Code No: R05320105 Set No.

1
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)

1. How do you find the quantity of masonry work in a semi-circular arch. [16]

2. Calculate the rate for water proof cement painting in two coats on plastered surface.
[16]

3. Write short notes on:

(a) Scope of Contract


(b) Sufficiency of tender
(c) Interim Payments
(d) Arbitration. [16]

PART-B (Marks:48 marks)

4. Calculate the quantities of the following items for the building shown in figure 4
using centre line method

1 of 3
Code No: R05320105 Set No. 1

Figure 4

(a) Earth work excavation


(b) PCC ( 1 : 5 : 10 ) below the plinth.
(c) CRS masonry below the plinth
(d) Brick masonry in CM (1:6) for super structure. [48]

2 of 3
Code No: R05320105 Set No. 1
⋆⋆⋆⋆⋆

3 of 3
Code No: R05320105 Set No. 2
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)

1. Explain centre line method. [16]

2. Write about

(a) Gross income


(b) Net income and
(c) Out goings [16]

3. (a) Write technical specifications for earthwork in soft soil and timber door in
Teak
(b) Write specifications for workmanship in RCC and steel structural work. [16]

PART-B (Marks:48 marks)

4. Calculate the quantities of the following items for the building shown in figure 4

1 of 2
Code No: R05320105 Set No. 2

Figure 4
(a) Brick work in CM (1:6) in foundation
(b) 10 mm thick Damp proof course.
(c) OBD inside the rooms
(d) Water proof painting for outside the building. [48]

⋆⋆⋆⋆⋆

2 of 2
Code No: R05320105 Set No. 3
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)

1. Estimate the quantities of earthwork required for 240m length of road in a tabular
form using standard prismoidal formula from the following Data
Chainage R.L of ground R.L of Formation
0 113.00 ↑
30 112.80
60 112.70
90 112.60 113.70 level
120 112.50
150 112.40
180 112.30
210 112.40
240 112.50 ↓

The formation width of the road is 10 metre and the side slopes are 2:1 (2 horizontal:
1 Vertical). [16]

2. Write about

(a) Capital Cost and


(b) Capitalized Value. [16]

3. Write the detailed specifications of cement concrete 1:2:4 M15 . [16]

PART-B (Marks:48 marks)

4. Calculate the quantities of the following items for the building shown in figure 4
using centre line method

1 of 2
Code No: R05320105 Set No. 3

Figure 4

(a) Earth work in excavation


(b) PCC ( 1 : 5 : 10 ) below the foundation.
(c) CRS masonry below the plinth
(d) Brick masonry in CM (1:6) for super structure. [48]

⋆⋆⋆⋆⋆

2 of 2
Code No: R05320105 Set No. 4
III B.Tech II Semester Supplimentary Examinations, Aug/Sep 2008
ESTIMATING QUANTITY SURVEY AND VALUATION
(Civil Engineering)
Time: 3 hours Max Marks: 80
Note: Answer any TWO Questions from PART-A
PART-B is compulsory
⋆⋆⋆⋆⋆
PART-A (Marks:32)

1. Explain long wall and short wall method. [16]

2. Calculate the rate for 50 cum of 1st class brick work in CM (1:3) in F Floor. [16]

3. Write specifications for the following items of work:

(a) Plastering of walls in CM (1:4) 20mm thick, 2 coats


(b) Brick masonry in CM 1:5 for superstructure. [16]

PART-B (Marks:48 marks)

4. Calculate the quantities of the following items for the building shown in figure 4
using long wall short wall method.

1 of 3
Code No: R05320105 Set No. 4

Figure 4
(a) Brick masonry in CM (1:6) for super structure
(b) 20mm thick plastering outside the building
(c) 12 mm thick plastering in side the building
(d) Plain cement concrete (1:5:10) for flooring bed. [48]