III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)
1. How do you find the quantity of masonry work in a semi-circular arch. [16]
2. Calculate the rate for water proof cement painting in two coats on plastered surface.
[16]
4. Calculate the quantities of the following items for the building shown in figure 4
using centre line method
1 of 3
Code No: R05320105 Set No. 1
Figure 4
2 of 3
Code No: R05320105 Set No. 1
⋆⋆⋆⋆⋆
3 of 3
Code No: R05320105 Set No. 2
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)
2. Write about
3. (a) Write technical specifications for earthwork in soft soil and timber door in
Teak
(b) Write specifications for workmanship in RCC and steel structural work. [16]
4. Calculate the quantities of the following items for the building shown in figure 4
1 of 2
Code No: R05320105 Set No. 2
Figure 4
(a) Brick work in CM (1:6) in foundation
(b) 10 mm thick Damp proof course.
(c) OBD inside the rooms
(d) Water proof painting for outside the building. [48]
⋆⋆⋆⋆⋆
2 of 2
Code No: R05320105 Set No. 3
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)
1. Estimate the quantities of earthwork required for 240m length of road in a tabular
form using standard prismoidal formula from the following Data
Chainage R.L of ground R.L of Formation
0 113.00 ↑
30 112.80
60 112.70
90 112.60 113.70 level
120 112.50
150 112.40
180 112.30
210 112.40
240 112.50 ↓
The formation width of the road is 10 metre and the side slopes are 2:1 (2 horizontal:
1 Vertical). [16]
2. Write about
4. Calculate the quantities of the following items for the building shown in figure 4
using centre line method
1 of 2
Code No: R05320105 Set No. 3
Figure 4
⋆⋆⋆⋆⋆
2 of 2
Code No: R05320105 Set No. 4
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)
2. Calculate the rate for 50 cum of 1st class brick work in CM (1:3) in F Floor. [16]
4. Calculate the quantities of the following items for the building shown in figure 4
using long wall short wall method.
1 of 3
Code No: R05320105 Set No. 4
Figure 4
(a) Brick masonry in CM (1:6) for super structure
(b) 20mm thick plastering outside the building
(c) 12 mm thick plastering in side the building
(d) Plain cement concrete (1:5:10) for flooring bed. [48]
2 of 3
Code No: R05320105 Set No. 4
⋆⋆⋆⋆⋆
3 of 3