Você está na página 1de 363

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge Works This

Software runs on Microsoft Excel INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable SUMMARY - In this sheet summary of all the rates analysized is presented ANALYSIS- The analysis has been presented in 16 nos. of spread sheets Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS Worksheet- 2 : CHAPTER-2 SITE CLEARANCE Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND SHOULDERS Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS) Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES Worksheet- 9 : CHAPTER-9 PIPE CULVERTS Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS Worksheet- 11 : CHAPTER-11 HORTICULTURE Worksheet- 12 : CHAPTER-12 FOUNDATIONS Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION

(A) Usage Rates of Plant and Machinery


Sl. No.
P&M-001 P&M-002 P&M-003 P&M-004 P&M-005 P&M-006 P&M-007 P&M-008 P&M-009 P&M-010 P&M-011 P&M-012 P&M-013 P&M-014 P&M-015 P&M-016 P&M-017 P&M-018 P&M-019 P&M-020 P&M-021 P&M-022 P&M-023 P&M-024 P&M-025 P&M-026 P&M-027 P&M-028 P&M-029 P&M-030 P&M-031 P&M-032 P&M-033 P&M-034 P&M-035 P&M-036 P&M-037 P&M-038 P&M-039 P&M-040 P&M-041 P&M-042 P&M-043 P&M-044 P&M-045 P&M-046 P&M-047 P&M-048

Description of Machine
Air Compressor

Activity
General Purpose

Output of Machine
capacity in cfm cum/hour cum/hour sqm/hour capacity in litre cum / hour cum / hour capacity in cum cum/hour cum/hour

Output
170/250 20 13 1750 1500 20 33 / 22 1 2.5 7.5

Unit
hour hour hour hour hour hour hour hour hour hour hour hour hour

Rate
285 1526 1272 819 141 2035 165 10 165 165 825 550 230 2400 input 600 1042 874 input 737 19966 15294 13846 13506 1700 1942 6149 12936 200 44 230 2254 780 2182 945 3878 892 3228 644 91 input input 72 470 1035 38.2 3.8 497

Batching and Mixing Plant (a) 30 cum Concrete Mixing capacity Batching and Mixing Plant (b) 15 - 20 Concrete Mixing cum capacity Bitumen Pressure Distributor Bitumen Boiler oil fired Concrete Paver Finisher with 40 HP Motor Concrete Pump of 45 & 30 cum capacity Concrete Bucket Concrete Mixer (a) 0.4/0.28 cum Concrete Mixer (b) 1 cum Crane (a) 80 tonnes Cranes b) 35 tonnes Cranes c) 3 tonnes Dozer D - 80 - A 12 Dozer D - 50 - A 15 Emulsion Pressure Distributor Front End loader 1 cum bucket capacity Generator (a) 125 KVA Generator( b) 63 KVA GSB Plant 50 cum Hotmix Plant - 120 TPH capacity Hotmix Plant - 100 TPH capacity Hotmix Plant - 60 to 90 TPH capacity Hotmix Plant - 40 to 60 TPH capacity Hydraulic Chip Spreader Applying bitumen tack coat Bitumen Spraying Paving of concrete surface Pumping of concrete For Pouring concrete Concrete Mixing Concrete Mixing Lifting Purpose Lifting Purpose Lifting Purpose Spreading /Cutting / Clearing Spreading /Cutting / Clearing Applying emulsion tack coat Soil loading / Aggregate loading Genration of electric Energy Genration of electric Energy Producing GSB DBM/BM/SDC/ Premix DBM/BM/SDC/ Premix DBM/BM/SDC/ Premix DBM/BM/SDC/ Premix Surface Dressing

cum/hour cum/hour sqm/hour cum/hour KVA KVA cum/hour cum/hour cum/hour cum/hour cum/hour sqm/hour cum/hour TPH TPH Rm/hour capacity in tonne sqm/hour cum/hour sqm/hour cum/hour cum/hour Rm/hour cum/hour cum/hour cum/hour

300/ 150/250 200/ 120/150 1750 60 /25 100 50 40 40 30 25 17 1500 60 /60 /60 100 200 80 1 1250 200/200/50/50 2700 40 40/30 2 to 3 25 1.5 to 2.00 4

hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour

Soil Ordinary/Soil Marshy / Soil Hydraulic Excavator of 1 cum bucket Unsuitable Integrated Stone Crusher 100THP Integrated Stone Crusher 200 HP Kerb Casting Machine Mastic Cooker Mechanical Broom Hydraulic Motor Grader 3.35 mtr blade Mobile slurry seal equipment Crushing of Spalls Crushing of Spalls Kerb Making Mastic Wearing coat Surface Cleaning Clearing /Spreading /GSB /WBM Mixing and laying slurry seal

Paver Finisher Hydrostatic with sensor Paving of DBM/ BM/SDC/ control 100 TPH Premix Paver Finisher Mechanical 100 TPH Piling Rig with Bantonite Pump Pneumatic Road Roller Pneumatic Sinking Plant Pot Hole Repair Machine Paving of WMM /Paving of DLC 0.75 m dia to 1.2 m dia Boring attachment Rolling of Asphalt Surface Pneumatic Sinking of wells Repair of potholes

Prestressing Jack with Pump & access Stressing of steel wires/stands Ripper Rotavator Road marking machine Smooth Wheeled Roller 8 tonne Tandem Road Roller Tipper - 5 cum Tipper - 5 cum Tipper - 5 cum Scarifying Scarifying Road marking Soil Compaction /BM Compaction Rolling of Aspalt Surface Transportation of soil, GSB, WMM, Hotmix etc. Transportation of soil, GSB, WMM, Hotmix etc. Transportation of soil, GSB, WMM, Hotmix etc. cum/hour cum/hour Sqm/hour cum/hour cum/hour Capacity in cum Capacity in cum Capacity in cum 60 25 100 70/25 30 5.5 5.5 5.5

hour hour hour hour hour km tonne.km hour

Page 1 of 363

P&M-049 P&M-050 P&M-051 P&M-052 P&M-053 P&M-054 P&M-055 P&M-056 P&M-057 P&M-058 P&M-059 P&M-060 P&M-061 P&M-062

Transit Mixer 4.0/4.5 cum Transit Mixer 4/4.5 cum Transit Mixer 3.0 cum Transit Mixer 3.0 cum Tractor Tractor with Rotevator Tractor with Ripper Truck 5.5 cum per 10 tonnes Truck 5.5 cum per 10 tonnes Truck 5.5 cum per 10 tonnes Vibratory Roller 8 tonne Water Tanker Water Tanker Wet Mix Plant 60 TPH

Transportation of Concrete Mix to site Transportation of Concrete Mix to site Transportation of Concrete Mix to site Transportation of Concrete Mix to site Pulling Rate of Tractor + Rotevator Rate of Tractor 6+ Ripper Material Transport Material Transport Material Transport Earth or soil / GSB / WBM Water Transport Water Transport Wet Mix

cum/hour cum/hour cum/hour cum/hour capacity in HP

4.5 4.5 3 3 50

hour tonne.km input hour input

890

tonne.km input hour hour hour 300 300 300 38 497 4 1339 300 23.1 1002

capacity/cum capacity/cum capacity/cum cum/hour capacity in KL capacity in KL cum/hour

4.5 4.5 4.5 100/60/60 6 6 25

km hour tonne.km hour hour km hour

Sl. No.
P&M-063 P&M-064 P&M-065 P&M-066 P&M-067 P&M-068 P&M-069 P&M-070 P&M-071 P&M-072 P&M-073 P&M-074 P&M-075 P&M-076 P&M-077 P&M-078 P&M-079 P&M-080 P&M-081 P&M-082 P&M-083 P&M-084 P&M-085 P&M-086 P&M-087 P&M-088 P&M-089 P&M-090 P&M-091 P&M-092 P&M-093 P&M-094

Description of Machine
Air compressor with pneumatic chisel attachment for cutting hard clay. Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour Belt conveyor system Boat to carry atleast 20 persons Cement concrete batch mix plant @ 175 cum per hour (effective output) Cement concrete batch mix plant @ 75 cum per hour Cold milling machine @ 20 cum per hour Crane 5 tonne capacity Crane 10 tonne capacity Crane 15 tonne capacity Crane 20 tonne capacity Crane 40 T capacity Crane with grab 0.75 cum capacity Compressor with guniting equipment along with accessories Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. Epoxy Injection gun Generator 33 KVA Generator 100 KVA Generator 250 KVA Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. Joint Cutting Machine with 2-3 blades (for rigid pavement) Jack for Lifting 40 tonne lifting capacity. Piling rig Including double acting pile driving hammer (Hydraulic rig) Plate compactor Snow blower equipment 140 HP @ 600 cum per hour Texturing machine (for rigid pavement) Truck Trailor 30 tonne capacity Truck Trailor 30 tonne capacity Tunnel Boring machine Vibrating Pile driving hammer complete with power unit and accessories. Wet Mix Plant 100 TPH Wet Mix Plant 75 TPH

Unit
hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour hour day hrs hour hour hour hour t.km hour hour hour

Rate
600 input input input input input input input input input input input 4000 input input input 540 793 1336 input input input input 30 input input input input input input input input

Page 2 of 363

(B) Labour
Sl. No.
L-01 L-02 L-03 L-04 L-05 L-06 L-07 L-08 L-09 L-10 L-11 L-12 L-13 L-14 L-15 L-16 L-17 L-18 L-19

Description of Labour
Blacksmith (IInd class) Blacksmith (Ist class)/ Welder/ Plumber/ Electrician Blaster (Stone cutter) Carpenter I Class Chiseller (Head Mazdoor) Driller (Jumper) Diver Fitter Mali Mason (IInd class) Mason (Ist class) Mate / Supervisor Mazdoor Mazdoor/Dresser (Semi Skilled) Mazdoor/Dresser/Sinker (Skilled) Medical Officer Operator(grouting) Painter I class Para medical personnel

Unit
day day day day day day day day day day day day day day day day day day day input input

Rate
180 250 250 250 250 250 350 250 116 180 250 350 180 180 250

250 250

(C) Materials
Sl. No.
M-001 M-002 M-003 M-004 M-005 M-006 M-007 M-008 M-009 M-010 M-011 M-012

Description
Stone Boulder of size 150 mm and below at Cruser Plant Supply of quarried stone 150 - 200 mm size for Hand Broken at site Boulder with minimum size of 300 mm for Pitching at Site Coarse sand at Mixing Plant Coarse sand at Site Fine sand at Site Moorum at Site Gravel/Quarry spall at Site Granular Material or hard murrum for GSB works at Site Granular Material or hard murrum for GSB works at Mixing Plant Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Page 3 of 363

Unit
cum cum cum cum cum cum cum Cum Cum Cum Cum Cum input input input input input input input input input input input input

Rate

Description

Unit

Rate at Plant Rate at Site (HMP/Batc hing)

Sr No 1.1

Ref. to MoRTH Spec.

Description

Unit

Remark QuantityRate Rs Cost Rs s/ Input ref.

1.4

1.4(I)

Loading and unloading of stone boulder / stone aggregates / sand / kanker tipper at loading point, loading with Placing / moorum. front end loader, dumping, turning for return trip, excluding time for haulage and return trip Unit : cum Taking output = 5.5 cum Time required for i) Positioning of tipper at loading point ii) Loading by front end loader 1 cum bucket capacity @ 25 cum per hour iii) Maneuvering, reversing, dumping and turning for return iv) Waiting time, unforeseen Total a) Machinery Tipper 5.5 tonnes capacity Front end-loader 1 cum bucket capacity @ 25 cum/hour b) Overheads @ 2.244% on (a) c) Contractors profit @ 5% on (a+b) Cost for 5.5 cum = a+b+c Rate per cum = (a+b+c)/ 5.5 Note Unloading will be by tipping. Cost of Haulage Excluding Loading and Unloading Haulage of materials by tipper excluding cost of loading, unloading and stacking. Unit : t.km Taking output 10 tonnes load and lead 10 km = 100 t.km Case I Surfaced Road Speed with load : 25 km / hour. Speed while Returning empty : 35 km / a) Machinery. i) Tipper 10 tonne capacity Time taken for onward haulage with Time taken for empty return trip. b) Overheads @ 2.244% on (a) c) Contractors profit @ 5% on (a+b) cost for 100 t km = a+b+c Rate per t.km = (a+b+c)/100

1 Min 13 Min 2 Min 4 Min 20 Min hour hour 0.330 497.00 0.330 1042.00 164.01 343.86 11.40 25.96 545.23 99.13 99.00 P&MP&M017

say

hour hour

0.400 0.290

497.00 497.00

say 1.4(II) Case II Unsurfaced Gravelled Road Speed with load : 20 km / hour Speed for empty return trip : 30 km / hour a)Machinery Tipper 10 tonnes capacity Time taken for onward hanlage with Time taken for empty return trip b) Overheads @ 2.244% on (a) c) Contractors profit @ 5% on (a+b)

198.80 144.13 7.70 17.53 368.16 3.68 3.70

P&MP&M-

hour hour

0.500 0.330

497.00 497.00

248.50 164.01 9.26 21.09

P&MP&M-

Page 4 of 363

Cost for 100 t .km = a+b+c Rate per t.Km = (a+b+c)/100 say 1.4(III) Case III Katcha Track and Track in river bed / nallah bed and choe bed. Speed with load : 10 km / hour Speed while returning empty : 15 km / a) Machinery I) Tipper 10 tonnes capacity Time taken for onward haulage Time taken for empty return trip b) Overheads @ 2.244% on (a) c) Contractors profit @ 5% on (a+b) Cost for 100 t .km = a+b+c Rate per t.Km = (a+b+c)/100 1.5 Hand Broken Stone Aggregates 63 mm nominal size Supply of quarried stone, hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50 mm sieve) cum stacking as directed and Unit : Taking output = 1 cum a) Labour Mate Mazdoor b) Material cum 1.100 input Supply of quarried stone 150 - 200 mm c) size Overheads @ 2.244% on (a+b) d) Contractors profit @ 5% on (a+b+c) cum = a+b+c+d Rate per say 1.6 Crushing of stone aggregates 13.2 mm nominal size. Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone : cum Unit aggregates of 13 mm nominal size. Taking Output = 600 cum at crusher a) Labour Mate Mazdoor Skilled Mazdoor including breaking of any b) Material Stone Boulder of size 150 mm and c) Machinery Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens loader 1 cum bucket capacity Front end Tipper 5.5 cum capacity d) Overheads @ 2.244% on (a+b+c) day day 0.060 1.500 350.00 180.00

442.86 4.43 4.40

hour hour

1.000 0.670

497.00 497.00

say

497.00 332.99 18.62 42.43 891.05 8.91 8.90

P&MP&M-

21.00 270.00

L-12 L-13

#VALUE! M-002 #VALUE! #VALUE! #VALUE! #VALUE!

day day day cum Hour Hour Hour

0.760 2.000 17.000

350.00 180.00 180.00

266.00 360.00 3060.00

L-12 L-14 L-13

800.000 input 6.000

#VALUE! M-001 P&M028 P&MP&M-

### 77616.00

20.000 1042.00 20840.00 20.000 497.00 9940.00 #VALUE!

Page 5 of 363

e) Contractors profit @ 5% on Cost for 600 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)*0.95/600 say Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm. 2. 95% of above cost will be attributed to the production of 600 cum of stone chips of 13.2 mm size and balance 5% to the production of stone dust which comes out as The integrated stone crusher includes 3. a by-product. primary and secondary crushing units. 1.7 Crushing of stone aggregates 20 mm Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 20 mm nominal size. Unit : cum Taking Output = 670 cum at crusher a) Labour Mate Mazdoor Skilled Mazdoor including breaking of any size b) Material Stone Boulder of size 150 mm and c) Machinery Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens loader 1 cum bucket capacity Front end Tipper 5.5 cum capacity d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on Cost for 670 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)*0.90/670

#VALUE! #VALUE! #VALUE! #VALUE!

day day day cum Hour Hour Hour

0.760 2.000 17.000

350.00 180.00 180.00

266.00 360.00 3060.00

L-12 L-14 L-13

800.000 input 6.000

#VALUE! M-001 P&M028 P&MP&M-

### 77616.00

20.000 1042.00 20840.00 20.000 497.00 9940.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note

1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 20 and 40 90% of above cost will be attributed to 2. mm. the production of 670 cum of stone aggregates of 20mm size and balance 10% will be for smaller size aggregates and stone dust which stone crusher includes 3. The integrated comes out as a byprimary and secondary crushing units.

1.8

Crushing of stone aggregates 40 mm Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 40 mm nominal size. Unit : cum Taking Output = 750 cum at crusher a) Labour

Page 6 of 363

Mate Mazdoor Skilled Mazdoor b) Material Stone Boulder of size 150 mm and c) Machinery Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens loader 1 cum bucket capacity Front end Tipper 5.5 cum capacity d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on Cost for 750 cum = (a+b+c+d+e)x0.85 Rate per cum = (a+b+c+d+e)x0.85/750 Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm. 2. 85% of above cost will be attributed to the production of 750 cum of stone aggregates of 40mm size and balance 15% will be for smaller size aggregates and stone dust which stone crusher includes 3. The integrated comes out as a byprimary and secondary crushing units. Surface Dressing Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller Unit = sqm Taking output = 9000 sqm Case -1:-19 mm nominal chipping size a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Hydraulic self propelled chip spreader @ 1500 sqm per hour Tipper 10 tonne capacity for carriage of stone chips from stockpile on road side to chip spreader Front end loader 1 cum bucket capacity Bitumen pressure distributor Smooth wheeled roller 8-10 tonne c) weight Material Bitumen@ 1.20 kg per sqm Crushed stone chipping,19 mm nominal size @ 0.015 cum per sqm d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d)

day day day cum Hour Hour Hour

0.760 2.000 17.000

350.00 180.00 180.00

266.00 360.00 3060.00

L-12 L-14 L-13

800.000 input 6.000

#VALUE! M-001 P&M028 P&MP&M-

### 77616.00

20.000 1042.00 20840.00 20.000 497.00 9940.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.9

510

day day day hour hour hour hour hour hour hour

0.440 9.000 2.000 7.200 7.200

350.00 180.00 250.00 230.00 285.00

154.00 1620.00 500.00 1656.00 2052.00

L-12 L-13 L-15 P&M031 P&M001 P&M025 P&M048 P&M017 P&M004 P&M044

6.000 1700.00 10200.00 6.000 497.00 2982.00 6252.00 4914.00 2820.00

6.000 1042.00 6.000 6.000 819.00 470.00 ###

tonne 10.800

### M-074 #VALUE! M-053 #VALUE! #VALUE!

cum 135.000 input

Page 7 of 363

Cost for 9000 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/9000 say Case - II13 mm nominal size chipping a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Hydraulic self propelled chip spreader @ 1500 sqm per hour Tipper 10 tonne capacity for carriage of stone chips from stockpile on road side to chip spreader Front end loader 1 cum bucket capacity Bitumen pressure distributor @ 1750 sqm per hour 8-10 tonne weight Vibratory roller c) Material Bitumen@ 1.00 kg per sqm Crushed stone chipping,13 mm nominal size @ 0.01 cum per sqm d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 9000 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/9000 say Note 1.Where the proposed aggregate fails to pass the stripping test, an approved adhesion agent may be added to the binder as per clause 510.2.4. Alternatively, chips may be for the second coat, 2.Input pre-coated as per clause 510.2.5 where required, will be the same as per the Ist coat mentioned above Slurry Seal tonne 9.000 ### cum 90.000 input hour hour hour hour hour hour hour 7.200 7.200 230.00 285.00 day day day 0.440 9.000 2.000 350.00 180.00 250.00

#VALUE! #VALUE! #VALUE!

154.00 1620.00 500.00 1656.00 2052.00

L-12 L-13 L-15 P&M031 P&M001 P&M025 P&M048 P&M017 P&M004 P&M059

6.000 1700.00 10200.00 6.000 497.00 2982.00 6252.00 4914.00 8034.00

6.000 1042.00 6.000 819.00 6.000 1339.00

### M-074 #VALUE! M-052 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

5.15

516

Providing andlaying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and Case I 5 mm thickness Unit = sqm Taking output = 16000 sqm (80 cum) Taking density of 2.2 tonnes per cum, weight of mix = 264 tonnes weight of mix = 176 tonnes a) Labour Mate Mazdoor b) Machinery day day 0.240 6.000 350.00 180.00 84.00 1080.00 L-12 L-13

Page 8 of 363

Mechanical broom Air compressor 250 cfm Mobile slurry seal equipment Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment,bitumen emulsion and filler. tyred roller with individual Pneumatic wheel load not exceeding 1.5 tonnes Water tanker6 KL capacity c) Material Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 Fine aggregate 4.75 mm and below 87 % of total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,= 153.12/1.5 = 102.08 cum total mix = 80 x 2.2 x Filler @ 2 % of 0.02 of water Cost d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 16000 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/16000

hour hour hour hour hour

6.000 6.000 6.000 6.000

230.00 285.00 780.00 497.00

1380.00 1710.00 4680.00 6252.00 2982.00

P&M031 P&M001 P&M033 P&M017 P&M048 P&M037 P&M060

6.000 1042.00

hour hour

6.000 2.000

892.00 300.00

5352.00 600.00

tonne 19.360 input cum 102.080 input

#VALUE! M-077 #VALUE! M-005

tonne

3.520

118.00

415.36 #VALUE! #VALUE! #VALUE! #VALUE!

M-188

KL 12.000 input

#VALUE! M-189

say Case II 3 mm thickness Unit = sqm Taking output = 20000 sqm (60 cum) a) Labour Mate Mazdoor b) Machinery Mechanical broom Air compressor 250 cfm Mobile slurry seal equipment Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment,bitumen emulsion and filler Water tanker6 KL capacity c) Material Residual Binder @ 13 % of mix = 60 x 2.2 xaggregate 3 mm and below 85 % Fine 0.13 of total mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking total mix =60x 2.2 x Filler @ 2 % of density 1.5, 0.02 of water Cost d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 30000 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/20000 say tonne 17.160 input cum 74.800 input tonne 2.640 118.00 hour hour hour hour hour 6.000 6.000 6.000 6.000 230.00 285.00 780.00 497.00 day day 0.200 5.000 350.00 180.00

#VALUE!

70.00 900.00 1380.00 1710.00 4680.00 6252.00 2982.00

L-12 L-13 P&M031 P&M001 P&M033 P&M017 P&M048 P&M060

6.000 1042.00

hour

2.000

300.00

600.00

#VALUE! M-077 #VALUE! M-005 311.52 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! M-188

KL 12.000 input

#VALUE! M-189

Page 9 of 363

Case III 1.5 mm thickness Unit = sqm Taking output = 24000 sqm (36 cum) a) Labour Mate Mazdoor b) Machinery Mechanical broom Air compressor 250 cfm Mobile slurry seal equipment Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment,bitumen emulsion and filler. Water tanker6 KL capacity c) Material Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 Fine aggregate 2.36 mm and below,82 % of total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5 Filler @ 2 % of total mix = 36x 2.2 x 0.02 of water Cost d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 24000 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/24000 say Note 1.Tack coat, if required to be provided, before laying slurry seal may be measured and paid separately Fog Spray Providing and applying low viscosity bitumen emulsion for sealing cracks less than 3 mm wide or incipient fretting or disintegration in an existing bituminous Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Bitumen emulsion pressure distributor @ 1750 sqm per hour c) Material Bitumenemulsion @ 0.75 kg per sqm d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) hour hour tonne 6.000 6.000 6.000 230.00 285.00 819.00 1380.00 1710.00 4914.00 P&M031 P&M001 P&M004 day day 0.120 3.000 350.00 180.00 42.00 540.00 L-12 L-13 tonne 12.670 input cum 43.300 input hour hour hour hour hour 6.000 6.000 6.000 6.000 230.00 285.00 780.00 497.00 1380.00 1710.00 4680.00 6252.00 2982.00 P&M031 P&M001 P&M033 P&M017 P&M048 P&M060 day day 0.200 5.000 350.00 180.00 70.00 900.00 L-12 L-13

6.000 1042.00

hour

2.000

300.00

600.00

#VALUE! M-077 #VALUE! M-022

tonne

1.580

118.00

186.44 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

M-188

KL 12.000 input

#VALUE! M-189

5.17

518

tonne

7.880 input

#VALUE! M-077 #VALUE! #VALUE!

Page 10 of 363

Cost for 10500 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500 say 1.In case it is decided by the engineer to blind the fog spray, the following may be added a) Labour Mate Mazdoor for precoating of grit c) Material Crushed stone grit 3 mm size @ 3.75 kg per sqm Bitumenemulsion for precoating grit @ 2 % of grit,39.38 x 0.02 cum 26.250 input tonne 0.790 input day day 0.160 4.000 350.00 180.00

#VALUE! #VALUE! #VALUE!

56.00 720.00

L-12 L-13

#VALUE! M-024 #VALUE! M-077 #VALUE! #VALUE!

say 5.21 522 Crack Prevention Courses

#VALUE!

Case - I Stress Absorbing Membrane (SAM) crack width less than 6 mm Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Bitumen pressure distributor @ 1750 sqm per hour spreader Hydraulic Chip Smooth wheeled road roller 8-10 tonne c) Material Modified binder Crushed stone aggregates 5.6 mm size d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 10500 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500 say tonne 9.450 input cum 105.000 input hour hour hour hour hour 6.000 6.000 6.000 6.000 230.00 285.00 819.00 470.00 1380.00 1710.00 4914.00 2820.00 P&M031 P&M001 P&M004 P&M025 P&M044 day day 0.240 6.000 350.00 180.00 84.00 1080.00 L-12 L-13

6.000 1700.00 10200.00

#VALUE! M-078 #VALUE! M-050 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 11 of 363

Case II

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfem capacity Bitumen pressure distributor @ 1750 sqm per hour spreader Hydraulic Chip Smooth wheeled road roller 8-10 tonne c) Material Modified binder Crushed stone chipping 11.2 mm size d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 10500 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500 say tonne 11.550 input cum 105.000 input hour hour hour hour hour 6.000 6.000 6.000 6.000 230.00 285.00 819.00 470.00 1380.00 1710.00 4914.00 2820.00 P&M031 P&M001 P&M004 P&M025 P&M044 day day 0.240 6.000 350.00 180.00 84.00 1080.00 L-12 L-13

6.000 1700.00 10200.00

#VALUE! M-078 #VALUE! M-051 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Case III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50laying a single coatn of a Providing and % stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfem capacity hour hour 6.000 6.000 230.00 285.00 1380.00 1710.00 P&M031 P&M001 day day day 0.240 6.000 2.000 350.00 180.00 250.00 84.00 1080.00 500.00 L-12 L-13 L-15

Page 12 of 363

Bitumen pressure distributor @ 1750 sqm per hour spreader Hydraulic Chip Smooth wheeled road roller 8-10 tonne c) Material Modified binder Crushed stone aggregates 11.2 mm size d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 10500 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500

hour hour hour

6.000 6.000

819.00 470.00

4914.00 2820.00

6.000 1700.00 10200.00

P&M004 P&M025 P&M044

tonne 15.750 input cum 126.000 input

#VALUE! M-078 #VALUE! M-051 #VALUE! #VALUE! #VALUE! #VALUE!

say Case IV Case - IV : Bitumen Impregnated Geotextile and Providing laying a bitumen impregnated geotextile layer after cleaning the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause Unit = sqm Taking output = 3500 sqm a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfem capacity Bitumen pressure distributor @ 1750 sqm per hour Pneumatic roller c) Material Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per sqm Geotextile including 10 % for overlaps d) Overheads @ 2.244% on (a+b+c) e) Contractors profit @ 5% on (a+b+c+d) Cost for 10500 sqm= a+b+c+d+e Rate per sqm = (a+b+c+d+e)/3500 say NOTE As bitumen overlay construction shallfollow closely the fabric placement on the same day, an output of 3500 sqm only has been considered for the analysis which will cover a length of 500 m, of 7 m widecarriagway. This can be conveniently overlaid by a bitumenious course in a dayfigures of any Printing new letter and 801 shade new letter and figures of any shade Printing with synthetic enamel paint black or any other approved colour to give an even shade ii) English and Roman tonne sqm 3.680 input ### input hour hour tonne hour 2.800 2.800 2.000 2.000 230.00 285.00 819.00 892.00 day day 0.560 2.000 350.00 180.00 250.00

#VALUE!

196.00 2160.00 500.00 644.00 798.00 1638.00 1784.00

L-12 L-13 L-15 P&M031 P&M001 P&M004 P&M037

day 12.000

#VALUE! M-075 #VALUE! M-108 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

8.3

Page 13 of 363

Hyphens and the like not to be measured and paid for100 letters of 16 cm height. Detail for i.e.1600 cm Unit = per cm height per letter a) Labour Mate Painter Ist class Mazdoor b) Material Paint c) Overheads @ 2.244% on (a+b) d) Contractors profit @ 5% on (a+b+c) Cost for 1600 cm = a+b+c+d Rate per cm height per (a+b+c +d)/1600 8.8 803 letter = Litre 0.50 input #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! day day day 0.07 1.25 0.50 350 250 180 24.50 312.50 90.00

Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces Unit = sqm Taking output = 40 sqm a) Labour Mate Painter Mazdoor b) Material Paint conforming to requirement of clause 803.3. Add for scaffolding @ 1% of labour cost where required c) Overheads @ 2.244% on (a+b) d) Contractors profit @ 5% on (a+b+c) Cost for 40 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/40 day day day Litre 0.12 2.00 1.00 6.00

350 250 180

42.00 500.00 180.00

input #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.9

803

Painting on Steel Surfaces Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade Unit = sqm Taking output = 10 sqm a) Labour Mate Painter Mazdoor b) Material Paint ready mixed approved brand. Add @ 1% on cost of material for scaffolding c) Overheads @ 2.244% on (a+b) Litre 1.25 input #VALUE! #VALUE! #VALUE! day day day 0.03 0.45 0.25 350 250 180 10.50 112.50 45.00

Page 14 of 363

d) Contractors profit @ 5% on (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/10 12.6 Sub- Cement mortar1:3 (1cement :3 sand) analysi s (A) Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) Sub- Cement mortar1:2 (1cement :2 sand) analysi s (B) Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) Sub- Cement mortar1:6 (1cement :6 sand) analysi s (D) Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) 1400 Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification Unit = cum Taking output = 5 cum (A) Square Rubble Coursed Rubble Masonry (first sort) a) Material Stone Through and bond stone (35no.x0.24mx0.24mx0.39m = 0.79 cu.m) Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

#VALUE! #VALUE! #VALUE! say #VALUE!

MT cum day day

0.51 1.05 0.04 0.90

input #VALUE! input #VALUE! 350.00 180.00 14.00 162.00 #VALUE!

MT cum day day

0.67 0.93 0.04 0.90

input #VALUE! input #VALUE! 350.00 180.00 14.00 162.00 #VALUE!

MT cum day day

0.29 1.20 0.04 0.90

input #VALUE! input #VALUE! 350.00 180.00 14.00 162.00 #VALUE!

12.7

cum each cum

5.50 35.00 1.50

input #VALUE! M-169 input #VALUE! M-182 ### #VALUE! Item 12.6 (A)

Page 15 of 363

b)

Labour Mate Mason Mazdoor c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Cost for 5 cum = a+b+c+d Rate per cum (a+b+c+d)/5

day day day

0.66 7.50 9.00

350.00 250.00 180.00

231.00 1875.00 1620.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

L-12 L-11 L-13

1405.3 B) Random Rubble Masonry ( coursed/uncoursed ) Unit = cum Taking output = 5 cum a) Material Stone cum Through and bond stone Nos (35nos.x0.24mx0.24mx0.39m = 0.79 cu.m) Cement mortar 1:3 (Rate as in item 12.6 A)cum b) Labour Mate day Mason day Mazdoor day c) Overheads @ 10% on (a+b) d) Contractors profit @ 10% on (a+b+c) Cost for 5 cum = a+b+c+d Rate per cum (a+b+c+d)/5 The labour already considered in cement mortar has been taken into account while proposing labour for masonry works. 1400 Stone masonry work in cement mortar 1:6 in foundation complete as drawing and Technical Specification Unit = cum Taking output = 5 cum 1405.3 B) Random Rubble Masonry ( coursed/uncoursed ) Unit = cum Taking output = 5 cum a) Material Stone cum Through and bond stone Nos (35nos.x0.24mx0.24mx0.39m = 0.79 cu.m) Cement mortar 1:3 (Rate as in item 13.6 D) cum b) Labour Mate day Mason day Mazdoor day c) Overheads @ 10% on (a+b) d) Contractors profit @ 10% on (a+b+c) Cost for 5 cum = a+b+c+d Rate per cum (a+b+c+d)/5 @ The labour already considered in cement mortar has been taken into account while proposing labour for masonry works. @

5.50 35.00 1.55 0.62 6.00 9.00

input #VALUE! input #VALUE! ### #VALUE! 350.00 250.00 180.00 217.00 1500.00 1620.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.7 (Add)

5.50 35.00 1.55 0.62 6.00 9.00

input #VALUE! input #VALUE! ### #VALUE! 350.00 250.00 180.00 217.00 1500.00 1620.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 16 of 363

1500, Plain/Reinforced cement concrete in 1700 & open foundation complete as per 2100 drawing and technical specifications A PCC Grade M15 Unit = cum Taking output = 15 cum a) Material Cement MT Coarse sand cum 40 mm Aggregate cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 63 KVA hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) d) Formwork @ 4% on cost of concrete i.e.cost of material, labour and machinery e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/15 Nedle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not added in rate analysis of cement concrete 12.8 B PCC Grade M20 works. Unit : cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 12.8 C RCC Grade M20 Unit = cum Case I Using concrete mixer Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate Note

12.8

4.13 6.75 8.10 4.05 1.35 0.86 1.50 20.00 6.00 6.00 ###

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00

165.00 990.00 input #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

MT cum cum cum cum day day day hour hour

5.16 6.75 5.40 5.40 2.70 0.86 1.50 20.00 6.00 6.00 ###

input input input input input 350.00 250.00 180.00 165.00 540.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00 990.00 3240.00

MT cum cum

5.21 6.75 8.10

input #VALUE! input #VALUE! input #VALUE!

Page 17 of 363

10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 33 KVA hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Case II With Batching Plant, Transit Mixer and Conrete Pump Unit : cum Taking Output = 120 cum a) Material Cement MT Coarse Sand cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Lead beyond 1 km, L-lead in km T-km Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) d) Formwork @ 4% on cost of concrete i.e.cost of material, labour and machinery e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = ( a+b+c+d+e+f )/120 PCC Grade M25 Unit = cum Case I Using concrete Mixer Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 12.8 D

5.40 0.86 1.50 20.00 6.00 6.00 ###

input #VALUE! 350.00 250.00 180.00 165.00 540.00 301.00 375.00 3600.00 990.00 3240.00

41.66 54.00 64.80 43.20 0.84 3.00 18.00

input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6 165.00 990.00 ### #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

MT cum cum cum cum day day day hour hour

5.99 6.75 5.40 5.40 2.70 0.86 1.50 20.00 6.00 6.00 ###

input input input input input 350.00 250.00 180.00 165.00 540.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00 990.00 3240.00

Page 18 of 363

Case II With Batching Plant, Transit Mixer and Conrete Pump Unit : cum Taking Output = 120 cum a) Material Cement MT Coarse sand cum 40 mm Aggregate cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity lead T-Km beyond 1 Km, L - lead in KilometerPump Concrete hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) d) Formwork @ 3.75% of cost of concrete i.e.cost of material, labour and machinery e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/120 RCC Grade M25 Unit = cum Case I Using concrete Mixer Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Case II With Batching Plant, Transit Mixer and Conrete Pump Unit : cum Taking Output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate 12.8 E

47.95 54.00 43.20 43.20 21.60 0.84 3.00 18.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6 165.00 ### #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 990.00

MT cum cum cum day day day hour hour

6.05 6.75 8.10 5.40 0.86 1.50 20.00 6.00 6.00 ###

input input input input 350.00 250.00 180.00 165.00 540.00

#VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00 990.00 3240.00

MT cum cum cum

48.38 54.00 64.80 43.20

input input input input

#VALUE! #VALUE! #VALUE! #VALUE!

Page 19 of 363

Admixer Kg b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity 1 cum hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 12.8 F PCC Grade M30 Unit = cum Case I Using Concrete Mixer Taking output = 15 cum a) Material Cement MT Coarse sand cum 40 mm Aggregate cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 33 KVA hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Case II Using Batching Plant, Transit Mixer and Conrete Pump Unit : cum Taking Output = 120 cum a) Material Cement MT Coarse sand cum 40 mm Aggregate cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 12.8 G RCC Grade M30

193.52 0.84 3.00 18.00

input #VALUE! 350.00 250.00 180.00 294.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00

6.08 6.75 5.40 5.40 2.70 0.86 1.50 20.00 6.00 6.00 ###

input input input input input 350.00 250.00 180.00 165.00 540.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00 990.00 3240.00

48.60 54.00 43.20 43.20 21.60 0.84 3.00 18.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00

Page 20 of 363

Case I Using Concrete Mixer Unit = cum Taking output = 15 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 33 KVA hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Case II Using Batching Plant, Transit Mixer and Conrete Pump Unit = cum Taking output = 120 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity lead T-Km beyond 1 Km, L - lead in KilometerPump Concrete hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 12.8 H RCC Grade M35 Case I Using Concrete Mixer Unit = cum Taking output = 15 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 33 KVA hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

6.10 6.75 8.10 5.40 0.86 1.50 20.00 6.00 6.00 ###

input input input input 350.00 250.00 180.00 165.00 540.00

#VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00 990.00 3240.00

48.80 54.00 64.80 43.20 0.84 3.00 18.00

input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00

6.33 6.75 8.10 5.40 0.86 1.50 20.00 6.00 6.00 ###

input input input input 350.00 250.00 180.00 165.00 540.00

#VALUE! #VALUE! #VALUE! #VALUE! 301.00 375.00 3600.00 990.00 3240.00

Page 21 of 363

Case II Using Batching Plant, Transit Mixer and Conrete Pump Unit ; cum Taking Output = 120 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum Admixer Kg b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) d) Formwork @ 3% on cost of concrete i.e.cost of material, labour and machinery e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/120 Rate per cum (a+b+c+d)/120 Note: Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers @ 0.4% of weight of cement may be added for achieving desired slump of concrete. 12.11 1200, Plain/Reinforced cement concrete, in 1500 & well foundation complete as per 1700 drawing and technical specification Bottom Plug Concrete to be placed using tremie pipe Case I Using Concrete Mixer (i) PCC Grade M20 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixer b) Labour Mate Mason C

50.64 54.00 64.80 43.20 202.56 0.84 3.00 18.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE!

MT cum cum cum cum Kg day day

5.55 6.75 5.40 5.40 2.70 18.60 0.90 1.50

input input input input input input 350.00 250.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 315.00 375.00

Page 22 of 363

Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 33 KVA hour Light Crane 3 tonnes capacity for hour handling tremie pipe Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Note 10% extra cement may be added where under water concreting is involved. Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit ; cum Taking Output = 120 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum Admixer Kg b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity, lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) (ii) PCC Grade M25

20.00 6.00 6.00 6.00 ###

180.00 165.00 540.00 230.00

3600.00 990.00 3240.00 1380.00

44.40 54.00 64.80 43.20 148.80 0.88 3.00 18.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 308.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00

Case I Using Concrete Mixer Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixer b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane of 3 tonnes capacity for handling tremie pipe Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

MT cum cum cum cum Kg day day day hour hour hour

5.99 6.75 5.40 5.40 2.70 21.60 0.90 1.50 20.00 6.00 6.00 6.00 ###

input input input input input input 350.00 250.00 180.00 165.00 540.00 230.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 315.00 375.00 3600.00 990.00 3240.00 1380.00

Page 23 of 363

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit = cum Taking output = 120 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum Admixer Kg b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity, lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) (iii) PCC Grade M30 Case I Using Concrete Mixer Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixer b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane of 3 tonnes capacity for handling tremie pipe Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixer b) Labour

47.88 54.00 64.80 43.20 172.80 0.88 3.00 18.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 308.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00

MT cum cum cum cum Kg day day day hour hour hour

6.08 6.75 5.40 5.40 2.70 21.60 0.90 1.50 20.00 6.00 6.00 6.00 ###

input input input input input input 350.00 250.00 180.00 165.00 540.00 230.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 315.00 375.00 3600.00 990.00 3240.00 1380.00

MT cum cum cum Kg

48.64 54.00 64.80 43.20 172.80

input input input input input

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 24 of 363

Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity, lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) (iv) PCC Grade M35 Case I Using Concrete Mixer Unit = 1 cum Taking output = 15 cum a) Material Cement MT Coarse sand cum 40 mm Aggregate cum 20 mm Aggregate cum 10 mm Aggregate cum Admixer Kg b) Labour Mate day Mason day Mazdoor day c) Machinery Concrete mixer (cap. 0.40/0.28 cum) hour Generator 33 KVA hour Light Crane of 3 tonnes capacity for hour handling tremie pipe Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit = cum Taking output = 120 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum Admixer Kg b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader 1 cum capacity hour Transit Mixer 4 cum capacity for lead upto 1 km. hour Transit Mixer 4 cum capacity, lead T-Km beyond 1 Km, L - lead in Kilometer Concrete Pump hour

0.88 3.00 18.00

350.00 250.00 180.00

308.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 ### 990.00

6.29 6.75 5.40 5.40 2.70 21.60 0.90 1.50 20.00 6.00 6.00 6.00 ###

input input input input input input 350.00 250.00 180.00 165.00 540.00 230.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 315.00 375.00 3600.00 990.00 3240.00 1380.00

50.28 54.00 64.80 43.20 172.80 0.88 3.00 18.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 308.00 750.00 3240.00

6.00 1526.00 9156.00 6.00 793.00 4758.00 6.00 1042.00 6252.00 15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 990.00

Page 25 of 363

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) Add 5% of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreteing with tremie pipe.. d) Overheads @ 10% on (a+b+c) e) Contractors profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum (a+b+c+d+e)/120 F Well cap iv) RCC Grade M35 Case II Using Batching Plant, Transit Mixer and Conrete Pump Unit = cum Taking output = 120 cum a) Material Cement MT Coarse sand cum 20 mm Aggregate cum 10 mm Aggregate cum b) Labour Mate day Mason day Mazdoor day c) Machinery Batching Plant @ 20 cum/hour hour Generator 100 KVA hour Loader(capacity 1 cum) hour Transit Mixer ( capacity 4.0 cu.m ) Transit Mixer 4 cum capacity for lead upto 1 km. hour Lead beyond 1 Km, L - lead in Kilometer T-Km Concrete Pump hour Formwork @ 3% of (a+b+c) d) Overheads @ 10% on (a+b+c) e) Contractors profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum (a+b+c+d+e)/120 Note Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers @ 0.4% of weight of cement may be added for achieving desired slump of concrete. Excavation for Structures Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the I) Ordinary soil Unit = cum Taking output = 10 cum A Manual Means

### #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! Say #VALUE!

50.64 54.00 64.80 43.20 0.84 3.00 18.00

input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00 9156.00 4758.00 6252.00

6.00 1526.00 6.00 793.00 6.00 1042.00

15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 990.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! Say #VALUE!

3.13

304

Page 26 of 363

(i) Depth upto 3 m a) Labour Mate Mazdoor b) Overheads @ 2.244% on (a) c) Contractors profit @ 5% on (a+b) Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 say Note Cost of dewatering may be added where required upto 10 % of labour cost Assessment for dewatering shall be made as per site conditions.. Mechanical Means (i) Depth upto 3 m Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 1.0 cum bucket capacity hour c) Overheads @ 2.244% on (a+b) d) Contractors profit @ 5% on (a+b+c) Cost for 300 cum = a+b+c+d Rate per cum = (a+b+c+d)/300 say Note Cost of dewatering upto 5% of (a+b) may be added, where required. Assessment for dewatering shall be made as per site conditions.. 6.00 1942 11652.00 296.30 675.01 14175.31 47.25 47.00 day day 0.32 8.00 350 180 112.00 1440.00 day day 0.320 8.000 350.00 180.00 112.00 1440.00 34.83 79.34 1666.17 166.62 167.00 L-12 L-13

13.6

Section Supplying, fitting and placing HYSD 1600 & bar reinforcement in sub-structure 2200 complete as per drawing and technical specifications Output : MT Taking output = 1 MT a) Material HYSD bars including 5% overlaps and Binding wire b) Labour for cutting, bending, shifting to site, tying and placing in position Mate Blacksmith Mazdoor c) Overheads @ 10% on (a+b) d) Contractors profit @ 10% on (a+b+c) Rate for per MT (a+b+c+d) 1500 Furnishing and Placing &1600 Reinforced/Prestressed cement 1700 concrete in super-structure as per drawing and Technical Specification Page 27 of 363

MT kg

1.05 6.00

input #VALUE! 0.00 0.00

day day day

0.34 2.00 6.50

350.00 250.00 180.00

119.00 500.00 1170.00 #VALUE! #VALUE! #VALUE! say #VALUE!

14.1

A RCC Grade M20 Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) Transit Mixer 4 cum capacity lead upto 1 Lead beyond 1 Km, L - lead in Kilometer Concrete Pump Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum (i) (p)

MT cum cum cum day day day hour hour hour Km hour T-Km hour

40.92 54.00 64.80 43.20 0.84 3.00 18.00

input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00 9156.00 4758.00 6252.00

6.00 1526.00 6.00 793.00 6.00 1042.00

15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 990.00 ###

For solid slab super-structure, 20-30% Height upto 5m Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum d) Formwork and staging 20 % of (a+b+c) e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/120 RCC Grade M25

#VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) Transit Mixer 4 cum capacity lead upto 1 Lead beyond 1 Km, L - lead in Kilometer

MT cum cum cum day day day hour hour hour Km hour T-Km

47.95 54.20 64.80 43.20 0.84 3.00 18.00

input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! 294.00 750.00 3240.00 9156.00 4758.00 6252.00

6.00 1526.00 6.00 793.00 6.00 1042.00

15.00 890.00 13350.00 300L input #VALUE! L= 35

Page 28 of 363

Concrete Pump Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum For formwork and staging add the following: (i) For solid slab super-structure, 20-30% (p) of (a+b+c) 5m Height upto Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum d) Formwork and staging 20 % of (a+b+c) e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) Cost for 15 cum= a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/120

hour

6.00 165.00 ###

990.00

#VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

RCC Grade M 30

Case II Using Batching Plant, Transit Mixer and Concrete Pump. Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) Transit Mixer 4 cum capacity lead upto 1 Lead beyond 1 Km, L - lead in Kilometer Concrete Pump Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum For formwork and staging add the (i) (p)

MT cum cum cum day day day hour hour hour Km hour T-Km hour

48.79 54.60 64.80 43.20 0.88 3.00 19.00

input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! 308.00 750.00 3420.00 9156.00 4758.00 6252.00

6.00 1526.00 6.00 793.00 6.00 1042.00

15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 990.00 ###

For solid slab super-structure, 20-30% Height upto 5m Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum d) Formwork and staging 20 % of (a+b+c) e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/120

#VALUE! 20.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Rate per cum (a+b+c+d)/120 ( including formwork and excluding #VALUE! OH & CP) Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding#VALUE! OH & CP)

Page 29 of 363

E PSC Grade M-40 Case 1 Using concret mixer. Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4% of cement b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4% of cement Admixer b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) Transit Mixer 4 cum capacity lead upto 1 Lead beyond 1 Km, L - lead in Kilometer Concrete Pump Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum For formwork and staging add the following: (i) For solid slab super-structure, 18-28% (p) of (a+b+c) 5m Height upto Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum d) Formwork and staging 18 % of (a+b+c) e) Overheads @ 10% on (a+b+c+d) f) Contractors profit @ 10% on (a+b+c+d+e) Cost for 15 cum= a+b+c+d+e+f Rate per cum (a+b+c+d+e+f)/120

MT cum cum cum kg day day day hour hour

6.45 6.75 8.10 5.40 25.80 0.96 2.00 22.00

input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 336.00 500.00 3960.00 990.00 3240.00

6.00 165.00 6.00 540.00 ###

MT cum cum cum kg Kg day day day hour hour hour Km hour T-Km hour

51.60 54.00 64.80 43.20 206.40 216.00 0.94 3.50 20.00

input input input input input input 350.00 250.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 329.00 875.00 3600.00 9156.00 4758.00 6252.00

6.00 1526.00 6.00 793.00 6.00 1042.00

15.00 890.00 13350.00 300L input #VALUE! L= 35 6.00 165.00 990.00 ###

#VALUE! 18.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 30 of 363

say #VALUE! Note 1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers conforming IS: 9103 @ 0.4% of weight of cement may be added for achieving desired slumpvarious components 2. Cement provided for of concrete. of the super structure is for estimating purpose only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix 3. The items like needle and surface vibrators are part of minor T & P which is already covered under the overhead charges. As such these items have not been added seperately in theplacing HYSD A) Supplying ,fitting and rate analysis.

14.2

1600

bar reinforcement in super-structure complete as per drawing and technical specifications Unit = 1 MT Taking output = 1 MT a) Material HYSD bars including 5% for laps and wastage MT Binding wire Kg b) Labour for cutting, bending, tying and placing in position Mate day Blacksmith day Mazdoor day Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

1.05 8.00

input #VALUE! 0.00 0.00

0.44 350.00 3.00 250.00 8.00 180.00 ###

154.00 750.00 1440.00

Page 31 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-1 CARRIAGE OF MATERIALS


1.1 1.2 1.3 1.4 (i) (ii) (iii) 1.5 Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum. (Placing tipper at loading point, loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip) Loading and Unloading of Boulders by Manual Means Loading and Unloading of Cement or Steel by Manual Means and stacking. Cost of Haulage Excluding Loading and Unloading Surfaced Road Unsurfaced Gravelled Road Katcha Track and Track in river bed / nallah bed and choe bed. Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone, hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50 mm sieve) and stacking as directed) Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 13 mm nominal size.) Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 20 mm nominal size.) Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone aggregates of 40 mm nominal size.) tonne.km tonne.km tonne.km cum 3.70 4.40 8.90 #VALUE! cum cum tonne 99.00 107.00 148.00

1.6

cum

#VALUE!

1.7

cum

#VALUE!

1.8

cum

#VALUE!

CHAPTER-2 SITE CLEARANCE


2.1 (i) (ii) (iii) (iv) 2.2

Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.) Girth from 300 mm to 600 mm Girth from 600 mm to 900 mm Girth from 900 mm to 1800 mm Girth above 1800 mm Clearing Grass and Removal of Rubbish Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness.) By Manual Means:In area of light jungle In area of thorny jungle By Mechanical Means In area of light jungle In area of thorny jungle Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres) Lime /Cement Concrete By Manual Means Lime Concrete, cement concrete grade M-10 and below Cement Concrete Grade M-15 & M-20 Prestressed / Reinforced cement concrete grade M-20 & above By Mechanical Means for items No. 202( b) & ( c) Cement Concrete Grade M-15 & M-20 Prestressed / Reinforced cement concrete grade M-20 & above Dismantling Brick / Tile work In lime mortar In cement mortar In mud mortar Dry brick pitching or brick soling Dismantling Stone Masonry

each each each each hectare

156.00 286.00 545.00 1026.00 10414.00

2.3

(i) A B (ii) A B

hectare hectare hectare hectare

31563.00 42298.00 26921.00 32651.00

2.4

(i) I A B C II A B (ii) A B C D (iii)

cum cum cum cum cum cum cum cum cum

236.00 278.00 709.00 317.00 524.00 153.00 195.00 136.00 128.00

Page 32 of 363

Summary of Rate Analysis


Item No. A B C D E F (iv) (v) A B C (vi) A B (vii) A B (viii) (ix) A B C 2.5 I A B II A Descriptions Rubble stone masonry in lime mortar Rubble stone masonry in cement mortar. Rubble Stone Masonry in mud mortar. Dry rubble masonry Dismantling stone pitching/ dry stone spalls. Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. Wood work wrought framed and fixed in frames of trusses upto a height of 5 m abovework inlevel Steel plinth all types of sections upto a height of 5 m above plinth level excluding cutting of rivet. Including dismembering Excluding dismembering. Extra over item No( V ) A and( V ) B for cutting rivets. Scraping of bricks dismantled from brick work including stacking. In lime/Cement mortar In mud mortar Scraping of Stone from dismantled stone masonry In cement and lime mortar In Mud mortar Scarping plaster in lime or cement mortar from brick/ stone masonry Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of masonry works. Up to 600 mm dia Above 600 mm to 900 mm dia Above 900 mm Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately) By Manual Means Bituminous courses Granular courses By Mechanical Means Bituminous course Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately) Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.) Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre) Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre) Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back filling of pit.) 5th KM stone Ordinary KM Stone Hectometre Stone Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable material and unserviceable material separately. ) Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned department) Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.) Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable material separately) metre metre metre 108.00 147.00 251.00 Unit cum cum cum cum cum cum cum tonne tonne tonne 1000 numbers 1000 numbers cum cum sqm Rate 170.00 195.00 153.00 145.00 136.00 153.00 350.00 879.00 673.00 6.00

729.00 260.00

293.00 62.00 9.00

cum cum cum

435.00 315.00 190.00

2.6

cum

#VALUE!

2.7 2.8 2.9 2.10 A B C 2.11

metre metre metre

47.00 10.00 15.00

each each each metre

242.00 136.00 27.00 30.00

2.12

metre

74.00

2.13

metre

#VALUE!

2.14

each

104.00

Page 33 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE


3.1 3.2 Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.) Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres ) Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.) Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres ) Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m) Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.) Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.) Mechanised Manual Method Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres ) Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections.) Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.) Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead upto 1000 m, all as specified in clause No. 303) Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.) Ordinary soil Manual Means (Depth upto 3 m) Mechanical Means (Depth upto 3 m) Ordinary rock (not requiring blasting) Manual Means (Depth upto 3 m) Mechanical Means Hard rock ( requiring blasting ) Manual Means Hard rock ( blasting prohibited ) Mechanical Means Marshy soil Manual means ( upto 3 m depth) cum cum 123.00 166.00

3.3

cum

88.00

3.4

cum

149.00

3.5

cum

#VALUE!

3.6

cum

60.00

3.7

cum

78.00

3.8 A B

cum cum

502.00 748.00

3.9

cum

#VALUE!

3.10

cum

67.00

3.11

cum

60.00

3.12

sqm

#VALUE!

3.13

(i) A B (ii) A B (iii) A (iv) A (v) A

cum cum cum cum cum cum cum

167.00 47.00 208.00 64.00 #VALUE! 410.00 #VALUE!

Page 34 of 363

Summary of Rate Analysis


Item No. B 3.14 Descriptions Mechanical Means Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. ) Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.) Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2) Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2) Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2) Compacting Original Ground Compacting original ground supporting subgrade (Loosening of the ground upto a level of500 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.) :Compacting original ground supporting embankment Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to plant growth) Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.) Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of rods and watering) Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including watering for 3 months all as per clause 308) Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of50 metres (average lead 25 metres)) Mechanical means Manual Means Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309. Excavated material to be used in embankment at site.) Mechanical Means Manual Means Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard Surface Drains with Perforated Pipe (Construction of subsurface drain with Sub rock as per design.) perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of excavation 450 x 550 mm. Excavated material to be utilised in roadway at site ) Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates conforming to table 300-4, excavated material to be utilised in roadway ) Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads) Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud and slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.) Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top layer with granular material, rolled with vibratory road roller, all complete as per clause 313) Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres) Unit cum sqm Rate #VALUE! 16.00

3.15

sqm

4.00

3.16

cum

#VALUE!

3.17

cum

#VALUE!

3.18 3.19 Case-I Case-II 3.20

cum

#VALUE!

cum cum cum

#VALUE! #VALUE! 130.00

3.21

cum

53.00

3.22

sqm

#VALUE!

3.23

sqm

#VALUE!

3.24 A B 3.25 A B 3.26

metre metre

74.00 42.00

metre metre metre

150.00 62.00

3.27

#VALUE!

3.28 3.29

metre metre

#VALUE! #VALUE!

3.30

sqm

#VALUE!

3.31

cum

#VALUE!

3.32

cum

115.00

Page 35 of 363

Summary of Rate Analysis


Item No. 3.33 Descriptions Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres ) Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.) Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following reasons:) Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in IRC: SP: 58-2001 and as per approved plans.) Unit cum Rate 169.00

3.34

cum

#VALUE!

3.35

3.36

cum

#VALUE!

Page 36 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-4 SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS


4.1 A (i) (ii) (iii) B (i) (ii) (iii) Granular Sub-base with Close Graded Material (Table:- 400-1) Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 ) for grading- I Material for grading- II Material for grading-III Material By Mix in Place Method (Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401) for grading- I Material for grading- II Material for grading-III Material Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401) for grading- I Material for grading- II Material for grading-III Material Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the subgrade on a prepared surface, pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of improved sub grade) By Mechanical Means By Manual Means Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading with motor grader and compacting with the road roller at OMC to achieve at least 98%of the max dry density to form a layer of sub base.) Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base.) Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base (Providing, laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of subbase/base.) For Sub-Base course

cum cum cum

#VALUE! #VALUE! #VALUE!

cum cum cum

#VALUE! #VALUE! #VALUE!

4.2

(i) (ii) (iii)

cum cum cum

#VALUE! #VALUE! #VALUE!

4.3

A B

cum cum

#VALUE! #VALUE!

4.4

cum

#VALUE!

4.5

cum

#VALUE!

4.6

(i) (ii)
4.7

cum cum sqm

#VALUE! #VALUE! 471.00

For Base course


Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450 to the center line of the road and at one metre interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material within 1000 metres lead) Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc) Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density.) By Manual Means Grading- I (Using Screening Crushable type such as Moorum or Gravel) Using Screening Crushable type such as Moorum or Gravel Using Screening Type-A (13.2mm Agg.) Grading- II (Using Screening Crushable type such as Moorum or Gravel) Using Screening Crushable type such as Moorum or Gravel Using Screening Type-A (13.2mm Agg.)

4.8

cum

#VALUE!

4.9

A (i) (a) (b) (ii) (a) (b)

cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE!

Page 37 of 363

Summary of Rate Analysis


Item No. (c) (iii) (a) (b) B (i) (a) (b) (ii) (a) (b) (c) (iii) (a) (b) Descriptions Using Screening Type-B (11.2mm Agg.) Grading- III (Using Screening Crushable type such as Moorum or Gravel) Using Screening Crushable type such as Moorum or Gravel Using Screening Type-B (11.2mm Agg.) By Mechanical Means: Grading- I (Using Screening Crushable type such as Moorum or Gravel) Using Screening Crushable type such as Moorum or Gravel Using Screening Type-A (13.2mm Agg.) Grading- II (Using Screening Crushable type such as Moorum or Gravel) Using Screening Crushable type such as Moorum or Gravel Using Screening Type-A (13.2mm Agg.) Using Screening Type-B (11.2mm Agg.) Grading- III (Using Screening Crushable type such as Moorum or Gravel) Using Screening Crushable type such as Moorum or Gravel Using Screening Type-B (11.2mm Agg.) Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM to clause 404 except the use of screening or binding Material.) Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8) Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.) Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other structures, spread, graded and compacted as per clause 407) Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above road level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407) Construction of Shoulders (A. Earthen Shoulders) Footpaths and Separators (Construction of footpath/separator by providing a 150 mm compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15, over laid with precast concrete tiles in cement mortar 1:3 including provision of all drainage arrangements but excluding kerb channel..) Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of subbase/Base) By Mix in Place Method Unit cum cum cum Rate #VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

4.10

cum

#VALUE!

4.11

sqm

#VALUE!

4.12

cum

#VALUE!

4.13

cum

#VALUE!

4.14 4.15 4.16

cum

#VALUE!

sqm

#VALUE!

4.17 A

(i) (ii)
B

For 53 mm maximum size For 45 mm maximum size


By Mixing Plant :

cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE!

(i) (ii)

For 53 mm maximum size For 45 mm maximum size


Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture with granular soil, free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50%, fly ash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to 30%, the minimum un-confined compressive strength and CBR value after 28 days curing and 4 days soaking to be 7.5kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984. )

4.18

cum

#VALUE!

Page 38 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)


5.1 5.2 Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.) Tack coat Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction) for Grading I ( 40 mm nominal size ) for GradingII(19 mm nominal size) Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction) 50 mm thick 75 mm thick Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two layer composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the second layer to serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness being 75 mm) Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.) for Grading I ( 40 mm nominal size ) for GradingII(19 mm nominal size) Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects) (i) (ii) for Grading I ( 13 mm nominal size ) for GradingII(10 mm nominal size) Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause nominalcomplete in all respects) for Grading-I ( 13 mm No. 509 size ) for Grading-II(10 mm nominal size) Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller) :-19 mm nominal chipping size 13 mm nominal size chipping Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.) Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75 tonnes/hour . Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm sqm #VALUE! #VALUE! cum cum 4021.00 4292.00 sqm #VALUE!

sqm

#VALUE!

5.3

(i) (ii)

cum cum

#VALUE! 3711.00

5.4

A B

sqm sqm

#VALUE! #VALUE!

5.5

sqm

#VALUE!

5.6

(i) (ii)

cum cum

#VALUE! 4316.00

5.7

5.8

(i) (ii) 5.9 Case -1 Case - II

cum cum

#VALUE! 4382.00

5.10

(i) (ii)

sqm sqm

#VALUE! #VALUE!

Page 39 of 363

Summary of Rate Analysis


Item No. Descriptions Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to required level and grade. ) Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A and B seal coats) (i) (ii) Case - I : Type A Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.) Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection, transportation, stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-loading charges and cost of carriage may be added to these rates to arrive at the cost at site.) Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.) Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and compacting to provide even riding surface) 5 mm thickness 3 mm thickness 1.5 mm thickness Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of the required quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and compacting to the required grade, level and thickness, all as specified in clause 517.) Fog Spray 1.In case it is decided by the engineer to blind the fog spray, the following may be added Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing to specified grades and Using levels.) bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and bituminous binder on a prepared sub-grade or subbase to the lines, levels, grades and cross sections as per the drawings including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.) Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending of modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified binder to be delivered in drums which shall be agitated in melted condition using suitable device before use to ensure uniform dispersion.) Crack Prevention Courses Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.) Unit Rate

5.11

sqm

#VALUE!

5.12

sqm sqm

#VALUE! #VALUE!

5.13

cum

5.14

sqm

#VALUE!

5.15 (i) (ii) (iii)

sqm sqm sqm

#VALUE! #VALUE! #VALUE!

5.16

cum

#VALUE!

5.17 added 5.18 (i) (ii) (iii) (iv) 5.19

sqm sqm

#VALUE! #VALUE!

cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

5.20

tonne

5.21

(i)

sqm

#VALUE!

Page 40 of 363

Summary of Rate Analysis


Item No. Descriptions Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to conform to clause 902.) Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and laying a single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates Bitumen Impregnated Geotextile (Providing Case - IV : and surface finished to conform to clause 902.) and laying a bitumen impregnated geotextile layer after cleaning the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and 704.4.5) emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth steel wheel roller, all as per clause 519.3) 75 mm thickness 40 mm thickness 25 mm thickness Unit Rate

(ii)

sqm

#VALUE!

(iii)

sqm

#VALUE!

(iv)

sqm

#VALUE!

5.22 (i) (ii) (iii)

cum cum cum

#VALUE! #VALUE! #VALUE!

Page 41 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-6 CEMENT CONCRETE PAVEMENTS


Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Subbase over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.) Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing ) Rolled Cement Concrete Base (Construction of rolled cement concrete base course with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, mixing in batching plant at optimum moisture content, transporting to site, laying with a paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled vibratory roller to achieve, the designed flexural strength, finishing and curing.) Transition section between rigid and flexible pavement (Due to change in the properties of materials and type of construction, a gradual changeover from rigid pavement to flexible pavement is desirable to avoid any damage at the butting joint. After provision of an expansion joint in the cement concrete slab, the thickness of slab should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The deficiency of thickness caused due to tapering of the slab should be made up by the asphaltic layers.) Base/Sub-base of pavement with lean concrete - fly ash. Construction of (Construction of Base/sub-base using cement, sand, fly ash and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and with water content ratio, slump and compressive strength as defined in the said table, mix prepared in a batching and mixing plant and compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid down vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved plans.) Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15% and sand by 10%, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing ) CHAPTER-7

6.1

cum

#VALUE!

6.2

cum

#VALUE!

6.3

cum

#VALUE!

6.4

6.5

cum

#VALUE!

6.6

cum

#VALUE!

GEOSYNTHETICS AND REINFORCED EARTH


7.1 Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using geotextiles treated with carbon black with physical properties as given in clause 702.2.3 formed in to a stable network and a planar geocomposite structure, joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved drawings including excavation and backfilling) Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed as per clause 702.3 and 309.3.5 including excavation and backfilling) Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with physical requirements as per table 704-2 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to provide a water resistant membrane and crack retarding layer. Paving fabric to be free of wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface with pneumatic roller to maximise paving fabric contact with pavement surface) metre #VALUE!

7.2

metre

#VALUE!

7.3

sqm

#VALUE!

Page 42 of 363

Summary of Rate Analysis


Item No. Descriptions Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids having characteristics as per clause 704.2, joining sides with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the foundation recess in case of sloping ground and laid over a layer of geotextile to prevent migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.) Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components as under: a) Excavation for foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia material). b) Facia material and its placement. c) Assembling, joining with facing elements and laying of the reinforcing elements. d) Earthfill with granular material which is to be retained by the wall.) elements of RCC Facing Assembling, joining and laying of reinforcing elements. With reinforcing element of steel / Aluminium strips / polymeric strips. 1.Galvanised carbon steel strips 2.Copper Strips 3.Aluminium Strips 4.Stainless steel strips 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips With reinforcing elements of synthetic geogrids Unit Rate

7.4

cum

#VALUE!

7.5

(i) (ii) A Type 1 Type 2 Type 3 Type 4 Type 5 B

sqm

#VALUE!

metre metre metre metre metre sqm

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 43 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES


8.1 Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408) Using Concrete Mixer Using Concrete Batching and Mixing Plant Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408) Using Concrete Mixer Using Concrete Batching and Mixing Plant Printing new letter and figures of any shade (Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade) Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half ) English and Roman Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing) (i) ( ii ) ( iii ) ( iv ) (v) (vi ) ( vii ) 90 cm equilateral triangle 60 cm equilateral triangle 60 80 60 60 90 cm circular mm x 60 mm rectangular cm x 45 cm rectangular cm x 60 cm square cm high octagon each each each each each each each #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

A B

metre metre

#VALUE! #VALUE!

8.2

A B 8.3 (i) (ii)

metre metre

#VALUE! #VALUE!

cm height per letter cm height per letter

#VALUE! #VALUE!

8.4

8.5

Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing) Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction and place identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing) Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles and trusses of sections and type as per structural design requirements and approved plans) Truss and Vertical Support Aluminium alloy plate for over head sign Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces) Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade) Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface after through cleaning of surface to give an even shade) Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control ) Over 10 cm in width

sqm

#VALUE!

8.6

sqm

#VALUE!

8.7

A B 8.8 8.9 8.10

tonne tonne sqm sqm sqm

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

8.11 (i)

sqm

#VALUE!

Page 44 of 363

Summary of Rate Analysis


Item No. (ii) 8.12 (i) (ii) Descriptions Up to 10 cm in width Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on roads in two coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control ) Over 10 cm in width Up to 10 cm in width Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.) Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc) 5th kilometre stone (precast) Ordinary Kilometer stone (Precast) Hectometer stone (Precast) Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.) Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in position including finishing and lettering but excluding painting) G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807 ) wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI G.I Barbed barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 807 ) welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing Fencing with 1.20 metre high fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete, corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete inRailing on Medium Weight steel channel ( ISMC series) 100 mm x Tubular Steel all respects.) 50 mm (Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings) Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing) Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with premoulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as specified) M 20 grade concrete Metal Beam Crash Barrier Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810) Unit sqm Rate #VALUE!

sqm sqm

#VALUE! #VALUE!

8.13

sqm

#VALUE!

8.14 (i) (ii) (iii)

each each each

#VALUE! #VALUE! #VALUE!

8.15

each

#VALUE!

8.16

each

#VALUE!

8.17

metre

#VALUE!

8.18

metre

#VALUE!

8.19

metre

#VALUE!

8.20

metre

#VALUE!

8.21

metre

#VALUE!

8.22

(i) 8.23

metre

#VALUE!

metre

#VALUE!

Page 45 of 363

Summary of Rate Analysis


Item No. Descriptions Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810) Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in this field and ISI certified for the approved design and drawing.) Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per approved design and drawing, rate excluding excavation and cement concrete.) Anti - Glare Devices in Median Plantation (Plantation of shrubs and plants of approved species in the median. apart from cutting off glare from vehicle coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is available in the chapter 11 on horticulture. ) Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre length and 1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design of MS sheet (Providing and erecting Anti - Glare Screen with Rectangular Vane and drawings.) anti - glare screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete as per approved design and drawings) Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.) For Fixing in Median For fixing in Footpath Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp) Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.) Single Row for one utility service Double Row for two utility services Triple Row for three utility services Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. ) Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/ subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the approved designs and drawings) Traffic Control System and Communication system (Providing a traffic control centre and communication system including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer system These are specialised item of telecommunication system and are the commercial products. The designer is required to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these installations, pricing may be done as per rates in relevant chapters for quantities derived approved design and drawing.) Unit Rate

metre

#VALUE!

8.24

8.25

metre

#VALUE!

8.26 A

metre

#VALUE!

metre

#VALUE!

8.27 (i) (ii) 8.28

each each each

#VALUE! #VALUE! #VALUE!

8.29

(i) (ii) (iii) 8.30

metre metre metre

#VALUE! #VALUE! #VALUE!

8.31

8.32

Page 46 of 363

Summary of Rate Analysis


Item No. 8.33 (i) (ii) 8.34 A Descriptions Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause Gantry Support System 802.3) Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for flashing the pre-determined messages.) Traffic Impact Attenuators at Abutments and Piers With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as per approved design and drawings.) Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire rope as per approved design and drawings) With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic tubes on impact over a pre-determined time, thus absorbing the energy)) Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973) Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873) Roadside Amenities Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required to be assessed for specific location as per actual site conditions) Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates for items may be from respective chapters.) Lawn (Providing a lawn planted with grass and its maintenance ) Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.) Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a paint) high mast pole lighting with 30 m high hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and drawings This is a specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are submitted by the firms alongwith their tender for checks by the Department. The cost of this work is required to be worked out based on approved design, drawings and estimate of the Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken lowest tender. A separate contract for this work is concluded as the contractors for road into separate items of work as under based on the approved design and drawings:-) and bridge works generally donot undertake such jobs.) Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable locations in construction zone comprising of warning zone, approach transition zone, working zone and terminal transition zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings, removed and disposed of after completion of construction work, all as per IRC:SP:552001) Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001 ) Permanent Type Barricade in Construction Zone sqm #VALUE! Unit Rate

tonne

#VALUE!

sqm

#VALUE!

sqm

#VALUE!

8.35

each

#VALUE!

8.36 8.37

each

#VALUE!

B C 8.38

sqm

8.39

each

8.40

8.41

8.42

8.43

each

#VALUE!

8.44

Page 47 of 363

Summary of Rate Analysis


Item No. Descriptions With Steel Components (Construction of a permanent type barricade made of steel components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 ) With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:552001 ) With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips) Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter, 800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001) Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic) Unit Rate

each

#VALUE!

each

#VALUE!

each

#VALUE!

8.45

each

#VALUE!

8.46

each

#VALUE!

CHAPTER-9 PIPE CULVERTS


9.1 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row . (Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets . ) 1000 mm dia 1200 mm dia Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding in double row . (Laying Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets . ) 1000 mm dia 1200 mm dia cum #VALUE!

9.2

A B

metre metre

#VALUE! #VALUE!

9.3

A B

metre metre

#VALUE! #VALUE!

Page 48 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-10 MAINTENANCE OF ROADS


10.1 Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting with plate compactor or power rammers to restore the original alignment, levels and slopes) Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/ irregularities on shoulder to the design level by adding fresh approved soil and compacting it with appropriate equipment.) Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder surface to achieve the approved level and compacting with plate compactor) Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 511, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2) Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2) for grading I Material for grading II Material Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher dust in case crack are wider than 3mm.) Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has occurred.) (ref item 5.17) Fog Seal (i) (ii) (iii) (iv) C (i) (ii) (iii) D (i) (ii) 10.9 10.10 10.11 10.12 10.13 10.14 10.15 Crack Prevention courses. (ref item 5.21) Stress Absorbing Membrane (SAM) crack width less than 6 mm Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % Bitumen Impregnated Geotextile Slurry Seal (ref item 5.15) 5 mm thickness 3 mm thickness 1.5 mm thickness Surface Dressing for maintance works. (ref item 5.9) 19 mm nominal chipping size 13 mm nominal size chipping Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints, longitudinal joints and expansion joints in concrete pavements using epoxy mortar or epoxy concrete) Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction, longitudinal or expansion joints in concrete pavement with fresh sealant material) Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on the valley side manually) Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side) Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock requiring blasting for 50% of the boulders and disposal of the same on the valley side.) Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bulldozer 165 Hp and disposing it on the valley side) Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow blower and disposing on the valley side.) cum #VALUE!

10.2 10.3

sqm sqm

#VALUE! 6.00

10.4

sqm

#VALUE!

10.5

(i) (ii) 10.6 10.7 10.8 A B

sqm sqm metre sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm metre metre metre cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! 22.00 45.00 #VALUE! 3.00 #VALUE!

Page 49 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-11 HORTICULTURE
11.1 Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm- yard manure or/and good earth to be paid for separately)) Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for moving including supplying good earth if needed) (i) (ii) 11.3 In rows 15 cm apart in either direction In rows 7.5 cm apart in either direction Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns including ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs grass roots and planting at 15 cm apart, including supplying and spreading of farm yard manure at rate of 0.18 cum per 100 sqm) Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough grassing) for a period of one year including watering etc) Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine grassing including ploughing, dressing including breaking of clods, removal of rubbish, dressing and supplying doobs grass roots at 10 cm apart, including supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm) Maintenance of Lawns with Fine Grassing for the First Year a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges including digging of trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed with farmyard manure, supplied at the rate of 4.65 cum per 100 metres and supplying and planting hedge plants at 30 cm apart) Maintenance of Hedge for one year a) Planting Flowering Plants and Shrubs in Central Verge Maintenance of Flowering Plants and Shrubs in Central Verge for one Year Planting of Trees and their Maintenance for one Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trench, watering, fixing the tree guard and maintaining the plants for one year) Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil (Renovation lawns including, weeding, forking the ground, top dressing with forked soil, watering and maintenance the lawns, for 30 days or more, till the grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish as directed, including supplying good earth, if needed but excluding the cost of well decayedat Site Well Decayed Farm Yard Manure (Supply at site of work well decayed Supply farm yard manure) farm yard manure, from any available source, approved by the engineer in charge including screening and stacking) Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ storedeoiled neem cake duly packed in used gunny bags) Supplying Sludge (Supplying sludge duly stacked at site/ store) Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd class brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid dry, and top three courses in cement mortar 1:6 ( 1 cement 6 sand) and the intermediate courses being in dry honey comb masonry, as per design complete) Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry lengthwise, including excavation, refilling, consolidation, with a hand packing and spreading nearly surplus earth within a lead of 50 metres) Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making tree guard 53 cm dia and 1.3 m high as per design from empty bitumen drum, slit suitably to permit sun and air, (supplied by the department at stock issue rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect) Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums (Making tree guard 53 cm dia and 2 metres high as per design from empty bitumen drums, slit suitably to permit sun and air, ( supplied by the department at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects) Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using angles, square bars, tees and channel grills, grating frames, gates and tree guards of any size and design etc. including cost of screens and welding rods or bolts and nuts complete fixed in position but without the cost of excavation and concrete for fixing which will be paid separately) cum 14.00

11.2

sqm sqm sqm

#VALUE! #VALUE! #VALUE!

11.4

sqm

#VALUE!

11.5 11.6 11.7 (b) 11.8 (b) 11.9

sqm sqm metre metre km km each

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

11.10

sqm

#VALUE!

11.11 11.12 11.13

cum quintal cum

11.14

each

#VALUE!

11.15

metre

#VALUE!

11.16

each

#VALUE!

11.17

each

#VALUE!

11.18

quintal

#VALUE!

Page 50 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) each tree vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 guard mm dia and 30 mm long bolts including painting two coats with paint of approved brand over a coat of priming, complete in all respects.) Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 each tree metre square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron guard 25 x 3 mm and steel wire3 mm dia welded and fabricated as per design in two halves bolted together) Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290 trees per hectare at a spacing of 6 m by grubbing and leveling the ground upto a hectare depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil, planting of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering) Rate

11.19

#VALUE!

11.20

#VALUE!

11.21

#VALUE!

Page 51 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-12 FOUNDATIONS
12.1 I A (i) (ii) (iii) B (i) (ii) (iii) II A (i) B III A IV A V (i) A B VI 12.2 12.3 12.4 12.5 12.6 A B C D 12.7 (a) (b) 12.8 A B C Case I Case II D Case I Case II E Case I Case II F Case I Case II G Case I Case II Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) Ordinary soil Manual Means upto 3 m depth 3 m to 6 m depth Above 6 m depth Mechanical Means Depth upto 3 m Depth 3 m to 6 m Depth above 6m Ordinary rock (not requiring blasting) Manual Means Depth upto 3 m Mechanical Means Hard rock ( requiring blasting ) Manual Means Hard rock ( blasting prohibited ) Mechanical Means Marshy soil upto 3 m depth Manual means Mechanical Means Back Filling in Marshy Foundation Pits Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per items 13.4.) Sand Filling in Foundation Trenches as per Drawing & Technical Specification PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per drawing and technical specifications Cement Cement Cement Cement mortar1:3 mortar1:2 mortar1:4 mortar1:6 (1cement (1cement (1cement (1cement :3 :2 :4 :6 sand) sand) sand) sand) cum cum cum cum cum cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! cum cum cum cum cum cum 82.00 106.00 141.00 67.00 76.00 91.00

cum cum cum cum

117.00 86.00 #VALUE! 324.00

cum cum cum

332.00 114.00 238.00

Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification Square Rubble Coursed rubble masonry( first sort ) Random Rubble Masonry Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications PCC Grade M15 PCC Grade M20 RCC Grade M20 Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump PCC Grade M25 Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump RCC Grade M25 Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump PCC Grade M30 Using Concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump RCC Grade M30 Using Concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump

cum cum cum cum cum cum cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 52 of 363

Summary of Rate Analysis


Item No. H Case I Case II 12.9 A B C 12.10 12.11 A (i) Case I Case II (ii) Case I Case II (iii) Case I Case II B (I) (ii) (iii) Case I Case II (iv) Case I Case II (v) Case I Case II (vi) Case I Case II (vii) Case I Case II (viii) Case I Case II (ix) C (i) Case I Case II (ii) Case I Case II (iii) Case I Case II (iv) Case I Case II D (I) Case I Descriptions RCC Grade M35 Using Concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well. Assuming depth of water 1.0 m and height of island to be 1.25m. Assuming depth of water 4.0 m and height of island 4.5 m. Providing and constructing one span service road to reach island location from one pier location to another pier location Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per drawing and technical specification. Plain/Reinforced cement concrete, in well foundation complete as per drawing and curb Welltechnical specification RCC M20 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump RCC M25 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump RCC M35 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump Well steining PCC M15 Grade PCC M20 Grade RCC M20 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump PCC M25 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump RCC M25 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump PCC M30 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump RCC M30 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump RCC M35 Grade Using concrete mixer With Batching Plant, Transit Mixer and Concrete Pump RCC M40 Grade Bottom Plug PCC Grade M20 Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete PCC Grade M25 Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete PCC Grade M30 Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete PCC Grade M35 Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete Intermediate plug Grade M20 PCC Using Concrete Mixer cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! each each metre tonne #VALUE! #VALUE! #VALUE! #VALUE! Unit cum cum Rate #VALUE! #VALUE!

pump

cum cum cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

pump

pump

pump

cum

#VALUE!

Page 53 of 363

Summary of Rate Analysis


Item No. Case II (ii) Case I Case II (iii) Case I Case II E (i) Case I (ii) Case I (iii) Case I Case II (iv) Case I Case II F (i) Case I Case II (ii) Case I Case II (iii) Case I Case II (iv) Case I Case II (v) 12.12 A (i) (ii) (iii) a (iv) a b (v) a b B (i) (ii) (iii) a b (iv) a b c (v) a b c Descriptions Using Batching Plant, Transit Mixer and Crane/concrete pump Grade M25 PCC Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete pump Grade M30 PCC Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete pump Top plug Grade M15 PCC Using Concrete Mixer Grade M20 PCC Using Concrete Mixer Grade M25 PCC Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete pump Grade M30 PCC Using Concrete Mixer Using Batching Plant, Transit Mixer and Crane/concrete pump Well cap RCC Grade M20 Using concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump RCC Grade M25 Using concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump RCC Grade M30 Using Concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump RCC Grade M35 Using Concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump RCC M40 Grade Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous 30 m Beyond 20m upto meter Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Clayey soil ( 6m dia. Well ) Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the dewatering @ Add forprevious meter5% of cost, if required. Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering of the cost, if required Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering, if required Add 20% of cost for Kentledge including supports, loading arrangement and Labour). cum cum cum cum cum cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! cum cum #VALUE! #VALUE! cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! Unit cum cum cum cum cum Rate #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre

11437.00 16958.00 22396.00 42010.00 50411.00 99810.00 119772.00 16979.00 35556.00 46959.00 49307.00 88083.00 115609.00 110103.00 209271.00 263682.00 251125.00

Page 54 of 363

Summary of Rate Analysis


Item No. C (i) D (i) 12.13 A (i) (ii) (iii) a (iv) a b (v) a b B (I) (ii) (iii) a b (iv) a b c (v) a b c C (i) D (i) 12.14 A (i) (ii) (iii) a (iv) a b (v) a b B (i) (ii) (iii) a b (iv) a b c Descriptions Soft rock (6m dia well ) Depth of soft rock strata upto 3m Hard rock (6m dia well ) Depth of soft rock strata upto 3m Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. Clayey soil ( 7m dia. Well ) Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the dewatering @ Add forprevious meter5% of cost, if required. Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the of cost for dewatering on the cost, if required Add 5%previous meter Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering, if required Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock ( 7m dia well ) Depth of soft rock strata upto 3m Hard rock ( 7m dia well ) Depth upto 3 m Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. Clayey soil ( 8m dia. Well ) Depth upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter5% of cost, if required. Add for dewatering @ Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering on the cost, if required Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre metre metre metre metre metre metre metre metre metre metre metre metre metre 33203.00 62280.00 74736.00 147970.00 177563.00 25141.00 36725.00 48502.00 50927.00 90979.00 119409.00 113723.00 216154.00 272354.00 259385.00 32327.00 #VALUE! metre metre 36276.00 25141.00 Unit metre metre Rate 31454.00 #VALUE!

metre metre

metre metre metre metre metre metre metre metre metre metre metre metre metre metre

22479.00 28018.00 37002.00 69407.00 83288.00 24397.00 29277.00 30742.00 36611.00 48352.00 50769.00 90695.00 119037.00 113369.00

Page 55 of 363

Summary of Rate Analysis


Item No. (v) a b c C (i) D (i) 12.15 A (i) (ii) (iii) a (iv) a b (v) a b B (i) (ii) (iii) a b (iv) a b c (v) a b c C (i) D (i) 12.16 A (i) (ii) (iii) a (iv) a b (v) a b B (i) (ii) (iii) a b Descriptions Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering, if required Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock ( 8m dia well ) Depth in soft rock strata upto 3m Hard rock ( 8m dia well ) Depth in hard rock strata upto 3 m Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. Clayey soil ( 9m dia. Well ) Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter5% of cost, if required. Add for dewatering @ Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering on the cost, if required Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering, if required Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock ( 9m dia well ) Depth upto 3m Hard rock ( 9m dia well ) Depth of hard rock strata upto 3 m Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. Clayey soil (10m dia. Well ) Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter5% of cost, if required. Add for dewatering @ metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre 22538.00 30797.00 40674.00 76295.00 91553.00 181265.00 217518.00 32212.00 39590.00 52287.00 54901.00 98075.00 128724.00 122594.00 233011.00 293594.00 279613.00 47179.00 #VALUE! Unit metre metre metre metre metre Rate 215476.00 271500.00 258572.00 35857.00 #VALUE!

metre metre metre metre metre metre metre metre metre metre metre

27921.00 32275.00 42625.00 79955.00 95946.00 189962.00 227955.00 34004.00 37413.00 49411.00 51882.00

Page 56 of 363

Summary of Rate Analysis


Item No. (iv) a 'b c (v) a b c C (i) D (i) 12.17 A (i) (ii) (iii) a (iv) a b (v) a b B (i) (ii) (iii) a b (iv) a b c (v) a b c C (i) D (i) 12.18 A (i) (ii) (iii) a (iv) a b (v) a b B (i) Descriptions Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering on the cost, if required Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering, if required Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock (10m dia well ) Depth of soft rock strata upto 3m Hard rock (10m dia well ) Depth of hard rock strata upto 3 m Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth from bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous for Kentledge including supports, loading arrangement, and Add 20% of cost meter Labour etc. Clayey soil (11 m dia. Well ) Depth from bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter5% of cost, if required. Add for dewatering @ Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering on the cost, if required Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the of cost for dewatering, if required Add 5%previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock (11m dia well ) Depth of soft rock strata upto 3m Hard rock (11m dia well ) Depth of hard rock upto 3 m Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil I) Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. Clayey soil (12 m dia. Well ) Depth below bed level upto 3.0 M metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre 60797.00 114042.00 136850.00 270948.00 325138.00 56715.00 75663.00 99925.00 104922.00 187432.00 246005.00 234290.00 445311.00 561092.00 534373.00 109477.00 #VALUE! Unit metre metre metre metre metre Rate 92683.00 121647.00 115855.00 220202.00 277455.00 264243.00 metre metre 48347.00 #VALUE!

metre metre

66411.00 46033.00

metre metre metre metre metre metre metre metre

133751.00 146214.00 193102.00 362208.00 434649.00 860553.00 1032663.00 141159.00

Page 57 of 363

Summary of Rate Analysis


Item No. (ii) (iii) a b (iv) a b c (v) a b c C (i) D (i) 12.19 A (i) (ii) (iii) a (iv) a b (v) a b B (i) (ii) (iii) a b (iv) a b c (v) a b c C (i) D (i) Descriptions Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter5% of cost, if required. Add for dewatering @ Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering on the cost, if required Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the of cost for dewatering, if required Add 5%previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock (12m dia well ) Depth of soft rock strata upto 3m Hard rock (12m dia well ) Depth of hard rock strata upto 3 m Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level. Sandy soil Depth from bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10m upto 20m Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement and Labour . Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. Clayey soil (Twin D Type Well ) Depth below bed level upto 3.0 M Beyond 3m upto 10m depth Beyond 10 m upto 20 m Add 5% for every additional meter depth of sinking over the rate of sinking for the dewatering @ Add forprevious meter5% of cost, if required. Beyond 20m upto 30 m Add 7.5% for every additional meter depth of sinking over the rate of sinking for the of cost for dewatering on the cost, if required Add 5%previous meter Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). Beyond 30m upto 40 m Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter Add 5% of cost for dewatering, if required Add 20% of cost for Kentledge including supports, loading arrangement and Labour). Soft rock (Twin D Type well ) Depth of soft rock strata upto 3m Hard rock (Twin D Type well ) Depth of hard rock strata upto 3 m Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and trained personnel and comprising of compression and decompression chambers, reducers, two air locks separately for men and plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plate forms with railing, arrangement for compression and decompression, electric lighting of 50 V maximum, proper rooms for rest and medical examinations and compliance with safety precautions as per IS:4138, all as filling in wells complete as per drawing and technical specifications Sand per clause1207.6 of MoRTH Specifications. Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting out as per detailed drawing metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre metre 30562.00 32757.00 43262.00 81150.00 97379.00 192800.00 231360.00 35013.00 41585.00 54921.00 57667.00 103016.00 135208.00 128770.00 244750.00 308385.00 293700.00 57225.00 #VALUE! Unit metre metre metre metre metre metre metre metre metre metre metre Rate 202348.00 267237.00 280598.00 501264.00 657909.00 626580.00 1190931.00 1500573.00 1429117.00 267169.00 #VALUE!

12.20

12.21 12.22

cum tonne

#VALUE! #VALUE!

Page 58 of 363

Summary of Rate Analysis


Item No. 12.23 12.24 12.25 12.26 12.27 12.28 12.29 12.30 12.31 12.32 12.33 12.34 12.35 12.36 12.37 12.38 A (i) (ii) B (i) (ii) C (i) (ii) D (i) (ii) 12.39 12.40 12.41 Descriptions Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm) Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm) Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm) Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and & Technical Specification (Pile diameter - 750 mm) Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile diameter - 1000 mm) Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile diameter - 1200 mm) Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile Diameter=500 mm) Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile Diameter=750 mm) Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Pile Diameter=1000 mm) Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Size of pile - 300 mm x 300 mm) Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Size of pile - 500 mm x 500 mm) Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical Specification (Size of pile - 750 mm x 750 mm) Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel column 400 x 250 mm (ISHB Series) ) Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel column 450 x 250 mm (ISHB Series) ) Pile load test on single vertical pile in accordance with IS:2911(Part-IV) Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification RCC Grade M20 Using Concrete Mixer Using Batching Plant, Transit Mixer and Concrete Pump RCC Grade M25 Using concrete mixer. Using Batching Plant, RCC Grade M30 Using concrete mixer. Using Batching Plant, RCC Grade M35 Using concrete mixer. Using Batching Plant, Levelling course for Pile Transit Mixer and Concrete Pump cum cum cum cum cum cum cum cum cum tonne tonne #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! Unit metre metre metre metre metre metre metre metre metre metre metre metre metre metre Rate #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Transit Mixer and Concrete Pump

Transit Mixer and Concrete Pump cap

Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and technical specifications Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and technical specification

Page 59 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-13 SUB-STRUCTURE
13.1 13.2 13.3 13.4 A B C 13.5 A (p) B (p) C (p) Case I Case II (q) Case I Case II (r) Case I Case II D (p) Case I Case II (q) Case I Case II (r) Case I Case II E (p) Case I Case II (q) Case I Case II (r) Case I Case II F (p) Case I Case II (q) Case I Case II (r) Case I Case II G (p) Case I Case II Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and technical specifications Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specificationsmortar (1:3 ) on brick work in sub-structure as per Plastering with cement Technical specificationscement mortar 1:3 for substructure complete as per Stone masonry work in drawing and Technical Specifications Random Rubble Masonry Coursed rubble masonry (first sort ) Ashlar masonry ( first sort ) Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications PCC Grade M15 Height upto 5m PCC Grade M20 Height upto 5m PCC Grade M25 Height upto 5m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height 5m to 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height above 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump PCC Grade M30 Height upto 5m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height 5m to 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height above 10m Using concrete Mixer With Batching Plant, RCC Grade M20 Height upto 5m Using concrete Mixer With Batching Plant, Height 5m to 10m Using concrete Mixer With Batching Plant, Height above 10m Using concrete Mixer With Batching Plant, RCC Grade M25 Height upto 5m Using concrete Mixer With Batching Plant, Height 5m to 10m Using concrete Mixer With Batching Plant, Height above 10m Using concrete Mixer With Batching Plant, RCC Grade M30 Height upto 5m Using concrete Mixer With Batching Plant, cum #VALUE! cum cum cum #VALUE! #VALUE! #VALUE! cum sqm sqm #VALUE! #VALUE! #VALUE!

cum

#VALUE!

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Transit Mixer and Concrete Pump

Transit Mixer and Concrete Pump

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Transit Mixer and Concrete Pump

Transit Mixer and Concrete Pump

Transit Mixer and Concrete Pump

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Transit Mixer and Concrete Pump

Transit Mixer and Concrete Pump

Transit Mixer and Concrete Pump

cum cum

#VALUE! #VALUE!

Page 60 of 363

Summary of Rate Analysis


Item No. (q) Case I Case II (r) Case I Case II H (p) Case I Case II (q) Case I Case II (r) Case I Case II 13.6 13.7 Descriptions Height 5m to 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height above 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump RCC Grade M35 Height upto 5m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height 5m to 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Height above 10m Using concrete Mixer With Batching Plant, Transit Mixer and Concrete Pump Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications Supplying, fitting and placing Mild steel reinforcement complete in substructure as per drawing and technical specification Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification A B Granular material Sandy material Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and technical specification. Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications. Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications. Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications. Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications. Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding on stainless steel plate with mild steel matrix complete including all accessories as per drawing and Technical Specifications. Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, completre assembly to be of cast steel/fabricated structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and approved technical specifications. cum cum cum cum cum cum tonne tonne #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! Unit cum cum cum cum Rate #VALUE! #VALUE! #VALUE! #VALUE!

13.8

each

#VALUE!

13.9

cum cum

#VALUE! #VALUE!

13.10

cum

#VALUE!

13.11

tonne capacity tonne capacity tonne capacity cubic centimetr e tonne capacity

#VALUE!

13.12

#VALUE!

13.13

#VALUE!

13.14

#VALUE!

13.15

#VALUE!

13.16

tonne capacity

#VALUE!

Page 61 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-14 SUPER-STRUCTURE
14.1 A Case I (i) (p) (q) (r) (ii) (p) (q) (r) Case II (i) (p) (q) (r) (ii) (p) (q) (r) B Case I (i) (p) (q) (r) (ii) (p) (q) (r) Case II (i) (p) (q) (r) (ii) (p) (q) (r) C Case I (i) (p) (q) (r) (ii) (p) (q) (r) Case II (i) (p) (q) (r) (ii) (p) (q) Furnishing and Placing Reinforced/Prestressed cement concrete in superstructure as per drawing and Technical Specification RCC Grade M20 Using Concrete Mixer For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m Using Batching Plant, Transit Mixer and Concrete Pump For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m RCC Grade M25 Using Concrete Mixer For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m Using Batching Plant, Transit Mixer and Concrete Pump For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m RCC Grade M 30 Using Concrete Mixer For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m Using Batching Plant, Transit Mixer and Concrete Pump. For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m cum cum cum #VALUE! #VALUE! #VALUE! cum cum cum #VALUE! #VALUE! #VALUE! cum cum cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 62 of 363

Summary of Rate Analysis


Item No. (r) D Case 1 (i) (p) (q) (r) (ii) (p) (q) (r) (iii) (p) (q) (r) Case II (i) (p) (q) (r) (ii) (p) (q) (r) (iii) (p) (q) (r) E Case 1 (i) (p) (q) (r) (ii) (p) (q) (r) Case II (i) (p) (q) (r) (ii) (p) (q) (r) (iii) (p) (q) (r) F (i) (p) (q) (r) (ii) (p) (q) Descriptions Height above 10m RCC/PSC Grade M35 Using concrete mixer. For solid slab super-structure, 18-28% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 23-33% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For box girder and balanced cantilever, 38-58% of cost of concrete. Height upto 5m Height 5m to 10m Height above 10m Using Batching Plant, Transit Mixer and Concrete Pump For solid slab super-structure, 18-28% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 23-33% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For box girder and balanced cantilever, 38-58% of cost of concrete. Height upto 5m Height 5m to 10m Height above 10m PSC Grade M-40 Using concrete mixer. For solid slab super-structure, 20-30% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 25-35% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m Using Batching Plant, Transit Mixer and Concrete Pump For solid slab super-structure, 18-28% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For T-beam & slab, 23-33% of (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For box girder and balanced cantilever, 38-58% of cost of concrete. Height upto 5m Height 5m to 10m Height above 10m PSC Grade M-45 For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c) Height upto 5m Height 5m to 10m Height above 10m For I-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-31% of cost of concrete. Height upto 5m Height 5m to 10m cum cum #VALUE! #VALUE! cum cum cum cum cum cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! cum cum cum cum cum cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! Unit cum Rate #VALUE!

cum cum cum

#VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

cum cum cum

#VALUE! #VALUE! #VALUE!

Page 63 of 363

Summary of Rate Analysis


Item No. (r) (iii) (p) (q) (r) G (i) (p) (q) (r) H (i) (p) (q) (r) 14.2 14.3 14.4 Descriptions Height above 10m For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of concrete. Height upto 5m Height 5m to 10m Height above 10m PSC Grade M-50 For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete Height upto 5m Height 5m to 10m Height above 10m PSC Grade M- 55 For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete Height upto 5m Height 5m to 10m Height above 10m a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting complete as per drawing and Technical Specifications Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.) Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications. Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications. Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification Drainage Spouts complete as per drawing and Technical specification PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification approach slab including reinforcement and Reinforced cement concrete formwork complete as per drawing and Technical specification Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC) (To be taken as per the prevailing market rates.) Precast - pretensioned Girders (Providing, precasting, transportation and placing in position precast pretensioned concrete girders as per drawing and technical specifications) Providing and fixing Helical pipes in voided concrete slabs Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation.) Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. ) Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along the centre line of the plate, all as specified in clause 2604.) Filler joint (i) (ii) Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical Specification. Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical Specification. cum cum cum tonne tonne cum #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! cum cum cum #VALUE! #VALUE! #VALUE! Unit cum cum cum cum Rate #VALUE! #VALUE! #VALUE! #VALUE!

14.5

sqm

#VALUE!

14.6

metre

#VALUE!

14.7

metre

#VALUE!

14.8 14.9 14.10 14.11 14.12 14.13 14.14 14.15

metre each cum cum tonne cum metre

#VALUE! #VALUE! #VALUE! #VALUE!

#VALUE! #VALUE!

14.16

metre

#VALUE!

14.17

metre

#VALUE!

14.18

metre metre

#VALUE! #VALUE!

Page 64 of 363

Summary of Rate Analysis


Item No. (iii) Descriptions Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete as per drawing and technical specifications. Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and 6% bitumen by weight Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings and specifications.) Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel expansion joint, catering to right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH specifications for road & bridge works.) Compression Seal Joint (Providing and laying of compression seal joint consisting of steel armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and vertical movement of 3 mm.) Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.) Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.) Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.) Unit metre Rate #VALUE!

(iv)

metre

#VALUE!

14.19

metre

#VALUE!

14.20

metre

#VALUE!

14.21

metre

#VALUE!

14.22

metre

#VALUE!

14.23

metre

#VALUE!

14.24

metre

#VALUE!

Page 65 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS


15.1 A 15.2 Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification. Boulder laid dry without wire crates. Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra for laps and joints laid with stone boulders weighing not less than 40 kg each.) Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cement content of 250 kg/cum as per IRC: 21-2000.) Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications Stone/Boulder Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free movement of water without creating any uplift head on the pitching.) Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix if cement concrete block have been used for pitching . Rates for toe wall can be adopted from respective clauses depending upon approved design. The rate for excavation for foundation, dry rubble masonry and PCC M15 have been analysed and Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concrete bedding. A B 15.9 15.10 A B 15.11 Rubble stone laid in cement mortar 1:3 Cement Concrete blocks Grade M15 Dry rubble Flooring Curtain wall complete as per drawing and Technical specification Stone masonry in cement mortar (1:3) Cement concrete Grade M15 Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less than 40 kg beyond curtain wall. Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm galvanised steel wire) Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and constructing gabain structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel wire.)

cum cum

#VALUE! #VALUE!

15.3

cum

#VALUE!

15.4 A B 15.5

cum cum cum

#VALUE! #VALUE! #VALUE!

15.6

sqm

#VALUE!

15.7

15.8

cum cum cum cum cum cum

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

15.12

cum

#VALUE!

15.13

cum

#VALUE!

Page 66 of 363

Summary of Rate Analysis


Item No. Descriptions Unit Rate

CHAPTER-16 REPAIR AND REHABILITATION


16.1 Removal of existing cement concrete wearing coat including its disposal complete as per Technical specification without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with all lifts and lead upto 1000m(Thickness 75 mm) Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12 mm thick mastic asphalt including disposal with all lift and lead upto 1000m. Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying with epoxy complete as per Technical specification Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting with Cement/Epoxy Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical specification. A B 16.6 Cement Grout Cement mortar (1:1) Grouting Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter, available in present formulations, to be applied as per instructions of manufacturer and as approved by the Engineer. Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1. Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel reinforcement complete as per Technical specification Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6. Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled concrete Eproxy bonding of new concrete to old concrete Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification Replacement of bearings complete as per Technical specification Rectification of bearings as per Technical specifications Replacement of Expansion Joints complete as per drawings Replacement of damaged concrete railing. Replacement of crash barrier. Replacement of damaged mild steel railing Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired thoroughly, applying cement concrete after erection of proper form work.) Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.) of steel Railing (Repair of steel railing to bring it to the original shape) Repair sqm #VALUE!

16.2 16.3

sqm sqm

#VALUE! #VALUE!

16.4

each

#VALUE!

16.5

kg kg sqm

#VALUE! #VALUE! #VALUE!

16.7 16.8

kg sqm

#VALUE! #VALUE!

16.9

sqm

#VALUE!

16.10 16.11 16.12

sqm sqm tonne

#VALUE! #VALUE! #VALUE!

16.13

tonne

#VALUE!

16.14 16.15 16.16 16.17 16.18 16.19 16.20 16.21 16.22 16.23

tonne each each metre metre metre metre metre metre metre

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 67 of 363

Ref. to Sr No MoRT H 1.1 Spec.

CHAPTER-1 CARRIAGE OF MATERIALS


Description Loading and Unloading of Stone Boulder/Stone aggregates/Sand/Kanker/Moorum. with Placing tipper at loading point, loading front end loader, dumping, turning for return trip, excluding time for haulage and return cum Unit =trip Taking output = 5.5 cum Time required for i) Positioning of tipper at loading ii) Loading by front end loader 1 cum bucket capacity @ 25 cum per hour iii) Maneuvering, reversing, dumping and turning for return iv) Waiting time, unforeseen Total a) Machinery Tipper 5.5 tonnes capacity Front end-loader 1 cum bucket capacity @ 25 cum/hour b) Overhead charges @ 2.244% on c) Contractor's profit @ 5% on (a+b) Cost for 5.5 cum = a+b+c Rate per cum = (a+b+c)/ 5.5 Note Unloading will be by tipping. Loading and Unloading of Boulders by Manual Means Unit = cum Taking output = 5.5 cum a) Labour Mate Mazdoor for loading and unloading b) Machinery Tipper 5.5 tonne capacity c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for5.5 cum = a+b+c+d Rate per cum = (a+b+c+d)/5.5 Note Unloading will be by tipping. Loading and Unloading of Cement or Steel by Manual Means and Stacking. Unit = tonne Taking output = 10 tonnes a) Labour Mate Mazdoor for loading and unloading b) Machinery Truck 10 tonne capacity c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for10 tonnes = a+b+c+d Rate per tonnes = (a+b+c+d)/10 Cost of Haulage Excluding Loading and Haulage of materials by tipper excluding cost of loading, unloading and stacking. Unit = t.km Taking output 10 tonnes load and lead 10 km = 100 t.km Surfaced Road Speed with load : 25 km / hour. Speed while Returning empty :35 km / hour. a) Machinery. Tipper 10 tonne capacity Time taken for onward haulage with Time taken for empty return trip. b) Overhead charges @ 2.244% on c) Contractor's profit @ 5% on (a+b) Page 1 of 363 Unit cum Quantity Rate Rs Remark Cost Rs s/ Input ref.

1 Min 13 Min 2 Min 4 Min 20 Min hour hour 0.330 0.330 497.00 1042.00 164.01 343.86 11.40 25.96 545.23 99.13 99.00 P&MP&M017

say

1.2

day day hour

0.110 0.750 0.750

350.00 180.00 497.00

38.50 135.00 372.75 12.26 27.93 586.43 106.62 107.00

L-12 L-13 P&M-

say

1.3

day day hour

0.080 2.000 2.000

350.00 180.00 497.00

28.00 360.00

L-12 L-13 P&M-

994.00 31.01 70.65 1483.66 148.37 say 148.00

1.4

(i)

hour hour

0.400 0.290

497.00 497.00

198.80 144.13 7.70 17.53

P&MP&M-

Ref. to Sr No MoRT H Spec.

Description cost for 100 t km = a+b+c Rate per t.km = (a+b+c)/100 (ii) Unsurfaced Graveled Road Speed with load: 20 km / hour Speed for empty return trip :30 km / hour a) Machinery Tipper 10 tonnes capacity Time taken for onward haulage with load taken for empty return trip Time b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 368.16 3.68 say 3.70

1.4

hour hour

0.500 0.330

497.00 497.00

248.50 164.01 9.26 21.09 442.86 4.43

P&M048 P&M048

Cost for 100 t .km = a+b+c Rate per t.Km = (a+b+c)/100 say 1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and Choe Bed. Speed with load :10 km / hour Speed while returning empty:15 km / hour a) Machinery Tipper 10 tonnes capacity Time taken for onward haulage Time taken for empty return trip b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) hour hour 1.000 0.670 497.00 497.00

4.40

497.00 332.99 18.62 42.43 891.05 8.91

P&M048 P&M048

Cost for 100 t .km = a+b+c Rate per t.Km = (a+b+c)/100 say 1.5 Hand Broken Stone Aggregates 63 mm Nominal Size Supply of quarried stone, hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained on 50 mm sieve) and stacking as directed Unit = cum Taking output = 1 cum a) Labour Mate Mazdoor b) Material Supply of quarried stone 150 - 200 mm c) size Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per cum = a+b+c+d 1.6 Crushing of Stone Aggregates 13.2 mm Nominal Size. Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone= cum Unit aggregates of 13.2 mm nominal size. Taking Output = 600 cum at crusher location. a) Labour Mate Mazdoor Skilled Mazdoor including breaking of any b) oversize boulder. Material Stone Boulder of size 150 mm and below Page 2 of 363 day day day cum 0.760 2.000 17.000 350.00 180.00 180.00 cum 1.100 input day day 0.060 1.500 350.00 180.00

8.90

21.00 270.00

L-12 L-13

#VALUE! M-002 #VALUE! #VALUE! #VALUE! say #VALUE!

266.00 360.00 3060.00

L-12 L-14 L-13

800.000 input

#VALUE! M-001

Ref. to Sr No MoRT H Spec.

Description c) Machinery Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens loader 1 cum bucket capacity Front end Tipper 5.5 cum capacity d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 600 Rate per cum = (a+b+c+d+e)*0.95/600 Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm. 2. 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 13.2 mm size and balance 5 per cent to the production of stone dust which comes out as stone crusher includes 3. The integrated a by-product.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. P&M028 P&M017 P&M048

Hour Hour Hour

6.000 20.000 20.000

12936.00 77616.00 1042.00 20840.00 497.00 9940.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

1.7

primary and secondary crushing units. Crushing of Stone Aggregates 20 mm Nominal Size Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone= cum Unit aggregates of 20 mm nominal size. Taking Output = 670 cum at crusher location. a) Labour Mate Mazdoor Skilled Mazdoor including breaking of any size b) boulder. Material Stone Boulder of size 150 mm and c) below Machinery Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens loader 1 cum bucket capacity Front end Tipper 5.5 cum capacity d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 670 Rate per cum = (a+b+c+d+e)*0.90/670 Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 20 and 40 mm.per cent 2. 90 of above cost will be attributed to the production of 670 cum of stone aggregates of 20mm size and balance 10 per cent will be for smaller size aggregates and stone dust which comes out as a by-product. 3. The integrated stone crusher includes day day day cum Hour Hour Hour 0.760 2.000 17.000 350.00 180.00 180.00 266.00 360.00 3060.00 L-12 L-14 L-13

800.000 input 6.000 20.000 20.000

#VALUE! M-001 P&M028 P&M017 P&M048

12936.00 77616.00 1042.00 20840.00 497.00 9940.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

1.8

primary and secondary crushing units. Crushing of Stone Aggregates 40 mm Nominal of stone boulders of 150 mm size Crushing Size in an integrated stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain stone= cum Unit aggregates of 40 mm nominal size. Taking Output = 750 cum at crusher location. a) Labour Mate Mazdoor Skilled day day 0.760 2.000 350.00 180.00 266.00 360.00 L-12 L-14

Page 3 of 363

Ref. to Sr No MoRT H Spec. b)

Description Mazdoor Material Stone Boulder of size 150 mm and c) below Machinery Integrated stone crusher of 200 TPH including belt conveyor and vibrating screens loader 1 cum bucket capacity Front end Tipper 5.5 cum capacity d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = (a+b+c+d+e)x0.85 Cost for 750 Rate per cum (a+b+c+d+e)x0.85/750 =

Unit day cum Hour Hour Hour

Quantity 17.000

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 3060.00 L-13 #VALUE! M-001 P&M028 P&M017 P&M048

800.000 input 6.000 20.000 20.000

12936.00 77616.00 1042.00 20840.00 497.00 9940.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm. 2. 85 per cent of above cost will be attributed to the production of 750 cum of stone aggregates of 40mm size and balance 15 per cent will be for smaller size aggregates and stone dust which comes out as a by-product. 3. The integrated stone crusher includes primary and secondary crushing units.

Page 4 of 363

Ref. to Sr No MoRT H 2.1 Spec. 201

CHAPTER-2 SITE CLEARANCE


Description Cutting of Trees, including cutting of Trunks, Branches and Removal Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling= Each Unit in the depression/pit. (i) Girth from 300 mm to 600 mm a) Labour Mate Mazdoors for cutting trees including cutting, refilling, compaction of backfilling and stacking of serviceable b) materials within 1000 metres lead by Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate for each tree = a+b+c+d say day day 0.020 0.600 350.00 180.00 7.00 108.00 L-12 L-13 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

hour

0.100

300.00

30.00 3.25 7.41 155.67 156.00

P&M053

2.1

(ii)

Girth from 600 mm to 900 mm a) Labour Mate Mazdoors for cutting trees including cutting, refilling, compaction of backfilling, and stacking of serviceable b) materials within 1000 metres lead by Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate for each tree = a+b+c+d say day day 0.040 0.900 350.00 180.00 14.00 162.00 L-12 L-13

hour

0.300

300.00

90.00 5.97 13.60 285.57 286.00

P&M053

2.1

(iii)

Girth from 900 mm to 1800 mm a) Labour Mate Mazdoors for cutting trees including cutting, refilling, compaction of backfilling and stacking of serviceable b) materials within 1000 metres Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate for each tree = a+b+c+d say day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13

hour

0.400

300.00

120.00 11.40 25.97 545.37 545.00

P&M053

2.1

(iv)

Girth above 1800 mm a) Labour Mate Mazdoors for cutting trees including cutting, refilling, compaction of backfilling and stacking of serviceable b) materials within 1000 metres Machinery Tractor-trolley c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Rate for each tree = a+b+c+d Clearing Grass and Removal of Rubbish Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area By Manual Means . Unit = Hectare Taking output = 1 Hectare Page 1 of 363

day day

0.160 4.000

350.00 180.00

56.00 720.00

L-12 L-13

hour

0.600

300.00

180.00 21.45 48.87 1026.33 say 1026.00

P&M-

2.2

201

Ref. to Sr No MoRT H Spec.

Description a) Labour Mate Mazdoor b) Overhead charges @ 2.244% on c) Contractor's profit @ 5% on (a+b) Rate per Hectare = a+b+c Clearing and Grubbing Road Land . Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top Unit = Hectare Taking output = 1 Hectare By Manual Means:In area of light jungle a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Hectare = a+b+c+d Rate per

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. L-12 L-13

day day

2.000 50.000

350.00 180.00

700.00 9000.00 217.67 495.88 10413.55 say ###

2.3

201

(i) A

day

6.000

350.00

2100.00

L-12 L-13 P&M053

day 150.000 hour 1.000

180.00 27000.00 300.00 300.00 659.74 1502.99 31562.72 say ###

2.3 (i)

In area of thorny jungle a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Hectare = a+b+c+d Rate per say hour 2.000 300.00 600.00 884.14 2014.21 42298.34 ### P&M053 day 8.000 350.00 2800.00 L-12 L-13 day 200.000 180.00 36000.00

2.3

(ii) A

By Mechanical Means In area of light jungle a) Labour Mate Mazdoor b) Machinery Dozer 80 HP with attachment for removal of trees & stumps Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Hectare = a+b+c+d Rate per say hour hour 10.000 1.000 2400.00 24000.00 300.00 300.00 562.71 1281.94 26920.64 ### P&M014 P&M053 day day 0.160 4.000 350.00 180.00 56.00 720.00 L-12 L-13

2.3 (ii)

In area of thorny jungle a) Labour Mate Mazdoor b) Machinery Dozer 80 HP with attachment for removal of trees & stumps Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Page 2 of 363 hour hour 12.000 1.500 2400.00 28800.00 300.00 450.00 682.49 P&M014 P&M053 day day 0.240 6.000 350.00 180.00 84.00 1080.00 L-12 L-13

Ref. to Sr No MoRT H Spec.

Description d) Contractor's profit @ 5% on (a+b+c) Hectare = a+b+c+d Rate per

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 1554.82 32651.31 ###

say 2.4 202 Dismantling of Structures Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of Unit = cum Taking output = 1.25 cum (i) I Lime /Cement Concrete By Manual Means Lime Concrete, cement concrete grade M-10 and below a) Labour Mate Mazdoor for dismantling and loading b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 (i) B Cement Concrete Grade M-15 & M-20 a) Labour Mate Mazdoor for dismantling and loading b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 (i) C Prestressed / Reinforced concrete grade M-20 & above a) Labour Mate Blacksmith Mazdoor for dismantling, loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 II By Mechanical Means for items No. 202( b)& ( c) Cement Concrete Grade M-15 & M-20 a) Labour Mate Mazdoor for loading and unloading Mazdoor with Pneumatic breaker b) Machinery day day day 0.020 0.250 0.250 350.00 180.00 180.00 cement hour 0.270 300.00 day day 0.050 1.250 350.00 180.00 hour 0.270 300.00 day day 0.040 1.000 350.00 180.00

14.00 180.00 81.00 6.17 14.06 295.23 236.18 236.00

L-12 L-13 P&M053

17.50 225.00 81.00 7.26 16.54 347.30 277.84 278.00

L-12 L-13 P&M053

day day day hour

0.150 0.250 3.500 0.270

350.00 250.00 180.00 300.00

52.50 62.50 630.00 81.00 18.54 42.23 886.76 709.41 709.00

L-12 L-02 L-13 P&M053

7.00 45.00 45.00

L-12 L-13 L-14

Page 3 of 363

Ref. to Sr No MoRT H Spec.

Description Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1.5 cum per hour Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25

Unit hour hour

Quantity 0.670 0.270

Rate Rs

Remark Cost Rs s/ Input ref. 285.00 190.95 P&M001 300.00 81.00 P&M053 8.28 18.86 396.09 316.87 say 317.00

2.4 II

Prestressed / reinforced concrete grade M-20 & above a) Labour Mate

cement

day day day day hour hour

0.050 0.660 0.250 0.250 1.000 0.270

350.00 180.00 250.00 180.00 285.00 300.00

17.50 118.80 62.50 45.00 285.00 81.00 13.68 31.17 654.66 523.73

L-12 L-14 L-02 L-13 P&M001 P&M053

Mazdoor with Pneumatic breaker Blacksmith Mazdoor for loading and unloading b) Machinery Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1.00 cum per hour Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25

say 2.4 (ii) A Dismantling Brick / Tile work In lime mortar a) Labour Mate Mazdoor for dismantling, loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 (ii) B In cement mortar a) Labour Mate Mazdoor for dismantling, loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 (ii) C In mud mortar a) Labour Mate Mazdoor for dismantling and loading b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 hour 0.270 300.00 day day 0.016 0.400 350.00 180.00 day day hour 0.030 0.750 0.270 350.00 180.00 300.00 day day hour 0.020 0.500 0.270 350.00 180.00 300.00

524.00

7.00 90.00 81.00 3.99 9.10 191.09 152.88 153.00

L-12 L-13 P&M053

10.50 135.00 81.00 5.08 11.58 243.16 194.53 195.00

L-12 L-13 P&M053

5.60 72.00 81.00 3.56 8.11 170.27 136.21

L-12 L-13 P&M053

Page 4 of 363

Ref. to Sr No MoRT H Spec. 2.4 (ii) D a) Labour Mate

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. say 136.00

Dry brick pitching or brick soling day day hour 0.014 0.350 0.270 350.00 180.00 300.00 4.90 63.00 81.00 3.34 7.61 159.85 127.88 say 128.00 L-12 L-13 P&M053

Mazdoor for Dismantling, loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 2.4 (iii) A Dismantling Stone Masonry Rubble stone masonry in lime mortar a) Labour Mate Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25

day day hour

0.024 0.600 0.270

350.00 180.00 300.00

8.40 108.00 81.00 4.43 10.09 211.92 169.54

L-12 L-13 P&M053

say 2.4 (iii) B Rubble stone mortar. a) Labour Mate Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 (iii) C Rubble Stone Masonry in mud mortar. a) Labour Mate Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say 2.4 (iii) D Dry rubble masonry a) Labour Mate Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 day day hour 0.018 0.450 0.270 350.00 180.00 300.00 day day hour 0.020 0.500 0.270 350.00 180.00 300.00 masonry in cement day day hour 0.030 0.750 0.270 350.00 180.00 300.00

170.00

10.50 135.00 81.00 5.08 11.58 243.16 194.53 195.00

L-12 L-13 P&M053

7.00 90.00 81.00 3.99 9.10 191.09 152.88 153.00

L-12 L-13 P&M053

6.30 81.00 81.00 3.78 8.60 180.68 144.54

L-12 L-13 P&M053

Page 5 of 363

Ref. to Sr No MoRT H Spec. 2.4 (iii) E

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. say 145.00

Dismantling stone pitching/ dry stone spalls. a) Labour Mate Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say day day hour 0.016 0.400 0.270 350.00 180.00 300.00 5.60 72.00 81.00 3.56 8.11 170.27 136.21 136.00 L-12 L-13 P&M053

2.4 (iii)

Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials. a) Labour Mate Mazdoor for dismantling, loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say day day hour 0.020 0.500 0.270 350.00 180.00 300.00 7.00 90.00 81.00 3.99 9.10 191.09 152.88 153.00 L-12 L-13 P&M053

2.4

(iv)

Wood Work wrought framed and fixed in frames of trusses upto a height of 5 m a) above plinth level Labour Mate Carpenter Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say day day day hour 0.060 0.500 1.000 0.270 350.00 250.00 180.00 300.00 21.00 125.00 180.00 81.00 9.13 20.81 436.94 349.55 350.00 L-12 L-04 L-13 P&M053

2.4

(v)

Steel Work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet. Unit = tonne Taking output = 1 tonne Including dismembering a) Labour Mate Blacksmith Mazdoor for dismantling, loading and Add unloading 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc. b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) tonne = a+b+c+d Rate per say day day day 0.140 1.000 2.500 350.00 250.00 180.00 49.00 250.00 450.00 18.73 L-12 L-02 L-13

hour

0.170

300.00

51.00 18.37 41.85 878.95 879.00

P&M053

2.4 (v)

Excluding dismembering. a) Labour Mate Page 6 of 363 day 0.220 350.00 77.00 L-12

Ref. to Sr No MoRT H Spec.

Description Mazdoor for dismantling, loading and unloading Blacksmith Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc. b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) tonne = a+b+c+d Rate per

Unit day day

Quantity 2.000 0.500

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 360.00 L-13 250.00 125.00 14.05 L-02

hour

0.170

300.00

51.00 14.07 32.06 673.18

P&M053

say 2.4 (v) C Extra over item No( v ) A and( v ) B for cutting rivets. Unit = each Taking output = 10 rivets a) Labour Mate Blacksmith Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) day day day 0.010 0.130 0.130 350.00 250.00 180.00

673.00

3.50 32.50 23.40 1.33 3.04 63.77 6.38

L-12 L-02 L-13

Cost for 10 rivets = a+b+c Rate for each rivet = ( a+b+c)/10 say 2.4 (vi) Scraping of Bricks Dismantled from Brick Work including Stacking. Unit = numbers Taking output = 1000 numbers A In lime/Cement mortar a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) say 2.4 (iv) B In mud mortar a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) say 2.4 (vii) Scraping of Stone from Dismantled Stone Masonry Unit = cum Taking output = 1 cum A In cement and lime mortar a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) say 2.4 (vii) B In Mud mortar a) Labour Mate Page 7 of 363 day 0.010 350.00 day day 0.060 1.400 350.00 180.00 day day 0.050 1.250 350.00 180.00 day day 0.140 3.500 350.00 180.00

6.00

49.00 630.00 15.24 34.71 728.95 729.00

L-12 L-13

Rate per1000 Nos = a+b+c

17.50 225.00 5.44 12.40 260.34 260.00

L-12 L-13

Rate per1000 Nos = a+b+c

21.00 252.00 6.13 13.96 293.08 293.00

L-12 L-13

Rate per cum = a+b+c

3.50

L-12

Ref. to Sr No MoRT H Spec. b) (a) c)

Description Mazdoor Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b)

Unit day

Quantity 0.300

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 54.00 L-13 1.29 2.94 61.73 say 62.00

Rate per cum = a+b+c 2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry Unit = sqm Taking output = 100 sqm a) Labour Mate Mazdoor for scarping and loading b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 100 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/100 say 2.4 (ix) Removing all type of Hume Pipes and Stacking within a lead of 1000 metres including Earthwork and Dismantling of Masonry Works. Unit = metre Taking output = 1 metre A Up to 600 mm dia a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) say 2.4 (ix) B Above 600 mm to 900 mm dia a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) say 2.4 (ix) C Above 900 mm a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) say Note 1. The excavation of earth, dismantling of stone masonry work in head walls and protection works is not included which is to be Credit for retrieved separately. masonry 2. measured and paid stone from work may be taken as per actual availability. Dismantling of Flexible Pavements Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and = cum Unitunserviceable materials separately Taking output = 1 cum Page 8 of 363 day day 0.050 1.200 350.00 180.00 day day 0.030 0.700 350.00 180.00 day day 0.020 0.520 350.00 180.00 hour 0.320 300.00 day day 0.160 4.000 350.00 180.00

56.00 720.00 96.00 19.57 44.58 936.15 9.36 9.00

L-12 L-13 P&M053

7.00 93.60 2.26 5.14 108.00 108.00

L-12 L-13

Rate per metre = a+b+c

10.50 126.00 3.06 6.98 146.54 147.00

L-12 L-13

Rate per metre = a+b+c

17.50 216.00 5.24 11.94 250.68 251.00

L-12 L-13

Rate per metre = a+b+c

2.5

202

Ref. to Sr No MoRT H Spec.

Description I A By Manual Means Bituminous courses a) Labour Mate Mazdoor for dismantling, loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = a+b+c+d Rate per

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.060 1.500 0.380

350.00 180.00 300.00

21.00 270.00 114.00 9.09 20.70 434.79

L-12 L-13 P&M053

say 2.5 I B Granular courses a) Labour Mate Mazdoor for dismantling, loading and b) unloading. Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = a+b+c+d Rate per say 2.5 II A By Mechanical Means Bituminous course a) Labour Mate Mazdoor b) Machinery Tractor-trolley Farm tractor with ripper @ 60 cum per c) hour Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per cum = a+b+c+d say 2.6 202 Dismantling of Cement Concrete Pavement Dismantling of cement concrete pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and Unit = cum Taking output = 1 cum a) Labour Mate Semi skilled mazdoor for operating pneumatic tools Mazdoors as helpers including loading and unloading b) Machinery Air compressor 250 cfm with two leads for pneumatic cutters/ hammers @ 1 cum per hour Tractor-trolley Joint Cutting Machine with 2-3 blades c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = a+b+c+d Rate per hour hour hour 1.000 0.400 285.00 300.00 day day day 0.030 0.500 0.500 350.00 180.00 180.00 hour hour 0.380 0.017 300.00 300.00 day day 0.010 0.300 350.00 180.00 day day hour 0.040 1.000 0.330 350.00 180.00 300.00

435.00

14.00 180.00 99.00 6.57 14.98 314.55 315.00

L-12 L-13 P&M053

3.50 54.00 114.00 5.10 3.96 9.03 189.59 190.00

L-12 L-13 P&M053 P&M055

10.50 90.00 90.00

L-12 L-14 L-13

285.00 120.00 #VALUE! #VALUE! #VALUE! #VALUE!

1.000 input

P&M001 P&M053 P&M083

say #VALUE!

Page 9 of 363

Ref. to Sr No MoRT Description H Spec. Note The above analysis is for removal of complete pavement. In case full depth repair work is required to be done after dismantling, provision of a concrete cutting and sawing machine may be added for 0.25 2.7 202 Dismantling of Guard Rails Dismantling guard rails by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials Unit = running metre separately. Taking output = 1 metre a) Labour Mate Mazdoor including loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metre = a+b+c+d Rate per

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.006 0.150 0.050

350.00 180.00 300.00

2.10 27.00 15.00 0.99 2.25 47.34

L-12 L-13 P&M053

say 2.8 202 Dismantling of Kerb Stone Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre Unit = running metre Taking output = 10 metre a) Labour Mate Mazdoor including loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 say 2.9 202 Dismantling of Kerb Stone Channel Dismantling kerb stone channel by manual means and disposal of dismantled material with all lifts and up to a lead of 1000 metre Unit = running metre Taking output = 10 metre a) Labour Mate Mazdoor including loading and b) unloading Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 say 2.10 202 Dismantling of Kilometre Stone Dismantling of kilometre stone including cutting of earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back filling of pit. Unit = Each Taking output = one KM stone A 5th KM stone day day hour 0.015 0.225 0.300 350.00 180.00 300.00 day day hour 0.010 0.150 0.200 350.00 180.00 300.00

47.00

3.50 27.00 60.00 2.03 4.63 97.16 9.72 10.00

L-12 L-13 P&M053

5.25 40.50 90.00 3.05 6.94 145.74 14.57 15.00

L-12 L-13 P&M053

Page 10 of 363

Ref. to Sr No MoRT H Spec.

Description Quantity of cement concrete = 0.392 cum a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) one 5th KM stone = a+b+c+d Rate for

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.130 0.750 0.150

350.00 180.00 300.00

45.50 135.00 45.00 5.06 11.53 242.09

L-12 L-13 P&M053

say B Ordinary KM Stone Quantity of cement concrete = 0.269 cum a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) one ordinary KM stone = Rate for a+b+c+d C Hectometre Stone Quantity of cement concrete = 0.048 cum a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate for a+b+c+d 2.11 202 one Hectometre stone = say hour 0.020 300.00 day day 0.004 0.100 350.00 180.00 say hour 0.100 300.00 day day 0.020 0.500 350.00 180.00

242.00

7.00 90.00 30.00 2.85 6.49 136.34 136.00

L-12 L-13 P&M053

1.40 18.00 6.00 0.57 1.30 27.27 27.00

L-12 L-13 P&M053

Dismantling of Fencing Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable material and unserviceable material separately. Unit = running metre Taking output = 30 metres a) Labour Mate Mazdoor including loading and unloading Blacksmith b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metres = a+b+c+d Cost for 30 Rate per metre = (a+b+c+d)/30 say hour 0.150 300.00 45.00 18.51 42.18 885.69 29.52 30.00 P&M053 day day day 0.150 3.000 0.750 350.00 180.00 250.00 52.50 540.00 187.50 L-12 L-13 L-02

2.12

202

Dismantling of CI Water Pipe Line Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of concerned department Page 11 of 363

Ref. to Sr No MoRT H Spec.

Description Unit = running metre Taking output = 10 metres a) Labour Mate Mazdoor Plumber b) Machinery Truck 10 tonne capacity Light Crane 3 tonne capacity c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metres = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour

0.090 2.000 0.250 0.250 0.500

350.00 180.00 250.00 497.00 230.00

31.50 360.00 62.50 124.25 115.00 15.56 35.44 744.25 74.42

L-12 L-13 L-02 P&M057 P&M013

say Note The rate analysis does not include any excavation in earth or dismantling of masonry works which are to be measured and paid separately. Removal of Cement Concrete Pipe of Sewer Gutter Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling Unit = running metre Taking output = 10 metres a) Labour Mate Mazdoor b) Machinery Crane 5 tonne capacity Truck flat body 10 tonne c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metres = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 Note The rate analysis does not include any excavation in earth or dismantling of masonry works which are to be measured and paid separately. Removal of Telephone / Electric Poles and Linesof telephone / Electric poles Removal including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1000 = each and stacking the serviceable Unit metres Taking output = 30 Nos a) Labour Mate Mazdoor Electrician/Lineman b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) poles = a+b+c+d Cost for 30 Rate per pole = (a+b+c+d)/30 say hour 1.500 300.00 day day day 0.480 10.000 2.000 350.00 180.00 250.00 hour hour 0.300 input 1.000 497.00 day day 0.100 2.500 350.00 180.00

74.00

2.13

202

35.00 450.00 #VALUE! 497.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13 P&M070 P&M057

say #VALUE!

2.14

202

168.00 1800.00 500.00 450.00 65.48 149.17 3132.65 104.42 104.00

L-12 L-13 L-02 P&M053

Page 12 of 363

Ref. to Sr No MoRT H 3.1 Spec. 301

CHAPTER - 3 EARTH WORK, EROSION CONTROL AND DRAINAGE


Description Excavation in Soil by Manual Means . Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all cumand lead upto1000 metres. Unit = lifts Taking output = 120 cum a) Labour Mate Mazdoor b) Machinery Truck 5.5 cum capacity c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost of 120 cum = a+b+c+d Rate per cum = (a+b+c+d)/120 Note In case there is a situation where the crosssection is of cut and fill and cut earth is required to be used in embankment in the immediate vicinity, the item of carriage in the truck shall be omitted. Rock by Manual Excavation in Ordinary Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres Unit = cum Taking output = 120 cum a) Labour Mate Mazdoor b) Machinery Truck 5.5 cum capacity c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 120 cum = a+b+c+d Rate per cum = (a+b+c+d)/120 Note In case there is a situation where the crosssection is of cut and fill and cut earth is required to be used in embankment in the immediate vicinity, the item of carriage in the truck shall be omitted. Dozer with lead Excavation in Soil with upto 100 metres Excavation for road way in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross Unit = cum Taking output = 180 cum a) Labour Mate Mazdoor b) Machinery Dozer, 80 HP @ 30 cum per hour c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 180 cum = a+b+c+d Rate per cum = (a+b+c+d)/180 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day hour

1.800 45.000 10.000

350.00 180.00 497.00

630.00 8100.00

L-12 L-13 P&M-

4970.00 307.43 700.37 14707.80 122.56 say 123.00

3.2

301

day day hour

2.800 70.000 10.000

350.00 980.00 180.00 12600.00 497.00 4970.00 416.26 948.31 19914.58 165.95 say 166.00

L-12 L-13 P&M-

3.3

301

day day hour

0.080 2.000 6.000

350.00 180.00

28.00 360.00

L-12 L-13 P&M-

2400.00 14400.00 331.84 755.99 15875.83 88.20 say 88.00

3.4

301

Excavation in Ordinary Rock with Dozer with lead upto 100 metres

Page 1 of 363

Ref. to Sr No MoRT H Spec.

Description Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross Unit = cum Taking output = 108 cum a) Labour Mate Mazdoor b) Machinery Dozer, 80 HP @ 20 cum per hour c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 108 cum = a+b+c+d Rate per cum = (a+b+c+d)/108 Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and Unit = cum Taking 0utput = 180 cum a) Labour Mate Mazdoor Driller Blaster b) Machinery Dozer, 80 HP @ 30 cum per hour Air compressor, 250 cfm with 2 jack hammer loader 1 cum bucket capacity Front end Tipper10 tonne capacity c) Materials Gelatin 80 per cent Electric Detonators @ 1 detonator for 2 gelatin sticks of 125 gms each Credit for excavated rock found suitable for use @ 50 per cent quantity blasted d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 180 Rate per cum = (a+b+c+d+e)/180 Note 1. The quality and availability of rock shall be checked before affording credit. 2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced/restricted to that extent. Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with Disposal upto 1000 metres. Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts Unit = cum Taking output = 360 cum a) Labour Mate Page 2 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.120 3.000 6.000

350.00 180.00

42.00 540.00

L-12 L-13 P&M-

2400.00 14400.00 336.20 765.91 16084.11 148.93 say 149.00

3.5

301

day day day day hour hour hour hour kg

0.220 3.000 2.000 0.250 6.000 6.000 6.000 11.250

350.00 180.00 250.00 250.00

77.00 540.00 500.00 62.50

L-12 L-13 L-06 L-03 P&M014 P&M001 P&M017 P&M048

2400.00 14400.00 285.00 1042.00 497.00 1710.00 6252.00 5591.25

63.000 input

#VALUE! M-104

each 252.000 cum 90.000

#VALUE! #VALUE! M-094 / 100 0.00 0.00 M-089 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.6

301

day

0.080

350.00

28.00

L-12

Ref. to Sr No MoRT H Spec. b)

Description Mazdoor Machinery Hydraulic excavator 0.9 cum bucket capacity @ 60 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 360 cum = a+b+c+d Rate per cum = (a+b+c+d)/360

Unit day hour hour

Quantity 2.000 6.000 16.000

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 360.00 L-13 P&M026 P&M048

1942.00 11652.00 497.00 7952.00 448.62 1022.03 21462.65 59.62 say 60.00

3.7

301

Excavation in Ordinary Rock using Hydraulic Excavator CK-90 and Tippers with Disposal upto 1000 metres. Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, Unit = cum Taking output = 240 cum a) Labour Mate Mazdoor b) Machinery hour hour 6.000 11.000 1942.00 11652.00 497.00 5467.00 392.86 894.99 18794.85 78.31 say 78.00 P&M026 P&M048 Hydraulic Excavator 0.90 cum bucket capacity @ 36 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 240 cum = a+b+c+d Rate per cum = (a+b+c+d)/240 day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13

3.8

301

Excavation in Hard Rock (blasting prohibited) for roadway in hard rock Excavation (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of Mechanised Unit = cum Taking output = 36 cum a) Labour Mate Mazdoor for trimming slopes including mannul loading in truck b) Machinery Hydraulic excavator with rock breaker attachment @ 6 cum per hour Tipper 5.5 cum capacity, 1 trip per hour. Credit for excavated rock found suitable for use @ 50 per cent of excavated c) quantity Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = a+b+c+d Cost for 36 Rate per cum = (a+b+c+d)/36 say day day 0.400 10.000 350.00 180.00 140.00 1800.00 L-12 L-13

hour hour cum

6.000 6.500 18.000

1942.00 11652.00 497.00 0.00 3230.50 0.00 377.50 860.00 18060.00 501.67 502.00

P&M026 P&M048 M-089

Note 1. The quality and availability of rock shall be checked before affording credit. 2. In case some rock is issued to the contractor at site, the item of carriage shall be restricted/reduced to that extent. Page 3 of 363

Ref. to Sr No MoRT H Spec. 3.8 B

Description 3.Being small quantity, manual loading will be economical in this case and has been provided Method Manual accordingly. Unit = cum Taking output = 16 cum a) Labour Mate Mazdoor including loading in truck Chiseller Blacksmith b) Machinery Tipper 5.5 cum capacity, 1 trip per hour. Credit for excavated rock found suitable for use @ 50 per cent of excavated c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = a+b+c+d Cost for 16 Rate per cum = (a+b+c+d)/16

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day day hour cum

1.640 16.000 24.000 1.000 2.900 8.000

350.00 180.00 250.00 250.00 497.00 0.00

574.00 2880.00 6000.00 250.00 1441.30 0.00 250.10 569.77 11965.17 747.82

L-12 L-13 L-05 L-02 P&M048 M-089

say Note 1. Credit is considered for 50 per cent of quantity of work. disposal will be done 2. Loading for manually, being small quantity. 3. In case some rock is issued to contractor at site, the item of carriage shall be omitted to the extent of quantity issued to the contractor. Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres Excavation for roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and Unit = cum Taking output = 180 cum a) Labour Mate Mazdoor Driller Blaster b) Machinery Dozer 80 HP @ 30 cum per hour Air compressor, 250 cfm with 2 jack hammers Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity, 4 trips per c) hour. Materials Gelatin 80 per cent Electric Detonators @ 1 detonator for1/2 gelatin stick of 125 gms each Credit for excavated rock found suitable for use @ 50 per cent quantity blasted Add 5 per cent of cost of a+b+c towards muffling arrangements to guard against any rock fly off during d) blasting Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 180 Rate per cum = (a+b+c+d+e)/180 Note 1. Credit is considered for 50 per cent of quantity of blastered rock, if found suitable for construction.. hour hour hour hour kg 6.000 6.000 6.000 8.200 day day day day 0.220 3.000 2.000 0.500 350.00 180.00 250.00 250.00

748.00

3.9

301

77.00 540.00 500.00 125.00

L-12 L-13 L-06 L-03 P&M014 P&M001 P&M017 P&M048

2400.00 14400.00 285.00 1042.00 497.00 1710.00 6252.00 4075.40

63.000 input

#VALUE! M-104

each 1008.000 cum 90.000

#VALUE! #VALUE! M-094 / 100 0.00 0.00 M-089 #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 4 of 363

Ref. to Sr No MoRT H Spec. 3.10 301

Description 2. In case some rock is issued to the contractor at site, the item of carriage shall be reduced to that extent. Excavation in Marshy Soil Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 0.90 cum bucket capacity @ 50 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 300 cum = a+b+c+d Rate per cum = (a+b+c+d)/300

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour hour

0.080 2.000 6.000 13.640

350.00 180.00

28.00 360.00

L-12 L-13 P&M026 P&M048

1942.00 11652.00 497.00 6779.08 422.30 962.07 20203.45 67.34 say 67.00

3.11

301

Removal of Unserviceable Soil with Disposal upto 1000 metres Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305. Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor b) Machinery hour hour 6.000 16.360 1942.00 11652.00 497.00 8130.92 452.64 1031.18 21654.73 60.15 say Note This item does not include replacement of unsuitable soil by suitable soil. Replacement, where required, is to be provided and of Rock Excavation Slopes Presplitting paid separately under clause Carrying out excavation in hard rock to achieve a specified slope of the rock face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead upto 1000 m, Unit = sqm Taking output = 400 sqm( 120 cum considering 300mm average depth of excavation over the existing rock face) a) Labour Mate Mazdoor b) Machinery day day 0.600 15.000 350.00 180.00 210.00 2700.00 L-12 L-13 60.00 P&M026 P&M048 Excavator0.90 cum bucket capacity @ 60 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 360 cum = a+b+c+d Rate per cum = (a+b+c+d)/360 day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13

3.12

303

Page 5 of 363

Ref. to Sr No MoRT H Spec.

Description Air compressor 250 cfm with 2 leads @ 20 cum per hour Dozer, 80 HP Front end loader 1 cum bucket capacity c) Materials Gelatin 80 per cent Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 400 Rate per sqm = (a+b+c+d+e)/400 Note In case blasted rock is used to the contractor against payment for constructed work, the cost of carriage shall be reduced to that extent. Excavation for Structures Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the Ordinary soil Unit = cum Taking output = 10 cum A Manual Means (Depth upto 3 m) a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b)

Unit hour hour hour kg

Quantity 6.000 6.000 6.000

Rate Rs

Remark Cost Rs s/ Input ref. 285.00 1710.00 P&M001 2400.00 14400.00 P&M014 1042.00 6252.00 P&M017 #VALUE! M-104

42.000 input

each 672.000

#VALUE! #VALUE! M-094 / 100 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.13

304

(i)

day day

0.320 8.000

350.00 180.00

112.00 1440.00 34.83 79.34 1666.17 166.62

L-12 L-13

Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 say Note Cost of dewatering may be added where required upto 10 per cent of labour cost Assessment for dewatering shall be made as per site conditions.. B Mechanical Means (Depth upto 3 m) Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 1.0 cum bucket c) capacity Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 300 cum = a+b+c+d Rate per cum = (a+b+c+d)/300 say Note Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made (ii) as per site conditions.. requiring blasting) Ordinary Rock (not A Manual Means (Depth upto 3 m) Unit = cum Taking output = 10 cum a) Labour Mate Page 6 of 363 day 0.400 350.00 hour 6.000 day day 0.320 8.000 350.00 180.00

167.00

3.13 (i)

112.00 1440.00

L-12 L-13 P&M026

1942.00 11652.00 296.30 675.01 14175.31 47.25 47.00

3.13

140.00

L-12

Ref. to Sr No MoRT H Spec. b) (a) c)

Description Mazdoor Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b)

Unit day

Quantity 10.000

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 1800.00 L-13 43.53 99.18 2082.71 208.27 say 208.00

Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 Note Cost of dewatering upto 10 per cent of labour cost may be added, where required. Assessment for dewatering shall be made as per site conditions.. B Mechanical Means Unit = cum Taking output = 216 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 1.0 cum bucket c) capacity Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 216 cum = a+b+c+d Rate per cum = (a+b+c+d)/216 say Note 1.Cost of dewatering upto 5 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per siteof rock, foundation beyond3 m is 2.In case conditions. not dug and hence not included. (iii) Hard Rock ( requiring blasting ) A Manual Means Unit = cum Taking output = 10 cum a) Labour i) Mate ii) Driller iii) Blaster iv) Mazdoor b) Machinery hour 0.667 285.00 Air Compressor 250 cfm with 2 jack hammer @ 15 cum per hour c) Material Blasting Material Detonator electric d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/10 Note Cost of dewatering @ 10 per cent of labour cost may be added, where required Assessment for dewatering shall be made (iv) as perRock ( blasting prohibited ) Hard site conditions. Unit = cum Taking output = 10 cum A Mechanical Means a) Labour Mate Mazdoor day day 0.200 5.000 350.00 180.00 day day day day 0.530 0.840 0.400 12.000 350.00 250.00 250.00 180.00 hour 6.000 day day 0.240 6.000 350.00 180.00

3.13 (ii)

84.00 1080.00

L-12 L-13 P&M026

1942.00 11652.00 287.59 655.18 13758.77 63.70 64.00

3.13

185.50 210.00 100.00 2160.00 190.00

L-12 L-06 L-03 L-13 P&M001

kg each

3.500 input 14.000

#VALUE! M-104

#VALUE! #VALUE! M-094 / 100 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.13

70.00 900.00

L-12 L-13

Page 7 of 363

Ref. to Sr No MoRT H Spec.

Description b) Machinery

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 2850.00 85.72 195.29 4101.01 410.10 P&M001

Air Compressor 250 cfm with 2 leads of pneumatic breaker @ 1 cum per hour c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = a+b+c+d Cost for 10 Rate per cum = (a+b+c+d)/10

hour

10.000

285.00

say Note 1. Cost of dewatering upto 5 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per site conditions. 2.In case of rock, foundation beyond 3 m is not dug and hence not included. (v) Marshy soil Unit = cum Taking output = 10 cum A Manual means ( upto 3 m depth) a) Labour Mate/Supervisor Mazdoor b) c) Machinery Tractor-trolley Material Selected earth for refilling d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 cum = a+b+c+d+e Rate per cum = ( a+b+c+d+e)/ 10 Note 1. Cost of dewatering @ 30 per cent of (a), may be added, where required Assessment for dewatering shall be made as per site conditions. & strutting 20 per cent of (a), 2. Shoring where required may be added 3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item (i) to (iv) for ordinary soil B Mechanical Means a) Labour i) Mate ii) Mazdoor for dressing sides, bottom b) and backfilling Machinery Hydraulic excavator 1.0 cum bucket capacity @ 60 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Material Selected earth for refilling d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/10 Note 1. Cost of dewatering @ 20 per cent of (a+b) may be added, where required 2. Shoring & strutting @ 10 per cent of (a+b), where required may be added 3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item (i) toExisting Granular Surface to 3.14 305.4. Scarifying (iv) for ordinary soil 3 a Depth of 50 mm by Manual Means Page 8 of 363 day day hour hour cum 0.080 2.000 0.170 0.450 350.00 180.00 1942.00 497.00 cum 5.000 input hour 2.670 300.00 day day 0.400 10.000 350.00 180.00

410.00

3.13

140.00 1800.00 801.00

L-12 L-13 P&M053

#VALUE! M-163 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.13 (v)

28.00 360.00 330.14 223.65

L-12 L-13 P&M026 P&M048

5.000 input

#VALUE! M-163 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec.

Description Scarifying the existing granular road surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto = sqm Unit 1000 metres. Taking output = 100 sqm a) Labour Mate Mazdoor including loading and b) unloading Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 100 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/100

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.200 5.000 1.670

350.00 180.00 300.00

70.00 900.00 501.00 33.01 75.20 1579.21 15.79

L-12 L-13 P&M053

say Note In case material is to be reused at site, transportation cost catered above for disposal shall be deleted. 3.15 305.4. Scarifying Existing Bituminous Surface 3 to a depth of 50 mm by Mechanical Means Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto = sqm Unit 1000 metres. Taking output = 100 sqm a) Labour Mate Mazdoor b) Machinery hour hour hour 0.080 0.200 0.230 300.00 1042.00 497.00 Tractor with ripper attachment @ 60 cum per hour Front end loader 1 cum bucket capacity @ 25 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 100 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/100 say 3.16 305 Construction of Embankment with Material obtained from Borrowpits Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting Unit = cum to meet requirement of table Taking output = 100 cum a) Labour Mate Mazdoor b) Machinery Hydraulic Excavator1 cum bucket capacity @ 60 cum per hour Tipper 10 tonne capacity hour tonne.k m 1.670 160 x L 1942.00 4.00 day day 0.040 1.000 350.00 180.00 day day 0.010 0.250 350.00 180.00

16.00

3.50 45.00 24.00 208.40 114.31 8.87 20.20 424.28 4.24 4.00

L-12 L-13 P&M055 P&M017 P&M048

14.00 180.00 3243.14

L-12 L-13

Add 10 per cent of cost of carriage to cover cost of loading and unloading Dozer 80 HP for spreading @ 200 cum per hour Motor grader for grading @ 100 cum per hour Water tanker6 KL capacity Vibratory roller 8 -10 tonnes @ 100 cum per hour Page 9 of 363

P&M026 #VALUE! Lead =input km & P&M#VALUE! 058 1200.00 2254.00 1200.00 1339.00 P&M014 P&M032 P&M060 P&M059

hour hour hour hour

0.500 1.000 4.000 1.000

2400.00 2254.00 300.00 1339.00

Ref. to Sr No MoRT H Spec.

Description c) Material Cost of water Compensation for earth taken from d) private land charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 100 Rate per cum = (a+b+c+d+e)/100 Note Compensation for earth will vary from place to place and will have to be assessed realistically as per particular ground situation. In case earth is available from Govt. land, compensation for earth will not be required. The Embankment with to be Construction of position is required Material Deposited from Roadway Cutting Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table Unit = cum Taking output = 100 cum a) Labour Mate Mazdoor b) Machinery Dozer 80 HP for spreading @ 200 cum per hour Motor grader for grading @ 100 cum per hour Water tanker6 KL capacity Vibratory roller 8-10 tonnes @ 100 cum c) per hour Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Rate for 100 Rate per cum = (a+b+c+d+e)/100 Note In case the earth cutting is done by dozer and pushed for filling in the embankment, the input of dozer in the cost of embankment shall be deleted as the same is already provided in the cost of excavation. However, if the earth is dumped by tippers from roadway cutting, the input Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 Unit = cum Taking output = 100 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator1 cum bucket capacity @ 60 cum per hour Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! M-189 #VALUE! M-092 #VALUE! #VALUE! #VALUE! #VALUE!

KL

24.000 input

cum 100.000 input

say #VALUE!

3.17

305

day day hour hour hour hour KL

0.020 0.500 0.500 1.000 4.000 1.000

350.00 180.00 2400.00 2254.00 300.00 1339.00

7.00 90.00 1200.00 2254.00 1200.00 1339.00

L-12 L-13 P&M014 P&M032 P&M060 P&M059

24.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.18

305

day day hour tonne.k m

0.040 1.000 1.670 175xL

350.00 180.00 1942.00 4.00

14.00 180.00 3243.14

L-12 L-13

Add 10 per cent of cost of carriage to cover cost of loading and unloading Page 10 of 363

P&M026 #VALUE! Lead =input km & P&M#VALUE! 058

Ref. to Sr No MoRT H Spec.

Description Dozer 80 HP for spreading @ 200 cum per hour Motor grader for grading @ 50 cum per hour tanker with 6 km lead Water Vibratory roller 8-10 tonnes @ 80 cum c) per hour Material Cost of water Compensation for earth taken from d) private land charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 100 Rate per cum = (a+b+c+d+e)/100

Unit hour hour hour hour KL

Quantity 0.500 2.000 4.000 1.250

Rate Rs

Remark Cost Rs s/ Input ref. 2400.00 1200.00 P&M014 2254.00 4508.00 P&M032 300.00 1200.00 P&M1339.00 1673.75 060 P&M059

24.000 input

#VALUE! M-189 #VALUE! M-092 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 100.000 input

3.19 305.3. Compacting Original Ground 4 Case-I Compacting original ground supporting sub-grade the ground upto a level of 500 Loosening of mm below the sub-grade level, watered, graded and compacted in layers to meet requirement of table 300-2 for sub-grade construction. Unit = cum Taking output = 600 cum a) Labour Mate Mazdoor b) Machinery Tractor with ripper attachment Motor grader for grading Water tanker 6 KL capacity Vibratory roller 8-10 tonne @ 80 c) cum/hour Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 600 Rate per cum = (a+b+c+d+e)/600 3.19 Case- :Compacting original ground II supporting embankment Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300Unit = cum Taking output = 600 cum a) Labour Mate Mazdoor b) Machinery Tractor with ripper attachment Vibratory road roller 8-10 tonne capacity Water tanker6 KL capacity c) Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = (a+b+c+d+e) Cost for 600 Rate per sqm = (a+b+c+d+e)/600 KL 24.000 input #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Page 11 of 363 hour hour hour 6.000 7.500 4.000 300.00 300.00 1800.00 1200.00 1339.00 10042.50 P&M055 P&M059 P&M060 day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13 hour hour hour hour KL 9.000 6.000 4.000 7.500 300.00 300.00 2700.00 1200.00 2254.00 13524.00 1339.00 10042.50 P&M055 P&M032 P&M060 P&M059 24.000 input #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! day day 0.120 3.000 350.00 180.00 42.00 540.00 L-12 L-13

#VALUE! M-189

Ref. to Sr No MoRT H 3.20 Spec. 305

Description Stripping and Storing Top Soil Stripping, storing of top soil by road side at 15 m internal and re-application on embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to Unit = cum Taking output = 10 cum a) Labour Mate Mazdoor b) Machinery Dozer 80 HP @ 100 cum per hour c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) cum = (a+b+c+d) Cost for 10 Rate per cum = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.200 5.000 0.100

350.00 180.00 2400.00

70.00 900.00 240.00 27.15 61.86 1299.01 129.90

L-12 L-13 P&M014

say 3.21 Stripping, Storing and Re-laying Top Soil from Borrow Areas in Agriculture Fields. Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor b) Machinery Dozer, 80 HP c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 300 cum = (a+b+c+d) Rate per cum = (a+b+c+d)/300 say 3.22 307 Turfing with Sods Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of sods and Unit = sqm Taking output = 100 sqm a) Labour Mate Mazdoor for preparation of ground and fetching of sods b) Machinery Water tanker including watering for 3 months Tractor-trolley c) Material Farm yard manure @ 0.18 cum per 100 sqm at site of work Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 100 sqm = a+b+c+d+e Rate per 100 sqm = (a+b+c+d+e)/100 cum KL 0.180 input 12.000 input day day 0.120 3.000 350.00 180.00 hour 6.000 day day 0.080 2.000 350.00 180.00

130.00

28.00 360.00

L-12 L-13 P&M014

2400.00 14400.00 331.84 755.99 15875.83 52.92 53.00

42.00 540.00

L-12 L-13

hour hour

2.000 1.000

300.00 300.00

600.00 300.00

P&M060 P&M053

#VALUE! M-167 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 12 of 363

Ref. to Sr No MoRT H 3.23 Spec. 308

Description Seeding and Mulching Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of 0.23 litres per sqm and laying and fixing jute netting,sqm Unit = including watering for 3 months all Taking output = 240 sqm a) Labour Mate Mazdoor b) Machinery Water tanker 6 KL capacity including watering for 3 months Tractor-trolley c) Material Seeds Sludge/Farm yard manure @ 0.18 cum per 100 sqm Bitumen Emulsion Jute netting, open weave, 2.5 cm square opening 3 months Cost of water for d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 240 Rate per sqm = (a+b+c+d+e)/240

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour hour kg cum litre KL

0.400 10.000 14.000 2.400

350.00 180.00 300.00 300.00

140.00 1800.00 4200.00 720.00

L-12 L-13 P&M060 P&M053

3.600 input 0.430 input 55.200

#VALUE! M-162 #VALUE! M-167 #VALUE! M-121 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! M-077

sqm 264.000 input 84.000 input

3.24

309

Surface Drains in Soil Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 Unit = metre Taking output = 10 metres A Mechanical means a) Labour Mate Mazdoor for dressing of bed and side of b) drain Machinery Hydraulic Excavator 0.3 cum bucket capacity @ 30 metres per hour c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metres = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 say day day hour 0.010 0.250 0.330 350.00 180.00 1942.00 3.50 45.00 640.86 15.47 35.24 740.07 74.01 74.00 L-12 L-13 P&M026

3.24

Manual Means a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) day day 0.080 2.000 350.00 180.00 28.00 360.00 8.71 19.84 416.54 41.65 say 42.00 L-12 L-13

Cost for 10 metres = a+b+c Rate per metre = (a+b+c)/10 Note Where lining of drain is provided, quantity shall be worked out based on approved design and drawing and priced on rate of cement concrete of approved grade or stone/brick masonryOrdinary Rock be. Surface Drains in as the case may Page 13 of 363

3.25

309

Ref. to Sr No MoRT H Spec.

Description Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309. Excavated material to be used Unit = metre Taking output = 10 metres A Mechanical Means a) Labour Mate Mazdoor for dressing of bed and side of b) drain Machinery Hydraulic Excavator 0.3 cum bucket capacity @ 15 metres per hour c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metres = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.020 0.500 0.670

350.00 180.00 1942.00

7.00 90.00 1301.14 31.37 71.48 1500.99 150.10

L-12 L-13 P&M026

say 3.25 B Manual Means a) Labour Mate Mazdoor b) (a) c) Overhead charges @ 2.244% on Contractor's profit @ 5% on (a+b) day day 0.120 3.000 350.00 180.00

150.00

42.00 540.00 13.06 29.75 624.81 62.48

L-12 L-13

Cost for 10 metres = a+b+c Rate per metre = (a+b+c)/10 say 3.26 309 Surface Drains in Hard Rock Rate per metre may be worked out based on quantity of hard rock as per design. For rate of hard rock cutting, refer relevant item in this chapter Sub-Surface Drains with Perforated Pipe Construction of subsurface drain with perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of excavation 450 x Unit = metre Taking output = 10 metres a) Labour Mate Mazdoor for excavation and back filling c) Material Perforated pipe of cement concrete, internal dia 100 mm Crushed stone as per table 300-3 d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 metres = a+b+c+d+e Rate per metre = (a+b+c+d+e)/10 Note Type of pipe may be modified depending upon provision in design. Aggregate Sub-Surface Drains metre cum 10.000 input 2.400 input day day 0.040 2.000 350.00 180.00

62.00

3.27

309

14.00 360.00

L-12 L-13

#VALUE! M-135 #VALUE! M-012 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.28

309

Page 14 of 363

Ref. to Sr No MoRT H Spec.

Description Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates conforming to table 300-4, excavated material to be Unit = metre utilised in roadway. Taking output = 10 metres a) Labour Mate Mazdoor for excavation and back filling with aggregates b) Material Crushed stone as per table 300-3 c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metres = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day

0.020 1.500

350.00 180.00

7.00 270.00

L-12 L-13

cum

1.350 input

#VALUE! M-012 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.29

309

Underground Drain at Edge of Pavement of an underground drain 1 m x Construction 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads. Unit = Running metre Taking output = one metre a) b) Earthwork in soil RCC work M-20 cum cum 1.500 0.495 70.50 Item No. 3.13 #VALUE! #VALUE! Item 12.8 (C) #VALUE! RCC say #VALUE! 47.00

Rate per metre = (a+b)


3.30 310 Rates for these items may be taken from chapters on earth work and substructures respectively. and Surface Treatment of Preparation Formation. Preparation and surface treatment of formation by removing mud and slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile and rolling with = sqmtonne smooth wheeled roller, Unit 8-10 Taking output = 3500sqm a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Smooth 3 wheeled steel roller 8-10 tonnestanker 6 KL, one trip per hour Water c) Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 3500 Rate per sqm = (a+b+c+d+e)/3500 3.31 313 Construction of Rock fill Embankment Construction of rock fill embankment with broken hard rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top layer with granular material, rolled with vibratory road roller, all complete as per Unit = cum Taking output = 100 cum a) Labour Page 15 of 363 KL hour hour 3.000 3.000 day day day 0.280 6.000 1.000

350.00 180.00 250.00 470.00 300.00

98.00 1080.00 250.00 1410.00 900.00

L-12 L-13 L-15 P&M044 P&M060

18.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec. b)

Description Mate Mazdoor Machinery Dozer 80 HP for spreading @ 200 cum per hour road roller 8-10 tonnes @ 100 Vibratory cum per hour Water tanker 6 KL, one trip per hour c) Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 100 Rate per cum = (a+b+c+d+e)/100 Note It is assumed that rock is available locally at site from roadway cutting. In case, portion of the rock requires breaking to acceptable size of 300 mm, breaking charges will have to be added. EARTH WORK ON HILL ROAD

Unit day day hour hour hour KL

Quantity 0.040 1.500 0.500 1.000 2.000

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 14.00 L-12 180.00 270.00 1200.00 1339.00 600.00 L-13 P&M014 P&M059 P&M060

2400.00 1339.00 300.00

12.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.32

301

Excavation in Hill Area in Soil by Mechanical Means Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto Unit = cum Taking output = 260 cum a) Labour Mate Mazdoor for trimming slopes and helping in excavation etc. b) Machinery Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour loader Front end Tipper 5.5cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 260 cum = a+b+c+d Rate per cum = (a+b+c+d)/260 say Note In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.in Ordinary Excavation in Hilly Area Rock by Mechanical Means not Requiring Blasting. in ordinary rock not Excavation in hilly area requiring blasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000 metres. Unit = cum Taking output = 170 cum a) Labour Mate Mazdoor b) Machinery Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour loader Front end Tipper 5.5cum capacity, 4 trips per c) hour. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Page 16 of 363 hour hour hour 6.000 7.000 7.000 2400.00 14400.00 1042.00 497.00 7294.00 3479.00 599.71 1366.24 P&M014 P&M017 P&M048 day day 0.320 8.000 350.00 180.00 112.00 1440.00 L-12 L-13 day day 0.240 6.000 350.00 180.00 84.00 1080.00 L-12 L-13

hour hour hour

6.000 6.000 12.000

2400.00 14400.00 1042.00 497.00 6252.00 5964.00 623.38 1420.17 29823.55 114.71 115.00

P&M014 P&M017 P&M048

3.33

301

Ref. to Sr No MoRT H Spec.

Description Cost for 170 cum = a+b+c+d Rate per cum = (a+b+c+d)/170

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 28690.94 168.77 169.00

say Note In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision of front end loader and tipper shall be deleted as excavated earth can be disposed off on the valley side. Excavation in Hilly Areas in Hard Rock Requiring Blasting Excavation in hilly areas in hard rock requiring blasting, by mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres. cum Unit = Taking output = 170 cum a) Labour Mate Mazdoor Driller Blaster b) Machinery Dozer 80 HP (D-80 A 12)@ 28.32 cum per compressor 250 cfm with two jack Air hour hammer @ 20 cum per hour Front end loader Tipper 5.5cum capacity, 4 trips per c) hour. Materials Gelatine 80 per cent Electric Detonators @ 1 Detonator for 2 Gelatine sticks of 125 gms each d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 170 Rate per cum = (a+b+c+d+e)/170 Note In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision of front end loader and tipper shall be deleted as excavated earth can be disposed of on the valley side. In case off hill roads, the altitude effect comes into play. The output of men and machines decreases progressively after 2100 m elevation leading to increase in cost . High in Urban Roads been explained in Work altitude effect has The cost of earth work in urban roads inhabited area will be comparatively higher due toThere is mixed traffic on urban roads following reasons: a) like slow moving hand and animal driven carts, rickshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting into traffic jams. This causes loss of working time which may be disruption of b) There is considerable in the range traffic adversely affecting the efficiency of the working parties including machines due to congestion caused by pedestrian traffic, local road side venders, parking of vehicles by the road side, encroachments by the shopkeepers and local shops who make use of the berms of the road in front of these shops and unauthorised conversion of road berms into mini local market The output of c) Cost of living in urban areas is comparatively more resulting into higher wages. Page 17 of 363 hour hour hour hour kg 6.000 5.000 7.000 7.000 day day day day 0.490 10.000 2.000 0.250 350.00 180.00 250.00 250.00

3.34

301

171.50 1800.00 500.00 62.50

L-12 L-13 L-06 L-03 P&M014 P&M001 P&M017 P&M048

2400.00 14400.00 285.00 1042.00 497.00 1425.00 7294.00 3479.00

35.000 input

#VALUE! M-104

each 140.000

#VALUE! #VALUE! M-094 / 100 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.35

Ref. to Sr No MoRT H Spec.

Description d) At times, work is executed during night time due to heavy traffic during day time. This involves extra expenditure by way of making arrangement for lighting and special transport for working parties due to In the light of above, the authorities engaged in preparing the cost estimates may exercise their judgment and cater for the additional cost to the extent of 2 to 3 per cent, keeping in view the severity of factors mentioned above. Supporting details for the extra cost based on the actual Embankment Construction with Flyash/Pond ash available from coal or lignite burning Thermal Plants as waste material. embankment with Flyash Construction of conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in IRC: SP: 58-2001 and as per approved Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor b) Machinery Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum/hour Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

3.36 Sugge stive

day day hour tonne.k m

0.160 4.000 6.000 432 x L

350.00 180.00

56.00 720.00

L-12 L-13

1942.00 11652.00 4.00

Add 10 per cent of cost of carriagefor loading and unloading Dozer 80 HP for spreading @ 200 cum/hour Motor Grader for grading @ 100 cum/hour Water tanker6 KL capacity Vibratory Roller 8-10 tonne @ 100 c) cum/hour Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 360 cum = a+b+c+d Rate per cum = (a+b+c+d)/360 Note 1.As flyash is available free of cost as waste material from Thermal Plants, cost of material has not been added. sides 2.The earth cover on and intermediate layers of earth sandwiching the flyash have not been included in this analysis. The same are required to be provided as per approved design and priced separately as embankment construction.

P&M026 #VALUE! Lead =input km & P&M#VALUE! 058 4320.00 8114.40 3600.00 4820.40 #VALUE! #VALUE! #VALUE! #VALUE! P&M014 P&M032 P&M060 P&M059

hour hour hour hour

1.800 3.600 12.000 3.600

2400.00 2254.00 300.00 1339.00

say #VALUE!

Page 18 of 363

Ref. to Sr No MoRT H 4.1 Spec. 401 A

CHAPTER - 4 SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS


Description Granular Sub-Base with Close Graded Material (Table:- 400-1) Plant Mix Method Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired Unit = cum Taking output = 225 cum (450 tonne) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Wet mix plant @ 75 tonne capacity per Electric generator 125 KVA Water tanker 6 KL capacity 5 km lead with one trip per hour Front end loader 1 cum bucket capacity Tipper 10 tonne Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day day hour hour hour hour tonne.k m

0.400 2.000 8.000

350.00 250.00 180.00

140.00 500.00 1440.00 #VALUE! 5244.00 1350.00

L-12 L-15 L-13

6.000 input 6.000 874.00 4.500 300.00 6.000 450 x L

4.1A

(i)

Add 10 per cent of cost of carriage to cover loading and unloading Motor Grader 110 HP Vibratory roller 8-10 t c) Material Close graded Granular sub-base Material as per table 400-1 For Grading-I Material 53 mm to 9.5 mm @ 50 per cent 9.5 mm to 2.36 mm @ 20 per cent 2.36 mm below @ 30 per cent Cost of water OR For Grading-II Material 26.5 mm to 9.5 mm @ 35 per cent 9.5 mm to 2.36 mm @ 25 per cent 2.36 mm below @ 40 per cent Cost of water OR For Grading-III Material 9.5 mm to 4.75 mm @ 35 per cent 4.75 mm to 2.36 mm @ 12.5 per cent 2.36 mm below @ 52.5 per cent Cost of water Rate per cum for grading-I Material d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225 Rate per cum for grading-II Material d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225 Rate per cum for grading-III Material d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225

P&MP&MP&M060 1042.00 6252.00 P&M4.00 63000.00 Lead =35 km & P&M058 6300.00 2254.00 13524.00 1339.00 8034.00 P&MP&M-

hour hour

6.000 6.000

cum 144.000 input cum 57.000 input cum 86.400 input KL 27.000 input

#VALUE! #VALUE! #VALUE! #VALUE!

M-013 M-017 M-020 M-189

363.1 210.35 145

cum 100.800 input cum 72.000 input cum 115.200 input KL 27.000 input

#VALUE! #VALUE! #VALUE! #VALUE!

M-015 M-017 M-020 M-189

cum 100.800 input cum 36.000 input cum 151.200 input KL 27.000 input

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

M-016 M-018 M-020 M-189

4.1A

(ii)

4.1A

(iii)

Page 1 of 363

Ref. to Sr No MoRT Description H Spec. Note Any one of the grading for material may be adopted as per design 4.1 B By Mix in Place Method Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor skilled Mazdoor unskilled b) Machinery Motor Grader 110 HP @ 50 cum Vibratory roller 8 -10 tonne Tractor - Rotavator Water tanker 6 KL capacity c) Material Close graded Granular sub-base Material as per table 400-1 For Grading-I Material 53 mm to 9.5 mm @ 50 per cent 9.5 mm to 2.36 mm @ 20 per cent 2.36 mm below @ 30 per cent Cost of water OR For Grading-II Material 26.5 mm to 9.5 mm @ 35 per cent 9.5 mm to 2.36 mm @ 25 per cent 2.36 mm below @ 40 per cent Cost of water OR For Grading-III Material 9.5 mm to 4.75 mm @ 35 per cent 4.75 mm to 2.36 mm @ 12.5 per cent 2.36 mm below @ 52.5 per cent Cost of water 4.1B (i) Rate per cum for grading-I Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300 4.1B (ii) Rate per cum for grading-II Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 4.1B (iii) Rate per cum for grading-III Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 Note Any one of the grading for material may be adopted as per design Page 2 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour

0.480 2.000 10.000 6.000 6.000 12.000 3.000

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M032 P&M059 P&M054 P&M060

2254.00 13524.00 1339.00 300.00 300.00 8034.00 3600.00 900.00

cum 192.000 input cum KL 76.000 input 18.000 input cum 115.200 input

#VALUE! M-013 #VALUE! M-017 #VALUE! M-020 #VALUE! M-189

cum 134.400 input cum KL 96.000 input 18.000 input cum 153.600 input

#VALUE! M-015 #VALUE! M-017 #VALUE! M-020 #VALUE! M-189

cum 134.400 input cum KL 48.000 input 18.000 input cum 201.600 input

#VALUE! M-016 #VALUE! M-018 #VALUE! M-020 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H 4.2 Spec. 401

Description Granular Sub-Base with Coarse Graded Material (Table:- 400- 2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Mortar Grader 110 HP @ 50 cum per hour Vibratory roller 8 -10 tonne Water tanker 6 KL capacity c) Material sub-base For coarse graded Granular Materials per table 400-2 For grading-I Material

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour

0.400 2.000 8.000 6.000 6.000 3.000

350.00 250.00 180.00

140.00 500.00 1440.00

L-12 L-15 L-13 P&M032 P&M059 P&M060

2254.00 13524.00 1339.00 300.00 8034.00 900.00

53 mm to 26.5 mm @ 35 per cent 26.5 mm to 4.75 mm @ 45 per cent 2.36 mm below @ 20 per cent (Coarse Sand) water Cost of OR For Grading-II Material 26.5 mm to 4.75 mm @ 75 per cent 2.36 mm below @ 25 per cent Cost of water OR For Grading-III Material 9.5 mm to 4.75 mm @ 66 per cent 2.36 mm below @ 34 per cent Cost of water 4.2 (i) Rate per cum for grading-I Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 4.2 (ii) Rate per cum for grading-II Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 4.2 (iii) Rate per cum for grading-III Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300 Note Any one of the grading for material may be adopted as per design Lime Stabilisation for Improving Subgrade

cum 134.400 input cum 172.800 input cum KL 76.800 input 18.000 input

#VALUE! M-029 #VALUE! M-026 #VALUE! M-022 #VALUE! M-189

cum 288.000 input cum KL 96.000 input 18.000 input

#VALUE! M-026 #VALUE! M-022 #VALUE! M-189

cum 255.000 input cum 129.000 input KL 18.000 input

#VALUE! M-025 #VALUE! M-022 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.3

402

Page 3 of 363

Ref. to Sr No MoRT H Spec.

Description Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil in place with rotavator with 3 per cent slaked lime having minimum content of 70 per cent of CaO, grading with motor grader and compacting with the road roller at OMC to the desired density to form a Unit = cum Taking output = 300 cum (525 tonne) A By Mechanical Means a) Labour Mate Skilled mazdoor for alignment and geometrics spraying lime Mazdoor for b) Machinery Tractor with ripper and rotavator attachments @ 60 cum per hour for ripping and 25 cum per hour for mixing Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne capacity Water tanker 6 KL capacity c) Material Lime at site Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum= a+b+c+d+e Cost for 300 Rate per cum =( a+b+c+d+e)/300 Note * Though vibratory roller is required only for 3 hours as per norms, but the same has to be available at site for 6 hours as other machines for spreading and mixing will take 6 hours. The usage rates of roller have been multiplied with a factor of 0.65. B By Manual Means Unit = cum Taking output = 150 cum (263 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Vibratory roller 8 - 10 tonne @ 60 cum per hour Water tanker 6 KL capacity c) Material Lime at site Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum= a+b+c+d+e Cost for 150 Rate per cum =( a+b+c+d+e)/150

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.360 1.000 8.000 12.000

350.00 250.00 180.00 300.00

126.00 250.00 1440.00 3600.00

L-12 L-15 L-13 P&M055 P&M032 P&M059 P&M060 M-188

hour hour tonne KL

6.000 12.000 15.750

2254.00 13524.00 1339.00 300.00 118.00 5222.10 3600.00 1858.50 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

hour6.00x0.65*

72.000 input

#VALUE! M-189

4.3

day day day hour hour tonne KL

1.440 1.000 35.000 2.500 6.000 8.000

350.00 250.00 180.00 1339.00 300.00 118.00

504.00 250.00 6300.00 3347.50 1800.00 944.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-15 L-13 P&M059 P&M060 M-188

36.000 input

#VALUE! M-189

say #VALUE! 4.4 402 Lime Treated Soil for Sub- Base Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the spread soil in place with rotavator with 3 per cent slaked lime with minimum content of 70 per cent of CaO, grading with motor grader and compacting with the road roller at OMC to achieve at least 98 per cent of the max dry density to form a layer of sub base. Unit = cum

Page 4 of 363

Ref. to Sr No MoRT H Spec.

Description Taking output = 300 cum (525 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Excavator 0.90 cum bucket capacity Tipper for carriage of soil

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour tonne.k m

0.480 2.000 10.000 6.000 525 x L

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M026 Lead

1942.00 11652.00 4.00 #VALUE!

Add 10 per cent of cost of carriage to cover cost of loading and unloading Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne Tractor with Rotavator and blade @ 25 cum per hour 6 KL capacity Water tanker c) Material Lime at site Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum= (a+b+c+d+e)/300 4.5 403 Cement Treated Soil Sub Base/ Base Providing, laying and spreading soil on a prepared sub grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form Unit = cum Taking output = 300 cum (525 tonnes) For 4 per cent quantity of cement by weight of soil a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Excavator 0.90 cum bucket capacity Tipper for carriage of soil

=input km & P&M#VALUE! 058 6.000 6.000 12.000 12.000 15.750 2254.00 13524.00 1339.00 300.00 300.00 118.00 8034.00 3600.00 3600.00 1858.50 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M032 P&M059 P&M054 P&M060 M-188

hour hour hour hour tonne KL

72.000 input

#VALUE! M-189

day day day hour tonne.k m

0.480 2.000 10.000 6.000 525 x L

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M026 Lead

1942.00 11652.00 4.00 #VALUE!

Add 10 per cent of cost of carriage to cover cost of loading and unloading Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne Tractor with Rotavator and blade @ 25 cum per hour Water tanker 6 KL capacity c) Material Cement at site (@ 4 per cent of 525 tonne) Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum= (a+b+c+d+e)/300

=input km & P&M#VALUE! 058 6.000 6.000 12.000 12.000 2254.00 13524.00 1339.00 300.00 300.00 8034.00 3600.00 3600.00 P&M032 P&M059 P&M054 P&M060

hour hour hour hour tonne KL

21.000 input 72.000 input

#VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 5 of 363

Ref. to Sr No MoRT H 4.6 Spec. 403

Description Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ BaseMaterial on a Providing, laying and spreading prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form Unit = cum Taking output = 300 cum (600 tonnes) Quantity of cement assumed as 4 per cent of quantity of crushed rock by weight. a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne Tractor with Rotavator and blade @ 25 cum per hour Water tanker 6 KL capacity c) Material Cement at site @ 4 per cent by weight of crushed aggregate (600 tonne) Grading of material for sub-base course 37.5 mm to 9.5 mm @ 55 per cent 9.5 mm to 4.75 mm @ 20 per cent 4.75 mm to 75 micron @ 25 per cent Cost of water or Grading of material for Base course 37.5 mm to 9.5 mm @ 32.5 per cent 9.5 mm to 4.75 mm @ 5 per cent 4.75 mm to 75 micron @ 62.5 per cent Cost of water

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour tonne

0.480 2.000 10.000 6.000 6.000 12.000 10.000

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M032 P&M059 P&M054 P&M060

2254.00 13524.00 1339.00 300.00 300.00 8034.00 3600.00 3000.00

24.000 input

#VALUE! M-081

cum 211.200 input cum cum KL 76.800 input 96.000 input 60.000 input

#VALUE! M-014 #VALUE! M-025 #VALUE! M-019 #VALUE! M-189

cum 124.800 input cum KL 19.200 input 60.000 input cum 240.000 input

#VALUE! M-028 #VALUE! M-025 #VALUE! M-023 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.6

(i)

For Sub-Base course d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300

4.6

(ii)

For Base course d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note Quantities of aggregates provided under 'c' above are uncompacted quantities. 4.7 404.3. Making 50 mm x 50 mm Furrows 1 Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to the center line of the road and at one metre interval in the existing thin bituminous wearing coarse including sweeping and Unit = sqm disposal of excavated material Taking output = 30 m x 7 m = 210 sqm (i) 25mm deep furrow cutting a) Labour Mate Mazdoor Page 6 of 363 day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13

Ref. to Sr No MoRT H Spec.

Description b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 210 sqm= a+b+c+d Rate per sqm =(a+b+c+d)/210

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 60.00 10.05 22.90 480.96 470.96 P&M053

hour

0.200

300.00

say (ii) 50mm deep furrow cutting a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 210 sqm= a+b+c+d Rate per sqm =(a+b+c+d)/210 say 4.8 404.3. 2 Inverted Choke Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power Unit = cum Taking output = 600 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Motor Grader 110 HP Vibratory roller 8-10 tonnes @ 60 cum per hour Water tanker 6 KL capacity c) Material Screening type 'B' or coarse sand Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 600 Rate per cum = ( a+b+c+d+e)/600 4.9 404 Water Bound Macadam Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse By Manual Means Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery day day 10.080 2.000 350.00 250.00 cum 720.000 input KL 108.000 input hour hour hour 6.000 6.000 18.000 day day day 0.920 2.000 21.000 350.00 250.00 180.00 hour 0.400 300.00 day day 0.160 4.000 350.00 180.00

471.00

56.00 720.00 120.00 20.11 45.81 961.91 951.91 952.00

L-12 L-13 P&M053

322.00 500.00 3780.00

L-12 L-15 L-13 P&M032 P&M059 P&M060

2254.00 13524.00 1339.00 300.00 8034.00 5400.00

#VALUE! M-004 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3528.00 500.00

L-12 L-15 L-13

day 250.000

180.00 45000.00

Page 7 of 363

Ref. to Sr No MoRT H Spec.

Description Vibratory roller 8 - 10 tonne @ 60cum per hour or Smooth 3 wheeled steel roller @ 30cum/hour 6 KL capacity Water tanker

Unit hour hour hour

Quantity 6.000 12.000 24.000

Rate Rs

Remark Cost Rs s/ Input ref. 1339.00 8034.00 P&M059 300.00 7200.00 P&M060

4.9A

(i)

c) Material ( Refer table 400 - 7, 8 & 9 ) Grading-I


Aggregate Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for compacted thickness of 100 mm Stone Screening Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading-I @ 0.30 cum per 10 sqm Binding material Binding Material @ 0.08cum per 10 sqm for grading I material Cost of water cum 28.800 input cum 97.200 input cum 435.600 input

#VALUE! M-039

#VALUE! M-052

cum 108.000 input

#VALUE! M-007

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9A (i)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A (i)

(b)

Using Scrining Type-A (13.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A

(ii)

Grading-II
Aggregate Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm OR Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 57.600 input #VALUE! M-052 #VALUE! M-007 cum 435.600 input #VALUE! M-038

cum 105.590 input

cum

86.400 input

#VALUE! M-051

cum

28.800 input

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9A (ii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Page 8 of 363

Ref. to Sr No MoRT H Spec. 4.9A (ii) (b)

Description OR

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Using Scrining Type-A (13.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A (ii)

(c)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A

(iii)

Grading-III
Aggregate Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 28.800 input #VALUE! M-007 #VALUE! M-189 cum 86.400 input #VALUE! M-051 cum 435.600 input #VALUE! M-036

cum 105.590 input

#VALUE! M-007

KL 144.000 input

4.9A (iii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A (iii)

(b)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 ( Anyone of the aggregate grading, screening and binding material may be used as per design) By Mechanical Means: Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Motor grader 110 HP @ 50cum/hr. for spreading Vibratory roller 8-10 tonnes @ 60cum/hr. or Smooth 3 wheeled steel roller @ 30cum/hr. Page 9 of 363 hour 12.000 hour hour 7.200 6.000 2254.00 16228.80 1339.00 8034.00 P&M032 P&M059 day day day 0.680 2.000 15.000 350.00 250.00 180.00 238.00 500.00 2700.00 L-12 L-15 L-13 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9

Ref. to Sr No MoRT H Spec. 4.9B (i)

Description Water tanker 6 KL capacity

Unit hour

Quantity 24.000

Rate Rs

c) Material ( Refer table 400 - 7, 8 & 9 ) Grading-I


Aggregate Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for compacted thickness of 100 mm Stone Screening Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading-I @ 0.30 cum per 10 sqm Binding material Binding Material @ 0.08cum per 10 sqm for grading I material Cost of water cum cum

Remark Cost Rs s/ Input ref. 300.00 7200.00 P&M060

cum 435.600 input

#VALUE! M-039

97.200 input

#VALUE! M-052

cum 108.000 input

#VALUE! M-007

28.800 input

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9B (i)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B (i)

(b)

Using Scrining Type-A (13.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B

(ii)

Grading-II
Aggregate Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm OR Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 57.600 input #VALUE! M-052 #VALUE! M-007 cum 435.600 input #VALUE! M-038

cum 105.590 input

cum

86.400 input

#VALUE! M-051

cum

28.800 input

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9B (ii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B (ii)

(b)

Using Scrining Type-A (13.2mm agg.)

Page 10 of 363

Ref. to Sr No MoRT H Spec.

Description d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 4.9B (ii) (c)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B

(iii)

Grading-III
Aggregate Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 28.800 input #VALUE! M-007 #VALUE! M-189 cum 86.400 input #VALUE! M-051 cum 435.600 input #VALUE! M-036

cum 105.590 input

#VALUE! M-007

KL 144.000 input

4.9B (iii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B (iii)

(b)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.10

405

Note As three wheeled smooth rollers are also very commonly used, the same has been provided as an alternative. Crushed Cement Concrete Sub-base / Base Breaking and crushing of material obtained by breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM to clause Unit = cum Taking output =360 cum a) Labour Mate Mazdoor skilled Mazdoor for crushing broken cement concrete pavement/slabs into aggregate b) Machinery Page 11 of 363 day day 4.160 2.000 350.00 250.00 1456.00 500.00 L-12 L-15 L-13

day 102.000

180.00 18360.00

Ref. to Sr No MoRT H Spec.

Description Motor Grader,110 HP @ 50 cum/hr. Vibratory roller 8 - 10 tonne@ 60 cum per hour or Smooth 3 wheeled steel roller @ 30cum/hr.loader 1 cum bucket capacity Front end Tipper 10 tonne capacity

Unit hour hour hour hour tonne.k m

Quantity 6.000 6.000 12.000 6.000 720 x L

Rate Rs

Remark Cost Rs s/ Input ref. 2254.00 13524.00 P&M032 1339.00 8034.00 P&M059 1042.00 4.00 6252.00 ### P&M017 Lead

Add 10 per cent of cost of carriage to cover cost of loading and unloading Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour c) Material Material available from dismantled concrete slab after crushing / breaking and only carriage is required to be provided Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 Note 1. It is assumed that dismantling of concrete slab/pavement has been considered separately. Hence same is not added in this analysis. Only labour for crushing the dismantled slab into aggregate has been added. Carriage from stock pile to work site 2. In case of breaking of slabs is done locally without involvement of transportation, the provision of tipper, front end loader and loading/unloading charges may be deleted. 3. As three wheeled smooth steel rollers are commonly in use, the same has been provided as an Coat Over Top Layer of Penetration alternative. Crushed Cement Concrete Base Spraying of bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as Unit = sqm Taking output = 7500 sqm a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Mechanical broom hydraulic @ 1250 sqm per hour self propelled chips spreader Hydraulic Front end loader 1 cum bucket capacity Tipper 10 tonne capacity Vibratory roller 8 -10 tonnes @ 30 cum per hour pressure distributor @ 1750 Bitumen c) sqm per hour Material Crushed stone aggregate 11.2 mm size Bitumen (60-70 grade) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 7500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/7500

=35 km & P&M058 10080.00 12.000 300.00 3600.00 P&M060

hour

KL

72.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.11 405.2

day day day hour hour hour hour hour cum tonne

0.560 2.000 12.000 6.000 6.000 6.000 6.000 4.280

350.00 250.00 180.00 230.00 1042.00 497.00 1339.00 819.00

196.00 500.00 2160.00 1380.00 6252.00 2982.00 5222.10 3505.32

L-12 L-15 L-13 P&M031 P&M025 P&M017 P&M048 P&M059 P&M004

1700.00 10200.00

hour6.00x0.65*

97.500 input 0.250 22129.50

#VALUE! M-051 5532.38 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! M-074

Page 12 of 363

Ref. to Sr No MoRT Description H Spec. Note Though vibratory roller is required only for 3 hours as per norms, the same is required to be available at site for 6 hours to match with other machines. The usage rates of vibratory roller may Macadam 4.12 406 Wet Mix be multiplied with a factor of 0.65. Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in subbase / base course on well prepared surface and compacting with vibratory roller to Unit = cum Taking output = 225 cum (495 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Wet mix plant of 75 tonne hourly capacity Electric generator 125 KVA Front end loader 1 cum capacity Paver finisher Vibratory roller 8 - 10 tonne or Smooth 3 wheeled steel roller @ 8-10 tonnes. Water tanker 6 KL capacity Tipper

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour hour hour hour tonne.k m

0.480 2.000 10.000

350.00 250.00 180.00

168.00 500.00 1800.00 #VALUE! 5244.00 6252.00 5670.00 5222.10

L-12 L-15 L-13 P&M094 P&M018 P&M017 P&M035 P&M059 P&M060 Lead

9.000 input 6.000 6.000 6.000 6x0.65 12.000 3.000 495 x L 300.00 874.00 1042.00 945.00 1339.00

900.00

4.00 69300.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material ( Table 400-11) 45 mm to 22.4 mm@ 30 per cent 22.4 mm to 2.36 mm @ 40 per cent 2.36 mm to 75 micron@ 30 per cent Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225 Note 1. Though vibratory roller is required only for 3 hours as per norms, the same is required to be available at site for 6 hours to match with other machines. The usage rates of vibratory roller may be multiplied with a factor of 0.65 2. As three wheeled smooth steel rollers are commonly in use, the same has been provided as an alternative which can be used if the thickness of individual layer does not exceed 100 mm.. Median and Island with Construction of Soil Taken from Roadway Cutting Construction of Median and Island above road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other structures, spread, cum Unit = graded and compacted as per clause Taking output =21 cum a) Labour Mate Mazdoor b) Machinery Page 13 of 363 day day 0.240 6.000 350.00 180.00 cum cum KL 89.100 input 89.100 input 18.000 input cum 118.800 input

=35 km & P&M058 6930.00

#VALUE! M-034 #VALUE! M-031 #VALUE! M-022 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.13

407

84.00 1080.00

L-12 L-13

Ref. to Sr No MoRT H Spec. c)

Description Water tanker 6 KL with 5 km lead and 1 trip per hour Plate compactor @ 3.5 cum per hour Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 21 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/21 Note This analysis provides for median and island with earthen top. In case the surface is required to be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in the chapter on horticulture. In case granular fill is required to be paved, quantities of paving are required to be calculated as per Construction of Median and Island with Soil Taken from Borrow Areas Construction of median and Island above road level with approved material brought from borrow pits, spread, sloped and compacted as Unit = cum per clause 407 Taking output = 21 cum a) Labour Mate Mazdoor b) Machinery Water tanker with 5 km lead Plate Compactor @ 3.5 cum per hour Hydraulic Excavator1.0 cum bucket capacity @60 cum per hour Tipper 10 tonne capacity

Unit hour hour KL

Quantity 1.000 6.000

Rate Rs

Remark Cost Rs s/ Input ref. 300.00 300.00 P&M060 30.00 180.00 P&M086 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

6.000 input

4.14

407

day day hour hour hour tonne.k m

0.160 4.000 1.000 6.000 0.500 52.5 x L

350.00 180.00 300.00 30.00 1942.00 4.00

56.00 720.00 300.00 180.00 971.00

L-12 L-13 P&M060 P&M-

Add 10 per cent of cost of transportation to cover cost of loading and Material c) unloading Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 21 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/ 21 Note This analysis provides for median and island with earthen top. In case the surface is required to be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in the chapter on horticulture. In case surface finish is of hard type, the same may be provided Construction of Shoulders A. Earthen Shoulders The rate as applicable for construction may be adopted. B. Hard Shoulders sub-grade KL 6.000 input

086 P&M026 #VALUE! Lead =input km & P&M#VALUE! 058

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.15

Rate as applicable for sub-base and or base may be adopted as per approved design. C. Paved shoulders The rate may be adopted as applicable for different layers of pavement depending upon approved design of paved shoulders. Footpaths and Separators

4.16

409

Page 14 of 363

Ref. to Sr No MoRT H Spec.

Description Construction of footpath/separator by providing a 150 mm compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15, over laid with pre-cast concrete tiles in cement mortar 1:3 including of all drainage Unit = sqm provision Taking output = 300 sqm a) Labour Mate Mason Mazdoor b) Machinery Vibratory road roller 8 -10 tonnes @60 cum per hour 6 KL capacity @ 1 trip per Water tanker hour Concrete mixer 0.4/0.28 cum per hour c) Material 53 mm to 26.5 mm @ 35 per cent 26.5 mm to 4.75 mm @ 45 per cent 2.36 mm below @ 20 per cent ii) For cement concrete grade M157.5 cum Aggregate 12 mm crushed @ 0.9 cum of concrete Sand @ 0.45 cum/cum of concrete Cement iii) For cement plaster 1:3 Sand Cement iv) Pre-cast cement concrete tiles Tiles size 300 x 300 mm and 25 mm thick v) RCC pipes Pipes 200 mm dia,2.5 m long for drainage vi) Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 300 Rate per sqm = (a+b+c+d+e)/300 i) For Granular sub base material

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour

1.360 4.000 30.000 0.750 2.000 6.000

350.00 250.00 180.00 1339.00 300.00 165.00

476.00 1000.00 5400.00 1004.25 600.00 990.00

L-12 L-11 L-13 P&M059 P&M060 P&M009

cum cum cum cum cum tonne cum tonne

20.790 input 26.730 input 11.880 input 6.750 input 3.380 input 1.880 input 3.840 input 1.830 input

#VALUE! M-029 #VALUE! M-026 #VALUE! M-022 #VALUE! M-052 #VALUE! M-005 #VALUE! M-081 #VALUE! M-005 #VALUE! M-081 #VALUE! M-184 #VALUE! M-137 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

each 3300.000 input metre KL 22.500 input 12.000 input

4.17

410

Crusher Run Macadam Base Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base Unit = cum Taking output = 360 cum A By Mix in Place Method a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Tractor attached with rotavator @ 25 cum per hour 110 HP Motor grader Vibratory roller 8 -10 tonnes @ 60 cum per hour Water tanker 6 KL capacity c) Material Aggregate at site i) For 53 mm maximum size hour hour hour hour 12.000 6.000 6.000 6.000 300.00 1339.00 300.00 3600.00 8034.00 1800.00 2254.00 13524.00 P&M054 P&M032 P&M059 P&M060 day day day 0.480 2.000 10.000 350.00 250.00 180.00 168.00 500.00 1800.00 L-12 L-15 L-13

Page 15 of 363

Ref. to Sr No MoRT H Spec.

Description 63 mm to 45 mm @ 33 per cent 22.5 mm to 5.6 mm@ 32 per cent Below 5.6 mm @ 35 per cent Cost of water Or ii) For 45 mm maximum size 45 mm to 22.5 mm@ 5 per cent 22.4 mm to 5.6 mm@ 50 per cent Below 5.6 mm@ 45 per cent Cost of water

Unit

Quantity

Rate Rs

cum 157.460 input cum 151.060 input cum 166.680 input KL 36.000 input

Remark Cost Rs s/ Input ref. #VALUE! M-038 #VALUE! M-032 #VALUE! M-030 #VALUE! M-189

cum

24.120 input

#VALUE! M-034 #VALUE! M-032 #VALUE! M-030 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 237.600 input cum 213.480 input KL 36.000 input

4.17 A

(i)

For 53 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360.0cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 or

4.17 A

(ii)

For 45 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360.0cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360

4.17

Note Any one of the aggregate grading may be adopted B By Mixing Plant : Unit = cum Taking output = 225 cum (450 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Wet mix plant @ 75 tonne per hour Electric generator 125 KVA Front end loader 1 cum bucket capacity Motor grader 110 HP Vibratory roller 8 - 10 tonne Water tanker 6 KL capacity Tipper 10 tonne capacity hour hour hour hour hour hour tonne.k m 6.000 input 6.000 6.000 6.000 6.000 3.000 450 x L 874.00 1042.00 1339.00 300.00 #VALUE! 5244.00 6252.00 8034.00 900.00 P&M093 P&M018 P&M017 P&M032 P&M059 P&Mday day day 0.280 1.000 6.000 350.00 250.00 180.00 98.00 250.00 1080.00 L-12 L-15 L-13

2254.00 13524.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material Aggregate at site i) For 53 mm maximum size 63 mm to 45 mm @ 33 per cent 22.5 mm to 5.6 mm@ 32 per cent Below 5.6 mm @ 35 per cent Or ii) For 45 mm maximum size 45 mm to 22.5 mm@ 5 per cent 22.4 mm to 5.6 mm@ 50 per cent Below 5.6 mm@ 45 per cent Cost of water 4.17 B (i) For 53 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Page 16 of 363 cum 15.060 input cum cum 98.400 input 94.410 input

060 Lead =35 km & P&M058 6300.00

#VALUE! M-038 #VALUE! M-032 #VALUE! M-030

cum 104.180 input

#VALUE! M-034 #VALUE! M-032 #VALUE! M-030 #VALUE! M-189 #VALUE! #VALUE!

cum 148.500 input cum 133.430 input KL 18.000 input

Ref. to Sr No MoRT H Spec.

Description Cost for 225cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE! 4.17 B (ii) For 45 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360.0cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 4.18 Sugge stive Lime, Flyash Stabilised Soil Sub-Base Construction of Sub-base using lime - Flyash admixture with granular soil, free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50 per cent, Flyash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + Flyash content ranging between 10 to 30 per cent, the minimum un-confined compressive strength and CBR value after 28 days curing Unit = cum Taking output = 480 cum (720 tonnes, density 1.50 t/cum) Assumptions made Total mass taken for analysis = 720 t Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t= 576 t Soil = 720 -144 576 /1.6 = 360 cum Lime + Flyash = 144 t Ratio Lime 4 : Flyash 16 Lime = 29 kg. Flyash = 115 kg. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Machinery Hydraulic Excavator 0.90 cum bucket capacity @ 60cum/hr. for 360 cum soil Tipper 10T capacity for carriage of soil 576 tonnes hour tonne.k m 6.000 576 x L 1942.00 11652.00 4.00 P&M026 #VALUE! Lead =input km & P&M058 #VALUE! Lead =input km & P&M058 1491.00 P&M048 149.10 hour hour hour hour tonne 6.000 9.600 6.000 12.000 29.000 300.00 1800.00 P&M053 P&M032 P&M059 P&M060 118.00 3422.00 #VALUE! M-188 cum 360.000 input #VALUE! M-092 day day day 0.240 6.000 1.000 350.00 180.00 250.00 84.00 1080.00 250.00 L-12 L-13 L-15 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Tipper 10T capacity for carriage of 115 tonnes Flyash

tonne.k m

115 x L

4.00

Tipper 10T capacity for carriage of 29 tonnes of lime from store to work site Add 10 per cent of cost of carriage to cover cost of loading and unloading Tractor with disc harrows for pulverisation 110 HP @ 50 cum per hour Motor Grader for mixing in-place and grading Vibratory roller 8 - 10 tonne Water tanker 6 KL capacity c) Material Slaked Lime Compensation for earth taken from d) private sourcecharges @ 2.244% on Overhead (a+b+c) Page 17 of 363

hour

3.000

497.00

2254.00 21638.40 1339.00 300.00 8034.00 3600.00

Ref. to Sr No MoRT H Spec.

Description e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 480 Rate per cum= (a+b+c+d+e)/480 Note 1.Compensation for earth will vary from place to place and will have to be assessed realistically as per particular ground situation. In case earth is available from Govt. land, compensation for earth will not be required. Flyashposition been considered be 2.Cost of The has not is required to as same will be available free of cost. Only carriage of Flyash has been provided. 3.Lime + Flyash has been taken as 20 per cent of total mass and ratio of lime and Flyash as 1:4 for estimating purposes. Total quantities will be as per approved design.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE!

say #VALUE!

Page 18 of 363

Ref. to Sr No MoRT H 4.1 Spec. 401 A

CHAPTER - 4 SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS


Description Granular Sub-Base with Close Graded Material (Table:- 400-1) Plant Mix Method Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired Unit = cum Taking output = 225 cum (450 tonne) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Wet mix plant @ 75 tonne capacity per Electric generator 125 KVA Water tanker 6 KL capacity 5 km lead with one trip per hour Front end loader 1 cum bucket capacity Tipper 10 tonne Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day day hour hour hour hour tonne.k m

0.400 2.000 8.000

350.00 250.00 180.00

140.00 500.00 1440.00 #VALUE! 5244.00 1350.00

L-12 L-15 L-13

6.000 input 6.000 874.00 4.500 300.00 6.000 450 x L

4.1A

(i)

Add 10 per cent of cost of carriage to cover loading and unloading Motor Grader 110 HP Vibratory roller 8-10 t c) Material Close graded Granular sub-base Material as per table 400-1 For Grading-I Material 53 mm to 9.5 mm @ 50 per cent 9.5 mm to 2.36 mm @ 20 per cent 2.36 mm below @ 30 per cent Cost of water OR For Grading-II Material 26.5 mm to 9.5 mm @ 35 per cent 9.5 mm to 2.36 mm @ 25 per cent 2.36 mm below @ 40 per cent Cost of water OR For Grading-III Material 9.5 mm to 4.75 mm @ 35 per cent 4.75 mm to 2.36 mm @ 12.5 per cent 2.36 mm below @ 52.5 per cent Cost of water Rate per cum for grading-I Material d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225 Rate per cum for grading-II Material d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225 Rate per cum for grading-III Material d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225

P&MP&MP&M060 1042.00 6252.00 P&M4.00 63000.00 Lead =35 km & P&M058 6300.00 2254.00 13524.00 1339.00 8034.00 P&MP&M-

hour hour

6.000 6.000

cum 144.000 input cum 57.000 input cum 86.400 input KL 27.000 input

#VALUE! #VALUE! #VALUE! #VALUE!

M-013 M-017 M-020 M-189

453.88 262.94 181.25

cum 100.800 input cum 72.000 input cum 115.200 input KL 27.000 input

#VALUE! #VALUE! #VALUE! #VALUE!

M-015 M-017 M-020 M-189

cum 100.800 input cum 36.000 input cum 151.200 input KL 27.000 input

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

M-016 M-018 M-020 M-189

4.1A

(ii)

4.1A

(iii)

Page 19 of 363

Ref. to Sr No MoRT Description H Spec. Note Any one of the grading for material may be adopted as per design 4.1 B By Mix in Place Method Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor skilled Mazdoor unskilled b) Machinery Motor Grader 110 HP @ 50 cum Vibratory roller 8 -10 tonne Tractor - Rotavator Water tanker 6 KL capacity c) Material Close graded Granular sub-base Material as per table 400-1 For Grading-I Material 53 mm to 9.5 mm @ 50 per cent 9.5 mm to 2.36 mm @ 20 per cent 2.36 mm below @ 30 per cent Cost of water OR For Grading-II Material 26.5 mm to 9.5 mm @ 35 per cent 9.5 mm to 2.36 mm @ 25 per cent 2.36 mm below @ 40 per cent Cost of water OR For Grading-III Material 9.5 mm to 4.75 mm @ 35 per cent 4.75 mm to 2.36 mm @ 12.5 per cent 2.36 mm below @ 52.5 per cent Cost of water 4.1B (i) Rate per cum for grading-I Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300 4.1B (ii) Rate per cum for grading-II Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 4.1B (iii) Rate per cum for grading-III Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 Note Any one of the grading for material may be adopted as per design

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour

0.480 2.000 10.000 6.000 6.000 12.000 3.000

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M032 P&M059 P&M054 P&M060

2254.00 13524.00 1339.00 300.00 300.00 8034.00 3600.00 900.00

cum 192.000 input cum KL 76.000 input 18.000 input cum 115.200 input

#VALUE! M-013 #VALUE! M-017 #VALUE! M-020 #VALUE! M-189

cum 134.400 input cum KL 96.000 input 18.000 input cum 153.600 input

#VALUE! M-015 #VALUE! M-017 #VALUE! M-020 #VALUE! M-189

cum 134.400 input cum KL 48.000 input 18.000 input cum 201.600 input

#VALUE! M-016 #VALUE! M-018 #VALUE! M-020 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 20 of 363

Ref. to Sr No MoRT H 4.2 Spec. 401

Description Granular Sub-Base with Coarse Graded Material (Table:- 400- 2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Mortar Grader 110 HP @ 50 cum per hour Vibratory roller 8 -10 tonne Water tanker 6 KL capacity c) Material sub-base For coarse graded Granular Materials per table 400-2 For grading-I Material

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour

0.400 2.000 8.000 6.000 6.000 3.000

350.00 250.00 180.00

140.00 500.00 1440.00

L-12 L-15 L-13 P&M032 P&M059 P&M060

2254.00 13524.00 1339.00 300.00 8034.00 900.00

53 mm to 26.5 mm @ 35 per cent 26.5 mm to 4.75 mm @ 45 per cent 2.36 mm below @ 20 per cent (Coarse Sand) water Cost of OR For Grading-II Material 26.5 mm to 4.75 mm @ 75 per cent 2.36 mm below @ 25 per cent Cost of water OR For Grading-III Material 9.5 mm to 4.75 mm @ 66 per cent 2.36 mm below @ 34 per cent Cost of water 4.2 (i) Rate per cum for grading-I Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 4.2 (ii) Rate per cum for grading-II Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/300 4.2 (iii) Rate per cum for grading-III Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300 Note Any one of the grading for material may be adopted as per design Lime Stabilisation for Improving Subgrade

cum 134.400 input cum 172.800 input cum KL 76.800 input 18.000 input

#VALUE! M-029 #VALUE! M-026 #VALUE! M-022 #VALUE! M-189

cum 288.000 input cum KL 96.000 input 18.000 input

#VALUE! M-026 #VALUE! M-022 #VALUE! M-189

cum 255.000 input cum 129.000 input KL 18.000 input

#VALUE! M-025 #VALUE! M-022 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.3

402

Page 21 of 363

Ref. to Sr No MoRT H Spec.

Description Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil in place with rotavator with 3 per cent slaked lime having minimum content of 70 per cent of CaO, grading with motor grader and compacting with the road roller at OMC to the desired density to form a Unit = cum Taking output = 300 cum (525 tonne) A By Mechanical Means a) Labour Mate Skilled mazdoor for alignment and geometrics spraying lime Mazdoor for b) Machinery Tractor with ripper and rotavator attachments @ 60 cum per hour for ripping and 25 cum per hour for mixing Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne capacity Water tanker 6 KL capacity c) Material Lime at site Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum= a+b+c+d+e Cost for 300 Rate per cum =( a+b+c+d+e)/300 Note * Though vibratory roller is required only for 3 hours as per norms, but the same has to be available at site for 6 hours as other machines for spreading and mixing will take 6 hours. The usage rates of roller have been multiplied with a factor of 0.65. B By Manual Means Unit = cum Taking output = 150 cum (263 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Vibratory roller 8 - 10 tonne @ 60 cum per hour Water tanker 6 KL capacity c) Material Lime at site Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum= a+b+c+d+e Cost for 150 Rate per cum =( a+b+c+d+e)/150

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.360 1.000 8.000 12.000

350.00 250.00 180.00 300.00

126.00 250.00 1440.00 3600.00

L-12 L-15 L-13 P&M055 P&M032 P&M059 P&M060 M-188

hour hour tonne KL

6.000 12.000 15.750

2254.00 13524.00 1339.00 300.00 118.00 5222.10 3600.00 1858.50 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

hour6.00x0.65*

72.000 input

#VALUE! M-189

4.3

day day day hour hour tonne KL

1.440 1.000 35.000 2.500 6.000 8.000

350.00 250.00 180.00 1339.00 300.00 118.00

504.00 250.00 6300.00 3347.50 1800.00 944.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-15 L-13 P&M059 P&M060 M-188

36.000 input

#VALUE! M-189

say #VALUE! 4.4 402 Lime Treated Soil for Sub- Base Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the spread soil in place with rotavator with 3 per cent slaked lime with minimum content of 70 per cent of CaO, grading with motor grader and compacting with the road roller at OMC to achieve at least 98 per cent of the max dry density to form a layer of sub base. Unit = cum

Page 22 of 363

Ref. to Sr No MoRT H Spec.

Description Taking output = 300 cum (525 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Excavator 0.90 cum bucket capacity Tipper for carriage of soil

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour tonne.k m

0.480 2.000 10.000 6.000 525 x L

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M026 Lead

1942.00 11652.00 4.00 #VALUE!

Add 10 per cent of cost of carriage to cover cost of loading and unloading Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne Tractor with Rotavator and blade @ 25 cum per hour 6 KL capacity Water tanker c) Material Lime at site Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum= (a+b+c+d+e)/300 4.5 403 Cement Treated Soil Sub Base/ Base Providing, laying and spreading soil on a prepared sub grade, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form Unit = cum Taking output = 300 cum (525 tonnes) For 4 per cent quantity of cement by weight of soil a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Excavator 0.90 cum bucket capacity Tipper for carriage of soil

=input km & P&M#VALUE! 058 6.000 6.000 12.000 12.000 15.750 2254.00 13524.00 1339.00 300.00 300.00 118.00 8034.00 3600.00 3600.00 1858.50 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M032 P&M059 P&M054 P&M060 M-188

hour hour hour hour tonne KL

72.000 input

#VALUE! M-189

day day day hour tonne.k m

0.480 2.000 10.000 6.000 525 x L

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M026 Lead

1942.00 11652.00 4.00 #VALUE!

Add 10 per cent of cost of carriage to cover cost of loading and unloading Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne Tractor with Rotavator and blade @ 25 cum per hour Water tanker 6 KL capacity c) Material Cement at site (@ 4 per cent of 525 tonne) Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 cum = a+b+c+d+e Rate per cum= (a+b+c+d+e)/300

=input km & P&M#VALUE! 058 6.000 6.000 12.000 12.000 2254.00 13524.00 1339.00 300.00 300.00 8034.00 3600.00 3600.00 P&M032 P&M059 P&M054 P&M060

hour hour hour hour tonne KL

21.000 input 72.000 input

#VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 23 of 363

Ref. to Sr No MoRT H 4.6 Spec. 403

Description Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ BaseMaterial on a Providing, laying and spreading prepared sub grade, adding the designed quantity of cement to the spread Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form Unit = cum Taking output = 300 cum (600 tonnes) Quantity of cement assumed as 4 per cent of quantity of crushed rock by weight. a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Motor Grader 110 HP @ 50 cum per hour Vibratory roller 8 - 10 tonne Tractor with Rotavator and blade @ 25 cum per hour Water tanker 6 KL capacity c) Material Cement at site @ 4 per cent by weight of crushed aggregate (600 tonne) Grading of material for sub-base course 37.5 mm to 9.5 mm @ 55 per cent 9.5 mm to 4.75 mm @ 20 per cent 4.75 mm to 75 micron @ 25 per cent Cost of water or Grading of material for Base course 37.5 mm to 9.5 mm @ 32.5 per cent 9.5 mm to 4.75 mm @ 5 per cent 4.75 mm to 75 micron @ 62.5 per cent Cost of water

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour tonne

0.480 2.000 10.000 6.000 6.000 12.000 10.000

350.00 250.00 180.00

168.00 500.00 1800.00

L-12 L-15 L-13 P&M032 P&M059 P&M054 P&M060

2254.00 13524.00 1339.00 300.00 300.00 8034.00 3600.00 3000.00

24.000 input

#VALUE! M-081

cum 211.200 input cum cum KL 76.800 input 96.000 input 60.000 input

#VALUE! M-014 #VALUE! M-025 #VALUE! M-019 #VALUE! M-189

cum 124.800 input cum KL 19.200 input 60.000 input cum 240.000 input

#VALUE! M-028 #VALUE! M-025 #VALUE! M-023 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.6

(i)

For Sub-Base course d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300

4.6

(ii)

For Base course d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 300 Rate per cum = (a+b+c+d+e)/300 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note Quantities of aggregates provided under 'c' above are uncompacted quantities. 4.7 404.3. Making 50 mm x 50 mm Furrows 1 Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to the center line of the road and at one metre interval in the existing thin bituminous wearing coarse including sweeping and Unit = sqm disposal of excavated material Taking output = 30 m x 7 m = 210 sqm (i) 25mm deep furrow cutting a) Labour Mate Mazdoor Page 24 of 363 day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13

Ref. to Sr No MoRT H Spec.

Description b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 210 sqm= a+b+c+d Rate per sqm =(a+b+c+d)/210

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 60.00 10.05 22.90 480.96 470.96 P&M053

hour

0.200

300.00

say (ii) 50mm deep furrow cutting a) Labour Mate Mazdoor b) Machinery Tractor-trolley c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 210 sqm= a+b+c+d Rate per sqm =(a+b+c+d)/210 say 4.8 404.3. 2 Inverted Choke Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power Unit = cum Taking output = 600 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Motor Grader 110 HP Vibratory roller 8-10 tonnes @ 60 cum per hour Water tanker 6 KL capacity c) Material Screening type 'B' or coarse sand Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 600 Rate per cum = ( a+b+c+d+e)/600 4.9 404 Water Bound Macadam Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse By Manual Means Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery day day 10.080 2.000 350.00 250.00 cum 720.000 input KL 108.000 input hour hour hour 6.000 6.000 18.000 day day day 0.920 2.000 21.000 350.00 250.00 180.00 hour 0.400 300.00 day day 0.160 4.000 350.00 180.00

471.00

56.00 720.00 120.00 20.11 45.81 961.91 951.91 952.00

L-12 L-13 P&M053

322.00 500.00 3780.00

L-12 L-15 L-13 P&M032 P&M059 P&M060

2254.00 13524.00 1339.00 300.00 8034.00 5400.00

#VALUE! M-004 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3528.00 500.00

L-12 L-15 L-13

day 250.000

180.00 45000.00

Page 25 of 363

Ref. to Sr No MoRT H Spec.

Description Vibratory roller 8 - 10 tonne @ 60cum per hour or Smooth 3 wheeled steel roller @ 30cum/hour 6 KL capacity Water tanker

Unit hour hour hour

Quantity 6.000 12.000 24.000

Rate Rs

Remark Cost Rs s/ Input ref. 1339.00 8034.00 P&M059 300.00 7200.00 P&M060

4.9A

(i)

c) Material ( Refer table 400 - 7, 8 & 9 ) Grading-I


Aggregate Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for compacted thickness of 100 mm Stone Screening Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading-I @ 0.30 cum per 10 sqm Binding material Binding Material @ 0.08cum per 10 sqm for grading I material Cost of water cum 28.800 input cum 97.200 input cum 435.600 input

#VALUE! M-039

#VALUE! M-052

cum 108.000 input

#VALUE! M-007

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9A (i)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A (i)

(b)

Using Scrining Type-A (13.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A

(ii)

Grading-II
Aggregate Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm OR Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 57.600 input #VALUE! M-052 #VALUE! M-007 cum 435.600 input #VALUE! M-038

cum 105.590 input

cum

86.400 input

#VALUE! M-051

cum

28.800 input

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9A (ii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Page 26 of 363

Ref. to Sr No MoRT H Spec. 4.9A (ii) (b)

Description OR

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Using Scrining Type-A (13.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A (ii)

(c)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A

(iii)

Grading-III
Aggregate Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 28.800 input #VALUE! M-007 #VALUE! M-189 cum 86.400 input #VALUE! M-051 cum 435.600 input #VALUE! M-036

cum 105.590 input

#VALUE! M-007

KL 144.000 input

4.9A (iii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9A (iii)

(b)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 ( Anyone of the aggregate grading, screening and binding material may be used as per design) By Mechanical Means: Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Motor grader 110 HP @ 50cum/hr. for spreading Vibratory roller 8-10 tonnes @ 60cum/hr. or Smooth 3 wheeled steel roller @ 30cum/hr. Page 27 of 363 hour 12.000 hour hour 7.200 6.000 2254.00 16228.80 1339.00 8034.00 P&M032 P&M059 day day day 0.680 2.000 15.000 350.00 250.00 180.00 238.00 500.00 2700.00 L-12 L-15 L-13 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9

Ref. to Sr No MoRT H Spec. 4.9B (i)

Description Water tanker 6 KL capacity

Unit hour

Quantity 24.000

Rate Rs

c) Material ( Refer table 400 - 7, 8 & 9 ) Grading-I


Aggregate Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for compacted thickness of 100 mm Stone Screening Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading-I @ 0.30 cum per 10 sqm Binding material Binding Material @ 0.08cum per 10 sqm for grading I material Cost of water cum cum

Remark Cost Rs s/ Input ref. 300.00 7200.00 P&M060

cum 435.600 input

#VALUE! M-039

97.200 input

#VALUE! M-052

cum 108.000 input

#VALUE! M-007

28.800 input

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9B (i)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B (i)

(b)

Using Scrining Type-A (13.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B

(ii)

Grading-II
Aggregate Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm OR Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 57.600 input #VALUE! M-052 #VALUE! M-007 cum 435.600 input #VALUE! M-038

cum 105.590 input

cum

86.400 input

#VALUE! M-051

cum

28.800 input

#VALUE! M-007 #VALUE! M-189

KL 144.000 input

4.9B (ii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B (ii)

(b)

Using Scrining Type-A (13.2mm agg.)

Page 28 of 363

Ref. to Sr No MoRT H Spec.

Description d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 4.9B (ii) (c)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 360 Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B

(iii)

Grading-III
Aggregate Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm OR Crushable type such as Moorum or Gravel for grading II &III @ 0.22 cum per 10 sqm Binding material Binding Material @ 0.06cum per 10 sqm for grading II material Cost of water cum 28.800 input #VALUE! M-007 #VALUE! M-189 cum 86.400 input #VALUE! M-051 cum 435.600 input #VALUE! M-036

cum 105.590 input

#VALUE! M-007

KL 144.000 input

4.9B (iii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 OR #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.9B (iii)

(b)

Using Scrining Type-B (11.2mm agg.)


d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.10

405

Note As three wheeled smooth rollers are also very commonly used, the same has been provided as an alternative. Crushed Cement Concrete Sub-base / Base Breaking and crushing of material obtained by breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM to clause Unit = cum Taking output =360 cum a) Labour Mate Mazdoor skilled Mazdoor for crushing broken cement concrete pavement/slabs into aggregate b) Machinery Page 29 of 363 day day 4.160 2.000 350.00 250.00 1456.00 500.00 L-12 L-15 L-13

day 102.000

180.00 18360.00

Ref. to Sr No MoRT H Spec.

Description Motor Grader,110 HP @ 50 cum/hr. Vibratory roller 8 - 10 tonne@ 60 cum per hour or Smooth 3 wheeled steel roller @ 30cum/hr.loader 1 cum bucket capacity Front end Tipper 10 tonne capacity

Unit hour hour hour hour tonne.k m

Quantity 6.000 6.000 12.000 6.000 720 x L

Rate Rs

Remark Cost Rs s/ Input ref. 2254.00 13524.00 P&M032 1339.00 8034.00 P&M059 1042.00 4.00 6252.00 ### P&M017 Lead

Add 10 per cent of cost of carriage to cover cost of loading and unloading Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour c) Material Material available from dismantled concrete slab after crushing / breaking and only carriage is required to be provided Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 Note 1. It is assumed that dismantling of concrete slab/pavement has been considered separately. Hence same is not added in this analysis. Only labour for crushing the dismantled slab into aggregate has been added. Carriage from stock pile to work site 2. In case of breaking of slabs is done locally without involvement of transportation, the provision of tipper, front end loader and loading/unloading charges may be deleted. 3. As three wheeled smooth steel rollers are commonly in use, the same has been provided as an Coat Over Top Layer of Penetration alternative. Crushed Cement Concrete Base Spraying of bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as Unit = sqm Taking output = 7500 sqm a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Mechanical broom hydraulic @ 1250 sqm per hour self propelled chips spreader Hydraulic Front end loader 1 cum bucket capacity Tipper 10 tonne capacity Vibratory roller 8 -10 tonnes @ 30 cum per hour pressure distributor @ 1750 Bitumen c) sqm per hour Material Crushed stone aggregate 11.2 mm size Bitumen (60-70 grade) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 7500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/7500

=35 km & P&M058 10080.00 12.000 300.00 3600.00 P&M060

hour

KL

72.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.11 405.2

day day day hour hour hour hour hour cum tonne

0.560 2.000 12.000 6.000 6.000 6.000 6.000 4.280

350.00 250.00 180.00 230.00 1042.00 497.00 1339.00 819.00

196.00 500.00 2160.00 1380.00 6252.00 2982.00 5222.10 3505.32

L-12 L-15 L-13 P&M031 P&M025 P&M017 P&M048 P&M059 P&M004

1700.00 10200.00

hour6.00x0.65*

97.500 input 0.250 22129.50

#VALUE! M-051 5532.38 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! M-074

Page 30 of 363

Ref. to Sr No MoRT Description H Spec. Note Though vibratory roller is required only for 3 hours as per norms, the same is required to be available at site for 6 hours to match with other machines. The usage rates of vibratory roller may Macadam 4.12 406 Wet Mix be multiplied with a factor of 0.65. Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in subbase / base course on well prepared surface and compacting with vibratory roller to Unit = cum Taking output = 225 cum (495 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Wet mix plant of 75 tonne hourly capacity Electric generator 125 KVA Front end loader 1 cum capacity Paver finisher Vibratory roller 8 - 10 tonne or Smooth 3 wheeled steel roller @ 8-10 tonnes. Water tanker 6 KL capacity Tipper

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour hour hour hour tonne.k m

0.480 2.000 10.000

350.00 250.00 180.00

168.00 500.00 1800.00 #VALUE! 5244.00 6252.00 5670.00 5222.10

L-12 L-15 L-13 P&M094 P&M018 P&M017 P&M035 P&M059 P&M060 Lead

9.000 input 6.000 6.000 6.000 6x0.65 12.000 3.000 495 x L 300.00 874.00 1042.00 945.00 1339.00

900.00

4.00 69300.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material ( Table 400-11) 45 mm to 22.4 mm@ 30 per cent 22.4 mm to 2.36 mm @ 40 per cent 2.36 mm to 75 micron@ 30 per cent Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 225 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225 Note 1. Though vibratory roller is required only for 3 hours as per norms, the same is required to be available at site for 6 hours to match with other machines. The usage rates of vibratory roller may be multiplied with a factor of 0.65 2. As three wheeled smooth steel rollers are commonly in use, the same has been provided as an alternative which can be used if the thickness of individual layer does not exceed 100 mm.. Median and Island with Construction of Soil Taken from Roadway Cutting Construction of Median and Island above road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other structures, spread, cum Unit = graded and compacted as per clause Taking output =21 cum a) Labour Mate Mazdoor b) Machinery Page 31 of 363 day day 0.240 6.000 350.00 180.00 cum cum KL 89.100 input 89.100 input 18.000 input cum 118.800 input

=35 km & P&M058 6930.00

#VALUE! M-034 #VALUE! M-031 #VALUE! M-022 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.13

407

84.00 1080.00

L-12 L-13

Ref. to Sr No MoRT H Spec. c)

Description Water tanker 6 KL with 5 km lead and 1 trip per hour Plate compactor @ 3.5 cum per hour Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 21 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/21 Note This analysis provides for median and island with earthen top. In case the surface is required to be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in the chapter on horticulture. In case granular fill is required to be paved, quantities of paving are required to be calculated as per Construction of Median and Island with Soil Taken from Borrow Areas Construction of median and Island above road level with approved material brought from borrow pits, spread, sloped and compacted as Unit = cum per clause 407 Taking output = 21 cum a) Labour Mate Mazdoor b) Machinery Water tanker with 5 km lead Plate Compactor @ 3.5 cum per hour Hydraulic Excavator1.0 cum bucket capacity @60 cum per hour Tipper 10 tonne capacity

Unit hour hour KL

Quantity 1.000 6.000

Rate Rs

Remark Cost Rs s/ Input ref. 300.00 300.00 P&M060 30.00 180.00 P&M086 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

6.000 input

4.14

407

day day hour hour hour tonne.k m

0.160 4.000 1.000 6.000 0.500 52.5 x L

350.00 180.00 300.00 30.00 1942.00 4.00

56.00 720.00 300.00 180.00 971.00

L-12 L-13 P&M060 P&M-

Add 10 per cent of cost of transportation to cover cost of loading and Material c) unloading Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 21 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/ 21 Note This analysis provides for median and island with earthen top. In case the surface is required to be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in the chapter on horticulture. In case surface finish is of hard type, the same may be provided Construction of Shoulders A. Earthen Shoulders The rate as applicable for construction may be adopted. B. Hard Shoulders sub-grade KL 6.000 input

086 P&M026 #VALUE! Lead =input km & P&M#VALUE! 058

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

4.15

Rate as applicable for sub-base and or base may be adopted as per approved design. C. Paved shoulders The rate may be adopted as applicable for different layers of pavement depending upon approved design of paved shoulders. Footpaths and Separators

4.16

409

Page 32 of 363

Ref. to Sr No MoRT H Spec.

Description Construction of footpath/separator by providing a 150 mm compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15, over laid with pre-cast concrete tiles in cement mortar 1:3 including of all drainage Unit = sqm provision Taking output = 300 sqm a) Labour Mate Mason Mazdoor b) Machinery Vibratory road roller 8 -10 tonnes @60 cum per hour 6 KL capacity @ 1 trip per Water tanker hour Concrete mixer 0.4/0.28 cum per hour c) Material 53 mm to 26.5 mm @ 35 per cent 26.5 mm to 4.75 mm @ 45 per cent 2.36 mm below @ 20 per cent ii) For cement concrete grade M157.5 cum Aggregate 12 mm crushed @ 0.9 cum of concrete Sand @ 0.45 cum/cum of concrete Cement iii) For cement plaster 1:3 Sand Cement iv) Pre-cast cement concrete tiles Tiles size 300 x 300 mm and 25 mm thick v) RCC pipes Pipes 200 mm dia,2.5 m long for drainage vi) Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 300 Rate per sqm = (a+b+c+d+e)/300 i) For Granular sub base material

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour

1.360 4.000 30.000 0.750 2.000 6.000

350.00 250.00 180.00 1339.00 300.00 165.00

476.00 1000.00 5400.00 1004.25 600.00 990.00

L-12 L-11 L-13 P&M059 P&M060 P&M009

cum cum cum cum cum tonne cum tonne

20.790 input 26.730 input 11.880 input 6.750 input 3.380 input 1.880 input 3.840 input 1.830 input

#VALUE! M-029 #VALUE! M-026 #VALUE! M-022 #VALUE! M-052 #VALUE! M-005 #VALUE! M-081 #VALUE! M-005 #VALUE! M-081 #VALUE! M-184 #VALUE! M-137 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

each 3300.000 input metre KL 22.500 input 12.000 input

4.17

410

Crusher Run Macadam Base Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles, spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base Unit = cum Taking output = 360 cum A By Mix in Place Method a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Tractor attached with rotavator @ 25 cum per hour 110 HP Motor grader Vibratory roller 8 -10 tonnes @ 60 cum per hour Water tanker 6 KL capacity c) Material Aggregate at site i) For 53 mm maximum size hour hour hour hour 12.000 6.000 6.000 6.000 300.00 1339.00 300.00 3600.00 8034.00 1800.00 2254.00 13524.00 P&M054 P&M032 P&M059 P&M060 day day day 0.480 2.000 10.000 350.00 250.00 180.00 168.00 500.00 1800.00 L-12 L-15 L-13

Page 33 of 363

Ref. to Sr No MoRT H Spec.

Description 63 mm to 45 mm @ 33 per cent 22.5 mm to 5.6 mm@ 32 per cent Below 5.6 mm @ 35 per cent Cost of water Or ii) For 45 mm maximum size 45 mm to 22.5 mm@ 5 per cent 22.4 mm to 5.6 mm@ 50 per cent Below 5.6 mm@ 45 per cent Cost of water

Unit

Quantity

Rate Rs

cum 157.460 input cum 151.060 input cum 166.680 input KL 36.000 input

Remark Cost Rs s/ Input ref. #VALUE! M-038 #VALUE! M-032 #VALUE! M-030 #VALUE! M-189

cum

24.120 input

#VALUE! M-034 #VALUE! M-032 #VALUE! M-030 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 237.600 input cum 213.480 input KL 36.000 input

4.17 A

(i)

For 53 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360.0cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 or

4.17 A

(ii)

For 45 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360.0cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360

4.17

Note Any one of the aggregate grading may be adopted B By Mixing Plant : Unit = cum Taking output = 225 cum (450 tonnes) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Wet mix plant @ 75 tonne per hour Electric generator 125 KVA Front end loader 1 cum bucket capacity Motor grader 110 HP Vibratory roller 8 - 10 tonne Water tanker 6 KL capacity Tipper 10 tonne capacity hour hour hour hour hour hour tonne.k m 6.000 input 6.000 6.000 6.000 6.000 3.000 450 x L 874.00 1042.00 1339.00 300.00 #VALUE! 5244.00 6252.00 8034.00 900.00 P&M093 P&M018 P&M017 P&M032 P&M059 P&Mday day day 0.280 1.000 6.000 350.00 250.00 180.00 98.00 250.00 1080.00 L-12 L-15 L-13

2254.00 13524.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material Aggregate at site i) For 53 mm maximum size 63 mm to 45 mm @ 33 per cent 22.5 mm to 5.6 mm@ 32 per cent Below 5.6 mm @ 35 per cent Or ii) For 45 mm maximum size 45 mm to 22.5 mm@ 5 per cent 22.4 mm to 5.6 mm@ 50 per cent Below 5.6 mm@ 45 per cent Cost of water 4.17 B (i) For 53 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Page 34 of 363 cum 15.060 input cum cum 98.400 input 94.410 input

060 Lead =35 km & P&M058 6300.00

#VALUE! M-038 #VALUE! M-032 #VALUE! M-030

cum 104.180 input

#VALUE! M-034 #VALUE! M-032 #VALUE! M-030 #VALUE! M-189 #VALUE! #VALUE!

cum 148.500 input cum 133.430 input KL 18.000 input

Ref. to Sr No MoRT H Spec.

Description Cost for 225cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/225

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE! 4.17 B (ii) For 45 mm maximum size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360.0cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 4.18 Sugge stive Lime, Flyash Stabilised Soil Sub-Base Construction of Sub-base using lime - Flyash admixture with granular soil, free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than 50 per cent, Flyash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + Flyash content ranging between 10 to 30 per cent, the minimum un-confined compressive strength and CBR value after 28 days curing Unit = cum Taking output = 480 cum (720 tonnes, density 1.50 t/cum) Assumptions made Total mass taken for analysis = 720 t Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t= 576 t Soil = 720 -144 576 /1.6 = 360 cum Lime + Flyash = 144 t Ratio Lime 4 : Flyash 16 Lime = 29 kg. Flyash = 115 kg. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Machinery Hydraulic Excavator 0.90 cum bucket capacity @ 60cum/hr. for 360 cum soil Tipper 10T capacity for carriage of soil 576 tonnes hour tonne.k m 6.000 576 x L 1942.00 11652.00 4.00 P&M026 #VALUE! Lead =input km & P&M058 #VALUE! Lead =input km & P&M058 1491.00 P&M048 149.10 hour hour hour hour tonne 6.000 9.600 6.000 12.000 29.000 300.00 1800.00 P&M053 P&M032 P&M059 P&M060 118.00 3422.00 #VALUE! M-188 cum 360.000 input #VALUE! M-092 day day day 0.240 6.000 1.000 350.00 180.00 250.00 84.00 1080.00 250.00 L-12 L-13 L-15 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Tipper 10T capacity for carriage of 115 tonnes Flyash

tonne.k m

115 x L

4.00

Tipper 10T capacity for carriage of 29 tonnes of lime from store to work site Add 10 per cent of cost of carriage to cover cost of loading and unloading Tractor with disc harrows for pulverisation 110 HP @ 50 cum per hour Motor Grader for mixing in-place and grading Vibratory roller 8 - 10 tonne Water tanker 6 KL capacity c) Material Slaked Lime Compensation for earth taken from d) private sourcecharges @ 2.244% on Overhead (a+b+c) Page 35 of 363

hour

3.000

497.00

2254.00 21638.40 1339.00 300.00 8034.00 3600.00

Ref. to Sr No MoRT H Spec.

Description e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 480 Rate per cum= (a+b+c+d+e)/480 Note 1.Compensation for earth will vary from place to place and will have to be assessed realistically as per particular ground situation. In case earth is available from Govt. land, compensation for earth will not be required. Flyashposition been considered be 2.Cost of The has not is required to as same will be available free of cost. Only carriage of Flyash has been provided. 3.Lime + Flyash has been taken as 20 per cent of total mass and ratio of lime and Flyash as 1:4 for estimating purposes. Total quantities will be as per approved design.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE!

say #VALUE!

Page 36 of 363

Ref. to Sr No MoRT H 5.1 Spec. 502

CHAPTER - 5 BASES AND SURFACE COURSES (BITUMINOUS)


Description Prime Coat Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means. Unit = sqm Taking output = 3500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per Air compressor 250 cfm Bitumen pressure distributor @ 1750 Water tanker 6 KL capacity @ 1 trip per c) Material Bitumen emulsion @ 0.6 kg per sqm Cost of water d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 3500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/3500 Note Bitumen primer has been provided @ 0.60 kg per sqm as per clause 502.8. Payment shall be made with adjustment, plus or minus, for the variation between this quantity and the actual quantity approved by the Engineer after the preliminary trials Tack Coat Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleanedsqm mechanical broom. Unit = with Taking output = 3500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per Air compressor 250 cfm Emulsion pressure distributor @ 1750 c) Material Bitumen emulsion @ 0.2 kg per sqm d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 3500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/3500 Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8. Payment shall be made with adjustment, plus or minus, for the variation between this quantity and actual quantity approved by the AnEngineer of 3500 sqm has been 2. output after preliminary trials considered in case of prime coat and tack coat which can be covered by bituminous courses on the same day. Bituminous Macadam Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to Page 1 of 363 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day hour hour hour hour tonne KL

0.080 2.000 2.800 2.800 2.000 1.000

350.00 180.00 230.00 285.00 819.00 300.00

28.00 360.00 644.00 798.00 1638.00 300.00

L-12 L-13 P&MP&MP&MP&M-

2.100 input 6.000 input

#VALUE! M-077 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.2

503

day day hour hour hour tonne

0.080 2.000 2.800 2.800 2.000

350.00 180.00 230.00 285.00 819.00

28.00 360.00 644.00 798.00 1638.00

L-12 L-13 P&MP&MP&M-

0.700 input

#VALUE! M-077 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.3

504

Ref. to Sr No MoRT H Spec.

Description Unit = cum Taking output = 205 cum (450 tonnes) a) Labour Mate Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction Skilled mazdoor for checking line & b) levels Machinery Batch mix HMP 100-120 TPH @ 75 tonne per hour actual output Mechanical broom hydraulic @ 1250 sqm per hour 250 cfm Air compressor Paver finisher hydrostatic with sensor control @ 75 cum per hour Generator 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day

0.840 16.000

350.00 180.00

294.00 2880.00

L-12 L-13

day hour hour hour hour hour hour tonne.k m

5.000 6.000 2.200 2.200 6.000 6.000 6.000 450 x L

250.00 19966.00 230.00 285.00

1250.00 ### 506.00 627.00

L-15 P&M021 P&M031 P&M001 P&M034 P&M081 P&M-

2182.00 13092.00 1336.00 1042.00 8016.00 6252.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate with 6-8 tonnes smooth Finish rolling rolling. wheeled tandem roller. c) Material i) Bitumen@ 3.3 per cent of mix weight of mix = 205 x 2.2 = 450 tonne ii) Aggregate Total weight of mix = 450 tonnes Weight of bitumen = 14.85 tonnes Weight of aggregate = 450 -14.85 = 435.15 tonnes density of aggregate = 1.5 Taking ton/cum Volume of aggregate = 290.1 cum *Grading I ( 40 mm nominal size ) 37.5 - 25 mm 15 per cent 25 - 10 mm 45 per cent 10 - 5 mm 25 per cent 5 mm and below15 per cent or GradingII(19 mm nominal size) 25 - 10 mm 40 per cent 10 - 5 mm 40 per cent 5 mm and below 20 per cent * Any one of the alternative may be adopted as per approved design for Grading I ( 40 mm nominal size ) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/205 (For Grading I) (ii) for GradingII(19 mm nominal size) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/205 (For Grading-II) Page 2 of 363

017 Lead =35 km & P&M058 6300.00 1833.00 5222.10 4036.50 P&M044 P&M059 P&M045

hour6.00x0.65* hour6.00x0.65* hour6.00x0.65*

470.00 1339.00 1035.00

tonne

14.850

22129.50

### M-074

cum cum cum

43.510 input 853.45 72.530 43.510

#VALUE! M-049 ### M-046 M-040 M-030

cum 130.550

275.00 19945.75 275.00 11965.25

cum 116.040 cum 116.040 cum 58.020

853.45 99034.34 275.00 31911.00 275.00 15955.50

M-046 M-040 M-030

(i)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 15901.62 36226.51 ### 3711.01 say 3711.00

Ref. to Sr No MoRT Description H Spec. Note *1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been 2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula. 3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads offreshly laid tack 4. In case BM is laid over the contractor. coat, provision of Mechanical broom and 2 mazdoors for the same shall be deleted as the same has been included in the cost of tack coat. 5.4 505 Bituminous Penetration Macadam Construction of penetration macadam over prepared Base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the 50 mm thick Unit = sqm Taking output = 4500 sqm (225 cum) a) Labour Mate Mazdoor including for brooming of key aggregates Mazdoor skilled b) Machinery Hydraulic self propelled chip spreader both for aggregates and key aggregates@ 1500 sqm per hour for 4500 x 2 pressure distributor for @ 1750 Bitumen sqm = 9000 sqm sqm per hour Tipper 5.5 cum capacity for carriage of aggregates from stockpile to chip spreader Vibratory roller 8 tonnes Front end loader 1 cum bucket capacity c) Material Bitumen@ 5 kg per sqm Crushed stone coarse aggregate passing 45 mm and retained on 2.8 mm sieve @ 0.06 cum per sqm mm and Key aggregates passing 22.4 retained on 2.8 mm sieve @ 0.015 cum d) per sqm Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 4500 Rate per sqm = (a+b+c+d+e)/4500 Note 2 tippers will be needed to match the capacity of chip spreader and front end loader. B 75 mm thick Unit = sqm Taking output = 4500 sqm (337.5 cum compacted). a) Labour Mate Mazdoor including for brooming of key aggregates Mazdoor skilled b) Machinery

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.320 6.000 2.000 6.000

350.00 180.00 250.00

112.00 1080.00 500.00

L-12 L-13 L-15 P&M025 P&M004 P&M048 P&M059 P&M017

1700.00 10200.00

hour hour hour hour tonne

2.570 10.000 6.000 6.000 22.500

819.00 497.00 1339.00 1042.00 22129.50

2104.83 4970.00 8034.00 6252.00

### M-074 #VALUE! M-033 #VALUE! M-031 #VALUE! #VALUE! #VALUE! #VALUE!

cum 270.000 input cum 67.500 input

say #VALUE!

5.4

day day day

0.400 8.000 2.000

350.00 180.00 250.00

140.00 1440.00 500.00

L-12 L-13 L-15

Page 3 of 363

Ref. to Sr No MoRT H Spec.

Description Hydraulic self propelled chip spreader both for aggregates and key aggregates@ 1500 sqm per hour for 4500 x 2 pressure distributor for@ 1750 Bitumen sqm sqm per hour Tipper 5.5 cum capacity for carriage of aggregates from stockpile to chip spreader Vibratory roller 8 tonnes Front end loader 1 cum bucket capacity c) Material Bitumen@ 6.8 kg per sqm Crushed stone coarse aggregate (loose passing 63 mm and retained on 2.8 mm sieve @ 0.09 cum per sqm Key aggregates passing 26.5 mm and retained on 2.8 mm sieve @ 0.018 cum d) per sqm Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 4500 Rate per sqm = (a+b+c+d+e)/4500 Note 2 tippers and 2 rollers will be needed to match the capacity of chip spreader and front end loader. Built-up-Spray Grout Providing, laying and rolling of built-upspray grout layer over prepared base consisting of a two layer composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the second layer to serve as a Base conforming to the Unit = sqm Taking output = 3000 sqm (225 cum) a) Labour Mate Mazdoor including for brooming of key aggregates Mazdoor skilled b) Machinery Hydraulic self propelled chip spreader both for aggregates and key aggregates@ 1500 sqm per hour for 3000 x 3 pressure distributor for 3000 x Bitumen sqm 2 sqm @ 1750 sqm per hour Tipper 5.5 cum capacity Vibratory roller 8 tonnes Front end loader 1 cum bucket capacity c) Material Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for each layer Crushed stone coarse aggregate passing 53 mm and retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each layer Key aggregates passing 22.4 mm and retained on 2.8 mm sieve @ 0.13 cum d) per 10 sqm charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 3000 Rate per sqm = (a+b+c+d+e)/3000 Note 2 tippers will be needed to match the capacity of hydraulic chip spreader and front end loader. Page 4 of 363

Unit hour

Quantity 6.000

Rate Rs

Remark Cost Rs s/ Input ref. 1700.00 10200.00 P&M025 819.00 497.00 1339.00 1042.00 2104.83 4970.00 8034.00 6252.00 P&M004 P&M048 P&M059 P&M017

hour hour hour hour tonne

2.570 10.000 6.000 6.000 30.600

22129.50

### M-074 #VALUE! M-037

cum 405.000 input

cum

81.000 input

#VALUE! M-026 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.5

506

day day day hour

0.400 8.000 2.000 6.000

350.00 180.00 250.00

140.00 1440.00 500.00

L-12 L-13 L-15 P&M025 P&M004 P&M048 P&M059 P&M017

1700.00 10200.00

hour hour hour hour tonne

3.430 10.000 6.000 6.000 9.000

819.00 497.00 1339.00 1042.00 22129.50

2809.17 4970.00 8034.00 6252.00

### M-074 #VALUE! M-035

cum 300.000 input

cum

39.000 input

#VALUE! M-031 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec. 5.6 507

Description Dense Graded Bituminous Macadam Providing and laying dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the Unit = cum Taking output = 195 cum (450 tonnes) a) Labour Mate Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction Skilled mazdoor for checking line & b) levels Machinery Batch mix HMP @ 75 tonne per hour Paver finisher hydrostatic with sensor control @ 75 cum per hour Generator 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day

0.840 16.000

350.00 180.00

294.00 2880.00

L-12 L-13

day hour hour hour hour tonne.k m

5.000 6.000 6.000 6.000 6.000 450 x L

250.00

1250.00

L-15 P&M022 P&M034 P&M081 P&M017 Lead =35 km & P&M058 P&M044 P&M059 P&M045

15294.00 91764.00 2182.00 13092.00 1336.00 1042.00 8016.00 6252.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate with 6-8 tonnes smooth Finish rolling rolling. wheeled tandem roller. c) Materials Bitumen @ 4.6 per cent of weight of mix Aggregate Total weight of mix = 450 tonnes Weight of bitumen = 20.7 tonnes Weight of aggregate = 450 -19.13 = 430.87 tonnes density of aggregate = 1.5 Taking ton/cum aggregate = 287.25 cum Volume of Grading - I40 mm (Nominal Size) 37.5 - 25 mm 22 per cent 25 - 10 mm 13 per cent 10 -4.75 mm 19 per cent 4.75 mm and below 44 per cent Filler @ 2 per cent of weight of aggregates. or Grading - II19 mm (Nominal Size) 25 - 10 mm 30 per cent 10 - 5 mm 28 per cent 5 mm and below 40 per cent Filler @ 2 per cent of weight of aggregates. * Any one of the alternative may be adopted as per approved design For Grading I ( 40 mm nominal size ) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Page 5 of 363

hour6.00x0.65* hour6.00x0.65* hour6.00x0.65*

470.00 1339.00 1035.00

1833.00 5222.10 4036.50

tonne

20.700

22129.50

### M-074

cum cum cum tonne

63.190 input 37.340 54.580 8.620

#VALUE! M-049 M-046 M-040 M-030 M-188

853.45 31867.82 275.00 15009.50 275.00 34757.25 118.00 1017.16

cum 126.390

cum cum tonne

86.160 80.430 8.620

853.45 73533.25 275.00 22118.25 275.00 31597.50 118.00 1017.16

M-046 M-040 M-030 M-188

cum 114.900

(i)

#VALUE! #VALUE!

Ref. to Sr No MoRT H Spec.

Description Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/195 (For Grading I) (ii) For GradingII(19 mm nominal size) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/195 (For Grading-II) Note *1. Although the roller are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been 2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula. 3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads of freshly laid tack 4. In case DBM is laid over the contractor. coat, provision of mechanical broom and 2 mazdoors shall be deleted as the same has been included in the cost of tack coat. 5. The individual density for each size of aggregates to be used for construction I.e. 37.5-25 mm, 25-10 mm etc. should be found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a reference density in this Data 6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry aggregates. Semi-Dense Bituminous Concrete Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem Unit = cum Taking output = 195 cum (450 tonnes) a) Labour Mate Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction Skilled mazdoor for checking line & b) levels Machinery Batch mix HMP @ 75 tonne per hour Paver finisher hydrostatic with sensor control @ 75 cum per hour Generator 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE! 17592.66 40078.95 ### 4316.19 say 4316.00

5.7

508

day day

0.840 16.000

350.00 180.00

294.00 2880.00

L-12 L-13

day hour hour hour hour tonne.k m

5.000 6.000 6.000 6.000 6.000 450 x L

250.00

1250.00

L-15 P&M022 P&M034 P&M081 P&M017 Lead =35 km & P&M058

15294.00 91764.00 2182.00 13092.00 1336.00 1042.00 8016.00 6252.00

4.00 63000.00

Page 6 of 363

Ref. to Sr No MoRT H Spec.

Description Add 10 per cent of cost of carriage to cover cost of loading and unloading Smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate with 6-8 tonnes smooth Finish rolling rolling. wheeled tandem roller c) Material * Grading I: 13 mm (Nominal Size) i) Bitumen@ 4.5 per cent of weight of ii) Aggregate mix Total weight of mix = 450 tonnes Weight of bitumen = 20.25 tonnes Weight of aggregate = 450-20.25 = 429.75 tonnes density of aggregate = 1.5 ton/cum Taking Volume of aggregate = 286.5 cum 13.2 - 10 mm20 per cent 10 - 5 mm 38 per cent 5 mm and below 40 per cent Filler @ 2 per cent of weight of aggregates. or Grading II: 10 mm (Nominal Size) Bitumen@5 per cent of weight of mix weight of mix = 450 tonne Aggregate Total weight of mix = 450 tonnes Weight of bitumen = 22.5 tonnes Weight of aggregate = 450 -22.50 = 427.50 tonnes density of aggregate = 1.5 ton/cum Taking Volume of aggregate = 285 cum 9.5 - 4.75 mm@ 57 per cent 4.75 and below@ 41 per cent Filler @ 2 per cent of weight of aggregates. *Any one of the alternative may be adopted as per approved design for Grading I ( 13 mm nominal size ) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/195 (For Grading I)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 6300.00 1833.00 5222.10 4036.50 P&M044 P&M059 P&M045

hour6.00x0.65* hour6.00x0.65* hour6.00x0.65*

470.00 1339.00 1035.00

tonne

20.250

22129.50

### M-074

cum

57.300

275.00 15757.50 275.00 29939.25 275.00 31515.00 118.00 1017.16

M-044 M-040 M-030 M-188

cum 108.870 cum 114.600 tonne 8.620

tonne

22.500

22129.50

### M-074

cum 162.450 cum 116.850 tonne 8.620

275.00 44673.75 275.00 32133.75 118.00 1017.16

M-040 M-030 M-188

(i)

16387.73 37333.93 ### 4020.58 say 4021.00 17495.97 39858.70 ### 4292.48 say 4292.00

5.7

(ii)

for GradingII(10 mm nominal size) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

Note *1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been 2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula. 3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads of the contractor. Page 7 of 363

Ref. to Sr No MoRT H Spec.

Description 4. In case SDBC is laid over freshly laid tack coat, provision of broom and 2 mazdoor shall be deleted as the same has been included in the cost Bitumen to be adjusted 5. The quantity of of tack coat. as per job mix formula. Bituminous Concrete Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem Unit = cum Taking output = 191 cum (450 tonnes) a) Labour Mate Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction Skilled mazdoor for checking line & b) levels Machinery Batch mix HMP @ 75 tonne per hour Paver finisher hydrostatic with sensor control @ 75 cum per hour Generator 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

5.8

509

day day

0.840 16.000

350.00 180.00

294.00 2880.00

L-12 L-13

day hour hour hour hour tonne.k m

5.000 6.000 6.000 6.000 6.000 450 x L

250.00

1250.00

L-15 P&M022 P&M034 P&M081 P&M-

15294.00 91764.00 2182.00 13092.00 1336.00 1042.00 8016.00 6252.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate with 6-8 tonnes smooth Finish rolling rolling. wheeled tandem roller. c) Material i) Bitumen@ 5 per cent of weight of mix ii) Aggregate Total weight of mix = 450 tonnes Weight of bitumen = 22.5 tonnes Weight of aggregate = 450 -22.50 = 427.50 tonnes density of aggregate = 1.5 Taking ton/cum aggregate = 285 cum Volume of * Grading - I-19 mm (Nominal Size) 20 - 10 mm 35 per cent 10 - 5 mm 23 per cent 5 mm and below 40 per cent Filler @ 2 per cent of weight of aggregates. or Grading - II-13 mm (Nominal Size) 13.2 - 10 mm30 per cent 10 - 5 mm 25 per cent 5 mm and below43 per cent Filler @ 2 per cent of weight of aggregates. *Any one of the alternative may be adopted as per approved design for Grading-I ( 13 mm nominal size )

017 Lead =35 km & P&M058 6300.00 1833.00 5222.10 4036.50 P&M044 P&M059 P&M045

hour6.00x0.65* hour6.00x0.65* hour6.00x0.65*

470.00 1339.00 1035.00

tonne

22.500

22129.50

### M-074

cum cum tonne

99.750 input 65.550 8.620

#VALUE! M-045 M-040 M-030 M-188

275.00 18026.25 275.00 31350.00 118.00 1017.16

cum 114.000

cum cum tonne

85.500 71.250 8.620

275.00 23512.50 275.00 19593.75 275.00 33701.25 118.00 1017.16

M-044 M-040 M-030 M-188

cum 122.550

(i)

Page 8 of 363

Ref. to Sr No MoRT H Spec.

Description d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/191

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 5.8 (ii) for Grading-II(10 mm nominal size) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/191 (For Grading-II) Note *1. Although the rollers are required only for 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage rates have been 2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula. 3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative overheads offreshly laid tack 4. In case BC is laid over the contractor. coat, provision of mechanical broom and 2 mazdoors shall be deleted as the same has been included in the cost offor each size of 5. The individual density tack coat. aggregates to be used for construction i.e. 37.5-25 mm, 25-10 mm etc. should be found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a reference density in this Data 6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent Dressing of dry aggregates. Surface by weight Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller Unit = sqm Taking output = 9000 sqm Case :-19 mm nominal chipping size -1 a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Hydraulic self propelled chip spreader @ 1500 sqm per hour Tipper 10 tonne capacity for carriage of stone chips from stockpile on road side to chip spreader 1 cum bucket capacity Front end loader Bitumen pressure distributor Smooth wheeled roller 8-10 tonne c) weight Material Bitumen@ 1.20 kg per sqm hour hour hour hour hour hour hour tonne 7.200 7.200 6.000 6.000 6.000 6.000 6.000 10.800 230.00 285.00 1656.00 2052.00 P&M031 P&M001 P&M025 P&M048 P&M017 P&M004 P&M044 day day day 0.440 9.000 2.000 350.00 180.00 250.00 154.00 1620.00 500.00 L-12 L-13 L-15 17495.97 39858.70 ### 4382.37 say 4382.00

5.9

510

1700.00 10200.00 497.00 1042.00 819.00 470.00 22129.50 2982.00 6252.00 4914.00 2820.00

### M-074

Page 9 of 363

Ref. to Sr No MoRT H Spec.

Description Crushed stone chipping,19 mm nominal size @ 0.015 cum per sqm d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 9000 Rate per sqm = (a+b+c+d+e)/9000

Unit

Quantity

Rate Rs

cum 135.000 input

Remark Cost Rs s/ Input ref. #VALUE! M-053 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 5.9 Case - 13 mm nominal size chipping II a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Hydraulic self propelled chip spreader @ 1500 sqm per hour Tipper 10 tonne capacity for carriage of stone chips from stockpile on road side to chip spreader 1 cum bucket capacity Front end loader Bitumen pressure distributor @ 1750 sqm per hour 8-10 tonne weight Vibratory roller c) Material Bitumen@ 1.00 kg per sqm Crushed stone chipping,13 mm nominal size @ 0.01 cum per sqm d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 9000 Rate per sqm = (a+b+c+d+e)/9000 Note 1.Where the proposed aggregate fails to pass the stripping test, an approved adhesion agent may be added to the binder as per clause 510.2.4. Alternatively, chips may be pre-coated as coat, where required, 2.Input for the second per clause 510.2.5 5.10 511 will be the same as per the Ist coat mentioned above Open - Graded Premix Surfacing Providing, laying and rolling of open graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8Unit = sqm Taking output = 10250 sqm (205 cum) (i) Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75 tonnes/hour a) Labour . Mate Mazdoor working with HMP, road sweeper, paver and roller Skilled mazdoor for checking line & b) levels Machinery i) Batch type HMP 75 tonne per hour ii) Electric Generator Set 250 KVA iii) Front end loader 1 cum bucket capacity Page 10 of 363 day day day hour hour hour 0.840 16.000 5.000 6.000 6.000 6.000 350.00 180.00 250.00 19966.00 1336.00 1042.00 294.00 2880.00 1250.00 ### 8016.00 6252.00 L-12 L-13 L-15 P&M021 P&M081 P&M017 tonne cum 9.000 22129.50 90.000 input hour hour hour hour hour hour hour 7.200 7.200 6.000 6.000 6.000 6.000 6.000 230.00 285.00 1656.00 2052.00 P&M031 P&M001 P&M025 P&M048 P&M017 P&M004 P&M059 day day day 0.440 9.000 2.000 350.00 180.00 250.00 154.00 1620.00 500.00 L-12 L-13 L-15

1700.00 10200.00 497.00 1042.00 819.00 1339.00 2982.00 6252.00 4914.00 8034.00

### M-074 #VALUE! M-052 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

Ref. to Sr No MoRT H Spec.

Description iv) Tipper 10 tonne capacity

Unit tonne.k m

Quantity 450 x L

Rate Rs

Add 10 per cent of cost of carriage to cover cost of loading and unloading v) Paver finisher hydrostatic with sensor attachmentwheeled/tandom roller 8-10 iv) Smooth c) tonnes weight Material Bitumen@ 14.60 kg per 10 sqm Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum per 10 sqm d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10250 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10250 Note If a premix sand seal coat of 'B' type is proposed, the same is required to be provided over the open graded premix carpet immediately on the same day. As the same HMP and other machines will be used for laying of premix sand seal coat, out of 6 effective working hours, 4.00 hours may be utilised for laying of premix carpet and balance 2.00 hours for the seal coat. The rate for the premix sand seal coat under clause 513 (case II) has been worked out accordingly by utilising the HMP for 2.00 hours for the purpose of seal coat. In case type 'A' seal coat is proposed, HMP can be (ii) Case II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion Unit = sqm Taking output = 900 sqm (24.3 cum) a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Concrete mixer 0.4/0.28 cum capacity Smooth wheeled steel roller 8-10 tonne c) Material Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum per 10 sqm d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 900 Rate per sqm = (a+b+c+d+e)/900 5.11 512 Close Graded Premix Surfacing/Mixed Seal Surfacing Case I Mechanical means using HMP of appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, Unit = sqm Page 11 of 363

Remark Cost Rs s/ Input ref. 4.00 63000.00 Lead =35 km & P&M058 6300.00 P&M034 P&M045

hour hour

6.000 6.000

2182.00 13092.00 1035.00 6210.00

tonne

14.970

22129.50

### M-074 #VALUE! M-043 #VALUE! #VALUE! #VALUE! #VALUE!

cum 276.750 input

say #VALUE!

5.10

day day day hour hour tonne cum

0.800 18.000 2.000 6.000 6.000

350.00 180.00 250.00 165.00 470.00

280.00 3240.00 500.00 990.00 2820.00

L-12 L-13 L-15 P&M009 P&M044

1.940 input 24.300 input

#VALUE! M-073 #VALUE! M-043 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec.

Description Taking output = 10250 sqm (205 cum) a) Labour Mate Mazdoor working with HMP, road sweeper, paver and roller Skilled mazdoor for checking line & b) levels Machinery i) HMP of appropicate capacity. ii) Electric Generator Set 250 KVA iii) Front end loader 1 cum bucket capacity 10 tonne capacity iv) Tipper

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour tonne.k m

0.840 16.000 5.000 6.000 6.000 6.000 450 x L

350.00 180.00 250.00 19966.00 1336.00 1042.00

294.00 2880.00 1250.00 ### 8016.00 6252.00

L-12 L-13 L-15 P&M021 P&M081 P&M017 Lead

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading v) Paver finisher hydrostatic with sensor attachmentwheeled8-10 tonnes weight iv) Smooth c) Material * Bitumen@ 22 kg per 10 sqm Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum per 10 sqm or Type - B Bitumen @ 19 kg per 10 sqm Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum per 10 sqm d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10250 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10250 * Any one of the alternative may be adopted Seal Coat Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A sqm Unit = and B seal coats (i) Taking output = 10250 sqm (92.25 cum) Case - I : Type A a) Labour Mate Mazdoor b) Machinery Hydraulic self propelled chip spreader Tipper 5.5 cum capacity Front end loader 1 cum bucket capacity Bitumen pressure distributor @ 1750 sqm per wheeled roller 8 -10 tonne Smooth hour c) weight Material Bitumen@ 9.80 kg per 10 sqm Crushed stone chipping of 6.7 mm size defined as 100 per cent passing 11.2 mm sieve and retained on 2.36 mm d) sieve applied @ 0.09 cum 2.244% on Overhead charges @ per 10 sqm (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10250 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10250 Type - A

=35 km & P&M058 6300.00 6.000 6.000 2182.00 13092.00 470.00 2820.00 P&M034 P&M044

hour hour

tonne

22.500

22129.50

### M-074 #VALUE! M-041

cum 276.750 input

tonne

19.480

22129.50

### M-074 #VALUE! M-042 #VALUE! #VALUE! #VALUE! #VALUE!

cum 276.750 input

say #VALUE! 5.12 513

day day hour hour hour hour hour tonne cum

0.240 6.000 6.000 6.000 6.000 6.000 6.000 10.050

350.00 180.00

84.00 1080.00

L-12 L-13 P&M025 P&M048 P&M017 P&M004 P&M044

1700.00 10200.00 497.00 1042.00 819.00 470.00 22129.50 2982.00 6252.00 4914.00 2820.00

### M-074 #VALUE! M-050

92.250 input

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 12 of 363

Ref. to Sr No MoRT Description H Spec. Note Since seal coat is provided immediately over the bituminous layers, mechanical broom for clearing has not been catered. 5.12 (ii) Case - II : Type B Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade. Unit = sqm Taking output = 7858 sqm (47.16 cum) a) Labour Mate Mazdoor b) Machinery HMP of 75 tonnes/hour. Electric Generator Set 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour hour hour tonne.k m

0.160 4.000 2.000 2.000 2.000 104 x 'L'

350.00 180.00

56.00 720.00

L-12 L-13 P&M022 P&M081 P&M017 Lead

15294.00 30588.00 1336.00 1042.00 2672.00 2084.00

4.00 14560.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Paver finisher hydrostatic with sensor attachment Smooth wheeled 8-10 tonnes capacity c) Material Bitumen@ 6.80 kg per 10 sqm Crushed stone chipping of 6.7 mm size defined as passing 11.2 mm sieve and retained on 2.36 mm sieve applied @ d) 0.06 cum per 10 sqm @ 2.244% on Overhead charges (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 7858 Rate per sqm = (a+b+c+d+e)/7858 Note Since seal coat is required to be provided over the premix carpet on the same day, out of the 6 working hours of the HMP, 4.00 hours are proposed to be utilised for the premix carpet and the balance 2.00 hours for the seal coat. Hence 2.00 hours have been considered for this case. This may be linked to rate analysis worked out under Supply of Stone Aggregates for Pavement Courses Supply of stone aggregates from approved sources conforming to the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection, transportation, stacking and testing market rates to be as Competitive and measured in cum as per certained. Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of aggregates at site are not available, nearest crusher site may be as certained. Loading and un-loading charges and cost of carriage may be added to these rates to arrive at Mastic Asphalt

=35 km & P&M058 1456.00 2.000 2.000 5.340 2182.00 470.00 22129.50 4364.00 940.00 P&M034 P&M044

hour hour tonne cum

### M-074 #VALUE! M-050

47.160 input

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.13

514

5.14

515

Page 13 of 363

Ref. to Sr No MoRT H Spec.

Description Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated finegrained hard stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces is Unit = sqm Taking output = 35.00 sqm (0.87 cum ) assuming a density of 2.3 tonnes/cum.2 a)tonnes Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Mastic cooker 1 tonne capacity Bitumen boiler 1500 litres capacity Tractor for towing and positioning of mastic cooker and bitumen boiler c) Material Base mastic (without coarse aggregates) = 60 per cent Coarse aggregate (6.3mm to 13.2 mm) = 40 per centof material required for mastic Proportion . asphalt with coarse aggregates (based on mix design done by CRRI for a specific case) I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight of mix. 2 x 10.2/100 = 0.204 aggregate passing 2.36mm and ii) Fine retained on 0.075mm sieve @ 31.9 per cent by weight of mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39 iii) Lime stone dust filler with calcium content not less than 80 per cent by weight @ 17.92 per cent by weight of mix = 2 x 17.92/100 =6.3 mm to 13.2 iv) Coarse aggregates 0.36 mm @ 40 per cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55 v) Pre-coated stone chips of 13.2 mm nominal size for skid resistance = 35 x 0.005/10 = 0.018 vi) Bitumen for coating of chips @ 2 per cent by weight = 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 35.00 Rate per sqm = (a+b+c+d+e)/35 Note 1.The rates for 50 mm & 40 mm thick layers may be worked out on pro-rata basis. 2.Where tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately. 3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities shall be as per mix design. 4.This rate analysis is based on design made by CRRI for a specific case and is meant for estimating purposes only. Actual design is required to be done for each case. Slurry Seal Page 14 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour hour hour

0.440 10.000 1.000 0.060 0.060 6.000 6.000 1.000

350.00 180.00 250.00 230.00 285.00 44.00 141.00 300.00

154.00 1800.00 250.00 13.80 17.10 264.00 846.00 300.00

L-12 L-13 L-15 P&M031 P&M001 P&M030 P&M005 P&M053

tonne cum

0.204

22129.50

4514.42

M-074

0.390 input

#VALUE! M-021

tonne

0.360

118.00

42.48

M-188

cum

0.550 input

#VALUE! M-043

cum kg

0.018 input 0.500 22.00

#VALUE! M-142 11.00 M-074

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.15

516

Ref. to Sr No MoRT H Spec.

Description Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile thickness 5 mm plant, laying and compacting to Unit = sqm Taking output = 16000 sqm (80 cum) Taking density of 2.2 tonnes per cum weight of mix = 176 tonnes a) Labour Mate Mazdoor b) Machinery Mechanical broom Air compressor 250 cfm Mobile slurry seal equipment Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment, bitumen emulsion and filler. tyred roller with individual Pneumatic wheel load not exceeding 1.5 tonnes Water tanker6 KL capacity c) Material Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 Fine aggregate 4.75 mm and below 87 per cent of total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5, = 153.12/1.5per102.08 cum mix = 80 x Filler @ 2 = cent of total 2.2 xof water Cost 0.02 d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 16000 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/16000

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

(i)

day day hour hour hour hour hour

0.240 6.000 6.000 6.000 6.000 6.000 6.000

350.00 180.00 230.00 285.00 780.00 1042.00 497.00

84.00 1080.00 1380.00 1710.00 4680.00 6252.00 2982.00

L-12 L-13 P&M031 P&M001 P&M033 P&M017 P&M048 P&M037 P&M060

hour hour tonne

6.000 2.000

892.00 300.00

5352.00 600.00

19.360 input

#VALUE! M-077 #VALUE! M-030

cum 102.080 input

tonne KL

3.520

118.00

415.36 #VALUE! #VALUE! #VALUE! #VALUE!

M-188

12.000 input

#VALUE! M-189

say #VALUE! 5.15 (ii) 3 mm thickness Unit = sqm Taking output = 20000 sqm (60 cum) a) Labour Mate Mazdoor b) Machinery Mechanical broom Air compressor 250 cfm Mobile slurry seal equipment Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment, bitumen emulsion and filler Water tanker6 KL capacity c) Material Residual Binder @ 13 per cent of mix = 60 x 2.2 x 0.13 Fine aggregate 3 mm and below 85 per cent of total mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5, Filler @ 2 per cent of total mix = 60x 2.2 xof water Cost 0.02 d) Overhead charges @ 2.244% on (a+b+c) Page 15 of 363 tonne cum 17.160 input 74.800 input hour hour hour hour hour 6.000 6.000 6.000 6.000 6.000 230.00 285.00 780.00 1042.00 497.00 1380.00 1710.00 4680.00 6252.00 2982.00 P&M031 P&M001 P&M033 P&M017 P&M048 P&M060 day day 0.200 5.000 350.00 180.00 70.00 900.00 L-12 L-13

hour

2.000

300.00

600.00

#VALUE! M-077 #VALUE! M-022

tonne KL

2.640

118.00

311.52 #VALUE!

M-188

12.000 input

#VALUE! M-189

Ref. to Sr No MoRT H Spec.

Description e) Contractor's profit @ 5% on (a+b+c+d) Cost for 30000 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/20000

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE!

say #VALUE! 5.15 (iii) 1.5 mm thickness Unit = sqm Taking output = 24000 sqm (36 cum) a) Labour Mate Mazdoor b) Machinery Mechanical broom Air compressor 250 cfm Mobile slurry seal equipment Front end loader 1 cum bucket capacity Tipper 5.5 cum capacity for carriage of aggregate from stockpile on road side to slurry equipment, bitumen emulsion and filler. Water tanker6 KL capacity c) Material Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 Fine aggregate 2.36 mm and below,82 per cent of total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5 Filler @ 2 per cent of total mix = 36x 2.2 xof water Cost 0.02 d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 24000 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/24000 Note 1.Tack coat, if required to be provided, before laying slurry seal may be measured and paid separately Recycling of Bituminous Pavement with Central Recycling Plant Recycling pavement by cold milling of existing bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 per cent of the required quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and Unit = cum Taking output = 120 cum (276 tonnes) a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Cold milling machine @ 20 cum per hour Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Bitumen pressure distributor @ 1750 sqmmix plant 100-120 TPH producing Hot per hour an average of 75 tonnes per hour Electric generator set 250 KVA Front end loader 1.00 cum bucket capacity Page 16 of 363 hour hour hour hour hour hour hour 6.000 input 1.280 1.280 0.910 3.000 3.000 3.000 230.00 285.00 819.00 #VALUE! 294.40 364.80 745.29 P&M069 P&M031 P&M001 P&M004 P&M021 P&M081 P&M017 day day day 0.480 10.000 2.000 350.00 180.00 250.00 168.00 1800.00 500.00 L-12 L-13 L-15 tonne cum 12.670 input 43.300 input hour hour hour hour hour 6.000 6.000 6.000 6.000 6.000 230.00 285.00 780.00 1042.00 497.00 1380.00 1710.00 4680.00 6252.00 2982.00 P&M031 P&M001 P&M033 P&M017 P&M048 P&M060 day day 0.200 5.000 350.00 180.00 70.00 900.00 L-12 L-13

hour

2.000

300.00

600.00

#VALUE! M-077 #VALUE! M-022

tonne KL

1.580

118.00

186.44 #VALUE! #VALUE! #VALUE! #VALUE!

M-188

12.000 input

#VALUE! M-189

say #VALUE!

5.16

517

19966.00 59898.00 1336.00 1042.00 4008.00 3126.00

Ref. to Sr No MoRT H Spec.

Description Tipper 5.5 cum capacity Smooth wheeled roller 8-10 tonnes Vibratory roller 8 tonnes Smooth wheeled tandem roller 6-8 c) tonnes Material i) Bitumen A bitumen content is 4.5 per cent bitumen weight of mix. For reclaimed material, fresh bitumen will be required to the extent of 60 per a mixofof 276 requirement. tonne is normal tonnes, 82.8 In cent reclaimed and balance 193.2 tonne is fresh mix.Bitumen required for reclaimed mix of 82.8 tonne @ 60 per cent = 82.8 x 0.60 x0.04 = 1.99for fresh mix of 193.2 Bitumen required tonnes = 193.2 x 0.04 = 7.73 ii) Aggregates Percentage of mix requiring fresh aggregates - 70 per cent Weight of fresh mix = 276 x 0.70 = 193.2 tonne of fresh aggregate in the mix = Weight 193.2 x 0.96 = 185.47 tonne Taking average density of 1.5 tonnes/cum, total volume of aggregate = 123.65requirement of fresh aggregates Size wise cum. 37.5 - 25 mm @ 23 per cent 25 - 10 mm @ 15 per cent 10- 5 mm @ 20 per cent Below 5 mm @40 per cent Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum of DBM = a+b+c+d+e Cost for 120 Rate per cum = (a+b+c+d+e)/120 Note Although the total rolling time is only 4 hours as per norms, all the three rollers have to be available at site for 3 hours each to match with the output of re-cycling plant. To cater for their idling time, these have beenSpray Fog multiplied with a factor of 0.65. Providing and applying low viscosity bitumen emulsion for sealing cracks less than 3 mm wide or incipient fretting or disintegration in an existing bituminous Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Bitumen emulsion pressure distributor @ 1750 sqm per hour c) Material Bitumen emulsion @ 0.75 kg per sqm d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500

Unit hour

Quantity 18.000

Rate Rs

hour3.00x0.65* hour3.00x0.65* hour3.00x0.65*

Remark Cost Rs s/ Input ref. 497.00 8946.00 P&M048 470.00 916.50 P&M044 1339.00 2611.05 P&M1035.00 2018.25 059 P&M045

tonne tonne

1.987 7.728

22129.50 43975.74 22129.50

M-074

### M-074

cum cum cum cum tonne

28.440 input 18.550 24.730 49.460 275.00

#VALUE! M-049 M-046 M-040 M-030 6800.75

853.45 15831.50 275.00 13601.50

5.520 input

#VALUE! M-081 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.17

518

day day hour hour tonne

0.120 3.000 6.000 6.000 6.000

350.00 180.00 230.00 285.00 819.00

42.00 540.00 1380.00 1710.00 4914.00

L-12 L-13 P&M031 P&M001 P&M004

tonne

7.880 input

#VALUE! M-077 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 17 of 363

Ref. to Sr No MoRT H Spec.

Description 1.In case it is decided by the engineer to blind the fog spray, the following may be added a) Labour Mate Mazdoor for precoating of grit b) Material Crushed stone grit 3 mm size @ 3.75 kg per sqm emulsion for precoating grit @ Bitumen 2 per cent of grit,39.38 x 0.02

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day cum tonne

0.160 4.000

350.00 180.00

56.00 720.00

L-12 L-13

26.250 input 0.790 input

#VALUE! M-024 #VALUE! M-077 #VALUE! #VALUE! say #VALUE!

5.18

519

Bituminous Cold Mix ( Including Gravel Emulsion)laying and rolling of bituminous Providing, cold mix on prepared base consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing to specified grades and levels. Unit = cum Taking output = 205 cum (450 tonne) (i) Using bitumen emulsion and 9.5 mm or 13.2 mm size aggregate Composition of mix (450 tonne) is assumed to be as under:Bitumen Emulsion 8 per cent Filler2 per cent Total aggregates 90 per cent Proportion of aggregates 19 mm to 9.5 mm25 per cent 9.5 mm to 6 mm29 per cent 6 mm to 0.075 mm 36 per cent a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. Electric generator 125 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity hour hour hour tonne.k m 6.000 input 6.000 6.000 450 x L 874.00 1042.00 #VALUE! 5244.00 6252.00 P&M077 P&M018 P&Mday day day 0.840 16.000 5.000 350.00 180.00 250.00 294.00 2880.00 1250.00 L-12 L-13 L-15

By weight of total

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Paver finisher Pneumatic tyred roller 12-15 tonnes Smooth wheeled steel tandem roller 6-8 c) tonnes Material Bitumen emulsion @ 8 per cent Filler (lime)@ 2 per cent Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5size 9.5 to 6 mm - 450 x Aggregates 0.29 x 1/1.5size 6 to 0.075 mm - 450 x Aggregates d) 0.36 x 1/1.5 charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/205

017 Lead =35 km & P&M058 6300.00 P&M034 P&M037 P&M045 M-188 M-040 M-030

hour

6.000

2182.00 13092.00 892.00 1035.00 3478.80 4036.50

hour6.00x0.65* hour6.00x0.65* tonne tonne cum cum

36.000 input 9.000 87.000 118.00 75.000 input

#VALUE! M-077 1062.00 #VALUE! M-045

275.00 23925.00 275.00 29700.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 108.000

Page 18 of 363

Ref. to Sr No MoRT H Spec.

Description (Applicable to cases I to IV) Note 1.Density of aggregates has been assumed 1.5 gms/cccoat where provided will be 2. Tack measured and paid separately. *3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a (ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate Composition of mix (450 tonne) is assumed to be as under:Bitumen Emulsion 8 per cent Filler2 per cent Total aggregates 90 per cent Proportion of aggregates 37.5 mm to 19 mm25 per cent 19 mm to 6 mm 30 per cent 6 mm to 0.075 mm 35 per cent a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Drum mix plant for cold mixes 60-90 tonne per hour producing average output generator 125 KVA Electricof 75 tonnes per hour Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

5.18

day day day hour hour hour tonne.k m

0.840 16.000 5.000

350.00 180.00 250.00

294.00 2880.00 1250.00 #VALUE! 5244.00 6252.00

L-12 L-13 L-15 P&M077 P&M018 P&M-

6.000 input 6.000 6.000 450 x L 874.00 1042.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Paver finisher Pneumatic tyred roller 12-15 tonnes Smooth wheeled steel tandom roller 6-8 c) tonnes Material Bitumen emulsion @ 8 per cent Filler (lime)@ 2 per cent Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5size 19 to 6 mm - 450 x 0.3 Aggregates x 1/1.5 Aggregates size 6 to 0.075 mm - 450 x d) 0.35 x 1/1.5 charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/205 Note 1.Density of aggregates has been assumed 1.5 gms/cccoat where provided will be 2. Tack measured and paid separately. *3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a (iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate Composition of mix (450 tonne) is assumed to be as under:Page 19 of 363

017 Lead =35 km & P&M058 6300.00 P&M034 P&M037 P&M045 M-188

hour

6.000

2182.00 13092.00 892.00 1035.00 3478.80 4036.50

hour6.00x0.65* hour6.00x0.65* tonne tonne cum cum

36.000 input 9.000 118.00 75.000 input 90.000 input

#VALUE! M-077 1062.00 #VALUE! M-048 #VALUE! M-047 M-030 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 105.000

275.00 28875.00

5.18

Ref. to Sr No MoRT H Spec.

Description Cutback bitumen 5 per cent Filler (lime) 2 per cent Total aggregates 93 per cent Proportion of aggregates 19 mm to 9.5 mm26 per cent 9.5 mm to 6 mm31 per cent 6 mm to 0.075 mm 36 per cent a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Drum mix plant for cold mixes 60-90 tonne per hour producing average output generator 125 KVA Electricof 75 tonnes per hour Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour tonne.k m

0.840 16.000 5.000

350.00 180.00 250.00

294.00 2880.00 1250.00 #VALUE! 5244.00 6252.00

L-12 L-13 L-15 P&M077 P&M018 P&M-

6.000 input 6.000 6.000 450 x L 874.00 1042.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Paver finisher Pneumatic tyred roller 12-15 tonnes Smooth wheeled steel tandem roller 6-8 c) tonnes Material Cutback bitumen @ 5 per cent Filler (lime)@ 2 per cent Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5 Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 Aggregates size 6 to 0.075 mm - 450 x d) 0.36 x 1/1.5 charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/205 Note 1.Density of aggregates has been assumed 1.5 Tack 2. gms/cccoat where provided will be measured and paid separately. *3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a (iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate Composition of mix (450 tonne) is assumed to be as under:Cutback bitumen 5 per cent Filler2 per cent Total aggregates 93 per cent Proportion of aggregates 37.5 mm to 19 mm25 per cent 19 mm to 6 mm 30 per cent 6 mm to 0.075 mm 38 per cent a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Page 20 of 363

017 Lead =35 km & P&M058 6300.00 P&M034 P&M037 P&M045 M-188 M-040 M-030

hour

6.000

2182.00 13092.00 892.00 1035.00 3478.80 4036.50

hour6.00x0.65* hour6.00x0.65* tonne tonne cum cum

22.500 input 9.000 93.000 118.00 78.000 input

#VALUE! M-076 1062.00 #VALUE! M-045

275.00 25575.00 275.00 29700.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 108.000

5.18

day day day

0.840 16.000 5.000

350.00 180.00 250.00

294.00 2880.00 1250.00

L-12 L-13 L-15

Ref. to Sr No MoRT H Spec.

Description Drum mix plant for cold mixes 60-90 tonne per hour producing output of 75 tonnes per hour 125 KVA Electric generator Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

Unit hour hour hour tonne.k m

Quantity

Remark Cost Rs s/ Input ref. 6.000 input #VALUE! P&M077 6.000 874.00 5244.00 P&M018 6.000 1042.00 6252.00 P&M017 450 x L 4.00 63000.00 Lead Rate Rs =35 km & P&M058 6300.00 6.000 2182.00 13092.00 892.00 1035.00 3478.80 4036.50 P&M034 P&M037 P&M045 M-188

Add 10 per cent of cost of carriage to cover cost of loading and unloading Paver finisher Pneumatic tyred roller 12-15 tonnes. Smooth wheeled steel tandem roller 6-8 c) tonnes Material Cutback bitumen on @ 5 per cent Filler (lime)@ 2 per cent Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5size 19 to 6 mm - 450 x 0.3 Aggregates x 1/1.5 Aggregates size 6 to 0.075 mm - 450 d) x0.38 x 1/1.5 charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/205 Note 1.Density of aggregates has been assumed 1.5 gms/cccoat where provided will be 2. Tack measured and paid separately. *3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been multiplied by a Sand Asphalt Base Course Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings including mixing in a plant of suitable type and capacity, transporting, Unit = cum Taking output = 205 cum (450 tonne) a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Hot Mix Plant of appropriate capacity but not less than 75 tonnes/hour Electric generator set 250 KVA Front end loader 1 cum bucket capacity Tipper 10 tonne capacity

hour

hour6.00x0.65* hour6.00x0.65* tonne tonne cum cum

22.500 input 9.000 118.00 75.000 input 90.000 input

#VALUE! M-076 1062.00 #VALUE! M-048 #VALUE! M-047 M-030 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 114.000

275.00 31350.00

5.19

520

day day day hour hour hour tonne.k m

0.840 16.000 5.000 6.000 6.000 6.000 450 x L

350.00 180.00 250.00

294.00 2880.00 1250.00

L-12 L-13 L-15 P&M023 P&M081 P&M-

13846.00 83076.00 1336.00 1042.00 8016.00 6252.00

4.00 63000.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Paver finisher smooth wheeled roller 8-10 tonnes for initial break down rolling. Vibratory roller 8 tonnes for intermediate with 6-8 tonnes smooth Finish rolling rolling. wheeled tandom rollers. c) Material

017 Lead =35 km & P&M058 6300.00 P&M034 P&M044 P&M059 P&M045

hour

6.000

2182.00 13092.00 470.00 1339.00 1035.00 1833.00 5222.10 4036.50

hour 6.00x0.65 hour 6.00x0.65 hour 6.00x0.65

Page 21 of 363

Ref. to Sr No MoRT H Spec.

Description Composition of mix (450 tonne) assumed to be as under:Density 2.20 tonne per cum Weight450 tonne Bitumen5 per cent Filler2 per cent Sand of size 4.75 to 0.075 mm 93 per cent Bitumen@ 5 per cent Filler (lime)@ 2 per cent Sand of size 4.75 to 0.075 mm - 450 x d) 0.93 x 1/1.5 charges @ 2.244% on Overhead (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 205 Rate per cum = (a+b+c+d+e)/205 Note 1. Tack coat will be measured and paid separately the rollers are required only for 2. Although 3 hours as per norms of output, but the same have to be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the output of 450 tonnes considered in this analysis. To cater for the idle period of this roller, their usage rates has been multiplied Modified Binder Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC:SP: 53 blending of modifier with bitumen to be done either at the refinery or at central unit with all facilities Unit = tonne The use of modified binder is expected to result in an extended service life of bituminous pavements subject to heavy traffic loads in extreme climatic conditions, thus justifying the entire cost of adding modifiers/fibres. Other advantages include lower temperature susceptibility, higher resistance to aging, higher fatigue life, higher resistance to cracking and better Detailed information and inductive dose level on the use of polymer modified binder is available in IRC : SP-53 / 2002. A number of proprietary products are now available in the market. For such proprietary products, test reports and cost effectiveness should be the basis for their selection in road The modifier, in the required quantity shall be blended at the refinery or at central unit with all facilities by proper industrial process, is essential. If supplied in drums it shall be agitated in melted condition with suitable device for achieving homogeneity Proposals to use glass fibre, polypropylene fibres or any other similar material in a bituminous mixture should be substantiated, complete with all details including test results, manufacturer's recommendations for addition or means of incorporating the fibres, homogeneously, Before agreeing to the use of a fibre, it should have been proved to be satisfactory in use under circumstances, similar to the work, elsewhere or it would have under gone appropriate performance trials. Documented evidence of use and trials of the fibre, in any country having conditions where information on use of trials is inadequate or lacking, trials may be required to be under taken before agreeing to the use of the fibre. Page 22 of 363 is

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

tonne tonne

22.500 9.000

22129.50 118.00

### M-074 1062.00 #VALUE! #VALUE! #VALUE! #VALUE! M-188 #VALUE! M-004

cum 288.620 input

say #VALUE!

5.20

521

Ref. to Sr No MoRT Description H Spec. Note 1. The modified binder is usually manufactured by specialised firms as a proprietary product. The rate for this product is required to be as certainedof road 2.The specifications for various item from works using polymer/rubber modified bitumens are same as those for penetration grade bitumen except those for any special conditions which the manufacturer laying 3.The other controls during mixing, may shall be same as specified in IRC - 14, 29, 94 and 95 for open graded premix carpet, bituminous concrete, DBM and SDBC respectively 4.The temperature of mixing and rolling will be slightly higher than conventional bituminous mixes as indicated in Table 8 of IRC: SP: 53 - 2002 Courses Crack Prevention (i) Stress absorbing membrane (SAM) crack width less than 6 mm Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Bitumen pressure distributor @ 1750 sqm per hour spreader Hydraulic Chip Smooth wheeled road roller 8-10 tonne c) Material Modified binder Crushed stone aggregates 5.6 mm size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500 5.21 (ii) Stress absorbing membrane (SAM) with crack width 6 mm to 9 mm Providing and laying of a stress absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm capacity Bitumen pressure distributor @ 1750 sqm per hour Page 23 of 363

Unit

Quantity `

Rate Rs

Remark Cost Rs s/ Input ref.

5.21

522

day day hour hour hour hour hour tonne

0.240 6.000 6.000 6.000 6.000 6.000 6.000

350.00 180.00 230.00 285.00 819.00 470.00

84.00 1080.00 1380.00 1710.00 4914.00 2820.00

L-12 L-13 P&M031 P&M001 P&M004 P&M025 P&M044

1700.00 10200.00

9.450 input

#VALUE! M-078 #VALUE! M-050 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 105.000 input

day day hour hour hour

0.240 6.000 6.000 6.000 6.000

350.00 180.00 230.00 285.00 819.00

84.00 1080.00 1380.00 1710.00 4914.00

L-12 L-13 P&M031 P&M001 P&M004

Ref. to Sr No MoRT H Spec. c)

Description Hydraulic Chip spreader Smooth wheeled road roller 8-10 tonne Material Modified binder Crushed stone chipping 11.2 mm size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500

Unit hour hour tonne

Quantity 6.000 6.000

Rate Rs

Remark Cost Rs s/ Input ref. 1700.00 10200.00 P&M025 470.00 2820.00 P&M044 #VALUE! M-078 #VALUE! M-051 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

11.550 input

cum 105.000 input

5.21

(iii)

Stress absorbing membrane (SAM) crack width above 9 mm and cracked area above 50 layingcentsingle coat of a Providing and per a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area above 50 per cent after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of Unit = sqm Taking output = 10500 sqm a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm capacity Bitumen pressure distributor @ 1750 sqm per hour spreader Hydraulic Chip Smooth wheeled road roller 8-10 tonne c) Material Modified binder Crushed stone aggregates 11.2 mm size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10500 tonne 15.750 input cum 126.000 input hour hour hour hour hour 6.000 6.000 6.000 6.000 6.000 230.00 285.00 819.00 470.00 1380.00 1710.00 4914.00 2820.00 P&M031 P&M001 P&M004 P&M025 P&M044 day day day 0.240 6.000 2.000 350.00 180.00 250.00 84.00 1080.00 500.00 L-12 L-13 L-15

1700.00 10200.00

#VALUE! M-078 #VALUE! M-051 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

5.21

Note In case 2nd coat is also required to be provided, material provided for the 2nd coat per : Bitumen (iv) shall be-as IV table 500-47. impregnated Case geotextile and Providing laying a bitumen impregnated geotextile layer after cleaning the road surface, geotextile conforming to requirements of clause 703.3, laid over a tack coat with 1.05 kg per sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause Unit = sqm Taking output = 3500 sqm a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm capacity Bitumen pressure distributor @ 1750 sqm per hour Page 24 of 363 hour hour tonne 2.800 2.800 2.000 230.00 285.00 819.00 644.00 798.00 1638.00 P&M031 P&M001 P&M004 day day day 0.560 12.000 2.000 350.00 180.00 250.00 196.00 2160.00 500.00 L-12 L-13 L-15

Ref. to Sr No MoRT H Spec. c)

Description Pneumatic roller Material Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per sqm Geotextile including 10 per cent for d) overlaps Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/3500

Unit hour tonne

Quantity 2.000

Rate Rs

Remark Cost Rs s/ Input ref. 892.00 1784.00 P&M037 #VALUE! M-075 #VALUE! M-108 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

3.680 input

sqm 3850.000 input

5.22

NOTE As bitumen overlay construction shall follow closely the fabric placement on the same day, an output of 3500 sqm only has been considered for the analysis which will cover a length of 500 m, of 7 m wide carriagway. This can be conveniently overlaid by a bitumenious course in a day 519.3 Recipe Cold Mix Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth steel wheel roller, all as per clause 519.3 Unit = cum Taking output = 205 cum (450 tonnes) (i) 75 mm thickness a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Batch type cold mixing plant 100-120 TPH capacity producing an average output generator per hour Electricof 75 tonne125 KVA Front end loader 1 cum capacity Paver finisher hydrostatic with sensor control @ 75 cum per hour Tipper 10 tonne capacity hour hour hour hour tonne.k m 6.000 input 6.000 6.000 6.000 450 x L 874.00 1042.00 #VALUE! 5244.00 6252.00 P&M064 P&M018 P&Mday day day 1.000 12.000 5.000 350.00 180.00 250.00 350.00 2160.00 1250.00 L-12 L-13 L-15

2182.00 13092.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Pneumatic tyred roller12-15 tonnes. Smooth wheeled steel roller6-8 tonnes. Water tanker6 KL capacity c) Material Bitumen emulsion @ 45 litres per tonne Crushed stone aggregates 40 mm nominal size Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/205 Note (Case I to III) 1. These mixes are considered suitable for minor repair work and temporary road surface improvement. 2. In case concrete mixtures are required to be used for mixing, a number of these will be needed to match the capacity of road rollers. 3. Tack coat, where provided, will be measured and paid separately. Page 25 of 363

017 P&M034 4.00 63000.00 Lead =35 km & P&M058 6300.00 3478.80 1833.00 300.00 P&M037 P&M044 P&M060

hour6.00x0.65* hour6.00x0.65* hour tonne KL 1.000

892.00 470.00 300.00

20.250 input 6.000 input

#VALUE! M-077 #VALUE! M-055 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 297.000 input

Ref. to Sr No MoRT H Spec.

Description *4.Both the rollers have to be available at site to match with the output of batch mixing plant and paver finisher. A multiplying factor of 0.65 has been adopted to cater thickness period of road rollers. 40 mm for the idling a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Batch type cold mixing plant100-120 TPH capacity producing an average output of 75 tonne125 KVA Electric generator per hour Front end loader 1 cum capacity Paver finisher hydrostatic with sensor control @ 75 cum per hour Tipper 10 tonne capacity

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

5.22

(ii)

day day day hour hour hour hour tonne.k m

1.000 12.000 5.000

350.00 180.00 250.00

350.00 2160.00 1250.00 #VALUE! 5244.00 6252.00

L-12 L-13 L-15 P&M064 P&M018 P&M-

6.000 input 6.000 6.000 6.000 450 x L 874.00 1042.00

2182.00 13092.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Pneumatic tyred roller 12-15 tonnes. Smooth wheeled steel roller 6-8 tonnes. Water tanker6 KL capacity c) Material Bitumen emulsion @ 70 litres per tonne Crushed stone aggregates 14 mm nominalwater Cost of size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/205 5.22 (iii) 25 mm thickness a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Batch type cold mixing plant 100-120 TPH capacity producing an average output generator per hour Electricof 75 tonne125 KVA Front end loader 1 cum capacity Paver finisher hydrostatic with sensor control @ 75 cum per hour Tipper 10 tonne capacity

017 P&M034 4.00 63000.00 Lead =35 km & P&M058 6300.00 3478.80 1833.00 300.00 P&M037 P&M044 P&M060

hour6.00x0.65* hour6.00x0.65* hour tonne KL 1.000

892.00 470.00 300.00

31.500 input 6.000 input

#VALUE! M-077 #VALUE! M-052 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum 287.000 input

day day day hour hour hour hour tonne.k m

1.000 12.000 5.000

350.00 180.00 250.00

350.00 2160.00 1250.00 #VALUE! 5244.00 6252.00

L-12 L-13 L-15 P&M064 P&M018 P&M-

6.000 input 6.000 6.000 6.000 450 x L 874.00 1042.00

2182.00 13092.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Pneumatic tyred roller Smooth wheeled steel roller Water tanker6 KL capacity c) Material Bitumen emulsion @ 85 litres per tonne Crushed stone aggregates 6 mm nominalwater Cost of size d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10500 sqm = a+b+c+d+e

017 P&M034 4.00 63000.00 Lead =35 km & P&M058 6300.00 3478.80 1833.00 300.00 P&M037 P&M044 P&M060

hour6.00x0.65* hour6.00x0.65* hour tonne KL 1.000

892.00 470.00 300.00

38.250 input 6.000 input

#VALUE! M-077 #VALUE! M-050 #VALUE! M-189 #VALUE! #VALUE! #VALUE!

cum 270.000 input

Page 26 of 363

Ref. to Sr No MoRT H Spec.

Description Rate per sqm = (a+b+c+d+e)/205

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE!

say #VALUE!

Page 27 of 363

CHAPTER- 6 CEMENT CONCRETE PAVEMENTS


Ref. to Sr No MoRTH Spec. 6.1 601 Description Dry Lean Cement Concrete Sub- base Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with Unit = cum Taking output = 450 cum (990 tonne) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Front end loader 1 cum bucket capacity Cement concrete batch mix plant @ 75 Electric generator 100 KVA Paver with electronic sensor Vibratory roller 8-10 t capacity Water tanker6 KL capacity Tipper Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day day hour hour hour hour hour hour tonne.k m

1.120 6.000 22.000

350.00 250.00 180.00

392.00 1500.00 3960.00

L-12 L-15 L-13

6.000 1042.00 6252.00 6.000 input #VALUE! 6.000 793.00 4758.00 6.000 2182.00 13092.00 8.000 1339.00 10712.00 8.000 300.00 2400.00 990 x L 4.00 ###

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material Crushed stone coarse aggregate of 25 mm and 12.5 mm nominal sizes graded as per table 600-1 @ 0.90 cum/cum of concrete conforming to383 @ 0.45 Coarse Sand as per IS: clause 602.2.4. cum/cum of concrete Cement @ 150 kg/cum of concrete Cost of water d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 205 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/450 Note 6.2 602 Quantity provided for aggregate is for estimating purpose. Exact quantity shall be as per mix design. Cement Concrete Pavement Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, Unit = cum Taking output = 1050 cum (2415 a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Page 1 of 363

P&MP&MP&MP&MP&MP&MLead =35 km & P&M058 13860.00

cum 405.000

0.00

cum 203.000 input tonne KL 67.500 input 48.000 input

M-052 and M054 #VALUE! M-004

0.00

#VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day

2.000 15.000 35.000

350.00 250.00 180.00

700.00 3750.00 6300.00

L-12 L-15 L-13

Ref. to Sr No MoRTH Spec.

Description Road Sweeper @ 1250 sqm per hour Front end loader 1 cum bucket capacity Cement concrete batch mix plant @ 175 cum per hour (effective output) Electric generator 250 KVA Slip form paver with electronic sensor Water tanker6 KL capacity Transit truck agitator 5 cum capacity.

Unit hour hour hour hour hour hour tonne.k m

Quantity

Rate Rs

2.800 230.00 18.000 1042.00 6.000 input 6.000 6.000 36.000 2415xL 1336.00 2035.00 300.00 4.00

Add 10 per cent of cost of carriage to cover cost of loading and unloading Concrete joint cutting machine . Texturing machine . c) Material Crushed stone coarse aggregates of 25mm and 12.5mm nominal size @ 0.90 cum/cum of concrete conforming to clause 602.2.4. . and conforming to Sand as per IS: 383 clause 602.2.4 @ 0.45 cum/cum of concrete43 grade @ 400 kg/cum of Cement 32 mm mild steel dowel bars of grade S 16 mm deformed steel tie bars of grade Separation Membrane of impermeable plastic sheeting 125 micron thick Pre moulded Joint filler, 25 mm thick for expansion joint. Joint sealant Sealant primer Plastic sheath,1.25 mm thick for dowel Curing compound Super plastisizer admixture IS marked as per 9103-1999 @ 0.5 per cent by weight water Cost of of cement Add 1 per cent of material for cost of miscellaneous materials like tarpauline, Hessian cloth, metal cap, cotton / compressible sponge and cradle for dowel bars, work bridges for men to approach concrete surface without walking over it, cutting blades and bites, minor equipments like scabbling machine, threads, ropes, guide Overhead charges @ 2.244% on wires and any other unforeseen d) items. (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 1050cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/1050 Note The quantities for cement, coarse aggregate and fine aggregates are for estimating only .The exact quantities will be as per Cement Concrete Base Rolledmix design. Construction of rolled cement concrete base course with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement content of 200 kg/cum, aggregate gradation to be as per table 6004 after blending, mixing in batching plant at optimum moisture content, transporting to site, laying with a paver with electronic sensor, compacting with 8-10 tonnes Unit = cum Taking output = 450 cum (990 tonne) a) Labour Mate Mazdoor skilled Mazdoor Page 2 of 363

Remark Cost Rs s/ Input ref. 644.00 P&M18756.00 P&M#VALUE! P&M067 8016.00 P&M12210.00 P&M10800.00 P&M### Lead =35 km & P&M058 33810.00 #VALUE! #VALUE! P&MP&M-

hour hour

12.000 input 12.000 input 0.00

cum 945.000

cum 473.000 input tonne 414.000 tonne 9.450 tonne 1.170 sqm 3675.000 sqm input input input input

M-052 and M054 #VALUE! M-004 #VALUE! #VALUE! #VALUE! #VALUE! M-081 M-126 M-082 M-164

0.00

16.330 input input input input input input

#VALUE! M-141 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! M-120 M-097 M-138 M-090 M-180

kg 875.000 kg 116.670 sqm 46.670 liter 1850.000 kg 2070.000

KL 216.000 input

#VALUE! M-189 #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

6.3 603

day day day

1.200 7.000 23.000

350.00 250.00 180.00

420.00 1750.00 4140.00

L-12 L-15 L-13

Ref. to Sr No MoRTH Spec. b)

Description Machinery Front end loader 1 cum bucket capacity Cement concrete batch mix plant @ 75 cum pergenerator 100 KVA Electric hour Paver with electronic sensor @ 75 cum/hr. roller 8-10 t capacity Vibratory Water tanker with 5 km lead 6 KL capacity Tipper

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 6252.00 #VALUE! 4758.00 P&M017 P&M068 P&M080 P&M034 P&M059 P&M-

hour hour hour hour hour hour tonne.k m

6.000 6.000 6.000 8.000 8.000 990xL

1042.00 793.00

6.000 input

2182.00 13092.00 1339.00 10712.00 300.00 4.00 2400.00 ###

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material Crushed stone coarse aggregates of 25mm and 12.5mm nominal size @ 0.90 cum/cum of concrete conforming to clause 602.2.3. and conforming to Sand as per IS: 383 clause 602.2.3 @ 0.45 cum/cum of concrete Cement @ 200 kg/cum of concrete Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 450cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/450 Note The quantities for cement, coarse aggregate and fine aggregates are for estimating only .The exact quantities will be as per mix design. Transition Section between Rigid and Flexible Pavement Due to change in the properties of materials and type of construction, a gradual changeover from rigid pavement to flexible pavement is desirable to avoid any damage at the butting joint. After provision of an expansion joint in the cement concrete slab, the thickness of slab should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The deficiency of thickness caused due to tapering of the slab The quantities of items should be worked out based on the approved design and drawings and priced as per rates given under respective clauses for cement concrete and asphalticBase/Sub-Base of work. Construction of Pavement with Lean Concrete - Flyash. Construction of Base/sub-base using cement, sand, fly ash and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and with water content ratio, slump and compressive strength as defined in the said table, mix prepared in a batching and mixing plant and compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid down vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of day's work, cured for Unit = cum Taking output = 450 cum (990 tonne) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Front end loader 1 cum bucket capacity Cement concrete batch mix plant @ 75 cum per hour Page 3 of 363 hour hour 6.000 1042.00 day day day 1.120 6.000 22.000 350.00 250.00 180.00 cum 405.000 0.00

060 Lead =35 km & P&M058 13860.00

cum 203.000 input tonne KL 90.000 input 48.000 input

M-052 and M054 #VALUE! M-004 #VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE!

0.00

say #VALUE!

6.4 New

6.5 Suggesti ve

392.00 1500.00 3960.00 6252.00 #VALUE!

L-12 L-15 L-13 P&M017 P&M068

6.000 input

Ref. to Sr No MoRTH Spec.

Description Electric generator 100 KVA Paver finisher with electronic sensor Vibratory roller 8-10 t capacity Water tanker6 KL capacity Tipper 10 T Capacity

Unit hour hour hour hour tonne.k m

Quantity 6.000 6.000 8.000 8.000 990 x L

Rate Rs

Remark Cost Rs s/ Input ref. 793.00 4758.00 P&M080 2182.00 13092.00 P&M034 1339.00 10712.00 P&M300.00 4.00 2400.00 ### 059 P&M060 Lead

Add 10 per cent of cost of carriage to cover cost of loading and unloading c) Material Crushed stone coarse aggregate of 40 mm nominal size @ 0.90 cum/cum of concrete conforming to table 2 of IRC: 74-1979. Coarse Sand as per IS: 383 - 1970 Cement @ 150 kg/cum of concrete Fly ash conforming to IS: 3812 ( Part II ) ( Total fine aggregates = 450 x 0.45 = 202.50 cum To be divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC: 741979).Overhead charges @ 2.244% on d) (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 450cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/450 Note 1.Depending upon approved designs, crushed stone aggregates of nominal size 20mm can also be used as per gradation given in table specific gravities of fly ash 2.The ratio of 2 of IRC: 74-1979. and sand has been assumed to be 0.827. 3.The quantities of materials given in the analyses are for estimating purposes. Actual quantities shall be as per job mix formula. 4.Construction procedure as laid down in clause, of IRC: 74-1979 shall be followed. Cement - Flyash Concrete Pavement. Construction reinforced-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15 per cent and sand by 10 per cent, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, Unit = cum sealant primer, joint sealant, Taking output tonne) a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Road Sweeper @ 1250 sqm per hour Front end loader 1 cum bucket capacity Cement concrete batch mix plant @ 175 cum per hour (effective output) Electric generator 250 KVA Slip form paver with electronic sensor Water tanker6 KL capacity hour hour hour hour hour hour 2.800 18.000 230.00 = 1050 cum (2415 day day day 2.000 15.000 35.000 350.00 250.00 180.00 cum 405.000 input

=35 km & P&M058 13860.00

#VALUE! M-055

cum 110.960 input tonne cum 67.500 input 91.540 input

#VALUE! M-004 #VALUE! M-081 #VALUE! M-011

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

6.6 Suggesti ve

700.00 3750.00 6300.00 644.00 #VALUE! 8016.00

L-12 L-15 L-13 P&M031 P&M017 P&M067 P&M081 P&M006 P&M060

1042.00 18756.00

6.000 input 6.000 6.000 36.000 1336.00

2035.00 12210.00 300.00 10800.00

Page 4 of 363

Ref. to Sr No MoRTH Spec.

Description Transit truck agitator 5 cum capacity.

Unit tonne.k m

Quantity

Rate Rs

2415xL input

Add 10 per cent of cost of carriage to cover cost of loading and unloading Concrete joint cutting machine . Texturing machine . c) Material Crushed stone coarse aggregates of 25mm and 12.5mm nominal size @ 0.90 cum/cum of concrete conforming to clause 602.2.4. . and conforming to Sand as per IS: 383 clause 602.2.4 Cement 43 grade Fly ash conforming to IS: 3812-1966 (Part-I) 32 mm mild steel dowel bars of grade S 240 16 mm deformed steel tie bars of grade S 415 Separation Membrane of impermeable plastic sheeting 125 micron thick Pre moulded Joint filler, 25 mm thick for expansion joint. Joint sealant Sealant primer Plastic sheath,1.25 mm thick for dowel bars compound Curing Super plastisizer admixture IS marked as per 9103-1999 @ 0.5 per cent by weight water Cost of of cement Add 1 per cent of material for cost of miscellaneous materials like tarpauline, Hessian cloth, metal cap, cotton / compressible sponge and cradle for dowel bars, work bridges for men to approach concrete surface without walking over it, cutting blades and bites, minor equipments like scabbling machine, threads, ropes, d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 1050cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/1050 Note 1.The quantities for cement, coarse aggregate and fine aggregates are for estimating only .The exact quantities will be as per mix design. 2.IRC: 68-1976 may be referred for guidelines on the design of cement-fly ash concrete for rigid pavement construction. *Calculation of cement, sand and fly ash. Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes. 15 per cent of cement to be replaced by fly ash = 63 tonnes. Balance cement = 357 tonnes. Quantity of fly ash = 63 x specific gravity of fly ash /specific gravity of = Sand @ 0.45 cum / cum of concrete 1050 x 0.45 = 472.50 x 1.6 = 756 tonnes.10 per cent to be replaced by flyash. Balance sand = 756 x 0.9 = 680.4 tonnes = 680.4 / 1.6 = 425 cum. Quantity of flyash = (756-680.4) x specific gravity of fly ash/specific gravity of sand = 76.4 x 2.25 / 2.687 = Fly ash Total fly ash = 45 + 64 = 109 tonnes.

Remark Cost Rs s/ Input ref. #VALUE! P&M050 Lead= #VALUE! 35 km #VALUE! #VALUE! P&M083 P&M088

hour hour

12.000 input 12.000 input 0.00

cum 945.000

cum 425.000 input tonne 357.000 input tonne 109.000 input tonne tonne 9.450 input 1.170 input

M-052 and M054 #VALUE! M-004 #VALUE! M-081 #VALUE! M-011 #VALUE! M-126 #VALUE! M-082 #VALUE! M-164 #VALUE! M-141 #VALUE! M-120 #VALUE! M-097 #VALUE! M-138 #VALUE! M-090 #VALUE! M-180 #VALUE! M-189 #VALUE!

0.00

sqm 3675.000 input sqm 16.330 input

kg 875.000 input kg 116.670 input sqm 46.670 input liter 1850.000 input kg 2070.000 input KL 216.000 input

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 5 of 363

Ref. to Sr No MoRT H 7.1 Spec. 702

CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH


Description Sub-Surface Drain with Geotextiles Construction of sub surface drain 200 mm dia using geotextiles treated with carbon black with physical properties as given in clause 702.2.3 formed in to a stable network and a planar geocomposite structure, joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved drawings including Unit = Running metre Taking output = one metre a) Labour Mate Mazdoor skilled Mazdoor b) Material Geonets, geomembrane and geotextile to make planar geocomposite stable network for sub surface drain including wrapping of joints with 160 mm over lapping with geotextile . Geonets Geomembrane Geotextile Add 2 per cent cost of material for miscellaneous items like synthetic cord c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Rate per metre = a+b+c+d Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day day

0.040 0.250 0.500

350.00 250.00 180.00

14.00 62.50 90.00

L-12 L-15 L-13

sqm sqm sqm

1.000 input 1.000 input 2.000 input

#VALUE! M-107 #VALUE! M-106 #VALUE! M-108 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.2

Note Surplus excavated material to be used at site. Hence seprate cost for disposal not added. 702.4 Narrow Filter Sub-Surface Drain Construction of a narrow filter sub- surface drain consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed as per clause 702.3 and 309.3.5 including excavation and backfilling Unit = Running metre length Taking output = one metre a) Labour Mate Mazdoor skilled Mazdoor b) Material Perforated geosynthetic pipe 150 mm Geotextile filter fabric Add 2 per cent cost of material for miscellaneous item like synthetic cord c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Rate per metre = a+b+c+d Note Surplus excavated material to be used at site. Hence Separate cost for disposal not added. Laying Paving Fabric Beneath a Providing and laying paving fabric with physical requirements as per table 704-2 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to provide a water resistant membrane and crack retarding layer. Paving fabric to be free of wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface Unit = sqm Taking output = 2800 sqm a) Labour Page 1 of 363

day day day metre sqm

0.040 0.250 0.500

350.00 250.00 180.00

14.00 62.50 90.00

L-12 L-15 L-13

1.000 input 1.250 input

#VALUE! M-134 #VALUE! M-109 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.3

703

Ref. to Sr No MoRT H Spec.

Description Mate Mazdoor b) Machinery Road sweeper 1250 sqm per hour Pneumatic roller 14 tonnes 2000 sqm Bitumen pressure distributor 1750 sqm c) Material Paving Fabric Paving Bitumen 80-100 c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 2800 sqm = a+b+c+d+e Rate per sqm =(a+b+c+d+e)/2800 Laying Boulder Apron in Crates of Synthetic Geogrids Providing, preparing and laying of geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids having characteristics as per clause 704.2, joining sides with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the foundation recess cum Unit = in case of sloping ground and laid Taking output = 3.00 cum a) Labour Mate Mazdoor skilled Mazdoor b) Material Geo grids Connectors/ Staples Polymer braids Stones with minimum size of 200 mm Stones spall for filling voids c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 3 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 3

Unit day day hour hour hour

Quantity 0.800 20.000 2.240 1.400 1.680

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 280.00 L-12 180.00 3600.00 L-13 230.00 892.00 819.00 515.20 1248.80 1375.92 P&MP&MP&M-

sqm 2940.000 input tonne 2.800 input

#VALUE! M-133 #VALUE! M-075 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.4

704

day day day sqm each metre cum cum

0.060 0.500 1.500

350.00 250.00 180.00

21.00 125.00 270.00

L-12 L-15 L-13

21.000 input 50.000 input 20.000 input 3.450 input 0.450 input

#VALUE! M-105 #VALUE! M-085 #VALUE! M-140 #VALUE! M-003 #VALUE! M-008 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.5

3100

Reinforced Earth Structures Reinforced earth Structures have four main components as under: a) Excavation for foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia material). placement. b) Facia material and its c) Assembling, joining with facing elements and laying of the reinforcing elements. fill with granular material which d) Earth is to be retained by the wall. Each component is analysed separately as under: considering Average height of wall = 8 m.

7.5

3102

(i) A

Assembling, joining and laying of reinforcing elements. With reinforcing element of steel / Aluminium strips / polymeric strips. Unit = Running Metre Page 2 of 363

Ref. to Sr No MoRT H Spec.

Description Taking Output = 450 m a) Labour Mate Mazdoor Mazdoor skilled b) Material @ Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. 1.Galvanised carbon steel strips or 2.Copper Strips or 3.Aluminium Strips or 4.Stainless steel strips or 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips @ Any one of the above alternative may be adopted as per approved design. Add 10 per cent of the cost of reinforcing strip towards accessories like tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements with the facia pannels, overlaps, heat carbon steel strips Type 1 1.Galvanised bonding or extension. c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost of 450 Rate per metre =(a+b+c+d)/450 Type 2 2.Copper Strips c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost of 450 Rate per metre =(a+b+c+d)/450 Type 3 3.Aluminium Strips c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost of 450 Rate per metre =(a+b+c+d)/450 Type 4 4.Stainless steel strips c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost of 450 Rate per metre =(a+b+c+d)/450 Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) m = a+b+c+d Cost of 450 Rate per metre =(a+b+c+d)/450

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day

0.360 6.000 3.000

350.00 180.00 250.00

126.00 1080.00 750.00

L-12 L-13 L-15

metre metre metre metre metre

450*1.1 input 450*1.1 input 450*1.1 input 450*1.1 input 450*1.1 input

#VALUE! M-154 #VALUE! M-153 #VALUE! M-157 #VALUE! M-156 #VALUE! M-155

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.5(i)

With reinforcing elements of synthetic geogrids Unit = sqm Taking output = 300 sqm a) Labour Page 3 of 363

Ref. to Sr No MoRT H Spec.

Description Mate Mazdoor Mazdoor skilled b) Material Synthetic Geogrids as per clause 3102.8 and approved design and specifications. Add 10 per cent of the cost of reinforcing elements (synthetic geogrids) for accessories like tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements with the facia c) pannels, overlaps and other protective Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c)300 sqm of Synthetic geogrids = Cost of a+b+c+d sqm = (a+b+c+d)/ 300 Rate per

Unit day day day

Quantity 0.360 6.000 3.000

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 126.00 L-12 180.00 250.00 1080.00 750.00 L-13 L-15

sqm 300.000 input

#VALUE! M-181 #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.5

3104

(ii)

Facing elements of RCC Unit = sqm Taking output = 75 sqm a) Labour Mate Mazdoor Mazdoor skilled b) Machinery hour cu.m 6.000 13.500 230.00 1380.00 P&M013 Item 12.8 (H) Item 13.6 Light crane with lifting capacity upto 3 c) tonne Material Pre-cast RCC M-35 facing elements of size as per design and 18 cm thick for 75 sqm. (Refer Item 12.8 (H)) HYSD steel @ 5 kg / sqm (Refer Item Add 12.6) cent of cost of facia pannels, for 2 per all necessary temporary form work, scaffolding and provision of loops/lugs for lifting of pannels and joining the reinforcing elements. d) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on e) (a+b+d) Cost for 75 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/ 75 day day day 0.180 3.000 1.500 350.00 180.00 250.00 63.00 540.00 375.00 L-12 L-13 L-15

#VALUE! #VALUE!

tonnes

0.380

#VALUE! #VALUE! #VALUE!

52.91 120.55 #VALUE! #VALUE! say #VALUE!

Note 1.The specification and construction details to be adopted shall be as per section 3100 of MoRTH Specification. shall be made as 2.Drainage arrangement per approved design and drawings. 3.The quantity of filler media shall be calculated as per approved design and specifications and shall be priced separately.The rate for same to be adopted from chapter for foundation including 4.Excavation 15. foundation concrete and groove in the foundation for seating of bottom most facia panel and capping beam to be calculated as per design and priced separately. The rates for excavation and foundation concrete shall be taken from the chapter 12 & 13 in 5.The earth fill to be retained is not included in this analysis. The same is to be worked out and provided separately complete as per clause 305. 6.For compaction of Earthwork, attention is invited toof reinforcing strips will vary with 7.Length clause 3105.5 of MoRTH Specification.wall and will be as per the height of approved design and drawings. 8.The type of reinforcing elements to be adopted shall be as per approved design and specifications.

Page 4 of 363

Ref. to Sr No MoRT H Spec.

Description 9.The market rate for supply of reinforcing elements and their accessories are to be ascertained from reputed firms in the field of earthearth fill material shall be clean, free 10.The reinforcement. draining, granular with high friction and low cohesion, non-corrosive, coarse grained with not 10 per cent of particles passing 75 micron sieve, free of any deleterious matter, chlorides, salts, acids, alkalies, mineral oil, fungus and microbes and shall 11.Capping beam is to be priced separately as per approved design. The rate for cement concrete shall be taken from the chaptercost of reinforcedin bridge section. 12.The of sub-structure earth retaining wall shall include following: (I) Excavation for foundation including backfilling. (ii) Foundation concrete as per approved design. of facial pannels and their (iii) Cost erection . reinforcing elements including (iv) Cost of their fixing and joining with the facial pannels. (v) Drainage arrangement including filter media as per approved design and drawings. 13. The compacted earth filling to be retained shall form part of embankment.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Page 5 of 363

Ref. to Sr No MoRT H 8.1 Spec. 408

CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES


Description Cast in Situ Cement Concrete M20 Kerb top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause Unit = Running metre Taking output = 360 metre Using Concrete Mixer Cement Concrete Cement concrete of grade M20 = 12.60 cum Cement concrete of grade M10 for base= 11.61 cum Total Concrete = 24.21 cu.m a) Labour Mate Mason Mazdoor b) Machinery Kerb casting machine @ 60 metres/hour Concrete mixer 0.48/0.28 cum capacity Water tanker6 KL capacity c) Material Crushed stone aggregate 20 mm nominal size 59 per cent Coarse sand 30 per cent Cement 11 per cent Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 meter = a+b+c+d+e Rate per metre = (a+b+c+d+e)/360 Using Concrete Batching and Mixing Plant Cement Concrete Cement concrete of grade M20 = 12.60 cum Cement concrete of grade M10 for base = 11.61 cum Total Concrete = 24.21 cu.m a) Labour Mate Mason Mazdoor b) Machinery Kerb casting machine @ 60 metres/hour Concrete batching and mixing plant @ 15 cum/hr. Water tanker6 KL capacity Tipper 5.5 cum capacity c) Material Crushed stone aggregate 20 mm nominal size 59 per cent Coarse sand 30 per cent Cement 11 per cent Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 meter = a+b+c+d+e Rate per metre = (a+b+c+d+e)/360 Cast in Situ Cement Concrete M 20 Kerb with Channel channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCCM20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause Page 1 of 363 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

A.

day day day hour hour hour cum cum tonne KL

0.720 2.000 16.000 6.000 12.000 5.000 21.790

350.00 250.00 180.00 200.00 165.00 300.00 input

252.00 500.00 2880.00 1200.00 1980.00 1500.00

L-12 L-11 L-13 P&MP&MP&M-

#VALUE! M-053 #VALUE! M-005 #VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

10.900 input 5.700 input 30.000 input

day day day hour hour hour hour cum cum tonne KL

0.120 1.000 2.000 6.000 1.600 5.000 6.000 21.790

350.00 250.00 180.00 200.00 1272.00 300.00 497.00 input

42.00 250.00 360.00 1200.00 2035.20 1500.00 2982.00

L-12 L-11 L-13 P&MP&MP&MP&M-

#VALUE! M-053 #VALUE! M-004 #VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

10.900 input 5.700 input 30.000 input

8.2

408

Ref. to Sr No MoRT H Spec.

Description A Using Concrete Mixer Unit = Running metre Taking output = 300 metre length Cement Concrete Cement concrete of grade M20= 17.48 cum Cement concrete of grade M10 for base = 23.18 cum Total Concrete = 40.66 cum a) Labour Mate Mason Mazdoor b) Machinery Kerb casting machine @ 50 metres/hour for laying kerb and channel Concrete mixer 0.48/0.28 Water tanker6 KL capacity c) Material Crushed stone aggregate 20 mm nominal size 60 per cent Coarse sand 30 per cent Cement 10 per cent Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 360 meter = a+b+c+d+e Rate per metre = (a+b+c+d+e)/300

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour hour hour cum cum tonne KL

0.720 2.000 16.000 6.000 16.000 6.000 36.590

350.00 250.00 180.00 200.00 165.00 300.00 input

252.00 500.00 2880.00 1200.00 2640.00 1800.00

L-12 L-11 L-13 P&M029 P&M009 P&M060

#VALUE! M-053 #VALUE! M-005 #VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

18.300 input 9.010 input 36.000 input

8.2

Using Concrete Batching and Mixing Plant Unit = Running metre Taking output = 300 metre length Cement Concrete Cement concrete of grade M20= 17.48 cum Cement concrete of grade M10 for base = 23.18 cum Total Concrete = 40.66 cum a) Labour Mate Mason Mazdoor b) Machinery Kerb casting machine @ 50 metres/hour for laying kerb and channel Concrete batching and mixing plant @ 15 cum/hr. Water tanker6 KL capacity Tipper of 5.5 cum capacity c) Material Crushed stone aggregate 20 mm nominal size 60 per cent Coarse sand 30 per cent Cement 10 per cent Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 300 meter = a+b+c+d+e Rate per metre = (a+b+c+d+e)/300 day day day hour hour hour hour cum cum tonne KL 0.120 1.000 2.000 6.000 2.700 6.000 6.000 36.590

350.00 250.00 180.00 200.00 1272.00 300.00 497.00 input

42.00 250.00 360.00 1200.00 3434.40 1800.00 2982.00

L-12 L-11 L-13 P&M029 P&M003 P&M060 P&M048

#VALUE! M-053 #VALUE! M-004 #VALUE! M-081 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

18.300 input 9.010 input 36.000 input

8.3

801

Printing New Letter and Figures of any Shade Printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade Page 2 of 363

Ref. to Sr No MoRT H Spec.

Description (i)

Unit

Quantity

Rate Rs

Hindi ( Matras commas and the like not to


be measured and paid for Half letter shall be counted 100 letters of 16 cm height Details foras half ) i.e. 1600 cm Unit = per cm height per letter a) Labour Mate Painter Mazdoor b) Material Litre 0.700 input Paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1600 cm = a+b+c+d Rate per cm height per (a+b+c+ d)/1600 letter = day day day 0.120 2.000 1.000 350.00 250.00 180.00

Remark Cost Rs s/ Input ref.

42.00 500.00 180.00

L-12 L-18 L-13

#VALUE! M-131 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.3

(ii)

English and Roman Hyphens and the like not to be measured and paid for100 letters of 16 cm height. Detail for i.e.1600 cm Unit = per cm height per letter a) Labour Mate Painter Ist class Mazdoor b) Material Litre 0.500 input #VALUE! M-131 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 1600 cm = a+b+c+d Rate per cm height per letter = (a+b+c +d)/1600 day day day 0.070 1.250 0.500 350.00 250.00 180.00 24.50 312.50 90.00 L-12 L-18 L-13

8.4

801

Retro-Reflectorised Traffic Signs cautionary, mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below Unit = Each Taking output = one traffic sign i) Excavation for foundation cum cum sqm day day kg 0.216 0.120 0.430 0.010 0.250 19.000 36.07 Item No. 3.13 #VALUE! #VALUE! Item 12.8 (A) #VALUE! #VALUE! Item 8.9 350.00 180.00 3.50 45.00 L-12 L-13 167.00

ii) Cement concrete M15 grade iii) Painting angle iron post two coats a) Labour (For fixing at site) Mate Mazdoor b) Material Mild steel angle iron 75 x 75 x 6 mm Aluminium sheeting fixed with encapsulated lens type reflective sheeting of size including lettering and signs as applicable Add 2 per cent of cost of angle iron towards cost of drilling holes, nuts, bolts etc. 90 cm equilateral triangle or ( ii ) 60 cm equilateral triangle Page 3 of 363

#VALUE! #VALUE! M-179 / 1000

(i)

sqm sqm

0.350 input 0.156 input

#VALUE! M-061 #VALUE! M-061

Ref. to Sr No MoRT H Spec. ( iii ) ( iv ) (v) (vi ) ( vii ) c) (i)

Description or 60 cm circular or 80 mm x 60 mm rectangular or 60 cm x 45 cm rectangular or 60 cm x 60 cm square or 90 cm high octagon Machinery Tractor-trolley 90 cm equilateral triangle d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) ( ii ) 60 cm equilateral triangle d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) ( iii ) 60 cm circular d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) ( iv ) 80 mm x 60 mm rectangular d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) ( v ) 60 cm x 45 cm rectangular d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) (vi ) 60 cm x 60 cm square d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) ( vii ) 90 cm high octagon d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1.Any one area of aluminium sheeting given at (i) to (vii) may be adopted as per site requirement and in accordance with IRC : 67 2.Rate for excavation, cement concrete M15 and painting may be taken from respective chapters 3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having higher wind velocities like in coastal areas. This is applicable to all road signs and directions boards. Direction and Place Identification Signs upto 0.9 sqm Size Board. Page 4 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! M-061 #VALUE! M-061 #VALUE! M-061 #VALUE! M-061 #VALUE! M-061 3.00 #VALUE! #VALUE! P&M053

sqm sqm sqm sqm sqm hour

0.283 input 0.480 input 0.270 input 0.360 input 0.672 input 0.010 300.00

#VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note

8.5

801

Ref. to Sr No MoRT H Spec.

Description identification retro-reflectorised sign as per IRC:67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved Unit = sqm Taking output = 0.9 sqm i) Excavation for foundation ii) Cement concrete M15 grade iii) Painting angle iron post two coats a) Labour (For fixing at site) Mate Mazdoor b) Material Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 metres long Aluminium sheeting fixed with encapsulated lens type reflective sheeting of size 0.9 sqm Add 2 per cent of cost of materials for drilling holes, nuts, bolts, fabrication etc. c) Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e Rate per sqm (for sign having area upto 0.9 sqm) = (I+ii+iii+a+b+c+d+e)/0.90 I) Lettering and arrow marks on sign board to be provided separately as per actual Note requirement. Rates for these items have been analysed separately ii) Rate for excavation, cement concrete M15 and painting may be taken from respective chapters Place Identification Direction and Signs with size more than 0.9 sqm size Board. identification retro- reflectorised sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per Unit = sqm Taking output = 1.50 sqm i) Excavation for foundation

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum cum sqm day day kg sqm

0.216 0.120 0.430 0.010 0.200 19.000 0.900

36.07 Item No. 3.13 #VALUE! #VALUE! Item 12.8 (A) #VALUE! #VALUE! Item 8.9 350.00 180.00 3.50 36.00 L-12 L-13

167.00

#VALUE! #VALUE! M-179 / 1000 input #VALUE! M-061

hour

0.020

300.00

6.00 #VALUE! #VALUE! #VALUE! #VALUE!

P&M053

say #VALUE!

8.6

801

cum cum sqm day day kg sqm

0.430 0.240 0.860 0.010 0.300 38.000 1.500

ii) Cement concrete M15 grade iii) Painting angle iron post 2 coats a) Labour (For fixing at site) Mate Mazdoor b) Material Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 metres long, 2 nos Aluminium sheeting fixed with encapsulated lens type reflective sheeting Page 5 of 363

71.81 Item No. 3.13 #VALUE! #VALUE! Item 12.8 (A) #VALUE! #VALUE! Item 8.9 350.00 180.00 3.50 54.00 L-12 L-13

167.00

#VALUE! #VALUE! M-179 / 1000 input #VALUE! M-061

Ref. to Sr No MoRT H Spec.

Description Add 2 per cent of cost of materials for drilling holes, nuts, bolts, fabrication etc. c) Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e Rate per sqm ( for sign having area more than 0.9 sqm) = ( i+ii+iii+a+b+c+d+e)/1.50 i) Lettering and arrow marks on sign board to be provided separately as per actual Note requirement. Rates for these items have been analysed separately ii) Rate for excavation, cement concrete M15 and painting may be taken from respective chapters Overhead Signs a corrosion resistant 2mm thick aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles and trusses of sections and type as per structural design A Truss and Vertical Support Unit = tonne Taking output = 1 tonne a) Labour Mate Blacksmith Mazdoor including for handling & fixing at site. b) Material Aluminium alloy/galvanised steel including 5 per cent wastage Add 1 per cent on cost of material for nuts, bolts and drilling and welding consumables Add 15 per cent on cost of material for fabrication of trusses as per approved design c) Machinery Crane 3 tonne capacity Truck d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per tonne = (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

hour

0.020

300.00

6.00 #VALUE! #VALUE! #VALUE! #VALUE!

P&M053

say #VALUE!

8.7

802

day day day tonne

0.240 2.000 4.000 1.050

350.00 250.00 180.00 input

84.00 500.00 720.00

L-12 L-02 L-13

#VALUE! M-060 #VALUE! #VALUE!

hour hour

3.000 0.500

230.00 497.00

690.00 248.50 #VALUE! #VALUE!

P&M013 P&M057

8.7

Aluminium Alloy Plate for Over Head Sign Unit = sqm Taking output = 1 sqm a) Labour Mate Blacksmith Mazdoor b) Material Aluminium alloy plate,2 mm thick, fixed with high intensity grade sheeting vide clause 801.3 Miscellaneous Add 1 per cent of cost of labour for lifting arrangement, like ladders, pulleys, ropes etc c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per sqm = (a+b+c+d) day day day sqm 0.020 0.100 0.150 1.000

#VALUE! say #VALUE!

350.00 250.00 180.00 input

7.00 25.00 27.00

L-12 L-02 L-13

#VALUE! M-059

0.59 #VALUE! #VALUE! #VALUE!

Page 6 of 363

Ref. to Sr No MoRT H Spec.

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

1. The cost of excavation and foundation concrete for fixing of vertical support Note system to be worked out separately as per the approved drawing/design and to be included in the estimate. 2. Lettering and arrow marks on sign board to be provided separately as per actual requirement. Rates for these items have been included separately in New Concrete Painting Two Coats on this chapter. Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces Unit = sqm Taking output = 40 sqm a) Labour Mate Painter Mazdoor b) Material Paint conforming to requirement of clause 803.3. Add for scaffolding @ 1 per cent of labour cost where required Add @ 5 per cent cost of labour and materials to prepare the surface by filling minuts roughness on the surface and priming the surface before laying 2 c) coats of painting. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 40 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/40 8.9 803 Painting on Steel Surfaces Providing and applying two coats of ready mix paint of approved brand on steel surface after through cleaning of surface to give an even shade Unit = sqm Taking output = 10 sqm a) Labour Mate Painter Mazdoor b) Material Paint ready mixed approved brand. Add @ 1 per cent on cost of material for scaffolding Add @ 5 per cent cost of labour and materials to prepare the surface by filling minuts roughness on the surface and priming the surface before laying 2 c) coats of painting. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm= (a+b+c+d)/10 8.10 803 Painting on Wood Surfaces Providing and applying two coats of ready mix paint of approved brand on wood surface after thorough cleaning of surface to give an even shade Unit = sqm Taking output = 10 sqm a) Labour Mate day 0.030 Litre 1.250 input day day day 0.030 0.450 0.250 day day day Litre 0.120 2.000 1.000

say #VALUE!

8.8

803

350.00 250.00 180.00

42.00 500.00 180.00

L-12 L-18 L-13

6.000 input

#VALUE! M-132 #VALUE! #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

350.00 250.00 180.00

10.50 112.50 45.00

L-12 L-18 L-13

#VALUE! M-131 #VALUE! #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

350.00

10.50

L-12

Page 7 of 363

Ref. to Sr No MoRT H Spec. b)

Description Painter Mazdoor Material Paint ready mixed of approved brand. Add @ 1 per cent on cost of material for scaffolding Add @ 5 per cent cost of labour and materials to prepare the surface by filling minuts roughness on the surface and priming the surface before laying 2 c) coats of painting. Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/10

Unit day day Litre

Quantity 0.500 0.200

Rate Rs

Remark Cost Rs s/ Input ref. 250.00 125.00 L-18 180.00 36.00 L-13

1.500 input

#VALUE! M-131 #VALUE! #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.11

803

Painting Lines, Dashes, Arrows etc on Roads in Two dashes,on New etc on roads Painting lines, Coats arrows Work in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control cm in width Over 10 Unit = sqm Taking output = 10 sqm a) Labour Mate Painter Mazdoor b) Material Litre 1.480 input #VALUE! M-132 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Road marking Paint as per IS :164 c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm= (a+b+c+d)/10 day day day 0.090 0.550 1.550 350.00 250.00 180.00 31.50 137.50 279.00 L-12 L-18 L-13

(i)

8.11

(ii)

Up to 10 cm in width Unit = sqm Taking output = 10 sqm a) Labour Mate Painter Mazdoor b) Material Litre 1.480 input #VALUE! M-132 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Road marking paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/10 day day day 0.070 0.350 1.350 350.00 250.00 180.00 24.50 87.50 243.00 L-12 L-18 L-13

8.12

803

Painting Lines, Dashes, Arrows etc on Roads in Two Coats arrows etc on Painting lines, dashes,on Old Work roads in two coats on old work with ready mixed road marking paint conforming to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control10 cm in width Over Unit = sqm Taking output = 10 sqm a) Labour Page 8 of 363

(i)

Ref. to Sr No MoRT H Spec.

Description Mate Painter Ist class Mazdoor b) Material Road marking paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/10

Unit day day day Litre

Quantity 0.060 0.300 1.250

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 21.00 L-12 250.00 180.00 75.00 225.00 L-18 L-13

0.900 input

#VALUE! M-132 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.12

(ii)

Up to 10 cm in width Unit = sqm Taking output = 10 sqm a) Labour Mate Painter Ist class Mazdoor b) Material Litre 0.900 input #VALUE! M-132 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Road marking Paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 10 sqm= a+b+c+d Rate per sqm = (a+b+c+d)/10 Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes. Unit = sqm Taking output = 600 sqm a) Labour Mate Mazdoor b) Machinery Road marking machine @ 60 sqm per hour Tractor-trolley Material Hot applied thermoplastic compound Reflectorising glass beads d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 600 sqm = a+b+c+d+e Rate per sqm = a+b+c+d+e)/600 Litre kg 1500.000 input 150.000 input day day hour hour 0.030 0.750 10.000 0.500 350.00 180.00 72.00 300.00 10.50 135.00 720.00 150.00 L-12 L-13 P&M043 P&M053 #VALUE! M-118 #VALUE! M-152 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! day day day 0.070 0.350 1.350 350.00 250.00 180.00 24.50 87.50 243.00 L-12 L-18 L-13

8.13

803

c)

8.14

804

1. A sealing primer may be applied in advance on cement concrete pavement to ensure proper bonding. Any laitance and/or Note curing compound to be removed where paint is required to be applied on concrete surface. painter is already included in hire 2.Cost of charges of road marking machine. Kilometre Stone Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc (i) 5th kilometre stone (precast) Page 9 of 363

Ref. to Sr No MoRT H Spec.

Description Unit = Nos. Taking output = 6 Nos. a) M-15 grade of concrete

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum

2.350

#VALUE! #VALUE!

b) Steel reinforcement @ 5 kg kg 22.080 per sqm c) Excavation in soil for cum 1.680 foundation d) Painting two coats on sqm 9.850 concrete surface per cm e) Lettering on km post (average per 1800.000 30 letters of 10 cm height each) letter Transportation and fixing f) Labour Mate Mason Mazdoor including loading/unloading g) Machinery hour 6.000 Tractor-trolley h) Overhead charges @ 2.244% on (f+g)Contractor's profit @ 5% on i) (f+g+h) 6 Nos. 5th km stone = a+b+c+ Cost for d+e +f+g+h +i Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i ) /6 8.14 (ii) Ordinary kilometer stone (precast) Unit = Nos. Taking output = 14 Nos. a) M-15 grade of concrete cum kg cum 3.770 26.320 2.770 day day day 0.260 0.600 6.000

Item 12.8 (A) #VALUE! #VALUE! Item 13.6 / 1000 167.00 280.56 Item No. 3.13 #VALUE! #VALUE! Item 8.8 #VALUE! #VALUE! Item 8.3

350.00 250.00 180.00 300.00

91.00 150.00 1080.00 1800.00 70.04 159.55 #VALUE! #VALUE!

L-12 L-11 L-13 P&M053

say #VALUE!

#VALUE! #VALUE!

b) Steel reinforcement @ 5 kg per sqm c) Excavation in soil for foundation d) Painting two coats on concrete surface km post e) Lettering on ( average 12 letters of 10 cm height each) Transportation and fixing f) Labour Mate Mason Mazdoor g) Machinery Tractor-trolley h) Overhead charges @ 2.244% on (f+g)Contractor's profit @ 5% on i) (f+g+h) Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i) Rate for each ordinary km stone = (a+b+ c +d+e+f+g+h+j) /14 8.14 (iii) Hectometer stone (precast) Unit = Nos. Taking output = 33 Nos. a) M-15 grade of concrete

sqm 11.410 per cm per 1680.000 letter

Item 12.8 (A) #VALUE! #VALUE! Item 13.6 / 1000 167.00 462.59 Item No. 3.13 #VALUE! #VALUE! Item 8.8 #VALUE! #VALUE! Item 8.3

day day day hour

0.320 1.000 7.000 6.000

350.00 250.00 180.00 300.00

112.00 250.00 1260.00 1800.00 76.79 174.94 #VALUE! #VALUE!

L-12 L-11 L-13 P&M053

say #VALUE!

cum

1.580 66.000 1.390 6.270 330.000

#VALUE! #VALUE!

b) Steel reinforcement @ 5 kg kg per sqm c) Excavation in soil for cum foundation d) Painting two coats on sqm concrete surface per cm e) Lettering on km post (average per 1 letter of 10 cm height each) letter Page 10 of 363

Item 12.8 (A) #VALUE! #VALUE! Item 13.6 / 1000 167.00 232.13 Item No. 3.13 #VALUE! #VALUE! Item 8.8 #VALUE! #VALUE! Item 8.3

Ref. to Sr No MoRT H Spec.

Description Transportation and fixing f) Labour Mate Mason Mazdoor g) Machinery Tractor-trolley h) Overhead charges @ 2.244% on (f+g)Contractor's profit @ 5% on i) (f+g+h) Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+ g+h+i) Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i) 33 The rate for excavation, cement concrete, Note steel reinforcement, painting and lettering may be taken from respective chapters.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.340 1.500 7.000 6.000

350.00 250.00 180.00 300.00

119.00 375.00 1260.00 1800.00 79.75 181.69 #VALUE! #VALUE!

L-12 L-11 L-13 P&M053

say #VALUE!

8.15

805

Road Delineators Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming toIRC-79 and the drawings. Unit = Each Taking output= 30 Nos. a) Labour Mate Mazdoor for fixing b) Material Cost of approved type of delineators from ISI certified firm as per the Add standard drawing given in IRC - 79 10 per cent cost of material for installation c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 30 Nos. delineators = (a+b+ c+d) Rate per delineators = (a+b+c+d) /30 In case of soft ground, a proper foundation may be provided as per approved design. In case foundation is required to be provided, Note the items of excavation and foundation concrete are required to be measured and paid separately. Boundary pillar Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in position including finishing and lettering but excluding paintingEach Unit = Taking output = 57 Nos. a) M-15 grade of the boundary stone b) c) d) Steel reinforcement Excavation in soil Lettering, each 10 cm high cum kg 1.250 79.800 day day each 0.040 1.000 30.000 350.00 180.00 input 14.00 180.00 L-12 L-13

#VALUE! M-091 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.16

806

#VALUE! #VALUE!

Transportation and fixing e) Labour Mate Mazdoor Page 11 of 363

cum 10.720 per letter 2280.000 per cm high

Item 12.8 (A) #VALUE! #VALUE! Item 13.6 / 1000 167.00 1790.24 Item No. 3.13 #VALUE! #VALUE! Item 8.3

day day

0.570 14.250

350.00 180.00

199.50 2565.00

L-12 L-13

Ref. to Sr No MoRT H Spec.

Description f) g) Machinery Tractor-trolley Material Stone spall h) Overhead charges @ 2.244% on (e+f+g) i) Contractor's profit @ 5% on (e+f+g+h) Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i ) Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 In case of soft ground, a proper foundation may be provided as per approved design. In case foundation is required to be provided, Note the items of excavation and foundation concrete are required to be measured and paid separately. G.I Barbed Wire Fencing 1.2 Metre High barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc Unit = per running metre Taking output = 30 metres a) Labour Mate Blacksmith Mazdoor b) Material Barbed wire 335 metres length @ 9.38 kg per 100 metres MS angle iron 40 mm x 40mm x 6 mm, 23 metres in length @ 3.5 kg per metre Add for GI staple binding wire, drilling holes etc. @ 2 per cent of the cost of material c) Painting Applying two coats of painting on exposed surface of angle iron posts d) ( Rate as per item no. 8.9)2.244% on Overhead charges @ (a+b) Contractor's profit @ 5% on e) (a+b+d) Cost for 30 metres fencing = a+b+c+d+e Rate per metre = (a+b+c+d+e)/30 Cost of excavation for foundation and foundation concrete to be added separately Note in the cost estimate as per approved design. The rate for these items may be taken from respectiveFencing 1.8 Metre G.I Barbed Wire chapters. High barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc Unit = per running metre Taking output = 30 metres a) Labour Page 12 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 1800.00 P&M053

hour cum

6.000

300.00

11.970 input

#VALUE! M-008 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.17

807

day day day kg kg

0.090 0.250 2.000 31.420 80.500

350.00 250.00 180.00 input

31.50 62.50 360.00

L-12 L-02 L-13

#VALUE! M-063

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! #VALUE! Item 8.9 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

sqm

2.110

8.18

807

Ref. to Sr No MoRT H Spec.

Description Mate Blacksmith Mazdoor b) Material Barbed wire 428 metres length @ 9.38 kg per 100 metres MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in length @ 4.5 kg per metre GI staple, binding wire, drilling Add for holes etc. @ 2 per cent of the cost of material c) Painting Applying two coats of painting on exposed surface of angle iron posts d) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on e) (a+b+d) Cost for 30 metres fencing = a+b+c+d+e Rate per metre fencing = (a+b+c +d+e)/30 Cost of excavation for foundation and foundation concrete to be added separately Note in the cost estimate as per approved design. The rate for these items may be taken from respective chapters.

Unit day day day kg kg

Quantity 0.120 0.400 2.500 40.150 152.000

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 42.00 L-12 250.00 180.00 100.00 450.00 L-02 L-13

input

#VALUE! M-063

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! #VALUE! Item 8.9 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

sqm

3.960

8.19 Sugge stive

Fencing With Welded Steel Wire Fabric 75 mm x 50 mm angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete, corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in Unit = Running metre Taking output = 30 m a) Labour Mate Welder Mazdoor b) Material i) Angle iron for posts 50 x 50 x 6 mm ii) Runner flat 50 x 5 mm iii) Welded steel wire fabric 75x50 mm mesh @ 4 kg/sqm,4 x 30 x 1.2 + 5 per cent wastage OR Welded steel wire fabric 75 x 25 mm mesh @ 7.75 kg/sqm, 7.75 x 30 x 1.2 + per cent wastage Add 52.5 per cent of cost of material for drilling holes in angles, flats, splitting angle at bottom, nuts and bolts and welded consumables c) Machinery Tractor-trolley d) Painting sqm 8.000 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Painting two coats including priming e) Overhead charges @ 2.244% on (a+b+c) f) Contractor's profit @ 5% on (a+b+c+e) Cost for 30 metre = a+b+c+d+e+f Rate per metre = (a+b+c+d+e+f)/30 i) Adopt any one type of welded steel wire Note fabric 75 x 50 mm or 75 x 25 mm as per approved design. kg kg kg #VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 26.000 1000 input #VALUE! M-191 151.000 106.000 day day day 0.120 1.000 2.000 350.00 250.00 180.00 42.00 250.00 360.00 L-12 L-02 L-13

kg

293.000

hour

0.100

300.00

30.00

P&M053

#VALUE! #VALUE! Item 8.9

Page 13 of 363

Ref. to Sr No MoRT H Spec. 8.20 808

Description ii) The item of excavation and cement concrete in foundation shall be measured and paid separatelyRailing on Medium Tubular Steel Weight Steel Channel ( ISMC series) 100 mm x fixing and erecting 50 mm dia Providing, 50 mm steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings Unit = Running metre Taking output = 10metres i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 0.3 iii) Painting of pipe iv) Painting of channel section 6 nos,1.8 metres each 0.2 x 1.8 x 6 = 2.16 a) Labour (For fixing at site) Mate Mazdoor Plumber b)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum cum sqm sqm day day day

1.296 0.648 4.710 2.160 0.010 0.250 0.010

216.43 Item No. 3.13 #VALUE! #VALUE! Item 12.8 (A) #VALUE! #VALUE! Item 8.9 #VALUE! #VALUE! Item 8.9

167.00

350.00 180.00 250.00

3.50 45.00 2.50

L-12 L-13 L-02

Material Steel pipe 50 mm external dia as per metre IS:1239 weight steel channel (ISMC Medium kg series) 100 mm x 50 mm,10.8 metres Add length @ 9.2 kg per metre cent of cost for drilling holes @ 2 per of channels c) Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) 10 Cost for metre =i+ii+iii+iv+ a+b+c+d+e per Rate metre = (i+ii+iii+iv+a+b+c+d+e)/10 8.21 808 Tubular Steel Railing on Precast RCC Posts, 1.2 m High Above Ground Level Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing Unit = Running metre Taking output = 10metres i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 x 0.3 iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres each iv) Painting of pipe a) Labour Mate Mazdoor Plumber b) c) Material Steel pipe 50 mm dia as per IS:1239 Machinery hour Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) 10 Cost for metre =i+ii+iii+iv+ a+b+c+d+e per Rate metre = (i+ii+iii+iv+a+b+c+d+e)/10 Page 14 of 363 metre day day day cum cum cum sqm hour

#VALUE! M-175 30.000 input #VALUE! #VALUE! M-179 / 99.360 1000 #VALUE! 0.040 300.00 12.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053

1.296 0.648 0.320 4.710 0.014 0.350 0.010

216.43 Item No. 3.13 #VALUE! #VALUE! Item 12.8 (A) #VALUE! #VALUE! Item 14.1(A) #VALUE! #VALUE! Item 8.9 350.00 180.00 250.00 4.90 63.00 2.50 L-12 L-13 L-02

167.00

30.000 input 0.250 300.00

#VALUE! M-175 75.00 #VALUE! #VALUE! #VALUE! #VALUE! P&M053

Ref. to Sr No MoRT H Spec. 8.22 809

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Reinforced Cement Concrete Crash Barrier crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, Unit = Linear metre Taking output = 10 m (i) a) M 20 grade concrete M 20 grade concrete b) Labour Mate Mazdoor c) Material HYSD steel reinforcement including dowel bars Pre-moulded asphalt filler board d) Overhead charges @ 2.244% on (b+c) Contractor's profit @ 5% on e) (b+c+d) Cost for 10 metre = a+b+c+d+e Rate per metre = (a+b+c+d+e)/10 Note i) Excavation and backfilling are incidental to work and not to be measured separately. ii) Rate for RCC M 20 may be taken from chapter on super structure. Metal Beam Crash Barrier Type - A, "W" : Metal Beam Crash Barrier crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm Unit = Running metre Taking output = 4.5 metre length a) Labour Mate Blacksmith Mazdoor b) c) Machinery Tractor-trolley Material Corrugated sheet,3 mm thick, "W" beam section railing,4.5 m in length Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg per metre Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 16.4 kg per metre Nuts and bolts Add 25 per cent of the cost of material for fabrication, nuts, bolts and washers etc.) Page 15 of 363 hour kg kg kg kg 0.100 41.210 day day day 0.060 0.500 1.000 day day tonne sqm 0.040 1.000 cum 3.000

say #VALUE!

#VALUE! #VALUE!

Item 14.1(A) L-12 L-13

350.00 180.00

14.00 180.00

0.280 input 0.320 input

#VALUE! M-082 #VALUE! M-144 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.23

810 A

350.00 250.00 180.00 300.00

21.00 125.00 180.00 30.00

L-12 L-02 L-13 P&M053

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 88.560 1000 #VALUE! #VALUE! M-179 / 16.240 1000 #VALUE! M-130 20.000 input #VALUE!

Ref. to Sr No MoRT H Spec.

Description d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 4.5 metre = a+b+c+d+e Rate per metre = (a+b+c+d+e)/4.5

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE!

8.23

Type - B, "THRIE" : Metal Beam Crash Barrier beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm Unit = Running metre Taking output = 4.5 metre length a) Labour Mate Blacksmith Mazdoor b) c) Machinery Tractor-trolley Material Corrugated sheet,3 mm thick, "Thrie" beam section railing,4.5 m in length Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 kg per metre Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos Nuts and bolts Add 15 per cent of the cost of material for fabrication, nuts, bolts and washers etc.) d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 4.5 metre = a+b+c+d+e Rate per metre= (a+b+c+d+e)/4.5 hour kg kg kg kg 0.100 72.940 98.400 day day day 0.060 0.500 1.000

#VALUE! say #VALUE!

350.00 250.00 180.00 300.00 input

21.00 125.00 180.00 30.00

L-12 L-02 L-13 P&M053

#VALUE! M-088

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 26.860 1000 #VALUE! M-130 30.000 input #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

In the case of median crash barrier, 'W' metal beam or thrie beam section should be provided on both sides of the vertical posts Note fixed in the median. Extra provision for metal beam railing and spacer is required to be made when fixed in the median Road Traffic Signals depending on approved design. electrically 8.24 811 Since it is a ready made item commercially operated produced and erected by specialised firm in the electrical and electronic field, rate may Note be taken based on market enquiry from firms specialised in this field and ISI certified for the approved design and drawing. Crash Barrier, Wire Rope Sugge Flexible 8.25 stive Safety Barrier

Page 16 of 363

Ref. to Sr No MoRT H Spec.

Description barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15 grade cement concrete foundation 2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per approved design and = Running excluding excavation and Unitdrawing, ratemetre Taking output = 15 metre a) Labour Mate Mazdoor Blacksmith b) Material i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 x 11.50 iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for terminal posts @ 62.80 kg/sqm (2 x 1.5) 40 mm, including iv) Steel wire rope 7.50 per cent extra for fixing at ends Add 15 xperx cent @ 1 cost ofm 5 4 1.075 of kg per material for drilling, gripping, fixing, fabrication and welding consumables c) Painting Applying 2 coats of painting on exposed surface d) Machinery Tractor-trolley e) Overhead charges @ 2.244% on (a+b+d) f) Contractor's profit @ 5% on (a+b+d+e) Cost for 15 m = a+b+c+d+e+f Rate per m = (a+b+c+d+e+f)/15 The items of excavations and cement concrete works will be measured and included separately as per the approved designs and drawings. Anti-Glare Devices in Median Plantation shrubs and plants of approved Plantation of species in the median. apart from cutting off glare from vehicle coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is available in the chapter 11 Anti-glare screen with 25 mm steel on horticulture. pipe framework fixed with circular and rectangular vans screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre length and 1.75 metre height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation concrete, applying 2 coats of paint on all exposed surfaces, all as per approved Unit = Running metre Taking output = one metre a) Labour Page 17 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day kg kg kg kg

0.120 2.000 1.000 190.000

350.00 180.00 250.00

42.00 360.00 250.00

L-12 L-13 L-02

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 46.000 1000 #VALUE! #VALUE! M-179 / 188.400 1000 input #VALUE! M-177 65.000 #VALUE!

sqm hour

16.500 0.250

#VALUE! #VALUE! Item 8.9 300.00 75.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053

Note 8.26 Sugge stive A

Ref. to Sr No MoRT H Spec. b)

Description Mate Mazdoor Material i) 25 mm steel pipe ii) MS sheet for 600 x 300 x 3 mm rectangular vane, one number @ 24kg/sqm iii) MS sheet for 250 mm dia circular vane 3 mm thick,4 numbers @ 24 Add kg/sqm cent 5 per cost of material for fabrication, welding, bending, nuts, bolts etc c) Painting Applying 2 coats of painting on exposed d) surface Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on e) (a+b+d) Rate per metre = a+b+c+d+e The items of excavation and cement Note concrete as per approved design to be measured and paid separately Anti-glare screen with rectangular C vane of MS sheet with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in M-15 cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces, all complete as per Unit = Running metre Taking output = 1.50 metre a) Labour Mate Mazdoor b) Material i) Angle iron post,50 x 50 x 6 mm, length 2.35 m ii) MS sheet 3 mm thick @ 24 kg/sqm Add 5 per cent of cost of material for fabrication, nuts, bolts etc c) Machinery Tractor-trolley d) Painting Applying 2 coats of painting e) Overhead charges @ 2.244% on (a+b+c) f) Contractor's profit @ 5% on (a+b+c+e) Cost for 1.5 m = a+b+c+d+e+f Rate per metre = (a+b+c+d+e+f)/1.50

Unit day day metre kg kg

Quantity 0.004 0.100

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 1.40 L-12 180.00 18.00 L-13

#VALUE! M-174 16.000 input #VALUE! #VALUE! M-179 / 4.320 1000 #VALUE! #VALUE! M-179 / 4.800 1000 #VALUE!

sqm

1.830

#VALUE! #VALUE! Item 8.9 #VALUE! #VALUE! #VALUE! say #VALUE!

8.26

day day kg kg

0.004 0.100 10.580 9.000

350.00 180.00

1.40 18.00

L-12 L-13

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 1000 #VALUE!

hour sqm

0.100 0.850

300.00

30.00

P&M053

#VALUE! #VALUE! Item 8.9 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

The items of excavation and cement concrete as per approved design to be Note measured and paid separately. Rate of painting has been analaysed separately in this chapter. Sugge 8.27 Street Lighting stive Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation. Unit = Each

Page 18 of 363

Ref. to Sr No MoRT H Spec.

Description Taking output = one light a) Labour Mate Mazdoor Electrician b) Material i) Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level ii) Sodium vapour lamp Add 5 per cent of cost of material for holder, electric cable, insulation, ladder, scaffolding etc c) Painting For Fixing in Median Providing two coats of alluminium paint over steel circular hollow pipe with overhang on both sides For fixing in Footpath Providing two coats of alluminium paint over steel circular hollow pipe with overhang on one side For Fixing in Median d) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on e) (a+b+d) light for fixing in Median= Rate per a+b+c+d+e (ii) For fixing in Footpath Rate per light for Fixing in Footpath = a+b+c+d+e

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day

0.030 0.500 0.250

350.00 180.00 250.00 input

10.50 90.00 62.50

L-12 L-13 L-02

#VALUE! M-171

each each

1.000 1.000 input #VALUE! M-168 #VALUE!

sqm

5.750

#VALUE! #VALUE! Item 8.9

sqm

4.630

#VALUE! #VALUE! Item 8.9

(i)

#VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! say #VALUE!

The items of excavation and cement concrete foundation will be measured and Note included separately in the estimate as per approved design and drawing. The rate for painting has been analysed in this chapter. Sugge 8.28 Lighting on Bridges stive Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp Unit = Each Taking output = one light a) Labour Mate Mazdoor Electrician b) Material i) Steel circular hollow pole of standard specification for street lighting to mount light at 5 m above deck level ii) Sodium vapour lamp 70 watt Add 1 per cent of cost of material for holder, electric cable, insulation, ladder, scaffolding etc c) Painting Providing two coats of alluminium paint over steel circular hollow pipe d) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on e) (a+b+d) Rate per light = a+b+c+d+e The items of cement concrete to be measured and paid separately as per approved design. The rate for painting has already been analysed in this chapter. Cable Duct Across the Road input each each 1.000 1.000 input day day day 0.020 0.400 0.200

350.00 180.00 250.00

7.00 72.00 50.00

L-12 L-13 L-02

#VALUE! M-170

#VALUE! M-168 #VALUE!

sqm

2.760

#VALUE! #VALUE! Item 8.9 #VALUE! #VALUE! #VALUE! say #VALUE!

Note 8.29 Sugge stive

Page 19 of 363

Ref. to Sr No MoRT H Spec.

Description concrete pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved Single row for one utility service Unit = Running metre Taking output = 20metres a) Random Rubble masonry/Brick masonry in cement mortar 1:6 for head wall both side b) Labour Mate Mazdoor Mazdoor skilled c) Material Reinforced Cement Concrete pipe 300 mm dia soil with PI less than 6 for Granular bedding and sides of pipe (0.6 x 0.6 x 20 m) Collar for joints 300 mm dia Cement mortar 1:2 for joints d) Machinery Tractor-trolley e) Overhead charges @ 2.244% on (b+c+d) f) Contractor's profit @ 5% on (b+c+d+e) Cost for 20 metre = a+b+c+d+e+f Rate per metre = (a+b+c+d+e+f)/20

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

(i)

cum day day day metre cum each cum hour

2.360 0.050 1.000 0.250

#VALUE! #VALUE!

Item 12.7 (Addl) B) L-12 L-13 L-15

350.00 180.00 250.00

17.50 180.00 62.50

20.000 input input 7.200

#VALUE! M-151 #VALUE! M-009

#VALUE! M-083 9.000 input #VALUE! #VALUE! Item 0.020 12.6 (B) 0.500 300.00 150.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053

8.29

(ii)

Double row for two utility services Unit = Running metre Taking output = 20metres a) Random Rubble brick/Brick masonry in cement mortar 1:6 for head wall both sides. b) Labour Mate Mazdoor Mazdoor skilled c) Material Reinforced Cement Concrete pipe 300 mm dia soil with PI less than 6 for Granular bedding and sides of pipe (0.6 x 0.6 x 40 m) Collar for joints 300 mm dia Cement mortar 1:2 for joints d) Machinery hour 1.000 300.00 300.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053 Tractor-trolley e) Overhead charges @ 2.244% on (b+c+d) f) Contractor's profit @ 5% on (b+c+d+e) Cost for 20 metre = a+b+c+d+e+f Rate per metre = (a+b+c+d+e+f)/20 cum day day day metre cum each cum 3.370 0.050 2.000 0.250 #VALUE! #VALUE! Item 12.7 (Addl) B) L-12 L-13 L-15

350.00 180.00 250.00

17.50 360.00 62.50

40.000 input input 14.400

#VALUE! M-151 #VALUE! M-009

#VALUE! M-083 18.000 input #VALUE! #VALUE! Item 0.040 12.6 (B)

8.29

(iii)

Triple rRow for three utility services Unit = Running metre Page 20 of 363

Ref. to Sr No MoRT H Spec.

Description Taking output = 20metres a) Random Rubble brick/Brick masonry in cement mortar 1:6 for head wall both sides. b) Labour Mate Mazdoor Mazdoor skilled c) Material Reinforced Cement Concrete pipe 300 mm dia soil with PI less than 6 for Granular bedding and sides of pipe (0.6 x 0.6 x 60 m) Collar for joints 300 mm dia Cement mortar 1:2 for joints d) Machinery Tractor-trolley e) Overhead charges @ 2.244% on (b+c+d) f) Contractor's profit @ 5% on (b+c+d+e) Cost for 20 metre = a+b+c+d+e+f Rate per metre = (a+b+c+d+e+f)/20

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. Item 12.7 (Addl) B) L-12 L-13 L-15

cum day day day metre cum each cum hour

4.380 0.160 3.000 1.000

#VALUE! #VALUE!

350.00 180.00 250.00

56.00 540.00 250.00

60.000 input input 21.600

#VALUE! M-151 #VALUE! M-009

#VALUE! M-083 27.000 input #VALUE! #VALUE! Item 0.060 12.6 (B) 1.500 300.00 450.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053

1.Inspection chamber at both ends is the Note responsibility of the agency who is laying the duct. Hence not included. 2.The rates for stone masonry / brick masonry and cement mortar to be adopted from respective clauses. Sugge 8.30 Highway Patrolling and Traffic Aid Post stive It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. The organisation and financial aspect are required to be finalised in consultation with administrative and traffic authorities . Items Related to Underpass/ Subway/ Sugge Overhead Bridge/ Overhead Foot 8.31 stive The items involved for underpass/ subway/ Bridge overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the approved designs and drawings Sugge Traffic Control System and 8.32 stive Communication System Providing a traffic control centre and communication system including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer system telecommunication system and are the commercial products. The designer is required to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these installations, pricing may be done as per rates in relevant chapters for quantities derived as per approved design and As regards the locations where such devices are required to be installed, the traffic control authority should be consulted to finalise the location Sugge Gantry Mounted Variable Message 8.33 stive Sign Board Providing and erecting gantry mounted variable message sign board electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3 (i) Gantry Support System Unit = tonne Page 21 of 363

Ref. to Sr No MoRT H Spec.

Description Taking output=1 tonne a) Labour Mate Mazdoor Blacksmith b) Material Alluminium alloy/galvanised steel including 5 per cent wastage Add 15 per cent of cost of material for fabrication and erection. Add 1 per cent of cost of material for nuts, bolts and welding c) Machinery Truck 10 tonne d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per tonne = a+b+c+d+e

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day tonne

0.120 2.000 1.000 1.050

350.00 180.00 250.00 input

42.00 360.00 250.00

L-12 L-13 L-02

#VALUE! M-060 #VALUE! #VALUE!

hour

1.000

497.00

497.00 #VALUE! #VALUE!

P&M057

#VALUE! say #VALUE!

8.33

(ii)

Message Display Message display board 6 sqm electronically operated with complete electronic fitments for flashing the pre-determined messages. This is a specilised commercial product and the lumpsum rate including erection at site is required to be as certained from the market and including in the rate analysis. The size of the board will vary depending upon specific location. The rate for the gantry mounted variable sign would be the addition of cost of gantry support system as per approved design determined at (i) above and the cost of message display board as certained from the market at (ii) above Traffic Impact Attenuators at Abutments and Piers With Scrap Tyres Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as per approved design and drawings. Unit = sqm Taking output = 20sqm a) Labour Mate Mazdoor Blacksmith b) Material Scrap tyres of size 900 x 20 20 mm steel wire rope Add 1 per cent of cost of wire rope for clamps etc. c) Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 20 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/20 each kg 80.000 input 150.000 input #VALUE! M-161 #VALUE! M-176 #VALUE! hour 3.000 300.00 900.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053 day day day 0.080 1.500 0.250 350.00 180.00 250.00 28.00 270.00 62.50 L-12 L-13 L-02

8.34

Sugge stive A

8.34

Using Plastic/Steel Barrel, Filled with Sand

Page 22 of 363

Ref. to Sr No MoRT H Spec.

Description Provision and installation of traffic impact attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire rope as per approved design and drawings Unit = sqm Taking output = 20sqm a) Labour Mate Mazdoor Blacksmith b) Material Plastic barrels or Steel barrels Sand 20 mm steel wire rope Add 1 per cent of cost of wire rope for clamps etc. c) Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 20 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/20

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day each each cum kg

0.130 3.000 0.250 50.000

350.00 180.00 250.00

45.50 540.00 62.50

L-12 L-13 L-02

50.000 input 8.000 input 15.000 input

#VALUE! M-172 #VALUE! M-004 #VALUE! M-176 #VALUE!

hour

2.000

300.00

600.00 #VALUE! #VALUE! #VALUE!

P&M053

8.34

With HI - DRO cell Sandwich (Patented) (In this patented HI - DRO cell system, water gets discharged from plastic tubes on impact over a pre-determined time, thus absorbing the energy) Providing and installing a patentend HI DRO cell system as a traffic impact attenuators, using plastic tubes 50 cm dia, 1.2 m in height, 25 mm opening at the top, placed in three rows, filled with water and tied with a 20 mm steel wire rope Unit = sqm Taking output = 10sqm a) Labour Mate Mazdoor b) Material Plastic tubes 50 cm dia,1.2 m high Cost of water 20 mm steel wire rope Add 1 per cent of cost of wire rope for clamps etc. c) Machinery Tractor-trolley Water tanker6 KL capacity d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10 each KL kg 40.000 input 12.000 input 100.000 input day day 0.100 2.500

#VALUE! say #VALUE!

350.00 180.00

35.00 450.00

L-12 L-13

#VALUE! M-139 #VALUE! M-189 #VALUE! M-176 #VALUE!

hour hour

2.000 2.000

300.00 300.00

600.00 600.00 #VALUE! #VALUE! #VALUE!

P&M053 P&M060

#VALUE! say #VALUE!

8.35

Sugge stive

Road Markers/Road Stud with Lense Reflectorand fixing of road stud 100x 100 Providing mm, die-cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973 Page 23 of 363

Ref. to Sr No MoRT H Spec.

Description Unit = Nos Taking output = 50Nos a) Labour Mate Mazdoor b) Material Aluminium studs 100 x 100 mm fitted with lense reflectors Add 10 per cent of cost of material for fixing and installation c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 50 studs = a+b+c+d Rate per studs = (a+b+c+d)/50

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day each

0.040 1.000 50.000

350.00 180.00 input

14.00 180.00

L-12 L-13

#VALUE! M-062 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.36

Sugge stive

Traffic Cone Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873 Unit = Running metre Taking output = 68 Nos. a) Labour Mate Mazdoor b) Material Traffic cones with 150 mm reflective sleeve c) Machinery Tractor-trolley d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 68 Nos. = a+b+c+d+e Rate per metre = (a+b+c+d+e)/68 day day each hour 0.020 0.500 350.00 180.00 7.00 90.00 L-12 L-13

68.000 input 0.100 300.00

#VALUE! M-186 30.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M053

8.37

Sugge stive A

Roadside Amenities Rest areas Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required to be assessed for specific location as per actual site conditions Parking areas and bus laybyes for trucks, buses and light vehicles Pricing of parking areas may be done for the quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates for items may be from respective chapters. Lawn Providing a lawn planted with grass and its maintenance Pricing of lawn may be done as per rates given in the chapter on horticulture for the quantities as per approved dimensions in the drawings Rumble Strips

8.38

Sugge stive

Page 24 of 363

Ref. to Sr No MoRT H Spec.

Description Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint. Unit = sqm Taking output = 100 sqm (including gaps) The rate per sqm of premix carpet and road marking may be adopted from chapter 5 & 8 respectively for the quantities calculated from approved drawings Policeman Umbrella Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts = each Unit to be given 2 coats of paint Taking output = one number Earthwork Quantities of these items to be Cement Concrete calculated as per approved design and cost brick masonry or added as per rates of these stone masonry items given in chapter 3 and 13 Painting a) Labour Mate Mazdoor Blacksmith Welder b) Material Steel pipe 100 mm dia Steel pipe 25 mm dia CGI sheets Add 25 per cent of cost of material for fabrication Add 2 per cent of cost of material for welding consumables, J-hooks, washers etc. c) Machinery Tractor-trolley d) Overheads @ per cent on (a+b+c) e) Contractors Profit@ per cent on (a+b+c+d) Rate per policeman umbrella =

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

8.39

Sugge stive

cum cum cum cum sqm day day day day metre metre kg 2.500 0.090 1.000 1.000 0.250 3.500 10.000 8.000

hour

0.500

8.40

sugge stive

a+b+c+d+e High Mast Pole Lighting at Interchanges and high hot dip galvanised lighting with 30 m Flyovers mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and

Page 25 of 363

Ref. to Sr No MoRT H Spec.

Description This is a specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are submitted by the firms along with their tender for checks by the Department. The cost of this work is required to be worked out based on approved design, drawings and estimate of the lowest tender. A separate contract for this work is concluded as the contractors for road and bridge works generally donot undertake such jobs. Toll Plaza The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under based on the approved design and drawings:- lane a) Provision of toll collection service to separate different categories of vehicles for purpose of toll collection. This involves considerable increase m carriage way width b) Provision of 2.5 in wide separators for different toll collection service lanes for safety c) Toll booths with integrated roof cover d) Barrier gates for individual lanes e) Provision of building to provide facility to toll plaza personnel f) Toll plaza office equipment and furniture g) Water supply, electricity, sanitation, septic-tank system and drainage h) Telephone, intercomes, wireless communication system i) High mast lighting j) Pavement marking k) Overhead signs l) Fixed message signs (Advance) m) Variable message signs n) Traffic cones and pylons o) First aid post p) Traffic aid post and security The quantities for the above mentioned items may be calculated from the approved design and drawings and their rates adopted from respective chapters of the Standard Data Book Safety Devices and Signs in Construction Zonessuitable locations in limited period at construction zone comprising of warning zone, approach transition zone, working zone and terminal transition zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings, removed and disposed of after completion of construction work, all as per Unit = each Taking output = one sign post Following types of signs are required to be fixed in construction zones for safety of traffic a) Diversion one km ahead b) c) d) e) f) g) h) Traffic sign ahead Road ahead closed Men at work Road narrow Single file traffic Right lane diverted Left lane diverted Page 26 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

8.41

8.42

Ref. to Sr No MoRT H Spec.

Description i) Right lane closed

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

j) Left lane closed k) Median closed l) Diversion to other carriageway m) Traffic signal ahead n) Two way traffic o) Un - even road p) Slippery road q) Loose chippings r) Dual carriageway ends s) Diversion t) Do not enter u) Road closed v) Stop w) Slow x) One way y) Give way z) aa) bb) cc) dd) Overtaking prohibited Speed limit Weight limit Height and length limit No stopping or standing

8.43

sugge stive

ee) Any other warning or regulatory safety sign as per site requirement and consistent with IRC:SP:55-2001 and IRC:67 The rate for traffic signs are already worked out and given elsewhere in this chapter. The same may be adopted. Portable Barricade in Construction Zone Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001 Unit = each Taking output = one steel portable barricade a) Labour Mate Mazdoor Painter Welder b) Material Angle iron 45 x 45 x 5 mm MS sheet 300 mm wide,2.5 m long and 2.6 mm thick Paint Add 2 per cent of cost of steel for welding consumables, nuts & bolts and drilling holes c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per barricade = a+b+c+d kg kg litre #VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 15.000 1000 #VALUE! M-131 0.500 input 25.000 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! in day day day day 0.020 0.250 0.500 0.250 350.00 180.00 250.00 250.00 7.00 45.00 125.00 62.50 L-12 L-13 L-18 L-02

8.44

sugge stive A

Permanent Type Barricade Construction Zone With steel components

Page 27 of 363

Ref. to Sr No MoRT H Spec.

Description Construction of a permanent type barricade made of steel components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:552001 = each Unit Taking output = one barricade a) Labour Mate Mazdoor Painter Welder b) Material Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m length Paint Add 1 per cent of cost of steel for welding consumables, nuts & bolts and drilling holes c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per barricade = a+b+c+d

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day day kg kg litre

0.050 0.300 0.600 0.300 15.000

350.00 180.00 250.00 250.00

17.50 54.00 150.00 75.00

L-12 L-13 L-18 L-02

#VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 50.000 1000 #VALUE! M-131 1.000 input #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

8.44

With wooden components type barricade Construction of a permanent made of wooden components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 Unit = each Taking output = one barricade a) Labour Mate Mazdoor Painter Carpenter b) Material cum 0.180 input #VALUE! M-185 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Timber Add 1 per cent of cost of timber for nuts & bolts, nails, etc. charges @ 2.244% on c) Overhead (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per barricade = a+b+c+d day day day day 0.050 0.300 0.600 0.600 350.00 180.00 250.00 250.00 17.50 54.00 150.00 150.00 L-12 L-13 L-18 L-04

8.44

With bricks Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips Unit = each Taking output = one barricade a) Labour Mate Mazdoor Painter Mason b) Material Brick each 1800.000 input #VALUE! M-079 day day day day 0.240 3.000 1.000 2.000 350.00 180.00 250.00 250.00 84.00 540.00 250.00 500.00 L-12 L-13 L-18 L-11

Page 28 of 363

Ref. to Sr No MoRT H Spec.

Description Cement Sand Paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per barricade = a+b+c+d

Unit kg cum litre

Quantity

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! M-081 / 22.000 1000 #VALUE! M-005 0.090 input #VALUE! M-131 1.250 input Rate Rs #VALUE! #VALUE! #VALUE! say #VALUE!

8.45

sugge stive

Drum Delineator in Construction Zone Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter, 800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001 Unit = each Taking output = one drum delineator a) Labour Mate Mazdoor Painter b) Material Steel drum 300 mm dia 1.2 m high/empty bitumen drum Paint c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per drum delineator = a+b+c+d day day day each litre 0.020 0.250 0.250 1.000 350.00 180.00 250.00 input 7.00 45.00 62.50 L-12 L-13 L-18

#VALUE! M-172 #VALUE! M-131 #VALUE! #VALUE! #VALUE! say #VALUE!

0.500 input

8.46

sugge stive

Flagman Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic Unit = each Taking output = one flagman a) Labour Mate Mazdoor b) Material each each 1.000 input input 1.000 #VALUE! M-099 #VALUE! M-196 #VALUE! #VALUE! #VALUE! say #VALUE! Flag of red color cloth 600 x 600 mm Wooden staff for fastening of flag 25 mm dia, one m long c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per flagman = a+b+c+d day day 0.040 1.000 350.00 180.00 14.00 180.00 L-12 L-13

Page 29 of 363

Ref. to Sr No MoRT H 9.1 Spec. 408

CHAPTER-9 PIPE CULVERTS


Description PCC 1:3:6 in Foundation Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. Unit = cum Taking output = 15 cum a) Labour Mate Mason Mazdoor b) Material 40mm Aggregate at site Sand at site Cement at site Cost of water c) Machinery Concrete mixer0.4/ 0.28 cum Generator set 33 KVA Water tanker6 KL capacity d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 Note Vibrator is a part of minor T & P which is already included in overhead charges of the contractor. Laying Reinforced Cement Concrete Pipe NP4 / Prestressed Concrete Pipe on First Class Bedding in Single Row . Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls Unit = metre Taking output = 12.5 metres ( 5 pipes of 2.5 m length each ) A 1000 mm dia a) Labour Mate Mason Mazdoor b) Material Sand at site Cement at site RCC pipe NP-4 /prestressed concrete pipe including collar at site Granular material passing 5.6 mm sieve c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 12.5 metres = a+b+c+d Rate per metre = (a+b+c+d)/12.5 Note 1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added . 2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates B 1200 mm dia a) Labour Mate Mason Page 1 of 363 day day 0.280 1.000 350.00 250.00 98.00 250.00 L-12 L-11 day day day cum tonne metre cum 0.180 0.500 4.000 350.00 250.00 180.00 63.00 125.00 720.00 L-12 L-11 L-13 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day day cum cum tonne KL hour hour hour

0.640 1.000 15.000 13.800 6.900 3.300 18.000 6.000 6.000 3.000

350.00 250.00 180.00 input input input input 165.00 540.00 300.00

224.00 250.00 2700.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-11 L-13 M-055 M-005 M-081 M-189 P&MP&MP&M-

990.00 3240.00 900.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

9.2

2900

0.070 input 0.050 input 12.500 input 4.500 input

#VALUE! M-005 #VALUE! M-081 #VALUE! M-149 #VALUE! M-009 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

9.2

Ref. to Sr No MoRT H Spec.

Description Mazdoor Material Sand at site Cement at site RCC pipe NP-4/prestressed concrete pipe including collar at site Granular material passing 5-6 mm sieve for class bedding c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 12.5 metres = a+b+c+d Rate per metre= (a+b+c+d)/12.5 b) Note 1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added . 2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates Laying Reinforced Cement Concrete Pipe NP4 / Prestressed Concrete Pipe on First Class Bedding in Double Row . Laying Reinforced cement concrete pipe NP4 / prestressed concrete pipe for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls Unit = metre Taking output = 12.5 metres ( 10 pipes of 2.5 m length each in two rows.) 1000 mm dia a) Labour Mate Mason Mazdoor b) Material Sand at site Cement at site RCC pipe NP-4/prestressed concrete pipe including collar at site Granular material passing 5.6 mm sieve c) for bedding charges @ 2.244% on Overhead (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 12.5 metres = a+b+c+d Rate per metre = (a+b+c+d)/12.5 Note 1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added . 2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates B 1200 mm dia a) Labour Mate Mason Mazdoor b) Material Sand at site Cement at site

Unit day cum tonne metre cum

Quantity 6.000

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 1080.00 L-13 #VALUE! M-005 #VALUE! M-081 #VALUE! M-150 #VALUE! M-009 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

0.090 input 0.070 input 12.500 input 5.000 input

9.3

2900

day day day cum tonne metre cum

0.360 1.000 8.000

350.00 250.00 180.00

126.00 250.00 1440.00

L-12 L-11 L-13

0.140 input 0.100 input 25.000 input 12.500 input

#VALUE! M-005 #VALUE! M-081 #VALUE! M-149 #VALUE! M-009 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

9.3

day day day cum tonne

0.560 2.000 12.000

350.00 250.00 180.00

196.00 500.00 2160.00

L-12 L-11 L-13

0.180 input 0.140 input

#VALUE! M-005 #VALUE! M-081

Page 2 of 363

Ref. to Sr No MoRT H Spec.

Description RCC pipe NP-4 /prestressed concrete pipe including collar at site Granular material passing 5-6 mm sieve for class bedding c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 12.5 metres = a+b+c+d Rate per metre= (a+b+c+d)/12.5 Note 1. In case of cement craddle bedding, quantity of PCC M15 is to be calculated as per design and priced separately and added . 2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling, protection works and parapet walls. The same are to be calculated as per approved design and drawings and priced separately on rates

Unit metre cum

Quantity

Rate Rs

25.000 input 13.750 input

Remark Cost Rs s/ Input ref. #VALUE! M-150 #VALUE! M-009 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

Page 3 of 363

Ref. to Sr No MoRT H 10.1 Spec. 3002

CHAPTER- 10 MAINTENANCE OF ROADS


Description Restoration of Rain Cuts Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting with plate compactor or power rammers to restore the original alignment, levels and Unit = cum Taking output = 10 cum a) Labour Mate Mazdoor b) Machinery Excavator1.0 cum bucket capacity @ 60 cum per hour Tipper ( L is average lead in km for borrow earth) Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day hour tonne.k m

0.080 2.000 0.130 12 x L

350.00 180.00 1942.00 4.00

28.00 360.00 252.46

L-12 L-13

Add 10 per cent of cost of carriage towards loading and unloading charges. Plate compactor c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 10 cum = a+b+c+d Rate per cum = (a+b+c+d)/10 Note Only 75 per cent of fresh material has been provided as 25 per cent can be retrieved at site from earth that is flown down the slope in the form of slurry and deposited at the foot of there in cuts Maintenance of Earthen Shoulder (filling with fresh soil) Making up loss of material/ irregularities on shoulder to the design level by adding fresh approved soil and compacting it with appropriate equipment. Unit = sqm Taking output = 100 sqm Assuming average thickness of filling to be Quantity of fresh material = 15 cum a) Labour Mate Mazdoor b) Machinery Excavator1.0 cum bucket capacity @ 60 cum per hour Tipper ( L is average lead in km for borrow earth)

P&M026 #VALUE! Lead =input km & P&M#VALUE! 058 P&M-

hour

0.500

30.00

15.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

10.2 3003

day day hour tonne.k m

0.180 4.500 0.250 24xL

350.00 180.00 1942.00 4.00

63.00 810.00 485.50

L-12 L-13

Add 10 per cent of cost of transportation to cover cost of loading and unloading Plate compactor @ 25 sqm per hour c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 100 sqm = a+b+c+d Rate per sqm = (a+b+c+d)100 10.3 3003 Maintenance of Earth Shoulder (stripping excess soil) Stripping excess soil from the shoulder surface to achieve the approved level and compacting Unit = sqmwith plate compactor Taking output = 100 sqm Assuming average depth of stripping as 75 Quantity of earth cutting involved = 7.5 a) Labour Page 1 of 363

P&M026 #VALUE! Lead =input km & P&M#VALUE! 058 P&M-

hour

12.000

30.00

360.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec.

Description Mate Mazdoor b) Machinery Plate compactor @ 25 sqm per hour c) Overhead charges @ 2.244% on d) Contractor's profit @ 5% on Cost for 100 sqm = a+b+c+d Rate per sqm on = (a+b+c+d)100

Unit day day hour

Quantity 0.100 2.500 4.000

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 35.00 L-12 180.00 450.00 L-13 30.00 120.00 13.58 30.93 649.51 6.50 6.00 P&M-

say Note The earth stripped from earthen shoulders to be dumped on the side slopes locally for disposal. Pot-holes and Patch Repairs 10.4 3004. Filling 2 with open-Graded Premix surfacing, 20mm. of all failed material, trimming of Removal completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 511, compacting, trimming and finishing the surface to form a smooth Unit = Sqm Taking out put = 10250 sqm (205 cum) a) Labour Mate Mazdoor Mazdoor skilled b) Machinery Air compressor 250 cfm HMP 100-110 TPH Capacity Tipper 10 tonnes capacity Smooth wheeled roller 8-10 tonnes c) Material Crushed stone aggregates nominal size 13.2mm stone aggregates nominal size Crushed 11.2mm 80/100 Bitumen Bitumen emulsion for tack coat including vertical sides of pot hole. d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10250 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10250 10.5 3004. 2 Filling Pot-holes and Patch Repairs with Bituminous concrete, 40mm. Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth Unit = Sqm Taking out put = 4900 sqm (196 cum) (450 Labour Tonnes) a) Mate Mazdoor Mazdoor skilled b) Machinery Air compressor 250 cfm HMP 100-110 TPH Capacity Tipper 10 tonnes capacity Smooth wheeled roller 8-10 tonnes c) Material Page 2 of 363 hour hour hour hour 6.000 6.000 45.000 12.000 285.00 Day Day Day 2.920 70.000 3.000 350.00 250.00 cum 184.500 input cum tonne tonne 92.250 input 14.970 input 2.460 input hour hour hour hour 6.000 6.000 45.000 12.000 285.00 19966.00 470.00

Day Day Day

3.760 90.000 4.000

350.00 250.00

1316.00 1000.00 1710.00 ### 5640.00

L-12 L-13 L-15 P&M001 P&M021 P&M048 P&M044

180.00 16200.00

497.00 22365.00

#VALUE! M-052 #VALUE! M-051 #VALUE! M-075 #VALUE! M-077 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

1022.00 750.00 1710.00

L-12 L-13 L-15 P&M001 P&M022 P&M048 P&M044

180.00 12600.00

15294.00 91764.00 497.00 22365.00 470.00 5640.00

Ref. to Sr No MoRT H Spec.

Description I) Bitumen ii) Bitumen emulsion for tack coat . iii) Aggregates Grading I - 19mm(Nominal size) 20-10mm 35 per cent

Unit tonne tonne

Quantity

Rate Rs

22.500 input 1.180 input

Remark Cost Rs s/ Input ref. #VALUE! M-075 #VALUE! M-077

cum

99.750

0.00

10-5 mm 23 per cent 5mm and below40 per cent

cum

65.550 input 0.00

M051,M052,M053 and #VALUE! M-054 M-025 M021,M022 and #VALUE! M-024 0.00

0.00

cum 114.000

Add 5 per cent for wastage or Grading-II 13mm (Nominal size) 13.2-10 mm 30 per cent 10-5 mm 25 per cent 5 mm and Below43 per cent cum cum 85.500 71.250 input 0.00 0.00

M-051 and M052 #VALUE! M-025 M021,M022 and M-024 1062.00 M-188 #VALUE! 0.00

0.00

cum 122.550

Filler 2 per cent Add 5 per cent for wastage Any one of the above alternatives of aggregate i.e. 19mm or 13mm nominal size may be adopted as per approved design. for grading I Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 4900 Rate per cum = (a+b+c+d+e)/4900 10.5 (ii) for grading II Material d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) cum = a+b+c+d+e Cost for 4900 Rate per cum = (a+b+c+d+e)/4900 Note For detailed working of quantities of aggregates, refer item 5.8 of chapter 5 10.6 3004. Crack Filling 3.3 Filling of crack using slow - curing bitumen emulsion and applying crusher dust in case crack= Running Meter Unit are wider than 3mm. Taking out put = 500m a) Labour Mate Mazdoor b) Material Slow-curing bitumen emulsion Stone crusher dust c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 500sqm = a+b+c+d Rate per meter = (a+b+c+d+e)/500 10.7 3004. 4 Dusting Applying crusher dust to areas of road where bleeding of excess bitumen has occurred. Unit = Sqm Page 3 of 363

tonne

9.000

118.00

10.5

(i)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day Kg cum

0.040 1.000 33.000

350.00 180.00

14.00 180.00

L-12 L-13

#VALUE! #VALUE! M-077 #VALUE! M-021 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

0.020 input

Ref. to Sr No MoRT H Spec.

Description Taking output = 3500 sqm a) Labour Mate Mazdoor b) Material Stone crusher dust finer than 3mm with not more than 10 per cent c) passing 0.075 sieve. @ 2.244% on Overhead charges (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 3500sqm = a+b+c+d Rate per meter = (a+b+c+d)/3500

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day cum

0.080 2.000

350.00 180.00

28.00 360.00

L-12 L-13

6.250 input

#VALUE! M-021 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

10.8

(A) 3004. 3.2 (B) 3004. 3.4 (i) (ii) (iii) (iv)

Fog Seal

sqm

#VALUE!

Item 5.17

Crack Prevention courses.

Stress Absorbing Membrane (SAM) crack width less than 6 mm Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 per cent Bitumen Impregnated Geotextile Slurry Seal

sqm sqm sqm sqm

#VALUE!

10.8

(C) 3004. 5

Item 5.21 #VALUE! Case-I Item 5.21 #VALUE! Case-II Item 5.21 #VALUE! Case-IV Item 5.21 Case-IV #VALUE! Item 5.15 #VALUE! Case-I Item 5.15 #VALUE! Case-II Item 5.15 Case-III #VALUE! Item 5.9 Case-I #VALUE! Item 5.9 Case-II

(i) (ii) (iii)

5 mm thickness 3 mm thickness 1.5 mm thickness Surface Dressing for maintenance works. 19 mm nominal chipping size 13 mm nominal size chipping The above mentioned items have already been included in chapter 5. Repair of Joint Grooves with Epoxy Mortar of spalled joint grooves of Repair contraction joints, longitudinal joints and expansion joints in concrete pavements using= running metre Unit epoxy mortar or epoxy concrete Taking output = 10 metres a) Labour Mate Mazdoor Chiseller b) Material Epoxy primer Epoxy compound with accessories for preparing epoxy mortar c) Machinery Air compressor 250 cfm for cleaning d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 metres = a+b+c+d+e Rate per metre = (a+b+c+d+e)/10

sqm sqm sqm

10.8

(D) 3004. 6

(i) (ii)

sqm sqm

10.9 3005. 1

day day day kg kg

0.040 0.500 0.500

350.00 180.00 250.00

14.00 90.00 125.00

L-12 L-13 L-05

2.500 input 10.000 input

#VALUE! M-097 #VALUE! M-095

hour

0.050

285.00

14.25 #VALUE! #VALUE! #VALUE! #VALUE!

P&M001

say #VALUE!

Page 4 of 363

Ref. to Sr No MoRT H Spec. 10.1 3005. 0 2

Description Repair of old Joints Sealant Removal of existing sealant and re sealing of contraction, longitudinal or expansion joints in concrete pavement with fresh sealant material Unit = running metre Taking output = 10 metres a) Labour Mate Mazdoor b) Material Primer Sealant c) Machinery Air compressor 250 cfm for cleaning d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 metres = a+b+c+d+e Rate per metre = (a+b+c+d+e)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day kg kg hour

0.040 0.500

350.00 180.00

14.00 90.00

L-12 L-13

0.250 input 1.000 input 0.050 285.00

#VALUE! M-146 #VALUE! M-120 14.25 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M001

10.1 3000 1

Hill Side Drain Clearance Removal of earth from the choked hill side drain and disposing it on the valley side manually Unit = running metre Taking output = 10 metres Assuming muck causing choking of drain to be 0.2 cum per metre, quantity of earth to be removed for 10 metres = 2 cum a) Labour Mate Mazdoor b) Overhead charges @ 2.244% on (a+b)Contractor's profit @ 5% on (a+b) c) Cost for 10 metres = a+b+c Rate per metre = (a+b+c)/10 say day day 0.080 1.000 350.00 180.00 28.00 180.00 4.67 10.63 223.30 22.33 22.00 L-12 L-13

10.1 3000 2

Land Slide Clearance in soil Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side Unit = cum Taking output = 100 cum a) Labour Mate Mazdoor b) Machinery Dozer 180 HP @ 60 cum per hour c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 100 cum = a+b+c+d Rate per cum = (a+b+c+d)/100 say Note Land Slide clearance involves pushing of loose earth slided on the road surface from hill face on the valley side. Since no cutting of original ground is involved, the output of dozer has been taken as 60 cum per hour for soil, ordinary rock and blasted hard rock. However, if there are objection to disposing of earth on valley side, additional resources for its disposal shall be considered as per hour 1.670 2400.00 4008.00 94.29 214.81 4511.11 45.11 45.00 P&M014 day day 0.040 1.000 350.00 180.00 14.00 180.00 L-12 L-13

Page 5 of 363

Ref. to Sr No MoRT H 3000 10.1 Spec. 3

Description Landslide Clearance in Hard Rock Requiring Blasting Clearing of land slide in hard rock requiring blasting for 50 per cent of the boulders and disposal of the same on the valley side. Unit = cum Taking output = 100 cum a) Labour Mate Mazdoor Driller Blaster b) Machinery Dozer D 80 A-12,180 HP @ 60 cum per hour Air compressor 250 cfm with two jack c) hammer Materials Gelatine 80 per cent @ 35 kg per 100 cum Electric Detonators @ 1 Detonator for 2 Gelatine sticks of 125 gms each c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 100 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/100 Note Credit for the rock if found acceptable as construction material shall be afforded Snow Clearance on Roads with Dozer Snow clearance from road surface by a bulldozer 165 Hp and disposing it on the valley side Unit = cum Taking output = 5000 cum a) Labour Mate Mazdoor b) Machinery Dozer D 80 A-12,180 HP @ 850 cum per c) hour Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Cost for 5000 cum = a+b+c+d Rate per cum = (a+b+c+d)/5000

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day day hour hour kg each

0.090 1.500 0.750 0.070 1.670 2.500

350.00 180.00 250.00 250.00 2400.00 285.00

31.50 270.00 187.50 17.50 4008.00 712.50

L-12 L-13 L-06 L-03 P&M014 P&M001

17.500 input 70.000

#VALUE! M-104

#VALUE! #VALUE! M-094 / 100 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

10.1 3000 4

day day hour

0.080 2.000 5.880

350.00 180.00

28.00 360.00

L-12 L-13 P&M014

2400.00 14112.00 325.38 741.27 15566.65 3.11 say 3.00

10.1 3000 5

Note i) Labour provided will not be cutting the snow. They will be guiding the dozer operator on the alignment of the road as entire surface gets covered with snow and the edges of the road are not visible and for changing the blade angle. Also they will keep a watch on the hill side for any Snow Clearance on Roads with Snow Blowers Snow clearance from road surface by a snow blower and disposing on the valley side. = cum Unit Taking output = 3600 cum a) Labour Mate Mazdoor b) Machinery hour 6.000 input #VALUE! #VALUE! #VALUE! P&M087 Snow blower equipment 140 HP @ 600 cum per hour c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Page 6 of 363 day day 0.080 2.000 350.00 180.00 28.00 360.00 L-12 L-13

Ref. to Sr No MoRT H Spec.

Description Cost for 3600 cum (a+b+c+d) Rate per cum = (a+b+c+d)/3600

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE!

Page 7 of 363

Ref. to Sr No MoRT H 11.1 Spec. 307

CHAPTER-11 HORTICULTURE
Description Spreading of Sludge Farm Yard Manure or/and good Earth Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paid for separately) Unit = cum Taking output = 15 cum a) Labour Mate Mazdoor b) Overhead charges @ 2.244% on c) Contractor's profit @ 5% on (a+b) Cost for 15 cum= a+b+c Rate per cum = (a+b+c)/15 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day

0.040 1.000

350.00 180.00

say 11.2 307 Grassing with ' Doobs' Grass Grassing with 'Doobs' grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for moving including supplying good earth if needed Unit = sqm (i) Taking output = 100 sqm In rows 15 cm apart in either direction a) Labour Mate Mazdoor for grassing Mazdoor for maintenance for 30 days b) Machinery Water tanker6 KL capacity c) Material Doob grass d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 100 sqm = a+b+c+d+e Rate per sqm= (a+b+c+d+e)/100 11.2 (ii) In rows 7.5 cm apart in either a) Labour Mate Mazdoor for grassing. for maintenance for 30 days b) Machinery Water tanker6 KL capacity c) Material Doob grass d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 100 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/100 day day day hour 0.170 0.750 1.000 0.500 350.00 180.00 180.00 300.00

14.00 180.00 4.35 9.92 208.27 13.88 14.00

L-12 L-13

59.50 135.00 180.00 150.00

L-12 L-13 L-13 P&M-

kg 100.000 input

#VALUE! M-112 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day hour

0.220 1.250 1.000 0.750

350.00 180.00 180.00 300.00

77.00 225.00 180.00 225.00

L-12 L-13 L-13 P&M-

kg 200.000 input

#VALUE! M-112 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

11.3

307

Note In the case of horticulture one mate has been provided for every 10 mazdoors as maintenance of grass and plants require more care. Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod Making lawns including ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs grass roots and planting at 15 cm apart, including supplying and spreading of farm yard manure sqm Unit = at rate of 0.18 cum per 100 sqm Taking output = 100 sqm a) Labour Mate Mazdoor for preparation of ground Mali for fetching doobs grass roots and grassing at 15 cm apart Page 1 of 363

day day day

0.150 0.500 1.000

350.00 180.00 116.00

52.50 90.00 116.00

L-12 L-13 L-09

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paid for separately) b) Machinery Water tanker6 KL capacity Tractor with tiller c) Material Supply of farm yard manure at site of Fine grass d) Overhead charges @ 2.244% on e) Contractor's profit @ 5% on Cost for 100 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/100 11.4 307 Maintenance of Lawns or Turfing of Slopes Maintenance of lawns or Turfing of slopes (rough grassing) for a period of one year including watering etc Unit = sqm Taking output = 100 sqm a) b) c) Labour Mali Machinery Water tanker6 KL capacity Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 100 Rate per sqm = (a+b+c+d+e)/100 11.5 307 Turfing Lawns with Fine Grassing including Ploughing, Dressing Turfing lawns with fine grassing including ploughing, dressing including breaking of clods, removal of rubbish, dressing and supplying doobs grass roots at 10 cm apart, including supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm Unit = sqm Taking output = 100 sqm a) Labour Mate Mazdoor for preparation of ground Mali for fetching doobs grass roots hedges and grassing at 10 cm apart b) Machinery Water tanker6 KL capacity Tractor with tiller c) Material Supply of farm yard manure at site of work @ 0.6 cum per 100 sqm Fine grass d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 100 Rate per sqm = (a+b+c+d+e)/100 11.6 307 Maintenance of Lawns with Fine Grassing for the First Year Maintenance of lawns with fine grassing for the first year including watering etc Unit = sqm Taking output = 100 sqm a) Labour

hour hour

0.500 0.010

300.00 300.00

150.00 3.00

P&MP&M-

cum 0.180 input kg 100.000 input

#VALUE! M-167 #VALUE! M-113 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day hour KL

10.000 15.000

116.00 300.00

1160.00 4500.00

L-09 P&M060

90.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day

0.250 1.000 1.500

350.00 180.00 116.00

87.50 180.00 174.00

L-12 L-13 L-09

hour hour cum

0.500 0.010

300.00 300.00

150.00 3.00

P&M060 P&M053

0.600 input

#VALUE! M-167 #VALUE! M-113 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

kg 100.000 input

Page 2 of 363

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paid for separately) Mali b) c) Machinery Water tanker6 KL capacity Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 100 Rate per sqm = (a+b+c+d+e)/100 11.7 307 (a) Planting and Maintaining of Permanent Hedges permanent hedges including Planting digging of trenches Planting permanent hedges including digging of trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed with farmyard manure, supplied at the rate of 4.65 cum per 100 metres and supplying and planting hedge plants at 30 cm apart Unit = Running metre Taking output = 100metre a) Labour Mate Mazdoor for digging of trench 60 cm wide and 45 cm deep Mazdoor for refilling the excavated earth mixed with cow dung, preparation of ground and digging of plant, from the nursery carriage to site and planting in b) position Machinery Water tanker6 KL capacity c) Material Cost of hedge plants 2 rows at 30 cm apart of farm yard manure at site of Supply work Pesticide Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) metres = a+b+c+d+e Cost for 100 Rate per metre = a+b+c+d+e)/100 (b) Maintenance of hedge for one year Unit = Running metre Taking output = 100 m a) Labour Mate Mazdoor b) c) Machinery Water tanker6 KL capacity Material Manure sludge/Farm yard manure Pesticide Cost of water Cost of hedge plants @ 10 per cent d) casualty Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 100 metres = a+b+c+d+e Rate per metre = a+b+c+d+e)/100

day hour KL

10.000 20.000

116.00 300.00

1160.00 6000.00

L-09 P&M060

60.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day

1.400 10.000 4.000

350.00 180.00 180.00

490.00 1800.00 720.00

L-12 L-13 L-13

hour each cum kg KL

0.500

300.00

150.00

P&M060

2x340 input 4.670 input 0.250 input 3.000 input

#VALUE! M-116 #VALUE! M-167 #VALUE! M-136 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day hour cum kg KL each

3.000 30.000 5.000

350.00 180.00 300.00

1050.00 5400.00 1500.00

L-12 L-13 P&M060

2.000 input 0.500 input 30.000 input 68.000 input

#VALUE! M-167 #VALUE! M-136 #VALUE! M-189 #VALUE! M-116 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 3 of 363

11.8

307 (a)

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paidMaintaining of Flowering Planting and for separately) Plants and Shrubs Planting flowering plants and shrubs in central verge Unit = Running metres 200 plants and 800 shrubs in two rows in one km length of road where width of verge is 3m andoutput = 1000 metres Taking above. a) Labour Mate Mazdoor b) c) Machinery Water tanker6 KL capacity Material Plants Shrubs Manure sludge/Farm yard manure Pesticide Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) = (a+b+c+d+e) Rate per Km each 200.000 input each 800.000 input cum kg KL 63.640 input 0.500 input 36.000 input hour 6.000 300.00 1800.00 P&M060 day day 1.200 12.000 350.00 180.00 420.00 2160.00 L-12 L-13

#VALUE! M-100 #VALUE! M-166 #VALUE! M-167 #VALUE! M-136 #VALUE! M-189 #VALUE! #VALUE! #VALUE! say #VALUE!

11.8

(b)

Maintenance of flowering plants and shrubs in central verge for one year Unit = km Taking output = one km a) Labour Mate Mazdoor b) c) Machinery Water tanker6 KL capacity Material Manure Sludge / farm yard manure at site of water Cost Replacement of casualties @ 10 per cent Plants Shrubs Pesticides d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) for one year = Rate per Km (a+b+c+d+e) each each kg 20.000 input 80.000 input 1.500 input #VALUE! M-100 #VALUE! M-166 #VALUE! M-136 #VALUE! #VALUE! #VALUE! say #VALUE! cum 10.000 input KL 180.000 input hour 90.000 300.00 27000.00 P&M060 day 36.000 350.00 12600.00 180.00 65700.00 L-12 L-13 day 365.000

#VALUE! M-167 #VALUE! M-189

11.9

307

Planting of Trees and their Maintenance for one Year Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge manure, planting the saplings, backfilling the trench, watering, fixing= Each Unit the tree guard and maintaining the Taking output = 10 trees a) Labour Mate Mazdoor for planting Mazdoor for maintenance for one year b) c) Machinery Water tanker6 KL capacity Material hour 2.000 300.00 600.00 P&M060 day day day 1.700 2.000 15.000 350.00 180.00 180.00 595.00 360.00 2700.00 L-12 L-13 L-13

Page 4 of 363

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paid high 25 mm dia Sapling 2 m for separately) Farm yard manure Pesticide Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Cost for 10 trees = a+b+c+d+e Rate per trees = (a+b+c+d+e)/10 11.1 0 308 Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil lawns including, weeding, Renovation forking the ground, top dressing with forked soil, watering and maintenance the lawns, for 30 days or more, till the grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish as directed, including supplying good earth, if needed but excluding the cost of well decayed farm Unit = sqm Taking output = 100 sqm a) Labour Mate Mazdoor b) c) Machinery Water tanker6 KL capacity Material Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) sqm = a+b+c+d+e Cost for 100 Rate per sqm = (a+b+c+d+e) 11.1 308.2 1 Supply at Site Well Decayed Farm Yard Manure site of work well decayed farm Supply at yard manure, from any available source, approved by the engineer in charge including screening and stacking Unit = cum Taking output = one cum a) Material a) Cost of well decayed farm yard manure duly screened, loading, carriage, unloading and stacking at b) site Overhead charges @ 2.244% on (a) c) Contractor's profit @ 5% on (a+b) Rate per cum = (a+b+c) 11.1 308.2 2 0 Supply at Site of Work/ Store-Deoiled Neem Cake of work/ store-deoiled neem Supply at site cake duly packed in used gunny bags Unit = quintal Taking output = one quintal a) Cost, carriage, loading, unloading and stacking in store/site b) Overheads@ per cent on (a) c) Contractors profit@ per cent on (a+b)per quintal = a+b+c Rate 11.1 308.2 3 Supplying Sludge Supplying sludge duly stacked at site/ store Unit = cum Taking output = one cum Page 5 of 363

each cum kg KL

10.000 input 0.940 input 0.500 input 12.000 input

#VALUE! M-160 #VALUE! M-167 #VALUE! M-136 #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day hour KL

0.120 3.000 0.500

350.00 180.00 300.00

42.00 540.00 150.00

L-12 L-13 P&M060

3.000 input

#VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

cum

1.000 input

#VALUE! M-167

#VALUE! #VALUE! #VALUE! #VALUE!

quintal

1.000

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth Cost of sludge including carriage, to be paid for separately) a) loading, unloading and stacking at site b) Overheads@ per cent on (a) c) Contractors profit@ per cent on (a+b)per cum = a+b+c Rate 11.1 4 New Half Brick Circular Tree Guard, in 2nd Class Brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20 metre below ground Half brick circular tree guard, in 2nd class brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid dry, and top three courses in cement mortar 1:6 (1 cement 6 sand) and the intermediate courses being in dry honey Unit = Each Taking output = one tree guard a) Labour Mate Mason Mazdoor b) Material Brick 2nd class including carriage Cement mortar 1:6 c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) tree Guard = a+b+c+d Rate per 11.1 5 New Edging with 2nd Class Bricks, Laid Dry Lengthwise 2nd class bricks, laid dry Edging with lengthwise, including excavation, refilling, consolidation, with a hand packing and spreading nearly surplus earth within a lead of 50 = Metre Unit metres Taking output= 10 metres a) Labour Mate Mason Mazdoor b) Material Brick 2nd class including carriage c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) metre = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 11.1 6 New Making Tree Guard 53 cm dia and 1.3 m High as per Design from Empty Bitumen Drums Making tree guard 53 cm dia and 1.3 m high as per design from empty bitumen drum, slit suitably to permit sun and air, (supplied by the department at stock issue rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, Unit = Each Taking output = one tree guard a) Labour Mate Blacksmith Mazdoor b) Material Empty bitumen drum Page 6 of 363

cum

1.000

day day day

0.050 0.250 0.250

350.00 250.00 180.00

17.50 62.50 45.00

L-12 L-11 L-13

each 230.000 input cum 0.025

#VALUE! M-079 Item 12.6 (D)

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day each

0.002 0.050 0.050

350.00 250.00 180.00

0.70 12.50 9.00

L-12 L-11 L-13

50.000 input

#VALUE! M-079 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day each

0.020 0.150 0.070

350.00 250.00 180.00

7.00 37.50 12.60

L-12 L-02 L-13

1.000 input

#VALUE! M-172

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth tosheet 50 for separately) MS be paid x 0.5 mm Rivets 6 mm dia and 10 mm in length d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate for each tree guard = a+b+c+d 11.1 7 New Making Tree Guard 53 cm dia and 2 Metre High as per Design from Empty Bitumen Drums 53 cm dia and 2 metres Making tree guard high as per design from empty bitumen drums, slit suitably to permit sun and air, ( supplied by the department at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets Unit = Each Taking output = one tree guard a) Labour Mate Blacksmith Mazdoor b) Material Empty bitumen drum MS sheet50 x 0.5 mm Rivets 6 mm dia and 10 mm in length MSplate30 x 3 mm c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) each tree guard = a+b+c+d Rate for 11.1 8 New Wrought Iron and Mild Steel Welded Work Wrought iron and mild steel welded work (using angles, square bars, tees and channel grills, grating frames, gates and tree guards of any size and design etc. including cost of screens and welding rods or bolts and nuts complete fixed in position but without the cost of excavation and Unit = quintal Taking output = one quintal a) Labour Mate Blacksmith/ welder for cutting to design and shape and jointing Mazdoor for fixing and helper for b) Blacksmith/welder Material Angle, tees, channels etc Deduct the cost of scrap Add 5 per cent of cost of material for welding rods and other welding accessories c) Overhead charges @ 2.244% on (a+b) Contractor's profit @ 5% on d) (a+b+c) Rate per quintal = a+b+c+d 11.1 9 New Tree Guard with MS Iron

kg each

#VALUE! #VALUE! M-179 / 1000 22.000 input #VALUE! M-158 #VALUE! #VALUE! #VALUE! say #VALUE!

0.650

0.040 day 0.200 0.200 each kg each kg

350.00 250.00 180.00

14.00 50.00 36.00

L-12 L-02 L-13

1.500 input 0.650

#VALUE! M-172

#VALUE! #VALUE! M-179 / 1000 50.000 input #VALUE! M-158 1.300 #VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! #VALUE! say #VALUE!

day day day quintal quintal

0.450 2.000 2.500 1.050 0.050

350.00 250.00 180.00

157.50 500.00 450.00

L-12 L-02 L-13

#VALUE! #VALUE! M-179 / 10 0.00 0.00 M#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 179/10/ 3

Page 7 of 363

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paid for separately) Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm dia and 30 mm long bolts including painting two coats with paint of approved brand over a coat of priming, Unit = Each Taking output = one tree guard a) Labour Mate Blacksmith Mazdoor b) Material MS iron 25 x 6 mm MS iron 25 x 3 mm Add 5 per cent of cost of material for riveting, bolting and welding c) accessories Machinery Tractor-trolley d) Painting Painting two coats including priming e) Overhead charges @ 2.244% on (a+b+c) f) Contractor's profit @ 5% on (a+b+c+e) Rate per tree guard =a+b+c+d+e+f Note 1 The items of excavation and concreting to be measured and paid separately as per design . of painting may be adopted from 2 . Rate the chapter as Traffic signs. New Tree Guard with MS Angle Iron and Steel Wire Providing and fixing tree guard 0.60 metre square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm dia welded and fabricated as Unit = Each per design in two halves Taking output = one a) Labour Mate Blacksmith Welder Mazdoor b) Material MS angle 30 x 30 x 3 mm MS iron 25 x 3 mm Steel wire 3 mm dia Add 5 per cent of cost of material for riveting, bolting and welding c) accessories Machinery Tractor-trolley d) Painting Painting two coats including priming e) Overhead charges @ 2.244% on (a+b+c) f) Contractor's profit @ 5% on (a+b+c+e) Rate per tree guard = a+b+c+d+e+f 11.2 1 New Compensatory Afforestation sqm 1.500 #VALUE! #VALUE! #VALUE! say #VALUE! hour 0.040 300.00 kg kg kg 13.500 #VALUE! #VALUE! M-179 / 1000 18.000 #VALUE! #VALUE! M-179 / 1000 6.000 input #VALUE! M-192 #VALUE! day day day day 0.050 0.250 0.250 0.250 350.00 250.00 250.00 180.00 17.50 62.50 62.50 45.00 L-12 L-02 L-02 L-13 sqm 1.770 #VALUE! #VALUE! #VALUE! say #VALUE! hour 0.040 300.00 12.00 P&M053 kg kg 19.200 9.600 #VALUE! #VALUE! M-179 / 1000 #VALUE! #VALUE! M-179 / 1000 day day day 0.050 0.250 0.250 350.00 250.00 180.00 17.50 62.50 45.00 L-12 L-02 L-13

#VALUE! #VALUE! Item 8.9

11.2 0

12.00

P&M053

#VALUE! #VALUE! Item 8.9

Page 8 of 363

Spreading of sludge farm yard manure or/ and good earth in required thickness (cost of sludge, farm yard manure or/and good earth to be paid for separately) Planting trees as compensatory afforestation at the rate of 290 trees per hectare at a spacing of 6 m by grubbing and leveling the ground upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil, planting of sapling 2 m high with 25 cm dia Unit = Hectare Taking output = one hectare a) Labour Mate Mazdoor ii) For Maintenance for one year Mate Mazdoor b) Machinery Dozer 80 HP @ 1000 sqm/hour Water tanker6 KL capacity (for planting) Water tanker6 KL capacity (for c) maintenance) Material Sapling 1 to 1.5 m high 2 cm dia stem Add 10 per cent of sapling Decayed farm yard/sludge manure (planting)farm yard/sludge manure Decayed (maintenance) Pesticides for planting Pesticides for maintenance Cost of water d) Overhead charges @ 2.244% on (a+b+c) e) Contractor's profit @ 5% on (a+b+c+d) Rate per hectare = a+b+c+d+e Note Cost of fencing to be provided as per size of plot and approved design, measured and paid separately hour hour hour 10.000 input 3.000 25.000 300.00 300.00 #VALUE! 900.00 7500.00 P&M015 P&M060 P&M060 day day 5.000 50.000 350.00 180.00 1750.00 9000.00 L-12 L-13 day day 2.500 25.000 350.00 180.00 875.00 4500.00 L-12 L-13 i) Planting

each 290.000 each cum cum kg kg KL

#VALUE! #VALUE! M-160 x 0.8 29.000 #VALUE! #VALUE! M-160 x 0.8 60.900 input #VALUE! M-167 4.000 input 0.500 input 1.500 input 18.000 input #VALUE! M-167 #VALUE! M-136 #VALUE! M-136 #VALUE! M-189 #VALUE! #VALUE! #VALUE! say #VALUE!

Page 9 of 363

CHAPTER-12 Ref. to Sr No MoRT H 12.1 Spec. 304 FOUNDATIONS Description Excavation for Structures Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and Ordinary soil Unit = cum Taking output = 10 cum A (i) Manual Means Depth upto 3 m a) Labour Mate Mazdoor b) Overhead charges @ 10% on (a) c) Contractor's profit @ 10% on Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day

0.14 3.50

350.00 180.00

say Note 1. Cost of dewatering may be added where required upto, 10 per cent of labour cost Assessment for dewatering shall be made as perexcavated earth can be used partially 2.The site conditions. for backfilling of foundation pit and partly for road work except for marshy soil. Hence cost of disposal has not been added except for marshy soil. This remark is common to all cases of item 12.1 excluding marshy soil. 3.The cost of shoring and shuttering, where needed, may be added @ 1 per cent on cost of excavation for open foundation. Depth 3 m to 6 m a) Labour Mate/Supervisor Mazdoor b) Overhead charges @ 10% on (a) c) Contractor's profit @ 10% on Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10

49.00 630.00 67.90 74.69 821.59 82.16 82.00

L-12 L-13

12.1

(ii)

day day

0.18 4.50

350.00 180.00

63.00 810.00 87.30 96.03 1056.33 105.63 say 106.00

L-12 L-13

12.1

Note Cost of dewatering may be added where required upto 15 per cent of labour cost. Assessment for dewatering shall be done as per actual ground conditions. (iii) Depth above 6 m a) Labour Mate/Supervisor Mazdoor b) Overhead charges @ 10% on (a) c) Contractor's profit @ 10% on Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 Note 1. Cost of dewatering may be added where required upto 20 per cent of labour cost. Assessment for dewatering shall be made as per site conditions.. B Mechanical Means (i) Depth upto 3 m Unit = cum Taking output = 240 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 1.0 cum bucket c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Cost for 240 cum = a+b+c+d Rate per cum = (a+b+c+d)/240 Page 1 of 363

day day

0.24 6.00

350.00 180.00

84.00 1080.00 116.40 128.04 1408.44 140.84 say 141.00

L-12 L-13

12.1

day day hour

0.32 8.00 6.00

350.00 180.00

112.00 1440.00

L-12 L-13 P&M-

1942.00 11652.00 1320.40 1452.44 15976.84 66.57

Ref. to Sr No MoRT H Spec.

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. say 67.00

12.1 (I) B

Note Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per 3 m to 6 m (ii) Depthsite conditions.. Unit = cum Taking output = 210 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 1.0 cum bucket c) capacity Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 210 cum = a+b+c+d Rate per cum = (a+b+c+d)/210 say Note Cost of dewatering upto 7.5 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per above 6m (iii) Depthsite conditions.. Unit = cum Taking output = 180 cum a) Labour Mate Mazdoor b) Machinery Hydraulic excavator 1.0 cum bucket c) capacity Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 180 cum = a+b+c+d Rate per cum = (a+b+c+d)/180 say Note 1. Cost of dewatering upto 10 per cent of (a+b) may be added, where required. Assessment for dewatering shall be made as per site provided 2.Labour conditions.. for excavation by mechanical means includes that required for trimming of bottom and side slopes. II Ordinary Rock (not requiring blasting) A (i) Manual Means Depth upto 3 m Unit = cum Taking output = 10 cum a) Labour Mate Mazdoor b) Overhead charges @ 10% on (a) c) Contractor's profit @ 10% on (a+b) Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 say Note Cost of dewatering upto 10 per cent of labour cost may be added, where required. Assessment for dewatering shall be made as per site conditions.. B Mechanical Means Unit = cum Taking output = 180 cum a) Labour Page 2 of 363 day day 0.20 5.00 350.00 180.00 70.00 900.00 97.00 106.70 1173.70 117.37 117.00 L-12 L-13 hour 6.00 1942.00 11652.00 1359.20 1495.12 16446.32 91.37 91.00 P&M026 day day 0.40 10.00 350.00 180.00 140.00 1800.00 L-12 L-13

day day hour

0.32 8.00 6.00

350.00 180.00

112.00 1440.00

L-12 L-13 P&M026

1942.00 11652.00 1320.40 1452.44 15976.84 76.08 76.00

12.1 (I) B

12.1

12.1(II )

Ref. to Sr No MoRT H Spec. b)

Description Mate Mazdoor Machinery Hydraulic excavator 1.0 cum bucket c) capacity Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 180 cum = a+b+c+d Rate per cum = (a+b+c+d)/180

Unit day day hour

Quantity 0.24 6.00 6.00

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 84.00 L-12 180.00 1080.00 L-13 P&M026

1942.00 11652.00 1281.60 1409.76 15507.36 86.15 say 86.00

12.1

Note 1.Cost of dewatering upto 10 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per siteof rock, foundation beyond3 m is 2.In case conditions. not dug and hence not included. III Hard Rock ( requiring blasting ) A Manual Means Unit = cum Taking output = 10 cum a) Labour Mate Driller Blaster Mazdoor b) Machinery hour 1.00 285.00 285.00 P&M001 Air Compressor 250 cfm with 2 jack hammer for drilling. c) Material Blasting Material Detonator electric d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 10 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/10 Note Cost of dewatering @ 10 per cent of (a+b) may be added, where required Assessment for dewatering shall be made as per site conditions. IV Hard Rock ( blasting prohibited ) Unit = cum Taking output = 10 cum A Mechanical Means a) Labour Mate Mazdoor b) Machinery hour 6.00 285.00 1710.00 268.00 294.80 3242.80 324.28 say Note 1. Cost of dewatering upto10 per cent of (a+b), may be added, where required Assessment for dewatering shall be made as per siteof rock, foundation beyond3 m is 2.In case conditions. not dug and hence not included. V Marshy Soil Unit = cum 324.00 P&M001 Air Compressor 250 cfm with 2 leads of pneumatic breaker c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 10 cum = a+b+c+d Rate per cum = (a+b+c+d)/10 day day 0.20 5.00 350.00 180.00 70.00 900.00 L-12 L-13 day day day day 0.35 0.50 0.25 8.00 350.00 250.00 250.00 180.00 122.50 125.00 62.50 1440.00 L-12 L-06 L-03 L-13

kg each

3.50 14.00

input #VALUE! M-104 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! M#VALUE! 094/100

12.1

12.1

Page 3 of 363

Ref. to Sr No MoRT H Spec. A

Description Taking output = 10 cum Depth upto 3 m Manual means a) Labour Mate/Supervisor Mazdoor b) Machinery Tractor-trolley for removal. c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 10 cum = a+b+c+d Rate per cum = ( a+b+c+d)/ 10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.40 10.00 2.67

350.00 180.00 300.00

140.00 1800.00 801.00 274.10 301.51 3316.61 331.66

L-12 L-13 P&M053

say Note 1. Cost of dewatering @ 30 per cent of (a), may be added, where required Assessment for dewatering shall be made as per site conditions. & strutting 15 per cent of (a), 2. Shoring where required may be added 3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item12.1 (i) to (iv) B Mechanical Means for ordinary soil a) Labour Mate Mazdoor for dressing sides, bottom and b) backfilling Machinery Hydraulic excavator 1.0 cum bucket capacity @ 60 cum per hour Tipper 5.5 cum capacity, 4 trips per c) hour. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 10 cum = a+b+c+d Rate per cum = (a+b+c+d)/10 say Note 1. Cost of dewatering @ 20 per cent of (a+b) may be added, where required 2. Shoring & strutting @ 10 per cent of (a+b), where required may be added 3. It is assumed that Marshy Soil will be available upto 3 m depth only. For deeper excavation below 3 m depth, refer analysis in item 12.1 in Marshy Foundation VI Back Filling(i) to (iv) for ordinary soil Pits Unit : Cum Taking Output : 6 cum a) Labour Mate Mazdoor for dressing sides, bottom and b) backfilling Machinery Tractor-trolley for transportation c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 6 cum = a+b+c+d Rate per cum = (a+b+c+d)/6 say 12.2 304 Filling Annular Space Around Footing in Rock Unit = cum Taking out put = 1 cum Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per item 12.4. day day hour 0.12 3.00 2.00 350.00 180.00 300.00 day day hour hour 0.08 2.00 0.17 0.45 350.00 180.00 1942.00 497.00

332.00

12.1 (V)

28.00 360.00 330.14 223.65 94.18 103.60 1139.57 113.96 114.00

L-12 L-13 P&M026 P&M048

42.00 540.00 600.00 118.20 130.02 1430.22 238.37 238.00

L-12 L-13 P&M053

Page 4 of 363

Ref. to Sr No MoRT H 12.3 Spec. 304

Description Sand Filling in Foundation Trenches as per Drawing & Technical Specification Unit = cum Taking output = 1 cum a) Labour Mate Mazdoor b) Material Sand (assuming 20 per cent voids) c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per cum = a+b+c+d

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day cum

0.01 0.30 1.20

350.00 180.00

3.50 54.00

L-12 L-13

input #VALUE! M-006 #VALUE! #VALUE! #VALUE! say #VALUE!

12.4

2100

PCC 1:3:6 in Foundation Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. Unit = cum Taking output = 15 cum a) Labour Mate Mason Mazdoor b) Material 40 mm Aggregate coarse Sand cement Cost of water c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Water tanker 6 KL capacity d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 Note Vibrator is a part of minor T & P which is already included in overhead charges of the contractor. Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. Unit = cum Taking output = 5 cum a) Material Bricks Ist class Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) b) Labour Mate Mason Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 5 cum = a+b+c+d Rate per cum (a+b+c+d)/5 each cum 2500.00 1.20 input #VALUE! M-079 #VALUE! #VALUE! Item 12.6 (A) L-12 L-11 L-13 hour hour hour 6.00 6.00 2.00 165.00 540.00 300.00 990.00 3240.00 600.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M009 P&M079 P&M060 cum cum tonne KL 13.50 6.75 3.45 18.00 input #VALUE! M-055 input #VALUE! M-005 input #VALUE! M-081 input #VALUE! M-189 day day day 0.64 1.00 15.00 350.00 250.00 180.00 224.00 250.00 2700.00 L-12 L-11 L-13

12.5

1300

day day day

0.48 4.00 8.00

350.00 250.00 180.00

168.00 1000.00 1440.00 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! Page 5 of 363

Ref. to Sr No MoRT H 12.6 Spec. Subanaly sis

Description (A) Cement Mortar 1:3 (1 cement : 3 sand)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) Subanaly sis (Addl. ) (B) Cement Mortar1:2 (1cement :2 sand) day day 0.04 0.90 350.00 180.00 14.00 162.00 L-12 L-13 tonne cum 0.51 1.05 input #VALUE! M-081 input #VALUE! M-005

say #VALUE!

Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) day day 0.04 0.90 350.00 180.00 14.00 162.00 L-12 L-13 tonne cum 0.67 0.93 input #VALUE! M-081 input #VALUE! M-005

say #VALUE!

Subanaly sis (Addl. )

(C)

Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) day day 0.04 0.90 350.00 180.00 14.00 162.00 L-12 L-13 tonne cum 0.40 1.12 input #VALUE! M-081 input #VALUE! M-005

say #VALUE!

Subanaly sis (Addl. )

(D)

Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum Taking output = 1 cum a) Materials Cement Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b) day day 0.04 0.90 350.00 180.00 14.00 162.00 L-12 L-13 tonne cum 0.29 1.34 input #VALUE! M-081 input #VALUE! M-005

say #VALUE!

12.7

1400

Stone Masonry Work in Cement Mortar 1:3 in Foundation complete as per Drawing and Technical Specifications. Unit = cum Taking output = 5 cum (A) Square Rubble Coursed Masonry (first sort) a) Material Stone Page 6 of 363 Rubble

1405. 4

cum

5.50

input #VALUE! M-169

Ref. to Sr No MoRT H Spec.

Description Through and bond stone (35no.x0.24mx0.24mx0.39m = 0.79 cu.m) Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) b) Labour Mate Mason Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 5 cum = a+b+c+d Rate per cum (a+b+c+d)/5

Unit each cum

Quantity 35.00 1.50

Rate Rs

Remark Cost Rs s/ Input ref. input #VALUE! M-182 Item 12.6 (A) L-12 L-11 L-13

#VALUE! #VALUE!

day day day

0.66 7.50 9.00

350.00 250.00 180.00

231.00 1875.00 1620.00 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 1405. 3 (B) Random Rubble Masonry ( coursed/uncoursed ) Unit = cum Taking output = 5 cum a) Material Stone Through and bond stone (35nos.x0.24mx0.24mx0.39m = 0.79 cu.m) Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) b) Labour Mate Mason Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 5 cum = a+b+c+d Rate per cum (a+b+c+d)/5 Note The labour already considered in cement mortar has been taken into account while proposing labour for masonry works. Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. A PCC Grade M15 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 63 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery Page 7 of 363 hour hour 6.00 6.00 #VALUE! #VALUE! 165.00 990.00 input #VALUE! P&M009 P&M019 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum cum 4.13 6.75 8.10 4.05 1.35 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 cum 1.55 #VALUE! #VALUE! Item 12.6 (A) L-12 L-11 L-13 cum each 5.50 35.00 input #VALUE! M-148 input #VALUE! M-182

day day day

0.62 6.00 9.00

350.00 250.00 180.00

217.00 1500.00 1620.00 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

12.8

1500, 1700 & 2100

Ref. to Sr No MoRT H Spec.

Description e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 Note Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not added in rate analysis of cement concrete PCC Grade M20 works. Unit : cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

12.8

tonne cum cum cum cum day day day hour hour

5.16 6.75 5.40 5.40 2.70 0.86 1.50 20.00 6.00 6.00 #VALUE!

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 165.00 540.00 301.00 375.00 3600.00 990.00 3240.00 L-12 L-11 L-13 P&M009 P&M079 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.8

RCC Grade M20 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 4 per cent on (a+b+c) e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = ( a+b+c+d+e+f )/15 hour hour 6.00 6.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 5.21 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051

Case I Using Concrete Mixer

Page 8 of 363

Ref. to Sr No MoRT Description H 12.8 C Spec. Case II With Batching Plant, Transit Mixer and Concrete Pump Unit : cum Taking Output = 120 cum a) Material Cement Coarse Sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 1 km, L-lead in km Lead beyond

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

tonne cum cum cum day day day hour hour hour hour tonne.k m hour

41.66 54.00 64.80 43.20 0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 294.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

890.00 13350.00 input #VALUE!

Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = ( a+b+c+d+e+f )/120 12.8 D PCC Grade M25 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.75 per cent of (a+b+c) e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = ( a+b+c+d+e+f )/15 12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump Unit : cum Page 9 of 363

6 #VALUE!

165.00

990.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case I Using Concrete Mixer

tonne cum cum cum cum day day day hour hour

5.99 6.75 5.40 5.40 2.70 0.86 1.50 20.00 6.00 6.00 #VALUE!

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 165.00 540.00 301.00 375.00 3600.00 990.00 3240.00 L-12 L-11 L-13 P&M009 P&M079 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec.

Description Taking Output = 120 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.75 per cent of cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

tonne cum cum cum cum day day day hour hour hour hour tonne.k m hour

47.95 54.00 43.20 43.20 21.60 0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 294.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

890.00 13350.00 input #VALUE!

6 #VALUE!

165.00

990.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.8

RCC Grade M25 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.75 per cent of a+b+c. e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 15 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f )/15 hour hour 6.00 6.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 6.05 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051

Case I Using Concrete Mixer

12.8 E

Case II With Batching Plant, Transit Mixer and Concrete Pump Unit: cum Taking Output = 120 cum a) Material

Page 10 of 363

Ref. to Sr No MoRT H Spec.

Description Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity 1 cum Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.75 per cent on cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f )/120

Unit tonne cum cum cum day day day hour hour hour hour tonne.k m hour

Quantity 48.38 54.00 64.80 43.20 0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

Rate Rs

Remark Cost Rs s/ Input ref. input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051

350.00 250.00 180.00 1526.00 793.00 1042.00

294.00 750.00 3240.00 9156.00 4758.00 6252.00

L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.8

PCC Grade M30 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.50 per cent of cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 15 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f )/15 hour hour 6.00 6.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum cum 6.08 6.75 5.40 5.40 2.70 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051

Case I Using Concrete Mixer

12.8 F

Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit : cum Taking Output = 120 cum a) Material Cement Coarse sand Page 11 of 363 tonne cum 48.60 54.00 input #VALUE! M-081 input #VALUE! M-004

Ref. to Sr No MoRT H Spec.

Description 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.50 per cent of cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f )/120

Unit cum cum cum day day day hour hour hour hour tonne.k m hour

Quantity 43.20 43.20 21.60 0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

Rate Rs

Remark Cost Rs s/ Input ref. input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051

350.00 250.00 180.00 1526.00 793.00 1042.00

294.00 750.00 3240.00 9156.00 4758.00 6252.00

L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.8

RCC Grade M30 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.5 per cent on cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 hour hour 6.00 6.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 6.10 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051

Case I Using Concrete Mixer

12.8 G

Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Page 12 of 363 tonne cum cum cum 48.80 54.00 64.80 43.20 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051

Ref. to Sr No MoRT H Spec.

Description b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3.5 per cent of cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum (a+b+c+d+e+f )/120

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 294.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

day day day hour hour hour hour tonne.k m hour

0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

350.00 250.00 180.00 1526.00 793.00 1042.00

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.8

RCC Grade M35 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3 per cent on a+b+c e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 hour hour 6.00 6.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 6.33 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051

Case I Using Concrete Mixer

12.8 H

Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit ; cum Taking Output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason day day 0.84 3.00 350.00 250.00 294.00 750.00 L-12 L-11 tonne cum cum cum 50.64 54.00 64.80 43.20 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051

Page 13 of 363

Ref. to Sr No MoRT H Spec. c)

Description Mazdoor Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 3 per cent on cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 Note: Where ever concrete is carried batching plant, transit mixer, pump, Admixtures @ 0.4 per cent of cement may be added for desired slump of concrete. out using concrete of weight achieving

Unit day hour hour hour hour tonne.k m hour

Quantity 18.00 6.00 6.00 6.00 15.00 300L

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 3240.00 L-13 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

1526.00 793.00 1042.00

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

WELL FOUNDATION

12.9

1200

Providing and Constructing Temporary Island 16 m diameter for Construction of Well Foundation for 8m dia. Well. Assuming depth of water 1.0 m and height of island to be 1.25 m. Unit = 1 No Taking output = 1 No. a) Material Earth (compacted) Sand bags b) Labour Mate Mazdoor for filling sand bags, stitching c) and placing Machinery Crane with grab 1 cum capacity Consumables @ 2.5 per cent of (c) above d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per No. (a+b+c+d+e) day day hour 0.40 15.00 20.00 350.00 180.00 140.00 2700.00 L-12 L-13 P&M012 cum each 251.20 750.00 input #VALUE! M-092 input #VALUE! M-159

550.00 11000.00 275.00 #VALUE! #VALUE! #VALUE! say #VALUE!

12.9

Note It is assumed that earth will be available within the working space of crane with grab bucket. B Assuming depth of water 4.0 m and height of island 4.5 m. Unit = 1No Taking output = 1 No a) Material Earth (compacted) Sand bags Wooden ballies 8" Dia and 9 m long Wooden ballies 2" Dia for bracing b) Labour Mate Mazdoor for piling 8" dia ballies for piling 8" dia ballies Mazdoor for bracing with 2" dia ballies day day day 5.60 18.00 12.00 350.00 180.00 180.00 1960.00 3240.00 2160.00 L-12 L-13 L-13 cum each each metre 904.32 6000.00 95.00 190.00 input #VALUE! M-092 input #VALUE! M-159 input #VALUE! M-194 input #VALUE! M-193

Page 14 of 363

Ref. to Sr No MoRT H Spec.

Description Mazdoor for filling sand bags, stitching c) and placing Machinery Crane with grab 1 cum capacity Consumables and other arrangements for piling ballies @ 2.5 per cent of (a+b+c). d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per No. (a+b+c+d+e) Note For other well diameters rate can be worked out on the basis of cross-sectional area of well. The diameter of the island shall be in the conformity with clause 1203.2 of MoRTH specifications. Providing and constructing one span service road to reach island location from one pier location to another pier location span length 30 m, width of Assuming service road 10m and depth of water 1m Unit = 1 meter Taking output = 30 metre a) Material Earth Sand bags b) Labour Mate Mazdoor for filling sand bags, stitching c) and placing Machinery Front end Loader 1 cum capacity Tipper 5.5 cum capacity d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 30 m (a+b+c+d+e) Rate per m (a+b+c+d+e)/30

Unit day hour

Quantity 110.00 50.00

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 19800.00 L-13 550.00 27500.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M012

12.9

cum each day day hour hour

450.00 300.00 0.24 6.00 27.00 28.00

input #VALUE! M-092 input #VALUE! M-159 350.00 180.00 84.00 1080.00 L-12 L-13 P&M017 P&M048

1042.00 28134.00 497.00 13916.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.10

1200 & 1900

Providing and Laying Cutting Edge of Mild Steel weighing 40 kg per metre for Well Foundation complete as per Drawing and Technical Specification. Unit = 1 MT Taking output = 1 MT a) Material Structural steel in plates, angles, etc including 5 per cent wastage Nuts & bolts b) Labour (for cutting, bending, making holes, joining, welding and erecting in position) Mate Fitter Blacksmith Welder Mazdoor Electrodes, cutting gas and other consumables @ 10 per cent of cost of (a) above Overhead charges @ 10% on c) (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per MT (a+b+c+d) tonne Kg 1.05 20.00 input #VALUE! M-179 input #VALUE! M-130

day day day day day

1.32 5.50 5.50 5.50 16.50

350.00 250.00 250.00 250.00 180.00

462.00 1375.00 1375.00 1375.00 2970.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-08 L-02 L-02 L-13

say #VALUE! 12.11 1200, 1500 & 1700 Plain/Reinforced Cement Concrete, in Well Foundation complete as per Drawing and Technical Specification. Page 15 of 363

Ref. to Sr No MoRT H Spec. A (i)

Description Unit = 1 cum Taking output = 1 cum Well curb RCC M20 Grade

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Same as for 12.8 (C) except for formwork which shall be@ 20 per cent of the cost of concrete instead of 4 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 20 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 A (i) Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 20 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 A (ii) RCC M25 Grade #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Same as for 12.8 (E) except for formwork which shall be@ 20 per cent of the cost of concrete instead of 3.75 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 20 per cent of the cost of e) concrete Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 A (ii)

Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 20 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 A

(iii)

RCC M35 Grade

Same as for 12.8 (H) except for formwork which shall be@ 20 per cent of the cost of concrete instead of 3.0 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 20 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 A (iii)

Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

#VALUE!

Page 16 of 363

Ref. to Sr No MoRT H Spec.

Description d) formwork @ 20 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) Note. If curb concrete is carried out within steel liner, cost of formwork shall be excluded.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

12.11

B (I)

Well steining PCC M15 Grade

Same as for 12.8 (A) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 B (ii) PCC M20 Grade #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Same as for 12.8 (B) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of e) concrete Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 B (iii) RCC M20 Grade #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Same as for 12.8 (C) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 B (iii) Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 B (iv) PCC M25 Grade #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Same as for 12.8 (D) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 4 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Page 17 of 363 #VALUE!

Ref. to Sr No MoRT H Spec.

Description d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 12.11 B (iv) Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) '12.11 B (v) RCC M25 Grade

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Same as for 12.8 (E) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3.5 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 B (v)

Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

'12.11 B

(vi)

PCC M30 Grade

Same as for 12.8 (F) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3.5 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of e) concrete Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 B (vi)

Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

'12.11 B

(vii)

RCC M30 Grade

Same as for 12.8 (G) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3.5 per cent. Case I Using Concrete Mixer Page 18 of 363

Ref. to Sr No MoRT H Spec.

Description Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 12.11 B (vii) Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) '12.11 B (viii) RCC M35 Grade Same as for 12.8 (H) except for formwork which shall be @ 10 per cent of the cost of concrete instead of 3 per cent. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.11 B (viii) Case II With Batching Plant, Transit Mixer and Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) formwork @ 10 per cent of the cost of concrete e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) '12.11 B (ix) RCC M40 Grade Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse Sand 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Meson Mazdoor c) Machinery Batching Plant Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity for lead Transit Mixer beyond 1 km. Concrete Pump Page 19 of 363 hour hour hour hour tonne.k m hour 6.00 6.00 6.00 15.00 300xL 6.00 1526.00 793.00 1042.00 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&Mday day day 0.84 3.00 18.00 350.00 250.00 180.00 294.00 750.00 3240.00 L-12 L-11 L-13 tonne cum cum cum kg 51.60 54.00 64.80 43.20 206.00 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

890.00 13350.00

049 input #VALUE! Lead= 35 , 165.00 990.00 P&MP&M007

Ref. to Sr No MoRT H Spec.

Description Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 10 per cent on cost of concrete i.e. cost of material, labour and machinery e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) cost of 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120

Unit

Quantity #VALUE!

Rate Rs

Remark Cost Rs s/ Input ref.

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 C

Bottom Plug Concrete to be placed using tremie pipe Note: 10% extra cement to be added where under water concreting is involved PCC Grade M20 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane 3 tonnes capacity for handling tremie pipe Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with Overhead d) tremie pipe.. charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 hour hour hour 6.00 6.00 6.00 #VALUE! #VALUE! 165.00 540.00 230.00 990.00 3240.00 1380.00 P&M009 P&M079 P&M013 day day day 0.90 1.50 20.00 350.00 250.00 180.00 315.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum cum Kg 5.55 6.75 5.40 5.40 2.70 18.60 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

(i)

Case I Using Concrete Mixer

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 C (i)

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit ; cum Taking Output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery day day day 0.88 3.00 18.00 350.00 250.00 180.00 308.00 750.00 3240.00 L-12 L-11 L-13 tonne cum cum cum Kg 44.40 54.00 64.80 43.20 148.80 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Page 20 of 363

Ref. to Sr No MoRT H Spec.

Description Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity, lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120

Unit hour hour hour hour tonne.k m hour

Quantity 6.00 6.00 6.00 15.00 300L

Rate Rs

Remark Cost Rs s/ Input ref. 1526.00 9156.00 P&M002 793.00 4758.00 P&M080 1042.00 6252.00 P&M890.00 13350.00 input #VALUE! 017 P&M049 P&M050 Lead= 35 km P&M007

6.00 #VALUE!

165.00

990.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

'12.11 C

(ii)

PCC Grade M25 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane of 3 tonnes capacity for handling tremie pipe Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 hour hour hour 6.00 6.00 6.00 #VALUE! #VALUE! 165.00 540.00 230.00 990.00 3240.00 1380.00 P&M009 P&M079 P&M013 day day day 0.90 1.50 20.00 350.00 250.00 180.00 315.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum cum Kg 5.99 6.75 5.40 5.40 2.70 21.60 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Case I Using Concrete Mixer

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 C (ii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture Page 21 of 363 tonne cum cum cum Kg 47.88 54.00 64.80 43.20 172.80 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Ref. to Sr No MoRT H Spec.

Description b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity, lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 308.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

day day day hour hour hour hour tonne.k m hour

0.88 3.00 18.00 6.00 6.00 6.00 15.00 300L

350.00 250.00 180.00 1526.00 793.00 1042.00

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

'12.11 C

(iii)

PCC Grade M30 Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane of 3 tonnes capacity for handling tremie pipe Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 hour hour hour 6.00 6.00 6.00 #VALUE! #VALUE! 165.00 540.00 230.00 990.00 3240.00 1380.00 P&M009 P&M079 P&M013 day day day 0.90 1.50 20.00 350.00 250.00 180.00 315.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum cum Kg 6.08 6.75 5.40 5.40 2.70 21.60 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Case I Using Concrete Mixer

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 C (iii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit = cum Taking output = 120 cum a) Material Page 22 of 363

Ref. to Sr No MoRT H Spec.

Description Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity, lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120

Unit tonne cum cum cum Kg day day day hour hour hour hour tonne.k m hour

Quantity 48.64 54.00 64.80 43.20 172.80 0.88 3.00 18.00 6.00 6.00 6.00 15.00 300L

Rate Rs

Remark Cost Rs s/ Input ref. input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

350.00 250.00 180.00 1526.00 793.00 1042.00

308.00 750.00 3240.00 9156.00 4758.00 6252.00

L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

'12.11 C

(iv)

PCC Grade M35 Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Light Crane of 3 tonnes capacity for handling tremie pipe Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 hour hour hour 6.00 6.00 6.00 #VALUE! #VALUE! 165.00 540.00 230.00 990.00 3240.00 1380.00 P&M009 P&M079 P&M013 day day day 0.90 1.50 20.00 350.00 250.00 180.00 315.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum cum Kg 6.29 6.75 5.40 5.40 2.70 21.60 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Case I Using Concrete Mixer

#VALUE! #VALUE! #VALUE! #VALUE!

Page 23 of 363

Ref. to Sr No MoRT H Spec. 12.11 C (iv)

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. say #VALUE!

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity, lead Transit Mixer beyond 1 Km, L - lead in Kilometer Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) Add 5 per cent of cost of material and labour towards cost of forming sump, protective bunds, chiselling and making arrangements for under water concreting with tremie pipe.. charges @ 10% on d) Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120 hour hour hour hour tonne.k m hour 6.00 6.00 6.00 15.00 300L 1526.00 793.00 1042.00 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&M049 P&M050 Lead= 35 km P&M007 day day day 0.88 3.00 18.00 350.00 250.00 180.00 308.00 750.00 3240.00 L-12 L-11 L-13 tonne cum cum cum Kg 50.28 54.00 64.80 43.20 172.80 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

990.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11

D (i)

Intermediate plug Grade M20 PCC

Same as in bottom plug concrete, excluding cost of forming sump, protective bunds, chiseling etc. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) 12.11 D (i) Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) '12.11 D (ii) Grade M25 PCC #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Same as in bottom plug concrete, excluding cost of forming sump, protective bunds, chiseling etc. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) Page 24 of 363 #VALUE! #VALUE!

Ref. to Sr No MoRT H Spec.

Description e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE! 12.11 D (ii)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

'12.11 D

(iii)

Grade M30 PCC

Same as in bottom plug concrete, excluding cost of forming sump, protective bunds, chiseling etc. Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11 D (iii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.11

E (i)

Top plug Grade M15 PCC Same as Item 12.8(a) excluding formwork

Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) '12.11 E (ii) Grade M20 PCC Same as Item 12.8(b) excluding formwork Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) '12.11 E (iii) Grade M25 PCC excluding #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 12.11 E (iii) Case II Using Batching Plant, Transit Mixer and Crane/concrete pump #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Same as Item 12.8 (d) formwork Case I Using Concrete Mixer #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e)

Page 25 of 363

Ref. to Sr No MoRT H Spec.

Description Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! '12.11 E (iv) Grade M30 PCC Same as Item 12.8(f) excluding formwork Case I Using Concrete Mixer Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) 12.11 E (iv) Case II Using Batching Plant, Transit Mixer and Crane/concrete pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) 12.11 F (i) Well cap RCC Grade M20 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Form Work @ 4 per cent of a+b+c d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 12.11 F (i) Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason day day 0.84 3.00 350.00 250.00 294.00 750.00 L-12 L-11 tonne cum cum cum 40.92 54.00 64.80 43.20 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 hour hour 6.00 6.00 165.00 540.00 990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 5.12 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case I Using Concrete Mixer

Page 26 of 363

Ref. to Sr No MoRT H Spec. c)

Description Mazdoor Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m )

Unit day hour hour hour

Quantity 18.00 6.00 6.00 6.00 15.00 300L

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 3240.00 L-13 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&M049 P&M-

1526.00 793.00 1042.00

hour Transit Mixer 4 cum capacity for lead upto 1 km. 1 Km, L - lead in Kilometer tonne.k Lead beyond m Concrete Pump Formwork @ 4 per cent of (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120 12.11 F (ii) RCC Grade M25 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Form Work @ 3.75 per cent of a+b+c d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 12.11 F (ii) Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) hour hour hour day day day tonne cum cum cum hour hour day day day tonne cum cum cum hour

890.00 13350.00 input #VALUE!

6.00

165.00

050 Lead= 990.00 35 km P&M#VALUE! 007 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! Case I Using Concrete Mixer

6.05 6.75 8.10 5.40 0.86 1.50 20.00 6.00 6.00

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 165.00 540.00 301.00 375.00 3600.00 990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-11 L-13 P&M009 P&M079

48.40 54.00 64.80 43.20 0.84 3.00 18.00 6.00 6.00 6.00

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 294.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017

Page 27 of 363

Ref. to Sr No MoRT H Spec.

Description

Unit

Quantity 15.00 300L

Rate Rs

hour Transit Mixer 4 cum capacity for lead upto 1 km. 1 Km, L - lead in Kilometer tonne.k Lead beyond m Concrete Pump Formwork @ 3.75 per cent of ( a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120 hour

Remark Cost Rs s/ Input ref. 890.00 13350.00 P&M049 input #VALUE! P&M050 Lead= 990.00 35 km P&M#VALUE! 007 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

6.00

165.00

12.11 F

(iii)

RCC Grade M30 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Formwork @ 3.5 per cent of (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 hour hour 6.00 6.00 165.00 540.00 990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 6.10 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051

Case I Using Concrete Mixer

12.11 F (iii)

Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) hour Transit Mixer 4 cum capacity for lead upto 1 km. 1 Km, L - lead in Kilometer tonne.k Lead beyond m Concrete Pump Formwork @ 3.5 per cent of (a+b+c) d) Overhead charges @ 10% on (a+b+c) Page 28 of 363 hour 15.00 300L 890.00 13350.00 input #VALUE! hour hour hour 6.00 6.00 6.00 1526.00 793.00 1042.00 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&M049 P&Mday day day 0.84 3.00 18.00 350.00 250.00 180.00 294.00 750.00 3240.00 L-12 L-11 L-13 tonne cum cum cum 48.79 54.00 64.80 43.20 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051

6.00

165.00

050 Lead= 990.00 35 km P&M#VALUE! 007 #VALUE!

Ref. to Sr No MoRT H Spec.

Description e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE!

say #VALUE! 12.11 F (iv) RCC Grade M35 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Formwork @ 3 per cent of (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15 12.11 F (iv) Case II Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) hour Transit Mixer 4 cum capacity for lead upto beyond Lead 1 km. 1 Km, L - lead in Kilometer tonne.k m Concrete Pump Formwork @ 3 per cent of (a+b+c) d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120 hour 15.00 300L 890.00 13350.00 input #VALUE! hour hour hour 6.00 6.00 6.00 1526.00 793.00 1042.00 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&M049 P&Mday day day 0.84 3.00 18.00 350.00 250.00 180.00 294.00 750.00 3240.00 L-12 L-11 L-13 tonne cum cum cum 50.64 54.00 64.80 43.20 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 hour hour 6.00 6.00 165.00 540.00 990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 6.33 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 Case I Using Concrete Mixer

6.00

165.00

050 Lead= 990.00 35 km P&M#VALUE! 007 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

Page 29 of 363

Ref. to Sr No MoRT H Spec.

Description Note Where ever concrete is carried batching plant, transit mixer, pump, Admixtures @ 0.4 per cent of cement may be added for desired slump of (v) RCC M40 Gradeconcrete. out using concrete of weight achieving

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

'12.11 F

Using Batching Plant, Transit Mixer and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse Sand 20 mm Aggregate 10 mm Aggregate Admixture b) Labour Mate Mason Mazdoor c) Machinery Batching Plant Generator 100 KVA Loader 1 cum capacity Transit Mixer 4 cum capacity for lead upto 1 km. 4 cum capacity for lead Transit Mixer beyond 1 km. Concrete Pump Formwork @ 3 per cent on cost of concrete i.e. cost of material, labour d) and machinery Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost of 120 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/120 hour hour hour hour tonne.k m hour 6.00 6.00 6.00 15.00 300.L 1526.00 793.00 1042.00 9156.00 4758.00 6252.00 P&M002 P&M080 P&M017 P&Mday day day 0.84 3.00 18.00 350.00 250.00 180.00 294.00 750.00 3240.00 L-12 L-11 L-13 tonne cum cum cum kg 52.20 54.00 64.80 43.20 206.00 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

890.00 13350.00 input #VALUE!

6.00

165.00

049 P&M050 Lead= 990.00 35 km P&M#VALUE! 007 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 12.12 Sectio n 1200 Sinking of 6 m external diameter well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter. Taking output = 1 m Diameter of well - 6 m. A (i) Sandy Soil Depth below bed level upto 3.0 M Rate of sinking = 0.50 m per hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 2.00 4000.00 8000.00 800.00 945.20 1039.72 11436.92 say 12.12 A (ii) Beyond 3m upto 10m depth Page 30 of 363 ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.12 1.00 2.00 350.00 250.00 180.00 42.00 250.00 360.00 L-12 L-15 L-14

Ref. to Sr No MoRT H Spec.

Description Rate of sinking = 0.33 m per hour. a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.15 1.25 2.50 3.00

350.00 250.00 180.00

52.50 312.50 450.00

L-12 L-15 L-14 P&M075

4000.00 12000.00 1200.00 1401.50 1541.65 16958.15 say ###

12.12 A

(iii) a

Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

17806.00 18696.00 19631.00 20613.00 21644.00 22726.00 23862.00 25055.00 26308.00 27623.00 ### ###

12.12 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour. 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

29695.00 31922.00 34316.00 36890.00 39657.00 42631.00 45828.00 49265.00 52960.00 56932.00

Including 20% for Kentledge 35634.00 38306.00 41179.00 44268.00 47588.00 51157.00 54994.00 59118.00 63552.00 68318.00

### 504114.00 ### 50411.00

12.12 A

(v) a b

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 31st m Labour. 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m Page 31 of 363

10% 10% 10% 10% 10% 10% 10% 10% 10%

62625.00 68888.00 75777.00 83355.00 91691.00

Including 20% for Kentledge 75150.00 82666.00 90932.00 100026.00 110029.00

### 121032.00 ### 133135.00 ### 146449.00 ### 161094.00

Ref. to Sr No MoRT H Spec.

Description 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit 10%

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

### 177204.00 ### ### ### ###

12.12

Clayey Soil ( 6m dia. Well ) Unit = Running Meter. Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M Rate of sinking = 0.33 m per hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 3.00 4000.00 12000.00 1200.00 1403.25 1543.58 16979.33 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.15 1.50 2.25 350.00 250.00 180.00 52.50 375.00 405.00 L-12 L-15 L-14

12.12 B

(ii)

Beyond 3m upto 10m depth Rate of sinking = 0.17 m per hour. a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour hour 6.00 2.00 4000.00 24000.00 600.00 1200.00 2520.00 2938.50 3232.35 35555.85 say ### P&M075 P&M063 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.30 3.00 4.50 350.00 250.00 180.00 105.00 750.00 810.00 L-12 L-15 L-14

12.12 B

(iii) a b

Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required.

11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre 12.12 B (iv) a Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter Page 32 of 363

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

37334.00 39201.00 41161.00 43219.00 45380.00 47649.00 50031.00 52533.00 55160.00 57918.00

Including for dewatering @ 5% of cost, if 39201.00 41161.00 43219.00 45380.00 47649.00 50031.00 52533.00 55160.00 57918.00 60814.00

### 493066.00 ### 49307.00

Ref. to Sr No MoRT H Spec.

Description b c Add 5 per cent of cost for dewatering of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 21st m 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

62262.00 66932.00 71952.00 77348.00 83149.00 89385.00 96089.00

Including Including 25% for 5% for Kentledge dewaterin g, if required 77828.00 81719.00 83665.00 87848.00 89940.00 94437.00 96685.00 103936.00 111731.00 120111.00 ### ### ### ### ### ### ### ### ###

### 129120.00 ### 138804.00 ### 149214.00 ### ### ### ###

12.12 B

(v) a b c

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 157570.00 required ### ### 173327.00 ### 190660.00 ### 209725.00 ### 230698.00 ### 253768.00 ### 279144.00 ### 307058.00 ### 337764.00 ### 371540.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

12.12

Soft Rock (6m dia well ) Unit = Running Meter. Taking output = 1 m Depth in Soft rock strata up to 3m Rate of sinking = 0.25 m per hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ of 5 per cent of Add for (a+b), if required c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) say hour hour 4.00 3.50 4000.00 16000.00 600.00 2100.00 1810.00 1237.85 2599.49 2859.43 31453.77 ### P&M075 P&M063 day day day day 0.92 3.00 20.00 0.50 350.00 250.00 180.00 350.00 322.00 750.00 3600.00 175.00 L-12 L-15 L-14 L-07

Page 33 of 363

Ref. to Sr No MoRT H 12.12 Spec.

Description D Hard Rock (6m dia well ) Unit = Running Meter Taking output = 1 m Depth in hard rock strata upto 3 m Rate of sinking = 0.17 m per hour. a) Material Gelatine 80 per cent Electric Detonators b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling. @ 5 per cent of cost of Dewatering (b+c), if required. Consumables in sinking @ 10 per cent d) of cost of (b). charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per metre = (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

Kg each day day day day day hour hour

4.00 18.00 1.56 2.00 0.25 12.00 4.00 6.00 2.00

input #VALUE! M-104 #VALUE! #VALUE! 350.00 250.00 250.00 180.00 250.00 546.00 500.00 62.50 2160.00 1000.00 M094/100 L-12 L-06 L-03 L-13 L-15 P&M075 P&M063

4000.00 24000.00 600.00 1200.00 1473.43 2520.00 #VALUE! #VALUE! #VALUE! say #VALUE!

12.13 Sectio n 1200

Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter. Taking output = 1 m Diameter of well - 7 m. A (i) Sandy Soil Depth below bed level upto 3.0 M Rate of sinking = 0.30 m per hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 3.25 4000.00 13000.00 1300.00 1511.50 1511.50 18138.00 36276.00 say day day day hour 0.18 1.50 3.00 4.50 350.00 250.00 180.00 ### 63.00 375.00 540.00 L-12 L-15 L-14 P&M075 P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.15 1.25 2.50 350.00 250.00 180.00 52.50 312.50 450.00 L-12 L-15 L-14

12.13 A

(ii)

Beyond 3m upto 10m depth Rate of sinking = 0.22 m per hour. a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Page 34 of 363

4000.00 18000.00 1800.00 2077.80

Ref. to Sr No MoRT H Spec.

Description d) Contractor's profit @ 10% on (a+b+c) Rate per metre = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 2285.58 25141.38 ###

say 12.13 A (iii) a Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

26398.00 27718.00 29104.00 30559.00 32087.00 33691.00 35376.00 37145.00 39002.00 40952.00 ### ###

0.17

15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

12.13 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour). 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

44023.00 47325.00 50874.00 54690.00 58792.00 63201.00 67941.00 73037.00 78515.00 84404.00

Including 20% for Kentledge 52828.00 56790.00 61049.00 65628.00 70550.00 75841.00 81529.00 87644.00 94218.00 101285.00

### 747362.00 ### 74736.00

12.13 A

(v) a b

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

92844.00

Including 20% for Kentledge 111413.00

### 122554.00 ### 134809.00 ### 148290.00 ### 163120.00 ### 179431.00 ### 197375.00 ### 217112.00 ### 238824.00 ### 262706.00 ### ### ### ###

12.13

Clayey Soil ( 7m dia. Well ) Unit = Running Meter. Taking output = 1 cum

(I)

Depth below bed level upto 3.0 M Rate of sinking = 0.22 m per hour. a) Labour

Page 35 of 363

Ref. to Sr No MoRT H Spec.

Description Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables d) of (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on e) (a+b+c) Rate per metre = (a+b+c+d)

Unit day day day hour

Quantity 0.18 1.50 3.00 4.50

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 63.00 L-12 250.00 180.00 375.00 540.00 L-15 L-14 P&M075

4000.00 18000.00 1800.00 2077.80 2285.58 25141.38 say ###

12.13 B

(ii)

Beyond 3m upto 10m depth Rate of sinking = 0.17 m per hour. a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour hour 6.00 3.25 4000.00 24000.00 600.00 2400.00 2640.00 3035.10 3338.61 36724.71 say ### P&M075 P&M063 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.26 2.00 4.00 350.00 250.00 180.00 91.00 500.00 720.00 L-12 L-15 L-14

12.13 B

(iii) a b

Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required.

11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre 12.13 B (iv) a b c Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m Page 36 of 363

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

38561.00 40489.00 42513.00 44639.00 46871.00 49215.00 51676.00 54260.00 56973.00 59822.00

Including for dewatering @ 5% of cost, if 40489.00 42513.00 44639.00 46871.00 49215.00 51676.00 54260.00 56973.00 59822.00 62813.00

### 509271.00 ### 50927.00

7.5% 7.5% 7.5% 7.5% 7.5%

64309.00 69132.00 74317.00 79891.00 85883.00

Including Including 25% for 5% for Kentledge dewaterin g, if required 80386.00 84405.00 86415.00 90736.00 92896.00 97541.00 99864.00 107354.00 ### ###

Ref. to Sr No MoRT H Spec.

Description 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit 7.5% 7.5% 7.5% 7.5% 7.5%

Quantity 92324.00 99248.00

Remark Cost Rs s/ Input ref. 115405.00 ### Rate Rs 124060.00 ### ### ### ### ### ###

### 133365.00 ### 143368.00 ### 154120.00 ### ### ### ###

12.13 B

(v) a b c

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 162751.00 required ### ### 179027.00 ### 196930.00 ### 216623.00 ### 238285.00 ### 262114.00 ### 288325.00 ### 317158.00 ### 348874.00 ### 383761.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

12.13

Soft Rock ( 7m dia well ) Unit = Running Meter. Taking output = 1 m Depth in soft rock strata upto 3m Rate of sinking = 0.22 m per hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ of 5 per cent of Add for (a+b), if required c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) say hour hour 4.50 3.75 4000.00 18000.00 600.00 2250.00 2025.00 1175.78 2671.63 2938.79 32326.69 ### P&M075 P&M063 day day day day 0.58 4.00 10.00 0.75 350.00 250.00 180.00 350.00 203.00 1000.00 1800.00 262.50 L-12 L-15 L-14 L-07

12.13

Hard Rock ( 7m dia well ) Unit = Running Meter Taking output = 1 m Depth in Hard rock strata up to 3 m Rate of sinking = 0.17 m per hour. a) Material Gelatine 80 per cent Electric Detonators b) Labour Mate day 1.60 350.00 560.00 Kg each 7.00 30.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12

Page 37 of 363

Ref. to Sr No MoRT H Spec.

Description Driller Blaster Mazdoor Mazdoor (Skilled) Diver c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling. @ 5 per cent of cost of Dewatering (b+c), if required. Consumables in sinking @ 10 per cent d) of cost of (b). charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per metre = (a+b+c+d+e)

Unit day day day day day hour hour

Quantity 2.00 0.25 18.00 4.00 0.50 6.00 2.00

Rate Rs

Remark Cost Rs s/ Input ref. 250.00 500.00 L-06 250.00 180.00 250.00 350.00 62.50 3240.00 1000.00 175.00 L-03 L-13 L-15 L-07 P&M075 P&M063

4000.00 24000.00 600.00 1200.00 1536.88 2673.69 #VALUE! #VALUE! #VALUE! say #VALUE!

12.14 Sectio n 1200

Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter. Taking output = 1 m Diameter of well - 8 m. A (i) Sandy Soil Depth below bed level upto 3.0 M Rate of sinking @ 0.25 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 4.00 4000.00 16000.00 1600.00 1857.80 2043.58 22479.38 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.18 1.50 3.00 350.00 250.00 180.00 63.00 375.00 540.00 L-12 L-15 L-14

12.14 A

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.20 m/hour a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour 5.00 4000.00 20000.00 2000.00 2315.50 2547.05 28017.55 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.25 1.75 3.50 350.00 250.00 180.00 87.50 437.50 630.00 L-12 L-15 L-14

12.14 A

(iii) a

Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m

5% 5%

29418.00 30889.00

Page 38 of 363

Ref. to Sr No MoRT H Spec.

Description 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

Unit 5% 5% 5% 5% 5% 5% 5% 5%

Quantity 32433.00 34055.00 35758.00 37546.00 39423.00 41394.00 43464.00 45637.00 ### ###

Rate Rs

Remark Cost Rs s/ Input ref.

12.14 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour. 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

49060.00 52740.00 56696.00 60948.00 65519.00 70433.00 75715.00 81394.00 87499.00 94061.00

Including 20% for Kentledge 58872.00 63288.00 68035.00 73138.00 78623.00 84520.00 90858.00 97673.00 104999.00 112873.00

### 832879.00 ### 83288.00

12.14 A

(v) a b

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including 20% for Kentledge ### 124160.00 ### 136577.00 ### 150234.00 ### 165258.00 ### 181784.00 ### 199963.00 ### 219960.00 ### 241956.00 ### 266152.00 ### 292766.00 ### 292766.00 ### 29277.00

12.14

Clayey Soil ( 8m dia. Well ) Unit = Running Meter. Taking output = 1 meter

(i)

Depth from bed level upto 3.0 M Rate of sinking @ 0.18 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery 5.50 4000.00 22000.00 2200.00 2540.70 P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Page 39 of 363 day day day 0.22 2.00 3.50 350.00 250.00 180.00 77.00 500.00 630.00 L-12 L-15 L-14

Ref. to Sr No MoRT H Spec.

Description d) Contractor's profit @ 10% on (a+b+c) Rate per metre = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 2794.77 30742.47 ###

say 12.14 B (ii) Beyond 3m upto 10m depth Rate of sinking @ 0.17 m/hour a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour hour 6.00 3.50 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) say 12.14 B (iii) a b Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required. day day day 0.32 2.50 4.50 350.00 250.00 180.00

112.00 625.00 810.00

L-12 L-15 L-14 P&M075 P&M063

4000.00 24000.00 600.00 2100.00 2610.00 3025.70 3328.27 36610.97 ###

11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre 12.14 B (iv) a b c Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 12.14 B (v) Beyond 30m upto 40 m Page 40 of 363

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

38442.00 40364.00 42382.00 44501.00 46726.00 49062.00 51515.00 54091.00 56796.00 59636.00

Including for dewatering @ 5% of cost, if 40364.00 42382.00 44501.00 46726.00 49062.00 51515.00 54091.00 56796.00 59636.00 62618.00

### 507691.00 ### 50769.00

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

64109.00 68917.00 74086.00 79642.00 85615.00 92036.00 98939.00

Including Including 25% for 5% for Kentledge dewaterin g, if required 80136.00 84143.00 86146.00 90453.00 92608.00 97238.00 99553.00 107019.00 115045.00 123674.00 ### ### ### ### ### ### ### ### ###

### 132949.00 ### 142920.00 ### 153639.00 ### ### ### ###

Ref. to Sr No MoRT H Spec.

Description a b c Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 162242.00 required ### ### 178466.00 ### 196313.00 ### 215944.00 ### 237538.00 ### 261292.00 ### 287420.00 ### 316163.00 ### 347779.00 ### 382558.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

12.14

Soft Rock ( 8m dia well ) Unit = Running Meter. Taking output = 1 m Depth in soft rock strata upto 3m Rate of sinking @ 0.20 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ of 5 per cent of Add for (a+b), if required c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) say hour hour 5.00 3.75 4000.00 20000.00 600.00 2250.00 2225.00 1411.15 2963.42 3259.76 35857.32 ### P&M075 P&M063 day day day day 0.68 4.00 12.00 1.00 350.00 250.00 180.00 350.00 238.00 1000.00 2160.00 350.00 L-12 L-15 L-14 L-07

12.14

Hard Rock ( 8m dia well ) Unit = Running Meter Taking output = 1 m Depth in hard rock strata upto 3 m Rate of sinking @ 0.17 m/hour a) Material Gelatine 80 per cent Electric Detonators b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling. Page 41 of 363 hour hour 6.00 2.00 4000.00 24000.00 600.00 1200.00 P&M075 P&M063 day day day day day 1.09 2.00 0.25 20.00 4.00 350.00 250.00 250.00 180.00 250.00 381.50 500.00 62.50 3600.00 1000.00 Kg each 8.00 32.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12 L-06 L-03 L-13 L-15

Ref. to Sr No MoRT H Spec.

Description Dewatering @ 5 per cent of cost of (b+c), if required. Consumables in sinking @ 10 per cent d) of cost of (b). charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per metre = (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 1537.20 554.40 #VALUE! #VALUE! #VALUE!

say #VALUE! 12.15 Sectio n 1200 Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter. Taking output = 1 m Diameter of well - 9 m. A (i) Sandy Soil Depth below bed level upto 3.0 M Rate of sinking @ 0.25 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 4.00 4000.00 16000.00 1600.00 1862.65 2048.92 22538.07 say 12.15 A (ii) Beyond 3m upto 10m depth Rate of sinking @ 0.18 m/hour a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour 5.50 4000.00 22000.00 2200.00 2545.20 2799.72 30796.92 say 12.15 A (iii) a Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre Page 42 of 363 ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.27 1.75 4.00 350.00 250.00 180.00 94.50 437.50 720.00 L-12 L-15 L-14 ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.19 1.50 3.25 350.00 250.00 180.00 66.50 375.00 585.00 L-12 L-15 L-14

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

32337.00 33954.00 35652.00 37435.00 39307.00 41272.00 43336.00 45503.00 47778.00 50167.00 ### ###

Ref. to Sr No MoRT H 12.15 Spec. A

Description (iv) a b Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour. 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

53929.53 57974.00 62322.00 66996.00 72021.00 77423.00 83230.00 89472.00 96182.00

Including 20% for Kentledge 64715.00 69569.00 74786.00 80395.00 86425.00 92908.00 99876.00 107366.00 115418.00

### 124075.00 ### 915533.00 ### 91553.00

12.15 A

(v) a b

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including 20% for Kentledge ### 136483.00 ### 150131.00 ### 165144.00 ### 181658.00 ### 199824.00 ### 219806.00 ### 241787.00 ### 265966.00 ### 292562.00 ### 321818.00 ### ### ### ###

12.15

Clayey Soil ( 9m dia. Well ) Unit = Running Meter. Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M Rate of sinking 0.17 m / hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 5.75 4000.00 23000.00 2300.00 2662.15 2928.37 32212.02 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.24 2.25 3.75 350.00 250.00 180.00 84.00 562.50 675.00 L-12 L-15 L-14

12.15 B

(ii)

Beyond 3m upto 10m depth Rate of sinking 0.15 m / hour a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery day day day 0.34 2.50 5.00 350.00 250.00 180.00 119.00 625.00 900.00 L-12 L-15 L-14

Page 43 of 363

Ref. to Sr No MoRT H Spec.

Description Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d)

Unit hour hour

Quantity 6.50 3.75

Rate Rs

Remark Cost Rs s/ Input ref. 4000.00 26000.00 P&M075 600.00 2250.00 P&M063 2825.00 3271.90 3599.09 39589.99 say ###

12.15 B

(iii) a b

Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required.

11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre 12.15 B (iv) a b c Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 12.15 B (v) a b c Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m Page 44 of 363

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

41570.00 43649.00 45831.00 48123.00 50529.00 53055.00 55708.00 58493.00 61418.00 64489.00

Including for dewatering @ 5% of cost, if 43649.00 45831.00 48123.00 50529.00 53055.00 55708.00 58493.00 61418.00 64489.00 67713.00

### 549008.00 ### 54901.00

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

69326.00 74525.00 80114.00 86123.00 92582.00 99526.00

Including Including 25% for 5% for Kentledge dewaterin g, if required 86658.00 90991.00 93156.00 97814.00 100143.00 107654.00 115728.00 124408.00 ### ### ### ### ### ### ### ### ### ###

### 133738.00 ### 143768.00 ### 154550.00 ### 166141.00 ### ### ### ###

10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 175445.00 required ### ### 192989.00 ### 212287.00 ### 233516.00 ### ### ###

Ref. to Sr No MoRT H Spec.

Description 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit 10% 10% 10% 10% 10% 10%

Quantity

Remark Cost Rs s/ Input ref. ### 256868.00 ### Rate Rs ### 282556.00 ### 310811.00 ### 341892.00 ### 376081.00 ### 413689.00 ### ### ### ### ### ### ### ### ### ### ###

12.15

Soft Rock ( 9m dia well ) Unit = Running Meter. Taking output = 1 m Depth in soft rock strata up to 3m Rate of sinking 0.15 m / hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ of 5 per cent of Add for (a+b), if required c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) say hour hour 6.50 4.00 4000.00 26000.00 600.00 2400.00 2840.00 3544.60 3899.06 4288.97 47178.63 ### P&M075 P&M063 day day day day 0.76 4.00 14.00 1.20 350.00 250.00 180.00 350.00 266.00 1000.00 2520.00 420.00 L-12 L-15 L-14 L-07

12.15

Hard Rock ( 9m dia well ) Unit = Running Meter Taking output = 1 m Depth in hard rock strata upto 3 m Rate of sinking 0.15 m / hour a) Material Gelatine 80 per cent Electric Detonators b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) Diver c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer for drilling. @ 5 per cent of cost of Dewatering (b+c), if required. Consumables in sinking @ 10 per cent d) of cost of (b). charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per metre = (a+b+c+d+e) hour hour 7.00 2.50 4000.00 28000.00 600.00 1500.00 1789.10 628.20 #VALUE! #VALUE! #VALUE! say #VALUE! P&M075 P&M063 day day day day day day 1.17 2.00 0.25 22.00 4.00 1.00 350.00 250.00 250.00 180.00 250.00 350.00 409.50 500.00 62.50 3960.00 1000.00 350.00 Kg each 10.00 40.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12 L-06 L-03 L-13 L-15 L-07

Page 45 of 363

Ref. to Sr No MoRT H 12.16 Spec. 1200

Description Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter Taking output = 1 m Diameter of well - 10 m. A (i) Sandy Soil Depth below bed level upto 3.0 M Rate of sinking 0.20 m / hour a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.20 1.50 3.50 5.00

350.00 250.00 180.00

70.00 375.00 630.00

L-12 L-15 L-14 P&M075

4000.00 20000.00 2000.00 2307.50 2538.25 27920.75 say ###

12.16 A

(ii)

Beyond 3m upto 10m depth Rate of sinking 0.17 m / hour a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour 5.75 4000.00 23000.00 2300.00 2667.35 2934.09 32274.94 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.31 2.00 4.25 350.00 250.00 180.00 108.50 500.00 765.00 L-12 L-15 L-14

12.16 A

(iii) a

Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

33889.00 35583.00 37362.00 39230.00 41192.00 43252.00 45415.00 47686.00 50070.00 52574.00 ### ###

12.16 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour.

7.5%

56517.00

Including 20% for Kentledge 67820.00

Page 46 of 363

Ref. to Sr No MoRT H Spec.

Description 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

Unit 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

Quantity 60756.00 65313.00 70211.00 75477.00 81138.00 87223.00 93765.00

Rate Rs 72907.00 78376.00 84253.00 90572.00 97366.00 104668.00 112518.00

Remark Cost Rs s/ Input ref.

### 120956.00 ### 130028.00 ### 959464.00 ### 95946.00

12.16 A

(v) a b

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including 20% for Kentledge ### 143032.00 ### 157334.00 ### 173068.00 ### 190374.00 ### 209412.00 ### 230353.00 ### 253388.00 ### 278728.00 ### 306600.00 ### 337260.00 ### ### ### ###

12.16

Clayey Soil (10m dia. Well ) Unit = Running Meter Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M Rate of sinking 0.18m/hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) b) Machinery hour 6.00 4000.00 24000.00 2400.00 2810.25 3091.28 34004.03 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.25 2.50 5.50 350.00 250.00 180.00 87.50 625.00 990.00 L-12 L-15 L-14

12.16 B

(ii)

Beyond 3m upto 10m depth Rate of sinking 0.15m/hour. a) Labour Mate Sinker Sinking helper ( semi-skilled ) b) Machinery hour hour 6.00 4.00 4000.00 24000.00 600.00 2400.00 2640.00 3092.00 P&M075 P&M063 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Page 47 of 363 day day day 0.40 3.00 5.50 350.00 250.00 180.00 140.00 750.00 990.00 L-12 L-15 L-14

Ref. to Sr No MoRT H Spec.

Description d) Contractor's profit @ 10% on (a+b+c) Rate per metre = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 3401.20 37413.20 ###

say 12.16 B (iii) a b Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required.

11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre 12.16 B (iv) a b c Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 12.16 B (v) a b c Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m Page 48 of 363

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

39284.00 41248.00 43310.00 45476.00 47750.00 50138.00 52645.00 55277.00 58041.00 60943.00

Including for dewatering @ 5% of cost, if 41248.00 43310.00 45476.00 47750.00 50138.00 52645.00 55277.00 58041.00 60943.00 63990.00

### 518818.00 ### 51882.00

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

65514.00 70428.00 75710.00 81388.00 87492.00 94054.00

Including Including 25% for 5% for Kentledge dewaterin g, if required 81893.00 85988.00 88035.00 92437.00 94638.00 99370.00 101735.00 109365.00 117568.00 ### ### ### ### ### ### ### ### ###

### 126385.00 ### 135864.00 ### 146054.00 ### 157008.00 ### ### ### ###

10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 165800.00 required ### ### 182381.00 ### 200618.00 ### 220680.00 ### 242748.00 ### 267023.00 ### 293725.00 ### 323098.00 ### 355408.00 ### ### ### ### ### ### ### ###

Ref. to Sr No MoRT H Spec.

Description 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit 10%

Quantity

Remark Cost Rs s/ Input ref. ### 390948.00 ### Rate Rs ### ### ### ### ### ###

12.16

Soft Rock (10m dia well ) Unit = Running Meter. Taking output = 1 m Depth in soft rock strata upto 3m Rate of sinking 0.14m/hour. a) Labour Mate Sinker ( skilled ) Sinking helper ( semi-skilled ) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ 5 per cent of Add for c) cost, if required Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) say hour hour 7.00 4.25 4000.00 28000.00 600.00 2550.00 3055.00 1680.25 3995.63 4395.19 48347.06 ### P&M075 P&M063 day day day day 0.86 4.00 16.00 1.40 350.00 250.00 180.00 350.00 301.00 1000.00 2880.00 490.00 L-12 L-15 L-14 L-07

12.16

Hard Rock (10m dia well ) Unit = Running Meter. Taking output = 1 m Depth in hard rock strata upto 3 m Rate of sinking 0.12 m/ hour. a) Material Gelatine 80 per cent Electric Detonators b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill Dewatering @ 5 per cent of cost (c), if required. Consumables in sinking @ 10 per cent of cost of (b+c). d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per metre = (a+b+c+d+e) hour hour 8.50 3.00 4000.00 34000.00 600.00 1800.00 1790.00 4391.70 #VALUE! #VALUE! #VALUE! say #VALUE! P&M075 P&M063 day day day day day 1.27 2.00 0.25 24.00 4.00 350.00 250.00 250.00 180.00 250.00 444.50 500.00 62.50 4320.00 1000.00 Kg each. 11.00 44.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12 L-06 L-03 L-13 L-15

12.17

1200

Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter Taking output = 0.50 m Diameter of well - 11 m. A Sandy Soil Page 49 of 363

Ref. to Sr No MoRT H Spec.

Description (i) Depth from bed level upto 3.0 M Rate of sinking @ 0.15 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper (semi-skilled) b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables d) of (b) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 0.5m = a+b+c+d Rate per metre = (a+b+c+d)/0.50

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day hour

0.21 1.50 3.30 6.00

350.00 250.00 180.00

73.50 375.00 594.00

L-12 L-15 L-14 P&M075

4000.00 24000.00 2400.00 2744.25 3018.68 33205.43 66410.85 say ###

12.17 A

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.13 m/hour a) Labour Mate Sinker Sinking helper (semi-skilled) b) Machinery hour 4.00 4000.00 16000.00 1600.00 1902.20 2092.42 23016.62 46033.24 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b+c) d) Contractor's profit @ 10% on (a+b+c+d) Cost for 0.5m = a+b+c+d Rate per metre = (a+b+c+d)/0.50 day day day 0.32 2.00 4.50 350.00 250.00 180.00 112.00 500.00 810.00 L-12 L-15 L-14

12.17 A

(iii) a

Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

48335.00 50752.00 53290.00 55955.00 58753.00 61691.00 64776.00 68015.00 71416.00 74987.00 ### ###

12.17 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour. 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

80611.00 86657.00 93156.00

Including 20% for Kentledge 96733.00 103988.00 111787.00

### 120172.00 ### 129185.00 ### 138874.00 ### 149290.00 ### 160487.00

Page 50 of 363

Ref. to Sr No MoRT H Spec.

Description 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

Unit 7.5% 7.5%

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

### 172523.00 ### 185462.00 ### ### ### ###

12.17 A

(v) a b

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including 20% for Kentledge ### 204008.00 ### 224410.00 ### 246851.00 ### 271536.00 ### 298690.00 ### 328559.00 ### 361415.00 ### 397556.00 ### 437312.00 ### 481044.00 ### ### ### ###

12.17

Clayey Soil (11 m dia. Well ) Unit = Running Meter Taking output = 0.50 meter

(i)

Depth from bed level upto 3.0 M Rate of sinking @ 0.10 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper (semi-skilled) b) Machinery hour 5.00 4000.00 20000.00 2000.00 2343.60 2577.96 28357.56 56715.12 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.5m = a+b+c+d Rate per metre = (a+b+c+d)/0.50 day day day 0.26 2.50 4.00 350.00 250.00 180.00 91.00 625.00 720.00 L-12 L-15 L-14

12.17 B

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.08 m/hour a) Labour Mate Sinker Sinking helper (semi-skilled) b) Machinery hour hour 6.00 4.25 4000.00 24000.00 600.00 2550.00 2655.00 3126.55 3439.21 37831.26 75662.51 say ### P&M075 P&M063 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.5m = a+b+c+d Rate per metre = (a+b+c+d)/0.50 day day day 0.43 3.50 5.75 350.00 250.00 180.00 150.50 875.00 1035.00 L-12 L-15 L-14

12.17 B

(iii) a

Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter Page 51 of 363

Ref. to Sr No MoRT H Spec.

Description b Add for dewatering @ 5 per cent of cost, if required.

Unit

Quantity

Rate Rs Including for dewatering @ 5% of cost, if 83418.00 87589.00 91968.00 96566.00 101394.00

Remark Cost Rs s/ Input ref.

11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre 12.17 B (iv) a b c Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 12.17 B (v) a b c Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 12.17 C Soft Rock (11m dia well ) Unit = Running Meter. Taking output = 0.50 m Page 52 of 363

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

79446.00 83418.00 87589.00 91968.00 96566.00

### 106464.00 ### 111787.00 ### 117376.00 ### 123245.00 ### 129407.00 ### ### ### ###

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

Including Including 25% for 5% for Kentledge dewaterin g, if ### 165610.00 required ### ### 178031.00 ### 191384.00 ### 205738.00 ### 221168.00 ### 237755.00 ### 255586.00 ### 274755.00 ### 295361.00 ### 317514.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 335294.00 required ### ### 368824.00 ### 405706.00 ### 446276.00 ### 490904.00 ### 539995.00 ### 593995.00 ### 653395.00 ### 718735.00 ### 790609.00 4453112 ### ### ### ### ### ### ### ### ### ### ### ###

5343733 5610920

Ref. to Sr No MoRT H Spec.

Description Depth in soft rock strata upto 3m Rate of sinking @ 0.06 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper (semi-skilled) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ 5 per cent of Add for c) cost, if required Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.5m = a+b+c+d Rate per metre = (a+b+c+d)/0.50

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day day hour hour

0.95 4.25 18.00 1.50 8.00 4.50

350.00 250.00 180.00 350.00

332.50 1062.50 3240.00 525.00

L-12 L-15 L-14 L-07 P&M075 P&M063

4000.00 32000.00 600.00 2700.00 3470.00 1908.50 4523.85 4976.24 54738.59 ### say ###

12.17

Hard Rock (11m dia well ) Unit = Running Meter. Taking output = 0.50 m Depth in hard rock upto 3 m Rate of sinking @ 0.05 m/hour a) Material Gelatine 80 per cent Electric Detonators b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill Dewatering @ 5 per cent of cost (c), if required. Consumables in sinking @ 10 per cent of cost of (b+c). d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 0.5m = a+b+c+d Rate per metre = (a+b+c+d)/0.50 hour hour 10.00 3.50 4000.00 40000.00 600.00 2100.00 2105.00 4881.50 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M075 P&M063 day day day day day 1.35 2.00 0.25 26.00 4.00 350.00 250.00 250.00 180.00 250.00 472.50 500.00 62.50 4680.00 1000.00 Kg each. 12.00 48.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12 L-06 L-03 L-13 L-15

12.18

1200

Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter Taking output = 0.25 m Diameter of well - 12 m. A (i) Sandy Soil I) Depth below bed level upto 3.0 M Rate of sinking @ 0.05 m/hour a) Labour Mate Page 53 of 363 day 0.22 350.00 77.00 L-12

Ref. to Sr No MoRT H Spec. b)

Description Sinker ( skilled ) Sinking helper (semi-skilled) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.25m = a+b+c+d Rate per metre = (a+b+c+d)/0.25

Unit day day hour

Quantity 1.75 4.00 6.00

Rate Rs

Remark Cost Rs s/ Input ref. 250.00 437.50 L-15 180.00 720.00 L-14 P&M075

4000.00 24000.00 2400.00 2763.45 3039.80 33437.75 ### say ###

12.18 A

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.038 m/hour a) Labour Mate Sinker Sinking helper (semi-skilled) b) Machinery hour 6.50 4000.00 26000.00 2600.00 3020.95 3323.05 36553.50 ### say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.25m = a+b+c+d Rate per metre = (a+b+c+d)/0.25 day day day 0.37 2.50 4.75 350.00 250.00 180.00 129.50 625.00 855.00 L-12 L-15 L-14

12.18 A

(iii) a

Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

### ### ### ### ### ### ### ### ### ### ### ###

12.18 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour. 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

Including 20% for Kentledge ### 307236.00 ### 330278.00 ### 355049.00 ### 381678.00 ### 410304.00 ### 441077.00 ### 474157.00 ### 509719.00 ### 547948.00 ### 589044.00 ### ### ### ###

Page 54 of 363

Ref. to Sr No MoRT H 12.18 Spec. A

Description (v) a b Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including 20% for Kentledge ### 647948.00 ### 712744.00 ### 784018.00 ### 862420.00 ### 948661.00 ### ### ### ### ### 8605526 ### ### ### ### ### ### 10326631 ###

12.18

Clayey Soil (12 m dia. Well ) Unit = Running Meter. Taking output = 0.25 meter.

(i)

Depth below bed level upto 3.0 M Rate of sinking @ 0.04 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper (semi-skilled) b) Machinery hour 6.25 4000.00 25000.00 2500.00 2916.50 3208.15 35289.65 ### say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.25m = a+b+c+d Rate per metre = (a+b+c+d)/0.25 day day day 0.30 3.00 4.50 350.00 250.00 180.00 105.00 750.00 810.00 L-12 L-15 L-14

12.18 B

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.03 m/hour a) Labour Mate Sinker Sinking helper (semi-skilled) b) Machinery hour hour 8.33 4.50 4000.00 33320.00 600.00 2700.00 3602.00 4180.75 4598.83 50587.08 ### say ### P&M075 P&M063 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.25m = a+b+c+d Rate per metre = (a+b+c+d)/0.25 day day day 0.48 3.75 6.00 350.00 250.00 180.00 168.00 937.50 1080.00 L-12 L-15 L-14

12.18 B

(iii) a b

Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required.

Including for dewatering @ 5% of cost, if

Page 55 of 363

Ref. to Sr No MoRT H Spec.

Description 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

Unit 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

### 223089.00 ### 234243.00 ### 245955.00 ### 258253.00 ### 271166.00 ### 284724.00 ### 298960.00 ### 313908.00 ### 329603.00 ### 346083.00 ### ### ### ###

12.18 B

(iv) a b c

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

Including Including 25% for 5% for Kentledge dewaterin g, if ### 442904.00 required ### ### 476121.00 ### 511830.00 ### 550218.00 ### 591484.00 ### 635845.00 ### 683534.00 ### 734799.00 ### 789909.00 ### 849153.00 5012636 ### ### ### ### ### ### ### ### ### ### ### ###

6265797 6579087

12.18 B

(v) a b c

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if required ### 896705.00 ### ### 986375.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 14291173 ### ### ### ### ### ### ### ### ### ### ### ###

12.18

Soft Rock (12m dia well ) Unit = Running Meter Taking output = 0.25 m Depth in soft rock strata upto 3m Rate of sinking @ 0.025 m/hour a) Labour Page 56 of 363

Ref. to Sr No MoRT H Spec.

Description Mate Sinker ( skilled ) Sinking helper (semi-skilled) Diver b) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent of (b) dewatering @ 5 per cent, if Add for c) required Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 0.25m = a+b+c+d Rate per metre = (a+b+c+d)/0.25

Unit day day day day hour hour

Quantity 1.06 4.50 20.00 1.75 10.00 4.75

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 371.00 L-12 250.00 180.00 350.00 1125.00 3600.00 612.50 L-15 L-14 L-07 P&M075 P&M063

4000.00 40000.00 600.00 2850.00 4285.00 2356.75 5520.03 6072.03 66792.30 ### say ###

12.18

Hard Rock (12m dia well ) Unit = Running Meter Taking output = 0.25 m

(i)

Depth in hard rock strata upto 3 m Rate of sinking @ 0.020 m/hour a) Material Gelatine80 per cent Electric detonator b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill Dewatering @ 5 per cent, if required. Consumables in sinking @ 10 per cent d) of (c). Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 0.25m = a+b+c+d+e Rate per metre = (a+b+c+d+e)/0.25 hour hour 12.50 4.00 4000.00 50000.00 600.00 2400.00 2620.00 5502.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M075 P&M063 day day day day day 1.44 2.00 0.25 28.00 4.50 350.00 250.00 250.00 180.00 250.00 504.00 500.00 62.50 5040.00 1125.00 Kg each. 14.00 56.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12 L-06 L-03 L-13 L-15

12.19

1200

Sinking of Twin D Type well (other than pneumatic method of sinking) through all types of strata namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of sinking is Unit = Running Meter Taking output = 1 m Dimensions of well. Overall length = 12 m Overall width = 6 m A (i) Sandy Soil Depth from bed level upto 3.0 M Rate of sinking @ 0.18 m/hour a) Labour Mate Sinker ( skilled ) Page 57 of 363 day day 0.20 1.25 350.00 250.00 70.00 312.50 L-12 L-15

Ref. to Sr No MoRT H Spec. b)

Description Sinking helper (semi-skilled) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d)

Unit day hour

Quantity 3.75 5.50

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 675.00 L-14 P&M075

4000.00 22000.00 2200.00 2525.75 2778.33 30561.58 say ###

12.19 A

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.17 m/hour a) Labour Mate Sinker Sinking helper (semi-skilled) b) Machinery hour 5.88 4000.00 23520.00 2352.00 2707.20 2977.92 32757.12 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @10 per cent of Consumables c) (b) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.30 1.50 4.00 350.00 250.00 180.00 105.00 375.00 720.00 L-12 L-15 L-14

12.19 A

(iii) a

Beyond 10m upto 20m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter 11th m 12th m 13th m 14th m 15th m 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

5% 5% 5% 5% 5% 5% 5% 5% 5% 5%

34395.00 36115.00 37921.00 39817.00 41808.00 43898.00 46093.00 48398.00 50818.00 53359.00 ### ###

12.19 A

(iv) a b

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter of cost for Kentledge Add 20 per cent including supports, loading arrangement and 21st m Labour. 22nd m 23rd m 24th m 25th m 26th m 27th m 28th m 29th m 30th m Total Cost from 20m upto 30m Avg Rate per metre

7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5%

57361.00 61663.00 66288.00 71260.00 76605.00 82350.00 88526.00 95165.00

Including 20% for Kentledge 68833.00 73996.00 79546.00 85512.00 91926.00 98820.00 106231.00 114198.00

### 122762.00 ### 131970.00 ### 973794.00 ### 97379.00

12.19 A

(v) a

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter Page 58 of 363

Ref. to Sr No MoRT H Spec.

Description b Add 20 per cent of cost for Kentledge including supports, loading arrangement, and 31st m etc. Labour 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including 20% for Kentledge ### 145168.00 ### 159684.00 ### 175652.00 ### 193218.00 ### 212540.00 ### 233795.00 ### 257174.00 ### 282892.00 ### 311180.00 ### 342299.00 ### ### ### ###

12.19

Clayey Soil (Twin D Type Well ) Unit = Running Meter Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M Rate of sinking @ 0.16 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper (semi-skilled) b) Machinery hour 6.25 4000.00 25000.00 2500.00 2893.60 3182.96 35012.56 say ### P&M075 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. in sinking @ 10 per cent Consumables (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.26 2.50 4.00 350.00 250.00 180.00 91.00 625.00 720.00 L-12 L-15 L-14

12.19 B

(ii)

Beyond 3m upto 10m depth Rate of sinking @ 0.15 m/hour a) Labour Mate Sinker Sinking helper (semi-skilled) b) Machinery hour hour 6.67 4.50 4000.00 26680.00 600.00 2700.00 2938.00 3436.80 3780.48 41585.28 say ### P&M075 P&M063 Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic chisel attachment for cutting hard clay. Consumables in sinking @ 10 per cent (b) c) of Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d) day day day 0.45 3.25 6.00 350.00 250.00 180.00 157.50 812.50 1080.00 L-12 L-15 L-14

12.19 B

(iii) a b

Beyond 10 m upto 20 m Add 5 per cent for every additional meter depth of sinking over the rate of sinking for the for dewatering Addprevious meter @ 5 per cent of cost, if required.

11th m 12th m 13th m 14th m 15th m Page 59 of 363

5% 5% 5% 5% 5%

43665.00 45848.00 48140.00 50547.00 53074.00

Including for dewatering @ 5% of cost, if 45848.00 48140.00 50547.00 53074.00 55728.00

Ref. to Sr No MoRT H Spec.

Description 16th m 17th m 18th m 19th m 20th m Total Cost from 10m upto 20m Avg Rate per metre

Unit 5% 5% 5% 5% 5%

Quantity 55728.00 58514.00 61440.00 64512.00 67738.00

Rate Rs 58514.00 61440.00 64512.00 67738.00 71125.00

Remark Cost Rs s/ Input ref.

### 576666.00 ### 57667.00

12.19 B

(iv) a b c

Beyond 20m upto 30 m Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering on Add 5 per cent of the cost, if required Add 25 per cent of cost for Kentledge including supports, loading arrangement and Labour ). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 7.5% 72818.00 78279.00 84150.00 90461.00 97246.00

Including Including 25% for 5% for Kentledge dewaterin g, if required 91023.00 95574.00 97849.00 105188.00 113076.00 121558.00 ### ### ### ### ### ### ### ### ### ### ###

### 130674.00 ### 140474.00 ### 151009.00 ### 162335.00 ### 174510.00 ### ### ### ###

12.19 B

(v) a b c

Beyond 30m upto 40 m Add 10 per cent for every additional meter depth of sinking over the rate of sinking for the previous meter cost for dewatering, if Add 5 per cent of required Add 20 per cent of cost for Kentledge including supports, loading arrangement and Labour). 31st m 32nd 33rd m 34th m 35th m 36th m 37th m 38th m 39th m 40th m Total Cost from 30m upto 40m Avg Rate per metre 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%

Including Including 20% for 5% for Kentledge dewaterin g, if ### 184283.00 required ### ### 202711.00 ### 222983.00 ### 245281.00 ### 269809.00 ### 296790.00 ### 326470.00 ### 359117.00 ### 395028.00 ### 434531.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

12.19

Soft Rock (Twin D Type Well ) Unit = Running Meter Taking output = 1 m Depth in soft rock strata upto 3m Rate of sinking @ 0.12 m/hour a) Labour Mate Sinker ( skilled ) Sinking helper (semi-skilled) Diver b) Machinery Page 60 of 363 day day day day 0.86 4.50 15.00 1.50 350.00 250.00 180.00 350.00 301.00 1125.00 2700.00 525.00 L-12 L-15 L-14 L-07

Ref. to Sr No MoRT H Spec.

Description Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Air compressor with pneumatic breakers Consumables in sinking @ 10 per cent of (b) dewatering @ 5 per cent, if Add for c) required Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per metre = (a+b+c+d)

Unit hour hour

Quantity 8.33 6.00

Rate Rs

Remark Cost Rs s/ Input ref. 4000.00 33320.00 P&M075 600.00 3600.00 P&M063 3692.00 2030.60 4729.36 5202.30 57225.26 say ###

12.19

Hard Rock (Twin D Type Well ) Unit = Running Meter Taking output = 1 m Depth in hard rock strata upto 3 m Rate of sinking @ 0.10 m/hour a) Material Geletine80 per cent Electric detonators b) Labour Mate Driller Blaster Mazdoor Mazdoor (Skilled) c) Machinery Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories. Hire & running charges of compressor with pneumatic breaker/Jack hammer or drill Dewatering @ 5 per cent of cost of (b+c), if required. Consumables in sinking @ 10 per cent d) of (b). Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per metre = (a+b+c+d+e) hour hour 10.00 3.00 4000.00 40000.00 600.00 1800.00 2419.70 4421.97 #VALUE! #VALUE! #VALUE! say #VALUE! P&M075 P&M063 day day day day day 1.34 2.00 0.25 25.00 4.25 350.00 250.00 250.00 180.00 250.00 469.00 500.00 62.50 4500.00 1062.50 Kg each. 10.00 40.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 L-12 L-06 L-03 L-13 L-15

12.20

1200

Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent and trained personnel and comprising of compression and decompression chambers, reducers, two air locks separately for men and plant & materials, arrangement for supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plateforms with railing, arrangement for compression and decompression, electric lighting of 50 V maximum, proper rooms for rest Unit - 1 cum Taking output = 5 cum a) Material M35 grade RCC corbel provided for supporting of equipment (Dimensions as per ground conditions). Rate may be adopted vide Item 12.8 (H) corbel HYSD bar reinforcement in Blasting material Gelatine 80 per cent Electric detonators Kg each 1.50 6.00 input #VALUE! M-104 #VALUE! #VALUE! M094/100 Cum 8.00 #VALUE! #VALUE! Item 12.8 (H)

tonne

0.48

input #VALUE! M-082

Page 61 of 363

Ref. to Sr No MoRT H Spec.

Description b) Labour Medical Officer Para medical personnel Mate Driller Blaster Mazdoor (for cutting, blasting, cleaning, removal of Material etc.) Mazdoor (Skilled) (for fixation and removal of adopter for air lock, carrying out mechanical and electrical operations and repairs and other skilled jobs.) Diver c) Machinery (i) Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. Induction and deinduction Erection at site and commissioning Usage of plant and equipment for pneumatic method of well sinking Air compressor 250 cfm, 2 nos. Hire and running charges of crane of 15 tonne capacity Motorised barge of 20 tonne capacity Boat to carry atleast 20 persons Electric generating set 33 KVA Tipper 10 tonne capacity d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 5 cum = a+b+c+d+e (see notes below) Rate per cum = (a+b+c+d+e)/5 Note 1.The cost of induction, deinduction and erection of equipment shall be divided by the total quantity of pneumatic sinking for all the wells of a particular bridge to arrive at the perpneumaticon account of this item. 2.Cost of cum rate sinking per cum of individual wells will be added to the cost indicated at (1) above to arrive at the final rate ofcost of induction and deinduction will 3.The pneumatic sinking per cum. depend upon the distance involved for shifting of equipment which may be assessed in individual cases as per actual ground conditions at sinking is of makingon a 4.In case pneumatic the time involved of dry bed, the provision of barge and boat may be omitted.and dimensions of the 5.The necessity corbel will be as per actual ground conditions. 6.Small equipments like welding sets, pumps, vibrators, pneumatic tools, portable lamps, fire extinguishers, hose pipes etc., have not been included as the same are covered of sinking shall be T&P under to 30 7.Depth as items of minor restricted

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. L-16 L-19 L-12 L-06 L-03 L-13 L-15

day day day day day day day

0.50 1.00 1.86 1.00 0.50 30.00 10.00

input #VALUE! input #VALUE! 350.00 250.00 250.00 180.00 250.00 651.00 250.00 125.00 5400.00 2500.00

day hour

4.00 6.00

350.00

1400.00

L-07 P&M082

input #VALUE!

L.S L.S hour hour hour hour hour hour hour 6.00 2x6 6.00 6.00 6.00 6.00 6.00

### ### 3228.00 19368.00 285.00 3420.00 P&M038 P&M001 P&M072 P&M066 P&M066 P&M079 P&M048

input #VALUE! input #VALUE! input #VALUE! 540.00 497.00 3240.00 2982.00 #VALUE! #VALUE!

12.21

1207

m. Sand Filling in Wells complete as per Drawing and Technical Specifications. Unit = 1 cum Taking output = 1 cum a) b) Material Sand (assuming 20 per cent voids ) Labour Mate Mazdoor c) Overhead charges @ 10% on (a+b) Page 62 of 363 day day 0.01 0.30 350.00 180.00 3.50 54.00 #VALUE! L-12 L-13 cum 1.20 input #VALUE! M-006

Ref. to Sr No MoRT H Spec.

Description d) Contractor's profit @ 10% on (a+b+c) Rate per cum (a+b+c+d) Providing Steel Liner 10 mm thick for Curbs and 6 mm thick for Steining of Wells including Fabricating and Setting out as per Detailed Drawing. Unit = 1 MT Taking output = 1 MT a) Material i) Structural steel including 5 per cent b) wastage Labour Mate Fitter Blacksmith Welder Mazdoor Electrodes, cutting gas and other consumables @ 5 per cent on cost a (a) above. c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate for per MT (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE! 12.22 1200 & 1900

tonne day day day day day

1.05 1.24 6.00 5.00 5.00 10.00

input #VALUE! M-179 350.00 250.00 180.00 250.00 180.00 434.00 1500.00 900.00 1250.00 1800.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-08 L-01 L-02 L-13

12.23

1100 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with Pile diameter-750 mm all lifts and lead Unit = meter Taking output = 15 m a) Materials PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV) Concrete to be cast with a tremie pipe 200mm dia. b) Machinery( for boring and construction ) Hire and running charges of hydraulic piling rig with power unit and complete accessories including shifting from one bore and running charges of light crane Hire location to another. for lowering reinforcement cage Hire and running charges of Bentonite pump Loader I cum bucket capacity. Tipper 5.5 cum capacity for disposal of muck from pile bore hole Bentonite c) Labour Mate/Supervisor Mazdoor d) Overhead charges @ 10% on (b+c) Contractor's profit @ 10% on e) (b+c+d) Cost for 15 m = a+b+c+d+d+e Rate per metre (a+b+c+d+e)/15 day day 0.14 3.50 350.00 180.00 49.00 630.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-13 hour 6.00 3878.00 23268.00 cum 6.62 #VALUE! #VALUE! Item 12.11 (C) iv

P&M036 P&M013

hour hour hour hour kg

0.50 6.00 0.30 0.30 300.00

230.00 Rate included in piling rig 1042.00 497.00

115.00

312.60 149.10

P&M017 P&M-

048 input #VALUE! M-071

12.24 1100, 1600 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all Pile diameter-1000 mm lifts and lead

Page 63 of 363

Ref. to Sr No MoRT H Spec.

Description Unit = meter Taking output = 10 m a) Materials PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C to(IV)cast with a tremie pipe Concrete ) be 200mm dia. b) Machinery( for boring and construction ) Hire and running charges of hydraulic piling rig with power unit and complete accessories including shifting from one bore and running charges of light crane Hire location to another. for lowering reinforcement cage Hire and running charges of Bentonite pump Loader I cum bucket capacity. Tipper 5.5 cum capacity for disposal of muck from pile bore hole Bentonite c) Labour Mate/Supervisor Mazdoor d) Overhead charges @ 10% on (b+c) Contractor's profit @ 10% on e) (b+c+d) Cost for 10 m = a+b+c+d+d+e Rate per metre (a+b+c+d+e)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum

7.85

#VALUE! #VALUE!

Item 12.11 (C) iv

hour

6.00

3878.00 23268.00

P&M036 P&M013

hour hour hour hour kg day day

0.50 6.00 0.40 0.40 350.00 0.16 4.00

230.00 Rate included in piling rig 1042.00 497.00

115.00

416.80 198.80

P&M017 P&M-

048 input #VALUE! M-071 350.00 180.00 56.00 720.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-13

12.25

1100 & 1700

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all Pile diameter-1200 mm lifts and lead Unit = meter Taking output = 9 m a) Materials PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV) Concrete to be cast with a tremie pipe 200mm dia. b) Machinery( for boring and construction ) Hire and running charges of hydraulic piling rig with power unit and complete accessories including shifting from one bore and running charges of light crane Hire location to another. for lowering reinforcement cage Hire and running charges of Bentonite pump Loader I cum bucket capacity. Tipper 5.5 cum capacity for disposal of muck from pile bore hole Bentonite c) Labour Mate/Supervisor Mazdoor d) Overhead charges @ 10% on (b+c) Contractor's profit @ 10% on e) (b+c+d) Cost for 9 m = a+b+c+d+d+e Rate per metre (a+b+c+d+e)/9 day day 0.18 4.50 350.00 180.00 63.00 810.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-13 hour 6.00 3878.00 23268.00 cum 10.17 #VALUE! #VALUE! Item 12.11 (C) iv

P&M036 P&M013

hour hour hour hour kg

0.50 6.00 0.50 0.50 385.00

230.00 Rate included in piling rig 1042.00 497.00

115.00

521.00 248.50

P&M017 P&M-

048 input #VALUE! M-071

Page 64 of 363

Ref. to Sr No MoRT H 12.26 Spec. 1100 & 1700

Description Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and & Technical Specification Pile diameter - 750 mm Unit = Running meter Taking output = 40 metre a) Materials PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV) b) Materials Pile shoes i) C.I. shoes for the pile ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m helmet and cushion block on iii) Steel top of casing head during driving c) Machinery Hire and running charges of piling rig Including double acting pile driving hammer complete with power unit and accessories.. Hiring and running charges for light crane 5 tonnes lifting capacity for lowering reinforcement and handling d) steel casing. Labour Mate/Supervisor Mazdoor e) Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 40 m = a+b+c+d+e Rate per metre (a+b+c+d+e)/40 Note 1.The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate case steel lining is included in the 2.In analysis. design for driven cast-in-situ pile and is planned to be retained, the same may be included in the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an additional cost @ 0.50 per cent of cost of concrete Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and & Technical Specification Pile diameter - 1000 mm Unit = Running meter Taking output = 30 metre a) Materials PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV) Pile shoes b) Materials i) C.I. shoes for the pile ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m helmet and cushion block on iii) Steel top of casing head during driving c) Machinery Hire and running charges of piling rig Including double acting pile driving hammer complete with power unit and accessories. Hiring and running charges for light crane 5 tonnes lifting capacity for lowering reinforcement and handling steel casing. Page 65 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum

17.66

#VALUE! #VALUE!

Item 12.11 (C) iv

Kg Kg Kg

160.00 70.00 50.00

input #VALUE! M-080 input #VALUE! M-124 input #VALUE! M-173

hour

6.00

input #VALUE!

P&M085 P&M070

hour

0.50

input #VALUE!

day day

0.12 3.00

350.00 180.00

42.00 540.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13

say #VALUE!

12.27

1100 & 1700

cum

23.55

#VALUE! #VALUE!

Item 12.11 (C) iv

Kg Kg Kg

160.00 70.00 50.00

input #VALUE! M-080 input #VALUE! M-124 input #VALUE! M-173

hour

6.00

input #VALUE!

P&M085 P&M070

hour

0.50

input #VALUE!

Ref. to Sr No MoRT H Spec.

Description Hire and running charges for light crane for lowering reinforcement cage. d) Labour Mate/Supervisor Mazdoor e) Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 30 m = a+b+c+d+e Rate per metre (a+b+c+d+e)/30 Note 1.The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate case steel lining is included in the 2.In analysis. design for driven cast-in-situ pile and is planned to be retained, the same may be included in the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an additional cost @ 0.50 per cent of cost of concrete Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and & Technical Specification Pile diameter - 1200 mm Unit = Running meter Taking output = 20 metre a) Materials PCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV) Pile shoes b) Materials i) C.I. shoes for the pile ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m helmet on top of casing head iii) Steel c) during driving Machinery Hire and running charges of piling rig Including double acting pile driving hammer complete with power unit and accessories. Hiring and running charges for light crane 5 tonnes lifting capacity for lowering reinforcement and handling d) steel casing. Labour Mate/Supervisor Mazdoor e) Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 20 m = a+b+c+d+e Rate per metre (a+b+c+d+e)/20 Note 1.The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate case steel lining is included in the 2.In analysis. design for driven cast-in-situ pile and is planned to be retained, the same may be included in the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an additional cost @ 0.50 per cent of cost of concrete Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification Pile Diameter = 500 mm Unit = Running Meter

Unit hour

Quantity 0.50

Rate Rs

Remark Cost Rs s/ Input ref. 230.00 115.00 P&M013 350.00 180.00 56.00 720.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-13

day day

0.16 4.00

12.28

1100 & 1700

cum

22.61

#VALUE! #VALUE!

Item 12.11 (C) iv

Kg Kg Kg hour

160.00 70.00 50.00 6.00

input #VALUE! M-080 input #VALUE! M-124 input #VALUE! M-173 input #VALUE! P&M085 P&M070

hour

0.50

input #VALUE!

day day

0.18 4.50

350.00 180.00

63.00 810.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13

say #VALUE!

12.29

1100 & 1700

Page 66 of 363

Ref. to Sr No MoRT H Spec.

Description Taking output = 60 m a) Materials RCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F (IV) b ) Material)Pile shoes a) C.I Shoes b) M.S. shoes c) Steel helmet and cushion block on top of pile head during driving. c) Machinery Crane20 t capacity Vibrating Pile driving hammer complete with power unit and accessories. d) Labour Mate/Supervisor Mazdoor Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other e) imponderables during installation. Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 60 m = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f)/60 Note The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis. Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification Pile Diameter = 750 mm Unit = Running Meter Taking output = 50 m a) Materials RCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F (IV) b ) Material)Pile shoes a) C.I. shoes b) M.S. shoes c) Steel helmet and cushion block on top of pile head during driving. c) Machinery Crane 40 T capacity Vibrating Pile driving hammer complete with power unit and accessories. d) Labour Mate/Supervisor Mazdoor Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other e) imponderables during installation. Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 50 m = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f)/50

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum

11.78

#VALUE! #VALUE!

Item 12.11 (F) iv

Kg Kg Kg

240.00 105.00 30.00

input #VALUE! M-080 input #VALUE! M-125 input #VALUE! M-173

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M073 P&M092

day day

0.12 3.00

350.00 180.00

42.00 540.00 #VALUE!

L-12 L-13

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.30

1100 & 1700

cum

22.08

#VALUE! #VALUE!

Item 12.11 (F) iv

Kg Kg Kg

160.00 70.00 40.00

input #VALUE! M-080 input #VALUE! M-125 input #VALUE! M-173

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M074 P&M092

day day

0.16 4.00

350.00 180.00

56.00 720.00 #VALUE!

L-12 L-13

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 67 of 363

Ref. to Sr No MoRT H Spec.

Description Note The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis. Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification Pile Diameter = 1000 mm Unit = Running Meter Taking output = 40 m a) Materials RCC Grade M35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F (IV) b ) Material)Pile shoes a) C.I. shoes for the pile b) M.S. shoes @ 35 Kg per pile of 15 m c) Steel helmet and cushion block on top of pile head during driving. c) Machinery Crane 50 t capacity. Vibrating Pile driving hammer complete with power unit and accessories. d) Labour Mate/Supervisor Mazdoor Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other e) imponderables during installation. Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 40 m = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f)/40 Note The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis. Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification Size of pile - 300 mm x 300 mm Unit = Running Meter Taking output = 60 m a) Materials RCC Grade M-35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F (IV) b ) Material)Pile shoes a) C I shoes b) M. S shoes c) Steel helmet and cushion block on top of pile head during driving. c) Machinery Crane 10 tonne capacity Vibrating Pile driving hammer complete with power unit and accessories. d ) Labour Mate/Supervisor Mazdoor Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other imponderables during installation. Page 68 of 363

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

12.31

1100 & 1700

cum

31.40

#VALUE! #VALUE!

Item 12.11 (F) iv

Kg Kg Kg

160.00 70.00 50.00

input #VALUE! M-080 input #VALUE! M-125 input #VALUE! M-173

hour hour

6.00 6.00

825.00

4950.00

input #VALUE!

P&M011 P&M092

day day

0.20 5.00

350.00 180.00

70.00 900.00 #VALUE!

L-12 L-13

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.32

1100 &170 0

cum

5.40

#VALUE! #VALUE!

Item 12.11 (F) iv

kg kg Kg

240.00 105.00 30.00

input #VALUE! M-080 input #VALUE! M-125 input #VALUE! M-173

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M071 P&M092

day day

0.12 3.00

350.00 180.00

42.00 540.00 #VALUE!

L-12 L-13

Ref. to Sr No MoRT H Spec.

Description e) Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 60 m = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f)/60 Note The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis. Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification Size of pile - 500 mm x 500 mm Unit = Running Meter Taking output = 50 m a) Materials RCC Grade M-35 Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( F (IV) b ) Material)Pile shoes a) C I shoes b) M. S shoes c) Steel helmet and cushion block on top of pile head during driving. c) Machinery Crane 20 tonne capacity Vibrating Pile driving hammer complete with power unit and accessories. d ) Labour Mate/Supervisor Mazdoor Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other e) imponderables during installation. Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 50 m = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f)/50 Note The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis. Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete as per Drawing and & Technical Specification Size of pile - 750 mm x 750 mm Unit = Running Meter Taking output = 40 m a) Materials RCC Grade M-35 Rate for concrete may be adopted same as for bottom plug vide item no. 13.11( F b ) Material) (IV) Pile shoes a) C I shoes b) M. S shoes c) Steel helmet and cushion block on top of pile head during driving. c) Machinery Crane 20 tonne capacity Vibrating Pile driving hammer complete with power unit and accessories.

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

12.33

1100 &170 0

cum

12.50

#VALUE! #VALUE!

Item 12.11 (F) iv

kg kg Kg

160.00 70.00 30.00

input #VALUE! M-080 input #VALUE! M-125 input #VALUE! M-173

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M073 P&M092

day day

0.16 4.00

350.00 180.00

56.00 720.00 #VALUE!

L-12 L-13

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.34

1100 &170 0

cum

22.50

#VALUE! #VALUE!

Item 12.11 (F) iv

kg kg Kg

160.00 70.00 30.00

input #VALUE! M-080 input #VALUE! M-125 input #VALUE! M-173

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M073 P&M092

Page 69 of 363

Ref. to Sr No MoRT H Spec.

Description d ) Labour Mate/Supervisor Mazdoor Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and stacking, and other e) imponderables during installation. Overhead charges @ 10% on (b+c+d) f) Contractor's profit @ 10% on (b+c+d+e) Cost for 40 m = a+b+c+d+e+f Rate per metre (a+b+c+d+e+f)/40 Note The quantity of concrete required to be removed above the designed top level of concrete, if any, will be provided for in the rate analysis. Driven Vertical Steel Piles complete as per Drawing and & Technical Specificationpile - H Section steel column Section of the 400 x 250 mm (ISHB Series) Unit = Running Meter Taking output = 70 m a) Materials Structural steel including 5 per cent wastage @ 82.20 kg/m b) Machinery Crane 10 T capacity Vibrating Pile driving hammer complete with power unit and other accessories. c) Labour Mate/Supervisor Mazdoor Add 0.5 per cent of (a+b+c) for providing steel helmet on top of pile head during driving, stacking of piles at site, providing anti-corrosion treatment d) and other imponderables duringon Overhead charges @ 10% (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 70 m = a+b+c+d+e Rate per metre (a+b+c+d+e)/70

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 63.00 810.00 #VALUE! L-12 L-13

day day

0.18 4.50

350.00 180.00

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.35 1100, 1900

tonnes

6.04

input #VALUE! M-179

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M071 P&M092

day day

0.12 3.00

350.00 180.00

42.00 540.00 #VALUE!

L-12 L-13

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.36

1100 &190 0

Driven Vertical Steel Piles complete as per Drawing and & Technical Specificationpile - H Section steel column Section of the 450 x 250 mm (ISHB Series) Unit = Running Meter Taking output = 60 m a) Materials tonnes 5.83 input #VALUE! M-179 Structural steel including 5 per cent wastage @92.50 kg/m b) Machinery Crane 10 T capacity Vibrating Pile driving hammer complete with power unit and accessories. c) Labour Mate/Supervisor Mazdoor Add 0.5 per cent of (a+b+c) for providing steel helmet and cushion block on top of pile head during driving, stacking of piles at site, providing anticorrosive treatment and other d) imponderables during installation. Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Page 70 of 363

hour hour

6.00 6.00

input #VALUE! input #VALUE!

P&M071 P&M092

day day

0.14 3.50

350.00 180.00

49.00 630.00 #VALUE!

L-12 L-13

#VALUE! #VALUE!

Ref. to Sr No MoRT H Spec.

Description Cost for 60 m = a+b+c+d+e Rate per metre (a+b+c+d+e)/60

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE!

say #VALUE! 12.37 1100 Pile Load Test on single Vertical Pile in accordance with IS:2911(Part-IV) Unit = 1 MT Taking output = 1 MT a) Initial and routine load test b) Lateral load test Note Although, this item is incidental to work and is not required to be included in BOQ of contract, the same is required to be added in the estimate to assess cost of work. Cement Concrete for Reinforced Concrete in Pile Cap complete as per Drawing and Technical Specification A RCC Grade M20 Unit = cum Taking output = 15 cum (i) Using Concrete Mixer a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator (capacity 33 KVA) Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 (ii) 12.38A Using Batching Plant, Transit Mixer and Concrete Pump a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) Lead upto 1 Km hour 2.00 890.00 1780.00 day day day day 0.16 0.38 2.50 1.00 350.00 180.00 180.00 180.00 56.00 68.40 450.00 180.00 L-12 L-10 L-13 L-13 tonne cum cum cum 5.12 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 day day day day 0.90 1.50 20.00 1.00 350.00 180.00 180.00 180.00 315.00 270.00 3600.00 180.00 L-12 L-10 L-13 L-13 tonne cum cum cum 5.12 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 tonne tonne 1.00 1.00 300.00 5000.00

12.38 1100, 1500 &170 0

hour hour

6.00 6.00

165.00 540.00

990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

P&M009 P&M079

say #VALUE!

hour hour hour

0.75 0.75 0.75

1526.00 793.00 1042.00

1144.50 594.75 781.50

P&M002 P&M080 P&M017 P&M049

Page 71 of 363

Ref. to Sr No MoRT H Spec.

Description

Unit

Quantity 37.5L

Rate Rs

Lead beyond 1 Km, L - lead in Kilometer tonne.k m Concrete Pump Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 Note The value of a, b and c may be taken as applicable i.e. either using concrete mixer or batching M25 B RCC Grade plant. Unit = cum Taking output = 15 cum (i) Using Concrete Mixer a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator (capacity 33 KVA) Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 day day day day tonne cum cum cum hour

0.75

Remark Cost Rs s/ Input ref. input #VALUE! Lead =35 km & P&M050 165.00 123.75 P&M#VALUE! 007 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.38

5.99 6.75 8.10 5.40 0.90 1.50 20.00 1.00

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 180.00 180.00 180.00 315.00 270.00 3600.00 180.00 L-12 L-10 L-13 L-13

hour hour

6.00 6.00

165.00 540.00

990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

P&M009 P&M079

say #VALUE! 12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Batching Plant @ 20 cum/hour Generator 125 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) Lead upto 1 Km hour 2.00 37.5L 890.00 1780.00 Lead beyond 1 Km, L - lead in Kilometer tonne.k m input #VALUE! day day day day 0.16 0.38 2.50 1.00 350.00 180.00 180.00 180.00 56.00 68.40 450.00 180.00 L-12 L-10 L-13 L-13 tonne cum cum cum 5.99 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051

hour hour hour

0.75 0.75 0.75

1526.00 874.00 1042.00

1144.50 655.50 781.50

P&M002 P&M018 P&M017 P&M049 Lead =35 km & P&M050

Page 72 of 363

Ref. to Sr No MoRT H Spec.

Description Concrete Pump Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 Note The value of a, b and c may be taken as applicable i.e. either using concrete mixer or batching M30 C RCC Grade plant. Unit = cum Taking output = 15 cum (i) Using Concrete Mixer a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator (capacity 33 KVA) Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 (ii) Using Batching Plant, Transit Mixer and Concrete Pump a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) Lead upto 1 Km

Unit hour

Quantity 0.75

Rate Rs

Remark Cost Rs s/ Input ref. 165.00 123.75 P&M#VALUE! 007 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.38

tonne cum cum cum day day day day

6.10 6.75 8.10 5.40 0.90 1.50 20.00 1.00

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 180.00 180.00 180.00 315.00 270.00 3600.00 180.00 L-12 L-10 L-13 L-13

hour hour

6.00 6.00

165.00 540.00

990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

P&M009 P&M079

say #VALUE! '12.38 C

tonne cum cum cum day day day day

6.10 6.75 8.10 5.40 0.16 0.38 2.50 1.00

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 180.00 180.00 180.00 56.00 68.40 450.00 180.00 L-12 L-10 L-13 L-13

hour hour hour hour

0.75 0.75 0.75 2.00 37.5L

1526.00 793.00 1042.00 890.00

1144.50 594.75 781.50 1780.00

P&M002 P&M080 P&M017 P&M049 Lead

Lead beyond 1 Km, L - lead in Kilometer tonne.k m Concrete Pump hour

input #VALUE!

0.75

165.00

=35 km & P&M050 123.75 P&M007

Page 73 of 363

Ref. to Sr No MoRT H Spec.

Description Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 Note The value of a, b and c may be taken as applicable i.e. either using concrete mixer or batching M35 D RCC Grade plant. Unit = cum Taking output = 15 cum (i) Using Concrete Mixer a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator (capacity 33 KVA) Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Machinery d) Labour and c) charges @ 10% on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 (ii) Using Batching Plant, Transit Mixer and Concrete Pump a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor for concreting Mazdoor for breaking pile head, bending bars, cleaning etc. c) Machinery Batching Plant @ 20 cum/hour Generator 125 KVA Loader (capacity 1 cum) Transit Mixer ( capacity 4.0 cu.m ) Lead upto 1 Km

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

12.38

tonne cum cum cum day day day day

6.33 6.75 8.10 5.40 0.90 1.50 20.00 1.00

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 180.00 180.00 180.00 315.00 270.00 3600.00 180.00 L-12 L-10 L-13 L-13

hour hour

6.00 6.00

165.00 540.00

990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

P&M009 P&M079

say #VALUE! '12.38 D

tonne cum cum cum day day day day

6.33 6.75 8.10 5.40 0.16 0.38 2.50 1.00

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 180.00 180.00 180.00 56.00 68.40 450.00 180.00 L-12 L-10 L-13 L-13

hour hour hour hour

0.75 0.75 0.75 2.00 37.5L

1526.00 874.00 1042.00 890.00

1144.50 655.50 781.50 1780.00

P&M002 P&M018 P&M017 P&M049 Lead

Lead beyond 1 Km, L - lead in Kilometer tonne.k m Concrete Pump Formwork @ 4 per cent on cost of concrete i.e. cost of a) Material, b) Labour and c) Machinery Page 74 of 363 hour

input #VALUE!

0.75

165.00

=35 km & P&M050 123.75 P&M#VALUE! 007

Ref. to Sr No MoRT H Spec.

Description d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 12.39 1100 &170 0 Levelling Course for Pile cap Providing and laying of PCC M15 levelling course 100mm thick below the = cum Unitpile cap. Taking output = 15 cum a) Material Cement Coarse sand 40 mm aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per metre (a+b+c+d+e)/15 12.40 1600 Supplying, Fitting and Placing uncoated HYSD bar Reinforcement in Foundation complete as per Drawing and = 1 MT Unit Technical Specifications. Taking output = 1 MT a) Material HYSD bars including5 per cent overlaps and wastage Binding wire b) Labour for cutting, bending, shifting to site, tying and placing in position Mate Blacksmith Mazdoor tonne Kg 1.05 6.00 input #VALUE! M-082 input #VALUE! M-072 hour hour 6.00 6.00 165.00 540.00 990.00 3240.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 180.00 180.00 301.00 270.00 3600.00 L-12 L-10 L-13 tonne cum cum cum cum 4.13 6.75 8.10 4.05 1.35 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-055 input #VALUE! M-053 input #VALUE! M-051

day day day

0.40 2.00 6.00

350.00 250.00 180.00

140.00 500.00 1080.00 #VALUE! #VALUE! #VALUE!

L-12 L-02 L-13

say #VALUE! 12.41 1600 Supplying, fitting and placing uncoated Mild steel reinforcement complete in foundation as per drawing and = 1 MT Unit technical specification Taking output = 1 MT a) Material MS bars including 5 per cent overlaps and wastage Binding wire b) Labour for straightening, cutting, bending, shifting to site, tying andMate placing in position Blacksmith tonne Kg 1.05 6.00 input #VALUE! M-126 input #VALUE! M-072

day day

0.43 2.25

350.00 250.00

150.50 562.50

L-12 L-02

Page 75 of 363

Ref. to Sr No MoRT H Spec.

Description Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate for per MT (a+b+c+d)

Unit day

Quantity 6.50

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 1170.00 L-13 #VALUE! #VALUE! #VALUE! say #VALUE!

Page 76 of 363

Ref. to Sr No MoRT H 13.1 Spec. 1300 & 2200

CHAPTER-13 SUB-STRUCTURE
Description Brick masonry work in 1:3 in substructure complete excluding pointing and plastering, as per drawing and Technical Specifications Unit = cum Taking output = 1 cum a) Material Bricks Ist class Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) b) Labour Mate Mason Mazdoor Add for scaffolding @ 5 per cent of cost of material and labour c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Rate per cum (a+b+c+d) Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

each cum

500.00 0.24

input #VALUE! M-079 #VALUE! #VALUE! Item 12.6 (A) 350.00 250.00 180.00 21.00 200.00 144.00 #VALUE! L-12 L-11 L-13

day day day

0.06 0.80 0.80

#VALUE! #VALUE! #VALUE! say #VALUE!

13.2 1300 & 2200

Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications Unit = 10 sqm Taking output = 10 sqm a) Material Cement mortar 1:3 (Rate as in Item b) 12.6 ) Labour Mate Mason Mazdoor c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Rate per 10 sqm (a+b+c+d)

cum day day day

0.03 0.04 0.50 0.50

#VALUE! #VALUE! 350.00 250.00 180.00 14.00 125.00 90.00 #VALUE! #VALUE! #VALUE! say #VALUE!

Item 12.6 (A) L-12 L-11 L-13

Note 13.3 1300 & 2200

Scaffolding is already included in item 13.1 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications Unit = 10 sqm Taking output = 10 sqm a) Material Cement mortar 1:3 (Rate as in Item 12.6) b) Labour Mate Mason Mazdoor c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Rate per 10 sqm (a+b+c+d) 1.Scaffolding is already included in item no. 2.The number of masons and Mazdoors already catered in the cement mortar have been taken into account while providing these categories in brick masonry, pointing and plastering. Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications Random Rubble Masonry ( coursed/uncoursed ) Unit = cum Taking output = 1 cum a) Material Stone Through and bond stone (7no.x0.24mx0.24mx0.39m = 0.16 cu.m) Cement mortar 1:3 (Rate as in Item 12.6) Page 1 of 363

cum

0.144

#VALUE! #VALUE!

Item 12.6 (A) L-12 L-11 L-13

day day day

0.04 0.50 0.50

350.00 250.00 180.00

14.00 125.00 90.00 #VALUE! #VALUE! #VALUE! say #VALUE!

Note

13.4 1400 & 2200 A

cum No cum

1.00 7.00 0.33

input #VALUE! M-148 input #VALUE! M-182 #VALUE! #VALUE! Item 12.6 (A)

Ref. to Sr No MoRT H Spec.

Description b) Labour Mate Mason Mazdoor Add for scaffolding @ 5 per cent of cost of a) Material and b) Labour c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. 35.00 300.00 216.00 #VALUE! #VALUE! #VALUE! #VALUE! L-12 L-11 L-13

day day day

0.10 1.20 1.20

350.00 250.00 180.00

(a+b+c) Rate per cum (a+b+c+d) 13.4 B Coursed rubble masonry (first sort ) Unit = cum Taking output = 1 cum a) Material Stone Through and bond stone (7no.x0.24mx0.24mx0.39m = 0.16 cu.m) Cement mortar 1:3 (Rate as in Item 12.6) b) Labour Mate Mason Mazdoor Add for scaffolding @ 5 per cent of cost of material and labour c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per cum (a+b+c+d) 13.4 C Ashlar masonry ( first sort ) Plain ashlar Unit = cum Taking output = 1 cum a) Material Stone Through and bond stone (7no.x0.24mx0.24mx0.39m = 0.16 cu.m) Cement mortar 1:3 (Rate as in Item 12.6) b) Labour for masonry work Mate Mason Mazdoor Add for scaffolding @ 5 per cent of cost of a) Material and b) Labour c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per cum (a+b+c+d) Note The labour already considered in the cement mortar have been taken into account while providing these categories in the stone masonry cement concrete in Plain/Reinforced works. sub-structure complete as per drawing and Technical Specifications Unit = cum Taking output = 1 cum A PCC Grade M15 (p) Height upto 5m cum 0.33 cum each 1.11 7.00 cum 0.30 cum each 1.10 7.00

say #VALUE!

input #VALUE! M-148 input #VALUE! M-182 #VALUE! #VALUE! Item 12.6 (A) L-12 L-11 L-13

day day day

0.12 1.50 1.50

350.00 250.00 180.00

42.00 375.00 270.00 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

input #VALUE! M-169 input #VALUE! M-182 #VALUE! #VALUE! Item 12.6 (A) L-12 L-11 L-13

day day day

0.20 2.50 2.50

350.00 250.00 180.00

70.00 625.00 450.00 #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

13.5 1500, 1700 & 2200

Page 2 of 363

Ref. to Sr No MoRT H Spec.

Description Same as Item 12.8 (A) upto 5 m height, except for formwork which shall be 10 per cent instead of 4 per cent of cost of material, labour and machinery. Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (A) d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

#VALUE! Item 12.8 (A)

10.00

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5

PCC Grade M20 Same as Item 12.8 (B) upto 5 m height, except for formwork which shall be 10 per cent instead of 4 per cent of cost of material, labour and machinery. Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (B) d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 10.00

(p) Height upto 5m

#VALUE! Item 12.8 (B) PCC

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5

PCC Grade M25

(p) Height upto 5m Same as Item 12.8 (D) upto 5 m height with the only change that the provision of form work shall be 10 per cent instead of 3.75 per cent of cost of material, labour and machinery. Cas Using concrete Mixer eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case I d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 C (p) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case II d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 C (q) Height 5m to 10m Same as Item 12.8 (D) with the following changes: (i) Add 2 per cent of cost of material, Labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 12 per cent instead of 3.75 per cent Cas Using concrete Mixer of cost of material, eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case I Page 3 of 363 10.00 10.00

#VALUE! Item 12.8 (D)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! Item 12.8 (D)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! Item 12.8 (D)

Ref. to Sr No MoRT H Spec.

Description d) formwork Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 2 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

12.00 2.00

say #VALUE! 13.5 C (q) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case II d) formwork Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 2 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 C (r) Height above 10m Same as Item 12.8 (D) with the following changes: (i) Add 4 per cent of cost of material, labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 15 per cent instead of 3.75 per cent Cas Using concrete Mixer of cost of material, eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case I d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 C (r) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (D) Case II d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 D PCC Grade M30 (p) Height upto 5m Same as Item 12.8 (F) upto 5 m height with the only change that the provision of form work shall be 10 per cent instead of 3.50 per cent of cost of material, labour and machinery. Cas Using concrete Mixer eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case I Page 4 of 363 15.00 4.00 15.00 4.00 12.00 2.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! Item 12.8 (D)

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! Item 12.8 (D)

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

Ref. to Sr No MoRT H Spec.

Description d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

10.00

say #VALUE! 13.5 D (p) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case II d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 D (q) Height 5m to 10m Same as Item 12.8 (F) with the following changes: (i) Add 2 per cent of cost of material, Labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 12 per cent instead of 3.50 per cent Cas Using concrete Mixer of cost of material, eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case I d) formwork Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 2 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 D (q) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case II d) formwork Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 2 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 D (r) Height above 10m Same as Item 12.8 (F) with the following changes: (i) Add 4 per cent of cost of material, labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 15 per cent instead of 3.50 per cent Cas Using concrete Mixer of cost of material, eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case I d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork Page 5 of 363 15.00 12.00 2.00 12.00 2.00 10.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE!

Ref. to Sr No MoRT H Spec.

Description Add 4 per cent of cost of material, Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity 4.00

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 13.5 D (r) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (F) Case II d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 E RCC Grade M20 15.00 4.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

(p) Height upto 5m Same as Item 12.8 (C) upto 5 m height, except for formwork which shall be 10 per cent instead of 4 per cent of cost of material, labour Mixer Cas Using concreteand machinery. eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case I d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 E (p) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case II d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 E (q) Height 5m to 10m For height, upto 10m, add 2 per cent of cost as above excluding formwork. For cost of formwork add 12 per cent of cost of material, labour and machinery instead of 4 per cent . Cas Using concrete Mixer eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case I d) formwork Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 2 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.00 2.00 10.00 10.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

Page 6 of 363

Ref. to Sr No MoRT H Spec. 13.5 E (q)

Description

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. say #VALUE!

Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case II d) formwork Add 12 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 2 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 12.00 2.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 E

(r) Height above 10m Same as Item 12.8 (C) with the following changes: (i) Add 4 per cent of cost of material, labour and machinery excluding form work to cater for extra lift. (ii) The provision of form work shall be 15 per cent instead of 4 per cent Cas Using concrete Mixer of cost of material, eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case I d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 15.00 4.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 E (r)

Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (C) Case II d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 15.00 4.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5

RCC Grade M25

(p) Height upto 5m Same as Item 12.8 (E) upto 5m height, excluding formwork. For cost of formwork, add 10 per cent of cost of material, labour and machinery instead Cas Using concrete Mixerof 3.75 per cent . eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case I d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 F (p) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Page 7 of 363 10.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Ref. to Sr No MoRT H Spec.

Description Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case II d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE!

10.00

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 F

(q) Height 5m to 10m For height, upto 10m, add 1.8 per cent of cost as above excluding formwork. For cost of formwork add 11.8 per cent of cost of material, labour Mixer Cas Using concreteand machinery eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case I d) formwork Add 11.8 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 1.8 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 11.80 1.80

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 F (q)

Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case II d) formwork Add 11.8 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 1.8 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 11.80 1.80

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 F

(r) Height above 10m For height, above 10m, add 4 per cent of cost as above excluding formwork. For cost of formwork add 15 per cent of cost of material, labour Mixer Cas Using concreteand machinery eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case I d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 15.00 4.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 F (r)

Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (E) Case II d) formwork Add 15 per cent of cost of material, labour and machinery (a+b+c) for Formwork Page 8 of 363 15.00

#VALUE!

#VALUE!

Ref. to Sr No MoRT H Spec.

Description Add 4 per cent of cost of material, Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity 4.00

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE! 13.5 G RCC Grade M30 (p) Height upto 5m Same as Item 12.8 (G) upto 5m height, excluding formwork. For cost of formwork, add 10 per cent of cost of material, labour and machinery instead Cas Using concrete Mixerof 3.5 per cent . eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case I d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 G (p) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case II d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 G (q) Height 5m to 10m For height, upto 10m, add 1.6 per cent of cost as above excluding formwork. For cost of formwork add 11.5 per cent of cost of material, labour Mixer Cas Using concreteand machinery eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case I d) formwork Add 11.5 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 1.6 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 G (q) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case II d) formwork Add 11.5 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 1.6 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 11.50 1.60 11.50 1.60 10.00 10.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 9 of 363

Ref. to Sr No MoRT Description H 13.5 Spec. (r) Height above 10m G For height, above 10m, add 3.5 per cent of cost as above excluding formwork. For cost of formwork add 14 per cent of cost of material, labour Mixer Cas Using concreteand machinery eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case I d) formwork Add 14 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 3.5 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 G (r) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (G) Case II d) formwork Add 14 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 3.5 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 H RCC Grade M35 (p) Height upto 5m Same as Item 12.8 (H) upto 5m height, excluding formwork. For cost of formwork, add 10 per cent of cost of material, labour and machinery instead Cas Using concrete Mixerof 3 per cent . eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case I d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 H (p) Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case II d) formwork Add 10 per cent of cost of material, labour and machinery (a+b+c) for e) Formwork Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.5 H (q) Height 5m to 10m For height, upto 10m, add 1.4 per cent of cost as above excluding formwork. For cost of formwork add 11 per cent of cost of material, labour Mixer Cas Using concreteand machinery . eI

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

#VALUE!

14.00 3.50

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

14.00 3.50

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

10.00

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

10.00

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 10 of 363

Ref. to Sr No MoRT H Spec.

Description Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case I d) formwork Add 11 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 1.4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE!

11.00 1.40

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 H (q)

Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case II d) formwork Add 11 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 1.4 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 11.00 1.40

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 H

(r) Height above 10m For height, above 10m, add 3 per cent of cost as above excluding formwork. For cost of formwork add 13 per cent of cost of material, labour Mixer Cas Using concreteand machinery eI Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case I d) formwork Add 13 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 3 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) 13.00 3.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.5 H (r)

Cas With Batching Plant, Transit Mixer and e II Concrete Pump Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item 12.8 (H) Case II d) formwork Add 13 per cent of cost of material, labour and machinery (a+b+c) for Formwork cent of cost of material, Add 3 per Labour and machinery excluding e) formwork to cater for extra lift on Overhead charges @ 10% (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Rate perm (a+b+c+d+e+f) Note The basic components of this analysis are the same as those of items 13.8 (A to H). The only changes are as under: a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost for height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work spot by providing higher ramp/stair case for use by 13.00 3.00

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 11 of 363

Ref. to Sr No MoRT H Spec.

Description b) The above mentioned percentages have been suitably modified for different categories as cost for various categories varies, whereas effort for access for same height will be similar. As the cost of richer concrete is comparatively more, the percentage to be added has been reduced Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and Technical Specifications Output: MT Taking output = 1 MT a) Material HYSD bars including 5 per cent overlaps and wastage Binding wire b) Labour for cutting, bending, shifting to site, tying and placing in position Mate Blacksmith Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate for per MT (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

13.6 Sectio n 1600 &

tonne kg

1.05 6.00

input #VALUE! M-082 input #VALUE! M-072

day day day

0.34 2.00 6.50

350.00 250.00 180.00

119.00 500.00 1170.00 #VALUE! #VALUE! #VALUE!

L-12 L-02 L-13

say #VALUE! 13.7 1600 & 2200 Supplying, fitting and placing Mild steel reinforcement complete in substructure as per drawing and Technical Specification Unit = MT Taking output = 1 MT a) Material MS bars including 5 per cent overlaps and wastage Binding wire b) Labour for straightening, cutting, bending, shifting to site, tying and placing in position Mate Blacksmith Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate for per MT (a+b+c+d) 13.8 2706 & 2200 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Unit = Nos. Taking output = 30 Nos. a) Material metre 31.50 input #VALUE! M-056 AC pipe 100 mm dia. (including wastage @ 5 per cent ) Average length of weep hole is taken as one metre for the purpose of estimating. MS clamp collar for AC pipe (average) taking 10% of above pipe rate Cement mortar 1:3 (Rate as in Item 12.6) b) Labour Mate Mason tonne kg 1.05 6.00 input #VALUE! M-126 input #VALUE! M-072

day day day

0.28 1.50 5.50

350.00 250.00 180.00

98.00 375.00 990.00 #VALUE! #VALUE! #VALUE!

L-12 L-02 L-13

say #VALUE!

each. each. cum

30.00 10.00 0.05

input #VALUE! M-123 #VALUE! #VALUE! M056/10 #VALUE! #VALUE! Item 12.6 (A) 350.00 250.00 10.50 125.00 L-12 L-11

day day

0.03 0.50

Page 12 of 363

Ref. to Sr No MoRT H Spec.

Description Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 30 m = a+b+c+d Rate per m (a+b+c+d)/30

Unit day

Quantity 0.25

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 45.00 L-13 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note

13.9 710.1. 4.of IRC:7 8& 2200 A

1. In case of stone masonry, the size of the weep hole shall be 150 mm x 80 mm or circular with 150 mm diameter. 2. For structure in stone masonry, the weep holes shall be deemed to be included in the item of stone masonry work and shall not be paid separately. Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification Unit = cum Taking output = 10 cum Granular material a) Labour Mate Mazdoor b) c) Material Granular material Machinery Plate compactor/power rammer Water Tanker d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cum of granular backfill = Cost for 10 a+b+c+d+e Rate per cum = (a+b+c+d+e)/10 hour hour 2.50 0.05 30.00 300.00 75.00 15.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M086 P&M060 cum 12.00 input #VALUE! M-009 day day 0.28 7.00 350.00 180.00 98.00 1260.00 L-12 L-13

13.9

Sandy material a) Labour Mate Mazdoor for filling, watering, ramming b) etc. Material Sand c) Machinery Plate compactor/power rammer Water Tanker d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 10 cum of sandy backfill = a+b+c+d+e Rate per cum = (a+b+c+d+e)/10 hour hour 2.50 0.06 30.00 300.00 75.00 18.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M086 P&M060 day day cum 0.28 7.00 12.00 350.00 180.00 98.00 1260.00 L-12 L-13

input #VALUE! M-006

13.1 710.1. 0 4.of IRC:7 8 and 2200

Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a Unit = cum Taking output = 10 cum. a) Labour Mate Page 13 of 363 day 0.32 350.00 112.00 L-12

Ref. to Sr No MoRT H Spec. b)

Description Mazdoor for filling, watering, ramming etc. Mazdoor (Skilled) Material Filter media of stone aggregate conforming to clause 2504.2.2. of c) MoRTH specifications. Machinery Water Tanker of 6 KL capacity d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) cost for 10 cum of Fiter Media a+b+c+d+e Rate per cum = (a+b+c+d+e)/10 =

Unit day day cum

Quantity 7.00 1.00 12.00

Rate Rs

Remark Cost Rs s/ Input ref. 180.00 1260.00 L-13 250.00 250.00 L-15

input #VALUE! M-012

hour

0.06

300.00

18.00 #VALUE! #VALUE! #VALUE! #VALUE!

P&M060

say #VALUE! 13.1 2000, 1 1000 & 2200 Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories Unit: one tonne as per drawing and capacity Considering a 250 tonne capacity bearing for a) this analysis Labour Mate Mazdoor (Skilled) Mazdoor b) Material each. 1.00 input #VALUE! M-065 Cast steel rocker bearing assembly of 250 tonne design load capacity duly painted complete with all its components as per drawing and Add 1 per cent of cost of bearing assembly for foundation anchorage bolts, lifting arrangements, grease and c) other consumables. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) 250 tonnes capacity bearing = cost for a+b+c+dper Rate tonne capacity = (a+b+c+d)/250 13.1 2000 , 2 1000 & 2200 Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per Unit: one tonne capacity Considering a 250 tonne capacity bearing for a) this analysis Labour Mate Mazdoor Mazdoor (Skilled) b) Material each. 1.00 input #VALUE! M-067 Forged steel roller bearing of 250 tonne design load capacity duly painted complete with all its components as per drawing and specifications Add 1 per cent of cost of bearing assembly for foundation anchorage bolts, lifting arrangements, grease and c) other consumables. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) 250 tonnes capacity bearing = cost for a+b+c+dper Rate tonne capacity = (a+b+c+d)/250 day day day 0.06 1.00 0.50 350.00 180.00 250.00 21.00 180.00 125.00 L-12 L-13 L-15 day day day 0.06 0.50 1.00 350.00 250.00 180.00 21.00 125.00 180.00 L-12 L-15 L-13

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 14 of 363

Ref. to Sr No MoRT H 13.1 Spec. 2000 3 & 2200

Description Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and Unit: one tonne capacity Considering a 80 tonne capacity bearing for this Labour a) analysis Mate Mazdoor Mazdoor (Skilled) b) Material PTFE sliding plate bearing assembly of 80 tonnes design load capacity duly painted complete with all its components as per drawing and Technical cent for foundation Add 1 per Specifications anchorage bolts and consumables. c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) 80 tonnes capacity bearing = cost for a+b+c+dper Rate tonne capacity = (a+b+c+d)/80

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day day each.

0.06 1.00 0.50 1.00

350.00 180.00 250.00

21.00 180.00 125.00

L-12 L-13 L-15

input #VALUE! M-069

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.1 2000 4 & 2200

Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per Unit: one cubic centimetre drawing and Considering an elastomeric bearing of size 500 x 400 x 96 mm for this analysis. Overall volume - 19200 cu.cm Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel plates = 4545 cu.cm. Hence volume of elastometer = 14655 cu.cm. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Elastomeric bearing assembly consisting of 7 layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the process of vulcanisation, complete with all components as per drawing and Add 1 per cent of cost of bearing assembly for foundation anchorage c) bolts and consumables.@ 10% on Overhead charges (a+b) Contractor's profit @ 10% on d) (a+b+c)19200cc of elastomeric bearing = cost for a+b+c+d cc of elastomeric bearing = Rate per (a+b+c+d)/19200 say #VALUE! each. 1.00 input #VALUE! M-066 day day day 0.06 1.00 0.50 350.00 180.00 250.00 21.00 180.00 125.00 L-12 L-13 L-15

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

13.1 2000 5 & 2200

Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding on stainless steel plate with mild steel matrix complete including all one tonne capacity Unit:accessories as per drawing and Considering the sliding bearing of 80 tonnes design capacity for this analysis. a) Labour

Page 15 of 363

Ref. to Sr No MoRT H Spec.

Description Mate Mazdoor Mazdoor (Skilled) b) Material Supply of sliding plate bearing of 80 tonne design capacity complete as per drawings and Technical Specifications. Add 1 per cent of cost of bearing assembly for foundation anchorage c) bolts and consumables.@ 10% on Overhead charges (a+b) Contractor's profit @ 10% on d) (a+b+c)80 tonnes of cost for a+b+c+d capacity bearing =

Unit day day day each.

Quantity 0.04 0.75 0.35 1.00

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 14.00 L-12 180.00 250.00 135.00 87.50 L-13 L-15

input #VALUE! M-070

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

13.1 2000 6 & 2200

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, complete assembly to be of cast steel/fabricated structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of Unit: one tonne capacity Considering a Pot bearing assembly of 250 tonne capacity for this analysis. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material each. 1.00 Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components as per clause 2006 and complete as per drawings and Add 1 per cent of cost of bearing assembly for foundation anchorage c) bolts and consumables.@ 10% on Overhead charges (a+b) Contractor's profit @ 10% on d) (a+b+c) 250 tonnes capacity bearing = cost for a+b+c+dper Rate tonne capacity = (a+b+c+d)/250 day day day 0.08 1.50 0.50

387.20

350.00 180.00 250.00

28.00 270.00 125.00

L-12 L-13 L-15

input #VALUE! M-068

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 16 of 363

Ref. to Sr No MoRT H Spec. 14.1 1500 &160 0 1700

CHAPTER-14 SUPER-STRUCTURE
Description Furnishing and Placing Reinforced/ Prestressed cement concrete in superstructure as per drawing and Technical Specification RCC Grade M20 Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum For formwork and staging add the following: For solid slab super-structure, 20-30 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 #VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! hour hour 6.00 6.00 #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.86 1.50 20.00 350.00 250.00 180.00 301.00 375.00 3600.00 L-12 L-11 L-13 tonne cum cum cum 5.12 6.75 8.10 5.40 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

Case I Using Concrete Mixer

14.1A Case I

(i) (p)

14.1A Case I (i)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1A Case I (i) (r) Height above 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1A Case I (ii) For T-beam & slab, 25-35 per cent of (a+b+c) (p) Height upto 5m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 1 of 363

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1A Case I (ii) (q) Height 5m to 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1A Case I (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1A Case Using Batching Plant, Transit Mixer II and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) hour Transit Mixer 4 cum capacity lead upto1 Km Lead beyond 1 Km, L - lead in Kilometer tonne.k m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: slab super-structure, 20-30 For solid per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) Page 2 of 363 hour hour hour hour day day day tonne cum cum cum

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

40.92 54.00 64.80 43.20 0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 294.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 Lead

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1A Case II

(i) (p)

#VALUE! 20.00 #VALUE! #VALUE!

f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1A Case II (i) (q) Height 5m to 10m

#VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1A Case II (i) (r) Height above 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1A Case II (ii) For T-beam & slab, 25-35 per cent of (a+b+c) (p) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1A Case II (ii) (q) Height 5m to 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1A Case II (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1 B RCC Grade M25 Unit = 1 cum Taking output = 15 cum

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case I Using Concrete Mixer

Page 3 of 363

a)

Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate tonne cum cum cum day day day hour hour 5.99 6.75 8.10 5.40 0.86 1.50 20.00 6.00 6.00 #VALUE! input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 165.00 540.00 301.00 375.00 3600.00 990.00 3240.00 L-12 L-11 L-13 P&M009 P&M079

b)

Labour Mate Mason Mazdoor

c)

Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA

14.1B Case I

(i) (p)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum For formwork and staging add the following: slab super-structure, 20-30 For solid per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15

#VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

14.1B Case I (i)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1B Case I (i) (r) Height above 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1B Case I (ii) (p) For T-beam & slab, 25-35 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1B Case I (ii) (q) Height 5m to 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 4 of 363

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1B Case I (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1B Case Using Batching Plant, Transit Mixer II and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) hour Transit Mixer 4 cum capacity lead upto1 Km beyond 1 Km, L - lead in Kilometer tonne.k Lead m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: slab super-structure, 20-30 For solid per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1B Case II (i) (q) Height 5m to 10m hour hour hour hour day day day tonne cum cum cum

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

47.95 54.20 64.80 43.20 0.84 3.00 18.00 6.00 6.00 6.00 15.00 300L

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 294.00 750.00 3240.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 Lead

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1B Case II

(i) (p)

#VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) Page 5 of 363

#VALUE! 25.00 #VALUE! #VALUE!

f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1B Case II (i) (r) Height above 10m

#VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1B Case II (ii) (p) For T-beam & slab, 25-35 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1B Case II (ii) (q) Height 5m to 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1B Case II (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1 C RCC Grade M 30 Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery day day day tonne cum cum cum

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case I Using Concrete Mixer

6.10 6.75 8.10 5.40 0.90 1.50 21.00

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 315.00 375.00 3780.00 L-12 L-11 L-13

Page 6 of 363

Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum For formwork and staging add the following: For solid slab super-structure, 20-30 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1C Case I (i) (q) Height 5m to 10m

hour hour

6.00 6.00 #VALUE!

165.00 540.00

990.00 3240.00

P&M009 P&M079

14.1C Case I

(i) (p)

#VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1C Case I (i) (r) Height above 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1C Case I (ii) (p) For T-beam & slab, 25-35 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1C Case I (ii) (q) Height 5m to 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1C Case I (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 7 of 363

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1C Case Using Batching Plant, Transit Mixer II and Concrete Pump. Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) hour Transit Mixer 4 cum capacity lead upto1 Km beyond 1 Km, L - lead in Kilometer tonne.k Lead m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: slab super-structure, 20-30 For solid per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1C Case II (i) (q) Height 5m to 10m hour hour hour hour day day day tonne cum cum cum

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

48.79 54.60 64.80 43.20 0.88 3.00 19.00 6.00 6.00 6.00 15.00 300L

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 308.00 750.00 3420.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 Lead

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1C Case II

(i) (p)

#VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1C Case II (i) (r) Height above 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) Page 8 of 363

#VALUE! 30.00 #VALUE! #VALUE!

f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1C Case II (ii) (p) For T-beam & slab, 25-35 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1C Case II (ii) (q) Height 5m to 10m

#VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1C Case II (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1 D RCC/PSC Grade M35 Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum For formwork and staging add the following: For solid slab super-structure, 18-28 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 18 per cent of (a+b+c) Page 9 of 363 hour hour day day day tonne cum cum cum

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case I Using Concrete Mixer.

6.33 6.75 8.10 5.40 0.90 1.50 21.00 6.00 6.00 #VALUE!

input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 165.00 540.00 315.00 375.00 3780.00 990.00 3240.00 L-12 L-11 L-13 P&M009 P&M079

14.1D Case I

(i) (p)

#VALUE! 18.00 #VALUE!

e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (i) (q) Height 5m to 10m

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 23 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (i) (r) Height above 10m

#VALUE! 23.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 28 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (ii) (p) For T-beam & slab, 23-33 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 23 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (ii) (q) Height 5m to 10m

#VALUE! 28.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 23.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 28 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (ii) (r) Height above 10m

#VALUE! 28.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 33 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (iii) (p) For box girder and balanced cantilever, 38-58 per cent of cost of concrete. Height upto 5m

#VALUE! 33.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 10 of 363

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 38 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (iii) (q) Height 5m to 10m

#VALUE! 38.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 48 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1D Case I (iii) (r) Height above 10m

#VALUE! 48.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 58 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 Case Using Batching Plant, Transit Mixer II and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) hour Transit Mixer 4 cum capacity lead upto1 Km Lead beyond 1 Km, L - lead in Kilometer tonne.k m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: slab super-structure, 18-28 For solid per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 18 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) Page 11 of 363 hour hour hour hour day day day tonne cum cum cum

#VALUE! 58.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

50.64 54.00 64.80 43.20 0.88 3.00 19.00 6.00 6.00 6.00 15.00 300L

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 350.00 250.00 180.00 1526.00 793.00 1042.00 308.00 750.00 3420.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 Lead

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1D Case II

(i) (p)

#VALUE! 18.00 #VALUE! #VALUE!

f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (i) (q) Height 5m to 10m

#VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 23 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (i) (r) Height above 10m

#VALUE! 23.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 28 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (ii) (p) For T-beam & slab, 23-33 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 23 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (ii) (q) Height 5m to 10m

#VALUE! 28.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 23.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 28 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (ii) (r) Height above 10m

#VALUE! 28.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 33 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (iii) (p) For box girder and balanced cantilever, 38-58 per cent of cost of concrete. Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum Page 12 of 363

#VALUE! 33.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE!

d) Formwork and staging 38 cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum

per

38.00

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (iii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 48 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1D Case II (iii) (r) Height above 10m

#VALUE! 48.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 58 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1 E PSC Grade M-40

#VALUE! 58.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Case Using concrete mixer. 1 Unit = 1 cum Taking output = 15 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4 per cent of cement b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 33 KVA Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum For formwork and staging add the following: For solid slab super-structure, 20-30 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 20 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1E Case I (i) (q) Height 5m to 10m #VALUE! 20.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! hour hour 6.00 6.00 #VALUE! 165.00 540.00 990.00 3240.00 P&M009 P&M079 day day day 0.96 2.00 22.00 350.00 250.00 180.00 336.00 500.00 3960.00 L-12 L-11 L-13 tonne cum cum cum kg 6.45 6.75 8.10 5.40 25.80 input #VALUE! M-081 input #VALUE! M-005 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

14.1E Case I

(i) (p)

Page 13 of 363

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1E Case I (i) (r) Height above 10m

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1E Case I (ii) (p) For T-beam & slab, 25-35 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 25 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1E Case I (ii) (q) Height 5m to 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 25.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 30 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/15 14.1E Case I (ii) (r) Height above 10m

#VALUE! 30.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 14.1E Case Using Batching Plant, Transit Mixer II and Concrete Pump Unit = cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4 per cent of cement b) Labour Page 14 of 363 tonne cum cum cum kg

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

51.60 54.00 64.80 43.20 206.40

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m )

day day day hour hour hour

0.94 3.50 20.00 6.00 6.00 6.00 15.00 300L

350.00 250.00 180.00 1526.00 793.00 1042.00

329.00 875.00 3600.00 9156.00 4758.00 6252.00

L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 Lead

hour Transit Mixer 4 cum capacity lead upto1 Km beyond 1 Km, L - lead in Kilometer tonne.k Lead m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: For solid/voided slab super-structure, 18-28 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 18 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 15 cum Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (i) (q) Height 5m to 10m hour

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1E Case II

(i) (p)

#VALUE! 18.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 23 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (i) (r) Height above 10m

#VALUE! 23.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 28 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (ii) (p) For T-beam & slab, 23-33 per cent of (a+b+c) Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 23 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (ii) (q) Height 5m to 10m

#VALUE! 28.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 23.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 15 of 363

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 28 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (ii) (r) Height above 10m

#VALUE! 28.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 33 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (iii) For cast-in-situ box girder, segment construction and balanced cantilever, 38-58 per cent of cost of concrete. Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 38 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (iii) (q) Height 5m to 10m

#VALUE! 33.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

(p)

#VALUE! 38.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 48 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1E Case II (iii) (r) Height above 10m

#VALUE! 48.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 58 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F F PSC Grade M-45 Unit = 1 cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4 per cent of cement b) Labour Page 16 of 363 tonne cum cum cum kg

#VALUE! 58.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

55.80 54.00 64.80 43.20 223.20

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180

Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m )

day day day hour hour hour

0.94 3.50 20.00 6.00 6.00 6.00 15.00 300L

350.00 250.00 180.00 1526.00 793.00 1042.00

329.00 875.00 3600.00 9156.00 4758.00 6252.00

L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049 Lead

hour Transit Mixer 4 cum capacity lead upto1 Km beyond 1 Km, L - lead in Kilometer tonne.k Lead m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: For solid slab/voided slab superstructure, 16-26 per cent concrete (a+b+c) Height upto 5m of cost of hour

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1F

(i) (p)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 16 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (i) (q) Height 5m to 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 21 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (i) (r) Height above 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 26 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (ii) For T-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-31 per cent of cost of upto 5m Height concrete. Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 21 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (ii) (q) Height 5m to 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 26 per cent of (a+b+c) Page 17 of 363

#VALUE! 16.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 21.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 26.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

(p)

#VALUE! 21.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 26.00 #VALUE!

e) Overhead charges @ 10% on (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (ii) (r) Height above 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 31 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) Cost for 120 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/120 14.1F (iii) For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56 per cent of cost of concrete. Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 36 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (iii) (q) Height 5m to 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 46 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1F (iii) (r) Height above 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 56 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1 G PSC Grade M-50 Unit = 1 cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4 per cent of cement b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Page 18 of 363 hour 6.00 1526.00 day day day 0.94 3.50 20.00 350.00 250.00 180.00 tonne cum cum cum kg 58.80 54.00 64.80 43.20 235.20

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 31.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

(p)

#VALUE! 36.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 46.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 56.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180 329.00 875.00 3600.00 9156.00 L-12 L-11 L-13 P&M002

Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m )

hour hour

6.00 6.00 15.00 300L

793.00 1042.00

4758.00 6252.00

P&M080 P&M017 P&M049 Lead

Transit Mixer 4 cum capacity lead upto1 hour Km beyond 1 Km, L - lead in Kilometer tonne.k Lead m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55 per cent of cost of concrete Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1G (i) (q) Height 5m to 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 45 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1G (i) (r) Height above 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 55 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 14.1 H PSC Grade M- 55 Unit = 1 cum Taking output = 120 cum a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4 per cent of cement b) Labour Mate Mason Mazdoor c) Machinery Batching Plant @ 20 cum/hour Generator 100 KVA Loader Transit Mixer ( capacity 4.0 cu.m ) Transit Mixer 4 cum capacity lead upto1 Km Page 19 of 363 hour hour hour hour day day day tonne cum cum cum kg hour

890.00 13350.00 input #VALUE!

6.00 #VALUE!

165.00

=35 km & P&M050 990.00 P&M007

14.1G

(i)

(p)

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 45.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 55.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

63.50 54.00 64.80 43.20 254.00 0.94 3.50 20.00 6.00 6.00 6.00 15.00

input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180 350.00 250.00 180.00 1526.00 793.00 1042.00 329.00 875.00 3600.00 9156.00 4758.00 6252.00 L-12 L-11 L-13 P&M002 P&M080 P&M017 P&M049

890.00 13350.00

Lead beyond 1 Km, L - lead in Kilometer tonne.k m Concrete Pump Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum For formwork and staging add the following: For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55 per cent of cost of concrete Height upto 5m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 35 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 (q) 14.1H (i) Height 5m to 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 45 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 (r) 14.1H (i) Height above 10m Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum d) Formwork and staging 55 per cent of (a+b+c)charges @ 10% on e) Overhead (a+b+c+d) f) Contractor's profit @ 10% on (a+b+c+d+e) = a+b+c+d+e+f Cost for 120 cum Rate per cum = (a+b+c+d+e+f)/120 Note 1.Where ever concrete is carried out using batching plant, transit mixer, concrete pump, admixers conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for provided for various components 2. Cement achieving desired slump of of the super structure is for estimating purpose only. Actual quantity of cement will be as per approved mix design. Similarly, the provision for coarse and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design. 3. The items like needle and surface vibrators are part of minor T & P which is already covered under the overhead charges. As such these items have not been added separately in the rateplacing HYSD Supplying, fitting and analysis. bar reinforcement in super-structure complete as per drawing and technical specifications Unit = 1 MT Taking output = 1 MT a) Material HYSD bars including 5 per cent for laps and wastage Binding wire b) Labour for cutting, bending, tying and placing in position Mate Blacksmith tonne Kg hour

300L

input #VALUE!

6.00 #VALUE!

165.00

Lead =35 km & P&M050 990.00 P&M007

(i) 14.1H (p)

#VALUE! 35.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 45.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

#VALUE! 55.00 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

14.2

1600

1.05 8.00

input #VALUE! M-082 input #VALUE! M-072

day day

0.44 3.00

350.00 250.00

154.00 750.00

L-12 L-02

Page 20 of 363

Mazdoor Basic Cost of Labour & Material (a+b) c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) MT = a+b+c+d Rate per 14.3 1800 High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting complete as per drawing and Technical Specifications Unit = 1 MT Taking output = 0.377 MT Details of cost for 12T13 strand 40 m long cable (weight = 0.377 MT) a) Material H.T. Strand @ 9.42 kg/m including 2 per cent for wastage and extra length for jacking Sheathing duct ID 66 mm along with 5 per cent extra length 40 x 1.05 = 42 m. Tube anchorage set complete with bearing plate, permanent wedges etc Cement for grouting including 3 per cent wastage @ 3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg) Add 0.50 per cent cost of material for Spacers, Insulation tape and b) miscellaneous items Labour i) For making anchorages Mate Blacksmith Mazdoor ii) For prestressing Mate/Supervisor Prestressing operator / Fitter Mazdoor iii) For grouting Mate/Supervisor Mason Mazdoor c) Machinery Stressing jack with pump Grouting pump with agitator Generator 33 KVA. d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) MT (a+b+c+d+e) Cost for 0.377 Rate per MT = (a+b+c+d+e)/0.377 Note Cost of HT steel has been taken for delivery at site. Hence carriage has not been considered. and laying Cement concrete Providing wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications Unit = 1 cum Taking output = 1 cum a) Material Cement concrete M30 Grade Refer relevant item of concrete in Item 14.1 excluding reinforcement Rate as per HYSD bar formwork item No 14.2(Excluding OH & CP) b) Labour Mazdoor for cleaning deck slab concrete c) surface. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Page 21 of 363 and fixing cables,

day

8.00 #VALUE!

180.00

1440.00 #VALUE! #VALUE! #VALUE!

L-13

say #VALUE!

tonne metre each tonne

0.39 42.00 2.00 0.125

input #VALUE! M-119 input #VALUE! M-165 input #VALUE! M-187 input #VALUE! M-081

#VALUE!

day day day day day day day day day hour hour hour

0.16 1.00 3.00 0.05 0.25 1.00 0.05 0.25 1.00 2.50 1.00 3.50

350.00 250.00 180.00 350.00 250.00 180.00 350.00 250.00 180.00 91.00 540.00

56.00 250.00 540.00 17.50 62.50 180.00 17.50 62.50 180.00

L-12 L-02 L-13 L-12 L-08 L-13 L-12 L-11 L-13

227.50 P&M040 input #VALUE! M-111 1890.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! P&M079

14.4

2702

cum tonne

1.00 0.075

#VALUE! #VALUE!

Item 14.1(C) #VALUE! #VALUE! Item 14.2 A 180.00 27.00 #VALUE! #VALUE! L-13

day

0.15

Rate per cum (a+b+c+d) 14.5 515 & 2702 Mastic Asphalt Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than Unit = sqm Taking output = 72.46 sqm (2 tonnes) (0.869 cum) assuming a density of 2.3 tonnes/cum. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Mastic cooker 1 tonne capacity Bitumen boiler 1500 litres capacity Tractor for towing and positioning of mastic cooker and bitumen boiler c) Material Base mastic (without coarse aggregates) = 60 per cent Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .material required for mastic Proportion of asphalt with coarse aggregates (based on mix design done by CRRI for a specific case) i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent by weight of mix. 2 x 10.2/100 = stone dust @ 31.9 per cent ii) Crusher 0.204 by weight of mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39 iii) Lime stone dust filler with calcium carbonate content not less than 80 per cent by weight @ 17.92 per cent by weight of mix = 2 x 17.92/100 = 0.36 iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55 v) Pre-coated stone chips of 9.5 mm nominal size for skid resistance = 72.46x0.005/10coating of chips @ 2 per vi) Bitumen for = 0.036 cent by weight = 0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg d) Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) sqm = a+b+c+d+e Cost for 72.46 Rate per sqm = (a+b+c+d+e)/72.46 Note 1.The rates for 6 mm or any other thickness may be worked out on pro-rata basis. 2. Where tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately. 3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities shall be as per mix design. hour hour hour hour hour 0.06 0.06 6.00 6.00 1.00 230.00 285.00 44.00 141.00 300.00 day day day 0.49 11.00 1.25 350.00 180.00 250.00

#VALUE! say #VALUE!

171.50 1980.00 312.50 13.80 17.10 264.00 846.00 300.00

L-12 L-13 L-15 P&M031 P&M001 P&M030 P&M005 P&M053

tonne cum

0.204 0.39

22129.50

4514.42

M-074

input #VALUE! M-021

tonne

0.36

118.00

42.48

M-188

cum

0.55

input #VALUE! M-051

cum kg

0.036 1.05

input #VALUE! M-142 22.13 23.24 M074/100 0

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 22 of 363

14.6 2703, 1500, 1600 & 1700

4.This rate analysis is based on design made by CRRI for a specific case and is meant for estimating purposes only. Actual designquantity of bitumen works each17 per 5.The is required to be done for out case. cent of the mastic asphalt blocks without aggregates and falls within the standards laid down by MoRTH Specifications. Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per Unit = 1 RM Taking output = 2 x 24 m span = 48 m a) Material cum 4.09 #VALUE! #VALUE! Item 14.1(C) Cement concreteM30 Grade Refer relevant item of concrete in Item 14.1(C) by using batching plant, excluding formwork i.e. per cum basic No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = Add 5 per cent of above cost for form work for casting in casting yard. HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP) Refer MoRTH SD / 202. Add 5 per cent of (a) for handling and fixing of precast panels in position b) Overhead charges @ 10% on (a) c) Contractor's profit @ 10% on (a+b)for 48 m (a+b+c) Rate Rate per metre (a+b+c)/48 Note 1.Quantities of material have been adopted from standard plans of MoRTH vide drawing no. SD/202. 2.48 m length is the total linear length adding both sides of 24 m span. Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved Unit = 1 RM Taking output = 2 x 24 m span = 48 m. a) Material Cement concreteM30 Grade Refer relevant item of concrete in Item 14.1(C) by using batching plant, excluding formwork i.e. per cum basic No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total Concrete = Add 12 per cent of above cost for form work. bar reinforcement Rate as per HYSD item No 14.2(Excluding OH & CP) refer MoRTH SD / 202. b) Overhead charges @ 10% on (a) Page 23 of 363 #VALUE! cum 4.092 #VALUE! #VALUE! Item 14.1(C)

#VALUE! tonne 0.87 #VALUE! #VALUE! Item 14.2 A

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

14.7 2703, 1500, 1600 & 1700

#VALUE! tonne 0.87 #VALUE! #VALUE! Item 14.2 A

c) Contractor's profit @ 10% on (a+b) Rate for 48 m (a+b+c) Rate per metre (a+b+c)/48 Note 1. Quantities of material have been adopted from standard plans of MoRTH vide drawing length is the total linear length 2. 48 m no. SD/202. adding both sides of 24 m span. 2703. Providing, fitting and fixing mild steel 2& railing complete as per drawing and 1900 Technical Specification Unit = 1 RM Taking output = 2 x 50 m span = 100 m a) Material: 1) ISMC 100 = 2.806 x 1.05 = 2.946 MT 2) MS Flat = 0.964 x 1.05 = 1.012 MT 3) MS bars = 0.17 x 1.05 = 0.180 MT 4) MS bolts, nuts and washers Add @ 5 per cent of cost of material for painting one shop coat with red oxide primer and three coats of synthetic enamel paint and consumables to safeguard fixing Add for cost of concrete foragainst vertical posts in the performed recess @ 1 for electricity charges, welding and Add per cent of cost of material. drilling equipment, electrodes and other consumables @ 1 per cent of cost of b) material. Labour Mate Mazdoor (Skilled) Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 100 m steel railing = a+b+c+d Rate per metre (a+b+c+d)/100 14.9 2705 Drainage Spouts complete as per drawing and Technical specification Unit = 1 No. Taking output = 1 No. a) Material Corrosion resistant Structural steel including 5 per cent wastage GI pipe 100mm dia GI bolt 10 mm Dia Galvanised MS flat clamp b) Labour Mate Skilled (Blacksmith, welder etc.) Mazdoor For fixing in position Mate Mason Mazdoor Add @ 5 per cent of cost of material and labour for electrodes, cutting gas, sealant, anti-corrosive bituminous paint, c) mild steel grating etc. @ 10% on Overhead charges (a+b) Contractor's profit @ 10% on d) (a+b+c) metre (a+b+c+d) Rate per day day day 0.01 0.01 0.20 350.00 250.00 180.00 day day day 0.02 0.02 0.02 350.00 250.00 180.00 For fabrication Kg metre each each 4.00 6.00 6.00 2.00 day day day 2.80 30.00 40.00 350.00 250.00 180.00 tonne tonne tonne tonne 2.95 1.01 0.18 0.15

#VALUE! #VALUE! #VALUE! say #VALUE!

14.8

input #VALUE! M-179 input #VALUE! M-179 input #VALUE! M-179 #VALUE! #VALUE! M130*100 0 #VALUE!

#VALUE! #VALUE!

980.00 7500.00 7200.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-15 L-13

say #VALUE!

#VALUE! #VALUE!

M087/100 0 input #VALUE! M-056 input #VALUE! M-110 input #VALUE! M-101

7.00 5.00 3.60 3.50 2.50 36.00 #VALUE!

L-12 L-02 L-13 L-12 L-11 L-13

#VALUE! #VALUE! #VALUE! say #VALUE!

Page 24 of 363

Note 1. In case of viaducts in urban areas, the drainage spouts should be connected with suitably located pipelines to discharge the surface run-off to drains provided at ground level.case of bridges, sufficient length of G.I 2. In Pipe shall be provided to ensure that there is no splashing of water from the drainage spoutM15 Grade leveling course below PCC on the structure. approach slab complete as per drawing and Technical specification Unit = 1 cum Taking output = 1 cum Material Concrete, Rate as per item No. 12.8 (A) excluding formworks Rate per cum 14.11 1500, 1600, 1700 & Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and Technical specification Unit = 1 cum Taking output = 1 cum a) Material Cement concreteM30 Grade Refer relevant item of concrete in item 12.8(G)by using batching plant, excluding formwork i.e. per cum basic cost (a+b+c) (Excludingconcrete in item ( Refer relevant item of OH & CP) No. 13.8 (G) except that form work may be added at the rate of 2 per cent of cost against 3.5 per cent provided in the foundation concrete. Rate as per HYSD bar reinforcement item No 14.2(Excluding OH & CP) b) Overhead charges @ 10% on (a) c) Contractor's profit @ 10% on(a+b) cum (a+b+c) Rate per Note The grade of reinforced cement concrete may be adopted as M30 for severe conditions and M25 for moderate conditions. anti-corrosive treatment to Providing HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC) Unit = 1 MT Taking output = 1 MT To be taken as per the prevailing market Note rates. Contractors generally do not have expertise for this item . The job is therefore, got done from specialised firms who have the expertise in the field of construction chemicals. The prevailing rate in the market is required to be ascertained from the market and added in the cost estimate. Detailed guidelines in this regard have been issued by MoRTH vide their circular no. Precast - pretensioned Girders Providing, precasting, transportation and placing in position precast pretensioned concrete girders as per drawing cum Unit = 1 and technical specifications Taking output = 1 cum Grade of concrete - M40 a) Material Cement Coarse sand 20 mm Aggregate 10 mm Aggregate Admixture @ 0.4 per cent of cement Page 25 of 363 tonne cum cum cum Kg 0.47 0.45 0.54 0.36 1.88 input #VALUE! M-081 input #VALUE! M-004 input #VALUE! M-053 input #VALUE! M-051 input #VALUE! M-180 cum 1.00 #VALUE! #VALUE! Item 12.8 (G) cum 1.00 #VALUE! #VALUE! say #VALUE! Item 12.8 (A)

14.10 2700

#VALUE!

tonne

0.05

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Item 14.2 A

14.12 1600

14.13 1800 & 2300

HYSD steel . HT strand with 5 per cent as wastage and extra length for anchoring LDO for steam curing Add consumables such as binding wire, foam, packing tape, shuttering oil, HDPE pipe for unbonding of strand, bolt & nuts etc @ 1 per cent of material cost b) Labour (i) Cutting, bending, making reinforcement cage, placing in position, bindingof steel 100 Kg/cum of Taking quantity etc. complete concrete including laps and wastage Mate Mazdoor (Skilled) Mazdoor (ii) Cable cutting and threading in position including binding by insulation tape with HDPE pipes etc., prestessing and cutting of extra length of HT strand after de-stressing. Taking quantity of HT strand 60 Kg/cum Mate Mazdoor (Skilled) Mazdoor (iii) Erection and dismantling of shuttering Taking shuttering area 10 sqm/cum of concrete Mate Mazdoor (Skilled) Mazdoor (iv) Concreting by Batching plant and stationary concrete pump Mate Mazdoor (Skilled) Mazdoor (v) Steam curing and manual curing Mate Mazdoor (vi) Handling of precast girder, stacking in stockyard and again loading in trailor Mate Mazdoor (vii) Placement of girders in position over pier caps including placement of sand jacks, channel, levelling etc. Mate Mazdoor (Skilled) Mazdoor c) Machinery Generator 100 KVA Batching Plant @ 20 cum/hour Transit Mixer 4 cum capacity Concrete Pump stationary Crane 35 tonne capacity Trailor 30 tonne capacity Loader ii) For transportation and placement at siteCrane 35 tonne capacity Trailer 30 tonne capacity for transporting to site. (L - Lead in Kilometer) Trailor 30 tonne capacity during placement. Page 26 of 363 i) At casting yard

tonne tonne Litre

0.10 0.06 37.00

input #VALUE! M-082 input #VALUE! M-119 input #VALUE! M-122 #VALUE!

day day day

0.06 0.35 1.40

350.00 250.00 180.00

21.00 87.50 252.00

L-12 L-15 L-13

day day day

0.02 0.14 0.50

350.00 250.00 180.00

7.00 35.00 90.00

L-12 L-15 L-13

day day day

0.12 1.00 2.00

350.00 250.00 180.00

42.00 250.00 360.00

L-12 L-15 L-13

day day day day day

0.03 0.05 0.60 0.01 0.35

350.00 250.00 180.00 350.00 180.00

10.50 12.50 108.00 3.50 63.00

L-12 L-15 L-13 L-12 L-13

day day

0.01 0.25

350.00 180.00

3.50 45.00

L-12 L-13

day day day

0.01 0.06 0.24

350.00 250.00 180.00

3.50 15.00 43.20

L-12 L-15 L-13

hour hour hour hour hour hour hour hour tonne.k m

0.05 0.05 0.10 0.05 0.10 0.10 0.05 0.15 2.5xL

793.00 1526.00 890.00 165.00 550.00 1042.00 550.00

39.65 76.30 89.00 8.25 55.00 52.10 82.50

P&M080 P&M002 P&M049 P&M007 P&M012 P&M089 P&M017 P&M012 Lead =35 km & P&M090

input #VALUE!

input #VALUE!

hour

0.15

input #VALUE!

P&M089

Cost of formwork, steam curing arrangement, pretensioning arrangement etc @ 5 per cent of cost d) material, labour and machinery on Overhead charges @ 10% (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per cum = (a+b+c+d+e) 14.14 1700 & 1800 Providing and fixing Helical pipes in voided concrete slabs Unit = 1 RM Taking output = 1 RM a) Material Helical pipes 600mm diameter Tie rods 20mm diameter Consumables for sealing joints etc.@ 5 per cent of cost of material b) Labour Mate Fitter Mazdoor c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) cum (a+b+c+d) Rate per 14.15 800 Crash Barriers The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation. Painting on concrete surface Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 sqm. Unit = sqm Taking output = 10 sqm a) Labour Mate Painter Mazdoor (Skilled) b) Material Litres 5.00 Water based paint of approved quality for cement concrete surface c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 10 sqm (a+b+c+d) Rate per sqm (a+b+c+d)/10 14.17 2604 Burried Joint Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick, 200 mm wide galvanised weldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along the Unit = Running meter Taking output = 12 m a) Labour Mate Page 27 of 363 day 0.02 350.00 day day day 0.01 0.25 0.25 350.00 250.00 250.00 day day day 0.01 0.05 0.20 350.00 250.00 180.00 metre each 1.00 1.00

#VALUE!

#VALUE! #VALUE! #VALUE! say #VALUE!

input #VALUE! M-117 input #VALUE! M-183 #VALUE!

3.50 12.50 36.00 #VALUE! #VALUE! #VALUE!

L-12 L-08 L-13

say #VALUE!

14.16

800

3.50 62.50 62.50

L-12 L-18 L-15

input #VALUE! M-190 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

7.00

L-12

Mazdoor Mazdoor (Skilled) b) Material Galvanised M.S plate 200 mm wide,12 mm thick @ 94.20 kg/sqm including 5 per cent wastage cost of steel plate Add 1 per cent of cutting, welding consumables and c) galvanised nails. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 12 m = (a+b+c+d) Rate per m = (a+b+c+d)/12 Note Guidelines laid down vide the MoRTH circular No. RW/NH-34059/1/96-S&R dated 30.11.2000 and subsequent corrigendum dated 25.01.2001 may be reffered for expansion joints. Filler joint (i) Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical Specification. Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Copper plate - 12m long x 250 mm wide Area = 12 x 0.25 = 3 sqm Weight = 3 x 0.002 x 8900 = 53.4 kg Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = Overhead charges @ 10% on 55 kg. c) (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 14.18 (ii) Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical Specification. Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material 20 mm thick compressible fibre board 12 m long x 25 cm deep. Area = 12 x 0.25 = 3 sqm c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 14.18 (iii) Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete as per drawing and Unit = Running meter Page 28 of 363 For carrying, placing & fixing. Cutting, bending, carrying & fixing etc.

day day kg

0.40 0.20 237.50

180.00 250.00

72.00 50.00

L-13 L-15

#VALUE! #VALUE!

M060/100 0 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

say #VALUE!

14.18 2605

day day day kg

0.04 0.50 0.50 55.00

350.00 180.00 250.00

14.00 90.00 125.00

L-12 L-13 L-15

input #VALUE! M-086

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

day day day sqm

0.008 0.10 0.10 3.00

350.00 180.00 250.00

2.80 18.00 25.00

L-12 L-13 L-15

input #VALUE! M-084

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material sqm 3.60 input #VALUE! M-141 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! 14.18 (iv) Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand= Running cent bitumen by Unit and 6 per meter Taking output = 12 m 12m long x 100 mm wide x 10mm deep recess a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Sand Volume 12 x 0.1 x 0.01 = 0.012 cum Weight 0.012 x 1400 = 16.8kg Bitumen 16.8 x 0.06 = 1 kg c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 Note For arriving at the final rate of filler joints per m and per cm depth of joint filling length 14.19 2600 compound, Sl. No. i), ii), iii) & iv) shall be the rates at added Asphaltic Plug joint Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure plate of 200mm x 6mm of weldable structural steel conforming to IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Crushed stone aggregate 12.5 mm nominal size Polymer modified bitumen 2.4 Galvanised structural steel plate 200 mm wide,6 mm thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm including 5 per cent wastage Page 29 of 363 cum kg kg 0.75 77.50 113.00 input #VALUE! M-052 #VALUE! #VALUE! M-078/ 1000 input #VALUE! M-103 day day day 0.052 1.00 0.30 350.00 180.00 250.00 18.20 180.00 75.00 L-12 L-13 L-15 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! cum 0.001 22129.50 22.13 M-074 cum 0.012 input #VALUE! M-005 day day day 0.02 0.50 0.10 350.00 180.00 250.00 7.00 90.00 25.00 L-12 L-13 L-15 Premoulded joint filler 12 m long,20 mm thick and 300 mm deep. c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 day day day 0.01 0.20 0.10 350.00 180.00 250.00 3.50 36.00 25.00 L-12 L-13 L-15

Add 1 per cent for welding and foam caulking/backer rod and other c) incidentals. Machinery Mastic cooker 1 tonne capacity Smooth 3-wheeled steel roller 8-10 d) capacity Overhead charges @ 10% on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) asphalt plug joint = Cost for 12 m (a+b+c+d+e) Rate per m = (a+b+c+d+e)/12 Note The nominal size of aggregates shall be 12.5 mm for depth of joint upto 75 mm and 20 mm for joints of depth more than 75 mm. Elastomeric Slab Steel Expansion Joint Providing and laying of an elastomeric slab steel expansion joint, catering to right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material metre 12.00 Supply of elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 915.1 of IRC: 83 (part II), complete as per approved drawings and standard specification conforming to Add 5 per cent of cost of material for anchorage reinforcement, welding and c) other incidentals. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 14.21 2600 Compression Seal Joint Providing and laying of compression seal joint consisting of steel armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material 1. Galvanised angle sections 100mm x 100mm of 12mm thickness weldable structural steel as per IS: 2062, 2 nos. of 12 m length each @ 17.7 kg/m and 5 per cent wastage.cost of above for Add 5 per cent of structural steel for anchorage, welding and other incidentals. Page 30 of 363 kg 446.00 day day day 0.036 0.60 0.30 350.00 180.00 250.00 day day day 0.06 1.00 0.50 350.00 180.00 250.00 hour hour 1.00 0.50 44.00 470.00

#VALUE!

44.00 235.00 #VALUE! #VALUE! #VALUE! #VALUE!

P&M030 P&M044

say #VALUE!

14.20 2606

21.00 180.00 125.00

L-12 L-13 L-15

input #VALUE! M-093

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

12.60 108.00 75.00

L-12 L-13 L-15

input #VALUE! M-103

#VALUE!

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the full length cent joint to ensure water Add 1 per of a of cost of sealing element for lubricant-cum-adhesive and c) other consumables. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 Note 1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer. 2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck. joint 3. The anchoring bars of the expansion assembly shall be welded to the main reinforcement of the deck. Strip Seal Expansion Joint Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Supply of complete assembly of strip seal expansion joint comprising of edge beams, anchorage, strip seal element and complete accessories as per approved specificationsof material for Add 5 per cent of cost and drawings. anchorage reinforcement, welding and c) other incidentals. Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = (a+b+c+d) Cost for 12 Rate per m = (a+b+c+d)/12 Note 1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer. 2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of Joint Modular Strip / Box Seal RCC deck. Providing and laying of a modular strip Box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled)

metre

12.00

input #VALUE! M-143

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

14.22 2607

day day day metre

0.05 1.00 0.25 12.00

350.00 180.00 250.00

17.50 180.00 62.50

L-12 L-13 L-15

input #VALUE! M-178

#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

14.23 2600

day day day

0.056 1.00 0.40

350.00 180.00 250.00

19.60 180.00 100.00

L-12 L-13 L-15

Page 31 of 363

b)

Material metre 12.00 input #VALUE! M-127

Supply of a modular strip/box seal joint assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m Modular strip/box seal joint = Cost for 12 (a+b+c+d) = (a+b+c+d)/12 Rate per m Note 1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer. 2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck. joint 3. The anchoring bars of the expansion assembly shall be welded to the main reinforcement of the deck. Joint Modular Strip / Box Seal Providing and laying of a modular strip box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring Unit = Running meter Taking output = 12 m a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Supply of a modular box/box seal joint assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer or his c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) m Modular strip/box seal joint = Cost for 12 (a+b+c+d) = (a+b+c+d)/12 Rate per m Note 1. The installation shall be done by the manufacturer or his authorised representative to the satisfaction of the Engineer. 2. The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC deck. joint 3. The anchoring bars of the expansion assembly shall be welded to the main reinforcement of the deck.

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

14.24 2600

day day day metre

0.07 1.25 0.50 12.00

350.00 180.00 250.00

24.50 225.00 125.00

L-12 L-13 L-15

input #VALUE! M-128

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 32 of 363

Ref. to Sr No MoRT H 15.1 Spec. 2503

CHAPTER - 15 RIVER TRAINING AND PROTECTION WORKS


Description Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing Laid Technical specification. Boulder and Dry Without Wire Crates. Unit = cum Taking output = 1 cum a) Material Stone Stone Spalls b) Labour Mate Mason Mazdoor * c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Rate per cum = (a+b+c+d) * Including excavation for trimming for Note Nominal excavation required for preparation of bed has been taken into account while making provision Crates Boulder Apron Laid in Wire for labour. Providing and laying of boulder apron laid in wire crates made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10 per cent extra for laps and joints= cum Unit laid with stone boulders weighing not Taking output = 3 mx1.5mx1.25m = a) Material 4mm GI wire crates woven in mesh size of 100 mm x 100 mm. Stone Stone Spalls b) Labour Mate Mazdoor (Skilled) Mazdoor c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Cost for 5.63 cum = a+b+c+d Rate per cum = (a+b+c+d)/5.63 * Including excavation for trimming for Note Readymade woven wire crate rolls have been considered in the rate analysis. In case readymade rolls are not available, GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per cent of the cost of GIConcrete be added for weaving Cement wire may Blocks (size 0.5 x 0.5 Providing and laying of apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cement content of 250 kg/cum as per IRC: Unit = cum Taking out put = 1 cum Concrete Grade M15 Rate as per item No. 12.8 (A) including OH & CP Add 2 per cent of cost to account for excavation for preparation of bed, nominal surface reinforcement and filling of granular material in recesses between blocks. Rate per cum cum 1.00 #VALUE! #VALUE! #VALUE! Item 12.8 (A) Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

cum cum day day day

1.00 0.20 0.04 0.35 0.75

input #VALUE! M-003 input #VALUE! M-008 350.00 250.00 180.00 14.00 87.50 135.00 #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-11 L-13

15.2 2503

sqm cum cum day day day

22.00 5.63 1.13 0.18 1.50 *3.00

input #VALUE! M-102 input #VALUE! M-003 input #VALUE! M-008 350.00 250.00 180.00 63.00 375.00 540.0 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-15 L-13

15.3 2503

#VALUE! say #VALUE!

Page 1 of 363

Ref. to Sr No MoRT H 15.4 Spec. 2504

Description Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical Stone/Boulder Unit = cum Taking output = 1 cum a) Material Stone weighing not less than 40kg Stone spalls of minimum 25 mm size b) Labour Mate Mason Mazdoor c) Overhead charges @ 10% on d) Contractor's profit @ 10% on Rate per cum = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum cum day day day

1.00 0.20 0.04 0.35 0.75

input #VALUE! M-003 input #VALUE! M-008 350.00 250.00 180.00 14.00 87.50 135.00 #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-11 L-13

15.4

Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 Unit = cum Taking output = 1 cum Concrete Grade M15 Rate as per item No. 12.8 (A) Add 2 per cent of cost to account for nominal surface reinforcement and filling of granular material in recesses between blocks. Rate per cum cum 1.00 #VALUE! #VALUE! #VALUE! Item 12.8 (A)

#VALUE! say #VALUE!

15.5 2504

Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification Unit = cum Taking output = 1 cum a) b) Material Graded stone aggregate of required size Labour Mate Mazdoor (Skilled) Mazdoor * c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) cum = (a+b+c+d) Rate per Includes Mazdoor required for trimming of slope to proper profile and preparation of bed. Geotextile Filter Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free movement of water without creating any uplift head on the Unit = sqm Taking output = 10 sqm. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material sqm 11.00 input #VALUE! M-181 #VALUE! Permeable synthetic geotextile including 5 per cent for overlap and c) wastage Overhead charges @ 10% on (a+b) Page 2 of 363 day day day 0.02 0.30 0.10 350.00 180.00 250.00 7.00 54.00 25.00 L-12 L-13 L-15 day day day 0.05 0.25 1.00 350.00 250.00 180.00 17.50 62.50 180.00 #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-15 L-13 cum 1.20 input #VALUE! M-012

15.6 700 & 2504

Ref. to Sr No MoRT H Spec.

Description d) Contractor's profit @ 10% on (a+b+c) sqm = a+b+c+d Cost for 10 Rate per sqm = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE! #VALUE! #VALUE!

say #VALUE! 15.7 2504. 4 Toe protection A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix if cement concert block have been used for pitching . Rates for toe wall can be adopted from respective clauses depending upon approved design. The rate for excavation for foundation, dry rubble masonry and PCC M15 have been analysed and given in Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concert bedding. stone laid in cement mortar Rubble 1:3 Unit = cum Taking output = 1 cum a) Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis) excluding OH & CP b) Add for cement concrete bedding (M15 Nominal mix) vide Item 12.8 (A) excluding OH & CP . Quantity shall be adopted as per design ( Assume Rubble stone Flooring thickness 300mm 1 per cement cost to account for Add and cent of concrete bedding excavation for preparation of bed. c) Material Stone Stone Spalls d) Labour Mate Mason Mazdoor (for laying stones, filling of e) quarry spalls) charges @ 10% on Overhead (a+c+d) f) Contractor's profit @ 10% on (a+c+d+e) Rate per cum = (a+b+c+d+e+f) * 15.8 B Includes cement mortar for laying and filling of joints. Cement Concrete blocks Grade M15 Concrete Grade M15 block. (Rate as per item No. 12.8 (A) including OH & CP. Add for cement concrete bedding (M15 Nominal mix) vide Item 12.8 (A) including OH & CP. Quantity shall be adopted as per design ( Assume Cement Concrete blocks thickness 300mm and cement concrete bedding Add 1 per cent of cost to account for excavation for preparation of bed. Rate per cum 15.9 2506 Dry Rubble Flooring Construction of dry rubble flooring at cross drainage works for relatively less important works. Unit = cum Taking output = 1 cum a) Material Stone Stone Spalls b) Labour cum cum 1.00 0.20 input #VALUE! M-003 input #VALUE! M-008 cum cum 1.00 0.33 #VALUE! #VALUE! Item 12.8 (A) #VALUE! #VALUE! Item 12.8 (A) day day day 0.08 0.50 1.50 350.00 250.00 180.00 28.00 125.00 270.00 #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-11 L-13 cum cum 1.00 0.20 input #VALUE! M-003 input #VALUE! M-008 cum cum 0.33 0.33 #VALUE! #VALUE! Item 12.6 (A) #VALUE! #VALUE! Item 12.8 (A)

15.8 2505

#VALUE!

#VALUE! #VALUE! say #VALUE!

Page 3 of 363

Ref. to Sr No MoRT H Spec.

Description Mate Mason mazdoor Add 1 per cent of (b) for trimming and preparation of base. c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) cum = (a+b+c+d) Rate per

Unit day day day

Quantity 0.10 0.50 1.50

Rate Rs

Remark Cost Rs s/ Input ref. 350.00 35.00 L-12 250.00 180.00 125.00 270.00 4.30 #VALUE! #VALUE! #VALUE! say #VALUE! L-11 L-13

15.1 2507. 0 2 A

Curtain wall complete as per drawing and Technical specification Stone masonry in cement mortar (1:3) Coursed rubble masonry (1st sort) Rate same as per item No. 12.7 (A) including OH & CP Rate per cum or cum 1.00 #VALUE! #VALUE! Item 12.7 (A )

say #VALUE!

15.1 0

Cement concrete Grade M15 Concrete Grade M15 Rate as per item No. 12.8 (A) including OH & CP Rate per cum cum 1.00 #VALUE! #VALUE! say #VALUE! Item 12.8 (A)

Note Other items like excavation for foundation, filling behind wall, filter media, weep holes etc. shall be added separately as per approved Apron :Construction of flexible 15.1 2507. Flexible design. 1 2 apron 1 m thick comprising of loose stone boulders weighing not less than 40 kg cum Unit =beyond curtain wall. Taking Output = 1 cum a) Material Stone Stone Spalls b) Labour Mate Mason Mazdoor Add 1 per cent of cost of (a+b) for trimming and preparation of bed. c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per cum = (a+b+c+d) 15.1 2503. 2 3 Gabian Structure for Retaining Earth Providing and construction of a gabian structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with Unit = cum Taking output = 7 x 3 x 0.6 = 12.60 cum Labour a) Mate Mazdoor Mazdoor (Skilled) b) Material day day day 0.28 5.00 2.00 350.00 180.00 250.00 98.00 900.00 500.00 L-12 L-13 L-15 day day day 0.05 0.25 1.00 350.00 250.00 180.00 17.50 62.50 180.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-11 L-13 cum cum 1.00 0.20 input #VALUE! M-003 input #VALUE! M-008

Page 4 of 363

Ref. to Sr No MoRT H Spec.

Description Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. boulders with least dimension of Stone 200 mm Stone spalls of minimum size 25 mm c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 12.60 cum (a+b+c+d) Rate per cum (a+b+c+d)/12.60

Unit sqm

Quantity 61.00

Rate Rs

Remark Cost Rs s/ Input ref. input #VALUE! M-102

cum cum

12.60 2.52

input #VALUE! M-003 input #VALUE! M-008 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note Readymade woven wire crate rolls have been considered in the rate analysis. In case readymade rolls are not available, GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per cent of the cost of GIStructure be added for weaving 15.1 2503. Gabian wire may for Erosion Control, 3 3 River Training Works and Protection works Providing and constructing gabian structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with least Unit = cum Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum a) Labour Mate Mazdoor Mazdoor (Skilled) b) Material Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size toboulders with least dimension of Stone cover 6.00 cum. 200 mm Stone spalls of minimum size 25 mm c) Overhead charges @ 10% on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 6.00 cum (a+b+c+d) Rate per cum (a+b+c+d)/6.00 Note Readymade woven wire crate rolls have been considered in the rate analysis. In case readymade rolls are not available, GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per cent of the cost of GI wire may be added for weaving sqm 65.00 input #VALUE! M-102 day day day 0.14 2.50 1.00 350.00 180.00 250.00 49.00 450.00 250.00 L-12 L-13 L-15

cum cum

6.00 1.20

input #VALUE! M-003 input #VALUE! M-008 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 5 of 363

Ref. to Sr No MoRT H 16.1 Spec. 2809

CHAPTER-16 REPAIR AND REHABILITATION


Description Removal of existing cement concrete wearing coat including its disposal complete as per Technical Specification without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with all lifts and Unit = Sq m ( Thickness 75 mm) Taking output = 10 sqm a) Labour Mate Mazdoor b) Machinery Air Compressor 250 cfm with pneumatic breaker/jack hammer along with accessories. Tractor-trolley. c) Overhead charges @ input on d) Contractor's profit @ 10% on Cost for 10 sqm = (a+d+c+d) Rate per sqm = (a+b+c+d)/10 Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concert laid over 12 mm thick mastic asphalt including disposal with all lift andm Unit = Sq lead upto 1000 m. Taking output = 10 sqm a) Labour Mate Mazdoor b) Machinery Air Compressor 250 cfm with pneumatic Tractor-trolley. c) Overhead charges @ input on d) Contractor's profit @ 10% on Cost for 10 sqm = (a+d+c+d) Rate per sqm = (a+b+c+d)/10 Unit Quantity Rate Rs Remark Cost Rs s/ Input ref.

day day hour hour

0.06 1.00 1.00 0.50

350.00 180.00 285.00 300.00

21.00 180.00 285.00

L-12 L-13 P&M001 P&M-

150.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.2 2809

day day hour hour

0.03 0.75 0.75 0.40

350.00 180.00 285.00 300.00

10.50 135.00

L-12 L-13 P&MP&M-

213.75 120.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.3 2807

Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying with epoxy complete as per Technical Specification Unit = Sq m Taking output = 1 sqm Assuming thickness 25 mm a) Material Cement Graded sand Wire mesh 50mm x 50mm size of 3mm Epoxy Accelerator compound for guniting @ 4 per cent of weight of cement Add 2 per cent of cost of material for miscellaneous consumables like nozzles, wire brush, cotton waste etc. b) Labour Mate Mason Mazdoor c) Machinery Compressor with guniting equipment along with accessories d) Overhead charges @ input on e) Contractor's profit @ 10% on Rate per sqm = (a+b+c+d+e)

kg cum kg kg kg

16.00 0.04 2.00 0.67 0.64

#VALUE! #VALUE! input input input input #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

M081/100 0 M-005 M-192 M-095 M-180

day day day hour

0.01 0.04 0.14 0.10

350.00 250.00 180.00

3.50 10.00 25.20

L-12 L-11 L-13 P&M076

input #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Page 1 of 363

Ref. to Sr No MoRT H 16.4 Spec. 2800

Description Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical Specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting Unit = Number Taking output = 1 No. a) Material Nipples Cement, fixing compound and consumables @ 15 per cent of cost of b) nipple Labour Mate Mazdoor (Skilled) labour for drilling Mazdoor (Skilled) labour for fixing nipple and sealing inlets Mazdoor for cutting and removing of nipples Add 10 per cent of labour cost for c) drilling holes etc Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) Rate per No. = (a+b+c+d)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

each

1.00

input #VALUE! M-129 #VALUE!

day day day day

0.01 0.08 0.08 0.04

350.00 250.00 250.00 180.00

3.50 20.00 20.00 7.20 5.07 #VALUE! #VALUE! #VALUE!

L-12 L-15 L-15 L-13

say #VALUE! 16.5 2806 Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical Specification. Cement Grout Unit = kg Taking output = 1 kg a) Material Cement including 10 per cent wastage Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement b) Labour Mate Mazdoor (Skilled) Mazdoor c) Machinery Grout pump with agitator and d) accessories charges @ input on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) = (a+b+c+d+e) Rate per kg B Cement Mortar (1:1) Grouting Unit = kg Taking output = 1 kg a) Material Cement including 10 per cent wastage Sand including 10 per cent wastage Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement b) Labour Mate Mazdoor (Skilled) Mazdoor c) Machinery Grout pump with agitator and d) accessories charges @ input on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Page 2 of 363 hour 0.10 input #VALUE! M-111 #VALUE! #VALUE! day day day 0.08 0.10 0.10 kg kg 0.55 0.55 #VALUE! #VALUE! M081/100 0 #VALUE! #VALUE! M005/150 0 #VALUE! hour 0.10 input #VALUE! M-111 #VALUE! #VALUE! #VALUE! say #VALUE! day day day 0.08 0.10 0.10 350.00 250.00 180.00 kg 1.10 #VALUE! #VALUE! M081/100 0 #VALUE!

28.00 25.00 18.00

L-12 L-15 L-13

350.00 250.00 180.00

28.00 25.00 18.00

L-12 L-15 L-13

Ref. to Sr No MoRT H Spec. 16.6 2800

Description Rate per kg = (a+b+c+d+e) Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter, available in present formulations, to be applied as per instructions of manufacturer and as approved by the Unit = sqm Taking output = 10 sqm for an average thickness of 25mm. a) Labour Mate Mazdoor (Skilled) Mazdoor b) Material Pre-packed polymer concrete based on epoxy system complete with curing compound, intiator and promoter c) including 5 per cent wastage. Machinery Grout pump with agitator and d) accessories charges @ input on Overhead (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 10 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10 Note This item is a proprietory item available in market as pre-packed polymer concrete and is required to be applied as per instructions crack / porous concrete with Sealing of of the manufacturer. Epoxy Grout by injection through nipples complete as per clause 2803.1. Unit = kg Taking output = 1 kg a) b) Material Epoxy including 10 per cent wastage Labour Mate Mazdoor (Skilled) Mazdoor c) Machinery Epoxy Injection gun d) Overhead charges @ input on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Rate per kg = (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref. #VALUE!

say #VALUE!

day day day kg

0.06 0.75 0.75 315.00

350.00 250.00 180.00

21.00 187.50 135.00

L-12 L-15 L-13

input #VALUE! M-145

hour

2.00

input #VALUE! M-111 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.7 2803

kg day day day hour

1.10 0.08 0.10 0.10 0.10

input #VALUE! M-095 350.00 250.00 180.00 28.00 25.00 18.00 L-12 L-15 L-13 P&M078

input #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.8 2804

Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel reinforcement complete as per Technical Specification Unit = sqm Taking output = 10 sqm Assume average 10mm thickness of epoxy mortar a) Material Epoxy resin-hardener mix for prime coat Epoxy mortar Epoxy resin -hardener mix for seal coat. Add 3 per cent cost of material for other consumables like acetone etc and cover wastage. b) to Labour Mate day 0.04 350.00 kg kg kg 2.50 2.20 2.00 input #VALUE! M-098 input #VALUE! M-096 input #VALUE! M-098 #VALUE!

14.00

L-12

Page 3 of 363

Ref. to Sr No MoRT H Spec.

Description Mazdoor (Skilled) Mazdoor c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) sqm = a+b+c+d Cost for 10 Rate per sqm = (a+b+c+d)/10

Unit day day

Quantity 0.50 0.50

Rate Rs

Remark Cost Rs s/ Input ref. 250.00 125.00 L-15 180.00 90.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-13

16.9 2807

Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of unit: sqm Taking output = 10 sqm, 40 mm average thickness. a) Labour Mate Mazdoor Mazdoor (Skilled) b) Machinery Air compressor 250 cfm Shotcreteing equipment water tanker 6 KL capacity c) Material Cement Sand Coarse aggregate of size 4.75mm Quick setting compound Water d) Overhead charges @ input on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 10 sqm = a+b+c+d+e Rate per sqm = (a+b+c+d+e)/10 kg cum cum kg KL 120.00 0.15 0.15 2.50 0.10 #VALUE! #VALUE! hour hour hour 1.00 1.00 0.02 285.00 300.00 285.00 6.00 input #VALUE! P&M001 P&M076 P&M060 day day day 0.04 0.50 0.50 350.00 180.00 250.00 14.00 90.00 125.00 L-12 L-13 L-15

M081/100 0 input #VALUE! M-005 input #VALUE! M-024 input #VALUE! M-147 input #VALUE! M-189 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.1 2800 0

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled concrete Unit = sqm Taking output = 10 sqm Assumed thickness - 10 mm a) Material Acrylic polymer bonding coat pre-packed cement based polymer mortar of strength 45 Mpa at 28 days Add 3 per cent of (a ) above for b) wastage. Labour Mate Mazdoor (Skilled) Mazdoor c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for 10 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/10 Litre kg 1.40 12.00 input #VALUE! M-057 input #VALUE! M-145 #VALUE! day day day 0.04 0.50 0.50 350.00 250.00 180.00 14.00 125.00 90.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! Page 4 of 363 L-12 L-15 L-13

Ref. to Sr No MoRT H 2805 16.1 Spec. 1

Description Eproxy bonding of new concrete to old concrete Unit = sqm Taking output = 10 sqm a) Material Epoxy resin with pot life not less than 60-90 minutes and satisfying testing as Addper clause 2803.9 above for wastage. 3 per cent of (a ) b) Labour Mate Mazdoor (Skilled) Mazdoor c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) sqm = a+b+c+d Cost for 10 Rate per sqm = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

kg

8.00

input #VALUE! M-098 #VALUE!

day day day

0.04 0.50 0.50

350.00 250.00 180.00

14.00 125.00 90.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-15 L-13

say #VALUE! 16.1 2810 2 Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete m per drawing and Span assumed: 25 as No. of cables: 4 no. No. of anchorages : 8 no. Unit = MT Taking output = 1 MT Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42 kg/m of cable. a) Material HTS strand including 5 per cent wastage and extra length for jacking HDPE pipes 75mm dia including 5 per cent wastage Cement for grouting Tube anchorage set complete with bearing plate, permanent wedges etc Epoxy MS plates for deviator (where deviator blocks are not provided) Add 20 per cent cost of material for other materials like lead sheet, sleeves, b) deviator fixtures etc. Labour i) For making holes in the structure . Mate Mazdoor Semi-skilled) Mazdoor ii) For making and fixing anchorages for cables and placement of cables . Mate Blacksmith Mazdoor iii) For prestressing Mate/Supervisor Fitter Mazdoor iv) For grouting Mate/Supervisor Mason Mazdoor c) Machinery day day day 0.13 0.70 2.65 350.00 250.00 180.00 45.50 175.00 477.00 L-12 L-11 L-13 day day day 0.13 0.70 2.65 350.00 250.00 180.00 45.50 175.00 477.00 L-12 L-08 L-13 day day day 0.24 3.00 3.00 350.00 180.00 180.00 84.00 540.00 540.00 L-12 L-14 L-13 tonne metre kg each kg tonne 1.05 112.00 400.00 8.00 6.00 2.10 input #VALUE! M-119 input #VALUE! M-114 #VALUE! #VALUE! M081/100 0 input #VALUE! M-187 input #VALUE! M-095 input #VALUE! M-179 #VALUE!

day day day

0.44 3.00 8.00

350.00 250.00 180.00

154.00 750.00 1440.00

L-12 L-02 L-13

Page 5 of 363

Ref. to Sr No MoRT H Spec.

Description Stressing jack with pump Grouting pump with agitator d) Overhead charges @ input on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) = (a+b+c+d+e) Rate per MT

Unit hour hour

Quantity 4.00 1.35

Rate Rs

Remark Cost Rs s/ Input ref. 91.00 364.00 P&M040 input #VALUE! M-111 #VALUE! #VALUE! #VALUE! say #VALUE!

16.1 2810 3

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete m per drawing and Span assumed: 50 as No. of cables: 4 no. No. of anchorages : 8 no. Unit = MT Taking output = 3.10 MT Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable. a) Material HTS strand including 5 per cent wastage and extra length for jacking HDPE pipes 90mm dia including 5 per cent wastage Cement for grouting Tube anchorage set complete with bearing plate, permanent wedges etc Epoxy MS plates for deviator (where deviator blocks are not provided) Add 20 per cent cost of material for other materials like lead sheet, sleeves, b) deviator fixtures etc. Labour i) For making holes in the structure . Mate Mazdoor Semi-skilled) Mazdoor ii) For making and fixing anchorages for cables and placement of cables . Mate Blacksmith Mazdoor iii) For prestressing Mate/Supervisor Fitter Mazdoor iv) For grouting Mate/Supervisor Mason Mazdoor c) Machinery Stressing jack with pump Grouting pump with agitator d) Overhead charges @ input on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 3.10 MT = a+b+c+d+e Rate per MT = (a+b+c+d+e)/3.10 hour hour 7.00 3.00 91.00 637.00 P&M040 input #VALUE! M-111 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! day day day 0.26 1.50 5.00 350.00 250.00 180.00 91.00 375.00 900.00 L-12 L-11 L-13 day day day 0.20 1.00 4.00 350.00 250.00 180.00 70.00 250.00 720.00 L-12 L-08 L-13 day day day 0.08 8.00 8.00 350.00 180.00 180.00 28.00 1440.00 1440.00 L-12 L-14 L-13 tonne metre tonne each kg tonne 3.10 224.00 1.01 8.00 10.00 7.00 input #VALUE! M-119 input #VALUE! M-115 input #VALUE! M-081 input #VALUE! M-187 input #VALUE! M-095 input #VALUE! M-179 #VALUE!

day day day

1.28 7.00 25.00

350.00 250.00 180.00

448.00 1750.00 4500.00

L-12 L-02 L-13

Page 6 of 363

Ref. to Sr No MoRT H 16.1 Spec. 2810 4

Description Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Span assumed: 100 m No. of cables: 6 no. No. of anchorages : 12 no. Unit = MT Taking output = 9.28 MT Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable. a) Material HTS strand including 5 per cent wastage and extra length for jacking HDPE pipes 90 mm dia including 5 per cent wastage Cement for grouting Tube anchorage set complete with bearing plate, permanent wedges etc Epoxy MS plates for deviator (where deviator blocks are not provided) Add 20 per cent cost of material for other materials like lead sheet, sleeves, b) deviator fixtures etc. Labour i) For making holes in the structure . Mate Mazdoor Semi-skilled) Mazdoor ii) For making and fixing anchorages for cables and placement of cables . Mate Blacksmith Mazdoor iii) For prestressing Mate/Supervisor Fitter Mazdoor iv) For grouting Mate/Supervisor Mason Mazdoor c) Machinery Stressing jack with pump Grouting pump with agitator d) Overhead charges @ input on (a+b+c) e) Contractor's profit @ 10% on (a+b+c+d) Cost for 9.28 MT = a+b+c+d+e Rate per MT = (a+b+c+d+e)/9.28

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

tonne metre tonne each kg tonne

9.28 672.00 3.04 12.00 14.00 20.00

input #VALUE! M-119 input #VALUE! M-115 input #VALUE! M-081 input #VALUE! M-187 input #VALUE! M-095 input #VALUE! M-179 #VALUE!

day day day

1.72 18.00 25.00

350.00 180.00 180.00

602.00 3240.00 4500.00

L-12 L-14 L-13

day day day day day day day day day hour hour

4.00 20.00 80.00 0.30 1.50 6.00 1.00 5.00 20.00 10.00 10.00

350.00 250.00

1400.00 5000.00

L-12 L-02 L-13 L-12 L-08 L-13 L-12 L-11 L-13

180.00 14400.00 350.00 250.00 180.00 350.00 250.00 180.00 91.00 105.00 375.00 1080.00 350.00 1250.00 3600.00

910.00 P&M040 input #VALUE! M-111 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.1 2808 5

Replacement of Bearings complete as per Technical Specification Unit = No Taking output = 3 No. Lifting of superstructure span by jacking up from below i.e. by placing the jacks on pier/abutment caps for span length of 30m. a) Lifting of span i) Hire charges for jack of 40 tonne lifting capacity. Mate Day day 3.00 0.64 input #VALUE! 350.00 224.00 P&M084 L-12

Page 7 of 363

Ref. to Sr No MoRT H Spec.

Description Mazdoor (Skilled) Mazdoor v) Wooden packing b) Replacement of bearing Cost of bearing. c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost of repair of 3 bearings = a+b+c+d Rate of repair per bearing = (a+b+c+d)/3

Unit day day cum each

Quantity 4.00 12.00 0.15 3.00

Rate Rs

Remark Cost Rs s/ Input ref. 250.00 1000.00 L-15 180.00 2160.00 L-13 input #VALUE! M-195 input #VALUE! M-065 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

Note 16.1 2808 6

The work entails replacement of all the bearings on one side of the span. Rectification of Bearings as per Technical Specifications Unit = 1 No Taking output = 3 No. a) Lifting of superstructure span by jacking up from below i.e. by placing the jacks on pier/abutment caps for span Hire charges for jack of 40 tonne i) length of 30m. lifting capacity. ii) Mate iii) Mazdoor (Skilled) iv) Mazdoor v) Wooden packing b) Cost of parts to be replaced for 3 bearings. c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost of repair of 3 bearings = a+b+c+d Rate of repair per bearing = (a+b+c+d)/3 Note The rectification of 3 bearings included in this analysis are on the same side of the span. Replacement of Expansion Joints complete as per drawings Unit -1 RM Taking output = 12 RM a) Material Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i) b) Labour Removal of old expansion joint including breaking of concrete, cutting of lugs and shifting of broken material etc. Mate Mazdoor Mazdoor (Skilled) c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost for replacement of 12 RM = a+b+c+d Rate per RM = (a+b+c+d)/12 Note The rate for the installation of new expansion joints may be taken from the chapter on superstructure. Broken concrete will have to be replaced which has been included in this analysis. Replacement of Damaged Concrete Railing. Unit = RM Taking output = 10 RM a) Labour kg cum 9.60 3.60 input #VALUE! M-095 #VALUE! #VALUE! Item 14.1(C)

each day day day cum each

3.00 0.64 4.00 12.00 0.15 3.00

input #VALUE! 350.00 250.00 180.00 224.00 1000.00 2160.00

P&M084 L-12 L-15 L-13

input #VALUE! M-195 input #VALUE! M-064 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.1 7

day day day

0.26 6.00 0.50

350.00 180.00 250.00

91.00 1080.00 125.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13 L-15

say #VALUE!

16.1 8

Page 8 of 363

Ref. to Sr No MoRT H Spec.

Description Labour for dismantling old railing disposal of dismantled material. Mate Mazdoor b) Machinery Tractor-trolley for disposal of c) dismantled material Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 Note The rate for the provision of new railing may be adopted from the chapter on superstructure. of Crash Barrier. Replacement Unit = RM Taking output = 10 M a) Labour Labour for dismantling old railing disposal of dismantled material. Mate Mazdoor b) Machinery Tractor-trolley for disposal of c) dismantled material Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 Note The rate for the construction of new crash barrier may be adopted from chapter 8 on Traffic and Transportation. Replacement of Damaged Mild Steel RailingRM Unit = Taking output = 10 M a) Labour Labour for dismantling old railing disposal of dismantled material. Mate Mazdoor b) Machinery Tractor-trolley for disposal of c) dismantled material Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) m = a+b+c+d Cost for 10 Rate per metre = (a+b+c+d)/10 and and and

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

day day hour

0.20 5.00 1.00

350.00 180.00 300.00

70.00 900.00 300.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13 P&M053

say #VALUE!

16.1 9

day day hour

0.40 10.00 1.00

350.00 180.00 300.00

140.00 1800.00 300.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13 P&M053

say #VALUE!

16.2 0

day day hour

0.16 4.00 1.00

350.00 180.00 300.00

56.00 720.00 300.00 #VALUE! #VALUE! #VALUE! #VALUE!

L-12 L-13 P&M053

say #VALUE! 16.2 1 Repair of Crash Barrier Repair of concrete crash barrier with cement concert of M-30 grade by cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired thoroughly, applying cement concert Running meter.proper form work. Unit = after erection of Taking output = 10 M. It is assumed that damage is to the extent of 10 per cent of the volume of concrete .This will require 0.30 cum of concrete. a) Manpower* Mate Mazdoor day day 0.04 1.00 350.00 180.00 14.00 180.00 L-12 L-13

Page 9 of 363

Ref. to Sr No MoRT H Spec.

Description * For dismantling and trimming the surface to a regular shape and removal of damaged material. b) Material M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i) This may be priced based on the rate given the chapter of superstructure. c) Overhead charges @ input on (a) d) Contractor's profit @ 10% on (a+c) 10 m = a+b+c+d Cost for Rate per m = (a+b+c+d)/10

Unit

Quantity

Rate Rs

Remark Cost Rs s/ Input ref.

cum

0.30

#VALUE! #VALUE!

Item 14.1(C)

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.2 2

Repair of RCC Railing Carrying out repair of RCC M30 railing to bring it to the original shape. Unit = Running meter. Taking output = 10 M. It is assumed that damage is to the extent of 10 per cent . a) Material M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i) HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP) b) Labour* Mate mazdoor * For dismantling and trimming the surface to a regular shape and removal of damaged material. c) Overhead charges @ input on (b) d) Contractor's profit @ 10% on (b+c) Cost for 10 m = a+b+c+d Rate per m = (a+b+c+d)/10 cum tonne 0.10 0.01 #VALUE! #VALUE! Item 14.1(C) #VALUE! #VALUE! Item 14.2 A 350.00 180.00 5.60 36.00 L-12 L-13

day day

0.016 0.20

#VALUE! #VALUE! #VALUE! #VALUE! say #VALUE!

16.2 3

Repair of Steel Railing Repair of steel railing to bring it to the original shape It is assumed that the damage to the steel railing is to the extent of 10 per cent . Unit = Running meter. Taking output = 10 M. a) Material Mild steel ISMC series Flat iron MS Bolt and nuts Add 5 per cent of cost of material for b) painting. Labour Mate Mazdoor (Skilled) Mazdoor c) Overhead charges @ input on (a+b) Contractor's profit @ 10% on d) (a+b+c) Cost of repair for10m = a+b+c+d Cost of meter = (a+b+c+d)/10 day day day 0.016 0.20 0.20 350.00 250.00 180.00 kg kg kg 29.00 10.00 1.00 #VALUE! #VALUE! M179/100 0 #VALUE! #VALUE! M179/100 0 input #VALUE! M-130 #VALUE! 5.60 50.00 36.00 #VALUE! #VALUE! #VALUE! #VALUE! say #VALUE! L-12 L-15 L-13

Page 10 of 363

Você também pode gostar