Escolar Documentos
Profissional Documentos
Cultura Documentos
Ashwin Gambhir,
Senior Research Associate, Prayas (Energy Group), India. June 20-21, 2011, Manila
Workshop on Feed-in Tariff Policy
Prayas Energy Group, Pune
FiT is a combination of policy instruments. The FiT rate is only as good as the data and assumptions that go into making it. For a successful RE program, a number of other policy and regulatory enablers need to be in place.
2
Outline
Important parameters while setting FiT
Capital Cost Cost of Capital; financing considerations Capacity Utilization factor (Generation)
Examples
Wind; Bagasse Cogeneration; Solar (PV and CSP)
Other considerations
Retail Tariff Impact on consumers Tariff period & exit rules Other Govt and International subsidies/incentives
Conclusions
1. Information asymmetry
the Commission observed that no developer came up with relevant data as was required and also that developers or their representative associations failed to bring in transparency as mandated under the ERC Act, 1998 in the whole process by refusing to divulge details. Thus the Commission was constrained to proceed without adequate data and financial information. (Mah Wind Order 2003)
Data mainly from developers and industry. Very little independent analysis. No way to judge the appropriateness.
Still commission increased purchase price by 35% Similar Issues in Biomass pricing
5
Gujarat Alkalies and Chemicals Ltd Chennai Port Trust Rajasthan State Mines & Minerals Ltd ONGC Gujarat Bharat Electronics Ltd, Karnataka
45% variation
FiTs & capacity based incentives like accelerated depreciation coupled with vertical integration (especially in the wind sector) discourages competition and cost reduction.
6
Solar
CERC FiT with 13.25% interest rate and 15.88% discount rate (Rs/kWh) 15.39 15.04
With lower interest (6%) and discount rates (6.6%) 12.98 12.34
Price drop
ROE 10%
Price drop
PV CSP
16% 18%
10.11 9.6
34% 36%
The CERC discount rate of appraising thermal power projects is 10.19%, used only for comparison. However in RE, levelized tariffs for actual payments.
7
10
Example: Section 1.4.2, MH Wind Tariff Order, 2003: Commission notes that in Cost Plus Approach, rate per unit charged by such projects during initial period of 10 years is bound to be higher as during this period the project has various debt related obligations. However, it is essential that the consumer is able to enjoy the benefit of cheaper power once all debt related obligations are paid off and project has virtually no variable costs.
12
PV Tariffs in Rs/kWh
Rs 12.76 / kWh
Rs 10.95 / kWh
PV Capacity in MW
13
16 14 12 10 8 6 0 100 200
Rs 12.24/kWh
Rs 10.49/kWh
300
400
500
CST capacity in MW
14
Conclusions
Need to consider developing country political economy context and national - sectoral priorities. (Utility financial health, shortages,
universal access, paying ability, tariff impacts, caps for high cost solar)
Balancing project viability and windfall profits is a science and art. Regulator needs to do this tight rope walk. Need effective institutional structures (to compile and analyze data) coupled with independent analyses to take into account latest technological and cost trends to try and ensure a level playing field across technologies and investors.
15
THANK YOU
ashwin [at] prayaspune [.] org Prayas Energy Group www.prayaspune.org/peg
16