Você está na página 1de 258

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

PRELIMINARY FEASIBILITY REPORT NABA H. E. PROJECT


(4 x 250 MW)

TABLE OF CONTENTS

CHAPTER I II III IV V VI VII VIII IX X XI XII XIII

TITLE EXECUTIVE SUMMARY BACKGROUND INFORMATION PROJECT AREA TOPOGRAPHIC & GEO- TECHNICAL ASPECTS HYDROLOGY CONCEPTUAL LAYOUT & PLANNING POWER POTENTIAL STUDIES POWER EVACUATION ENVIRONMENTAL ASPECTS INFRASTRUCTURE CONSTRUCTION PLANNING & SCHEDULE COST ESTIMATES ECONOMIC EVALUATION PLATES ANNEXURES
(i)

PAGE 1-11 12-19 20-25 26-32 33-49 50-63 64-92 93-94 95-107 108-111 112-118 119-147 148-155 156-171 172-251

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

LIST OF TABLES
CHAPTER II TABLE NO 2.1 2.2 III IV V 3.1 4.1 5.1 5.2 5.3 VII 7.1 7.2 7.3 7.3A 7.4 7.5 IX 9.1 9.2 X XI XIII 10.1 11.1 13.1 13.2 13.2 A 13.3 13.3 A TITLE Power Supply Position of North Eastern Region Power Supply Position of All India Circle wise number of villages, household and population in Upper Subansiri District as per 1991 Census Generalised Geological Succession Data Availability status Average Monthly Rainfall Near Naba HE Project Flood Peaks Computed by various methods 10- daily Discharge Data 90% Dependable Year Flows for Power Generation Summary Sheet Availability of Units in KWH/KW for Incremental Installation in 90% Dependable Year Power Potential in 90% Dependable Year with 95% m/c availability Power Potential in 90% Dependable Year Landuse-landcover Information within the Submergence Area Landuse-landcover Information within the 7 Km Radius from the Dam site at Naba Status of Road Network connecting Project site Construction Schedule IDC Calculation at Present Day Cost Unit Cost of Energy at Bus Bar at Current Price Level with 12 % Free Power to Home State Unit Cost of Energy at Bus Bar at Current Price Level without Free Power to Home State Calculation of Energy Rate with Present Cost with 12 % Free Power to Home State Calculation of Energy Rate with Present Cost without Free Power to Home State
(ii)

PAGE 18 19 23 27 40 40 46 69 70 71 72 73 74 99 100 109 118 151 152 153 154 155

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

LIST OF PLATES

CHAPTER II

PLATE NO 2.1 2.2

TITLE Proposed Cascade Development Over River Subansiri Vicinity Map Geological Plan Geological X- section near Dam site Catchment Plan of Subansiri Basin showing Raingauge stations and G&D sites Catchment Plan of Subansiri Upper Basin upto Damsite of Naba General Layout Plan General Layout- L-Section Layout Plan- Dam area Dam- Upstream Elevation Dam- Cross Section Water Conductor System- Typical Cross Section Layout Plan- Power House Area Power House- Cross Section Single Line Diagram Power Evacuation Subansiri Basin- Power Evacuation System

PAGE 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171

IV V

4.1 4.2 5.1 5.2

VI

6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8

VIII

8.1 8.2

(iii)

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

LIST OF FIGURES

CHAPTER V

FIG NO 5.1

TITLE Reservoir elevation-area-capacity curve

PAGE 49

LIST OF ANNEXURES

CHAPTER I II

ANNEXURE 1.1 2.1 2.2 2.3 2.4 Salient Features

TITLE

PAGE 172 175 177 180 183 188 197 198 199

IV V

4.1 5.1A 5.1B 5.1C

Excerpts from CEAs reassessment study report Record note of discussion with CEA regarding vetting of Layout (dated 09.10.2003) Record note of discussion with CEA regarding vetting of Layout (dated 03.12.2003) Comments of HP&I Division, CEA vide letter No.7/9/NHPC/HP&I/2004/217 dt.06.02.2004 and reply of NHPC Preliminary Appraisal for PFR by GSI, New Delhi Monthly Rainfall (mm) at Taliha Monthly Rainfall (mm) at Siyum Monthly Rainfall (mm) at Limeking

(iv)

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

5.2 5.3 VI 6.1 6.2 VII 7.1

Average 10-Daily Flow at Dam site Observation of CWC Received vide letter No.7/9/NHPC/2003/HPI/188 dt 03.02.2004 and Reply of NHPC Comments of CMDD Division, CEA vide letter No.7/9/NHPC/2003/HPI/669-670 dt.01.04.2004 and reply of NHPC Comments of HCD(E&NE) Division, CEA vide letter No.3/5/2000-HCD(E&NE)/866 dt.07.04.2004 and reply of NHPC Comments of SP&PA Division, CEA vide letter No.7/9/NHPC/2003/HP&I/320 dt.13.02.2004 and reply of NHPC Comments of SP&PA Division on Cost Aspects, CEA vide letter No.7/9/NHPC/2003/HP&I/790 dt.15.04.2004 and reply of NHPC Report from NRSA, Hyderabad on satellite remote sensing based inputs for initial environmental studies for Naba project site Excerpts From Preliminary Floristic Report From Botanical Survey India, Itanagar Brief Report on Faunal Diversity From Zoological Survey India, Itanagar Report of Fishery Department, Govt of Arunachal Pradesh

200 202 212 216 218

7.2

226

IX

9.1 9.2 9.3 9.4

230 246 248 251

(v)

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER I EXECUTIVE SUMMARY


1.0 INTRODUCTION
Naba H.E. Project is located in remote area of Upper Subansiri District of Arunachal Pradesh. This project envisages utilisation of water of river Subansiri (called Si Ngit in upper reaches). Subansiri is the tributary of river Brahmaputra. Three scheme viz.,

Subansiri lower (2000 MW), Subansiri Middle (1600MW) and Subansiri Upper (2000MW) have been planned to harness power potential of river Subansiri. CEA has identified eight additional projects totalling about 7900 MW in Subansiri Basin (Arunachal Pradesh) in their ranking studies, as a part of exercise for development of balance hydroelectric potential in the country and accorded priority for preparation of Preliminary Feasibility Report (PFR) so that these could be taken up for preparation of Detailed Project Report (DPR) and further development during the XI and XII Five Year Plans. The Naba H.E. Project is one of the new additions. CEAs reassessment study report envisaged construction of diversion dam at location down stream of the power house of Niare H.E. Project and carry water through a 11.5 km long open channel to a power house with installed capacity of 1290 MW. Based on Topographical, Geological and Hydrometeorology study of the area, a few modifications have been made in the layout of the project. The dam site location as proposed by CEA at river bed level EL 1000m is shifted about 3.3 km downstream near Badok village , where river has

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

carved out narrow U shaped valley with rocky abutments on both flanks and river bed is EL + 945 m. Power house location is retained at same location ( CEA proposal) with tail race outfall at river bed level EL 770 m instead of EL 800 m as proposed by CEA . Based on topography, geology of the area and presence of loops in river, 9.75/9.80 km long head race tunnel is adopted as water conductor system instead of power channel. Installed capacity of this project would be 1000 MW (4X 250MW). 1.1 GENERAL PROJECT FEATURES The Naba HE Project envisages construction of

>

River diversion works comprising of 2 nos of

10.5 m diameter

horseshoe shaped diversion tunnels with u/s and d/s cofferdams.


>

A 110 m high concrete gravity dam from deepest foundation level to provide a gross storage of 31.9 Mcum at FRL (EL 1035 m) and a storage of 23.9 Mcum at MDDL (EL 1022 m ).

> Spillway comprising of (a) low level orifice spillway - 7 nos of opening size 8.25 m X 10 m with crest elevation at EL 990 m and elevation at EL 1025 m. > 6 nos of Desilting chambers of size 300m (L) x 16m (W) x 23 m (H) to remove silt particle of size 0.2mm and above. > 2 nos 9.75 / 9.80 km long 8.7 m diameter horseshoe shaped headrace tunnels. > 2 nos 110 m high 23 m diameter surge shaft. > 2 nos 7.25 m diameter steel lined pressure shafts (vertical height 181 m). (b) upper level crest type spillway - 2 nos of opening size 8 m X 10 m with crest

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

>

An underground power house cavern having overall size 136 m (L) X 23 m (W) X 48 m (H) with 4 units of 250 MW each

> 2 nos 100 m long, 8.7 m diameter horseshoe shaped tailrace tunnels. The power generated from the project will be evacuated at 400 KV level and will be pooled at Daporijo through one double circuit transmission line. Daporijo pooling point will be ultimately linked through HVDC line to the National Grid. The salient features of the project are as under :

SALIENT FEATURES

LOCATION State District River Dam site Nearest BG rail head Nearest airport HYDROLOGY Catchment area Location of catchment Latitude Longitude Average annual rainfall : : : 27o00 N to 28o22 N 91o45' E to 93o34' E 2825 mm 14300 sq.km. : : : : : : Arunachal Pradesh Upper Subansiri Subansiri/Si Ngit Near Badok/Doloring village Nagaon (Assam) Lilabari (Assam)

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

RESERVOIR Full reservoir level(FRL) Min. Draw Down Level (MDDL) Gross storage -at FRL -at MDDL Area under submergence at FRL DIVERSION TUNNEL Number Size Shape Length Diversion capacity (assumed) U/s coffer dam D/s coffer dam : : : : : : : 2 10.50 m Horse shoe 700 m each 2500 cumec 25 m 14 m : : : 31.9 mcm 23.9 mcm 81.28 ha : : 1035 m 1022 m

DAM Type Top elevation of dam Height of dam above deepest foundation level Length of dam at top River Bed level : : : : Concrete 1040 m 110 m 245 m 945 m

SPILLWAY Design flood : 12000 cumec

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Lower spillway Crest elevation Type Number Size of opening Upper spillway Crest elevation Type Number Size of opening Energy dissipation Length of spillway INTAKE Invert level Number Size of gate opening Trash rack Intake tunnel size Intake tunnel length DESILTING CHAMBERS Number Size Length Design discharge per chamber Particle size to be removed : : : : : 6 16 x 23 m 300 m 100.4 cum 0.2 mm : : : : 1000 m 2 8.60 X 9.8 m 25 X 22 m 9.8 m 450/270 m : : : 1025 m Crest 2 8.0 X 10 m Ski jump with preformed plunge pool 142 m : 990 m Orifice 7 8.25 X 10 m

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

HEAD RACE TUNNEL Number Size Shape Length Design discharge per tunnel SURGE SHAFT Number Size Height PRESSURE SHAFT Number Size Vertical height POWER HOUSE Type Installed capacity Number of units Power house size Type of turbine C.L of turbine MIV cavern size : 100 (L)x 12 (W) x 16 (H) : : : : : : Underground 1000 MW 4(250 MW each) 136mX23mX48m Vertical Shaft Francis 765.5 m 2 7.25 m 181 m : : : 2 23 m 110 m : : : : : 2 8.7 m Horse shoe 9.75/9.80 km 251 cumec

TRANSFORMER CUM DRAFT TUBE GATE CAVERN size Draft tube opening for each unit : : 100 (L)x 20 (W) x 25 (H) m 4.2m (W) X 6m(H) 2 nos

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TAIL RACE TUNNEL Number Size Shape Length Design discharge per tunnel River Bed level at outfall Maximum TWL(Assumed) POTHEAD YARD Size POWER GENERATED Installed capacity Annual energy generation in 90% dependable year : 3995.25 MU : 1000 MW : 50m (W) X 100m(L) : : : : 2 8.7 m Horse Shoe 100 m 251.00 cumec 770 m 780 m

1.2

STUDIES/INVESTIGATIONS UNDERTAKEN Study of topographic maps and remote sensing imageries. Reconnaissance of area for identifying probable alternative sites of project components. Study of regional geotechnical features/ seismotectonic aspects. Geological appraisal of proposed project components. Water availability & design flood studies based on available meteorological / hydrological data.

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Conceptual layout and project planning. Power potential studies. Study of biotic environment, socio-economic environment for prediction of environmental impacts of the project. Study of existing infrastructure. Cost benefit and Economic evaluation. Geophysical investigations are not expected to provide reliable results because of steep topography. Accordingly, geophysical methods are not attempted. 1.3 RESULTS OF STUDIES AND INVESTIGATIONS

1.3.1 Geology The entire project is located in biotite gneiss rocks of Gelensiniak Formation. These are hard jointed metamorphic rocks. The dam site has been chosen in a relatively straight reach of the river where rocks are exposed on both the banks of narrow valley. From regional geological assessment it is expected that entire HRT and underground power house will also be constructed in biotite gneiss rocks. 1.3.2 Hydrology The river Subansiri/ Si Ngit drains a catchment area of about 14300 sq. km at the proposed damsite. The water availability for the project has been considered on the basis of 10-daily discharge series for 20 year synthetic flow series at Subansiri Upper dam site, located d/s of this project on the Subansiri river itself, on the basis of catchment proportion. The computed inflow series worked out has been utilised for Power Potential studies. The design flood is assessed as 12000 cumec at dam site.

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

1.3.3 Infrastructure In order to complete the project in 6 years, broad Infrastructure requirements such as road network ( including upgradation of roads) project office, residential colonies, arrangement for construction power, explosive magazine, telecommunication etc. have been identified and provision has been made in the cost estimate of the project. The project is located in remote corner of Arunachal Pradesh. Area is connected by a 450 km long single lane road from Pahumara in Assam (Take-off point from NH-52). This road needs to be upgraded. Accordingly, provision for widening/strengthening of road sections/bridges has been kept in estimates of hydroelectric projects viz. Subansiri Middle, Upper, Dengser and Nalo, located downstream of this project. However, in case, Naba H.E. Project is to be taken up before construction of downstream projects, provision for R-Communication in the estimate shall need to be revised. 1.3.4 Power Potential Studies The computed inflow series for 20 years has been considered in the assessment of power benefits from the project. The design energy for tariff at 95 % availability in a 90% dependable year has been worked out 3995.25 MU. A live storage of 8 mcm has been provided in the dam which would enable the station to operate as peaking station. 1.3.5 Power Evacuation Aspects The power generated from the project would be evacuated at 400 KV level through one no. double circuit transmission line with Quad moose conductor line to pooling station proposed at Daporijo which in turn will be connected to National Grid. 9

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

1.3.6 Environmental Aspects The project is located in a remote area in the Subansiri Basin. The total land requirement for the construction of various components is 510 ha. Out of which 175 ha. is private land and remaining is forest land. Based on assessment of environmental impacts, management plans have to be formulated for catchment area treatment, Compensatory aforestation and other environmental issues. These issues would be addressed during the investigation of DPR. No major township will be submerged or affected due to construction of project 1.3.7 Estimate of Cost The project is estimated to cost Rs.4399.89 crores including IDC at June,2003 price level. The preliminary cost estimate of the project has been prepared as per guidelines of CEA/CWC. The break up of the cost estimate is given below: Civil Works Electro Mechanical Works Transmission Works Interest During Construction Grand Total : : : : : Rs. 3068.58 Crores Rs. 743.81 Crores Rs. 117.00 Crores Rs. 470.50 Crores Rs. 4399.89 Crores

1.3.8

Financial Aspects

The Naba HE Project, with an estimated cost of Rs.4399.89 Crores (including IDC of Rs.470.50 Cr) and design energy of 3995.25 MU in a 90% dependable year is proposed to be completed in 6 years. The tariff has been worked out considering a debt-equity ratio of 70:30; 16% return on equity, annual interest rate on loan at 10% and twelve percent free power to home state. The tariff for first year (with free power to home state) and levellised tariff is Rs.2.43 per unit and Rs.1.97 per unit

10

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

respectively. However, levellised tariff at present day cost without any free power to home state works out to be Rs.1.73 per unit. 1.3.9 Construction Schedule The main infrastructure development is proposed to be initiated simultaneously with preparation of DPR for which a provision of 18 months will be kept and completed in initial 12 months after taking up construction (Stage-III activity) of the project. Main construction activity is planned to be completed in 6 years. 1.4 CONCLUSION The project would afford a design energy of 3995.25 MU in a 90% dependable year. The cost per MW installed works out to Rs.4.40 Cr. The tariff for first year and levellised tariff have been worked out as Rs.2.43 per unit and Rs.1.97 per unit respectively (with provision of 12% free power to home state). The Preliminary Feasibility Report indicates that the scheme merits consideration for taking up for survey and Investigation and preparation of DPR. Nevertheless, it may be mentioned that MOEF has imposed ban on construction of dam on Subansiri River upstream of Subansiri Lower Project. Accordingly, matter needs to be taken up with MOEF for review and lifting of ban before taking up investigation work leading to preparation of DPR.

11

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER-II BACKGROUND INFORMATION


2.0 GENERAL

Subansiri River is a major tributary of Brahmaputra contributing about 10% of its total discharge. It has its origin in the Central Himalayas in Tibet at an approximate altitude of 5340 m. Traversing through the snow clad mountains of Great Himalayas, it enters India in its North-East corner in Arunachal Pradesh. The river bed level of it drops from more than 4000 m height in the mountainous region to less than 100 m in the foothills before it enters the plains of Assam promising stupendous hydropower potential with snowmelt combining with heavy rainfall it receives in its catchment ensuring significant discharge in the river throughout the year. 2.1. PROPOSALS FOR HARNESSING HYDRO-POWER POTENTIAL OF SUBANSIRI BASIN To harness hydro-power potential of Subansiri river and to derive benefits of flood moderation, DPR of Subansiri dam project (4800 MW) was prepared by Brahmaputra Board during April 1983. But the project could not be taken up for execution because of objections from Arunachal Pradesh Govt. on account of large submergence of its land and consequent displacement of inhabitants. development over river Subsequently, cascade Subansiri was planned considering three

projects namely Subansiri Lower HE Project at Gerukamukh over river Subansiri (2,000 MW), Subansiri Middle project at Tamen over river Kamla (1,600 MW) and Subansiri Upper Project at Menga over river Subansiri (2,000 MW).

12

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CCEA approval for taking up of Subansiri Lower HE Project stands already accorded and as such project has come under construction stage. The commercial viability of Subansiri Upper and Subansiri Middle project stands already accepted by CEA. Work of preparation of DPR for above two projects is in progress. In addition to the above 3 mega projects in Subansiri basin, 8 more projects have been taken up for pre-feasibility study on priority basis under 50,000 MW Hydro-electric Initiative launched by Honble Prime Minister of India launched in May, 2003. In fact, CEA has conducted Ranking Study for harnessing the balance Hydropower potential available in the country and identified 399 Schemes to add further 1,07,000 MW to narrow the gap between supply and demand of power in the interest of sustained growth of the country. In its first phase, 162 projects are taken up for pre-feasibility study to be completed within 10-18 months with a projected capacity addition of 50,560 MW. These projects are expected to be developed expeditiously within next 10 years. Eight new projects identified for preparation of PFR (Preliminary Feasibility Report) in Subansiri basin under 50,000 MW Hydroelectric Initiative were Naba, Niare, Oju-I & II, Kurung - I & II , Hegio and Duimukh. Kurung-I & II projects have been clubbed and named as Kurung HE

Project. Further, Heigo project has been found to be located within submergence of proposed Subansiri Middle Project. As such, in lieu of these two projects, two schemes namely Nalo & Dengser located in between Naba project and Subansiri Upper Project have been added to list of PFR projects in Subansiri Basin. Proposed cascade development over river Subansiri is enclosed as Plate 2.1. Naba HE Project is envisaged as a run-of-the-river Scheme on Si Ngit (Subansiri) river. It is located at about 160 km up stream of Daporijo As per Ranking town in Upper Subansiri District in Arunachal Pradesh.

13

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Study made by CEA, the Installed Capacity of the project was estimated to be 1290 MW. Location of the project is indicated in the vicinity map enclosed as Plate-2.2. 2.2 EVOLUTION OF CONCEPTUAL LAYOUT OF NABA HE SCHEME 2.2.1 CEA Proposal CEA in its Re-assessment Studies observed that down stream of proposed Power House of Niare HE Scheme, the reach of the river is steep and there is possibility of another Hydropower Project. The proposal of the CEA for this project by the name of Naba Hydro Electric Scheme is as under,Immediately downstream of the power house under Niare hydro electric scheme, the reach of the river is steep and appears to permit development of another hydro electric scheme of run-of-river type by constructing a diversion of a small height at a site where the river bed level is +1000m diverting the waters through a 11.5 km long channel to a power house to be located on the river where the river bed level is +800 m. The scheme would utilise a gross head of about 200 m and enable generation of 308 MW of firm power at the power house. With an optimum economic installed capacity of 1290 MW, the scheme would give benefit of 6038 GWH and 6915 GWH of annual energy respectively in 90% and 50% dependable years. (Annexure-2.1) 2.2.2 NHPC Proposal The proposed Naba HE Project sites were inspected by NHPC officers. Based on the topographical and geological inputs as collected, the NHPC opined that the channel alternative is not feasible. It proposed three alternatives for the schemes with the following parameters, -

14

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

ALT 1 Bed Level Tail Race Level Tunnel Length 1000 m 800 m 10.5 Km

ALT 2 1000 m 800 m 9.5 Km

ALT 3 1000 m 850 m 7.5 Km

These three alternatives are discussed with CEA Authorities on 09.10.2003. In the discussion, the ALT-2 was considered to be more attractive than the other two alternatives with provision for shifting of dam site down stream, if required, for providing necessary pondage for peaking operation. Summary Record of the discussion held with CEA is enclosed as Annexure-2.2 . Subsequently, NHPC reviewed the parameters of Naba HE Project taking into account the other three proposed up-stream projects namely Oju-I, Oju-II and Niare with the preliminary data/ information collected during site visits. In the ALT-2, the dam site is shifted downstream where River Bed Level is El 945 m. This proposal alongwith the parameters for the other three projects were taken up for discussion with CEA on 03.12.03 for vetting. Summary Record of the Meeting is enclosed as Annexure-2.3. Further, details of various alternative locations considered for finalising layout of Naba HE Project are given in Chapter-VI. At Naba HE project, it is proposed to construct a 110 m high concrete dam with provision for live storage of 8 MCM for peaking operation, 2 nos of Head race tunnel of length 9.75/9.80 km, 2 nos of 23m dia surge shaft, 7.25m dia steel lined pressure shaft and 1000 MW underground power house. Based on the limited available hydro meteorological data, hydrological studies have been carried out and a synthetic 90 % dependable water availability series developed for undertaking power potential studies. As

15

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

per power potential studies the installed capacity works out to 1000 MW. The design energy on a 90% dependable year works out to 3995.25 MU. Based on preliminary observations and study of available information, no major area of cultivable land is available around the proposed project area needing irrigation. As such, there is no scope for development of irrigation in this project. However, this aspect needs to be examined during feasibility stage investigations. PFR of Naba HE Project has been made in accordance with the scope of work and keeping in mind observations/ comments of CEA(Annexure 2.4) 2.3 POWER SCENARIO & EXISTING INSTALLATION

The power system in India has grown from small, isolated stations, serving limited consumers in and around large cities, into large regional Grids. The generating capacity installed in the country has already grown to 107643.70 MW by March 2003. The objective of the system development is to evolve self-sufficient regional grid catering to the individual regional power demands. It is also aimed at achieving the maximum benefits from integrated operation, through a proper mix of thermal and hydro generation and ultimately to tie the five regional grids together to form a robust National Power Grid, providing even greater reliability. At present Arunachal Pradesh Electricity Board has its own hydel generation of 32.52 MW and diesel generation of 23.64 MW. Share of Arunachal Pradesh in Central Sector Power Generation is around 117.0 MW (includes gas based Power projects)

16

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

2.4

NECESSITY OF THE PROJECT & RELATED ASPECTS

The power position in the North Eastern region and all India power supply position have been summarized in Table-2.1 and Table-2.2. The benefits from all schemes that have been cleared by CEA have been included. Even considering the co-ordinated operation of existing hydro, nuclear and thermal stations as well as benefits from ongoing projects and also from the scheme cleared by CEA and programmed for implementation in 10th Plan, the all India regions are expected to face power deficit in 10th five year plan. The regions will continue to remain in deficit in 11th Five year plan also except in North-Eastern region as it is evident from Table-2.1 even if all the cleared projects till date are implemented. The surplus in North-Eastern region is planned to be exported to regions having deficit. However, country as a whole will suffer from energy deficit even by the end of 11th plan as shown in Table-2.2. Construction of Naba HE Project will reduce this deficit.

17

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Table 2.1
POWER SUPPLY POSITION OF NORTH-EASTERN REGION

10th Plan North-Eastern Region Installed Capacity Peak availability Peak requirement Peak Surplus(Deficit) Peak Surplus(Deficit) Energy availability Energy requirement EnergySurplus(Deficit) EnergySurplus(Deficit) MW MW MW MW % MU MU MU % 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09

11th Plan 2009-10 2010-11 2011-12

2309 1135 1209 -74

2357 1159 1307 -148

2395 1177 1412 -235

2555 1256 1526 -270

2962 1456 1649 -193 -12.00% 7946 8707 -760 -9.00%


280 MW TRIPURA GAS(MONARCHAK) 84 MW MYNTDU(LISKA) 20 MW Dhansiri HEP 23 MW Dimapur DGPP

3042 1495 1785 -290 -16.50% 8161 9416 -1255 -13.50%


80 MW BAIRABI HYDRO

3342 1643 1933 -290 -15.50% 8966 10184 -1218 -12.00%


90 MW LOKTAK D/S 210 MW TUIVAI HEP

3942 1937 2092 -155 -7.50% 10575 11014 -438 -4.00%


600 MW KAMENG HEP

5942 2920 2265 655 29.00% 15940 11911 4029 34.00%


2000 MW SUBANSIRI LOWER

7442 3658 2452 1205 49.50% 19964 12882 7082 55.00%


1500 MW TIPAIMUKH MPP

-6.12% -11.50% 6195 6350 -155 -2.44% 6324 6871 -548 -8.00%
25 MW KOPILI II 23 MW BAIRABI (THERMAL)

-17.00% -18.00% 6426 7436 -1010 6855 8046 -1191

-14.00% -15.00%
38 MW LAKWA WH 60 MW TUIRIAL 100 MW KARBI LANGPI

POWER PLANT CONSIDERED TO BE ADDED IN RESPECTIVE YEAR OF 10TH AND 11TH PLAN

SOURCE: 1) Power on Demand by 2012 2) Web Sites www.cea.nic.in www.nhpcindia.com www.ntpc.co.in

NOTE: 1) Projects shown cleared by CEA on CEA web site have only been considered.

2) Projects cleared but not programmed for implimentation for 10th plan have been considered to come up in 11th plan

Total

MW

0 MW

48 MW

38 MW

160 MW

407 MW

80 MW

300 MW

600 MW

2000 MW

1500 MW

1.All the data for the year 2002-2003 has been taken from the website www.cea.nic.in. 2. Energy availability for the year 2003-2004 onwards have been estimated on the basis of ratio of Energy availability to Installed capacity for the 3. Peak availability for the year 2003-2004 onwards have been estimated on the basis of ratio of Peak availability to Installed capacity for the year 4. Energy requirement and peak requirement for the year 2003-2004 onwards is based on the annual increments given at page -117 and 118 of "Sixteenth Electric Power Survey of India". 5. Micro/mini hydel projects under construction have not been considered in this study.
This is a statistical analysis based on various publications mentioned above and are meant for study and planning purposes.

18

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Table 2.2
POWER SUPPLY POSITION OF ALL INDIA

10th Plan 2002-03 Installed Capacity Peak availability Peak requirement Peak Surplus(Deficit) Peak Surplus(Deficit) Energy availability Energy requirement EnergySurplus(Deficit) EnergySurplus(Deficit) MW MW MW MW % MU MU MU % 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09

11th Plan 2009-10 2010-11 2011-12

107644 71547 81492 -9945 -12.20% 497589 545674 -48085 -8.81%

113411 75380 86650 -11270 -13.50% 524250 580324 -56075 -10.00%

121137 80516 92135 -11620

125981 83735 97968 -14232

142842 94942 104169 -9227 -9.00% 660297 698045 -37748 -5.50%

157124 104435 110930 -6495 -6.00% 726314 741882 -15568 -2.50%

164485 109327 118129 -8801 -7.50% 760341 788472 -28132 -4.00%

171105 113727 125795 -12068 -10.00% 790942 837988 -47046 -6.00%

174095 115715 133960 -18245 -14.00% 804763 890614 -85850 -10.00%

176915 117589 142653 -25064 -18.00% 817799 946545 -128745 -14.00%

-13.00% -15.00% 559964 617175 -57211 -9.50% 582355 656366 -74010 -11.50%

CAPACITY CONSIDERED TO BE ADDED IN RESPECTIVE YEAR OF 10TH AND 11TH PLAN

NORTH-EASTERN REGION

48 MW

38 MW

160 MW

407 MW

80 MW

300 MW

600 MW

2000 MW

1500 MW

EASTERN REGION

500 MW

1130 MW

1750 MW

1160 MW

1132 MW

900 MW

1500 MW

660 MW

1320 MW

NORTHERN REGION

3735 MW

1046 MW

916 MW

5692 MW

2938 MW

522 MW

3200 MW

330 MW

0 MW

WESTERN REGION

357 MW

3179 MW

1215 MW

6683 MW

4677 MW

2716 MW

0 MW

0 MW

0 MW

SOUTHERN REGION

1128 MW

2333 MW

803 MW

2914 MW

5454 MW

2923 MW

1320 MW

0 MW

0 MW

A & N ISLANDS

5 MW Rangat Bay (DG)

LAKSHADWEEP

SOURCE: 1) Power on Demand by 2012

2) Web Sites www.cea.nic.in www.nhpcindia.com


www.ntpc.co.in

Total

0 MW

5768 MW

7726 MW

4844 MW

16861 MW

14282 MW

7361 MW

6620 MW

2990 MW

2820 MW

1.Installed capacities are based on summation of installed capacities of all the regions and 69.27 Mw for A&N Islands and Lakshadweep Islands. 2. Energy availability for the year 2003-2004 onwards have been estimated on the basis of ratio of Energy availability to Installed capacity for the year 3. Peak availability for the year 2003-2004 onwards have been estimated on the basis of ratio of Peak availability to Installed capacity for the year 20024. Energy requirement and peak requirement for the year 2003-2004 onwards is based on the annual increments given at page -117 and 118 of "Sixteenth Electric Power Survey of India". 5. Micro/mini hydel projects under construction have not been considered in this study.
This is a statistical analysis based on various publications mentioned above and are meant for study and planning purposes.

19

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER- III PROJECT AREA


3.0 THE PROJECT

The Naba HE Project is located in upper reaches of Subansiri River near Badok village. It is about 160 km from Daporijo town. In fact, hydropower potential of the river Subansiri is proposed to be harnessed through cascade of several projects, viz., Oju-I, Oju-II, Niare, Naba, Nalo, Dengser, Subansiri Upper Project and Subansiri Lower Project. The proposed dam site of Naba project is accessible through DaporijoLimeking road.

Naba Hydroelectric Project comprises of 110 m high dam, with 9.75/9.80 km long HRT, 23 m dia surge shaft, 7.25 m dia steel lined pressure shaft and 1000 MW underground power house
3.1 RIVER SYSTEM River Subansiri originates in Tibet at an altitude of around 5340 m beyond the Great Himalayan Range (Central Himalayas) and after traversing about 375 km joins the Brahmaputra river. The river flows through narrow gorge in most part of its length and generally follows an easterly direction up to Siyum, and, thereafter it takes a south-easterly course upto its confluence with Kamla. Thereafter, it flows in a southerly direction upto Kherkatiasuti and flowing for another 60 km (approx.) in south-westerly direction it confluences with the mighty Brahmaputra River. It is one of the largest right bank tributary of Brahmaputra and contributes about 10% of its total discharge. Major tributaries joining the Subansiri river in the project area are Laru chu, Nye chu, Yume chu, Sang chu, Ikte nallah, Gazi nallah, Koter nallah, Ghaghu nallah, Mazang nallah, Kopu Nallah, Libi

20

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

nallah, Thru nallah, Bate nallah, and Rembung nallah. These tributaries exhibit Trellis and Dendritic pattern of drainage. The total length of main tributaries of Subansiri is 1960 km. Major villages/ towns located in the vicinity of project area are Nacho, Nelu and Limeking. 3.2 LOCATION AND ACCESSIBILITY

The project area is located near Limeking village. An all weather metalled road connects Limeking with Daporijo, the district headquarter of Upper Subansiri district. Dam site of Naba HE Project is located at about 5 km u/s of Limeking and Powerhouse site is located at about 20 km d/s of Limeking. Limeking is about 160 km from Daporijo and is easily accessible by all weather Limeking - Daporijo road. Major villages/ towns present along the Daporijo- Limeking road are Taliha, Kodak, Siyum, Ayingmoring, Nacho & Limeking. However, beyond Limeking road condition is very bad and presently upto a distance of 7 km there exists only a fair weather motorable road. Proposed dam site is accessible by road on right bank of the river from Limeking. This is however only a fair weather road in poor condition as mentioned above. The left bank of the river at proposed dam site is almost inaccessible due to dense forest cover and steep rocky escarpment. The proposed powerhouse site is located on left bank of the river near villages Nelu and Naba and these sites can be approached only by crossing the Suabnsiri river through cane bridge located near Nelu village. All along, in this stretch also, the left bank is extremely difficult to traverse because of forest cover and steep rocky slopes. The nearest meter guage and broadguage railhead is North Lakhimpur and Nagaon respectively. Nearest airport is at North Lakhimpur (Lilabari) in Assam. Besides, there are helipads at Daporijo, Nacho, Limeking, Reddi & Taksing and these are frequently used by army helicopters. 21

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

3.3 CLIMATIC CONDITION The area experiences a subtropical climate with temperatures fluctuating from 00 to 100 during Winter and 200-250 during Summer. Ice-cold winds blow during the morning and evening hours of the winter season. Monsoon commences during May and lasts till the end of September. Nevertheless scanty rains are also common during winter season. Average annual rainfall is about 2825 mm. The relative humidity ranges from maximum 94% to minimum 62%. 3.4 SOCIO- ECONOMIC ASPECTS

The project area is located in the Upper Subansiri District in Arunachal Pradesh sharing the International Boundary with China in the North. Upper catchment of Subansiri Basin in Indian territory falls in this district. The area is inhabited mainly by the people from the Nyshis, Tagin community, Galos and Hill Miris. Most of the population belongs to the Tagins in the vicinity of the project area. The main livelihood of the population is cultivation. They commonly practice terrace and jhoom cultivation. 3.4.1 Demography The district is divided into 11(eleven) circles. The district has a diverse terrain extending over valleys of lower altitude to heights upto 18000 ft. Taksing is the remotest Circle bordering Tibet. It has snow bound peaks where no habitation exists. The Upper Subansiri District has an area of 7032 sqkm. The total

population of the district is 50,086 (1991 census). The population density is approximately 8 persons per sq.km in the district. The male population is 26,823 and the female population is 23,263. There is no educational institution above higher secondary level. There are 3 nos. of Higher

22

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Secondary Schools and 6 nos. of High Schools in the district. There are 3 nos. of Middle Schools and 5 nos. of Primary Schools in the vicinity of the project area within the Nacho and Limeking Circles. As such, overall scenario suggests a low literacy rate in the district. Population of Nacho and Limeking circle is 3404 and 863 persons respectively. Circle wise population pattern of the Upper Subansiri District is presented in tabulated form (Table 3.1) below. The figures are taken from Statistical Hand Book of Upper Subansiri District, Arunachal Pradesh, 2000 edition. Table 3.1 Circle wise number of villages, household and population in Upper Subansiri District as per 1991 census. Sl No. Name of Circles 01. 02. 03. 04. 05. 06. 07. 08. 09. Daporijo Dumporijo Baririjo Giba Taliha Taksing Nacho Limeking Siyum Total No. of Villages 56 57 24 62 89 12 42 18 45 Total No. of House hold 2948 4299 620 980 1666 168 827 209 835 Total Population 17425 7457 3292 5052 8057 733 3404 863 3803

Total

405

12552

50086

23

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

3.4.2 Ethnography Race: The people of Arunachal Pradesh have been generally described as descendants of Mongoloid, Paleo mongoloid and Proto-mongoloid race. The distinctive characteristics of the tribes in their language, dress, customs and food habits are direct reflection of the type of environment they live in - in geographical isolation over a long period of time. Tribes: There are about 25 major groups with a number of sub-groups found in the state. In the Census report of 1961, 1971 and 1981as many as 80,110 tribes and 105 sub-tribes were described. Census reports of 1991 and 2001 however did not include any tribal classification. The major tribes found in the project area are Tagin and Nyishi. These ethnic populations usually live in different groups called busthi in the local language. Each busthi generally comprises of 15-25 homesteads. The houses (constructed of wood, bamboo and thatches) are usually raised over a platform of logs about 3-4 feet above the ground. Social structure: The tribals of Arunachal Pradesh have highly ordered and organised system of functioning in their villages. All matters relating to the community as a whole are decided at the village level. The socioadministrative structure of the society, as evolved over a period of centuries, recognises democratic participation right down to the village level. Several self-governing institutions exist among these tribes. Such a structure of Nyshis in the area is locally known as Nyele. Agriculture: Jhum cultivation is one of the predominant forms of agriculture even today. Efforts are on to control this form of practice as this results in cutting of forest trees & degradation of slopes. Most of the people are dependent on agriculture. Only a few are working as traders, daily wage labourers or salaried employees. Of late, these people are adopting other forms of agriculture like Wet Rice Cultivation (WRC) and Terrace Rice Cultivation (TRC). 24

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Festival: Four main festivals are observed by the various communities of the district. These are, (i) Si-Donyi, (ii) Boori-Yullo, (iii) Boori- Boot and (iv) Mopin. The Tagin community celebrates the festival of Si-Donyi in the month of January. They are the prominent community residing in the project vicinity. Nyishis celebrates the Boori-Yullo festival during the month of January. The Hill Miris community observes Boori-Boot festival during the month of February. The Galo community celebrates the Mopin festival during the month of April. There is another festival known as Losar observed by the people of Taksing area in the month of February.

25

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER-IV TOPOGRAPHIC AND GEOTECHNICAL ASPECTS


4.0 INTRODUCTION

The Geological Survey of India has prepared a Preliminary Appraisal Report entitled Geology of area around the proposed Naba Hydroelectric Project, Subansiri Basin, Arunachal Pradesh (Jan04). This appraisal (Annexure 4.1) is the main source of geological inputs for evaluating geotechnical aspects of the project. Nevertheless, proposed sites were visited by NHPC geologists to collect site specific geotechnical details. Topographic and geological aspects of the area have been used while finalizing conceptual layout of the project (Plate-4.1) 4.1 REGIONAL TOPOGRAPHY AND GEOLOGY

The river Subansiri originates from Tibet and after traversing 375 km joins the Brahmaputra River. At the project site river flows in an almost W-E direction carving out a very narrow valley. Project area in general is characterised by rugged topography typical of Himalayan terrain. Geomorphologically, the area is composed of high mountain ridges with steep slopes and deep incised valleys carved by Subansiri river and perennial nallahs joining Subansiri river. The Project area falls within higher Himalayas. At the proposed dam site river valley is about 50 m wide followed by gentle slope at both the banks for a short stretch until the slope becomes steep because of presence of steep rocky escarpments. Rock present at the dam site is slightly weatherd Biotite Gneiss. Geologists of G.S.I. (Surendra singh, K.V.S

26

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Reddy, C.M.Bindal, B.V.Ganesh and K.K. Rao, 1985-86) have carried out regional geological mapping in this area. 4.2 REGIONAL GEOLOGY

The tectono-stratigraphic sequence of upper Subansiri area as given by Singh at (1986) is reproduced below from GSI (Jan,2004) report (Table-4.1) Table- 4.1: Generalised Geological Succession Group Formation S U B A N S I R I G R O U P Nacho Formation Maza Granite Taksing Formation Litho-assemblages Tourmaline leucogranite with biotite gneiss and hornblende gneiss Schistose quartzite interbanded with staurolite-garnet-biotite schists, calsilicate, marble, meta-amphibolites Galensiniak Formation Kyanite-sillimanite-garnet migmatite calc-silicate graphitic graphitic schists. Schistose Quartzite intercalated and interbanded with biotite schist. -----------------------------------------Kobaso Thrust------------------------------------Tali Group Massive quartzite, limestone/dolomite, phyllite and slate gneiss, rock, biotite gneiss, gneiss, garnetiferous biotite gneiss, marble with disseminations,

27

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Maza Granites Tourmaline leucogranites, extensively exposed at Maza and further north towards International Border with China have been designated as Maza Granites. It is light grey fine grained and profusely jointed. Maza Granites show hypidiomorphic granitar texure. Orthoclase, plagioclase and quartz are its amin mineral constituents. These are of intrusive igneous origin. Taksing Formation The metasedimentaries of Subansiri Valley constituting the Taksing Formation are exposed in a NE-SW trending belt and are encountered between Reddi and Taksing in Subansiri valley and also between Gelmo and Ridding in thre Tsari-Chu. White to light grey and fine quartzite constitute the dominant lithounit of the Taksing Formation. Interbands of staurolite garnet biotite- schist are commom in the Quartzite. Galensiniak Formation The Galensiniak Formation is most extensively developed in the Subansiri Valley. Various types of gneisses belonging to this formation are biotite gneiss, garnetiferrous biotite gneiss and kyanite- sillimanite gneiss. These can be distinguished in the field on the basis of appearance of index minerals such as Garnet, Kyanite, Sillimanite etc. Each type of gneiss forms a distinct belt and have gradational contacts with one another. In the project area light grey colured fine to medium grained well foliated biotite gneiss is exposed. Nacho Formation It constitutes a litho-assemblage of white to light brown coloured schistose-quartzite, intercalated as well as interbanded with dark biotite schist. At Nacho the biotite schist bands show preponderence over the quartzite. Further west dark grey biotite schist is well exposed. Near Dogi

28

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Nalo, the Nacho Formation grades into overtyping Gelensiuiak Formation. The quartzite, phyllite, limestone representing Tali Group are exposed around Mara in southeastern corner. These are overridden by the medium to high grade metamorphics and crystallines of the Subansiri Group along the Kabaso Thrust. 4.3 TOPOGRAPHIC AND GEOTECHNICAL ASPECTS OF

COMPONENT STRUCTURES To substantiate topographic/geological data entire area has been traversed and site specific information has been collected. A geological specific information has been collected across the river near proposed dam site (Plate-4.2), based on surface observations. There is no possibility of deploying geophysical survey techniques to assess overburden in the river bed because of narrow valley and steep slopes. 4.3.1 Dam At the proposed site river flows through a moderate U shaped valley. Abutments are steep, dotted with rock out crops. Width of the channel is about 50 m (Plate-4.2). Here, medium grained, dark grey coloured almost fresh to slightly weathered biotite gneiss of Galensiniak Formation is exposed. Rock is foliated and moderate to closely jointed, dissected by three to four prominent joint sets. The foliation is dipping gently (1700/150). Overburden on abutments appear to be thin Depth of overburden in the river channel is not known at this stage. This needs to be ascertained through exploratory drilling during feasibility / DPR stage Investigations.

29

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

4.3.2 Water Conductor System The steep topography all along the valley with deeply dissected hill slopes by cross drainages do not favour construction of a water channel as initially envisaged in CEAs proposal. Topography, geomorphology and geology are favourable for laying a tunnel on the left bank. Proposed head race tunnel would be laid in well foliated moderate to closely jointed light grey coloured fine to medium grained botite gneiss of Galensiniak Formation. 4.3.3 Power House The underground powerhouse is proposed on left bank near Naba village. It will be housed in moderate to closely joined dark grey coloured biotite gneiss of Galensiniak Formation. 4.4 SEISMICITY

Seismotectonically, the area falls in the seismic zone V of seismic zoning map of India (IS-1893: Part- I :2002). Site specific design parameters need to be worked out during Feasibility stage Investigations of the project. 4.5 CONSTRUCTION MATERIAL

The Subansiri River flows through a narrow valley. There are very few river shoals or small terraces of riverine material, seen along course of the river. Hence, very limited quantities of natural aggregates are expected to be available from riverine shoals / terraces. Therefore, samples from rock exposed around dam site and in reservoir area may be tested for using this material as coarse and fine aggregates for production of concrete. Excavated muck from underground excavations may also be used for concrete aggregates, if found suitable after testing. Detailed construction material surveys may be conducted to identify borrow areas and rock

30

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

quarries. Quality and quantity of material for each borrow area and rock quarry may also be ascertained during FR/DPR stage investigations. 4.6 RECOMMENDATIONS INVESTIGATIONS 4.6.1 Topographic Surveys Detailed contour plans for Dam, Water Conductor System, powerhouse and reservoir areas as per CWC guidelines. Cross- section of river at dam site and along other main components of the project. 4.6.2 Geological Geotechnical Studies Detailed geological mapping of project components. Petrographic studies on rock samples. Drill holes and exploratory drifts at dam axis, water conductor system and various components in the powerhouse area. Permeability / water pressure testing in drill holes. One or two sets of Groutability tests should also be done. Lab / In-situ rock mechanic testing for evaluation of physical properties and engineering properties of the rock mass. Geophysical surveys for estimation of overburden at main civil structures. 4.6.3 Remote Sensing Studies Regional geological appraisal of the area using remote sensing data and aerial photographs. Preparation of lineament/ tectonic map of the area. Landuse classification using toposheets and Satellite imageries. FOR FURTHER STUDIES /

31

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

4.6.4 Construction Material Surveys Identification of borrow areas/ rock quarries. Survey of borrow areas / rock quarries for quantity estimation. Testing of representative samples for determination of physical properties and alkali- aggregate reactivity potential.

32

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER V HYDROLOGY
5.0 GENERAL

Naba H.E. Project is proposed on river Subansiri a tributary of Brahmaputra river, near Badok, u/s of Doloring village in Upper Subansiri district of Arunachal Pradesh. The proposed dam site is located just upstream of confluence of Gazi Nadi with Subansiri, a right bank tributary of Subansiri river. The project envisages construction of 95 m high dam on Singit or Subansiri River with a gross storage capacity of 31.9 M.cum at FRL i.e EL 1035 m. The submergence area is estimated as 81.28 Ha at FRL whereas the reservoir length is measured as around 5 km. The hydrological investigations and analysis have been carried out with a view to: Assess the availability of water for power generation by establishing a long-term series of average 10-daily discharges at the project site. Estimate the spillway design flood. Determine the capacity of the reservoir and the area of submergence at different levels including FRL and MDDL. 5.1 Reservoir Sedimentation RIVER SYSTEM & BASIN CHARACTERISTICS

Subansiri is a major right bank tributary of river Brahmaputra. The river originates beyond the Great Himalayan Range (Central Himalaya) at an altitude of around 5340 m. Near its source, several mountain torrents, rather a big Chu family of streams, drains into main valley. The principal

33

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

stream belonging to this Chu group is the Nye Chu which may be considered as the main source of the river Subansiri originating from the snow clad peaks of Krakang, Shabota, Baru and Mata (El 5389 m) lying around 92o and 93o E longitudes and 28o and 29o N latitudes. The Nye Chu is then joined by another stream Laro Chu near Chayal and thereby taking the name of Chayal Chu. Another stream the Char Chu rising from the snow clad peaks in the North joins the main stream the Chyal Chu near Karutra and crosses the international boundary soon after. A small distance from the boundary, Yume Chu flowing from the north merges with mainstream. After flowing further it receives the Tsari Chu and the combined water of these streams flow as the Subansiri for about 200 km from this point finally outfalling into Kherkutia Suti, a spill channel of the Brahmaputra. In higher reaches, where it is known as Tsari chu, the Subansiri is flowing in an approximately westerly direction. The river cuts across the central Himalayan ridge, which has a series of high peaks of 5000 m and above. It follows a Southeasterly course along the lesser Himalayan zone with an average height of 3048 m and takes the name Subansiri. The river as it approaches the Miri hills in Arunachal Pradesh after crossing the international boundary runs in an unexplored valley and the course of the main river and its tributaries are more or less marked on conjectural lines rather than by accurate mapping. In its early reaches as the river gathers more and more torrents in the Himalayas, it rushes through deep gorges, far below the snow tipped mountain peaks. The main course of the Subansiri after entering the Miri hills in Arunachal Pradesh runs between the Dafla hills and the Abor hills. Even in this reach, very little is known of the river and its valley as it is covered with dense vegetation and impenetrable forests. It is an enormous virgin terrain of rugged mountains, covered by insatiable forest, fed by copious rains.

34

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

After traversing through the Miri Hills of the outer Himalaya (Siwalik foothills), the Subansiri debouches into the plains of Assam near Dulangmukh. Before entering the plains, Subansiri cuts a steep gorge of unique beauty through the Siwalik rocks of Arunachal Himalaya. Debouching from the hills near Dulangmukh the course of river lies in the fertile plains of North Lakhimpur Civil Sub-Division of Assam. In the broad and flat valley, the river flows in lazy and sinuous curves. The total length of the river in the mountainous terrain is about 208 km. The riverbed falls from a height of 4206 m to 80 m near Dulangmukh in the foothills. After flowing for about 70 km from the hills, the river falls in to the Kherkutia Suti and thereafter flowing for another 60 km it outfalls into the river Brahmaputra. Throughout its journey from the central Himalaya to the Arunachal foothills, the Subansiri receives the discharges of numerous mountainous big and small streams. The number of its tributaries is more in the Siwalik foothills than in other zones. The total length of the known and well-defined tributaries of Subansiri is 1960 km. The region may be divided into four parts; the distant Tibetan mountains beyond the international border, the reach lying between the international boundary and Miri hills of Arunachal Pradesh, the Arunachal Pradesh portion between the outskirt of Miri hills and the interstate boundary of Assam and Arunachal Pradesh and lastly the plains of Assam. The first two belongs to the great Himalayan range, the third belonging to the SubHimalayas and the fourth in the fertile plains of Assam. Tibet, the birthplace of Subansiri is a land to conjure with. In the mountains, blinding snow and ice build vast bewildering expanses. The streams flow beneath the ice in winter, which have their turn in summer when they melt and flow down the valleys lined up on either side with rows of white snow. In this region are found towns, highly inaccessible in their mountain retreats.

35

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Down below in the region between the Miri hills of Arunachal Pradesh and international boundary, the river passes through damp thick jungles and rocky terrain. The next reach is also in mountain terrain. These are the Sub-Himalayas, the pattern of the hills and valleys being the same imposition of the Himalayan range at a lower altitude. In the vastness of wild mountains, there are unbelievable settlements of human habitation. In the last lap of journey Subansiri passes through a broad fertile plain with gentle slopes. Debouched from the narrow confines of the gorge, it spreads and dissipates itself out in the plains of Lakhimpur District meandering and altering channels of flow. The topography of this region is almost flat formed of alluvial deposits. The river Subansiri in Arunachal Pradesh flows through Upper and Subansiri Lower districts and in Assam its catchment area falls in the North Lakhimpur and Dhemaji districts. The contribution of the river Subansiri is estimated to be about 10.66 percent of the total discharge of the river Brahmaputra at Pandu near Guwahati. The total catchment area of Subansiri basin is 37000 sq.km, out of which about 14000 sq.km lies in Tibet. The snow line or limit of perpetual snow in the Himalaya varies depending upon various local factors. The present snow line varies in altitude from about 4267 m in the eastern part to about 5182 m in the western Himalayas. The catchment plan of Subansiri along with rainfall stations, G&D sites marked is shown in Plate5.1.

36

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

5.1.1 Catchment Area The Naba basin lies between Longitude 91o45 E to 93o34E and Latitude 27o00 N to 28o22 N. The proposed dam site lies at Longitude 93o3400 E and Latitude 28o2200 N. The total catchment area up to the proposed dam site is about 14300 sq.km. The permanent snow cover has been assumed above an elevation of 4500 m. The snowfed area at proposed dam site has been estimated as 9484 sq.km. The rainfed area upto the proposed dam site is 4816 sq.km. The river bed level at the proposed dam site is around EL 945 m. Average slope of river upto proposed dam site is estimated as around 30 m per km. The catchment plan of Subansiri Upper basin upto Naba dam site is given in Plate-5.2. This catchment plan has been prepared on the basis of catchment plan prepared for the Subansiri basin by Brahmaputra Board and then by NHPC. Toposheets of 1:50000 scale covering the catchment area of the basin are not available and as most of the area falls in Tibetan catchment, therefore it is difficult to collect them in feasibility stage also. However on availability of toposheets, the catchment plan need to be verified in feasibility stage/DPR stage. 5.1.2 Temperature and Humidity The climate in the entire region is humid and fairly uniform. Thick mist formation from early morning everyday, which completely envelope the area and blocks out the sun is generally, the climatic feature during winter. The temperature varies from high altitude to lower altitude. The maximum and minimum temperature is 39.5oC and 11.5oC as observed at Menga. The relative humidity ranges from maximum 94% to minimum 62%.

37

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

5.1.3 Precipitation Characteristics Subansiri basin extends from tropical to temperate zones and therefore the area exhibits a great diversity in rainfall characteristics. In the Northern and Central Himalayan tracts precipitation is scarce on account of high altitudes. Southeast part of the Subansiri basin comprising the sub-Himalayan and the plain tract in Arunachal Pradesh and Assam, lies in the tropics. Precipitation occurs in this region in copious quantities due to Northeast as well as Southwest monsoon. Particularly the Southwest monsoon causes very heavy precipitation in the whole of this region during May to October. July and August are generally the high flood months. The Eastern and Central Himalayas function as a great climate divide. In winter, it serves as a barrier to the intense cold continental air flowing southwards and in monsoon months, the moist rain bearing winds are forced up the mountains to deposit their moisture. The southwest monsoon, which enters Assam and adjoining area around end of May and beginning of June establishes firmly over the entire North East India by June end. During the monsoon season a low-pressure region extends from the seasonal low over Rajasthan to the head of Bay of Bengal. This monsoon axis oscillates about the normal position to the North and South during the season. When it moves North towards the foothills of Himalaya the rainfall over Assam increases and this is one of the primary causes of flood in the Brahmaputra Valley. Sometimes a minor east west oriented trough over Assam and West Bengal, while the primary trough is along normal position, can also give rise to increased precipitation over the Brahmaputra catchment. Land based low and depressions form in situ over Assam and adjoining region or move across Bangladesh and influence in increasing the precipitation over the various reaches of Brahmaputra Valley.

38

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

The other features that normally cause increased precipitation over the Brahamputra basin are passage of upper air trough in the monsoon westerlies and sometimes by the appearance of the remnants of mid latitude western disturbances over extreme North Arunachal Pradesh in conjunction with other precipitation causing features. The above account of weather and precipitation distribution is influenced by local orographic effects, with minor ranges, spurs, valleys of different width and narrow gaps permitting winds to enter from particular direction, in the sheltered valleys. The orography of the catchment is so complex that a detailed study would be possible only with a dense network of observatories. The other meteorological situation causing very heavy rainfall is the passage of cyclonic storms, originating in Bay of Bengal, over the area. This is generally noted in late May or June and in late September or October, when the cyclonic storm developing over the Bay initially moves towards approximately 20oN. The raingauge network in Subansiri Upper basin is not as per desired standards. No raingauge station is available within the catchment of Naba H.E. Project. Upper Project. Naba. NHPC has established rain gauge stations at Taliha, Siyum, Menga, Daporijo, Dumporijo, and Limeking in respect of Subansiri Out of these raingauge stations namely Taliha, Siyum and Limeking lies near Naba dam site, though outside the catchment of Data Availability status of raingauge stations near Naba is placed as Table 5.1.

39

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-5.1 DATA AVAILABILITY STATUS ------------------------------------------------------------------------------------------------S.No STATION DATA AVAILABLE ------------------------------------------------------------------------------------------------1. Taliha 1968-69,76-86,2000-2003 2. Limeking 1966,68-69,77-80,2001-2002 3. Siyum 1966,68-69,2001-2002 ------------------------------------------------------------------------------------------------The rainfall data is not continuous and missing in between prior to year 2000. Further, it is not truly representative of entire basin. The raingauge stations could not be established due to inaccessibility and poor infrastructure of this region. Also most of the portion of this basin falls in Tibet. Monthly rainfall at all three stations for each year is given as Annexure 5.1A, 5.1B and 5.1C. Average monthly rainfall in near the catchment of proposed project is shown in Table 5.2. The average annual rainfall in the vicinity of the Naba sub-basin is around 2825 mm. TABLE- 5.2 AVERAGE MONTHLY RAINFALL NEAR NABA SUB-BASIN MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL TALIHA 62.5 116.1 186.2 283.7 286.5 315.5 373.3 281.0 294.3 123.7 66.7 49.3 2438.8 LIMEKING 111.8 79.0 174.5 199.9 384.0 537.2 488.5 444.0 384.8 186.5 44.6 40.2 3074.8 SIYUM 40.2 83.0 193.3 232.3 297.3 573.0 483.8 392.5 358.7 189.1 97.7 20.0 2960.9 AVERAGE 71.5 92.7 184.7 238.7 322.6 475.2 448.5 372.5 345.9 166.4 69.7 36.5 2824.8

40

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

5.2

WATER AVAILABILITY STUDY

5.2.1 Data Available Gauge and discharge data is not available anywhere in the catchment of Naba H.E. Project. Due to difficult condition of communication, accessibility and terrain, despite continuous efforts, much information about the discharge pattern in the catchment of proposed project could not be obtained. On the basis of available data and information the study has been made. However, few G&D sites has been established by various agencies within the Subansiri basin as detailed below. Brahmaputra Flood Control Commission (BFCC)/ Brahmaputra Board established a gauge discharge site at Daporijo 25 km d/s of Subansiri Upper dam site in 1978. The gauge and discharge Station at Bhimparaghat located 15 km downstream of the Subansiri Lower dam site was established by Central water Commission in 1956, which was subsequently shifted, to Chouldhowaghat in 1960 located 12 km downstream of the Subansiri Lower dam site. In 1971 the site was taken over by B.F.C.C., Govt. of Assam. The gauge discharge site at Gorge Mouth was established in July 1973 located 2 km down stream of Subansiri Lower dam site, which was subsequently shifted to Subansiri Lower dam site in August 1977. A G&D site was established at Tamen on Kamla River, where gauge and discharge data is available from 1980 to 1998. NHPC has established G&D sites at Menga (260 m u/s of proposed dam site, operational since June 2000), Tamen Bridge (3 km d/s of Subansiri Middle dam site, operational since June 2000), Deo Nallah (situated at around 300 m d/s of Subansiri Lower dam site, operational since October 2000) and Chouldhowaghat (operational since December 2000). A G&D site has also been established on Pein River, which joins Kamla near Tamen Bridge. A gauge site is at Ferryghat, which is around 1.9 km d/s of

41

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

proposed Subansiri Lower dam site. At present, floats are being used to measure the velocity. Current meters are also used mainly in lean season. 5.2.2 Methodology The following methodology thought up to apply to obtain water availability series at proposed dam site. 5.2.2.1 Rainfall Runoff Relationship First option is to generate discharge series on the basis of rainfall data available in the basin. A rainfall-runoff regression analysis could be performed in Naba basin and the relationship so developed could be used to compute the discharge at proposed dam site. However this could not be done due to non-availability of discharge as well as rainfall for Naba sub basin. A runoff factor of 0.73 had been established after detailed rainfallrunoff analysis in Subansiri basin as discussed in feasibility report of Subansiri Upper Project. This factor could be used to compute runoff from rainfall. This methodology could also not be adopted because of the nonavailability of discharge and rainfall data within the Naba sub-basin. 5.2.2.2 Based on Discharge Series at Subansiri Upper Dam site Water availability study in Subansiri at Menga had been performed considering entire Subansiri river system as one, so as to maintain consistency in the flow at all the observation sites. After detailed analysis a 20-year synthetic flow series had been obtained at Subansiri Upper dam site (CA=20250 sq.km, Rainfed=9564 sq.km). This synthetically generated 20 years discharge series at Subansiri Upper dam site may be transferred to Naba dam site on the basis of Catchment proportion considering the two basins as hydro-meteorologically homogeneous. The catchment correction factor has been worked out as 0.504.

42

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

For the present, the second methodology (catchment proportion) has been adopted. The discharge series so obtained has been checked for the consistency with the rainfall data available near Naba basin. The runoff factor thus worked out as 0.72. However, this factor has been computed based on non-concurrent data base, therefore, detailed analysis need be done on availability of concurrent rainfall-runoff within the basin. The average 10 daily flow series at proposed dam site has been placed as Annexure-5.2. Average annual yield of at proposed dam site has been worked out as 9761.6 Mcum. After establishing gauging station near proposed dam site with proper raingauge network in Subansiri Upper basin, detailed water availability study need be conducted in feasibility stage/DPR stage.

5.3

RESERVOIR ELEVATION AREA CAPACITY CURVE

The reservoir elevation-area-capacity curve at proposed dam site has been obtained on the basis of 1:50000 toposheets at 40 m contour interval. Area under various contours at 40 m interval has been measured from the elevation of 960 m to 1120 m. The volume between any two elevations is calculated using the conical formula : V = (A1+A2+A1A2)*H/3 Where V = The volume between two contours H = Contour interval A1 = Area at level of first contour A2 = Area at level of second contour

43

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

The incremental volumes thus obtained are added to obtain cumulative volume. The reservoir elevation-area-capacity curve at proposed dam site is given in Figure-5.1. This curve is subjected to modification after availability of reservoir cross-sections or 1:15000 scale contour maps for the catchment. 5.4 DESIGN FLOOD

Design Flood for a project can be estimated by following approaches: (i) (ii) (iii) (i) Deterministic approach using Unit Hydrograph technique. Statistical approach using Flood frequency analysis Empirical methods Deterministic Approach Using Unit Hydrograph Technique Due to non-availability of G&D data, short term rainfall, hourly gauges etc, design storm values in the proposed catchment, rating curves and observed flood hydrographs could not be obtained for computing the Unit Hydrograph and Design Flood hydrograph. However, this approach has been used partially while transferring the flood of Subansiri Upper dam site to the proposed dam site. (ii) Statistical Approach Using Flood Frequency Analysis Due to non-availability of long term, consistent G&D data near the proposed scheme, flood frequency analysis could not be performed at the project site. (iii) Empirical Methods The following empirical relationships have been used to estimate the design flood peak:

44

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Dickens Formula Q = CA 3/4

Where, C = Dickens constant with value between 11-14 for NorthIndian Hilly catchment. A value of 14 has been adopted in present study. A = Catchment area in sq.km Therefore Q = 14 x 4816 3/4 = 8094 cumec Fullers Formula Qmax = C.A 0.8(1+0.8logT)*(1+2.66A-0.3) Where, C = constant varying between 0.026 to 2.77 (2 adopted) in cumec A = Catchment Area in sq.km 1000 year Flood Q1000 =2 * 48160.8(1+0.8log(1000))*(1+2.66*4816-0.3) = 7262 cumec Ali Nawaz Jung Formula Q = C(0.386A)(0.925-1/14log0.386A) Where C = 49 to 60 (55 adopted) Q = 55* (0.386*4816)(0.925-1/14log(0.386*4816)) = 10023 cumec Qmax = Maximum 24-h flood with a frequency of T years

45

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Transferring design flood at Subansiri Upper dam site on the basis of Dickens formula. 1-Day and 2-day PMF of 12226 cumec and 15210 cumec has been estimated at Subansiri Upper dam site (CA=20250 sq.km, Rainfed Area = 9564 sq.km). A base flow (including snow melt) of 3000 cumec had been assumed during computation of design flood by deterministic approach. The Naba H.E. Project is located upstream of this dam site. Catchments of both the projects can be considered as hydro-meteorologically homogeneous. Therefore, it seems logical to transpose the design flood value of Subansiri Upper dam site to proposed dam site. This transposition has been done by Dickens formula using a conversion factor of 0.598 at proposed dam site. The design flood based on 1-day PMF and 2-day PMF at Subansiri Upper dam site thus computed as 10308 cumec and 12092 cumec respectively.

A comparative study of flood peak computed by various methods is placed as Table-5.3. TABLE- 5.3 FLOOD COMPUTED BY VARIOUS METHODS S.No. 1 2 3 4 5 Method Dickens Formula Fullers Formula Ali Nawaz Jung Formula Transposition of 2-day PMF on the basis of Dickens formula. Transposition of 1-day PMF on the basis of Dickens formula. 10308 Flood Peak (cumec) 8094 7262 10023 12092

46

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Based on above mentioned studies summarized in Table-5.3, for prefeasibility stage study, a design flood of 12000 cumec at dam site of the proposed project has been recommended. It is worth mentioning here that although deterministic approach of design flood computation has not been used in the present study for Naba sub basin, however, this approach has been used partially, as the design flood at Subansiri Upper dam site had been computed by this method only. The detail of design flood study may be referred in feasibility report of Subansiri Upper Project. On availability of more data/information, design flood need be estimated by deterministic approach using unit hydrograph technique and probabilistic approach using flood frequency analysis in feasibility stage/DPR stage. 5.5 RESERVOIR SEDIMENTATION

A rate of sedimentation of 0.057 Ham/Sq.km/Year has been established for Subansiri too. Detailed sediment study need be done during feasibility stage with more observed data at the proposed site using a suitable method. basin based on suspended sediment observations at Chouldhowaghat site. This silt rate may be adopted for Subansiri at Naba

47

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

5.6

RECOMMENDATIONS FOR FUTURE STUDIES

The following are the improvements suggested for feasibility/DPR stage study: Proper raingauge network along with Gauge-discharge-sediment observation sites on Subansiri river near proposed dam site need be established before taking up preparation of feasibility report /DPR. After establishing gauge and discharge site on Subansiri river with proper raingauge network in Subansiri Upper basin, detailed water availability study need be conducted in feasibility/DPR stage. The reservoir elevation area capacity curve need be revised after availability of reservoir cross-sections or 1:15000 scale contour maps in feasibility/DPR stage study. On availability of more data/information, design flood need be estimated by deterministic approach using unit hydrograph technique and probabilistic reservoir approach using flood study frequency need be analysis done in feasibility/DPR stage. Detailed sedimentation during feasibility/DPR stage with observed data on Subansiri river at the proposed dam site using a suitable method. The observations of CWC along with reply of NHPC have been enclosed as Annexure-5.3 and need be referred during feasibility/DPR stage.

48

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Figure 5.1 RESERVOIR ELEVATION AREA CAPACITY CURVE

Reservoir Elevation Reservoir Capacity (metre) Area (ha) (Mcum)


170 160 150 140 130 120 110

<----- Capacity (Mcum) 100 90 80 70 60 50 40 30 20 10 0 1120 1100 Capacity Curve Area Curve 1080 1120 1100 1080

945 960 1000 1040 1080 1120

0.00 12.29 38.98 87.32 160.57 247.78

0.00 0.61 10.37


-----> Elevation (m)

34.99 83.83 164.87

1040 1020 1000 980 960 940 0 15 30 45 60 75 90 105

1040 1020 1000

Note : This curve is applicable for pre-feasibility stage only.

980 960 940 255

120

135

150

165

180

195

210

225

240

-----> Area (Ha)

49

-----> Elevation (m)

1060

1060

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER-VI CONCEPTUAL LAYOUT AND PLANNING


6.1 6.1.1 FINALISATION OF CONCEPTUAL LAYOUT CEA Proposal

The Naba H.E. Project is one of the new schemes identified by CEA in ranking study. As per CEAs proposal Naba H.E. Project is located immediately downstream of the power house of Niare H.E. Project on river Subansiri (called Si Ngit in upper reaches). It is a run of river scheme, which consists of diversion structure at river bed level EL 1000 m, a 11.5 km long channel and a power house with tail water outfall at river bed level EL 800 m. The scheme would utilize a gross head of about 200m and enable a firm power of 308 MW with optimum economic installed capacity of 1290 MW. The scheme would give benefit of annual energy of about 6038 GWh and 6915 GWh respectively in 90% and 50% dependable years. (Refer Annexure 2.1). 6.1.2 NHPC Proposal The proposed Naba H.E. Project site was inspected by NHPC Officers. Based on the topographical input (SOI topo sheet no 82H/11 in 1:50000 scale) and geological appraisal from Geological Survey of India and project authority, the proposal was prepared by NHPC and discussed with CEA/ CWC. The details of proposal are as under. The dam site location as proposed by CEA at river bed level EL 1000m is shifted about 3.3 km downstream near Badok at river bed level EL 945m, where river has carved out moderate U shaped valley with rocky abutments on both flanks. Power house location was considered with tail Based on topography, geology race outfall at river bed level EL 800 m.

50

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

of the area and presence of loops in river, head race tunnel is proposed on left bank as water conductor system instead of 11.5 km long power channel as proposed by CEA. During discussions with CEA / CWC, the NHPC proposal was found to be in order and NHPC was advised to proceed with preparation of PFR. (Refer Annexure 2.2 & Annexure 2.3) Alternative Studies a) Location of Dam axis Three alternative dam sites, namely, alternative-1, alternative-2, and alternative-3 located 1.8 km u/s, 0.2 km u/s, and 1.5 km d/s of IGMI Siko nallah respectively have been considered (location as indicated on Plate 6.1). At these locations the river bed level is about 1000 m, 965 m and 945 m respectively. Taking into account topographical, geological conditions and layout of the project, the dam axis (alt- 3) is preferred and ,as such, adopted for PFR preparation. Needless to mention that during detailed investigation for DPR preparation location of dam axis shall need to be reviewed. b) Location of Power house and layout of water conductor system Alternative of laying water conductor system on left as well as right bank of the river were examined. Keeping in view the existing river topography between proposed dam and power house locations, aligning the water conductor system on left bank results in shorter length. As such, the same has been adopted. During initial discussions with CEA for vetting of layout of the project, power house location was considered with tail race outfall at river bed level EL 800m. Subsequently, alternative location of power house with tailrace

51

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

outfall at EL 770m was also considered. The length of water conductor system in two alternatives works out to be 9.0 km and 10.5 km respectively. Thus, by providing about 1500 m long additional water conductor system, an additional head of 30m can be utilised. Accordingly, power house location with tail race outfall at river bed level EL 770 m has been adopted for PFR. Final layout of the project has been developed with dam at river bed level EL 945m, Power house with tail race out fall at river bed level EL 770 m and 9.75/9.80 km long water conductor system is proposed for PFR studies. Based on the topographical details (toposheets no 82 H/11 1: 50,000 scale) & geological details project layout has been developed. Various components of the project are: a) River diversion works comprising of 2 nos of 10.5 m diameter horseshoe shaped diversion tunnel with u/s and d/s cofferdams. b) c) 110 m high concrete gravity dam from deepest foundation level. Water conductor system consisting of i) ii) iii) iv) v) vi) d) 2 nos Intake structure. 6 nos 300m (L) X16m (W) X23m (H) Desilting chamber. 2 nos 8.7m diameter horseshoe shaped headrace tunnel. 2 nos 23 m diameter surge shaft 2 nos of pressure shaft with 7.25 m dia each feeding 2 units. 2 nos 8.7 m diameter horseshoe shaped tailrace tunnel.

An underground power house consists of i) ii) 136m (L) X 23 m (W) X 48 m (H) powerhouse cavern 100 (L) X 20m (W) X 25m (H) transformer cum Draft Tube gates cavern iii) 100 m (L) X 12 m (W) X 16m (H) MIV Cavern.

e)

Pothead yard 50 m x 100 m.

52

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Proposed general layout-plan and longitudinal section are enclosed as Plate-6.1& Plate-6.2. 6.2. PRELIMINARY DESIGN FEATURES

6.2.1 River Diversion Works 6.2.1.1 Diversion Tunnel No G&D data of river Subansiri near proposed location of Dam axis is available. As such, considering diversion discharge as worked out in case of Subansiri upper project located on d/s, the diversion tunnels shall be designed for passing a assumed non-monsoon flood of 2500 cumec. For the construction of concrete gravity dam and appurtenant works, the river diversion is proposed to be carried out through 2 nos of 10.5 m diameter concrete lined, horseshoe shaped diversion tunnels located on the right bank of the river. The length of diversion tunnels shall be about 700 m. 6.2.1.2 Coffer Dam

To facilitate river diversion, upstream and downstream cofferdams with central impervious core shall be provided. These coffer dams shall be located about 100 m u/s and 250 m d/s of the proposed dam axis. The height of u/s and d/s cofferdams shall be 25 m and 14m respectively. As the diversion scheme has been proposed to be designed to cater for nonmonsoon flood, cofferdams may get damaged during monsoon period and as such, shall require rebuilding before undertaking works in subsequent working season. 6.2.2 6.2.2.1 Dam Dam Location

Various alternative locations for dam axis were examined as indicated in para 6.1.2 above. At location near Badok about 3.3 km d/s of dam location

53

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

as proposed by CEA , river has carved out a moderate U-shaped valley with rocky abutments on both flanks exhibiting outcrops of biotite geneiss. As such this site has been adopted for PFR. 6.2.2.2 Type of Dam The IS code stipulates consideration of 1 in 100 year monsoon flood for diversion in case of an embankment dam and 1 in 25 years non-monsoon flood for concrete dam. Further, for effective reservoir flushing, requirement of low-level spillway necessitate provisions of concrete dam. In view of above, preliminary feasibility of the project has been examined with concrete gravity dam. However, it may be mentioned that based on the topographical and geological data collected during feasibility stage, if required, type of the dam shall be reviewed. 6.2.2.3 Fixation of FRL and MDDL The bed level of tailrace outfall of proposed Niare H.E. Project located upstream is EL 1045m, keeping the difference of about 10 m between tailrace outfall bed level of upstream project & FRL, the FRL for Naba project has been proposed as EL 1035 m. Needless to mention that during FR/DPR stage considering the finally adopted parameters of upstream Niare H.E. Project, FRL of Naba H.E. Project shall need to be optimized to minimize loss of head. MDDL has been fixed at El 1022 m considering proposed power intake level and power potential studies. 6.2.2.4 Dam Arrangement The proposed dam is concrete gravity dam across the river with dam top at El 1040 m. The deepest foundation level has been assumed as El 930 m i.e. 15 m below the river bed level (overburden and weathered rock). The dam is divided in blocks of 16 /15 m width each. The central 9 blocks shall

54

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

be overflow / spillway blocks of 16/15 m width flanked by non-overflow blocks on either side of 15 m each Spillway Spillway for concrete dam is proposed to be designed for a probable maximum flood (PMF) of 12000 cumec. Seven bays of low level orifice type spillway (inclusive of 1 bay as emergency) have been proposed with crest at EL 990 m and spillway opening size 8.25 m x 10 m. In addition two bays of upper level crest type spillway have also been proposed with crest at EL 1025 m and spillway opening size 8 m x 10 m. Total length of spillway structure shall be 142m. Non Overflow Blocks The non-overflow blocks have been provided with top width of 12 m and downstream slope of 1.1 H: 1V. An upstream slope of 1H: 4V has been provided below the level of El 1020 m. Proposed layout plan of dam area, upstream elevation and cross sections of concrete dam are enclosed as Plate- 6.3, 6.4 & 6.5. 6.2.2.5 Energy Dissipation Arrangement

A ski-jump type energy dissipation arrangement has been provided downstream of spillway with flip bucket having lip angle of 300. It may be mentioned that lip of the bucket shall be kept above maximum water level (to be finalized subsequent to development of stage discharge curve at dam site during DPR stage). A preformed plunge pool of size 100 m (L) x 160 m (B) has been provided. 6.2.3 Water Conductor System 6.2.3.1 Head Race Tunnel Intake The water is led to two nos of headrace tunnels through two nos of intake structures with invert at El. 1000 m. The invert has been kept 10 m above

55

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

the spillway crest to minimize silt entry in water conductor system. An inclined type trash rack structure is proposed at the entrance of the intake structure with a trash rack cleaning machine. 6.2.3.2 Desilting chamber

In order to remove particle having size more than 0.2mm, desilting chamber has been proposed. Desilting chamber shall have six chambers (Three each for two nos of headrace tunnel) each of size 300m (L) X 16 m (W) X 23 m (H). 2 nos. of 9.8 m dia intake tunnel about 450 /270 m long each has been proposed between HRT intake and desilting chamber. Each intake tunnel trifurcates into 5.6 m dia feeder tunnel feeding the desilting chamber. Tunnel of size 5.0 m dia has been provided after each desilting chamber and three tunnels of 5.0 m dia combines into HRT of 8.7 m dia. For flushing out of accumulated silt, each desilting chamber has been provided with silt flushing tunnel of size 2.5 m (W) X 2.0 m (H). Three silt flushing tunnel combines to one SFT of size 4.0 m dia. 6.2.3.3 Head Race Tunnel

2 nos of 8.7 m diameter horseshoe shaped headrace tunnels have been proposed on the left bank of the river. The length of the tunnel shall be about 9.75 / 9.80 km. Three 6.5 m (D shaped) intermediate adits each about 400 m in length (average) have been proposed to facilitate construction of the HRT. Rock bolts, shotcrete with wire mesh has been proposed as tunnel support system. Provision of steel rib support has also been kept to take care of poor rock strata wherever encountered. The tunnels shall be 600 mm thick concrete lined.

56

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

6.2.3.4 Surge Shaft 2 nos of 23 m diameter concrete lined and 110 m high circular restricted orifice type surge shaft with gate has been proposed. Rock bolts, shotcrete with wire mesh has been proposed as shaft support system. Surge Shaft shall be concrete lined (1000 mm thick). 6.2.3.5 Pressure Shaft

Downstream of each Surge Shaft, a 7.25m diameter steel lined pressure shaft with 181 m vertical drop has been proposed. Pressure shaft consists of a 50 m horizontal portion at top and 50 m horizontal portion at bottom. The center line elevation of lower horizontal portion has been kept at El 765.5 m i.e. center line of turbine. After horizontal portion at bottom, each 7.25 m dia pressure shaft bifurcates into two penstocks of 5.0 m dia suitably connected to main inlet valve to each unit of powerhouse. 6.2.3.6 The Draft Tube and Tail Race Tunnel

water from turbine shall be discharged back to river through

draft tubes and tailrace tunnels. 2 nos of 4.2 m (W) x 6.0 m (H) draft tube gate opening with 2 m wide intermediate pier for each unit shall be provided. After the draft horseshoe tube gates, opening of two units shall be combined and thus discharge from four units shall be led to two shaped concrete lined tail race tunnels each of 8.7 m dia. The TRT shall be about 90/100 m long with suitable outlet arrangement. Rock bolts, shotcrete with wire mesh has been proposed as tunnel support system. Provision of steel rib support has also been kept to take care of poor rock strata wherever encountered. The tunnel shall be 600 mm thick concrete lined. Proposed typical cross-section of water conductor system is enclosed as Plate 6.6.

57

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

6.2.4

Power House

No flat terrace is available on left bank of river Subansiri to provide surface powerhouse. As such based on topography an underground powerhouse has been proposed. It may be mentioned that the location and orientation of power house shown in PFR is indicative only and shall need to be finalized during FR/ DPR stage based on collected detailed topography and geological data. 6.2.4.1 Power House Cavern

Underground powerhouse cavern has been proposed to house four units of 250 MW each. The size of power house cavern will be 23 m (W) x 136m (L) x 48 m (H). Four bus shafts, one for each unit, of 6 m x 6 m shall be provided connecting the powerhouse cavern to transformer cavern. Further, 8 m x 8 m D-shaped gallery is also proposed between powerhouse cavern to transformer cavern to facilitate toeing of transformers between service bay and transformer cavern. Rock bolts, shotcrete with wire mesh has been provided to support the roof arch and the wall of the cavern. Provision of pre-stressed anchors on downstream wall has also been kept. In addition 600 mm thick concrete lining in roof arch and 300 mm in wall has been provided. MIV is proposed to be housed in separate cavern (100mx12mx16m) located upstream of powerhouse cavern. 6.2.4.2 Transformer Cum Draft Tube Gate Cavern

Transformer cavern has been proposed on downstream of PH cavern to house the transformers. The size of cavern is proposed to be 20 m (W) x 100 m (L) x 25 m (H). Transformer cavern shall also facilitate housing of (a) GIS and (b) draft tube gate hoisting arrangements.

58

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Rock bolts, shotcrete with wire mesh has been provided to support the roof arch and the wall of the cavern. In addition, 500 mm thick concrete lining in roof arch and 300 mm in wall, has been provided. Cable cum ventilation tunnel is proposed to connect the transformer cum Draft Tube gate cavern to pothead yard. The size of tunnel shall be 8 m Dshaped. Proposed layout plan and cross-section through Power House are enclosed as Plate 6.7 & 6.8. 6.2.5 Pothead Yard Pothead yard is proposed on left bank. The size of pothead yard will be 50 m (W) x 100 m (L). 6.2.6 Hydro mechanical Equipment Following hydro-mechanical equipment have been envisaged for Naba Hydroelectric Project. 6.2.6.1 Diversion Tunnel Gate and Hoist

After the construction of the dam, for the purpose of plugging the diversion tunnel, four nos. (two nos. for each tunnel) fixed wheel type gates will be provided at the inlet of the tunnel. The gates shall be operated by means of electrically operated rope drum hoists located on the hoist platform installed over the trestles above deck level. The gate is meant for one time closure, just before plugging of the tunnel. 6.2.6.2 Lower Spillway Radial Gates, Hoists, Bulkheads and Gantry Cranes. Seven numbers submerged type radial gates shall be provided to regulate the water level in the reservoir. Each gate shall be operated by means of

59

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

suitable capacity hydraulic hoist from a power pack and two cylinders one on each end of the gate. One trolley mounted mobile gasoline engine operated power pack capable of operating one gate at 25% of the normal rated speed is envisaged for emergency operation of spillway radial gates. One portable oil filter unit for filtration, dehydration & degasification of hydraulic oil is also being provided. One number fixed wheel type bulkhead gate has been envisaged to cater to the maintenance requirement of seven numbers spillway radial gates. The bulkhead gate shall be able to be lowered under unbalanced / emergency / flowing water condition corresponding to MDDL by means of a suitable Capacity Gantry crane. 6.2.6.3 Upper Spillway Radial Gates, Hoists, Stoplogs and Gantry Crane Two numbers radial gates shall be provided to control the discharge through the gated portion of the spillway. Each gate shall be operated by means of suitable capacity hydraulic hoist from a power pack and two cylinders one on each end of the gate. One set of slide type stoplog has been envisaged to cater to the maintenance requirement of two numbers spillway radial gates. The stoplogs shall be operated under balanced head condition by means of a suitable Capacity Gantry crane with the help of a lifting beam. Storage grooves should be provided on the dam top to store the stoplog units. 6.2.6.4 Trash Rack and Trash Rack cleaning Machine Upstream face of each intake shall be provided with the trash rack screen, which will be cleaned by means of a trash rack-cleaning machine.

60

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

6.2.6.5 Intake Gate and Rope Drum Hoists Two numbers fixed wheel type gates shall be provided just downstream of the bell mouth of the intake tunnels. The intake gate is to be designed for self lowering against upstream water level corresponding to FRL. The gate shall be operated by means of electrically operated rope drum hoist of suitable capacity. 6.2.6.6 Desilting Chamber Gates & EOT Cranes Six numbers Fixed Wheel type gates shall be provided at the inlet of desilting chamber for the maintenance requirement of desilting chambers. The gates shall be lowered / raised under unbalanced / flowing water condition corresponding to FRL by means of suitable capacity electrically operated rope drum hoists. Two numbers slide type gates shall be provided at the outlet of desilting chambers to isolate the chambers for the maintenance requirements. The gate shall be lowered / raised under balanced head condition by means of suitable capacity EOT Crane with the help of lifting beam. 6.2.6.7 Flushing Tunnel Gates & Hoists In Six silt-flushing tunnels, each tunnel is provided with a set of two slide (Emergency & Service) gates for regulating the discharge through flushing tunnels. Both the (Emergency & Service) gates shall be operated by means of hydraulic hoists comprising of individual double acting cylinder and a common power pack. The gate grooves are provided with bonnet structures embedded in the concrete and a watertight bonnet cover at the top of the groove.

61

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

6.2.6.8

Surge Shaft Gate

The intake of pressure shaft is provided with a slide type gate. The gate shall be operated under balanced head condition by means of an electrically operated rope drum hoist. 6.2.6.9 Draft Tube Gates To isolate turbines from the tail race tunnel to cater to the inspection / maintenance requirements of turbines, eight numbers Fixed Wheel type draft tube gates (two for each unit) have been envisaged. The gates shall be operated under balanced head conditions by suitable capacity Gantry Crane with the help of lifting beam. 6.2.6.10 Adit Inspection Gates Three nos. adits shall be provided with manually operated hinged type gates in the concrete plug at the HRT construction to give access to the head race tunnel in the event of any inspection, repair and maintenance. 6.2.6.11 Pressure Shaft Steel Liner Two no. Pressure Shaft of dia. 7250 mm fully steel lined will take off from d/s of concrete transition of surge shaft gate to feed the turbine placed in the powerhouse. It comprises horizontal & vertical ferrules, 2 nos. vertical bends, 3 nos. plan bends, 1 no. bifurcation and branch pipes for each pressure shaft to feed four turbines. The material of Pressure Shaft liner shall conform to ASTM A537 Class 1. However for bifurcation material shall conform to ASTM A517 Gr. F. 6.2.6.12 Instrument and Remote Control

Gates shall be provided with PLC based remote control system for Control and operation of gates and automatic control of the reservoir level.

62

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

6.2.6.13 Diesel Generating Set One diesel generating set complete with all accessories, equipment, instrument and wiring will be provided for emergency operation of gates and hoists. 6.3 FURTHER STUDIES REQUIRED

Following are some of the studies required to be undertaken during the preparation of feasibility report / detailed project report: Optimisation / finalisation of location of dam and its height based on topographical and geological inputs Optimisation / finalisation of layout of water conductor system based on topographical and geological inputs Optimisation / finalisation of location and orientation of powerhouse based on topographical and geological inputs Evaluation of engineering properties of rock mass. Transient analysis Detailed design computation to fix size of various components of the project. Integrated reservoir operation and power potential studies of Naba HE Project with other Subansiri Basin projects. The observations of CWC along with reply of NHPC have been enclosed as Annexure 6.1 & 6.2 are need be referred during Feasibility/DPR stage.

63

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER - VII POWER POTENTIAL STUDIES

7.0

INTRODUCTION

The Chapter contains the optimization of power potential of the Naba H.E. project on the basis of the discharge data for the synthetic year 1-2 to year 19-20 (19 Years). Naba H.E. Project is located on Subansiri/Si Ngit River in Upper Subansiri district of Arunachal Pradesh. It is essentially a run-offthe-river scheme. The installed capacity of Naba H.E. Project has been proposed as 1000 MW comprising of four (4) units, each of 250 MW in the underground type power house. The salient features of the project are as follows: Installed capacity No. & size of unit Type of power house Net head Design discharge per unit Type of switchyard Turbine type Speed of turbine Generation voltage Transmission voltage GSU Transformer Energy generation in 90% dependable year with 95% Machine availability = 3995.25 MU = 1000 MW = 4 units of 250 MW = Underground type = 221 meters = 125.4 Cumecs = 400 KV GIS = Vertical Francis = 214.3 rpm = 16 KV = 400 KV = 13 Nos, 102 MVA, Single-phase

64

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

7.1

AVAILABLE DATA

The Power Potential studies have been carried out based on following data a) Discharge Data b) FRL, MDDL & TWL Levels and Head losses. c) Due to non availability of evaporation loss, evaporation loss has not been accounted for in the power potential study. 7.2 DISCHARGE DATA

Inflow series of 19 years i.e. 1-2 to 19-20 has been obtained and used for carrying Table-7.1. Table-7.2. 7.3 FIXATION OF FRL LEVEL out power potential and optimization studies. inflow is The 10-daily applied for discharge data in cumecs for all 19 years is shown in the enclosed The criterion of 90% dependable conducting power potential studies and inflow of same is shown in

The FRL level has been fixed at EL. 1035.0 m based on the consideration that the tailrace outfall of upstream proposed Niare H.E. Project is at EL. 1045.0 m. 7.4 FIXATION OF MINIMUM DRAW DOWN LEVEL (MDDL)

The choice of MDDL has mainly been based on firm power requirement, requirement of dead storage with regard to sedimentation, water cover to intake structure. the MDDL has been fixed at EL.1022.0 m. 7.5 FIXATION OF TAIL WATER LEVEL (TWL)

The River bed level at proposed tailrace outfall level of this project is around 770 m. As no tailrace rating curve is available, as such a margin of

65

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

10 m has been kept to arrive at max. TWL. The same will also help in future optimization of the power house location. All these values shall require to be reviewed during detail investigation of the power house complex and Tail race vis--vis Topographical and geological features of the area. 7.6 OPERATING HEAD AND HEAD LOSSES

The FRL Level is fixed at EL 1035.0 m while the average tail water level corresponding to 4 units running has been taken as 780.0 m. Head losses in the water conductor system have been taken as 12% of the gross head. The net operating head for turbines has been calculated from the following formula, Net Operating Head: = MDDL+2/3(FRL MDDL)-Max. Tail Water level Head Losses Thus, by above-mentioned formula, the net operating head works out to be 221 m. 7.7 DEFINITION OF TERMS

7.7.1 90% Dependable Year This is the lower decile of the series of the corresponding monthly period of the record i.e. (N+1) x 0.90th year where N is the years for which hydrological data are available. 90% dependable year comes out to be 10-11 as shown in Table 7.3. 7.7.2 Annual Design Energy This is the yearly energy generated during the 90% dependable year i.e. year 10-11 with 95% machine availability, which works out to be 3995.25 MU as shown in Table-7.4.

66

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

7.8

INSTALLED CAPACITY

The installed capacity of the Power house has been selected based on the following considerations Assessment of the energy generation with various installed capacities. Maximum utilization of the available inflow. Incremental value of energy generation with the increased installed capacity. Annual Load factor. Lean season load factor.

The power potential study has been carried out for different installed capacities ranging from 300 MW to 1800 MW with an increment of 100 MW, as shown in Table-7.5. Based on the above-mentioned parameters, the installed capacity of the power plant has been selected as 1000 MW. Taking installed capacity as 1000 MW, the Annual load factor comes out to be 46.46% while the monsoon season load factor & lean season load factor are 57.95% & 11.33% respectively as shown in enclosed Table-7.5. 7.9 SIZE OF GENERATING UNITS

The power load demand in India is increasing at a very rapid rate, and both hydro electric and thermal (including nuclear) power potential in the country are being developed not only to meet the overall requirements, but simultaneously also to provide a proper hydro and thermal power for optimum operation of the system. Keeping this in view current practice is to opt for largest size hydro units permissible within the parameters of economy, operating efficiency, maintenance, optimum utilization of available water, transport limitations etc. Based on the above-mentioned parameters, 4 No. Units of 250 MW each have been proposed for this project.

67

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

7.10

ANNUAL ENERGY GENERATION

The restricted energy generations for the 90% dependable year i.e. year 10-11 have been shown in the enclosed Table-7.3 & 7.4. Further, It may be seen from the enclosed Table-7.4 that the total annual energy generation in the 90% dependable year with 95% machine availability restricted to an installed capacity of 1000 MW is 3995.25 MU. The observations of CEA along with reply of NHPC have been enclosed as Annexure 2.4, Annexure 7.1 and Annexure 7.2 and needed to be referred during feasibility/ DPR stage. All the suggestions made by CEA have been incorporated in the report.

68

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE - 7.1
DISCHARGE DATA (Cumecs) Month 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10 10-11 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20

1-10 473.20 544.26 262.06 257.52 457.95 200.89 284.09 1082.09 194.58 137.52 245.60 329.74 314.48 481.44 149.69 606.35 140.34 128.73 586.97 JUNE 11-20 822.96 696.51 417.37 484.89 716.76 219.73 333.25 1352.80 185.40 286.05 278.47 401.06 296.49 821.62 280.37 421.86 179.87 168.78 898.82 21-30 1253.22 838.89 438.41 640.21 810.76 272.32 476.21 1212.87 298.91 354.15 259.09 573.02 534.51 1098.73 427.40 425.49 268.54 325.11 911.10 1-10 617.04 718.20 514.41 769.17 1043.47 517.27 557.65 1415.85 855.52 583.45 396.90 679.86 470.20 684.26 936.77 370.18 304.33 382.05 1073.07 JULY 11-20 968.49 722.85 504.10 1249.70 935.96 414.16 803.37 1562.41 667.11 449.94 685.21 542.47 737.61 808.14 876.77 307.27 589.13 726.77 1300.06 21-31 840.70 586.24 401.03 948.06 748.44 647.65 986.33 1967.92 956.15 716.32 500.66 888.69 583.48 989.15 769.48 342.95 733.00 654.06 1711.51 1-10 950.67 479.94 451.37 750.16 691.73 669.63 316.77 620.06 819.52 377.34 510.88 412.65 917.66 703.88 769.21 539.45 810.29 449.94 539.75 AUGUST 11-20 927.75 525.63 470.13 594.08 606.86 743.72 404.56 699.85 1047.00 578.96 558.89 560.56 1198.11 746.43 692.83 828.63 1075.70 415.96 603.60 21-31 599.93 604.15 865.87 487.21 736.37 680.57 373.81 766.92 775.26 516.35 922.27 991.57 763.10 705.87 606.52 904.31 1285.73 420.94 970.80 1-10 552.02 352.94 1366.81 350.68 458.03 532.00 287.79 640.25 581.13 369.22 871.13 749.15 389.15 637.23 331.81 669.19 1071.86 428.65 694.68 SEPTEMBER 11-20 696.42 593.02 1232.28 310.28 382.90 410.61 351.05 458.10 523.68 688.33 953.79 791.70 363.88 463.66 365.97 523.47 758.31 395.60 564.10 21-30 420.30 515.14 944.42 404.68 428.09 333.48 404.86 638.45 566.09 864.90 763.57 583.79 290.14 425.77 352.08 692.47 828.77 310.97 379.13 1-10 242.35 259.57 565.71 280.00 602.35 540.63 367.40 514.72 626.73 485.69 639.36 338.36 548.16 521.61 288.65 412.18 376.64 439.27 333.62 OCTOBER 11-20 427.50 248.96 388.61 393.47 600.51 489.84 193.20 555.14 267.92 258.69 242.57 376.68 238.15 265.57 216.22 252.83 410.92 439.83 334.37 21-31 233.52 226.98 281.22 217.09 292.18 253.23 155.36 252.18 279.31 151.47 227.81 190.67 197.34 155.87 190.30 179.12 322.89 262.46 305.91 1-10 148.73 214.92 171.08 123.87 147.04 196.47 141.81 250.10 156.84 111.54 164.52 115.94 159.39 163.12 209.29 184.11 192.53 156.94 153.09 NOVEMBER 11-20 108.01 182.19 103.34 101.25 117.24 114.21 155.35 214.11 164.06 130.34 141.04 109.91 151.44 139.61 172.21 165.56 115.82 99.05 92.28 21-30 116.62 105.17 115.27 93.63 100.43 98.97 140.62 141.01 102.32 92.11 127.92 90.08 111.80 100.30 119.16 125.61 79.72 85.66 91.25 76.90 97.89 116.47 75.79 103.93 77.94 136.16 89.27 70.77 79.16 86.50 98.76 75.54 104.68 129.02 85.76 80.48 102.25 111.50 1-10 DECEMBER 11-20 77.39 77.98 98.36 82.47 75.84 79.80 92.92 94.47 73.55 64.41 101.32 75.63 78.31 116.82 91.60 69.93 67.75 90.82 79.98 21-31 73.13 63.80 84.02 80.55 79.33 65.95 76.71 84.52 61.02 57.86 89.46 67.30 76.08 101.42 77.36 72.21 69.77 85.22 69.07 79.41 67.25 79.56 64.29 67.06 49.36 88.00 76.81 48.83 44.26 103.02 50.91 61.43 105.92 59.15 55.96 69.69 72.25 63.24 1-10 JANUARY 11-20 63.19 73.85 76.44 51.19 70.22 58.96 82.35 61.31 45.78 43.42 103.75 51.29 50.23 95.75 64.94 44.40 70.99 72.75 51.96 21-31 65.15 66.03 69.50 48.25 70.64 65.39 89.01 57.74 48.06 45.19 98.10 56.85 47.70 91.03 71.35 49.42 67.31 67.52 49.52 71.49 68.03 69.10 53.86 84.21 72.42 97.94 51.56 58.79 60.23 88.86 68.11 63.32 119.10 95.09 63.21 77.15 90.45 46.30 1-10 FEBRUARY 11-20 80.50 77.52 66.96 48.92 86.56 67.26 73.05 47.82 74.38 47.19 89.79 50.72 49.79 74.76 92.73 70.00 55.55 98.04 46.20 21-28 76.36 68.44 72.54 67.09 91.07 63.42 75.89 49.87 71.78 74.16 82.42 75.56 63.13 89.60 100.07 70.20 82.30 103.61 59.08 69.40 91.82 82.62 63.97 116.12 79.84 98.12 90.76 118.75 79.75 94.96 97.00 94.71 105.67 112.31 75.89 112.50 92.49 56.58 1-10 MARCH 11-20 78.08 110.31 110.15 65.55 111.40 72.98 91.07 94.83 93.66 113.79 85.22 125.87 128.71 116.23 88.20 84.41 93.21 122.47 66.77 21-31 70.30 127.97 140.29 72.82 91.15 69.64 115.58 83.05 95.26 105.64 97.84 126.68 110.36 101.02 85.97 120.47 81.20 155.05 74.55 1-10 119.23 183.68 155.21 131.60 164.14 111.34 163.44 99.26 117.89 110.33 153.10 155.49 145.48 107.99 157.00 217.32 121.02 190.30 98.34 APRIL 11-20 153.77 147.33 220.42 156.75 158.04 143.21 170.47 174.00 140.46 110.57 176.53 150.03 194.49 105.10 130.25 183.01 115.07 261.47 101.57 21-30 185.89 178.66 290.40 168.01 138.39 177.42 127.46 187.05 142.86 136.03 176.08 166.93 165.82 101.62 200.03 235.94 170.80 189.07 146.41 1-10 230.70 182.08 338.28 232.10 181.69 298.87 286.66 210.44 185.25 286.87 310.45 192.99 209.07 235.15 243.05 242.65 181.94 301.35 190.73 MAY 11-20 369.27 232.13 395.89 286.59 255.30 274.41 438.58 149.48 136.99 347.21 266.78 185.23 207.52 201.89 181.02 189.92 133.88 398.34 190.78 21-31 286.98 172.97 224.67 515.91 163.83 312.55 639.71 238.70 158.93 328.87 149.73 379.33 203.57 123.95 244.89 144.84 109.48 295.99 245.82

69

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-7.2
90% DEPENDABLE YEAR FLOWS FOR POWER GENERATION MONTH / PERIOD 1-10 11-20 21-30 1-10 11-20 21-31 1-10 11-20 21-31 1-10 11-20 21-30 1-10 11-20 21-31 1-10 11-20 21-30 1-10 11-20 21-31 1-10 11-20 21-31 1-10 11-20 21-28 1-10 11-20 21-31 1-10 11-20 21-30 1-10 11-20 21-31 90% dependable year 10-11 flows CUMECS 137.52 286.05 354.15 583.45 449.94 716.32 377.34 578.96 516.35 369.22 688.33 864.90 485.69 258.69 151.47 111.54 130.34 92.11 79.16 64.41 57.86 44.26 43.42 45.19 60.23 47.19 74.16 79.75 113.79 105.64 110.33 110.57 136.03 286.87 347.21 328.87

JUN

JUL

AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

70

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-7.3

NABA H.E.PROJECT
Installed Capacity FRL MDDL 1000 1035 1022 Selected Head Design Discharge Head Losses 221 501.36 12% Overall Effeciency Machine Availability
Monsoon Period Load Factor (%) (March to Nov.) 72.57% 61.93% 64.60% 66.16% 61.98% 64.79% 55.65% 62.57% 59.87% 58.07% 60.70% 62.84% 58.77% 60.34% 55.89% 58.37% 59.60% 57.95% 58.62%

92% 95%
Lean period Load factor (%) (Dec. to Feb.) 34.98% 12.92% 14.67% 16.42% 19.95% 16.08% 14.14% 13.13% 18.92% 12.18% 12.67% 14.63% 12.53% 12.84% 17.42% 18.20% 13.32% 11.33% 17.23%

Sl.No.

Year

Total Inflow (MCM)

Unrestricted Energy (MU)

Energy (with 95% M/C Availability) (MU) 4756.34 4232.21 4458.19 4636.31 4399.52 4500.93 3880.26 4302.83 4262.60 3973.39 4193.79 4341.15 4063.15 4174.83 3990.97 4195.02 4134.97 3995.25 4216.17

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

8-9 19-20 1-2 3-4 14-15 5-6 17-18 12-13 11-12 9-10 4-5 2-3 13-14 16-17 15-16 7-8 6-7 10-11 18-19

14360.43 11775.74 11083.60 10699.60 10557.09 10528.69 9983.47 9638.41 9541.97 9533.03 9456.68 9222.69 9051.20 8807.50 8789.75 8564.54 8357.44 8177.47 7995.12

7956.35 6524.32 6140.84 5928.08 5849.13 5833.39 5531.31 5340.13 5286.70 5281.74 5239.44 5109.80 5014.79 4879.77 4869.94 4745.16 4630.41 4530.70 4429.67

71

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-7.3A

NABA H. E. PROJECT
AVAILABILITY OF UNITS IN KWH/KW FOR INCREMENTAL INSTALLATION IN 90% DEPENDABLE YEAR 10-11

Net Head

221.00

Overall Efficiency

92% LOAD INCREMENTAL FACTOR FOR ENERGY ADDITIONAL KWH/KW CAPACITY %


3917.61 3912.00 3572.87 3057.82 2197.07 1961.85 1653.00 1302.93 1028.42 744.00 679.03 315.88 240.00 240.00 0.00 44.72% 44.66% 40.79% 34.91% 25.08% 22.40% 18.87% 14.87% 11.74% 8.49% 7.75% 3.61% 2.74% 2.74% 0.00%

INSTALLED ANNUAL S. CAPACITY ENERGY NO. MW MU


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 2042.43 2434.19 2825.39 3182.68 3488.46 3708.17 3904.35 4069.65 4199.94 4302.79 4377.19 4445.09 4476.68 4500.68 4524.68 4524.68

LOAD FACTOR %
77.72%

INCREMENTAL ENERGY MU

391.76 69.47% 391.20 64.51% 357.29 60.55% 305.78 56.89% 219.71 52.91% 196.19 49.52% 165.30 46.46% 130.29 43.59% 102.84 40.93% 74.40 38.44% 67.90 36.25% 31.59 34.07% 24.00 32.11% 24.00 30.38% 0.00 28.70%

72

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-7.4

NABA H. E. PROJECT
POWER POTENTIAL IN 90% DEPENDABLE YEAR WITH 95% m/c AVAILABILITY
10-11 Installed Capacity Month 1-10 11-20 21-30 1-10 July-10 11-20 21-31 1-10 Aug-10 11-20 21-31 1-10 Sep-10 11-20 21-30 1-10 Oct-10 11-20 21-31 1-10 Nov-10 11-20 21-30 1-10 Dec-10 11-20 21-31 1-10 Jan-11 11-20 21-31 1-10 Feb-11 11-20 21-28 1-10 Mar-11 11-20 21-31 1-10 Apr-11 11-20 21-30 1-10 May-11 Total Annual L/F 46.46% 11-20 21-31 1000 DISCHARGE ( MCum) 118.82 247.15 305.99 504.10 388.75 680.79 326.02 500.22 490.74 319.01 594.72 747.27 419.64 223.51 143.96 96.37 112.61 79.58 68.39 55.65 54.99 38.24 37.52 42.95 52.03 40.77 51.26 68.90 98.32 100.40 95.33 95.53 117.53 247.85 299.99 312.56 8177.47 L/F monsoon (Mar to Nov) 4432.38 57.95% Net Head DISCHARGE ( Qmecs) 137.52 286.05 354.15 583.45 449.94 716.32 377.34 578.96 516.35 369.22 688.33 864.90 485.69 258.69 151.47 111.54 130.34 92.11 79.16 64.41 57.86 44.26 43.42 45.19 60.23 47.19 74.16 79.75 113.79 105.64 110.33 110.57 136.03 286.87 347.21 328.87 221 UNRESTRICTED POWER ( MW) 274.29 570.55 706.38 1163.74 897.44 1428.74 752.63 1154.77 1029.90 736.44 1372.93 1725.10 968.75 515.98 302.13 222.47 259.97 183.71 157.89 128.47 115.41 88.28 86.61 90.14 120.12 94.12 147.92 159.06 226.97 210.70 220.07 220.54 271.32 572.17 692.54 655.96 Efficiency UNRESTRICTED ENERGY ( MU) 65.83 136.93 169.53 279.30 215.39 377.19 180.63 277.14 271.89 176.75 329.50 414.03 232.50 123.83 79.76 53.39 62.39 44.09 37.89 30.83 30.47 21.19 20.79 23.80 28.83 22.59 28.40 38.18 54.47 55.62 52.82 52.93 65.12 137.32 166.21 173.17 4530.70 L/F non-monsoon (Dec to Feb) Hours from live storage Live storage (Mcm) 92% RESTRICTED POWER ( 100.0 MW) 274 571 706 1000 897 1000 753 1000 1000 736 1000 1000 969 516 302 222 260 184 158 128 115 88 87 90 120 94 148 159 227 211 220 221 271 572 693 656 RESTRICTED ENERGY ( MU) 65.83 136.93 169.53 240.00 215.39 264.00 180.63 240.00 264.00 176.75 240.00 240.00 232.50 123.83 79.76 53.39 62.39 44.09 37.89 30.83 30.47 21.19 20.79 23.80 28.83 22.59 28.40 38.18 54.47 55.62 52.82 52.93 65.12 137.32 166.21 173.17 4069.65 11.33% 4.43 95% m/c Availability 65.83 136.93 169.53 228.00 215.39 250.80 180.63 228.00 250.80 176.75 228.00 228.00 232.50 123.83 79.76 53.39 62.39 44.09 37.89 30.83 30.47 21.19 20.79 23.80 28.83 22.59 28.40 38.18 54.47 55.62 52.82 52.93 65.12 137.32 166.21 173.17 3995.25 8

June10

MW hours

73

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

74

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
1-2 Installed Capacity Month 1-10 11-20 21-30 1-10 July-01 11-20 21-31 1-10 Aug-01 11-20 21-31 1-10 Sep-01 11-20 21-30 1-10 Oct-01 11-20 21-31 1-10 Nov-01 11-20 21-30 1-10 Dec-01 11-20 21-31 1-10 Jan-02 11-20 21-31 1-10 Feb-02 11-20 21-28 1-10 Mar-02 11-20 21-31 1-10 Apr-02 11-20 21-30 1-10 May-02 Total Annual L/F 11-20 21-31 1000 DISCHARGE ( MCum) 408.84 711.04 1082.78 533.12 836.77 799.00 821.38 801.58 570.17 476.95 601.70 363.14 209.39 369.36 221.94 128.50 93.32 100.76 66.44 66.86 69.50 68.61 54.60 61.92 61.77 69.55 52.78 59.97 67.46 66.81 103.01 132.86 160.61 199.32 319.05 272.75 11083.60 52.29% L/F monsoon (Mar to Nov) 64.60% Net Head DISCHARGE ( Qmecs) 473.20 822.96 1253.22 617.04 968.49 840.70 950.67 927.75 599.93 552.02 696.42 420.30 242.35 427.50 233.52 148.73 108.01 116.62 76.90 77.39 73.13 79.41 63.19 65.15 71.49 80.50 76.36 69.40 78.08 70.30 119.23 153.77 185.89 230.70 369.27 286.98 221 UNRESTRICTED POWER ( MW) 943.82 1641.45 2499.64 1230.73 1931.71 1676.83 1896.17 1850.46 1196.60 1101.05 1389.05 838.31 483.38 852.67 465.78 296.65 215.43 232.61 153.39 154.35 145.87 158.38 126.04 129.95 142.59 160.56 152.30 138.43 155.73 140.21 237.81 306.71 370.77 460.14 736.54 572.40 Efficiency UNRESTRICTED ENERGY ( MU) 226.52 393.95 599.91 295.38 463.61 442.68 455.08 444.11 315.90 264.25 333.37 201.19 116.01 204.64 122.97 71.20 51.70 55.83 36.81 37.04 38.51 38.01 30.25 34.31 34.22 38.53 29.24 33.22 37.37 37.02 57.07 73.61 88.98 110.43 176.77 151.11 6140.84 L/F non-monsoon (Dec to Feb) 92% RESTRICTED POWER ( 1000 MW) 944 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 838 483 853 466 297 215 233 153 154 146 158 126 130 143 161 152 138 156 140 238 307 371 460 737 572 RESTRICTED ENERGY ( MU) 226.52 240.00 240.00 240.00 240.00 264.00 240.00 240.00 264.00 240.00 240.00 201.19 116.01 204.64 122.97 71.20 51.70 55.83 36.81 37.04 38.51 38.01 30.25 34.31 34.22 38.53 29.24 33.22 37.37 37.02 57.07 73.61 88.98 110.43 176.77 151.11 4580.59 14.67% 95% m/c Availability 226.52 228.00 228.00 228.00 228.00 250.80 228.00 228.00 250.80 228.00 228.00 201.19 116.01 204.64 122.97 71.20 51.70 55.83 36.81 37.04 38.51 38.01 30.25 34.31 34.22 38.53 29.24 33.22 37.37 37.02 57.07 73.61 88.98 110.43 176.77 151.11 4458.19

June01

75

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
2-3 Installed Capacity Month 1-10 June-02 11-20 21-30 1-10 July-02 11-20 21-31 1-10 Aug-02 11-20 21-31 1-10 Sep-02 11-20 21-30 1-10 Oct-02 11-20 21-31 1-10 Nov-02 11-20 21-30 1-10 Dec-02 11-20 21-31 1-10 Jan-03 11-20 21-31 1-10 Feb-03 11-20 21-28 1-10 Mar-03 11-20 21-31 1-10 Apr-03 11-20 21-30 1-10 May-03 Total Annual L/F 11-20 21-31 1000 DISCHARGE ( MCum) 470.24 601.78 724.80 620.53 624.54 557.16 414.67 454.15 574.18 304.94 512.37 445.08 224.27 215.10 215.72 185.69 157.41 90.87 84.58 67.37 60.63 58.10 63.81 62.76 58.77 66.97 47.31 79.33 95.31 121.63 158.70 127.29 154.36 157.32 200.56 164.39 9222.69 50.95% L/F monsoon (Mar to Nov) 62.84% Net Head DISCHARGE ( Qmecs) 544.26 696.51 838.89 718.20 722.85 586.24 479.94 525.63 604.15 352.94 593.02 515.14 259.57 248.96 226.98 214.92 182.19 105.17 97.89 77.98 63.80 67.25 73.85 66.03 68.03 77.52 68.44 91.82 110.31 127.97 183.68 147.33 178.66 182.08 232.13 172.97 221 UNRESTRIC TED POWER ( MW) 1085.57 1389.23 1673.22 1432.50 1441.77 1169.29 957.28 1048.41 1205.01 703.96 1182.81 1027.49 517.74 496.57 452.72 428.68 363.38 209.77 195.25 155.53 127.24 134.13 147.30 131.70 135.68 154.61 136.51 183.14 220.03 255.25 366.36 293.86 356.34 363.17 463.01 345.00 Efficiency UNRESTRICT ED ENERGY ( MU) 260.54 333.42 401.57 343.80 346.02 308.69 229.75 251.62 318.12 168.95 283.88 246.60 124.26 119.18 119.52 102.88 87.21 50.35 46.86 37.33 33.59 32.19 35.35 34.77 32.56 37.11 26.21 43.95 52.81 67.39 87.93 70.53 85.52 87.16 111.12 91.08 5109.80 L/F non-monsoon (Dec to Feb) 92% RESTRICTE D POWER ( 1000 MW) 1000 1000 1000 1000 1000 1000 957 1000 1000 704 1000 1000 518 497 453 429 363 210 195 156 127 134 147 132 136 155 137 183 220 255 366 294 356 363 463 345 RESTRICTE D ENERGY ( MU) 240.00 240.00 240.00 240.00 240.00 264.00 229.75 240.00 264.00 168.95 240.00 240.00 124.26 119.18 119.52 102.88 87.21 50.35 46.86 37.33 33.59 32.19 35.35 34.77 32.56 37.11 26.21 43.95 52.81 67.39 87.93 70.53 85.52 87.16 111.12 91.08 4463.55 14.63% 95% m/c Availability 228.00 228.00 228.00 228.00 228.00 250.80 229.75 228.00 250.80 168.95 228.00 228.00 124.26 119.18 119.52 102.88 87.21 50.35 46.86 37.33 33.59 32.19 35.35 34.77 32.56 37.11 26.21 43.95 52.81 67.39 87.93 70.53 85.52 87.16 111.12 91.08 4341.15

76

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
3-4 Installed Capacity
Month

1000
DISCHAR GE ( MCum)

Net Head
DISCHARGE ( Qmecs)

221
UNRESTRIC TED POWER ( MW)

Efficiency
UNRESTRI CTED ENERGY ( MU)

92%
RESTRICTE D POWER ( 1000 MW) RESTRICTED ENERGY ( MU) 95% m/c Availability

1-10 June-03 11-20 21-30 1-10 July-03 11-20 21-31 1-10 Aug-03 11-20 21-31 1-10 Sep-03 11-20 21-30 1-10 Oct-03 11-20 21-31 1-10 Nov-03 11-20 21-30 1-10 Dec-03 11-20 21-31 1-10 Jan-04 11-20 21-31 1-10 Feb-04 11-20 21-29 1-10 Mar-04 11-20 21-31 1-10 Apr-04 11-20 21-30 1-10 May-04 Total Annual L/F 53.90% 11-20 21-31

226.42 360.60 378.79 444.45 435.55 381.14 389.98 406.19 822.93 1180.93 1064.69 815.98 488.78 335.76 267.27 147.82 89.29 99.60 100.63 84.99 79.86 68.74 66.04 66.05 59.70 57.86 56.41 71.38 95.17 133.33 134.10 190.44 250.91 292.28 342.05 213.52 10699.60

262.06 417.37 438.41 514.41 504.10 401.03 451.37 470.13 865.87 1366.81 1232.28 944.42 565.71 388.61 281.22 171.08 103.34 115.27 116.47 98.36 84.02 79.56 76.44 69.50 69.10 66.96 72.54 82.62 110.15 140.29 155.21 220.42 290.40 338.28 395.89 224.67

522.70 832.47 874.44 1026.03 1005.47 799.87 900.28 937.70 1727.04 2726.21 2457.87 1883.71 1128.36 775.11 560.91 341.24 206.12 229.92 232.31 196.19 167.59 158.69 152.46 138.61 137.83 133.56 144.69 164.79 219.71 279.81 309.58 439.65 579.22 674.73 789.63 448.11

125.45 199.79 209.87 246.25 241.31 211.17 216.07 225.05 455.94 654.29 589.89 452.09 270.81 186.03 148.08 81.90 49.47 55.18 55.75 47.09 44.24 38.09 36.59 36.59 33.08 32.05 31.25 39.55 52.73 73.87 74.30 105.51 139.01 161.94 189.51 118.30 5928.08

523 832 874 1000 1000 800 900 938 1000 1000 1000 1000 1000 775 561 341 206 230 232 196 168 159 152 139 138 134 145 165 220 280 310 440 579 675 790 448

125.45 199.79 209.87 240.00 240.00 211.17 216.07 225.05 264.00 240.00 240.00 240.00 240.00 186.03 148.08 81.90 49.47 55.18 55.75 47.09 44.24 38.09 36.59 36.59 33.08 32.05 31.25 39.55 52.73 73.87 74.30 105.51 139.01 161.94 189.51 118.30 4721.51 16.42%

125.45 199.79 209.87 228.00 228.00 211.17 216.07 225.05 250.80 228.00 228.00 228.00 228.00 186.03 148.08 81.90 49.47 55.18 55.75 47.09 44.24 38.09 36.59 36.59 33.08 32.05 31.25 39.55 52.73 73.87 74.30 105.51 139.01 161.94 189.51 118.30 4636.31

L/F monsoon (Mar to Nov)

66.16%

L/F non-monsoon (Dec to Feb)

77

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
4-5 Installed Capacity Month 1-10 June04 11-20 21-30 1-10 July-04 11-20 21-31 1-10 Aug-04 11-20 21-31 1-10 Sep-04 11-20 21-30 1-10 Oct-04 11-20 21-31 1-10 Nov-04 11-20 21-30 1-10 Dec-04 11-20 21-31 1-10 Jan-05 11-20 21-31 1-10 Feb-05 11-20 21-28 1-10 Mar-05 11-20 21-31 1-10 Apr-05 11-20 21-30 1-10 May-05 Total Annual L/F 11-20 21-31 1000 DISCHARGE ( MCum) 222.50 418.94 553.14 664.56 1079.74 901.04 648.13 513.29 463.05 302.99 268.08 349.65 241.92 339.96 206.32 107.02 87.48 80.90 65.48 71.26 76.55 55.55 44.23 45.85 46.54 42.26 46.37 55.27 56.64 69.21 113.70 135.43 145.16 200.53 247.61 490.32 9456.68 48.86% L/F monsoon (Mar to Nov) 60.70% Net Head DISCHARGE ( Qmecs) 257.52 484.89 640.21 769.17 1249.70 948.06 750.16 594.08 487.21 350.68 310.28 404.68 280.00 393.47 217.09 123.87 101.25 93.63 75.79 82.47 80.55 64.29 51.19 48.25 53.86 48.92 67.09 63.97 65.55 72.82 131.60 156.75 168.01 232.10 286.59 515.91 221 UNRESTRICTED POWER ( MW) 513.64 967.14 1276.94 1534.15 2492.62 1890.98 1496.24 1184.94 971.78 699.46 618.88 807.17 558.47 784.80 433.00 247.07 201.96 186.75 151.17 164.50 160.66 128.24 102.10 96.23 107.43 97.57 133.81 127.60 130.75 145.24 262.48 312.65 335.11 462.94 571.62 1029.01 Efficiency UNRESTRICTED ENERGY ( MU) 123.27 232.11 306.47 368.20 598.23 499.22 359.10 284.39 256.55 167.87 148.53 193.72 134.03 188.35 114.31 59.30 48.47 44.82 36.28 39.48 42.41 30.78 24.51 25.40 25.78 23.42 25.69 30.62 31.38 38.34 63.00 75.04 80.43 111.10 137.19 271.66 5239.44 L/F non-monsoon (Dec to Feb) 92% RESTRICTED POWER ( 1000 MW) 514 967 1000 1000 1000 1000 1000 1000 972 699 619 807 558 785 433 247 202 187 151 164 161 128 102 96 107 98 134 128 131 145 262 313 335 463 572 1000 RESTRICTED ENERGY ( MU) 123.27 232.11 240.00 240.00 240.00 264.00 240.00 240.00 256.55 167.87 148.53 193.72 134.03 188.35 114.31 59.30 48.47 44.82 36.28 39.48 42.41 30.78 24.51 25.40 25.78 23.42 25.69 30.62 31.38 38.34 63.00 75.04 80.43 111.10 137.19 264.00 4280.19 12.67% 95% m/c Availability 123.27 232.11 228.00 228.00 228.00 250.80 228.00 228.00 256.55 167.87 148.53 193.72 134.03 188.35 114.31 59.30 48.47 44.82 36.28 39.48 42.41 30.78 24.51 25.40 25.78 23.42 25.69 30.62 31.38 38.34 63.00 75.04 80.43 111.10 137.19 250.80 4193.79

78

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
5-6 Installed Capacity Month 1-10 June05 11-20 21-30 1-10 July-05 11-20 21-31 1-10 Aug-05 11-20 21-31 1-10 Sep-05 11-20 21-30 1-10 Oct-05 11-20 21-31 1-10 Nov-05 11-20 21-30 1-10 Dec-05 11-20 21-31 1-10 Jan-06 11-20 21-31 1-10 Feb-06 11-20 21-28 1-10 Mar-06 11-20 21-31 1-10 Apr-06 11-20 21-30 1-10 May-06 Total Annual L/F 11-20 21-31 1000 DISCHARGE ( MCum) 395.67 619.28 700.50 901.56 808.67 711.32 597.65 524.33 699.85 395.74 330.83 369.87 520.43 518.84 277.69 127.05 101.29 86.77 89.79 65.53 75.40 57.94 60.67 67.14 72.76 74.79 62.95 100.33 96.25 86.63 141.82 136.54 119.57 156.98 220.58 155.71 10528.69 52.78% L/F monsoon (Mar to Nov) 64.79% Net Head DISCHARGE ( Qmecs) 457.95 716.76 810.76 1043.47 935.96 748.44 691.73 606.86 736.37 458.03 382.90 428.09 602.35 600.51 292.18 147.04 117.24 100.43 103.93 75.84 79.33 67.06 70.22 70.64 84.21 86.56 91.07 116.12 111.40 91.15 164.14 158.04 138.39 181.69 255.30 163.83 221 UNRESTRICTED POWER ( MW) 913.41 1429.63 1617.12 2081.27 1866.83 1492.81 1379.70 1210.42 1468.75 913.57 763.73 853.85 1201.43 1197.77 582.78 293.29 233.84 200.31 207.29 151.27 158.23 133.75 140.05 140.89 167.96 172.65 181.65 231.62 222.20 181.81 327.39 315.21 276.03 362.40 509.22 326.77 Efficiency UNRESTRICTED ENERGY ( MU) 219.22 343.11 388.11 499.50 448.04 394.10 331.13 290.50 387.75 219.26 183.29 204.92 288.34 287.46 153.85 70.39 56.12 48.08 49.75 36.30 41.77 32.10 33.61 37.20 40.31 41.44 34.88 55.59 53.33 48.00 78.57 75.65 66.25 86.98 122.21 86.27 5833.39 L/F non-monsoon (Dec to Feb) 92% RESTRICTED POWER ( 1000 MW) 913 1000 1000 1000 1000 1000 1000 1000 1000 914 764 854 1000 1000 583 293 234 200 207 151 158 134 140 141 168 173 182 232 222 182 327 315 276 362 509 327 RESTRICTED ENERGY ( MU) 219.22 240.00 240.00 240.00 240.00 264.00 240.00 240.00 264.00 219.26 183.29 204.92 240.00 240.00 153.85 70.39 56.12 48.08 49.75 36.30 41.77 32.10 33.61 37.20 40.31 41.44 34.88 55.59 53.33 48.00 78.57 75.65 66.25 86.98 122.21 86.27 4623.33 16.08% 95% m/c Availability 219.22 228.00 228.00 228.00 228.00 250.80 228.00 228.00 250.80 219.26 183.29 204.92 228.00 228.00 153.85 70.39 56.12 48.08 49.75 36.30 41.77 32.10 33.61 37.20 40.31 41.44 34.88 55.59 53.33 48.00 78.57 75.65 66.25 86.98 122.21 86.27 4500.93

79

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR 6-7 Installed Capacity
Month 1-10 June-06 11-20 21-30 1-10 July-06 11-20 21-31 1-10 Aug-06 11-20 21-31 1-10 Sep-06 11-20 21-30 1-10 Oct-06 11-20 21-31 1-10 Nov-06 11-20 21-30 1-10 Dec-06 11-20 21-31 1-10 Jan-07 11-20 21-31 1-10 Feb-07 11-20 21-28 1-10 Mar-07 11-20 21-31 1-10 Apr-07 11-20 21-30 1-10 May-07 11-20 21-31 Total Annual 48.19% L/F

1000

Net Head

221

Efficiency

92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 173.57 189.84 235.29 446.92 357.84 615.53 578.56 642.57 646.81 459.64 354.77 288.13 467.11 423.22 240.67 169.75 98.68 85.51 67.34 68.95 62.68 42.65 50.94 62.14 62.57 58.11 43.84 68.98 63.05 66.18 96.20 123.73 153.29 258.23 237.09 297.05 8357.44 L/F monsoon (Mar to Nov) 59.60% 200.89 219.73 272.32 517.27 414.16 647.65 669.63 743.72 680.57 532.00 410.61 333.48 540.63 489.84 253.23 196.47 114.21 98.97 77.94 79.80 65.95 49.36 58.96 65.39 72.42 67.26 63.42 79.84 72.98 69.64 111.34 143.21 177.42 298.87 274.41 312.55 400.69 438.26 543.17 1031.73 826.08 1291.79 1335.63 1483.39 1357.44 1061.10 819.00 665.16 1078.33 977.03 505.09 391.87 227.80 197.40 155.45 159.16 131.54 98.45 117.59 130.42 144.45 134.15 126.50 159.25 145.56 138.90 222.08 285.63 353.87 596.13 547.33 623.41

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 96.16 401 96.16 96.16 105.18 130.36 247.62 198.26 341.03 320.55 356.01 358.37 254.66 196.56 159.64 258.80 234.49 133.34 94.05 54.67 47.38 37.31 38.20 34.73 23.63 28.22 34.43 34.67 32.20 24.29 38.22 34.94 36.67 53.30 68.55 84.93 143.07 131.36 164.58 4630.41 L/F non-monsoon (Dec to Feb) 438 543 1000 826 1000 1000 1000 1000 1000 819 665 1000 977 505 392 228 197 155 159 132 98 118 130 144 134 127 159 146 139 222 286 354 596 547 623 105.18 130.36 240.00 198.26 264.00 240.00 240.00 264.00 240.00 196.56 159.64 240.00 234.49 133.34 94.05 54.67 47.38 37.31 38.20 34.73 23.63 28.22 34.43 34.67 32.20 24.29 38.22 34.94 36.67 53.30 68.55 84.93 143.07 131.36 164.58 4221.37 13.32% 105.18 130.36 228.00 198.26 250.80 228.00 228.00 250.80 228.00 196.56 159.64 228.00 234.49 133.34 94.05 54.67 47.38 37.31 38.20 34.73 23.63 28.22 34.43 34.67 32.20 24.29 38.22 34.94 36.67 53.30 68.55 84.93 143.07 131.36 164.58 4134.97

80

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR 7-8 Installed Capacity
Month 1-10 June-07 11-20 21-30 1-10 July-07 11-20 21-31 1-10 Aug-07 11-20 21-31 1-10 Sep-07 11-20 21-30 1-10 Oct-07 11-20 21-31 1-10 Nov-07 11-20 21-30 1-10 Dec-07 11-20 21-31 1-10 Jan-08 11-20 21-31 1-10 Feb-08 11-20 21-29 1-10 Mar-08 11-20 21-31 1-10 Apr-08 11-20 21-30 1-10 May-08 Total Annual L/F 11-20 21-31

1000

Net Head

221

Efficiency

92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED UNRESTRICTED MCum) Qmecs) POWER ( MW) ENERGY ( MU) 245.45 287.93 411.45 481.81 694.11 937.41 273.69 349.54 355.27 248.65 303.31 349.80 317.43 166.93 147.65 122.52 134.22 121.50 117.64 80.28 72.90 76.03 71.15 84.59 84.62 63.12 59.01 84.78 78.68 109.85 141.21 147.28 110.13 247.68 378.93 607.98 8564.54 48.46% L/F monsoon (Mar to Nov) 58.37% 284.09 333.25 476.21 557.65 803.37 986.33 316.77 404.56 373.81 287.79 351.05 404.86 367.40 193.20 155.36 141.81 155.35 140.62 136.16 92.92 76.71 88.00 82.35 89.01 97.94 73.05 75.89 98.12 91.07 115.58 163.44 170.47 127.46 286.66 438.58 639.71 566.63 664.70 949.84 1112.28 1602.38 1967.31 631.82 806.93 745.59 574.01 700.19 807.52 732.80 385.36 309.87 282.85 309.85 280.48 271.58 185.34 153.00 175.51 164.26 177.53 195.35 145.70 151.37 195.71 181.64 230.53 325.99 340.01 254.23 571.77 874.78 1275.94 135.99 159.53 227.96 266.95 384.57 519.37 151.64 193.66 196.84 137.76 168.05 193.80 175.87 92.49 81.81 67.88 74.36 67.32 65.18 44.48 40.39 42.12 39.42 46.87 46.88 34.97 32.70 46.97 43.59 60.86 78.24 81.60 61.01 137.22 209.95 336.85 4745.16

RESTRICTED RESTRICTED 95% m/c POWER ( ENERGY ( Availability 1000 MW) MU) 567 135.99 135.99 665 950 1000 1000 1000 632 807 746 574 700 808 733 385 310 283 310 280 272 185 153 176 164 178 195 146 151 196 182 231 326 340 254 572 875 1000 159.53 227.96 240.00 240.00 264.00 151.64 193.66 196.84 137.76 168.05 193.80 175.87 92.49 81.81 67.88 74.36 67.32 65.18 44.48 40.39 42.12 39.42 46.87 46.88 34.97 32.70 46.97 43.59 60.86 78.24 81.60 61.01 137.22 209.95 264.00 4245.42 18.20% 159.53 227.96 228.00 228.00 250.80 151.64 193.66 196.84 137.76 168.05 193.80 175.87 92.49 81.81 67.88 74.36 67.32 65.18 44.48 40.39 42.12 39.42 46.87 46.88 34.97 32.70 46.97 43.59 60.86 78.24 81.60 61.01 137.22 209.95 250.80 4195.02

L/F non-monsoon (Dec to Feb)

81

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR 8-9 Installed Capacity
Month 1-10 June-08 11-20 21-30 1-10 July-08 11-20 21-31 1-10 Aug-08 11-20 21-31 1-10 Sep-08 11-20 21-30 1-10 Oct-08 11-20 21-31 1-10 Nov-08 11-20 21-30 1-10 Dec-08 11-20 21-31 1-10 Jan-09 11-20 21-31 1-10 Feb-09 11-20 21-28 1-10 Mar-09 11-20 21-31 1-10 Apr-09 11-20 21-30 1-10 May-09 Total Annual L/F 11-20 21-31

1000

Net Head

221

Efficiency

92%

RESTRICTED RESTRICTED DISCHARGE ( DISCHARGE ( UNRESTRICTED UNRESTRICTED 95% m/c POWER ( 1000 ENERGY ( MCum) Qmecs) POWER ( MW) ENERGY ( MU) Availability MW) MU) 934.93 1082.09 2158.30 517.99 1000 240.00 228.00 1168.82 1047.92 1223.29 1349.92 1870.31 535.73 604.67 728.88 553.18 395.80 551.62 444.72 479.64 239.67 216.09 184.99 121.83 77.13 81.62 80.32 66.37 52.97 54.87 44.55 41.31 34.47 78.41 81.93 78.93 85.76 150.34 161.61 181.82 129.15 226.86 14360.43 1352.80 1212.87 1415.85 1562.41 1967.92 620.06 699.85 766.92 640.25 458.10 638.45 514.72 555.14 252.18 250.10 214.11 141.01 89.27 94.47 84.52 76.81 61.31 57.74 51.56 47.82 49.87 90.76 94.83 83.05 99.26 174.00 187.05 210.44 149.48 238.70 2698.24 2419.16 2824.01 3116.33 3925.15 1236.75 1395.89 1529.68 1277.02 913.72 1273.44 1026.65 1107.26 502.99 498.84 427.06 281.26 178.05 188.42 168.57 153.21 122.29 115.16 102.84 95.38 99.46 181.02 189.14 165.65 197.97 347.06 373.08 419.73 298.14 476.09 647.58 580.60 677.76 747.92 1036.24 296.82 335.01 403.84 306.49 219.29 305.62 246.40 265.74 132.79 119.72 102.49 67.50 42.73 45.22 44.50 36.77 29.35 30.40 24.68 22.89 19.10 43.44 45.39 43.73 47.51 83.29 89.54 100.73 71.55 125.69 7956.35 67.59% L/F non-monsoon (Dec to Feb) 1000 1000 1000 1000 1000 1000 1000 1000 1000 914 1000 1000 1000 503 499 427 281 178 188 169 153 122 115 103 95 99 181 189 166 198 347 373 420 298 476 240.00 240.00 240.00 240.00 264.00 240.00 240.00 264.00 240.00 219.29 240.00 240.00 240.00 132.79 119.72 102.49 67.50 42.73 45.22 44.50 36.77 29.35 30.40 24.68 22.89 19.10 43.44 45.39 43.73 47.51 83.29 89.54 100.73 71.55 125.69 4756.34 13.69% 228.00 228.00 228.00 228.00 250.80 228.00 228.00 250.80 228.00 219.29 228.00 228.00 228.00 132.79 119.72 102.49 67.50 42.73 45.22 44.50 36.77 29.35 30.40 24.68 22.89 19.10 43.44 45.39 43.73 47.51 83.29 89.54 100.73 71.55 125.69 4597.94

54.30%

L/F monsoon (Mar to Nov)

82

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
9-10 Installed Capacity 1000 Net Head 221 Efficiency 92% RESTRICTED POWER ( 1000 MW) 388 370 596 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 534 557 313 327 204 141 147 122 97 91 96 117 148 143 237 187 190 235 280 285 369 273 317 RESTRICTED ENERGY ( MU) 93.15 88.75 143.09 240.00 240.00 264.00 240.00 240.00 264.00 240.00 240.00 240.00 240.00 128.25 147.08 75.08 78.54 48.98 33.88 35.21 32.13 23.38 21.92 25.31 28.14 35.61 27.49 56.84 44.84 50.16 56.43 67.24 68.39 88.68 65.58 83.69 4095.79 12.18%

Month

DISCHARGE ( MCum) 1-10 11-20 21-30 1-10 168.12 160.19 258.26 739.17 576.38 908.73 708.07 904.61 736.81 502.10 452.46 489.10 541.50 231.48 265.46 135.51 141.75 88.41 61.14 63.55 57.99 42.19 39.56 45.68 50.79 64.26 49.61 102.60 80.92 90.53 101.85 121.35 123.43 160.05 118.36 151.04 9533.03 46.76%

DISCHARGE ( Qmecs) 194.58 185.40 298.91 855.52 667.11 956.15 819.52 1047.00 775.26 581.13 523.68 566.09 626.73 267.92 279.31 156.84 164.06 102.32 70.77 73.55 61.02 48.83 45.78 48.06 58.79 74.38 71.78 118.75 93.66 95.26 117.89 140.46 142.86 185.25 136.99 158.93

UNRESTRICTED POWER ( MW) 388.11 369.80 596.20 1706.39 1330.60 1907.11 1634.59 2088.32 1546.32 1159.11 1044.51 1129.11 1250.07 534.38 557.11 312.82 327.24 204.09 141.15 146.71 121.71 97.40 91.32 95.86 117.25 148.36 143.16 236.85 186.81 190.00 235.13 280.15 284.95 369.49 273.23 316.99

UNRESTRICTED ENERGY ( MU) 93.15 88.75 143.09 409.53 319.34 503.48 392.30 501.20 408.23 278.19 250.68 270.99 300.02 128.25 147.08 75.08 78.54 48.98 33.88 35.21 32.13 23.38 21.92 25.31 28.14 35.61 27.49 56.84 44.84 50.16 56.43 67.24 68.39 88.68 65.58 83.69 5281.74

95% m/c Availability 93.15 88.75 143.09 228.00 228.00 250.80 228.00 228.00 250.80 228.00 228.00 228.00 228.00 128.25 147.08 75.08 78.54 48.98 33.88 35.21 32.13 23.38 21.92 25.31 28.14 35.61 27.49 56.84 44.84 50.16 56.43 67.24 68.39 88.68 65.58 83.69 3973.39

June09

July-09

11-20 21-31 1-10

Aug-09

11-20 21-31 1-10

Sep-09

11-20 21-30 1-10

Oct-09

11-20 21-31 1-10

Nov-09

11-20 21-30 1-10

Dec-09

11-20 21-31 1-10

Jan-10

11-20 21-31 1-10

Feb-10

11-20 21-28 1-10

Mar-10

11-20 21-31 1-10

Apr-10

11-20 21-30 1-10

May-10 Total Annual L/F

11-20 21-31

L/F monsoon (Mar to Nov)

58.07%

L/F non-monsoon (Dec to Feb)

83

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
11-12 Installed Capacity Mont h 1-10 11-20 21-30 July11 1-10 11-20 21-31 Aug11 1-10 11-20 21-31 Sep11 1-10 11-20 21-30 Oct11 1-10 11-20 21-31 Nov11 1-10 11-20 21-30 Dec11 1-10 11-20 21-31 Jan12 1-10 11-20 21-31 Feb12 1-10 11-20 21-29 Mar12 1-10 11-20 21-31 Apr12 1-10 11-20 21-30 May12 Total Annu al L/F 1-10 11-20 21-31 49.77 % 1000 DISCHARGE ( MCum) 212.20 240.60 223.86 342.92 592.02 475.83 441.40 482.88 876.53 752.66 824.08 659.73 552.41 209.58 216.51 142.14 121.86 110.52 74.73 87.54 85.02 89.01 89.64 93.24 76.78 77.58 64.09 82.05 73.63 92.99 132.28 152.52 152.14 268.23 230.50 142.31 9541.97 L/F monsoon (Mar to Nov) 59.87% Net Head DISCHARG E ( Qmecs) 245.60 278.47 259.09 396.90 685.21 500.66 510.88 558.89 922.27 871.13 953.79 763.57 639.36 242.57 227.81 164.52 141.04 127.92 86.50 101.32 89.46 103.02 103.75 98.10 88.86 89.79 82.42 94.96 85.22 97.84 153.10 176.53 176.08 310.45 266.78 149.73 221 UNRESTRICTE D POWER ( MW) 489.86 555.43 516.78 791.65 1366.69 998.61 1018.99 1114.74 1839.53 1737.53 1902.41 1522.99 1275.26 483.82 454.38 328.14 281.32 255.14 172.52 202.09 178.43 205.49 206.93 195.67 177.24 179.10 164.39 189.41 169.98 195.15 305.37 352.10 351.21 619.22 532.11 298.65 Efficiency UNRESTRICTE D ENERGY ( MU) 117.57 133.30 124.03 190.00 328.01 263.63 244.56 267.54 485.64 417.01 456.58 365.52 306.06 116.12 119.96 78.75 67.52 61.23 41.41 48.50 47.10 49.32 49.66 51.66 42.54 42.98 35.51 45.46 40.80 51.52 73.29 84.50 84.29 148.61 127.71 78.84 5286.70 18.92% 92% RESTRICTE D POWER ( 1000 MW) 490 555 517 792 1000 999 1000 1000 1000 1000 1000 1000 1000 484 454 328 281 255 173 202 178 205 207 196 177 179 164 189 170 195 305 352 351 619 532 299 RESTRICTE D ENERGY ( MU) 117.57 133.30 124.03 190.00 240.00 263.63 240.00 240.00 264.00 240.00 240.00 240.00 240.00 116.12 119.96 78.75 67.52 61.23 41.41 48.50 47.10 49.32 49.66 51.66 42.54 42.98 35.51 45.46 40.80 51.52 73.29 84.50 84.29 148.61 127.71 78.84 4359.80 95% m/c Availabilit y 117.57 133.30 124.03 190.00 228.00 263.63 228.00 228.00 250.80 228.00 228.00 228.00 228.00 116.12 119.96 78.75 67.52 61.23 41.41 48.50 47.10 49.32 49.66 51.66 42.54 42.98 35.51 45.46 40.80 51.52 73.29 84.50 84.29 148.61 127.71 78.84 4262.60

June11

84

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
12-13 Installed Capacity 1000 Net Head 221 Efficiency 92%

Month

RESTRICTED DISCHARGE ( DISCHARGE ( UNRESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 MCum) Qmecs) POWER ( MW) ENERGY ( MU) ENERGY ( MU) Availability MW) 1-10 284.89 346.51 495.09 587.40 468.69 844.61 356.53 484.32 942.39 647.26 684.03 504.40 292.35 325.45 181.21 100.17 94.96 77.83 85.33 65.35 63.96 43.99 44.32 54.03 58.85 43.82 52.23 83.81 108.75 120.40 134.34 129.63 144.23 166.74 160.04 360.51 9638.41 L/F monsoon (Mar to Nov) 62.57% 329.74 401.06 573.02 679.86 542.47 888.69 412.65 560.56 991.57 749.15 791.70 583.79 338.36 376.68 190.67 115.94 109.91 90.08 98.76 75.63 67.30 50.91 51.29 56.85 68.11 50.72 75.56 97.00 125.87 126.68 155.49 150.03 166.93 192.99 185.23 379.33 657.69 799.93 1142.92 1356.03 1081.99 1772.55 823.07 1118.07 1977.76 1494.23 1579.10 1164.41 674.89 751.31 380.31 231.25 219.21 179.67 196.99 150.86 134.22 101.54 102.31 113.39 135.85 101.16 150.71 193.47 251.06 252.67 310.13 299.25 332.95 384.93 369.46 756.60 157.84 191.98 274.30 325.45 259.68 467.95 197.54 268.34 522.13 358.62 378.98 279.46 161.97 180.32 100.40 55.50 52.61 43.12 47.28 36.21 35.44 24.37 24.55 29.94 32.60 24.28 28.94 46.43 60.26 66.71 74.43 71.82 79.91 92.38 88.67 199.74 5340.13 L/F non-monsoon (Dec to Feb) 658 800 1000 1000 1000 1000 823 1000 1000 1000 1000 1000 675 751 380 231 219 180 197 151 134 102 102 113 136 101 151 193 251 253 310 299 333 385 369 757 157.84 191.98 240.00 240.00 240.00 264.00 197.54 240.00 264.00 240.00 240.00 240.00 161.97 180.32 100.40 55.50 52.61 43.12 47.28 36.21 35.44 24.37 24.55 29.94 32.60 24.28 28.94 46.43 60.26 66.71 74.43 71.82 79.91 92.38 88.67 199.74 4413.23 13.13% 157.84 191.98 228.00 228.00 228.00 250.80 197.54 228.00 250.80 228.00 228.00 228.00 161.97 180.32 100.40 55.50 52.61 43.12 47.28 36.21 35.44 24.37 24.55 29.94 32.60 24.28 28.94 46.43 60.26 66.71 74.43 71.82 79.91 92.38 88.67 199.74 4302.83

June-12

11-20 21-30 1-10

July-12

11-20 21-31 1-10

Aug-12

11-20 21-31 1-10

Sep-12

11-20 21-30 1-10

Oct-12

11-20 21-31 1-10

Nov-12

11-20 21-30 1-10

Dec-12

11-20 21-31 1-10

Jan-13

11-20 21-31 1-10

Feb-13

11-20 21-28 1-10

Mar-13

11-20 21-31 1-10

Apr-13

11-20 21-30 1-10

May-13 Total

11-20 21-31

Annual 50.38% L/F

85

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
13-14 Installed Capacity Month 1-10 June-13 11-20 21-30 1-10 July-13 11-20 21-31 1-10 Aug-13 11-20 21-31 1-10 Sep-13 11-20 21-30 1-10 Oct-13 11-20 21-31 1-10 Nov-13 11-20 21-30 1-10 Dec-13 11-20 21-31 1-10 Jan-14 11-20 21-31 1-10 Feb-14 11-20 21-28 1-10 Mar-14 11-20 21-31 1-10 Apr-14 11-20 21-30 1-10 May-14 11-20 21-31 Total Annual L/F 47.37% 1000 Net Head 221 Efficiency 92%

RESTRICTED RESTRICTED DISCHARGE ( DISCHARGE ( UNRESTRICTED UNRESTRICTED 95% m/c POWER ( 1000 ENERGY ( MCum) Qmecs) POWER ( MW) ENERGY ( MU) Availability MW) MU) 271.71 256.17 461.82 406.26 637.29 554.54 792.86 1035.17 725.25 336.23 314.40 250.68 473.61 205.76 187.55 137.71 130.85 96.60 65.27 67.66 72.31 53.07 43.40 45.34 54.71 43.02 43.64 81.83 111.21 104.89 125.70 168.04 143.27 180.63 179.29 193.47 9051.20 L/F monsoon (Mar to Nov) 58.77% 314.48 296.49 534.51 470.20 737.61 583.48 917.66 1198.11 763.10 389.15 363.88 290.14 548.16 238.15 197.34 159.39 151.44 111.80 75.54 78.31 76.08 61.43 50.23 47.70 63.32 49.79 63.13 94.71 128.71 110.36 145.48 194.49 165.82 209.07 207.52 203.57 627.25 591.37 1066.11 937.86 1471.21 1163.79 1830.34 2389.71 1522.06 776.19 725.79 578.70 1093.35 475.00 393.61 317.91 302.07 223.00 150.68 156.19 151.75 122.52 100.20 95.14 126.30 99.31 125.92 188.91 256.73 220.13 290.17 387.93 330.74 417.00 413.90 406.04 150.54 141.93 255.87 225.09 353.09 307.24 439.28 573.53 401.82 186.29 174.19 138.89 262.40 114.00 103.91 76.30 72.50 53.52 36.16 37.49 40.06 29.41 24.05 25.12 30.31 23.84 24.18 45.34 61.61 58.11 69.64 93.10 79.38 100.08 99.34 107.19 5014.79 L/F non-monsoon (Dec to Feb) 627 591 1000 938 1000 1000 1000 1000 1000 776 726 579 1000 475 394 318 302 223 151 156 152 123 100 95 126 99 126 189 257 220 290 388 331 417 414 406 150.54 141.93 240.00 225.09 240.00 264.00 240.00 240.00 264.00 186.29 174.19 138.89 240.00 114.00 103.91 76.30 72.50 53.52 36.16 37.49 40.06 29.41 24.05 25.12 30.31 23.84 24.18 45.34 61.61 58.11 69.64 93.10 79.38 100.08 99.34 107.19 4149.55 12.53% 150.54 141.93 228.00 225.09 228.00 250.80 228.00 228.00 250.80 186.29 174.19 138.89 228.00 114.00 103.91 76.30 72.50 53.52 36.16 37.49 40.06 29.41 24.05 25.12 30.31 23.84 24.18 45.34 61.61 58.11 69.64 93.10 79.38 100.08 99.34 107.19 4063.15

86

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
14-15 Installed Capacity Month 1-10 June-14 11-20 21-30 1-10 July-14 11-20 21-31 1-10 Aug-14 11-20 21-31 1-10 Sep-14 11-20 21-30 1-10 Oct-14 11-20 21-31 1-10 Nov-14 11-20 21-30 1-10 Dec-14 11-20 21-31 1-10 Jan-15 11-20 21-31 1-10 Feb-15 11-20 21-28 1-10 Mar-15 11-20 21-31 1-10 Apr-15 11-20 21-30 1-10 May-15 11-20 21-31 Total 1000 Net Head 221 Efficiency 92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 415.96 709.88 949.30 591.20 698.23 940.09 608.16 644.92 670.86 550.57 400.60 367.86 450.67 229.45 148.13 140.94 120.62 86.66 90.44 100.93 96.39 91.52 82.72 86.51 102.90 64.60 61.93 91.30 100.42 96.01 93.31 90.81 87.80 203.17 174.43 117.80 10557.09 61.98% 481.44 821.62 1098.73 684.26 808.14 989.15 703.88 746.43 705.87 637.23 463.66 425.77 521.61 265.57 155.87 163.12 139.61 100.30 104.68 116.82 101.42 105.92 95.75 91.03 119.10 74.76 89.60 105.67 116.23 101.02 107.99 105.10 101.62 235.15 201.89 123.95 960.26 1638.78 2191.50 1364.81 1611.89 1972.93 1403.95 1488.81 1407.90 1271.00 924.80 849.22 1040.38 529.70 310.88 325.36 278.46 200.05 208.79 233.01 202.29 211.27 190.97 181.56 237.54 149.12 178.72 210.77 231.82 201.49 215.40 209.63 202.69 469.02 402.67 247.23

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 230.46 393.31 525.96 327.55 386.85 520.85 336.95 357.31 371.69 305.04 221.95 203.81 249.69 127.13 82.07 78.09 66.83 48.01 50.11 55.92 53.40 50.70 45.83 47.93 57.01 35.79 34.31 50.58 55.64 53.19 51.70 50.31 48.65 112.57 96.64 65.27 5849.13 L/F non-monsoon (Dec to Feb) 960 1000 1000 1000 1000 1000 1000 1000 1000 1000 925 849 1000 530 311 325 278 200 209 233 202 211 191 182 238 149 179 211 232 201 215 210 203 469 403 247 230.46 240.00 240.00 240.00 240.00 264.00 240.00 240.00 264.00 240.00 221.95 203.81 240.00 127.13 82.07 78.09 66.83 48.01 50.11 55.92 53.40 50.70 45.83 47.93 57.01 35.79 34.31 50.58 55.64 53.19 51.70 50.31 48.65 112.57 96.64 65.27 4521.92 19.95% 230.46 228.00 228.00 228.00 228.00 250.80 228.00 228.00 250.80 228.00 221.95 203.81 228.00 127.13 82.07 78.09 66.83 48.01 50.11 55.92 53.40 50.70 45.83 47.93 57.01 35.79 34.31 50.58 55.64 53.19 51.70 50.31 48.65 112.57 96.64 65.27 4399.52

Annual 51.62% L/F monsoon (Mar to Nov) L/F

87

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
15-16 Installed Capacity Month 1-10 June-15 11-20 21-30 1-10 July-15 11-20 21-31 1-10 Aug-15 11-20 21-31 1-10 Sep-15 11-20 21-30 1-10 Oct-15 11-20 21-31 1-10 Nov-15 11-20 21-30 1-10 Dec-15 11-20 21-31 1-10 Jan-16 11-20 21-31 1-10 Feb-16 11-20 21-29 1-10 Mar-16 11-20 21-31 1-10 Apr-16 11-20 21-30 1-10 May-16 11-20 21-31 Total 1000 Net Head 221 Efficiency 92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 129.33 242.24 369.28 809.37 757.53 731.31 664.60 598.60 576.43 286.68 316.20 304.19 249.39 186.81 180.86 180.83 148.79 102.96 111.47 79.14 73.52 51.11 56.11 67.81 82.15 80.12 77.81 97.04 76.20 81.71 135.65 112.54 172.82 210.00 156.40 232.74 8789.75 55.89% 149.69 280.37 427.40 936.77 876.77 769.48 769.21 692.83 606.52 331.81 365.97 352.08 288.65 216.22 190.30 209.29 172.21 119.16 129.02 91.60 77.36 59.15 64.94 71.35 95.09 92.73 100.07 112.31 88.20 85.97 157.00 130.25 200.03 243.05 181.02 244.89 298.56 559.23 852.48 1868.45 1748.79 1534.78 1534.24 1381.89 1209.74 661.81 729.95 702.24 575.73 431.26 379.57 417.45 343.49 237.68 257.33 182.70 154.29 117.98 129.52 142.32 189.66 184.97 199.59 224.02 175.92 171.48 313.14 259.79 398.97 484.78 361.06 488.45

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 71.65 134.21 204.60 448.43 419.71 405.18 368.22 331.65 319.37 158.84 175.19 168.54 138.17 103.50 100.21 100.19 82.44 57.04 61.76 43.85 40.73 28.32 31.09 37.57 45.52 44.39 43.11 53.76 42.22 45.27 75.15 62.35 95.75 116.35 86.66 128.95 4869.94 L/F non-monsoon (Dec to Feb) 299 559 852 1000 1000 1000 1000 1000 1000 662 730 702 576 431 380 417 343 238 257 183 154 118 130 142 190 185 200 224 176 171 313 260 399 485 361 488 71.65 134.21 204.60 240.00 240.00 264.00 240.00 240.00 264.00 158.84 175.19 168.54 138.17 103.50 100.21 100.19 82.44 57.04 61.76 43.85 40.73 28.32 31.09 37.57 45.52 44.39 43.11 53.76 42.22 45.27 75.15 62.35 95.75 116.35 86.66 128.95 4065.37 17.42% 71.65 134.21 204.60 228.00 228.00 250.80 228.00 228.00 250.80 158.84 175.19 168.54 138.17 103.50 100.21 100.19 82.44 57.04 61.76 43.85 40.73 28.32 31.09 37.57 45.52 44.39 43.11 53.76 42.22 45.27 75.15 62.35 95.75 116.35 86.66 128.95 3990.97

Annual 46.41% L/F monsoon (Mar to Nov) L/F

88

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
16-17 Installed Capacity Month 1-10 June-16 11-20 21-30 1-10 July-16 11-20 21-31 1-10 Aug-16 11-20 21-31 1-10 Sep-16 11-20 21-30 1-10 Oct-16 11-20 21-31 1-10 Nov-16 11-20 21-30 1-10 Dec-16 11-20 21-31 1-10 Jan-17 11-20 21-31 1-10 Feb-17 11-20 21-28 1-10 Mar-17 11-20 21-31 1-10 Apr-17 11-20 21-30 1-10 May-17 11-20 21-31 Total 1000 Net Head 221 Efficiency 92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 523.89 364.49 367.63 319.83 265.48 325.94 466.08 715.94 859.46 578.18 452.27 598.29 356.12 218.45 170.24 159.08 143.04 108.53 74.10 60.42 68.63 48.35 38.36 46.97 54.61 60.48 48.52 65.57 72.93 114.50 187.76 158.12 203.85 209.65 164.09 137.65 8807.50 60.34% 606.35 421.86 425.49 370.18 307.27 342.95 539.45 828.63 904.31 669.19 523.47 692.47 412.18 252.83 179.12 184.11 165.56 125.61 85.76 69.93 72.21 55.96 44.40 49.42 63.21 70.00 70.20 75.89 84.41 120.47 217.32 183.01 235.94 242.65 189.92 144.84 1209.41 841.43 848.68 738.35 612.88 684.03 1075.97 1652.76 1803.71 1334.75 1044.09 1381.18 822.12 504.30 357.28 367.23 330.22 250.54 171.06 139.48 144.03 111.61 88.57 98.58 126.07 139.62 140.01 151.37 168.35 240.29 433.46 365.03 470.59 483.99 378.81 288.89

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 290.26 201.94 203.68 177.20 147.09 180.58 258.23 396.66 476.18 320.34 250.58 331.48 197.31 121.03 94.32 88.14 79.25 60.13 41.05 33.47 38.02 26.79 21.26 26.02 30.26 33.51 26.88 36.33 40.40 63.44 104.03 87.61 112.94 116.16 90.91 76.27 4879.77 L/F non-monsoon (Dec to Feb) 1000 841 849 738 613 684 1000 1000 1000 1000 1000 1000 822 504 357 367 330 251 171 139 144 112 89 99 126 140 140 151 168 240 433 365 471 484 379 289 240.00 201.94 203.68 177.20 147.09 180.58 240.00 240.00 264.00 240.00 240.00 240.00 197.31 121.03 94.32 88.14 79.25 60.13 41.05 33.47 38.02 26.79 21.26 26.02 30.26 33.51 26.88 36.33 40.40 63.44 104.03 87.61 112.94 116.16 90.91 76.27 4260.03 12.84% 228.00 201.94 203.68 177.20 147.09 180.58 228.00 228.00 250.80 228.00 228.00 228.00 197.31 121.03 94.32 88.14 79.25 60.13 41.05 33.47 38.02 26.79 21.26 26.02 30.26 33.51 26.88 36.33 40.40 63.44 104.03 87.61 112.94 116.16 90.91 76.27 4174.83

Annual 48.63% L/F monsoon (Mar to Nov) L/F

89

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
17-18 Installed Capacity Month 1-10 June-17 11-20 21-30 1-10 July-17 11-20 21-31 1-10 Aug-17 11-20 21-31 1-10 Sep-17 11-20 21-30 1-10 Oct-17 11-20 21-31 1-10 Nov-17 11-20 21-30 1-10 Dec-17 11-20 21-31 1-10 Jan-18 11-20 21-31 1-10 Feb-18 11-20 21-28 1-10 Mar-18 11-20 21-31 1-10 Apr-18 11-20 21-30 1-10 May-18 11-20 21-31 Total 1000 Net Head 221 Efficiency 92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 121.25 155.41 232.01 262.94 509.01 696.65 700.09 929.40 1221.96 926.08 655.18 716.05 325.42 355.03 306.88 166.35 100.07 68.88 69.53 58.53 66.31 60.21 61.34 63.97 66.66 47.99 56.88 97.20 80.53 77.18 104.56 99.42 147.57 157.20 115.67 104.05 9983.47 55.65% 140.34 179.87 268.54 304.33 589.13 733.00 810.29 1075.70 1285.73 1071.86 758.31 828.77 376.64 410.92 322.89 192.53 115.82 79.72 80.48 67.75 69.77 69.69 70.99 67.31 77.15 55.55 82.30 112.50 93.21 81.20 121.02 115.07 170.80 181.94 133.88 109.48 279.91 358.77 535.61 607.00 1175.07 1462.03 1616.17 2145.56 2564.48 2137.89 1512.50 1653.03 751.24 819.60 644.04 384.02 231.02 159.01 160.52 135.13 139.17 139.01 141.60 134.24 153.89 110.79 164.15 224.39 185.91 161.97 241.38 229.51 340.66 362.89 267.02 218.36

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 67.18 86.11 128.55 145.68 282.02 385.98 387.88 514.93 677.02 513.09 363.00 396.73 180.30 196.70 170.03 92.17 55.44 38.16 38.52 32.43 36.74 33.36 33.98 35.44 36.93 26.59 31.52 53.85 44.62 42.76 57.93 55.08 81.76 87.09 64.09 57.65 5531.31 L/F non-monsoon (Dec to Feb) 280 359 536 607 1000 1000 1000 1000 1000 1000 1000 1000 751 820 644 384 231 159 161 135 139 139 142 134 154 111 164 224 186 162 241 230 341 363 267 218 67.18 86.11 128.55 145.68 240.00 264.00 240.00 240.00 264.00 240.00 240.00 240.00 180.30 196.70 170.03 92.17 55.44 38.16 38.52 32.43 36.74 33.36 33.98 35.44 36.93 26.59 31.52 53.85 44.62 42.76 57.93 55.08 81.76 87.09 64.09 57.65 3978.66 14.14% 67.18 86.11 128.55 145.68 228.00 250.80 228.00 228.00 250.80 228.00 228.00 228.00 180.30 196.70 170.03 92.17 55.44 38.16 38.52 32.43 36.74 33.36 33.98 35.44 36.93 26.59 31.52 53.85 44.62 42.76 57.93 55.08 81.76 87.09 64.09 57.65 3880.26

Annual 45.42% L/F monsoon (Mar to Nov) L/F

90

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
18-19 Installed Capacity Month 1-10 June-18 11-20 21-30 1-10 July-18 11-20 21-31 1-10 Aug-18 11-20 21-31 1-10 Sep-18 11-20 21-30 1-10 Oct-18 11-20 21-31 1-10 Nov-18 11-20 21-30 1-10 Dec-18 11-20 21-31 1-10 Jan-19 11-20 21-31 1-10 Feb-19 11-20 21-28 1-10 Mar-19 11-20 21-31 1-10 Apr-19 11-20 21-30 1-10 May-19 11-20 21-31 Total 1000 Net Head 221 Efficiency 92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 111.22 145.83 280.90 330.09 627.93 621.62 388.75 359.39 400.06 370.35 341.80 268.68 379.53 380.01 249.44 135.59 85.58 74.01 88.35 78.47 80.99 62.42 62.86 64.17 78.15 84.70 71.62 79.91 105.81 147.36 164.42 225.91 163.36 260.36 344.16 281.31 7995.12 58.62% 128.73 168.78 325.11 382.05 726.77 654.06 449.94 415.96 420.94 428.65 395.60 310.97 439.27 439.83 262.46 156.94 99.05 85.66 102.25 90.82 85.22 72.25 72.75 67.52 90.45 98.04 103.61 92.49 122.47 155.05 190.30 261.47 189.07 301.35 398.34 295.99 256.76 336.65 648.45 762.02 1449.58 1304.56 897.44 829.66 839.60 854.97 789.05 620.25 876.16 877.26 523.50 313.02 197.56 170.85 203.95 181.15 169.97 144.10 145.11 134.68 180.42 195.54 206.66 184.48 244.27 309.27 379.57 521.52 377.12 601.06 794.51 590.37

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 61.62 80.80 155.63 182.88 347.90 344.40 215.39 199.12 221.65 205.19 189.37 148.86 210.28 210.54 138.20 75.13 47.41 41.01 48.95 43.48 44.87 34.58 34.83 35.55 43.30 46.93 39.68 44.28 58.63 81.65 91.10 125.17 90.51 144.25 190.68 155.86 4429.67 L/F non-monsoon (Dec to Feb) 257 337 648 762 1000 1000 897 830 840 855 789 620 876 877 524 313 198 171 204 181 170 144 145 135 180 196 207 184 244 309 380 522 377 601 795 590 61.62 80.80 155.63 182.88 240.00 264.00 215.39 199.12 221.65 205.19 189.37 148.86 210.28 210.54 138.20 75.13 47.41 41.01 48.95 43.48 44.87 34.58 34.83 35.55 43.30 46.93 39.68 44.28 58.63 81.65 91.10 125.17 90.51 144.25 190.68 155.86 4241.37 17.23% 61.62 80.80 155.63 182.88 228.00 250.80 215.39 199.12 221.65 205.19 189.37 148.86 210.28 210.54 138.20 75.13 47.41 41.01 48.95 43.48 44.87 34.58 34.83 35.55 43.30 46.93 39.68 44.28 58.63 81.65 91.10 125.17 90.51 144.25 190.68 155.86 4216.17

Annual 48.42% L/F monsoon (Mar to Nov) L/F

91

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT
POWER POTENTIAL STUDY FOR YEAR
19-20 Installed Capacity Month 1-10 June-19 11-20 21-30 1-10 July-19 11-20 21-31 1-10 Aug-19 11-20 21-31 1-10 Sep-19 11-20 21-30 1-10 Oct-19 11-20 21-31 1-10 Nov-19 11-20 21-30 1-10 Dec-19 11-20 21-31 1-10 Jan-20 11-20 21-31 1-10 Feb-20 11-20 21-29 1-10 Mar-20 11-20 21-31 1-10 Apr-20 11-20 21-30 1-10 May-20 11-20 21-31 Total 1000 Net Head 221 Efficiency 92%

DISCHARGE ( DISCHARGE ( UNRESTRICTED MCum) Qmecs) POWER ( MW) 507.15 776.58 787.19 927.13 1123.25 1626.62 466.34 521.51 922.65 600.21 487.38 327.57 288.25 288.90 290.74 132.27 79.73 78.84 96.33 69.10 65.65 54.64 44.89 47.06 40.00 39.91 45.94 48.89 57.69 70.85 84.97 87.76 126.50 164.79 164.84 233.63 11775.74 61.93% 586.97 898.82 911.10 1073.07 1300.06 1711.51 539.75 603.60 970.80 694.68 564.10 379.13 333.62 334.37 305.91 153.09 92.28 91.25 111.50 79.98 69.07 63.24 51.96 49.52 46.30 46.20 59.08 56.58 66.77 74.55 98.34 101.57 146.41 190.73 190.78 245.82 1170.76 1792.75 1817.26 2140.30 2593.07 3413.73 1076.56 1203.92 1936.34 1385.60 1125.14 756.19 665.43 666.93 610.16 305.34 184.06 182.01 222.39 159.52 137.77 126.14 103.63 98.77 92.35 92.14 117.84 112.86 133.17 148.69 196.15 202.59 292.03 380.42 380.53 490.31

RESTRICTED UNRESTRICTED RESTRICTED 95% m/c POWER ( 1000 ENERGY ( MU) ENERGY ( MU) Availability MW) 280.98 430.26 436.14 513.67 622.34 901.22 258.37 288.94 511.19 332.54 270.03 181.49 159.70 160.06 161.08 73.28 44.17 43.68 53.37 38.29 36.37 30.27 24.87 26.08 22.16 22.11 25.45 27.09 31.96 39.25 47.08 48.62 70.09 91.30 91.33 129.44 6524.32 L/F non-monsoon (Dec to Feb) 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 1000 756 665 667 610 305 184 182 222 160 138 126 104 99 92 92 118 113 133 149 196 203 292 380 381 490 240.00 240.00 240.00 240.00 240.00 264.00 240.00 240.00 264.00 240.00 240.00 181.49 159.70 160.06 161.08 73.28 44.17 43.68 53.37 38.29 36.37 30.27 24.87 26.08 22.16 22.11 25.45 27.09 31.96 39.25 47.08 48.62 70.09 91.30 91.33 129.44 4366.61 12.92% 228.00 228.00 228.00 228.00 228.00 250.80 228.00 228.00 250.80 228.00 228.00 181.49 159.70 160.06 161.08 73.28 44.17 43.68 53.37 38.29 36.37 30.27 24.87 26.08 22.16 22.11 25.45 27.09 31.96 39.25 47.08 48.62 70.09 91.30 91.33 129.44 4232.21

Annual 49.85% L/F monsoon (Mar to Nov) L/F

92

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER - VIII POWER EVACUATION

8.0

INTRODUCTION

The Naba H.E. Project is envisaged for the installation of four generating units of 250 MW each, operating under a rated net head of 221.0 m in an underground type power house. The generation voltage is proposed to be 16 KV. This voltage will be stepped up to 400 KV voltage level through single-phase Generator step-up transformers. The Generator step-up transformers will be further connected to 400 KV Gas Insulated Switchgear (GIS) located above the transformers, both housed in the underground cavern. Gas Insulated Switchgear will be connected to the outdoor potyard through 400 KV XLPE cables. The power from Naba H.E. Project would be fed to the North-Eastern Grid to be ultimately connected to the National Grid through EHV/HVDC transmission lines. Provision of two outgoing bays has been kept in GIS for 1000 MW power evacuation from this project. 8.1 Power EXISTING POWER EVACUATION FACILITIES system is controlled by the Electricity boards/

Departments/Corporations of the states of Assam, Meghalaya, Arunachal Pradesh, Nagaland, Manipur, Mizoram and Tripura. Power System Networks of PSUs located in the region are two 400KV line going to Balipara from Dikrong (Ranga Nadi) power station and two 132KV line are also emanating from Dikrong Switchyard and feeding to Along and Nirjuli areas.

93

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

8.2

PROPOSED EVACUATION ARRANGEMENT

It is proposed to provide two outgoing bays for evacuating power at 400 KV level from Naba H.E. Project. This power would be pooled to the pooling point planned at Daporijo through one No.400kV Double circuit transmission line with Quad moose conductor (Plate-8.1). The power from Oju-I(700MW), Oju-II (1000MW), Naire (800MW), Nalo (360MW) & Dangser (552MW) H.E. Projects would also be pooled at Daporijo pooling point. The power from Daporijo pooling point would be ultimately pooled directly through HVDC Link to the National Grid. Further, it is to mention that the cost of the transmission network of 85 km distance from Naba H.E. Project to Daporijo pooling point & other end equipment at Daporijo pooling point have been considered. The Power evacuation system for Subansiri Basin is enclosed herewith for reference ( Plate-8.2).

94

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER- IX ENVIRONMENTAL ASPECTS

9.0

INTRODUCTION

The project is located near Badok/ Doloring villages under Limeking circle of Upper Subansiri district in Arunachal Pradesh. Limeking is located at about 5 km downstream of the proposed dam site. It is a small town with one primary school and one primary health center. The District headquarter, Daporijo, is located 155 km away from the dam site. 9.1 PHYSICAL ENVIRONMENT

9.1.1 Climate/Meteorology The climate in the entire region is humid and fairly uniform. Temperature varies between 39.5 C and 11.5 C as observed at Menga about 130 km d/s of project site. The relative humidity ranges between 94% and 62%. Pre-monsoon rains occur from mid-February. The average annual rainfall is about 2825 mm. 9.1.2 Topography The project lies in rugged mountaineous terrain, covered by insatiable forests fed by copious rains. A number of hilly streams intersect the region with gradual altitudinal variation.

9.1.3 Soil Cultivable land is mainly alluvial and composed of a mixture of sand and clay in varying proportions. Soils in the area are results of degradation and

95

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

weathering of rocks as well as depositional features in the form of river terraces. The soil on the slopes is mainly consists of slope wash material and supports good vegetation. The clayey soils formed on river terrace due to river deposits are fertile and has been developed into paddy fields by the local inhabitants. 9.1.4 Geology The project falls in Higher Himalayas. Here, Subansiri Group of rocks are extensively developed, from Taliha in the south-eastern part to Taksing in the northwest. The Subansiri Group consists of Maza Granite, Taksing Formation, Galensiniak Formation and Nacho Formation. All the components of the proposed project lie in metamorphic rocks of Galensiniak Formation. These are hard and competent rocks. The rocks of Subansiri Group override the quartzite/ limestone of Tali Group of rocks along a thrust plane designated as Kobaso Thrust. The other major structural elements of the region are the Main Central Thrust (MCT), Main Boundary Thrust (MBT) and intermittently exposed Main Foot Hill Thrust (FHT) along with some subsidiary thrusts and transverse faults. 9.1.5 Seismicity The entire northeast region has been classified in zone-V of the seismic zoning map of India. MBT and MCT associated with the tectonic activity are located at a far distance from the project area. Nevertheless, as a routine exercise site specific seismic design parameters needs to be determined for safe design of the civil structures, during feasibility/ DPR stage investigations.

96

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

9.1.6 Catchment Area Catchment area of Subansiri basin upto the dam site of Naba HE Project lies between longitude 9145E & 9334E and between latitude 2700N & 28 22N. The total catchment area upto the proposed dam site is about 14300 sq km. The vast stretch of the catchment possesses mainly subtropical forests, which is evergreen and dense in nature. The area above elevation of 4500 m is normally under snow cover. The snow fed area upto the proposed dam site has been estimated as 9484 sq km while the rain fed area is 4816 sq km. 9.1.7 Drainage Pattern Subansiri is a major right bank tributary of river Brahmaputra. It originates in Tibet beyond the Great Himalayan range (Central Himalaya) at an altitude of around 5340 m. main river. Several mountain streams drains into the The principal stream is Nye Chu, which may be considered Nye Chu is then joined

as the main source of river Subansiri originating from the snow clad peaks of Krakang, Shaota, Baru and Mata (EL 5389 m). Chayal Chu. 9.1.8 Initial Environmental Studies For ascertaining the land use pattern of the area, initial environmental study has been carried out as per the scope of work of the PFR. National Remote Sensing Agency (NRSA), Hyderabad, was engaged for the study. NRSA procured geo-coded Satellite data of IRS 1C PAN merged with LISS III images of 27th November, 2002 of the project area. The methodology adopted includes preparation of geo-referenced base map of project area and analysis on SGI Workstation using ERDAS Imagine image analysis software for land use/land cover classification, by another stream Laro Chu near Chayal thereby taking the name of

97

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

identification of infrastructural features, like roads and bridges etc of the area of interest. Based on the analysis of satellite data and other available ancillary information, the following outputs were generated by NRSA (Annexure-9.1) Map 1 (a) of 27th Shows IRS 1 C PAN + LISS III merged satellite image November, 2002 on 1:50,000 scale covering 7 km radius

from the dam site overlaid with FRL , location of dam site and power house. Map 1(b) Shows satellite derived landuse-landcover map on

1:50,000 scale covering 7 km radius from the dam site overlaid with FRL , location of dam site and power house. Land use /land cover map shows the following categories : Forest (High and Medium Dense Forest), Agricultural Land, Open Scrub, Barren and Rock Outcrop, Snow, River Course/ Dry River Bed.

Map 1(c) Shows the landuse- landcover classes and their


corresponding area statistics in hectares within the submergence area on 1: 25000 scale overlaid with FRL, location of dam site and power house. Map 1 (d) Shows the location of the National parks / Wildlife

Sanctuaries vis--vis the location of the dam/ Power House and 7 km radius area around the dam site.

98

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Following broad conclusions can be drawn from studies conducted by NRSA :

Total area under submergence at proposed FRL of 1035 m. (above MSL) is estimated to be 81.75 ha ( Table-9.1). (It may mentioned that as per area capacity curve, submergence area at FRL is 81.28 ha.)

It is observed that vegetation cover is mostly dominated by forest category which is 44.62 ha (54.58% of the submergence area). Entire forest vegetation is classified as high dense forest in the submergence area. Adequate compensatory afforestation will be required because of submergence of dense forest.

Table-9.1 Landuse-landcover Information within the Submergence Area S.No Landuse-landcover Category 1 2. 3. 4. 5. 6. 7. 8. 9. High Dense Forest Medium Dense Forest Low Dense Forest Open Scrub Barren / Rock Outcrop Snow Agricultural Land Human Settlement River Course including dry river bed Total 81.75 100.00 Area under submergence (Ha) 44.62 Nil Nil 2.43 Nil Nil Nil Nil 34.70 % of the total submergence area 54.58 Nil Nil 2.97 Nil Nil Nil Nil 42.45

99

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Table-9.2 Landuse-landcover Information within the 7 Km Radius from the Dam site at Naba S.No Landuse-landcover Category 1 2. 3. 4. 5. 6. 7. 8. 8. 9. High Dense Forest Medium Dense Forest Low Dense Forest Open Scrub Barren / Rock Outcrop Snow Agricultural Land Human Settlement River water River Course including dry river bed Total area 15393.87 100.00 Total Area ( ha) % of the total area

14000.40 620.30 Nil 272.76 Nil 392.71 Nil Nil 181.64 107.70

90.95 4.03 Nil 1.77 Nil 2.55 Nil Nil 1.18 0.70

There is no agricultural area present within the proposed submergence area as well as within 7 km radius (Table 9.2) which is positive sign to develop the proposed hydropower site.

100

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Other landuse categories consist of Open scrub (2.43 ha) which is insignificant in areal extent. There is no surface water bodies other than the river course. The area under river course including dry river bed is estimated to be 34.70 ha. The nearest National park is Mouling which is about 111 Km from the dam site. The nearest sanctuaries are Kane and Itanagar which are about at distance of 123 Km and 140 Km. So it is observed that the dam site is more than 100 Km away from the National park and sanctuaries.

The location of the National Parks/Sanctuaries vis--vis the dam site and the power house is presented in the Map No. 1(d) (Annexure 9.1). 9.1.9 Water Quality Population density along the reservoir is not very high. Scattered huts along the road have been observed. People are mostly engaged in agriculture. Since there is no industrial unit in or around the proposed project area and also the fact that the inhabitants are still following their age-old methods of cultivation, it is assumed that there would be no such chemical pollution in the river. However, a detailed water quality analysis would be carried out during the environmental survey to ascertain the quality of water and necessary measures would be adopted accordingly to prevent its deterioration. 9.2 BIOTIC ENVIRONMENT

9.2.1 Flora The predominant vegetation is sub-tropical type and is basically dense and evergreen in nature. Top storey comprises of the species of tall trees like Acer oblongum, Kydia calycina, Castanopsis indica, Saurauia

101

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

punduana, Schima wallichii. Middle storey comprises of species like Capparis multiflora, Photinia integrifolia in association with species like Eurya acuminata, Myrsine semiserrata, Camellia caudata, etc. The common climbers met within the area are Clematis acuminata, Holboellia latifolia, Tinospora sinensis, etc. The ground flora comprises of the bushy shrubs and herbs like Cassia mimosoides, Dianella ensifolia, Drymaria diandra, Plectranthus griffithii, Rosa indica, Solanum erianthum, etc. The excerpts from preliminary report of BSI, Itanagar, Arunachal Pradesh is placed at Annexure 9.2. 9.2.2 Fauna and Wildlife The entire project area has fairly good forest coverage. It serves as a habitat for many faunal species. But, with progress of time due to increases in human interference, shifting cultivation and other activities, wildlife has been affected. However, some of the faunal species found in the area are as follows: Bos frontalis, Felis bengalensis, Felis marmorata, Sus scrofa, Muntiacus mutjack, Macaca assamensis, Vulpes bengalensis, Vandeleuria oleracea, Talpa micrura, Ratus ratus, Coracias bengalensis, Alcedo atthius, Vanellus indicus, Dicrurus acneus, Acridotheres fuscus, Passer domesticus, Pycnonolus jocosus, etc.

Some of the high altitude fish species observed in the area are: Tor putitora, Tor tor, Schizothorax richardsonii, Barilius barna, B. bendelisis, Labeo dero, Gara gotyla gotyla, Psilorhynchus balitora, Naemacheilus botia botia, Xenentodon cancila, Channa punctatus, Mastacembelus armatus, Badis badis. There are no regular fish landing centers. Fishes are caught with the help of long line, cast nets and traps from different streams and nullahs in the area.

102

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Thus, from the above list it is evident that the species found are generally common fauna usually encountered in such ecological condition. There is no endangered or threatened species observed or recorded from the project area so far. However, a detailed survey of the area in different seasons of the year may yield a different picture on the faunal diversity of the area and which may be useful in preparation of the environmental impact assessment for the proposed project The preliminary report from ZSI, Itanagar, and from Department of Fishery Arunachal Pradesh are enclosed as Annexure 9.3 & 9.4 respectively. 9.3 PREDICTION OF ENVIRONMENTAL IMPACTS Based on above baseline data and project features, the potential impacts that are expected as a result of the proposed project are summarized as follows: 9.3.1 Impacts on land environment About 500 ha would be required for the proposed project out of which 81.28 ha would come under submergence. About 375 ha of forest land would get affected in the process. With the acquisition of forestland, the local population, dependent on these forests, might get affected. Most of the environmental impacts resultant of construction work is temporary in nature rarely lasting beyond the construction period. All these issues are to be properly addressed so that the long-term effects, if any, can be minimized. 9.3.2 Impact on Water Environment The construction of a reservoir will replace the riverine eco-system by a lacustrine ecosystem. The vectors of various diseases breed in shallow

103

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

areas are not very far from reservoir margins.

The breeding site for

mosquitoes and other vectors in impounded water is in direct proportion to the length of the shoreline. The construction of the reservoir would increase the shoreline many times as compared to the pre-project shoreline of various rivers and tributaries under submergence. In the proposed project area, malaria is the prominent vector borne disease. There are chances that its incidence may increase as the proposed project is a storage scheme. Because of the regulated flow of water some changes is also likely in the aquatic environment in the downstream areas of the project. The important changes that are likely to happen in this area are: reduction in flow rate changes in water temperature, reduction in population of stenothermal species (species adapted to small temperature range) and increase in population of eurythermal species (species adopted to higher temperature range). 9.3.3 Impacts on Air and Noise Environment Impacts on the air environment are limited to the construction period of a hydropower project. The major sources of air pollution during construction phase are emission from crushers, DG sets, construction equipments etc. Thus local air pollution (including dust and odour) will result from the operation of plant machinery and traffic. Noise and vibration due to construction activities (e.g. blasting, machinery and traffic) may disturb local wildlife and human populations. However, there will be only shortterm increase in emissions like SO2 and Suspended Particulate Matters (SPM) during the construction period of the project. The level of noise would also decrease substantially once the construction phase is over. Hence no major impact is anticipated on this account.

104

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

9.3.4 Impacts on flora and fauna Due to construction of dam about 81.28 ha of land will be inundated. The direct impact of construction activity of a water resources project in a hilly terrain is generally limited to the vicinity of the construction sites. This may alter the local diversity of flora and also affect habitat available for fauna. Changes to, or loss of habitat will affect areas used for mating, breeding, nursing, feeding and drinking for both resident and migratory wildlife. The extent and severity of these effects will vary according to the existing habitat and the particular species involved which would be known after detailed study is done on flora and fauna during the comprehensive EIA/EMP study and suitable mitigation measures would be formulated and implemented in consultation with the State Forest Department of Arunachal Pradesh. 9.3.5 Impacts on Avifauna The construction of the proposed dam will lead to formation of a reservoir, which will have a fluctuation in the water level, which precisely means the reservoir bank will remain wet throughout the year. Due to such reasons, some aquatic weeds / grasses may grow along the reservoir banks. Such conditions are generally ideal for various kinds of birds, especially water birds. However because of the presence of a good habitat it is quite likely that water birds will flock in this area in a large number. The birds from cold climatic areas could also use this area during the winter season.

9.3.6 Impacts on Fishes A dam will fragment and isolate upstream resident fish. The resident species may congregate in the tail water release site. Fish from upstream will occasionally sweep downstream during the monsoon, stay in the tail

105

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

water or swim further downstream. A dam may obstruct the route of the long and mid-distance migratory fish. There may be an impact on the fish composition due to construction of dam. A detailed fishery study would be conducted during the EIA/EMP study to determine the likely impacts and suitable mitigatory measures would be adopted. 9.3.7 Impacts on Socio-Economic Environment (Resettlement & Rehabilitation) To ascertain the extent of impact due to this proposed project, a detailed socio-economic survey would be carried out as a part of the EIA/EMP study to ascertain the degree and extent of impact and accordingly a suitable rehabilitation package would be formulated. During the construction of the project the basic problem relates to management of large population that migrate to the area in search of jobs and other allied activities. Thus migration of a population having different cultural, ethnic and social backgrounds has its own advantages and disadvantages. Exchange of ideas, cultures between various groups of people would result in a healthy bonding amongst the population at large. A new culture having a distinct socio-economic status with an entity of its own would develop. As a result of this project there would be all-round development of the region. 9.3.8 Impact on Archaeological structures/Sanctuaries or National Parks As per the initial survey there is neither any archaeological structure nor any Sanctuary or National Park that are likely to get affected due to the project directly or indirectly.

106

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

9.4

ENVIRONMENTAL MANAGEMENT PLANS

The objective of the Environmental Management Plan (EMP) is to ameliorate the negative impacts of a developmental project. The most reliable way to ensure proper implementation of these management plans is to integrate the same with various processes involved during project planning, designing, construction and operation phases. Based on the assessment of environmental impacts, following management plans will be formulated: Catchment Area Treatment Compensatory Afforestation Wildlife Conservation Resettlement and Rehabilitation Public Health Management System Muck Disposal Fishery Management Restoration of Construction Area Green Belt Development Free Fuel Provision Disaster Management MOEF Restriction on Construction of dams in Subansiri Basin Ministry of Environment and Forest (MOEF), vide their letter No: 6-I/2002 WL-I dated 27.05.2003, regarding diversion of 42 ha of land failing within the Tale Wildlife Sanctuary for construction of Subansiri Lower Project (SLP), has imposed a condition that there would be no construction of dam upstream of the Subansiri river in future. As this project is located u/s of SLP on Subansiri river this condition is required to be considered while considering the project for preparation of DPR.

107

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER X INFRASTRUCTURE

10.0

INTRODUCTION

The Dam site of Naba HE Project is located near Badok village in Upper Subansiri District of Arunachal Pradesh. Daporijo, the district Head Quarter of Upper Subansiri District is located at about 160 kms from the project site. The project township and its headquarters can be proposed at Limeking. Limeking is located almost midway between the damsite (near Badok village) and PH location (Naba village). Itanagar, the State Capital of Arunachal Pradesh is about 499 kms from the project site. Damsite is at about 825 kms from Guwahati and about 451kms from North Lakhimpur, the District HQ of North Lakhimpur District of Assam. The NH52 which runs parallel to the river Brahmaputra on its North Bank from Baihata Chariali (near Guwahati) to Murkongselek (Jonai) in Dhemaji District is about 443 Kms via Kimin from Badok village. Nearest MG Railhead is North Lakhimpur and Broad Gauge Railhead is at Nagaon. Nearest Airport is at North Lakhimpur (Lilabari). Presently, there is tri-weekly air service from Guwahati (Borjhar) to North Lakhimpur (Lilabari). There are helipads at Daporijo, Nacho, Limeking, Reddi and Taksing frequently used by Indian Army. Approximate distances and conditions of road from/to Project Site is given in Table 10.1.

108

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Table10.1 Status of Road Network connecting Project site Sl No. 1. Destination Pahumara (Take-off point of Road from NH52) to Daporijo 2. Daporijo to Nacho Approx distance 284 Km Condition of Road. Single lane road (maintained by BRO) 110 km Single lane black topped road (maintained by BRO) 3. Nacho Limeking to 40 km Single lane black (maintained by BRO) 4. Limeking Badok site) 5. Approach road 10 km to (Dam 10 km Formation cutting under progress by BRO New proposal. to PH and Adits on Left Bank 6. Approach road to Dam and Adits on Left Bank 10 Km New proposal New proposal Remarks

Provision of widening of bridges has been kept in FRs of Subansiri Middle/Upper Projects Provision of widening of road and strengthening of bridges has been kept in PFRs of Nalo and Dengser HE Projects To be widened. Provision has been kept in cost

black topped road and strengthening of

topped road estimate.

109

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Provision for widening of existing road from Pahumara/ Kimin to Daporijo has been kept in cost estimates of Subansiri Middle /Upper Projects and provision for widening and strengthening of roads & bridges from Daporijo to Nacho has been kept in cost estimates of Nalo and Dengser HE Projects. As such, the same has not been considered in cost estimate of this project. In case, Naba HE Project is decided to be taken for construction before construction of Subansiri Middle/Upper/Nalo/Dengser Projects, infrastructure requirement (R-Communication) of Naba HE Project shall need to be revised. 10.1 IDENTIFICATION REQUIREMENTS OF BROAD INFRASTRUCTURE

In order to complete the project over a period of 6 years, broad infrastructure requirements are identified as under: 10.1.1 Road Communication Network Strengthening/widening of existing road network (Table-10.1) including bridges/culvert between Limeking, project headquarter and project sites measuring about 40 km. New roads between Limeking and project sites measuring about 30 km Construction of about 20 km long roads in project township/ store areas.

10.1.2 Project headquarter, Offices and Colonies The project township is planned to accommodate about 650 quarters and 200 single/ shared accommodation in Field Hostel and Barracks.

110

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Non-residential buildings, such as Administrative building, School, Hospital, Bank, Post Office, Clubs, Auditorium, Shopping complex, Canteen, Workshops, Stores, Diesel Power House, etc will be required at project headquarter. It is estimated that the Non-residential buildings will be required about 30,000 Sqm of plinth area.

10.1.3 Miscellaneous Arrangements for Power, Fuel station and Telecommunication system etc will also require.

111

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER XI CONSTRUCTION PLANNING & SCHEDULE


11.0 INTRODUCTION

The Time Period required from Submission of this Preliminary Feasibility Report upto completion of the project has been divided into two phases: i) ii) The activities required upto obtaining investment sanction (CCEA clearance) i.e first and second stage activities. The actual period of project construction i.e third stage activities.

The activities leading to CCEA clearance need about 40 months time, and will be carried out in accordance with the prevalent guidelines for three stage clearance of hydroelectric projects circulated vide Ministry of Power Memorandum No. 16/31/2000-DO(NHPC) dated 08.06.2001. After preparation, vetting and sanction of estimates for first stage activities, the preliminary activities will be taken up at site, including survey and investigations, EIA and EMP studies and a feasibility report will be prepared and submitted to CEA, based on which CEA will declare the project commercially viable. Immediately thereafter, estimate for second stage activities will be got sanctioned and detailed investigation work will be taken up. Simultaneously, on the basis of EIA and EMP studies, clearance from MOEF will be obtained for the project so that land acquisition and infrastructure development can be taken up. After Submission of DPR the CCEA clearance is expected in 6 months.

112

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Thereafter the project will be taken up for construction and scheduled to be completed in six years (Table 11.1). The Construction Methodology & Equipment Planning has been developed on following considerations. 1. 2. 3. 4. The project construction (Stage-III) activity period has been considered as six years after completion of stage I & stage II activities. Available Geological Data at PFR Stage. Requirement of Construction Equipment has been planned to handle the quantities worked out on the basis of preliminary layout. Five Months (from May to September) rainy season has been considered while planning surface works. 11.1. CONSTRUCTION METHODOLOGY

11.1.1 Infrastructure Works The main infrastructure development is proposed to be initiated

simultaneously with preparation of DPR (STAGE-II activity) for which a provision of 18 month will be kept and completed in initial 12 months after taking up of construction activity (Stage-III). During infrastructure period Land Acquisition, construction of approach roads, bridges & culverts, arrangement of construction power will be undertaken. Critical component of project would be started from 7th month after construction of approach roads. Platform to accommodate batching plant, stores for construction material, site workshop, offices and other buildings (residential/ non residential) colonies will also be developed in infrastructure period. Crawler Dozer, Loader cum Excavator, Motor Grader, Air compressor, Road Rollers etc. are proposed for deployment during infrastructure stage.

113

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

11.1.2

Diversion of River

The construction of 2 nos 10.5 m finished diameter, Horse shoe shaped each 700m long diversion tunnel would be carried out by heading & benching method. Excavation of Diversion Tunnel will be carried out with 2 Boom drill jumbo, Air Track/Wagon Drill. Jack hammer, 2.5cum side dump loader and 20/25T L P Dumpers. Diversion tunnel excavation & concreting would be completed in 14 months. The concreting requirement of diversion tunnel would be created by Batching & Mixing plant being proposed at Dam site, Concrete pump, Transit mixer, shotcrete machine, Grout pump and shutters etc. U/s & D/s Coffer dam would be constructed immediately after construction of diversion tunnel within a period of 7 month to divert the river. However river bed excavation would be taken up after completion of 1st stage coffer dam in three months. 11.1.3 Concrete Dam

Dam abutment stripping is proposed to be carried out in 18 months. The excavation of river bed & foundation treatment would be carried out in 4 months time. Excavated material will be handled by 2.0/3.0 cum Hyd. Excavator and 25/35T Rear dumpers. Concreting of Dam & HM work would be carried out in further 36 months. Concreting would be done by developing 2 x 15 T cableways with 1.0/2.0/3.0/6.0 cum bucket. 1 No. 240cum/hr Batching& Mixing plant and 500TPH Aggregate Processing plant. 11.1.4 Intake Structure, Desilting Chamber, Silt Flushing tunnel & HRT Initially excavation of adits and approaches would be carried out in 6 months. Therefore 2 nos., 9.8 m diameter, 450/ 270 m long Intake tunnel, 6 nos. Desilting chamber of size 300m x 16m x23m and 2 nos. HRT of 8.7 m diameter would be excavated in 36 months. 2 nos. intake tunnel would be excavated by heading & benching method. Excavation of desilting chamber

114

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

would be taken up from intake tunnel. Initially a tunnel of 6.5m dia would be excavated upto full length of Desilting Chamber. Thereafter it will be expanded side wise to the full width of desilting chamber resulting in desilting chamber dome. Mucking of excavated material would be carried out through the intake tunnels. After the excavation of desilting chamber, concreting will be carried out with 10m gantry. Excavation of silt flushing tunnel & gate operation chamber would be a parallel activity. The equipment to be deployed are jack hammers, wagon drills, air compressors, skid steer loaders, hydraulic excavators, tippers, concrete pumps, transit mixers ect. Excavation of 9.75/9.80 km long, 2 nos. 8.7 m finished diameter horse shoe shaped Head Race Tunnel are proposed by Heading & Benching method. HRT will be excavated through 4 nos. adits. Excavation of HRT would be carried out by deploying four set of equipment for each tunnel i.e. 2 Boom drill jumbo, Air Track/Wagon Drill, Jack hammer, 2.5 cum side dump loader and 20/25 T L P Dumpers. Concreting will be carried out by deploying concreting equipment i.e. 38 cum/hr. Concrete pump, 6.0 cum. Transit Mixer etc. Concreting requirement would be catered by 1 no. 120 cum/hr Batching & Mixing plant installed at Desilting Chamber end & 2 nos. 80 cum Batching & Mixing plant installed at intermediate adit and surge shaft end and 500 TPH aggregate Processing Plant. 11.1.5 Surge Shaft For Construction of Surge Shaft adit to surge shaft bottom would be excavated in 2 months. After completion of construction adit, 2 nos. 23 m diameter, 110 m high, Surge shaft would be taken up from top of surge shaft. Excavation of Surge Shaft would involve pilot hole drilling, reaming of pilot hole & enlargement of reamed hole. Raise borer, Wagon Drill, 100 HP Dozers, 2.5 cum Side Dump Loader and 20/25 T LP Dumpers etc will be deployed for excavation of Surge shaft. Concreting would be completed

115

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

employing 2 m shutter, concrete pump & 80 cum batching & mixing plant installed for HRT. months. 11.1.6 Pressure Shaft Before construction of Pressure shaft, approaches and adits would be completed in 8 months. 2 nos. 7.25 m diameter & 181 m high pressure shafts will be excavated in the same manner as surge shaft by deploying Raise Borer, 2.5 cum side dump loader, 20 T LP dumper, Jack hammer etc. Steel liner erection & concreting will be carried out by deploying 30 T winches, Slipform liner etc Construction of Pressure shaft & erection of penstock would take 48 months. 11.1.7 Power House 4 X 250 (1000 MW) underground power house (136 m X 23 m X 48 m) and Transformer cum DT gate would be excavated in 18 months. For excavation of Power House ventilation tunnel would be excavated upto the crown of power house. Main access Tunnel would also be excavated simultaneously. Ventilation tunnel would be expanded side wise to the full length of power house. Thereafter it will be expanded side wise to the full width of power house resulting in Power House Cavern. Mucking of excavated material would be done through the ventilation tunnel. From Power House cavern 4 shafts of 2.0 m diameter would be excavated upto the bottom level of draft tube followed by Benching of power house cavern upto the bottom of the power house. Mucking will be carried out through Main access/TRT. The equipment to be deployed for excavation are jack hammers, wagon drills, air compressors, loader, excavators, dumpers, winches etc. Concreting of Power house would be carried out along-with Machine erection in 36 months by deploying 60 cum/hr Batching & Mixing Plant, 38 cum concrete pump etc.. Construction of surge shaft would be completed in 50

116

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Installation & Testing of Machine would be undertaken in such a manner that Project get commissioned in 72nd month from the start of Project construction. 11.1.8 Tail Race Tunnel

2 nos. 100m long horse shoe shaped Tail Race Tunnel having 8.7 m finished diameter will be excavated by heading & benching method. Excavation of Tail Race Tunnel would be carried out by one set of equipment i.e. 2 boom Drill Jumbo, Wagon drill, 2.5 cum. Side Dump Loader & 20/25 t LP Dumper etc. Excavation of TRT would be started from 9th month & will be completed in 4 months. After the excavation of powerhouse, the TRT will be concreted with the help of concrete pump, Transit mixer, Batching & mixing plant installed at Power House etc.

117

Table 11.1

CONSTRUCTION SCHEDULE OF NABA HE PROJECT IN SUBANSIRI BASIN (4X250=1000 MW), ARUNACHAL PRADESH
Sl. No. Name of Work Unit Quantity Duration (months)
1 Ha LS LS LS 8 12 3 3 2 3 4 5

Ist year
6 7 8

IInd year

IIIrd year

Schedule of Constructiom IVth year

V th year

VI th year

CCEA CLEARANCE 1 INFRASTRUCTURE DEVELOPMENT


a b 2 a b 3 a b c d 4 a b 5 Acquisition of private & forest land Construction of roads & buildings

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72

AWARD OF CONTRACTS
Tendering & awarding Mobilization

DIVERSION TUNNELS( 2 nos., 10.50 m dia, 700 m long horseshoe)


Excavation Erection of shutters & Conc. Lining HM Works Plugging of tunnels m3 m3 Job Job 4,35,000 1,12,000 LS LS 10 6 4 2

COFFER DAMS ( U/s of 25m height & D/s of 14m height)


Const.of Coffer Dams & River Diversion Reconstruction of Coffer Dams m3 6,44,000 7 4

CONCRETE DAM(110 m High, 257 m


Length at top) with Spillways & P.Pool Works

a b c d e 6

Dam abutments stripping


Excavation and foundation treatment Mass Concreting Hyromechanical Works Reservoir filling

m3 m3 m3 Job Job

8,30,000 3,00,000 11,25,000 LS

18 4 30 24 2

HRTs (2 nos., 10 km long & 8.7m dia horseshoe


) including INTAKES (2 Nos.) & DESILTING CHAMBERS ( 6 nos.)

a b c d e f g 7

Excavation of approches and Adits Excavation Concrete Lining Grouting HM Works Cleanning, Adit pluggings etc. Water conductor charging

Job m3 m3 Job Job Job Job

LS 36,66,000 10,90,000 LS LS LS LS

6 36 24 14 18 2 2

POWER HOUSE COMPLEX (Powerhouse cavern 136x30x48 & Transformer cavern 100x20x25
Const. of Adits Excavation of PH & TG
Concreting in sub & super structures Erection of EOT crane

a b c d 8

Job m3 m3 Job

LS 3,10,000 1,80,000 LS

4 18 36 3

SURGE SHAFTS (2 nos. 23m dia. of 110m high) a Const. of approches


Excavation Concreting & HM Works c

Job m3 m3

LS 1,89,600 50,000

4 30 20

b 9

STEEL LINED PRESSURE SHAFTS ( 2 nos., 7.2 m dia,181 m vertical hight ) & Penstocks a Const.of approaches & adit
Excavation Erection of steel liners & Concreting c

Job m3 m3

LS 95,000 40,000

8 24 24

b 10 a b 11 12 a

TAILRACE TUNNELS ( 2 nos. 8.7m dia of 100 m length )


Excavation Concreting & HM Works m3 m3 m3 10,600 7,000 Exc. 33,000 Conc. 12,500 4 6 12 -

POT HEAD YARD ELECTRO-MECHANICAL WORKS


Erection, Testing & Commisioning of all four units

Job

42

Note: Since the date of CCEA clearance cannot be anticipated at this stage, the time assumed for various activities is inclusive of the effect of monsoon.

118

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER XII COST ESTIMATE

12.0 12.1

COST ESTIMATE PRELIMINARY COST ESTIMATE FOR CIVIL, HYDRO-

MECHANICAL, ELECTRO-MECHANICAL WORKS The estimate has been prepared to arrive at the Capital Cost of Naba H.E. Project and is of Pre-feasibility level of accuracy. The base date of the estimate is June 2003 and the Cost is expressed in Indian Rupees. The Cost Estimate is divided into Civil, Electrical and Transmission Works. For Civil Works, the sub heads are as under 12.1.1 I-Works Under this head, provision has been made for various components of the Project as detailed hereunder 12.1.2 A-Preliminary Under A-Preliminary, provision has been made for all surveys and investigations to be conducted to arrive at the optimum of the Project Components. 12.1.3 B-Land This covers the provision for acquisition of land for construction of the Project, colonies, offices and stores and compensation for trees and standing crops etc. This head also contains the provision for Rehabilitation and Resettlement measures for Project Affected People.

119

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

12.1.4 C-Works This covers the cost of Diversion Tunnel, Coffer dam, Concrete Dam and Spillway along with associated Hydro-mechanical equipment. 12.1.5 J-Power Plant Civil Works This covers the cost of project components viz. Intake Structure, Headrace Tunnel and TRT, Power House and Transformer Cavern, Pressure Shaft, Surge Shaft and other Appurtenant Works. The quantities indicated in the estimates for C - Works & J-Power Plant Civil Works (Civil & HM) are calculated from the preliminary Engineering drawings and as per experience of other on-going or commissioned projects. The unit rates for various items are taken as per the Guidelines issued by CEA for preparation of PFRs. It has been assumed that the quarry is available at a distance of 10 Kms from the work site. 12.1.6 K-Buildings Buildings, both residential and non-residential have been provided under this head. Under the permanent category only those structures have been included which shall be subsequently utilized during the operation and maintenance of the project. The costs are worked out on plinth area basis prevalent in the area for the type of construction involved. 12.1.7 O-Miscellaneous Provision under this head has been made @ 4% of I- works for the Capital & running cost of Electrification, Water Supply, Sewage Disposal, Fire Fighting Equipments, Medical Assistance, Recreation, Post Office, Telephone and Telegraph Office, etc. The Provisions have been made for the security arrangements, inspection vehicles, schools, transport of labour, laboratory testing, R&M of guest house and transit camps, community center, retrenchment compensation, photographic instruments as well as R&M charges etc.

120

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

12.1.8 P-Maintenance During Construction and Y-Losses on Stock A provision of 1% and 0.25% of C-Civil works, J-Power Plants, KBuildings & R-Communications has been made for maintenance of works during construction period and losses on stock respectively. 12.1.9 Q-Special Tools and Plant It is assumed that the work will be carried out through Contracts and not through departmental construction. Accordingly, provision for general purpose equipment and inspection vehicle only has been made as per CWC guidelines. 12.1.10 R-Communication Provision under this head covers the cost of new roads, widening/improvement of roads and strengthening of bridges. The costs of roads and bridges are based on the rate structure prevalent in the area of the Project, for the type of construction involved. 12.1.11 X-Environment and Ecology Provision under this head has been taken as 2% of I -Works towards bio-diversity Conservation, creation of Green Belt, Restoration of Construction Area, Catchment Area Treatment, Compensatory Afforestation etc 12.1.12 II-Establishment Provision for establishment has been made at 8% of I-works minus BLand for civil works. 12.1.13 III-Tools and Plants This provision is distinct from that under Q-Special T&P and is meant to cover cost of survey instruments, camp equipment and other small tools and plants. The outlay is provided at 1% of cost of I-works.

121

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

12.1.14 IV-Suspense No provision has been made under this head as all the outstanding suspense are expected to be cleared by adjustment to appropriate heads at completion of the project. 12.1.15 V-Receipts and Recoveries Under this head, provision has been made for estimated recoveries by way of resale or transfer of equipment used in infrastructure works. 12.1.16 Electrical Works and Generating Plant The cost of Generating Plant and Equipment is based on indigenous sources. The prices of auxiliary equipment and services are based on prevailing market prices/costs incurred at other ongoing or commissioned projects.

122

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

NABA H. E. PROJECT, ARUNACHAL PRADESH, (4 X 250 MW) ABSTRACT OF COST OF WORKS Description

S.No

Amount (Rs. in Crores) ( June 2003 P.L.)

A 1.

CIVIL WORKS DIRECT CHARGES I - Works A - Preliminary B - Land C - Works J - Power Plant Civil Works K - Buildings O - Miscellaneous P - Maintenance Q-Special Tools & Plants R - Communication X - Environment & Ecology Y - Losses on Stock Total of I-Works II - Establishment @ 8% of cost of I-Works less B-Land III - Tools and Plants @ 1% of cost of I-Works IV - Suspense V - Receipt & Recoveries (-) TOTAL DIRECT CHARGES

29.89 6.34 750.64 1625.92 65.66 111.69 25.52 4.53 109.79 55.84 6.38 2792.20 222.87 27.92 0.00 -2.43 3040.56

2.

INDIRECT CHARGES a) Capitalised Value of Abatement of Land Revenue b) Audit and Account Charges @1% of cost of I-Works TOTAL INDIRECT CHARGES TOTAL OF DIRECT & INDIRECT CHARGES ABSTRACT :

0.10 27.92 28.02 3068.58

A B C C D

Civil Works Electrical Works Transmission Works TOTAL COST IDC Total Cost With IDC

3068.58 743.81 117.00 3929.39 470.50 4399.89

123

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

A - PRELIMINARY S. No. Particulars Unit Qty Rates Amount Rs. in Lakhs

1 2 3

Expenditure incurred for preparation of PFR Detailed Survey for final location Aerial Survey contour survey for reservoir basin including establishment of permanent bench marks Geological surveys, Geophysical surveys and rock mechanics tests Ground water studies Hydrological and Metrological Surveys including establishment of rain gauges/river gauges and discharge, sedimentation station and their running Investigation for foundation and rock testing. Drilling 3000m . Drifting - 1000m Investigation for availability of construction materials

-L. S. L. S.

----

----

14.00 200.00 60.00

4 5 6

L. S. L. S. L. S.

----

----

200.00 10.00 100.00

7 8 9 10 11 12 13 14 15 16 17 18 19 20

-L. S. -----10 --------

------5 -------Total

400.00 75.00 100.00 150.00 50.00 35.00 50.00 100.00 100.00 200.00 50.00 1000.00 20.00 75.00 2989.00

Construction of access roads to facilitate investigations L. S. Model Experiments Computer & Telecommunication Preparation & Printing of project report Vehicles for inspecting officers for site investigations L. S. L. S. L. S. No.

Construction power for investigation and infrastructure L. S. works Office and camp equipments L. S. R & M of Office and Transit camps etc. L. S. Preliminary soil test establishing soil testing laboratory L. S. Consultant's fees including charges for preliminary design work for advice Training of engineers during investigation and preparation of project reports. Environmental & ecological studies L. S. L. S. L. S.

124

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

B - LAND S. No. Particulars Area (ha) Rates (Rs Lakhs/ha) Amount (Rs. in Lakhs)

1a

Forest/Govt. Land a) Reservoir Area b) Project features c) Township, stores area and roads d) quarry site e) muck Disposable area f) Transit Camp and Guest houses g) Land for rehablitation purpose

60.00 100.00 60.00 20.00 10.00 5.00 80.00 Total

0.65 0.65 0.65 0.65 0.65 0.65 0.65

39.00 65.00 39.00 13.00 6.50 3.25 52.00 217.75

Private Land a) Reservoir Area b) Project features c) Township, stores area and roads d) Transit Camp and Guest houses

40.00 50.00 75.00 10.00

1.10 1.10 1.10 1.10 Total Grand Total

44.00 55.00 82.50 11.00 192.50 410.25 100.00

Rehabilitation & Resettlement L. S.

Cost of Establishment for land acquisition and Rehabilitation @ 6.25% of Item 1 & 2 Solatium charges @ 30% of the cost of Private Land Interest charges on amount of award for the period between taking over possession of land and date of award @ 12% per annum on 25% of cost of total compensation for 2 years Legal charges @ 1% of total compensation Labour and material required for measurement & demarcation of land/Properties @ 1% of cost of land Acquisition

31.89

57.75

24.62 5.10

6 7

4.10

Total 633.71 Note : 50% of rock quarries and all clay borrow areas fall in submergence area/ project area. Hence provision for these has not been made

125

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

ABSTRACT OF COST OF C - WORKS S. N. Description Amount (Rs. In Lakhs) CIVIL 1. 2. 3 DIVERSION TUNNEL COFFER DAMS CONCRETE DAM INCLUDING SPILLWAY AND PLUNGE POOL 10463.34 7412.92 HM TOTAL

489.30 10952.64 7412.92

48557.93 3361.05 51918.98

TOTAL 66434.19 3850.35 70284.54 ADD FOR WORKS TAX @ 6.8% 4517.52 261.82 4779.35

GRAND TOTAL 70951.72 4112.17 75063.89

126

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

DIVERSION TUNNEL S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

Surface Excavation Cum 45000 125 300 56.25 315

1.1 Common excavation 1.2 Rock excavation

Cum 105000

Underground excavation

Cum 285000

1000

2850

Support System M MT Cum Cum 73000 900 13000 1400 400 42000 4000 7000 292 378 520 98

3.1 Rockbolts 3.2 Steel Rib Supports 3.3 Shotcrete 3.4 Concrete lagging if required 4 Concrete

4.1 Concrete lining M-20 4.2 M-15 M-20 M-25

Cum Cum Cum Cum

49000 10000 31000 22000

4000 2930 3390 3610

1960 293 1050.9 794.2

Reinforcement

MT

1500 Sub total A

27000

405 9012.35

Miscellaneous and ancillary works @7.5% of sub-total A

7.50% Sub total B

675.93 9688.28 96.88 193.77 290.65 193.77

7 8 9 10

Instrumentation @ 1% of sub-total B Dewatering @ 2% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lum-sum items

1.00% 2.00% 3.00% 2.00%

Total civil works 10463.34

127

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

S. No. 1

Description

COFFER DAMS Unit Qty.

Rate

Amount (In Lakhs)

Surface Excavation Cum 20000 125 25

1.1 Common excavation

Embankment Construction Cum Cum Cum 1520000 390000 22000 342 354 901 5198.4 1380.6 198.22

2.1 Earth/ Rockfill 2.2 Impervious Core 2.3 Filter

Concrete Cum Cum 500 500 2560 2930 Sub Total(A) 12.8 14.65 6829.67 34.15 Sub Total(B) 6863.82 205.91 205.91 137.28

3.1 M-10 3.2 M-15

Miscellaneous and ancillary works @.50% of sub-total A

0.50%

5 6 7

Dewatering @ 3% of sub total-B Contingency @ 3% of sub-total-B Work Charged establishment @ 2% of Sub-total-B except of lum-sum items

3.00% 3.00% 2.00%

Total civil works

7412.92

128

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CONCRETE DAM INCLUDING SPILLWAY AND PLUNGE POOL S. No. Description Unit Quantity Rate Amount ( Rs. in Lakhs)

Surface Excavation Cum Cum 580000 550000 125 300 725 1650

1.1 Common excavation 1.2 Rock excavation

Support system M Cum 8000 4500 400 4000 32 180

2.1 Rock bolts 2.2 Shotcrete

Concrete Cum Cum Cum 650000 240000 235000 2930 3390 3610 19045 8136 8483.5

3.1 M-15 3.2 M-20 3.3 M-25

Reinforcement steel

MT

20000

27000

5400

Sub Total(A) 43651.50 5 Miscellaneous and ancillary works @3.0% of sub-total 3.0% 1309.55 Sub-Total(B) 44961.05

6 7 8 9

Instrumentation @ 1% of sub-total Dewatering @ 2% of sub total Contingency @ 3% of sub-total Work Charged establishment @ 2% of Sub-total except of lum-sum items

1% 2% 3%

449.61 899.22 1348.83

2% Total civil works

899.22 48557.93

129

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

J -POWER PLANT APPURTENANCES (CIVIL WORKS) S. NO. Description Amount (Rs. in Lakhs) CIVIL HM TOTAL

1 2

ADITS INTAKE STRUCTURE INCLUDING INTAKE TUNNEL UPTO DESILTING CHAMBERS

4095.84

21.42

4117.26 8656.37

7212.62 1443.75

3 4 5 6 7 8

DESILTING CHAMBERS HRT & TRT SURGE SHAFT PRESSURE SHAFT AND PENSTOCK POWER HOUSE AND TRANSFORMER CAVERN POTHEAD YARD

31752.34 653.42 73282.12 185.96 5286.35 298.20 3388.96 6857.55 16875.53 885.74

32405.75 73468.07 5584.55 10246.51 16875.53 885.74

Total 142779.50 9460.29 152239.79

ADD FOR WORKS TAX @ 6.8%

9709.01

643.30

10352.31

GRAND TOTAL 152488.50 10103.59 162592.09

130

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

ADITS S. No. 1 1.1 1.2 2 3 3.1 3.2 3.3 4 4.1 4.2 Description Unit Qty. Rate Amount ( Rs. in Lakhs) 13.75 96.00 1500.00

Surface Excavation at Portals Common excavation Rock excavation Underground excavation Rock stabilisation and supports Rockbolts/Rock 25 mm dia Shotcrete Structural steel Rib Concrete Cement Concrete lining M-20 Concete in portals, backfill etc. M-15 M-20 Reinforcing steel

Cum Cum Cum

11000 32000 150000

125 300 1000

m Cum MT

110000 12000 800

400 4000 42000

440.00 480.00 336.00

Cum Cum Cum MT

10000 2500 8000 200 Sub Total(A) 3.5% SubTotal(B) 1% 2% 3% 2%

4000 2930 3390


27000

400.00 73.25 271.20 54.00 3664.20 128.25 3792.45 37.92 75.85 113.77 75.85 4095.84

Miscellaneous and ancillary works @3.5% of sub-total A

7 8 9 10

Instrumentation @ 1% of sub-total B Dewatering @ 2% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total except of lum-sum items

Total Civil Cost

131

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

INTAKE STRUCTURE INCLUDING INTAKE TUNNEL UPTO DESILTING CHAMBERS S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

1 1.1 1.2

Surface excavation Common excavation Rock excavation Cum Cum 3000 49000 125 300 1000 3.75 147.00

Underground excavation

Cum

110000

1100

3 3.1 3.2 3.3 3.4 4 4.1 4.2 4.3 4.4 5 6

Rock stabilisation and supports Rock bolts Steel Rib Supports Shotcreting Concrete lagging if required Concrete Concrete Linning M20 Concrete M15/40 M-20 M-25 Reinforcing Steel Miscellaneous and ancillary works @1.5% of sub-total Instrumentation @ 1% of sub-total B Dewatering @ 1% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lum-sum items Cum Cum Cum Cum MT 24000 5000 11000 55000 4400 Sub Total(A) 1.5% Sub Total(B) 1% 1% 3% 4000 2560 3390 3610 27000 960.00 128.00 372.90 1985.50 1188.00 6641.15 99.62 6740.77 67.41 67.41 202.22 m MT Cum Cum 46000 500 8000 600 400 42000 4000 7000 184.00 210.00 320.00 42.00

7 8 9 10

2% Total Civil Cost

134.82 7212.62

132

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

DESILTING CHAMBERS S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

1 1.1 1.2

Surface excavation Common excavation Rock excavation Cum Cum 14000 35000 125 300 1000 17.50 105.00

Underground excavation

Cum

1320000

13200

3 3.1 3.2 3.3 4 4.1 4.2 4.3

Rock stabilisation and supports Rock bolts Steel Rib Supports Shotcreting Concrete Concrete Linning M20 Concrete Linning M25 Concrete in portals, backfill etc. Concrete M15/40 M-20 M-25 Cum Cum Cum Cum Cum Cum MT 6000 130000 20000 2560 3390 3610 153.60 4407.00 722.00 54.00 28406.10 994.21 29400.31 294.00 588.01 882.01 588.01 31752.34 115000 19000 4000 4500 4600.00 855.00 M MT Cum 320000 400 2600 42000 48000 4000 1280.00 1092.00 1920.00

5 6

Reinforcing Steel

200 27000 Sub Total(A)

Miscellaneous and ancillary works @3.5% of sub-total Instrumentation @ 1% of sub-total B Dewatering @ 2% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lum-sum items

3.5% Sub Total(B) 1% 2% 3% 2% Total Civil Cost

7 8 9 10

133

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

HRT & TRT S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

Surface excavation Cum Cum 6500 25000 125 300 8.13 75.00

1.1 Common excavation 1.2 Rock excavation

Underground excavation

Cum

2115000

1000

21150.00

Support System M MT Cum Cum 940000 9400 145000 12300 400 42000 4000 7000 3760.00 3948.00 5800.00 861.00

3.1 Rockbolts 3.2 Steel Rib Supports 3.3 Shotcrete 3.4 Concrete lagging if required 4

Concrete Cum Cum Cum Cum MT 505000 5000 190000 12000 4000 2930 3390 3610 20200.00 146.50 6441.00 433.20 297.00 63119.83 4733.99 67853.81 678.54 1357.08 2035.61 1357.08 73282.12

4.1 Concrete Linning M20 4.2 Concrete M15/40 4.3 M-20 4.4 M-25 5 6 Reinforcement Miscellaneous and ancillary works @7.5% of sub-total A Instrumentation @ 1% of sub-total B Dewatering @ 2% of sub total B

1100 27000 Sub-Total(A) 7.5% Sub-Total(B) 1% 2% 3% 2% Total civil works

7 8

9 Contingency @ 3% of sub-total B 10 Work Charged establishment @ 2% of Sub-total B except of lum-sum items

134

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

SURGE SHAFT S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

Surface Excavation Cum Cum 14000 40000 125 300 17.50 120.00

1.1 Common excavation 1.2 Rock excavation 2 Underground excavation

2.1 Surgeshaft Excavation 2.2 Surgeshaft Excavation with raise borer 2.3 Concrete Lagging

Cum Cum Cum

135000 995 400

1200 1620.00 1500 7000 14.93 28.00

Rock stabilisation and supports m Cum MT 32000 5000 300 400 4000 42000 128.00 200.00 126.00

3.1 Rock bolts / anchors 25mm dia 3.2 Shotcrete 3.3 Structural steel Rib 4 Concrete

4.1 Concrete M20 4.2 M-25 5 Reinforcing steel

Cum Cum MT

5000 45000 4000

3390

169.50

2930 1318.50 27000 1080.00 Sub Total(A) 4822.43

6 7 8 9 10

Miscellaneous and ancillary works @1.5% (sub-total) A Instrumentation @ 1% of sub-total B Dewatering @ 2% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lum-sum items

1.5% 1% 2% 3% 2% Total Civil Cost

72.34 Sub Total(B) 4894.77 48.95 97.90 146.84 97.90 5286.35

135

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

PRESSURE SHAFT AND PENSTOCK S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

Underground excavation

Cum

95000

1200

1140.00

Rock stabilisation and supports m Cum MT 47000 7000 300 400 4000 42000 188.00 280.00 126.00

2.1 Rock bolts / anchors 25mm dia 2.2 Shotcrete 2.3 Steel ribs support

Concrete Cum 40000 3390 Sub Total(A) 1356.00 3090.00 77.25 Sub Total(B) 3167.25 31.67 31.67 95.02 63.35 3388.96

3.1 Backfill concrete M20 4 Miscellaneous and ancillary works @2.5% (sub-total)

2.5%

5 6 7 8

Instrumentation @ 1% of sub-total B Dewatering @ 1% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lumsum items

1% 1% 3% 2% Total Civil Cost

136

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

POWER HOUSE AND TRANSFORMER CAVERN S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

Under ground excavation

Cum

360000

1000

3600.00

Rock stabilization and Supports including accessories

2.1 2.2 3 3.1 3.2 3.3 4 5 6 6.1 6.2 6.3 7

Rockbolts Shotcrete Concrete including formwork M15 M20 M25 Reinforcing Steel Structural Steel for roof trusses etc. Masonry Work Stone Masonry Brick Masonry Stone pitching Miscellaneous and ancillary works @4.5% of sub-total Instrumentation @ 1% of sub-total B Dewatering @ 2% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lum-sum items

m Cum

135000 15000

400 4000

540.00 600.00

Cum Cum Cum MT MT

10000 110000 65000 14000 100

2930 3390 3610 27000 42000

293.00 3729.00 2346.50 3780.00 42.00

Cum Cum Cum

150 800 400 4.5%

2000 2000 781 Sub Total(A)

3.00 16.00 3.12 14952.62 672.9 15625.49 156.25 312.51 468.76 312.51 16875.53

Sub Total(B) 8 9 10 11 1% 2% 3% 2% Total Civil Cost

137

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

POTHEAD YARD S. No. Description Unit Qty. Rate Amount ( Rs. in Lakhs)

Surface excavation Cum Cum 8000 25000 125 300 10.00 75.00

1.1 Common excavation 1.2 Rock excavation

Concrete including formwork Cum Cum Cum MT MT 50 2500 8000 2000 850 2930 3390 3610 27000 42000 73.25 271.20 72.20 229.50 21.00

2.1 M15 2.2 M20 2.3 M25 3 4 Reinforcing Steel Structural Steel for roof trusses etc. Masonry Work Stone Masonry/Brick Masonry 6 Miscellaneous and ancillary works @4.5% of sub-total A

Cum

2000 4.5%

2000

40.00 792.15 35.65

Sub Total(A)

Sub Total(B) 7 8 Dewatering @ 2% of sub total B Contingency @ 3% of sub-total B Work Charged establishment @ 2% of Sub-total B except of lum-sum items 2% 3%

827.80 16.56 24.83

2% Total Civil Cost

16.56

885.74

138

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

HYDRO MECHANICAL EQUIPMENT


S. No. Detail of Items Unit Qnty. Rate(Rs.) Amount

1 Diversion tunnel gate & hoist Gate(Fixed wheel type) (5.0m x 10.5m)- 4 No. Embedded Parts - 4 Set Ropedrum hoist 155 T Capacity - 4 Set Hoist Supporting structure and trestle - 4 Set

Ton Ton Ton Ton

280 100 188 120

60000 50000 100000 50000

168.00 50.00 188.00 60.00

2 Spillway structure a) Lower spillway Radial Gates (8.25m x 10m) - 7 Nos. Ton 1050 Embedded Parts (including anchorages, hoist structure) including breast wall liners - 7 Set Hydraulic Hoist 300T capacity (One power pack + Two cylinders of 150T Cap. each) b) Bulkhead Gate( Fixed Wheel type) 8.25m x 12m 1 No. Embedded Parts - 7 Set Gantry crane 320 T capacity Portable oil filter unit along with Contamination checking kit & Low vacuum dehydration and degassification unit Portable trolley mounted gasoline engine operated power pack c) Upper Spillway Radial Gates (8m x 10m) - 2 Nos. Embedded Parts (including anchorages, hoist structure) including breast wall liner - 2 Set Hydraulic Hoist 120T capacity (One power pack + Two cylinder of 60T Cap.each) d) Spillway Stoplogs (Slide type) 8.0m x 10m - 1 Set Embedded Parts - 2 Set Lifting Beam Gantry crane 25 T capacity Storage groove 3 Intake structure a) TrashRacks and Embedded parts (25m x 22m) - 2 Set Trash rack cleaning machine b) Intake gate(fixed wheel type) including ballast (8.6m x 9.8m) - 2 No. Embedded Parts -2 Set Rope drum hoist 200T Cap.- 2 Sets Hoist platform and trestle - 2 Sets Ton Set Ton Ton Ton Ton Ton Set Ton Ton Set Set 1 Set Ton Ton Set Ton Ton Ton Set Ton 1 130 70 2 40 24 3 1 5 630

100000 1050.00 50000 315.00 805.00 81.00 140.00 320.00

7 11500000 135 60000 280 50000 1 32000000

1000000 1500000 100000 50000 5500000 60000 50000 50000 2500000 50000

10.00 15.00 130.00 35.00 110.00 24.00 12.00 1.50 25.00 2.50

330 50000 1 10000000 210 64 120 80 60000 50000 100000 50000

165.00 100.00 126.00 32.00 120.00 40.00

139

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Desilting Chamber Gates Inlet Gates


Gate (Fixed Wheel Type) including ballast 5.6m x5.6m - 6No. Embedded parts - 6 Set Rope drum hoist 105T Capacity- 6 Sets Hoist platform and Trestles - 6 Sets Outlet Gates Gate (Slide Type) 5.0m x5.0m - 2No. Embedded parts - 6 Set Lifting Beam EOT Crane 50T Cap. Ton Ton Ton Ton Ton Ton Ton Set 348 108 192 132 60000 50000 100000 50000 208.80 54.00 192.00 66.00 30.00 24.00 2.50 45.00

50 60000 48 50000 5 50000 1 4500000

Silt Flushing Gates (Slide Type) Gates (Service & Emergency) 2.5m x2.0m - 12 Nos. Embedded parts (including bonnet, bonnet cover,gate body liner etc.)-2Set Hydraulic Hoist comparising of Two Double acting cylindres of 300T Cap. each and one common power pack for each set of service and emergency gates) Surge shaft gate & hoist Gate(Slide Type) 7.25m x7.25m - 2 No. Embedded parts - 2 Set Rope drum hoist 150T Cap.- 2 Set Hoist platform and trestle - 2 Set Draft Tube gates & hoist Gate (Fixed Wheel type) 4.2m x6.0m - 8 No. Embedded Parts - 8 Set Lifting Beam Gantry Crane 35T Cap. Pressure shaft steel Liner Steel Liner - 2 No. (ASTM A537 Cl.1) Bifurcation (ASTM A 517 Gr. F ) - 2 Nos. Adit Gates Adit gates (2.5m x2.5m) - 3 Nos. Embedded Parts - 3 Set Instruments and Remote Control D G Set 500 KVA Spare parts & contingency (5% of total cost)

Ton Ton Set

84 216

100000 50000

84.00 108.00 600.00

6 10000000

Ton Ton Ton Ton

200 80 94 60

60000 50000 100000 50000

120.00 40.00 94.00 30.00

Ton Ton Ton Set

176 60000 56 50000 3 50000 1 4200000

105.60 28.00 1.50 42.00

Ton Ton

9000 300

70000 77000

6300.00 231.00

Ton Ton Set Set

24 12

60000 50000

14.40 6.00 100.00 25.00 633.84

10 11 12

1 10000000 1 2500000

Total

13310.64

140

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

K - BUILDINGS S. No. Description Unit Total Plinth Area Rate(Rs.) Amount (Rs. in Lakhs)

Residential Building C/o Permanent residential buildings Service charges @ 31% Total Residential Buildings Sqm 45000 7000.00 3150.00 976.50 4126.50

Non-Residential Building C/o Permanent non-residential buildings Service charges @ 22.5% Total Non-Residential Buildings Sqm. 30000 5500.00 1650.00 371.25 2021.25

(Residential + Non-Residential)

6147.75

Add for Works Tax @ 6.8% Grand Total

418.047 6565.80

141

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

Q-Spl T&P for Infrastructure Development


Sl.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Description of equipment Hydraulic Excavator, 1.0 cum. Loader cum Excavator, 1.0/0.25 cum. Crawler Dozer, 200 FHP Crawler Dozer, 100 FHP Wheel Dozer 300 FHP Multi Utility Loader (Skid/Articulated) Motor Grader, 145 FHP Diamond Core Drill (Mechanical) Diamond Core Drill (Hyd) Rock splitter Hyd. Rock breaker mounted on 20 t Hydraulic Excavator Air Track/Wagon Drill Jack Hammer/Pavement Breaker Compressed Air(cfm) Mobile Crane, 10 t Pick & Carry Mobile Crane, 20 t (Rough terrain) Road Roller, 8/10 t Dewatering Pump Tipper 4.5/6.0 cum. Truck, 10 t Low Bed Tractor Trailor, 30 t Concrete Mixer, 14/10 cft Explosive Van, 5/7 t Water Tanker/Sprinkler, 10 KL Petrol/Diesel Tanker, 10 KL Bus/Mini Bus Car/MUV Jeep (Petrol/Diesel) Ambulance Workshop Equipment Fire Tender Recovery Van Pick up Van/L.C.V Motor Boat Quantity Rate Amount (Nos.) (Rs in (Rs in Lacs) Lacs) 1 50.00 50.00 1 1 2 1 1 1 2 2 2 1 4 10 3500 1 1 2 L.S 4 4 1 2 1 1 1 4 2 20 2 L.S 1 1 2 2 20.00 85.00 50.00 95.00 40.00 60.00 15.00 60.00 5.00 60.00 16.00 0.35 0.0125 10.00 70.00 10.00 20.00 10.00 8.00 50.00 2.00 10.00 15.00 12.00 10.00 5.50 4.50 10.00 20.00 15.00 5.00 5.00 5.00 Total 20.00 85.00 100.00 95.00 40.00 60.00 30.00 120.00 10.00 60.00 64.00 3.50 43.75 10.00 70.00 20.00 20.00 40.00 32.00 50.00 4.00 10.00 15.00 12.00 40.00 11.00 90.00 20.00 20.00 15.00 5.00 10.00 10.00 1285.25

142

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

DISTRIBUTION OF COST UNDER HEAD Q - SPECIAL T & P AND V - RECEIPT & RECOVERIES

Description

Cost (Rs. In lakhs)

R&R

Cost of equipments excluding inspection vehicles

1109.25 277.31

207.98

Cost of inspection vehicles (Item 26 to 29 & 31)

176.00 176.00

35.20

Provision under head Q - Spl. T&P Recoveries to be shown under V- Receipt and Recoveries

1285.25 453.31 243.18

143

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

R- COMMUNICATION S. No. Description Length (km) Rate (Rs. Amount In lakhs) (Rs. in Lakhs)

New Road 1 Left bank of Singit river connecting Limeking to Damsite 2 Approach road connecting Dam Site , PH site Adits etc left bank of Singit river 3 Road for Township and Store area a Township area i) ii) Two lane Single lane 5 10 120 90 600 900 10 20 90 90 900 1800

b Store area i) ii) Two lane Single lane 1 4 120 90 120 360 4680

Subtotal "A" B. Widening and Strengthening of roads (including Upgradation/improvement of existing Bridges)

1 Approach road from Nacho to Limeking 2 Widening of Miscellaneous sections of existing roads Subtotal "B"

40 20

70 70

2800 1400 4200

C Bridge on river Singit 1 Permanent Bridge 2 Bailey Bridge Near Power House/Damsite Subtotal "C" Grand Total (A+B+C) Add for Works Tax @ 6.8% Grand Total 2 X 0.12 2 X 0.12 L.S. L.S. 1000 400 1400 10280 699.04 10979.04

144

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

V - RECEIPT & RECOVERIES S. No. Item Amount (Rs. In Lakhs) 1. Recovery from the Sale of Equipments 243.18

Total

243.18

145

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

COST ESTIMATE OF NABA H.E. PROJECT ( 4 X 250 MW)


Electro Mechanical Works Generator, Turbine and Accessories
S.No. 1 A 1 2 3 4 5 6 7 8 9 10 11 12 B 13 14 15 16 17 18 19 20 21 Item Particulars 2 (a) Generating units and Bus Ducts 4 X 250 MW, 214.3 rpm, Head 221 meters Step up transformer 16/400/3 KV, 102 MVA Auxiliary Electrical Equipment for Power Stations, (Except Transformer) (5% of item 1) Auxiliary Equipment & Services for Power stations, (5% of Item 1) Spares (5% of 1, 3% of 2-4) SUB TOTAL (A1) Central Sales tax **4% of item 6 Transportation & Insurance 6% of basic cost(Item 1 - 5) Erection & commissioning 8% of item 6 except spares SUB TOTAL (A2) Establishment,Contingency,other charges , 11% of item 1-5 Except duties SUB TOTAL (A) GIS (400KV) XLPE Cable 400 kV with cable termination kit Switchyard Spares ( 2% of item 13 and item 14) Subtotal(B1) Transportation & Insurance 3% of basic cost(item 13-15) Erection & commissioning 8% of item 16 except spares Subtotal(B2) Establishment,Contingency,other charges , 8% of item 13-15 except duties + 2% handling charge on custom duties of item 13-15 SUB TOTAL (B) GRAND TOTAL (A+B) (In Lacs) *Custom duty in case of imported Items **Not applicable for Imported Items 7 bays 2.8 km 600 lacs/bay 400000 US$/km Qty 3 4 13 Rate 4 3700.00 Rs/KW 250.00 Rs/KVA Amount (Rs Lcs) 5 37000.00 3315.00 1850 1850 2060.45
Excise Duty* Rate 6 16 16 Amount 7 5920.00 530.40 (Rs Lcs) 5+7 42920.00 3845.40 Total

16 16 16

296 296 329.67

2146 2146 2390.12 53447.52 2137.90 2764.53 4084.59 62434.54 5068.30 67502.84

4200.00 515.2 94.30

22 Custom duty 22 Custom duty 22 Custom duty

924.00 113.344 20.75 1058.09

5124.00 628.54 115.05 5867.59 144.29 460.20 6472.08 405.92 6878.01 74380.85

146

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

COST ESTIMATE OF NABA H.E. PROJECT ( 4 X 250 MW)


Electro Mechanical Works Power Evacuation Cost S.No. 1 1 2 Item Particulars 2 400 KV Conventional Switchyard at receiving end Double circuit Transmission line with quad moose conductor (400 KV, 85km) Switchyard Spares [ 2% of item 1& 2 ] Subtotal(1) Central Sales tax **4% of item 1,2 & 3 Transportation & Insurance 3% of basic cost(item 1-3) Erection & commissioning 8% of item 4 except spares Subtotal(2) Establishment,Contingency,other charges , 8% of item 1-3 except duties GRAND TOTAL (In Lacs) *Custom duty in case of imported Items **Not applicable for Imported Items Qty 3 2 Rate Amount (Rs Lcs) 5 500 Excise Duty* Rate Amount 6 7 16 80.00 Total (Rs Lcs) 5+7 580.00

4 250 lacs/ba bays y 85 90 Lacs/k Km. m

7650

16

1224.00

8874.00

3 4 5 6 7 8 9

163.00

16

26.08

189.08 9643.08 385.72 249.39 756.32 11034.51 665.04 11699.55

147

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

CHAPTER XIII ECONOMIC EVALUATION


13.0 ECONOMIC EVALUATION

The Project has been contemplated as a run-off the river scheme on river Subhasiri/ Singit. The project is estimated to cost Rs. 3929.39 crores excluding IDC at June 2003 Price Level. Sale price of energy generated at powerhouse bus bars has been worked out as 2.43 Rs./unit (Table 13.2) with free power to Home State and Rs. 2.14 per unit (Table 13.2 A) without free power to Home state. 13.1 ECONOMIC JUSTIFICATION

The energy generation of the project with an installed capacity of 4 X 250 MW has been estimated at 3995.25 MU in a 90% dependable year.

13.2

COST ESTIMATES AND PHASING OF EXPENDITURES

The cost of construction of the project has been estimated at June 2003 price level with a construction schedule of 7.5 years including 1.5 years for Infrastructure works during stage-II activity. The estimated Present Day Cost of the project is Rs. 3929.39 Crores without IDC at June 2003 Price level. 13.3 PHASING OF EXPENDITURE

The phasing of expenditure has been worked out on the basis of anticipated construction programme. 148

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

The phasing of expenditure without IDC for the present cost is shown as below. Year Estimated Cost at June 2003 P.L. (Rs. in Crores) 1st 2nd 3rd 4th 5th 6th 7th 7.5th Net Cost 157.18 314.35 353.64 510.82 589.41 864.47 707.29 432.23 3929.39

13.4

INTEREST DURING CONSTRUCTION (IDC)

Based upon above phasing of expenditure the interest during construction (IDC) have been calculated with 70:30 debt equity ratio and 10.0% interest on loan. (Table 13.1) The estimated IDC with estimated present cost is Rs 470.50 Crores

149

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

13.5

COST OF ENERGY GENERATION

The cost of energy generation has been calculated for the annual energy generation in a 90% dependable year based upon following assumptions. 1. 2. 3. 4. 5. 6. 7. Debt-equity ratio Annual interest rate on loan Return on equity Annual interest rate on working capital O&M Charges Free power to Home State Depreciation considered 70 : 30 10.0% 16% 10.0% 1.5% of Project Cost 12% of the energy available after losses 1/12th of loan amount during loan repayment period. The levellised tariff of the Project at present day cost works out to be Rs. 1.97 Per Unit (Table 13.3) with free power to Home State and Rs. 1.73 per unit (Table 13.3 A) without free power to Home state.

150

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-13.1
STATEMENT SHOWING IDC CALCULATION AT PRESENT DAY COST (JUNE 2003 LEVEL) EQUITY LOAN 30% 70% PRESENT DAY COST Civil Works INTEREST RATE PER ANNUM Present Day Cost 2 157.18 314.35 353.64 510.82 589.41 864.47 707.29 432.23 3929.39 Amount Equity 3 157.18 314.35 353.64 494.80 Crs. Crs. Electrical Works 743.81 Crs. 10% Transmission cost 117.00 Crs. (Rs. in Crs.) Receivable I.D.C Loan Outstanding Amount Receivable Loan at the end of Equity Loan year (for the year) 4 5 6 7 8 157.18 314.35 353.64 494.80 3929.39 3068.58

Year % For Works Civil 1 1 2 3 4 5 6 7 7.5 Total 4.00% 8.00% 9.00% 13.00% 15.00% 22.00% 18.00% 11.00% 1.00 122.74 245.49 276.17 398.92 460.29 675.09 552.35 337.54 3068.58

Works Electrical Transmission Hard Cost 29.75 59.50 66.94 96.70 111.57 163.64 133.89 81.82 743.81 4.68 9.36 10.53 15.21 17.55 25.74 21.06 12.87 117.00

16.03 589.41 864.47 707.29 432.23

0.03 31.08 106.88 196.15 136.37

16.05 636.53 1607.88 2511.32 3079.92

16.05 620.48 971.34 903.44 568.60 3079.92 Crs. Crs.

1319.97

2609.42 470.50 Crs. Crs. Equity Loan

1319.97 1319.97 3079.92

IDC 470.50 Net cost of the project 4399.89

151

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-13.2 UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL (June 2003 P.L.)
(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital) 1 Installed capacity 2 Cost of the Project (Net) 3 Interest During Construction 4 Total Cost of Project (Including IDC) a) Equity b) Loan 5 Annual Energy Generation 6 0.7% As Auxiliary Consumption of No. 5 7 Energy Available After Auxiliary Consumption 8 0.5% As Transformer Loss of No. 7 9 Energy Available After Transformer Loss 10 Free Power to Home State 11 Energy Available After Allowing Free Power 12 A) a) b) Fixed and Running Charges Capacity Charges Interest on Loan Depreciation Charges (Limited to 1/12 th of Loan Amount) 12% 0.50% 0.70% 30% 70% Rs. Rs. Rs. Rs. Rs. 1000 MW 3929.39 Crores 470.50 Crores 4399.89 Crores 1319.97 Crores 3079.92 Crores 3995.25 MU 27.97 MU 3967.28 MU 19.84 MU 3947.45 MU 473.69 MU 3473.75 MU

10.00%

295.16 Crores 256.66 Crores 551.82 Crores 66.00 Crores 211.19 Crores 277.19 Crores 14.61 Crores

SUB-TOTAL B) Energy Charges a) O&M Charges b) Return on Equity 1.50% 16.00% SUB-TOTAL 10.00% 5.50 140.60 Rs.

c) Interest on Working Capital I) O&M Charges for 1 month II) 2 Months Average Billing TOTAL 13 Sale Price at Bus Bar/Unit 14 Cost of Generation at Bus Bar/Unit (Without Allowing Free Power to Home State and Return on Equity) Note : This unit rate is excluding water cess, income tax incentive, penalties etc.

843.62 Crores 2.43 Rs. 1.60 Rs.

152

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-13.2 A UNIT COST OF ENERGY AT BUS BAR AT CURRENT PRICE LEVEL (June 2003 P.L.) WITHOUT FREE POWER TO HOME STATE
(Based on 16% return on equity & 10% interest on loan, 10% interest on working capital) 1 Installed capacity 2 Cost of the Project (Net) 3 Interest During Construction 4 Total Cost of Project (Including IDC) a) Equity b) Loan 5 Annual Energy Generation 6 0.7% As Auxiliary Consumption of No. 5 7 Energy Available After Auxiliary Consumption 8 0.5% As Transformer Loss of No. 7 9 Energy Available After Transformer Loss 10 Free Power to Home State 11 Energy Available After Allowing Free Power 12 Fixed and Running Charges A) Capacity Charges a) Interest on Loan b) Depreciation Charges (Limited to 1/12 th of Loan Amount) SUB-TOTAL B) Energy Charges a) O&M Charges b) Return on Equity 1.50% 16.00% SUB-TOTAL c) Interest on Working Capital I) O&M Charges for 1 month II) 2 Months Average Billing TOTAL 13 Sale Price at Bus Bar/Unit 14 Cost of Generation at Bus Bar/Unit (Without Allowing Free Power to Home State and Return on Equity) Note : This unit rate is excluding water cess, income tax incentive, penalties etc. Rs. 10.00% 5.50 140.60 843.62 Crores 2.14 Rs. 1.60 Rs. 66.00 Crores 211.19 Crores 277.19 Crores 14.61 Crores 551.82 Crores 10.00% 295.16 Crores 256.66 Crores 0% 0.50% 0.70% 30% 70% Rs. Rs. 1319.97 Crores 3079.92 Crores 3995.25 MU 27.97 MU 3967.28 MU 19.84 MU 3947.45 MU 0.00 MU 3947.45 MU Rs. Rs. Rs. 1000 MW 3929.39 Crores 470.50 Crores 4399.89 Crores

153

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-13.3 NABA H. E. PROJECT, ARUNACHAL PRADESH, (4 X 250 MW) CALCULATION OF ENERGY RATE WITH PRESENT COST (JUNE 2003 PRICE LEVEL) AS PER TARIFF NOTIFICATION
Annual Generation in a 90% dependable year Annual Generation after allowing losses & free power to home state in a 90% dependable year Total cost including IDC Equity Loan 30% 70% 3995.25 MU 3473.75 4399.89 1319.97 3079.92 MU Crores Crores Crores O&M Charges Rate of increase of O&M Charges after 1st Year (Compounded) Interest rate on Loan Interest rate on Working Capital Return on Equity Discounting rate CHARGES PER UNIT (Rs. per Unit) Total Interest Capacity charges Energy charges Total 1.50% 6% 10.0% 10.00% 16% 12%

Rs. Rs. Rs.

YEAR Outstanding Loan (Rs.in Cr.) 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 2 3079.92 2823.26 2566.60 2309.94 2053.28 1796.62 1539.96 1283.30 1026.64 769.98 513.32 256.66 0.00

CAPACITY CHARGES (Rs.in Cr.) Interest on loan Depreciation Total Return on equity O&M Charges (Rs.in Cr.) Interest on Working Capital O&M 2 months for 1 Average month Billing 8 9 5.50 5.83 6.18 6.55 6.94 7.36 7.80 8.27 8.77 9.29 9.85 10.44 11.07 11.73 12.43 13.18 13.97 14.81 15.70 16.64 17.64 18.70 19.82 21.01 22.27 23.60 25.02 26.52 28.11 29.80 31.59 33.48 35.49 37.62 39.88 140.60 136.93 133.30 129.71 126.16 122.67 119.22 115.83 112.50 109.23 106.02 102.88 64.98 66.34 67.78 69.31 70.93 72.65 74.48 76.41 78.45 80.63 82.93 85.36 87.95 90.69 93.59 96.67 99.94 103.40 107.06 110.95 115.07 119.44 124.07

Discounting Discounted Factor Tariff (Paisa per Unit)

3 295.16 269.49 243.83 218.16 192.50 166.83 141.16 115.50 89.83 64.17 38.50 12.83 0.00 0.00

4 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26

5 551.82 526.15 500.49 474.82 449.16 423.49 397.82 372.16 346.49 320.83 295.16 269.49 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26

6 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19

7 66.00 69.96 74.16 78.61 83.32 88.32 93.62 99.24 105.19 111.50 118.19 125.28 132.80 140.77 149.22 158.17 167.66 177.72 188.38 199.68 211.67 224.37 237.83 252.10 267.22 283.26 300.25 318.27 337.36 357.60 379.06 401.80 425.91 451.47 478.56

10 14.61 14.28 13.95 13.63 13.31 13.00 12.70 12.41 12.13 11.85 11.59 11.33 7.60 7.81 8.02 8.25 8.49 8.75 9.02 9.30 9.61 9.93 10.27 10.64 11.02 11.43 11.86 12.32 12.81 13.32 13.87 14.44 15.06 15.71 16.39

11 291.80 295.43 299.30 303.43 307.83 312.52 317.52 322.84 328.51 334.55 340.97 347.81 351.60 359.77 368.43 377.61 387.34 397.66 408.59 420.18 432.47 445.49 459.30 473.93 489.44 505.88 523.31 541.78 561.36 582.12 604.12 627.44 652.16 678.37 706.15

12 1.59 1.51 1.44 1.37 1.29 1.22 1.15 1.07 1.00 0.92 0.85 0.78 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11

13 0.84 0.85 0.86 0.87 0.89 0.90 0.91 0.93 0.95 0.96 0.98 1.00 1.01 1.04 1.06 1.09 1.12 1.14 1.18 1.21 1.24 1.28 1.32 1.36 1.41 1.46 1.51 1.56 1.62 1.68 1.74 1.81 1.88 1.95 2.03 TOTAL

14 2.43 2.37 2.30 2.24 2.18 2.12 2.06 2.00 1.94 1.89 1.83 1.78 1.12 1.15 1.17 1.20 1.23 1.25 1.29 1.32 1.36 1.39 1.43 1.47 1.52 1.57 1.62 1.67 1.73 1.79 1.85 1.92 1.99 2.06 2.14

15 1.0000 0.8929 0.7972 0.7118 0.6355 0.5674 0.5066 0.4523 0.4039 0.3606 0.3220 0.2875 0.2567 0.2292 0.2046 0.1827 0.1631 0.1456 0.1300 0.1161 0.1037 0.0926 0.0826 0.0738 0.0659 0.0588 0.0525 0.0469 0.0419 0.0374 0.0334 0.0298 0.0266 0.0238 0.0212 9.1566 (A) Levellised Tariff =(B)/(A)

16 2.43 2.11 1.84 1.59 1.38 1.20 1.04 0.91 0.78 0.68 0.59 0.51 0.29 0.26 0.24 0.22 0.20 0.18 0.17 0.15 0.14 0.13 0.12 0.11 0.10 0.09 0.08 0.08 0.07 0.07 0.06 0.06 0.05 0.05 0.05 18.04 (B)

Note:

The charges per unit is exclusive of water cess, spares, incentive & Income Tax etc.

1.97

155

Preliminary Feasibility Report Naba HE Project (4 x 250 MW)

TABLE-13.3 A NABA H. E. PROJECT, ARUNACHAL PRADESH, (4 X 250 MW) CALCULATION OF ENERGY RATE WITH PRESENT COST (JUNE 2003 PRICE LEVEL) AS PER TARIFF NOTIFICATION WITHOUT FREE POWER TO HOME STATE
Annual Generation in a 90% dependable year Annual Generation after allowing losses in a 90% dependable year Total cost including IDC Equity Loan 3995.25 MU 3947.45 4399.89 1319.97 3079.92 MU Crores Crores Crores O&M Charges Rate of increase of O&M Charges after 1st Year (Compounded) Interest rate on Loan Interest rate on Working Capital Return on Equity Discounting rate CHARGES PER UNIT (Rs. per Unit) Energy charges 1.50% 6% 10.0% 10.00% 16% 12%

30% 70%

Rs. Rs. Rs.

YEAR Outstanding Loan (Rs.in Cr.) 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 2 3079.92 2823.26 2566.60 2309.94 2053.28 1796.62 1539.96 1283.30 1026.64 769.98 513.32 256.66 0.00

CAPACITY CHARGES (Rs.in Cr.) Depreciation (Rs.in Cr.) Interest on Working Capital O&M for 1 month 8 5.50 5.83 6.18 6.55 6.94 7.36 7.80 8.27 8.77 9.29 9.85 10.44 11.07 11.73 12.43 13.18 13.97 14.81 15.70 16.64 17.64 18.70 19.82 21.01 22.27 23.60 25.02 26.52 28.11 29.80 31.59 33.48 35.49 37.62 39.88 2 months Average Billing 9 140.60 136.93 133.30 129.71 126.16 122.67 119.22 115.83 112.50 109.23 106.02 102.88 64.98 66.34 67.78 69.31 70.93 72.65 74.48 76.41 78.45 80.63 82.93 85.36 87.95 90.69 93.59 96.67 99.94 103.40 107.06 110.95 115.07 119.44 124.07 Interest

Discounting Factor Total

Discounted Tariff (Paisa per Unit)

Interest on loan

Total

Return on equity

O&M Charges

Total

Capacity charges

3 295.16 269.49 243.83 218.16 192.50 166.83 141.16 115.50 89.83 64.17 38.50 12.83 0.00 0.00

4 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 256.66 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26

5 551.82 526.15 500.49 474.82 449.16 423.49 397.82 372.16 346.49 320.83 295.16 269.49 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26 38.26

6 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19 211.19

7 66.00 69.96 74.16 78.61 83.32 88.32 93.62 99.24 105.19 111.50 118.19 125.28 132.80 140.77 149.22 158.17 167.66 177.72 188.38 199.68 211.67 224.37 237.83 252.10 267.22 283.26 300.25 318.27 337.36 357.60 379.06 401.80 425.91 451.47 478.56

10 14.61 14.28 13.95 13.63 13.31 13.00 12.70 12.41 12.13 11.85 11.59 11.33 7.60 7.81 8.02 8.25 8.49 8.75 9.02 9.30 9.61 9.93 10.27 10.64 11.02 11.43 11.86 12.32 12.81 13.32 13.87 14.44 15.06 15.71 16.39

11 291.80 295.43 299.30 303.43 307.83 312.52 317.52 322.84 328.51 334.55 340.97 347.81 351.60 359.77 368.43 377.61 387.34 397.66 408.59 420.18 432.47 445.49 459.30 473.93 489.44 505.88 523.31 541.78 561.36 582.12 604.12 627.44 652.16 678.37 706.15

12 1.40 1.33 1.27 1.20 1.14 1.07 1.01 0.94 0.88 0.81 0.75 0.68 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10

13 0.74 0.75 0.76 0.77 0.78 0.79 0.80 0.82 0.83 0.85 0.86 0.88 0.89 0.91 0.93 0.96 0.98 1.01 1.04 1.06 1.10 1.13 1.16 1.20 1.24 1.28 1.33 1.37 1.42 1.47 1.53 1.59 1.65 1.72 1.79 TOTAL

14 2.14 2.08 2.03 1.97 1.92 1.86 1.81 1.76 1.71 1.66 1.61 1.56 0.99 1.01 1.03 1.05 1.08 1.10 1.13 1.16 1.19 1.23 1.26 1.30 1.34 1.38 1.42 1.47 1.52 1.57 1.63 1.69 1.75 1.82 1.89

15 1.0000 0.8929 0.7972 0.7118 0.6355 0.5674 0.5066 0.4523 0.4039 0.3606 0.3220 0.2875 0.2567 0.2292 0.2046 0.1827 0.1631 0.1456 0.1300 0.1161 0.1037 0.0926 0.0826 0.0738 0.0659 0.0588 0.0525 0.0469 0.0419 0.0374 0.0334 0.0298 0.0266 0.0238 0.0212 9.1566 (A) Levellised Tariff =(B)/(A)

16 2.14 1.86 1.62 1.40 1.22 1.06 0.92 0.80 0.69 0.60 0.52 0.45 0.25 0.23 0.21 0.19 0.18 0.16 0.15 0.13 0.12 0.11 0.10 0.10 0.09 0.08 0.07 0.07 0.06 0.06 0.05 0.05 0.05 0.04 0.04 15.88 (B) 1.73

Note:

The charges per unit is exclusive of water cess, spares, incentive & Income Tax etc.

156

Annexure-1.1 1-3

SALIENT FEATURES

LOCATION State District River Dam site Nearest BG rail head Nearest airport

: : : : : :

Arunachal Pradesh Upper Subansiri Subansiri/Si Ngit Near Badok village Nagaon (Assam) Lilabari (Assam)

HYDROLOGY Catchment area Location of catchment Latitude Longitude Average annual rainfall RESERVOIR Full reservoir level (FRL) Min.Draw Down Level (MDDL) Gross storage -at FRL -at MDDL Area under submergence at FRL DIVERSION TUNNEL Number Size Shape Length Diversion capacity (assumed) U/s coffer dam D/s coffer dam

: :

14300 sq.km. 27o00 N to 28o22 N 91o45' E to 93o 34' E 2825 mm

: :

1035 m 1022 m

: : :

31.9 mcm 23.9 mcm 81.28 ha

: : : : : : :

2 10.50 m Horse shoe 700 m 2500 cumec 25 m 14 m

172

DAM Type Top elevation of dam Height of dam above deepest foundation level Length of dam at top River Bed level SPILLWAY Design flood Lower spillway Crest elevation Type Number Size of opening Upper spillway Crest elevation Type Number Size of opening Energy dissipation Length of spillway

Annexure-1.1 2-3

: : : :

Concrete 1040 m 110 m 245 m 945 m

12000 cumec 990 m Orifice 7 8.25 X 10

1025 m : Crest 2 8.0 X 10 : Ski jump with preformed plunge pool : 142 m

INTAKE Invert level Number Size of gate opening Trash rack Intake tunnel size Intake tunnel length

: : : :

1000 2 8.60 25 9.8 450/270

m X 9.8 m X 22 m m m

DESILTING CHAMBERS Number : Size : Length : Design discharge : per chamber Particle size to be removed : HEAD RACE TUNNEL Number Size Shape Length Design discharge per tunnel

6 16 x 23 300 m 100.4 cum 0.2 mm

: : : : :

2 8.7 m Horse shoe 9.75/9.80 km 251.00 cumec

173

SURGE SHAFT Number Size Height PRESSURE SHAFT Number Size Vertical height POWER HOUSE Type Installed capacity Number of units Power house size Type of turbine C.L of turbine MIV cavern size

Annexure-1.1 3-3

: : :

2 23 m 110 m

10

2 7.25 m 181 m

11

: : : : : :

Underground 1000 MW 4(250 MW each) 136mX23mX48m Vertical Shaft Francis 765.5 m

12

100 (L)x 12 (W) x 16 (H)

13

TRANSFORMER CUM DRAFT TUBE GATE CAVERN size : 100 (L)x 20 (W) x 25 (H) m Draft tube opening for : each unit 4.2m (W) X 6m(H) 2 nos

14

TAIL RACE TUNNEL Number Size Shape Length Design discharge per tunnel River Bed levelat outfall Maximum TWL(Assumed)

: : : :

2 8.7 m Horse Shoe 100 m 251.00 cumec 770 m 780 m

15

POTHEAD YARD Size

50m (W) X 100m(L)

16

POWER GENERATED Installed capacity : Annual energy generation in 90% dependable year :

1000 MW 3995.25 MU
174

Annexure 2.1
1-2

EXCERPTS FROM CEAS REASSESSMENT STUDY REPORT

Naba Hydro Electric Scheme


(Drg No: HEPR-PS-BHM-805) Immediately downstream of the power house under Niare hydro electric scheme, the reach of the river is steep and appears to permit development of another hydro electric scheme of run-of river type by constructing a diversion of a small height at a site where the river bed level is +1000m diverting the waters through a 11.5 km long channel to a power house to be located on the river where the river bed level is +800 m. The scheme would utilise a gross head of about 200 m and enable generation of 308 MW of firm power at the power house. With an optimum economic installed capacity of 1290 MW, the scheme would give benefit of 6038 GWH and 6915 GWH of annual energy respectively in 90% and 50% dependable years.

175

Annexure 2.4 3-5 Reply to the comments of HP&I Division, CEA vide letter No. 7/9/NHPC/HP&I/2004/217 dt.6.2.2004 Naba H.E Project (4 x 250 MW)

Comments
General Comments

Reply

1. It may be ensured that the Initial Initial Environmental studies have Environmental studies incorporated in been got carried out by NRSA as per the PFR are as per scope of the work scope of work and incorporated in for PFR. PFR.

2. It may be ensured that the Financial Guidelines have been followed. Parameters may be taken as per guidelines sent vide our Lr. No. 7/9/HP&I-2003/1118-1123, dated 21st October, 2003. 3. It may be ensured that the Cost Cost estimates have been prepared Estimates is prepared as per the as per the guidelines. guidelines sent vide our Lr. No. 7/9/HP&I-2003/1163-1172, 24.10.2003 4. NHPC may indicate Recommendation for further studies dated

recommendations for further studies has been incorporated in the relevant required wherever necessary in the chapter of PFR. relevant chapters of PFRs for consideration during Feasibility

Report/DPR stage. 5. It may be ensured that the Installed Installed capacity and assessment of Capacities & Assessment of power power benefits have been vetted by benefits takes into account various CEA and comments have been taken comments and advise given in this into account. regard. 185

Annexure 2.4 4-5 6. It may be ensured that the hydrology Hydrology adopted is approved by CWC. chapter submitted to

CWC. Replies to comments received are appended with PFR.

7.The

layout

planning

of

project Comments

of

CWC

on

project to

components may take into account components the view & advise of CWC. with PFR. 8. The power evacuation arrangements Comments

received.

Replies

comments received are appended

on

power

evacuation

considered in the PFR should take arrangements by CEA have been into account views and suggestions of taken into account while finalizing SP & PA Division of CEA. 9. An sent 2003. Power Potential Studies 1. A table giving the summary of studies Yearly inflows, Annual energy indicating yearly inflows, annual energy generation, load factor of operation generation, load factor of operation during monsoon & lean flow period during monsoon and lean flow period for Naba H.E Project has already may be presented in the studies. been indicated in the summary sheet (Table-7.3) of chapter-VII of PFR. 2. The utilization of 10m drop available Noted. between TRL (1045m) of upstream Niare HE project and FRL (1035m) of Naba HE project may be kept in view at the time of FR/DPR stage. Executive vide our PFR. summary has been

Summary may be Executive Lr. No. 7/9/HPI-

prepared as per general guidance prepared as per CEAs guidelines. 2003/1412-1419 dated 2nd December,

186

Annexure 2.4 190-5 3. The pondage provided in the reservoir The pondage provided in the

for peaking in terms of MW hours and reservoir for peaking in terms of MW number of hours of peaking in lean hours and number of peaking hrs is flow period may be indicated in the indicated in Table-7.4 of chapter-VII power potential studies. of PFR for inclusion in the final PFR.

4. It is presumed that the selection of unit Generator Step-Up Transformer will size of 250 MW proposed, takes into be the heaviest equipment to be account the transportation constraints transported which is around 75 T for etc. which roads in route may be required to upgrade to 70 R. This aspect required to be seen during preparation of DPR. 5. NHPC may indicate recommendations Needful done. for further studies required for preparation of FR/DPR.

187

Annexure-5.1A

SUBANSIRI BASIN PROJECTS MONTHLY RAINFALL (MM) AT TALIHA


YEAR 1968 1969 1976 1977 1978 1979 1980 1981 1982 1983 1985 1986 1997 2000 2001 2002 2003 AVG JAN 83.0 FEB 167.9 75.0 124.4 71.1 144.1 139.5 126.5 93.2 241.7 147.9 36.7 83.6 69.5 104.2 116.1 MAR 183.4 164.1 99.1 141.1 174.4 182.4 219.9 189.2 167.5 419.7 APR 169.1 348.1 181.9 450.1 458.1 272.4 241.8 127.5 34.0 247.7 MAY 353.1 221.3 215.7 357.7 318.8 155.7 251.4 569.7 36.5 582.9 JUN 258.0 417.7 357.4 437.0 333.0 69.7 488.7 49.6 521.7 157.5 280.4 358.2 270.7 417.0 315.5 JUL 530.1 347.2 504.0 344.2 342.1 471.4 287.4 724.4 110.9 263.3 146.8 305.5 475.8 373.3 AUG 346.6 333.6 341.2 319.2 161.2 339.3 268.0 130.7 113.4 74.0 269.6 498.4 376.0 363.3 281.0 118.2 400.0 486.7 335.0 294.3 126.8 161.4 245.7 46.6 123.7 SEP 113.0 488.2 211.8 310.6 422.4 315.4 65.7 265.1 OCT 128.0 41.3 220.1 165.3 108.4 145.8 68.7 26.2 NOV DEC 3.0 128.0 49.5 184.7 20.7 51.7 0.0 52.6 Annual 2335.2 2018.8 2443.7 2738.4 2607.4 2621.8 1528.0 2716.8 930.2 2013.7 554.7 223.0 1664.9 1161.6 3073.6 2553.2 1280.5 2438.8

58.9 37.3 40.8 128.4 0.5 0.0 75.1

124.2 60.0 76.6 36.8 29.6 45.6 33.3 7.3 123.2 96.8 132.9 34.0 66.7

170.0 141.0 184.0 171.6 186.2

99.8 610.0 464.6 267.1 283.7

293.4 275.8 98.6 279.8 286.5

38.2 184.5 40.8 62.5

5.0 20.0 26.6 49.3

197

Annexure-5.1B

SUBANSIRI BASIN PROJECTS MONTHLY RAINFALL(MM) AT SIYUM


YEAR 1966 1968 1969 2001 2002 AVG 92.2 40.2 44.0 83.0 281.6 193.3 316.7 232.3 391.1 297.3 495.0 573.0 JAN 11.4 69.0 FEB 122.0 90.1 37.0 MAR 200.0 187.0 193.0 APR 293.0 188.0 216.0 MAY 217.0 383.0 292.0 JUN 604.0 511.0 604.0 JUL 372.0 615.0 567.0 381.0 766.7 483.8 284.1 418.0 475.3 354.3 392.5 AUG SEP 356.0 406.0 132.0 540.7 333.5 358.7 319.0 4.0 244.2 95.5 189.1 OCT NOV 129.4 80.0 88.0 93.4 15.0 97.7 20.0 28.3 20.0 DEC TOTAL 2304.8 3132.2 2551.0 1754.6 3213.9 2960.9

198

Annexure-5.1C

SUBANSIRI BASIN PROJECTS MONTHLY RAINFALL(MM) AT LEMEKING


YEAR 1966 1968 1969 1977 1978 1979 1980 2001 2002 AVG 33.9 111.8 37.9 79.0 120.7 174.5 64.8 199.9 306.6 384.0 537.2 488.5 444.0 384.8 186.5 44.6 40.2 19.1 296.9 183.9 55.7 140.2 123.0 33.8 227.2 416.0 111.4 325.3 464.2 381.6 540.2 588.6 25.0 69.0 48.2 149.0 100.0 JAN FEB MAR APR 169.6 98.0 166.1 MAY 209.0 332.0 330.0 JUN 516.6 448.1 503.1 55.7 548.6 733.0 955.3 JUL 558.6 449.0 502.0 519.8 461.4 511.6 663.8 241.4 399.0 394.5 458.0 206.0 599.2 548.1 503.0 AUG SEP 385.2 362.0 331.0 334.1 456.3 525.0 339.0 345.7 134.3 139.0 380.6 153.2 177.8 67.7 64.0 18.2 28.6 21.8 58.6 134.0 OCT NOV DEC TOTAL 1839.0 2465.1 2374.9 1501.9 2502.4 4401.8 4453.3 1296.5 563.9 3074.8

199

Annexure-5.2 1-2

NABA H.E. PROJECT


SYNTHETIC AVERAGE 10-DAILY DISCHARGE SERIES AT DAM SITE YEAR 1 I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III JAN 62.27 69.30 72.64 79.41 63.19 65.15 67.25 73.85 66.03 79.56 76.44 69.50 64.29 51.19 48.25 67.06 70.22 70.64 49.36 58.96 65.39 88.00 82.35 89.01 76.81 61.31 57.74 48.83 45.78 48.06 44.26 43.42 45.19 FEB 77.70 86.56 94.66 71.49 80.50 76.36 68.03 77.52 68.44 69.10 66.96 72.54 53.86 48.92 67.09 84.21 86.56 91.07 72.42 67.26 63.42 97.94 73.05 75.89 51.56 47.82 49.87 58.79 74.38 71.78 60.23 47.19 74.16 MAR 103.74 127.08 112.97 69.40 78.08 70.30 91.82 110.31 127.97 82.62 110.15 140.29 63.97 65.55 72.82 116.12 111.40 91.15 79.84 72.98 69.64 98.12 91.07 115.58 90.76 94.83 83.05 118.75 93.66 95.26 79.75 113.79 105.64 APR 154.88 137.90 234.85 119.23 153.77 185.89 183.68 147.33 178.66 155.21 220.42 290.40 131.60 156.75 168.01 164.14 158.04 138.39 111.34 143.21 177.42 163.44 170.47 127.46 99.26 174.00 187.05 117.89 140.46 142.86 110.33 110.57 136.03 MAY 227.50 152.89 342.27 230.70 369.27 286.98 182.08 232.13 172.97 338.28 395.89 224.67 232.10 286.59 515.91 181.69 255.30 163.83 298.87 274.41 312.55 286.66 438.58 639.71 210.44 149.48 238.70 185.25 136.99 158.93 286.87 347.21 328.87 JUN 473.20 822.96 1253.22 544.26 696.51 838.89 262.06 417.37 438.41 257.52 484.89 640.21 457.95 716.76 810.76 200.89 219.73 272.32 284.09 333.25 476.21 1082.09 1352.80 1212.87 194.58 185.40 298.91 137.52 286.05 354.15 245.60 278.47 259.09 JUL 617.04 968.49 840.70 718.20 722.85 586.24 514.41 504.10 401.03 769.17 1249.70 948.06 1043.47 935.96 748.44 517.27 414.16 647.65 557.65 803.37 986.33 1415.85 1562.41 1967.92 855.52 667.11 956.15 583.45 449.94 716.32 396.90 685.21 500.66 AUG 950.67 927.75 599.93 479.94 525.63 604.15 451.37 470.13 865.87 750.16 594.08 487.21 691.73 606.86 736.37 669.63 743.72 680.57 316.77 404.56 373.81 620.06 699.85 766.92 819.52 1047.00 775.26 377.34 578.96 516.35 510.88 558.89 922.27 SEP 552.02 696.42 420.30 352.94 593.02 515.14 1366.81 1232.28 944.42 350.68 310.28 404.68 458.03 382.90 428.09 532.00 410.61 333.48 287.79 351.05 404.86 640.25 458.10 638.45 581.13 523.68 566.09 369.22 688.33 864.90 871.13 953.79 763.57 OCT 242.35 427.50 233.52 259.57 248.96 226.98 565.71 388.61 281.22 280.00 393.47 217.09 602.35 600.51 292.18 540.63 489.84 253.23 367.40 193.20 155.36 514.72 555.14 252.18 626.73 267.92 279.31 485.69 258.69 151.47 639.36 242.57 227.81 NOV 148.73 108.01 116.62 214.92 182.19 105.17 171.08 103.34 115.27 123.87 101.25 93.63 147.04 117.24 100.43 196.47 114.21 98.97 141.81 155.35 140.62 250.10 214.11 141.01 156.84 164.06 102.32 111.54 130.34 92.11 164.52 141.04 127.92 DEC 76.90 77.39 73.13 97.89 77.98 63.80 116.47 98.36 84.02 75.79 82.47 80.55 103.93 75.84 79.33 77.94 79.80 65.95 136.16 92.92 76.71 89.27 94.47 84.52 70.77 73.55 61.02 79.16 64.41 57.86 86.50 101.32 89.46 AVG 352.33

295.97

323.35

307.97

337.86

261.36

248.79

479.18

304.04

10

246.99

11

297.24

200

Annexure-5.2 2-2

NABA H.E. PROJECT


SYNTHETIC AVERAGE 10-DAILY DISCHARGE SERIES AT DAM SITE YEAR 12 I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III JAN 103.02 103.75 98.10 50.91 51.29 56.85 61.43 50.23 47.70 105.92 95.75 91.03 59.15 64.94 71.35 55.96 44.40 49.42 69.69 70.99 67.31 72.25 72.75 67.52 63.24 51.96 49.52 68.43 65.10 64.82 FEB 88.86 89.79 82.42 68.11 50.72 75.56 63.32 49.79 63.13 119.10 74.76 89.60 95.09 92.73 100.07 63.21 70.00 70.20 77.15 55.55 82.30 90.45 98.04 103.61 46.30 46.20 59.08 73.85 69.21 76.56 MAR 94.96 85.22 97.84 97.00 125.87 126.68 94.71 128.71 110.36 105.67 116.23 101.02 112.31 88.20 85.97 75.89 84.41 120.47 112.50 93.21 81.20 92.49 122.47 155.05 56.58 66.77 74.55 91.85 99.00 101.89 APR 153.10 176.53 176.08 155.49 150.03 166.93 145.48 194.49 165.82 107.99 105.10 101.62 157.00 130.25 200.03 217.32 183.01 235.94 121.02 115.07 170.80 190.30 261.47 189.07 98.34 101.57 146.41 142.85 156.52 175.99 MAY 310.45 266.78 149.73 192.99 185.23 379.33 209.07 207.52 203.57 235.15 201.89 123.95 243.05 181.02 244.89 242.65 189.92 144.84 181.94 133.88 109.48 301.35 398.34 295.99 190.73 190.78 245.82 238.39 249.70 264.15 JUN 329.74 401.06 573.02 314.48 296.49 534.51 481.44 821.62 1098.73 149.69 280.37 427.40 606.35 421.86 425.49 140.34 179.87 268.54 128.73 168.78 325.11 586.97 898.82 911.10 303.75 560.35 560.74 359.06 491.17 598.98 JUL 679.86 542.47 888.69 470.20 737.61 583.48 684.26 808.14 989.15 936.77 876.77 769.48 370.18 307.27 342.95 304.33 589.13 733.00 382.05 726.77 654.06 1073.07 1300.06 1711.51 815.32 1111.79 1404.31 685.25 798.17 868.81 AUG 412.65 560.56 991.57 917.66 1198.11 763.10 703.88 746.43 705.87 769.21 692.83 606.52 539.45 828.63 904.31 810.29 1075.70 1285.73 449.94 415.96 420.94 539.75 603.60 970.80 595.63 735.07 568.82 618.83 700.72 727.32 SEP 749.15 791.70 583.79 389.15 363.88 290.14 637.23 463.66 425.77 331.81 365.97 352.08 669.19 523.47 692.47 1071.86 758.31 828.77 428.65 395.60 310.97 694.68 564.10 379.13 582.56 703.19 389.94 595.81 576.52 526.85 OCT 338.36 376.68 190.67 548.16 238.15 197.34 521.61 265.57 155.87 288.65 216.22 190.30 412.18 252.83 179.12 376.64 410.92 322.89 439.27 439.83 262.46 333.62 334.37 305.91 244.48 261.28 165.59 431.38 343.11 227.03 NOV 115.94 109.91 90.08 159.39 151.44 111.80 163.12 139.61 100.30 209.29 172.21 119.16 184.11 165.56 125.61 192.53 115.82 79.72 156.94 99.05 85.66 153.09 92.28 91.25 119.02 75.19 83.35 164.02 132.61 106.05 DEC 98.76 75.63 67.30 75.54 78.31 76.08 104.68 116.82 101.42 129.02 91.60 77.36 85.76 69.93 72.21 80.48 67.75 69.77 102.25 90.82 85.22 111.50 79.98 69.07 72.73 64.99 62.60 93.57 82.72 74.87 AVG 306.78

13

289.67

14

334.18

15

272.99

16

280.69

17

322.50

18

225.31

19

397.66

20

304.68

AVG

309.48

Note : All Discharges are in cumec.

201

Annexure-5.3 5-10

REPLY OF CWC COMMENTS ON HYDROLOGY CHAPTER OF NABA H.E.PROJECT RECEIVED VIDE LETTER NO. 7/9/NHPC/2003/HPI/188 dt. 0302-2004 SL.NO.
1

HEADING
Consistency of data

CWC COMMENTS
1. Since NHPC is observing discharge data at Menga site since June 2000, a comparative study may be made between the observed series and generated series at Menga site and the results may be incorporated in the PFR. 2. Efforts may be made to collect site specific discharge data and catchment rainfall and series may be generated. 3. As the catchment of Naba dam is approximate, the flow series obtained by area proportion basis will be more approximate. 1. A synthetic flow series reportedly developed for Subansiri upper dam site has been transferred to the Naba site by applying catchment correction factor of 0.504. The methodology adopted and the analysis done for such generation is not available in the report. These may be furnished. 2. Since NHPC is observing the discharge at Menga site since 2000, a series may be generated based on this data and the same may be compared with the synthetically generated series and a comparison

NHPC REPLY
1. A plot between average 10-daily discharge based on observed and generated series is enclosed. Average 10daily observed discharge seems to be slightly on higher side in monsoon months, however, comparing 20 years average with 3-years average is not logical. 2. Agreed, the efforts shall be continued.

3. Agreed, however, with the available information and data the study has been done. 1.Kindly refer water availability study of Hydrology Chapter of Feasibility report of Subansiri Upper Project, submitted in August 2002..

Water availability studies

2. A plot between average 10-daily discharge based on observed and generated series is enclosed, also replied in S.No.1

206

Annexure-5.3 6-10
may be made and the results may be incorporated in the report. The 20 years synthetic flow series obtained for Subansiri upper dam site may also be incorporated in the report to facilitate the checking of the transferred series of Naba. The design flood studies done by NHPC are too empirical to be relied upon. Four to five years concurrent rainfall runoff data base can be utilised to calculate design flood by unit hydrograph approach. However, in the absence of short interval concurrent rainfall runoff data the design flood may be calculated using relevant sub zonal report of CWC taking in to account the recommendations of 1993 workshop and by collecting PMP/SPS values from IMD. The results may be compared before recommending the design flood. The sedimentation rate for the region is about 0.1765 Ham/sqkm/year as per CWC studies published in the compendium on silting of reservoirs in India which is higher than the rate proposed for the project. As stated in the report more detail study is required. Data may also be collected from the completed projects on the basin/nearby basin. New zero elevation after

3.

3. Attached.

Design flood

a)

b)

c)

It is worth mentioning here that although deterministic approach of design flood computation has not been used directly in the present study for Naba sub basin, however, this approach has been used indirectly along with Emperical method, as the design flood at Subansiri Upper dam site had been computed by deterministic approach only. The details of design flood study may be referred in feasibility report of Subansiri Upper Project, August 2002.

d)

Sedimentation

1.

2.

We are aware of the findings of CWC studies published in the Compendium on silting of reservoirs in India. As per that report, the sediment rate varies from 0.05658 to 0.2785 Ham/Sq.km/year for Indus, Ganga and Brahmaputra basin. But the silt rate adopted for this particular project has been adopted on the basis of observed data at Chouldhowaghat in Subansiri basin and is more region specific than that given in Compendium on silting of

207

Annexure-5.3 7-10
70 years may be evaluated. 3. Revised area-elevationcapacity table after 25 years may be incorporated. As per the terms of preparation of PFRs and emphasised in the meetings conducted by CEA sedimentation studies are required to be carried out and incorporated in the PFRs. 5 General The PFR must bring out the various limitations of the hydrological studies carried out for the PFR and suggest improvements, specific recommendation for opening new hydrological and hydrometeorological stations, method of observations, data to be collected etc. may be given which will help as guidance to the agency undertaking detailed investigation. The agency taking up the detail investigations/DPR must review the network in consultation with HSO, CWC. The hydrological studies for the PFR may be revised incorporating the above observations. reservoirs in India.

Detailed reservoir sedimentation study need be done during feasibility stage with more observed data at the proposed site using a suitable method.

The PFR points out the limitation of the studies after each study and establishment of G&D site, rainfall stations etc. are also highlighted in the PFR, however, as suggested during different meetings held at CWC, the specific recommendations has been incorporated at the end of the chapter.

208

Annexure-5.3 8-10

SUBANSIRI UPPER PROJECT COMPARISON OF AVG 10 DAILY DISCHARGES AT MENGA


2200 2100 2000 1900 1800 1700 1600 1500 1400 1300 1200 1100 1000 900 800 700 600 500 400 300 200 100 0

AVERAGE OF OBSERVED SERIES (2001-2003) AVERAGE OF GENERATED SERIES

Discharge (Cumec)

JA N JA I N JA II N III FE B FE I B FE II B II M I AR M I AR M II AR III AP R AP I R AP II R II M I AY M I AY M II AY III JU N JU I N JU II N I JU II LY JU I LY JU II LY II AU I G AU I G AU II G I SE II PT SE I PT SE II PT II O I C T O I C T O II C T II N I O V N I O V N II O V II D I EC D I EC D II EC III

Month

209

Annexure-5.3 9-10

SUBANSIRI UPPER H.E. PROJECT


SYNTHETIC 10-DAILY FLOW SERIES AT MENGA (NHPC) YEAR 1 I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III JAN 123.66 137.62 144.25 157.69 125.49 129.38 133.55 146.66 131.13 158.00 151.80 138.01 127.68 101.66 95.81 133.17 139.44 140.28 98.02 117.08 129.85 174.75 163.54 176.76 152.54 121.76 114.66 96.98 90.92 95.44 FEB 154.30 171.89 187.98 141.97 159.86 151.64 135.09 153.94 135.92 137.23 132.98 144.06 106.96 97.14 133.23 167.23 171.90 180.86 143.82 133.57 125.95 194.50 145.07 150.71 102.39 94.96 99.03 116.74 147.71 142.54 MAR 206.02 252.37 224.34 137.83 155.05 139.60 182.34 219.07 254.14 164.07 218.75 278.59 127.04 130.18 144.61 230.61 221.23 181.02 158.56 144.93 138.29 194.86 180.85 229.53 180.23 188.32 164.93 235.82 186.00 189.17 APR 307.57 273.85 466.39 236.77 305.37 369.15 364.76 292.58 354.79 308.23 437.73 576.70 261.34 311.29 333.65 325.96 313.84 274.83 221.11 284.39 352.33 324.57 338.53 253.12 197.11 345.55 371.45 234.11 278.93 283.71 MAY 451.79 303.63 679.70 458.14 733.33 569.91 361.59 460.99 343.50 671.79 786.19 446.16 460.92 569.13 1024.53 360.82 507.00 325.35 593.53 544.95 620.69 569.28 870.97 1270.38 417.90 296.84 474.02 367.88 272.04 315.61 JUN 939.71 1634.30 2488.75 1080.84 1383.18 1665.93 520.42 828.84 870.63 511.40 962.93 1271.38 909.43 1423.40 1610.08 398.94 436.35 540.80 564.16 661.80 945.70 2148.90 2686.49 2408.62 386.42 368.19 593.60 273.10 568.06 703.30 JUL 1225.37 1923.30 1669.53 1426.26 1435.49 1164.20 1021.56 1001.09 796.39 1527.47 2481.76 1882.74 2072.20 1858.70 1486.31 1027.24 822.48 1286.16 1107.43 1595.40 1958.74 2811.71 3102.75 3908.05 1698.96 1324.80 1898.80 1158.67 893.53 1422.52 AUG 1887.91 1842.40 1191.39 953.11 1043.84 1199.76 896.36 933.62 1719.52 1489.72 1179.78 967.55 1373.69 1205.15 1462.35 1329.81 1476.93 1351.53 629.07 803.41 742.34 1231.36 1389.81 1523.02 1627.47 2079.22 1539.58 749.35 1149.74 1025.41 SEP 1096.25 1383.00 834.66 700.89 1177.66 1023.01 2714.33 2447.16 1875.50 696.41 616.18 803.65 909.59 760.40 850.13 1056.48 815.43 662.26 571.51 697.14 804.00 1271.46 909.74 1267.89 1154.06 1039.96 1124.19 733.23 1366.95 1717.59 OCT 481.27 848.96 463.75 515.48 494.41 450.75 1123.44 771.73 558.47 556.04 781.38 431.11 1196.20 1192.55 580.24 1073.63 972.77 502.89 729.61 383.68 308.52 1022.18 1102.44 500.80 1244.62 532.05 554.68 964.53 513.73 300.81 NOV 295.36 214.49 231.60 426.81 361.80 208.86 339.75 205.22 228.92 245.99 201.08 185.94 292.01 232.82 199.44 390.16 226.81 196.54 281.62 308.50 279.26 496.67 425.20 280.03 311.46 325.81 203.20 221.50 258.84 182.91 DEC 152.72 153.68 145.23 194.40 154.85 126.69 231.30 195.34 166.86 150.51 163.78 159.96 206.39 150.61 157.54 154.77 158.47 130.97 270.40 184.53 152.33 177.27 187.60 167.84 140.54 146.07 121.18 157.20 127.91 114.91 AVG 699.69

587.76

642.13

611.58

670.96

519.03

494.06

951.59

603.79

10

490.48

210

Annexure-5.3 10-10

11

12

13

14

15

16

17

18

19

20

AVG

I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III I II III

87.90 86.23 89.75 204.59 206.03 194.82 101.10 101.86 112.90 121.99 99.76 94.73 210.35 190.14 180.77 117.47 128.96 141.70 111.12 88.18 98.15 138.40 140.98 133.66 143.47 144.48 134.09 125.59 103.18 98.34 135.90 129.29 128.72

119.60 93.71 147.28 176.47 178.32 163.67 135.26 100.72 150.05 125.75 98.88 125.37 236.51 148.47 177.94 188.83 184.16 198.72 125.52 139.01 139.40 153.22 110.31 163.43 179.63 194.69 205.76 91.95 91.74 117.33 146.65 137.45 152.04

158.37 225.98 209.78 188.58 169.24 194.30 192.63 249.97 251.57 188.09 255.61 219.17 209.85 230.81 200.61 223.04 175.15 170.73 150.71 167.62 239.24 223.41 185.10 161.26 183.68 243.21 307.92 112.37 132.59 148.04 182.41 196.60 202.34

219.11 219.58 270.14 304.04 350.57 349.68 308.78 297.95 331.50 288.91 386.24 329.30 214.46 208.72 201.81 311.78 258.66 397.23 431.57 363.44 468.54 240.33 228.51 339.18 377.92 519.25 375.48 195.30 201.71 290.76 283.69 310.83 349.49

569.68 689.52 653.10 616.52 529.79 297.35 383.25 367.85 753.30 415.18 412.10 404.27 466.98 400.92 246.15 482.67 359.49 486.32 481.88 377.16 287.63 361.31 265.86 217.41 598.44 791.05 587.80 378.76 378.87 488.17 473.42 495.88 524.57

487.73 553.01 514.53 654.82 796.45 1137.94 624.52 588.79 1061.47 956.08 1631.64 2181.95 297.26 556.79 848.77 1204.14 837.76 844.98 278.69 357.21 533.28 255.64 335.18 645.63 1165.66 1784.94 1809.34 603.21 1112.78 1113.56 713.05 975.40 1189.51

788.20 1360.74 994.26 1350.12 1077.28 1764.83 933.77 1464.80 1158.72 1358.86 1604.87 1964.34 1860.31 1741.17 1528.09 735.13 610.21 681.05 604.36 1169.95 1455.66 758.70 1443.27 1298.88 2130.98 2581.77 3398.86 1619.12 2207.89 2788.79 1360.82 1585.06 1725.35

1014.55 1109.88 1831.52 819.48 1113.20 1969.14 1822.37 2379.30 1515.43 1397.83 1482.32 1401.77 1527.56 1375.87 1204.47 1071.28 1645.56 1795.85 1609.13 2136.21 2553.31 893.53 826.05 835.94 1071.87 1198.68 1927.90 1182.85 1459.76 1129.60 1228.92 1391.54 1444.37

1729.96 1894.12 1516.36 1487.72 1572.22 1159.34 772.81 722.63 576.18 1265.46 920.77 845.52 658.93 726.77 699.18 1328.94 1039.54 1375.16 2128.58 1505.91 1645.83 851.25 785.61 617.55 1379.56 1120.24 752.90 1156.89 1396.46 774.37 1183.22 1144.89 1046.26

1269.70 481.71 452.40 671.95 748.04 378.65 1088.59 472.93 391.90 1035.85 527.39 309.53 573.22 429.38 377.92 818.54 502.10 355.72 747.97 816.03 641.23 872.34 873.44 521.22 662.53 664.02 607.50 485.50 518.88 328.84 856.66 681.38 450.85

326.71 280.09 254.03 230.24 218.26 178.89 316.53 300.75 222.03 323.94 277.25 199.18 415.63 341.99 236.64 365.63 328.78 249.45 382.35 230.01 158.32 311.66 196.70 170.11 304.01 183.26 181.22 236.36 149.31 165.53 325.72 263.35 210.61

171.77 201.21 177.65 196.13 150.20 133.64 150.02 155.51 151.09 207.88 231.99 201.41 256.21 181.90 153.62 170.31 138.87 143.40 159.82 134.54 138.56 203.06 180.36 169.23 221.42 158.83 137.17 144.43 129.07 124.32 185.83 164.27 148.68

590.27

609.24

575.25

663.64

542.12

557.43

640.45

447.44

789.71

605.06

614.58

Note : All Discharges are in cumec.

211

Annexure 6.1 4-4 Reply to the comments of CMDD Division, Central Water Commission vide letter No.7/9/NHPC/2003/HPI/669-670 dt.01.04.2004 Naba H.E. Project (4x250MW)

Comments

Reply

1. The report should indicate alternative Various alternative locations of dam axis locations of dam axis examined during as examined during PFR preparation the preparation of PFR to bring out have been indicated/discussed in para their merits & demerits of each 6.1 of PFR. The same have also been including that finally adopted in PFR. indicated in plate 6.1. The reasons for rejecting the particular alternative should also be elucidated justifying the rejection. 2. As the rock fill coffer dam may get It may be mentioned that subsequent to damaged during monsoon flood, so a detailed colcrete coffer dam. 3. Justification for assuming coffer dam may be construction investigations material survey, including various

contemplated to avoid rebuilding of possible alternatives are examined and finalized. Accordingly type of coffer dam needs to be finalized at DPR stage. non- No G&D data is available for river the hydrological studies as carried out for Subansiri Upper HE Project value of diversion flood has been assumed ( Refer para 6.2.1). 4. It should be mentioned in the report Hydrology (NE) Dte. of CWC. codal provision. For reply to observation of Hydrology 5.3 may be referred. finalized during detailed Design. that the PMF has been vetted by (NE) Dte. CWC regarding PMF, annexure 5. Galleries should be shown as per Location and alignment of galleries are However, as desired galleries have been indicatively shown in cross section of dam (plate 6.5) 6. As per CI. 6.2.1.2.4, top width of non Dam top width is 10m as indicated in overflow block is 12.0 m, where on as drawings. Typographical error in clause per drawing it is 10 m. please justify. 6.2.1.2.4 has been corrected monsoon diversion discharge as 2500 Subansiri at proposed dam site. Based on cumec should be provided.

215

Annexure 6.2 2-2 Reply to the comments of HCD (E&NE) Division, Central Water Commission vide letter No.3/5/2000-HCD (E&NE)/866 dt. 07.04.2004 Naba H.E Project (4 x 250 MW)

Comments
1. chamber reviewed needs with the to

Reply
be chamber has been proposed in order to more provide estimate. adequate provision in cost of Requirement/provision

Provision/design of desilting In the absence of observed data, desilting

observed data.

desilting chamber needs to be reviewed based on sedimentation studies at DPR stage 2. Sizing, shape & location of As already indicated in para 6.3 of PFR, surge shaft needs to be transient analysis/studies needs to be reviewed with the more carried out during DPR stage. Based on transient studies size, type and location of surge shaft needs to be finalised. 3. Efficacy of silt flushing It is a standard practice to undertake through low level spillway on model studies to check efficacy of spillway the live storage and also at for silt removal from reservoir and from the the power intake vicinity power intake vicinity. and However, such needs to be examined. model studies are taken up after detailed topographical geotechnical investigations leading to firming up of design at DPR stage. 4. Alignment of pressure shaft It may be mentioned that subsequent to needs to be reviewed by detailed investigation in DPR stage, length providing in between of lower horizontal reach of pressure shaft needs to be optimized. horizontal alignment/reach. transient studies.

217

Annexure 7.1 5-8 Reply to the comments of SP&PA Division, CEA vide letter No. 7/9/NHPC/2003/HP&I/320 dt.13.2.2004. Naba H.E. Project (4 x 250 MW) A. Technical Comments Aspects Reply

1.Location Naba HEP, a run of river scheme is proposed It is a statement on Si Ngit (Subansiri river), (a major tributary of Brahmaputra river) in remote area of remote area of Upper Subansiri District of Arunachal Pradesh. The project is located in upper reaches of Subansiri River near Badok village immediately downstream of the power house of Niare HE Project on river Subansiri and is about 160 km upstream of Daporijo town.

2.Cost of the project The project is estimated to cost Rs 4569.93 It The levelised tariff of the project at present day is is a statement. as Rs. crores including IDC at June 2003 price level. However, project cost revised in cost works out to be Rs 2.05 per unit. However, 4399.89 crores due to levelised tariff at present day cost works without change per unit. certain any free power to state works out to be Rs 1.80 parameters of project components. Revised levelised tariff of the project at present day cost works out to be Rs. 1.97 per unit. However, levelised

tariff at present day works without any free power to home state works out to be Rs. 1.73 per unit.

222

Annexure 7.1 6-8


3.Power house Naba power house which would be an under It is a statement ground power house is located on the left bank near Naba village and about 20km. downstream of Limeking village. Limeking is about 160 km. from Daporijo town. Naba HEP envisages installation of 4 units of 250 MW each. Power is proposed to be generated at 16 kV step up generator at 16 kV and stepped upto 400kV through 13 nos., 102MVA, 16/400kV step up generator transformer as given on page 61 of the PFR. The generator step up transformers will be further connected to 400 kV Gas Insulated Switchgear (GIS) located above the transformers. This is in order.

4.Power evacuation

In order to evacuate 1000 MW of power The Transmission line from Naba HEP, a 400kV D/C transmission length line with Quad Moose conductor, 70 km in HEP point is proposed as stated on page 91 of the PFR. Accordingly, provision of 2 outgoing bays has been kept in the GIS for 1000 MW power evacuation from this
kms from to Naba Daporijo

length from NABA HEP to Daporijo pooling pooling point is 85


approximately, instead of 70 kms. Necessary correction has been made in Chapter on power

project. This is in order. The transmission evacuation (Chapterline length from Naba HEP to Daporijo VIII) and cost estimate pooling point is given as 70 Kms. On page for E&M works has 91 of the PFR while on page 18 of the PFR been revised (Page it has been stated that PH is located at 146 & 147, Chapter about 20 kms. downstream of Limeking XII). Further, it is to be village and Limeking village is about 160 kms. from Daporijo. This needs clarification.
mention that the distances from Naba PH to the Daporijo pooling point

223

Annexure 7.1 7-8


mentioned on page 18 of the draft PFR are the road distances, length of by whereas, been

transmission line has estimated, adopting toposheets. shortest

possible route, on SOI

5.Daporijo Pooling Point It has been stated on page 91 of the PFR that The other projects the power from Oju-I, Oju-II and Niare HE from where power is Projects would also be pooled at Daporijo to be pooled to pooling point. The capacity of these power Daporijo pooling point plants has not been given in the PFR. Also, the are:power from Subansiri upper HEP 2000 MW a) Oju-I (700MW) has been planned to be pooled at Daporijo b) Oju-II (1000 MW) pooling point, from where the total power from c) Naire (800MW) 5 projects would be ultimately pooled directly d) Nalo (360 MW) through HVDC link to the National Grid. e) Dangser (552 MW) f) Subansiri upper (2000MW) 6.Construction Power Source of construction power for the project has Requirements furnished. of not been stated in the PFR. This may please be construction power for this project would be met by suitable capacity D.G. Sets. 7.Cost of Transmission works a) It has been stated on page 91 of the PFR Details that the cost of 400 kV D/C transmission line transmission other end equipment at Naba pooling point has FR/DPR. been considered. The cost of transmission of works

form Naba HEP to Daporijo pooling point and will be provided in

224

Annexure 7.1 8-8


works has been given as Rs. 97.62 crores under the abstract of cost of works of AppendixI on page 116 of the PFR. Details of transmission works may be furnished.

8.General Comments a) It may be stated that the benefits from these Noted projects may not be fully absorbed from NE Region and needs to be exported to other regions. In long-term perspective for evacuating bulk power from we may need to adopt a combination of HVDC/EHVAC transmission system, which requires least transmission corridor, because of limited corridor in the chicken-neck area taking into account the various power projects likely to be developed in NER in foreseeable future. We may need to plan an integrated transmission system from the pooling points in NER and phase out the implementation schedule suitably. b) The transmission system as proposed for Noted above schemes is tentative. The final transmission system would be determined by detailed power system studies on the basis of total power to be transmitted from NER, which may require a change in the voltage levels or configuration of the transmission system taking into consideration the mountainous terrain, thick forest area and right of way problems. c) Beneficiaries States/Regions along with their It is a statement. tentative shares from these projects have not been identified so far.

B. Cost Aspects
Comments on the cost aspects shall be Appended forwarded in due course. Annexure 7.2 as

225

Annexure 7.2 4-4 Reply to the comments of SP&PA Division on Cost Aspects, CEA vide letter No. 7/9/NHPC/2003/HP&I/790 dt.15.04.2004 Naba H.E. Project (4 x 250 MW) comments Cost Aspects 1 Switchyard Cost of GIS (400) with 7 bays has been estimates at It is a statement Rs.600 lakhs/bay. XLPE cable @ 4 lakhs US $ per km for 2.8 kms of length with termination kit has been considered which on conversion (1US $=Rs 46) works out to Rs 1.84 crores/km. Over and above, custom duty @ 22%, has been considered. In addition to above, spares @ 2 %, transportation and insurance @ 3 %, erection and commissioning @ 8 %, establishment, contingency, other charges @ 8% (except duties) + 2% handling charges on custom duty has been considered. The overall estimate of Rs.6878.01 lakhs for GIS is generally in order. Transmission line 2 2 No. of 400kV bays for receiving end of the transmission It is a statement, line @ 250 lakhs/bay has been considered. Excise duty @ however, at the 16% has been considered in addition to basic cost. time of of D/C 400 kV line with Quad moose conductor for 70 km submission Reply

has been considered @ Rs 90 lakhs/km. In addition ED @ FR the detailed 16%, switchyard @ 2%, CST @ 4%, transportation and break up of the insurance @ 3%, erection and commissioning @8%, components establishment contingency and other charges @ 8% has cost been considered. The total cost of the D/C transmission line is marginally on the higher side by 10 to 15%. However, at the time of submission of FR the detailed break up of the components of cost will be required to be furnished. will furnished of be

229

Annexure 9.2 1-2 EXCERPT FROM PRELIMINARY REPORT ON FLORISTIC SURVEY IN NABA HE SCHEME

In connection with the Preliminary Feasibility Report of Hydroelectric Scheme of NHPC in four projects site in Subansiri river Basin, Upper Subansiri district, Arunachal Pradesh, a floristic exploration tour to the proposed project areas was undertaken by a team of scientists of BSI, AFS. Itanagar along with the officials of NHPC, Daporijo. The joint expedition team proceeded from Limeking on trekking and making base camp at Orak could proceed upto Tarna Chung Chung a place between second and third project sites for extensive floristic survey and overall vegetational study of the whole area. The area covering the four proposed projects from Naba to Oju-I possess a difficult terrain with rugged hills, dense forest- cover; intersected by a number of hilly streams and with a gradual altitudinal variation. The vast catchment area of the proposed projects possess mainly subtropical forests with pathches of lower temperate forests towards the area in Oju-I project site with comparatively higher altitudinal position. But the area of actual submergence covers mostly subtropical forests with a considerably diverse composition. Vegetation and the floristic components as observed in the proposed project areas are as follows.

Naba : The predominant vegetation is subtropical type and is basically of


evergreen in nature. Top storey comprises of the species of tall trees like Acer oblongum, Kydia calycina, C'astonopsis indica, Saurauia panduana, Schima wallichii... Middle storey comprises of species like Capparis multiflora, Photinia integrifolia, being associated with species like Eurya acuminata , Myrsine semiserrata. Camellia caudata, etc. The common climbers met with in the area are Clematis acuminata. Holboellia latifolia . Tinospora sinensis

246

Annexure 9.2 2-2 etc. The ground flora comprises of the bushy shrubs and herbs like Cassia mimosoides. Dianella ensifolia, Drymaria diandra .Plectranthus griffithii, Rosa Indica, Solanum erianthum etc.

No doubt the Vegetation of the area to be submerged will be adversely affected by the proposed hydel projects. The ecological pressure and microclimatic changes by submergence will inevitably threaten the floristic diversity of the area. But notably, the type of vegetation of the project site covers a vast expanse exhibiting the same type of vegetation, Moreover, the species occurring in the area to be submerged are also found in and around the vast adjoining areas.

247

Você também pode gostar