Você está na página 1de 3

**PRINTED COPIES MAY NOT BE CURRENT. CHECK DOCUMENT CONTROL FOR CURRENT REVISION LEVEL.

**

Digital Angel Corporation


490 Villaume Avenue South St. Paul, MN 55075

DCO #

FORM

Page 1 of 3
Rev. Level

Effective Date Document Number

SPIN WELD PROCESS TRAVELER


100,000 DESCRIPTION:
E-TAG, WLD, R/W, SUBASM, CATTLE, TEW, YELLOW

New RED-LINED
LOT NUMBER: SHOP ORDER: 50031709 06/12/2009

CONFIDENTIAL: THIS DOCUMENT AND ALL INFORMATION CONTAINED HEREIN IS PROPRIETARY TO DIGITAL ANGEL AND IS NOT TO BE DISCLOSED WITHOUT THE EXPRESS WRITTEN PERMISSION OF DIGITAL ANGEL.

ORDER QUANTITY: P/N: 727300802

Procedure 1 Pull Material


QUANTITY RELEASE:

Color Description:
Material Used: Part Number:
474210002 726300802

Material Pulled By:________________


Lot Number: Qty
100,000 100,000

Date: ________
Qty Total Qty

Lot Number

Qty

Lot Number

Cover Cup with Coil assembly Combo-Panel

Procedure 2 Spin welder Set Up (#1 & 4)


Equipment Verification
(Circle One)

Sheep Goat air pressure- 40-45 lbs. X Gen 2 with washer- 45-50 lbs. Gen 2 without washer- 45-50 lbs. Combo-Tag- 50 55 lbs. Spin Weld Integrity ( Pass on 3) QC Startup Disposition
(Accept/Reject)

Setup Operator Initials:_______


Oper. Date

Welder No.

Air Pressure

Read Distance
(50units)

Leak Read Range Failures


(Acc < 3)

Oper. initial

Date: ________ QC Initial/Date

Procedure 3 - Label / Packaging


Label / Packaging / Inventory Request
Qty count per carton: 700/ BOX Material Used: Performed By: Yee Yang Lot Number: Date: 12/11/08 Qty:

Part Number:

Label Carton

N/A Recycling Box

143 143

Procedure 4 - In-process Spin weld Inspection Report

**PRINTED COPIES MAY NOT BE CURRENT. CHECK DOCUMENT CONTROL FOR CURRENT REVISION LEVEL.**

Digital Angel Corporation


490 Villaume Avenue South St. Paul, MN 55075

DCO #

FORM

Page 2 of 3
Rev. Level

Effective Date Document Number

SPIN WELD PROCESS TRAVELER


100,000 DESCRIPTION:
E-TAG, WLD, R/W, SUBASM, CATTLE, TEW, YELLOW

New RED-LINED
LOT NUMBER: SHOP ORDER: 50031709 06/12/2009

CONFIDENTIAL: THIS DOCUMENT AND ALL INFORMATION CONTAINED HEREIN IS PROPRIETARY TO DIGITAL ANGEL AND IS NOT TO BE DISCLOSED WITHOUT THE EXPRESS WRITTEN PERMISSION OF DIGITAL ANGEL.

ORDER QUANTITY: P/N: 727300802

Inspection Report
Sample Date/ Time

Initiated By:___________
Comments QTY
Acc/Rej

Date: ________
QC Initials QTY
Acc/Rej

Inspection Characteristic: Visual


Bond Integrity QC Initials

Inspection Characteristic:
Date/ Time

Visual

Bond Integrity

List or reference any process deviations and/or the number of any nonconforming products made during the manufacturing process. By:____________________________ Process Dev # _____________________ NMR #_____________________________ Comments: 1. 2. 3. 4. 5.

Procedure 5: Product Removed/Rejected in Process


In Process QC
Time Qty Date Signature

Start Date:
Carton

End Date:

Parameters/Comments

**PRINTED COPIES MAY NOT BE CURRENT. CHECK DOCUMENT CONTROL FOR CURRENT REVISION LEVEL.**

Digital Angel Corporation


490 Villaume Avenue South St. Paul, MN 55075

DCO #

FORM

Page 3 of 3
Rev. Level

Effective Date Document Number

SPIN WELD PROCESS TRAVELER


100,000 DESCRIPTION:
E-TAG, WLD, R/W, SUBASM, CATTLE, TEW, YELLOW

New RED-LINED
LOT NUMBER: SHOP ORDER: 50031709 06/12/2009

CONFIDENTIAL: THIS DOCUMENT AND ALL INFORMATION CONTAINED HEREIN IS PROPRIETARY TO DIGITAL ANGEL AND IS NOT TO BE DISCLOSED WITHOUT THE EXPRESS WRITTEN PERMISSION OF DIGITAL ANGEL.

ORDER QUANTITY: P/N: 727300802

Attach additional page as necessary and indicate page nos.___________ Quantity Released:__________ QA Released by: _____________________ Date:________________ Inventory Control Review: ____________________ Date: _______________ Traveler Review by:____________________ Date:______________ Transfer this record with the attached shop order to QA for QA release to inventory. QA transfer traveler to front office buyer for inventory control and filing.