Você está na página 1de 11

Version 11.

Module 13
Isometric Production

Training Manual

PLEASE NOTE: AVEVA has a policy of continuing product development: therefore, the information contained in this document may be subject to change without notice. AVEVA MAKES NO WARRANTY OF ANY KIND WITH REGARD TO THIS DOCUMENT, INCLUDING BUT NOT LIMITED TO, THE IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE. While every effort has been made to verify the accuracy of this document, AVEVA shall not be liable for errors contained herein or direct, indirect, special, incidental or consequential damages in connection with the furnishing, performance or use of this material.

This manual provides documentation relating to products that you may not have access to or which may not be licensed to you. For further information on which products are licensed to you please refer to your licence conditions.

Copyright 2003 AVEVA Limited

All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without prior written permission of AVEVA.

The software programs described in this document are confidential information and proprietary products of AVEVA Ltd or its licensors.
Visit our website at http://www.aveva.com

AVEVA Ltd, High Cross, Madingley Road, Cambridge CB3 0HB, UK

Contents
Session

1 ..................................................................... 1-1

Isometric Production ............................................................................................ 1-1 Objectives ............................................................................................................... 1-1 Must Know Points ................................................................................................... 1-1 Isometric Production ............................................................................................... 1-2 Accessing Isodraft................................................................................................... 1-2 CE........................................................................................................................... 1-5 Detail....................................................................................................................... 1-5 Produce .................................................................................................................. 1-5 Option files .............................................................................................................. 1-6 Exercise 1 ............................................................................................................... 1-7

Module 13 Isometric Production

Contents-i

Session
Isometric Production
Objectives

From the pipe routes produced in design we can produce fabrication, erection, system and trim isometrics. Isodraft, the Isometric drawing production module uses a series of Option Files to produce these differing isometrics. At the end of this session you will be able to: Produce a simple Isometric from standard option files.

Must Know Points


It is important to understand the following points about Isometric Production The principles relating to Isometric Option Files.

Module 13 Isometric Production

1-1

Isometric Production

Isometric Production
Detail Isometric production is the subject other courses, however, since a requirement of all piping designers is the production of check or stress isometrics, the basic techniques of what is a simple operation are covered here.

Accessing Isodraft
Before you can produce an isometric, you must ensure that pipe(s) or branch(es) have been check through the Datacon utility. The isometric will fail if components have lost their Spref (specification reference), are poorly aligned or overlap. A visual check, ensuring that no dashed line appears is not sufficient. From design, you can access Isodraft using Design>modules>Isodraft> macro files.

Once in the Isodraft module, you will be presented with a members list, showing the contents of the Design DB and a graphical view, similar to that in Design.

1-2

Module 13 Isometric Production

Isometric Production

Default Isodraft forms

Isodraft has a number of options to control the appearance, content and type of isometric. 2 alternatives are supplied each with an option to produce metric or imperial output data, thus giving 4 option files altogether. Before accessing 1 of these option files, using the members form, navigate to a suitable pipe or branch as you would in Design. From the top menu bar on the viewing form, select Isometric>Standard

Module 13 Isometric Production

1-3

Isometric Production

The current element is that of the pipe in the hierarchy. The 4 option files are listed and BASIC.MET has been selected. Clicking the Apply button will generate an isometric in the graphical viewing area.

1-4

Module 13 Isometric Production

Isometric Production

CE
The member in the hierarchy becomes the current element. Navigating to another pipe or branch and then clicking the CE button will update the form and re-clicking apply will generate an isometric of the new pipe or branch

Detail
This can be changed to Detail List and several pipes or branches can be selected and multiple isometrics generated.

Produce
This can be changed to generate: Transfer files Batch macro Used to interface with other systems. Useful when large quantities of isometrics are required. Any such macro is usually run overnight. Bolts are only generated in Isodraft, so this function generate a report of bolts for pipes and branches identified in the detail list.

Bolt Report

The ADVANCED options will not work on the pipes you have created, since it requires part-numbers to be generated in the Design DB. This option is used in conjunction with the Spooler module of PDMS.

Module 13 Isometric Production

1-5

Isometric Production

Default Isometric

Option files
Within differing companies and the projects they undertake, there will be specific isometric requirements. Backing sheet details, dimensioning, material list contents etc.. It is the responsibility on the project administrator to create the option files required and inform designers of there significance.

1-6

Module 13 Isometric Production

Isometric Production

Exercise 1
Try producing isometrics of the pipes you have designed. Ensure you have Datacon checked them and amended any significant errors before running Isodraft.