PROJECT ENGIE - Projeto Básico para Planta de H2 verde e NH3

-
-
DISCIPLINE PROCESS
SCHEDULE 3 Month

TEAM
Alocação em Horas
Document/Activities Doc.Type
Desenhista Des.-Proj. Projetista Projet. Pleno Estagiário Eng. Junior Eng.Pleno Eng. Sênior Consultor Arquiteto Total
General Overview Chart Chart 8 10 6 2 26
Process Flow Diagram PFD 8 10 6 2 2 28
Utility Flow Diagram UFD 8 10 6 2 2 28
H2 Electrolizers & Conditioning - Process and Instrumentation Diagram PID 15 20 10 5 2 52
H2 Buffer & Compression - Process and Instrumentation Diagram PID 15 20 10 5 2 52

N2 Generation & Distribution System - Process and Instrumentation Diagram PID 15 20 10 5 2 52

H2 & N2 Compression / Pipeline Integration with Ammonia Plant - Process


PID 15 20 10 5 2 52
and Instrumentation Diagram
Ammonia Plant - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Air Compression System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Water Treatment System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Cooling Water System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Effluent Treatment System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Equipment Sizing Notes CALCULATION 30 16 4 2 52
Line Sizing CALCULATION 16 8 4 28
Process Data Sheet - Equipment SPECIFICATION 16 8 4 28
Process Data Sheet - Instrument SPECIFICATION 16 8 4 28
Equipment List LIST 8 4 2 14
Process Description DESCRIPTION 40 24 16 2 82
HAZOP ACTIVITY 4 16 4 2 26
0
0
0
0
Total de Horas por Perfil 159 0 0 0 0 340 192 89 28 0 808
TOTAL DE HORAS 808
OBS

0.32 0.00 0.00 0.00 0.00 0.67 0.38 0.18 0.06 0.00 1.60
SOFTWARE
Software Nº de Licenças Período OBS
MICROSOFT OFFICE 3 MESES
AUTOCAD 3 MESES
PRO II 3 MESES

OUTRAS DESPESAS
Despesa Quant. U.M. OBS

PREMISSAS E OUTRAS OBSERVAÇÕES


1 - No projeto de estruturas metálicas não é considerado desenhos de fabricação (shopdrawing)
2 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a projeto e aprovação junto aos orgãos rodoviários/ferroviários)
3 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a avaliação da capacidade suporte do corpo receptor que receberá a drenagem pluvial advinda do projeto em questão
4 - Nas memórias de cálculos, as horas não consideram análises específicas, como por exemplo: análise de fadiga, ou qualquer outra que não seja usual. Para tais análises, as horas deverão ser avaliadas caso a caso.

Entregáveis ( distribuição de pessoas) 5.75 5.75


Des.-Proj. 1 1 1 4.5
Projet. Pleno 1 1 1 1 4
Estagiário 1 1 1 1
Eng.Pleno 1 1 1 1
Eng. Sênior 1 0.5 0.5 0.5
Consultor 0.25 0.25
Arquiteto 1 1 mês 1 mês 2 mês 3 mês 4
mês 1 mês 2 mês 3 mês 4
PROJECT ENGIE - Projeto detalhamento para Planta de H2 verde e NH3
-
-
DISCIPLINE PROCESS
SCHEDULE 12 Month

TEAM
Alocação em Horas
Document/Activities Doc.Type
Desenhista Des.-Proj. Projetista Projet. Pleno Estagiário Eng. Junior Eng.Pleno Eng. Sênior Consultor Arquiteto Total
H2 Electrolizers & Conditioning - Process and Instrumentation Diagram PID 24 20 12 8 2 66
H2 Buffer & Compression - Process and Instrumentation Diagram PID 24 20 12 8 2 66

N2 Generation & Distribution System - Process and Instrumentation Diagram PID 24 20 12 8 2 66

H2 & N2 Compression / Pipeline Integration with Ammonia Plant - Process PID 24 20 12 8 2 66


and Instrumentation Diagram
Ammonia Plant - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Air Compression System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Water Treatment System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Cooling Water System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Effluent Treatment System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Equipment Sizing Notes CALCULATION 30 16 4 2 52
Line Sizing CALCULATION 16 8 4 28
Process Data Sheet - Equipment SPECIFICATION 16 8 4 28
Process Data Sheet - Instrument SPECIFICATION 16 8 4 28
Equipment List LIST 8 4 2 14
Process Description DESCRIPTION 40 24 16 2 82
HAZOP ACTIVITY 16 16 8 2 42
VDF ACTIVITY 60 40 32 132
0
0
0
Total de Horas por Perfil 216 0 0 0 0 382 232 146 24 0 1000
TOTAL DE HORAS 1000
OBS

0.43 0.00 0.00 0.00 0.00 0.76 0.46 0.29 0.05 0.00 1.98
SOFTWARE
Software Nº de Licenças Período OBS
MICROSOFT OFFICE 12 MESES
AUTOCAD 12 MESES
PRO II 12 MESES

OUTRAS DESPESAS
Despesa Quant. U.M. OBS

PREMISSAS E OUTRAS OBSERVAÇÕES


1 - No projeto de estruturas metálicas não é considerado desenhos de fabricação (shopdrawing)
2 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a projeto e aprovação junto aos orgãos rodoviários/ferroviários)
3 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a avaliação da capacidade suporte do corpo receptor que receberá a drenagem pluvial advinda do projeto em questão
4 - Nas memórias de cálculos, as horas não consideram análises específicas, como por exemplo: análise de fadiga, ou qualquer outra que não seja usual. Para tais análises, as horas deverão ser avaliadas caso a caso.

Entregáveis ( distribuição de pessoas) 5.75 5.75


Des.-Proj. 1 1 1 4.5
Projet. Pleno 1 1 1 1 4
Estagiário 1 1 1 1
Eng.Pleno 1 1 1 1
Eng. Sênior 1 0.5 0.5 0.5
Consultor 0.25 0.25
Arquiteto 1 1 mês 1 mês 2 mês 3 mês 4
mês 1 mês 2 mês 3 mês 4
PROJECT ENGIE - Projeto Básico para Planta de H2 verde
-
-
DISCIPLINE PROCESS
SCHEDULE 3 Month

TEAM
Alocação em Horas
Document/Activities Doc.Type
Desenhista Des.-Proj. Projetista Projet. Pleno Estagiário Eng. Junior Eng.Pleno Eng. Sênior Consultor Arquiteto Total
General Overview Chart Chart 8 10 6 2 26
Process Flow Diagram PFD 8 10 6 2 2 28
Utility Flow Diagram UFD 8 10 6 2 2 28
H2 Electrolizers & Conditioning - Process and Instrumentation Diagram PID 15 20 10 5 2 52
H2 Buffer & Compression - Process and Instrumentation Diagram PID 15 20 10 5 2 52

N2 Generation & Distribution System - Process and Instrumentation Diagram PID 15 20 10 5 2 52

H2 & N2 Compression PID 15 20 10 5 2 52


Air Compression System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Water Treatment System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Cooling Water System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Effluent Treatment System - Process and Instrumentation Diagram PID 15 20 10 5 2 52
Equipment Sizing Notes CALCULATION 30 16 4 2 52
Line Sizing CALCULATION 16 8 4 28
Process Data Sheet - Equipment SPECIFICATION 16 8 4 28
Process Data Sheet - Instrument SPECIFICATION 16 8 4 28
Equipment List LIST 8 4 2 14
Process Description DESCRIPTION 40 24 16 2 82
HAZOP ACTIVITY 4 16 4 2 26
0
0
0
0
Total de Horas por Perfil 144 0 0 0 0 320 182 84 26 0 756
TOTAL DE HORAS 756
OBS

0.29 0.00 0.00 0.00 0.00 0.63 0.36 0.17 0.05 0.00 1.50
SOFTWARE
Software Nº de Licenças Período OBS
MICROSOFT OFFICE 3 MESES
AUTOCAD 3 MESES
PRO II 3 MESES

OUTRAS DESPESAS
Despesa Quant. U.M. OBS

PREMISSAS E OUTRAS OBSERVAÇÕES


1 - No projeto de estruturas metálicas não é considerado desenhos de fabricação (shopdrawing)
2 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a projeto e aprovação junto aos orgãos rodoviários/ferroviários)
3 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a avaliação da capacidade suporte do corpo receptor que receberá a drenagem pluvial advinda do projeto em questão
4 - Nas memórias de cálculos, as horas não consideram análises específicas, como por exemplo: análise de fadiga, ou qualquer outra que não seja usual. Para tais análises, as horas deverão ser avaliadas caso a caso.

Entregáveis ( distribuição de pessoas) 5.75 5.75


Des.-Proj. 1 1 1 4.5
Projet. Pleno 1 1 1 1 4
Estagiário 1 1 1 1
Eng.Pleno 1 1 1 1
Eng. Sênior 1 0.5 0.5 0.5
Consultor 0.25 0.25
Arquiteto 1 1 mês 1 mês 2 mês 3 mês 4
mês 1 mês 2 mês 3 mês 4
PROJECT ENGIE - Projeto Detaljamento para Planta de H2 verde
-
-
DISCIPLINE PROCESS
SCHEDULE 12 Month

TEAM
Alocação em Horas
Document/Activities Doc.Type
Desenhista Des.-Proj. Projetista Projet. Pleno Estagiário Eng. Junior Eng.Pleno Eng. Sênior Consultor Arquiteto Total
H2 Electrolizers & Conditioning - Process and Instrumentation Diagram PID 24 20 12 8 2 66
H2 Buffer & Compression - Process and Instrumentation Diagram PID 24 20 12 8 2 66

N2 Generation & Distribution System - Process and Instrumentation Diagram PID 24 20 12 8 2 66

H2 & N2 Compression Process and Instrumentation Diagram PID 24 20 12 8 2 66


Air Compression System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Water Treatment System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Cooling Water System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Effluent Treatment System - Process and Instrumentation Diagram PID 24 20 12 8 2 66
Equipment Sizing Notes CALCULATION 30 16 4 2 52
Line Sizing CALCULATION 24 12 8 44
Process Data Sheet - Equipment SPECIFICATION 24 12 8 44
Process Data Sheet - Instrument SPECIFICATION 24 12 8 44
Equipment List LIST 12 8 4 24
Process Description DESCRIPTION 40 24 16 2 82
HAZOP ACTIVITY 4 16 4 2 26
0
0
0
0
Total de Horas por Perfil 192 0 0 0 0 318 196 116 22 0 844
TOTAL DE HORAS 844
OBS

0.38 0.00 0.00 0.00 0.00 0.63 0.39 0.23 0.04 0.00 1.67
SOFTWARE
Software Nº de Licenças Período OBS
MICROSOFT OFFICE 12 MESES
AUTOCAD 12 MESES
PRO II 12 MESES

OUTRAS DESPESAS
Despesa Quant. U.M. OBS

PREMISSAS E OUTRAS OBSERVAÇÕES


1 - No projeto de estruturas metálicas não é considerado desenhos de fabricação (shopdrawing)
2 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a projeto e aprovação junto aos orgãos rodoviários/ferroviários)
3 - Itens fora de Escopo:Não está previsto neste escopo esforço relativo a avaliação da capacidade suporte do corpo receptor que receberá a drenagem pluvial advinda do projeto em questão
4 - Nas memórias de cálculos, as horas não consideram análises específicas, como por exemplo: análise de fadiga, ou qualquer outra que não seja usual. Para tais análises, as horas deverão ser avaliadas caso a caso.

Entregáveis ( distribuição de pessoas) 5.75 5.75


Des.-Proj. 1 1 1 4.5
Projet. Pleno 1 1 1 1 4
Estagiário 1 1 1 1
Eng.Pleno 1 1 1 1
Eng. Sênior 1 0.5 0.5 0.5
Consultor 0.25 0.25
Arquiteto 1 1 mês 1 mês 2 mês 3 mês 4
mês 1 mês 2 mês 3 mês 4