TABLAS DE CONCRETOS NORMAL Y RESISTENCIA

-COSTO Y TIEMPO EN LAS OBRAS- ING. CARLOS SUAREZ SALAZAR 3ERA EDICION DE 2002

CLASIFICACION AGREGADO CEMENTO AREANA GRAVA AGUA M3


MAXIMO TON M3 M3

F'c REVENIMIENTO
100 KG/CM2 8 A 10 CM. 3/4" 0.26 0.5 0.68 0.195
1 1/2" 0.254 0.47 0.7 0.19
12 A 15 CM. 3/4" 0.286 0.5 0.68 0.215
1 1/2" 0.28 0.47 0.7 0.21

150 KG/CM2 8 A 10 CM. 3/4" 0.323 0.48 0.67 0.21


1 1/2" 0.308 0.45 0.7 0.2
12 A 15 CM. 3/4" 0.354 0.48 0.67 0.23
1 1/2" 0.338 0.45 0.7 0.22

200 KG/CM2 8 A 10 CM. 3/4" 0.355 0.47 0.65 0.195


1 1/2" 0.337 0.44 0.68 0.185
12 A 15 CM. 3/4" 0.391 0.47 0.65 0.215
1 1/2" 0.373 0.44 0.68 0.205

250 KG/CM2 8 A 10 CM. 3/4" 0.423 0.465 0.64 0.19


1 1/2" 0.4 0.435 0.67 0.18
12 A 15 CM. 3/4" 0.467 0.465 0.64 0.21
1 1/2" 0.445 0.435 0.67 0.2
TABLAS DE MORTEROS
DOSIFICAION Y PROPORCIONAMIENTO PARA FABRICAION DE CONCRETO
MANUAL TECNICO DE CONSTRUCCION APASCO

TAM= 19 MM

CONCRETO CEMENTO BULTO ARENA BOTE GRAVA BOTE AGUA BOTE

100 KG/CM2 1 7.5 8 3

150 KG/CM2 1 5.5 6.5 2.5

200 KG/CM2 1 4 6 2

250 KG/CM2 1 3.5 5 1.75

300 KG/CM2 1 2.5 4.5 1.25

1 BOTE= 19 LITROS
1 BULTO= 50KG

TAM= 40 MM

CONCRETO CEMENTO BULTO ARENA BOTE GRAVA BOTE AGUA BOTE

100 KG/CM2 1 7.5 9.5 3

150 KG/CM2 1 5.5 8.5 2.5

200 KG/CM2 1 4 7.5 2

250 KG/CM2 1 3.5 6.5 1.75

300 KG/CM2 1 2.5 5.5 1.25

1 BOTE= 19 LITROS
1 BULTO= 50KG
DOSIFICAION Y PROPORCIONAMIENTO PARA FABRICAION DE CONCRETO
MANUAL TECNICO DE CONSTRUCCION APASCO

PROPORCIONAMIENTO PARA 1 M3 DE CONCRETO TAM= 19 MM

CONCRETO CEMENTO ARENA GRAVA AGUA CONCRETO CEMENTO ARENA M3 GRAVA AGUA Σ DE
BULTO BOTE BOTE BOTE BULTO M3 M3 M3

100 KG/CM2 1 7.5 8 3 100 KG/CM2 1 0.1425 0.152 0.057 0.35

150 KG/CM2 1 5.5 6.5 2.5 150 KG/CM2 1 0.1045 0.1235 0.0475 0.28

200 KG/CM2 1 4 6 2 200 KG/CM2 1 0.076 0.114 0.038 0.23

250 KG/CM2 1 3.5 5 1.75 250 KG/CM2 1 0.0665 0.095 0.0333 0.19

300 KG/CM2 1 2.5 4.5 1.25 300 KG/CM2 1 0.0475 0.0855 0.0238 0.16

1 BOTE= 19 LITROS
1 BULTO= 50KG

CEMENTO ARENA M3 GRAVA M3 AGUA CEMENTO ARENA M3 GRAVA AGUA


CONCRETO CONCRETO
BULTO M3 TON M3 M3

100 KG/CM2 2.84495 0.40541 0.43243 0.16216 100 KG/CM2 0.14225 0.40541 0.43243 0.1622

150 KG/CM2 3.62976 0.37931 0.44828 0.17241 150 KG/CM2 0.18149 0.37931 0.44828 0.1724

200 KG/CM2 4.38596 0.33333 0.5 0.16667 200 KG/CM2 0.2193 0.33333 0.5 0.1667

250 KG/CM2 5.13479 0.34146 0.4878 0.17073 250 KG/CM2 0.25674 0.34146 0.4878 0.1707

300 KG/CM2 6.37959 0.30303 0.54545 0.15152 300 KG/CM2 0.31898 0.30303 0.54545 0.1515
DOSIFICAION Y PROPORCIONAMIENTO PARA FABRICAION DE CONCRETO
MANUAL TECNICO DE CONSTRUCCION APASCO

PROPORCIONAMIENTO PARA 1 M3 DE CONCRETO TAM= 40MM

CONCRETO CEMENTO ARENA GRAVA AGUA CONCRETO CEMENTO ARENA GRAVA AGUA Σ DE M3
BULTO BOTE BOTE BOTE BULTO M3 M3 M3

100 KG/CM2 1 7.5 9.5 3 100 KG/CM2 1 0.1425 0.1805 0.057 0.38

150 KG/CM2 1 5.5 8.5 2.5 150 KG/CM2 1 0.1045 0.1615 0.0475 0.314

200 KG/CM2 1 4 7.5 2 200 KG/CM2 1 0.076 0.1425 0.038 0.257

250 KG/CM2 1 3.5 6.5 1.75 250 KG/CM2 1 0.0665 0.1235 0.03325 0.223

300 KG/CM2 1 2.5 5.5 1.25 300 KG/CM2 1 0.0475 0.1045 0.02375 0.176

1 BOTE= 19 LITROS
1 BULTO= 50KG

CEMENTO ARENA GRAVA AGUA CEMENTO ARENA GRAVA AGUA


CONCRETO CONCRETO
BULTO M3 M3 M3 TON M3 M3 M3

100 KG/CM2 2.63158 0.375 0.475 0.15 100 KG/CM2 0.13158 0.375 0.475 0.15

150 KG/CM2 3.18979 0.3333 0.5152 0.15152 150 KG/CM2 0.15949 0.3333 0.5152 0.15152

200 KG/CM2 3.89864 0.2963 0.5556 0.14815 200 KG/CM2 0.19493 0.2963 0.5556 0.14815

250 KG/CM2 4.47928 0.2979 0.5532 0.14894 250 KG/CM2 0.22396 0.2979 0.5532 0.14894

300 KG/CM2 5.6899 0.2703 0.5946 0.13514 300 KG/CM2 0.2845 0.2703 0.5946 0.13514
DOSIFICACION PARA MORTEROS PARA FABRICAR 1 M3 DE MEZCLA

MORTERO: MORTERO MAESTRO-ARENA


DOSIFICACION MORTERO (TON) ARENA (M3) AGUA (M3)
1A4 0.3 1.15 0.29
1A5 0.26 1.2 0.285
1A6 0.225 1.24 0.28

MORTERO: CEMENTO-ARENA
DOSIFICACION CEMENTO (TON) ARENA (M3) AGUA (M3)
1A2 0.6 1 0.275
1A3 0.51 1.05 0.272
1A4 0.43 1.1 0.266
1A5 0.36 1.15 0.261
1A6 0.3 1.17 0.257