pasteurization 85 C
Pasturezation Machine
Digester
300 C output
Elec. 25 kW
Retail
Wholesale
2 kW waste
80% average total efficiency 0.15 lb/MWh NOx & 1,540 lb/MWh CO2
IECC 8
COST COMPARISON
1000 Liters/hr pasteurization plant with a wood fired boiler and Dis Gen set. Wood fired boiler costs $4500 Fuel ($500/mo $6000/Yr). A 30 Kw dis gen. set ($12,000 - it consumes 7 liter/hr $28/day (10,080/yr). Assume the pasteurization plant would operate 3-4 hrs per day.
Over 20 years cost : life span of the diesel generator and wood fired boiler are approximately 7-10 years ($16,500 X 2 = $33,000). (Diesel 20 yrs X $10,080 = $201,600, wood 20 yrs X $6,000 = $120,000). Maintenance is $ 2000/yr = $ 40,000. Total cost is $ $394,600.
The Capstone C30 Micro turbine and digester cost is approximately (Capstone - $61,000, Gas cleaning equip - $10,000, Digester - $15,000,). The C30 - 26 Kw of electricity and exhaust heat is used for pasteurization milk to temperature of 85C.
Over 20 years costs: life span of the Micro turbine is 10 yrs (2 X 61,000 = $ 122,000). Digester life is 30 years ($ 15,000). Maintenance $ 3000/yr = $ 60,000. This total is $ 207,000.
IECC
IECC
10
IECC
11
SUMMARY
Dairy 300 cows - C30 micro turbine 4-6 hours - 45-m3 (1,589-ft3) digester.
Methane 25 times more potent than CO2 and remains in atmosphere upto 15 years. Assume 41 days of operation. Approximately 10,785 m3 of CH4 emitted into
atmosphere - burned to generate electricity and heat. 10,785- m3 will produce approximately 19.4 tonnes of CO2 with a Global Warming Potential (GWP) of 19.
Heat recovery for water inlet temperature of 30C and flow rate of 1.5 l/s to 50-
Capstone/IECC
13