Você está na página 1de 38

Executive Summary

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Parvez Akhtar Qazi +91 22 4063 5405 parvez.qazi@edelcap.com


1

Edelweiss Securities Limited

Rohit Patni +91 22 6623 3392 rohit.patni@edelcap.com

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Executive Summary
We travelled more than 8,500 km by road, air, and railway and visited various road projects across North, South, East, and West India. We met developers, contractors and subcontractors executing projects at a cumulative cost of ~INR 65 bn. Our mission was to find answers to the following pertinent questions: What are the ground level issues in road project execution? Do land acquisition issues continue to hamper the pace of project development? What are the impediments in the land acquisition process? How smooth is the process of getting regulatory approvals in forest / environment / utility shifting? What is the likelihood of reducing cost/time overrun in future projects? Are there constraints in manpower/equipment/raw material availability?

Our key conclusions are as follows


Regulatory approvals a big dampener Land acquisition continues to remain the single biggest road block hampering developers. Lack of clear land titles, protests over land compensation and lackadaisical attitude of state government authorities are major causes for delays. Most developers indicated that execution time of EDT. DownloadPDF. ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 projects could be cut by up to six months by timely land acquisition. Similarly, getting timely approvals from railway and forest departments is very difficult due to the cumbersome process involved. Developer involvement in regulatory approvals ensures timely execution Many projects commissioned in the past had been delayed due to the above mentioned issues. However, developers have learnt from past mistakes and have started facilitating coordination within various government departments by hiring retired officials. As a result, many projects that we visited were running ahead of schedule; also, cost/time overruns, if any, in future projects may not be substantial and are likely to be less than in past projects. Resource availability not an issue We were positively surprised by the fact that resources (manpower, equipment, raw materials, financing or sub-contractors) were easily available. Even if there is any temporary resource crunch, the entrepreneurial spirit of contractors ensures that these issues are taken care of. Also, with multiple resource providers (in terms of equipment manufacturers, banks and other financial institutions), timeliness and cost efficacy of the supply is also reasonably ensured. Outlook on execution of road projects: Bright Over FY09-10, the government has initiated many steps to ensure that the pace of project award has picked up. This leaves execution issues as the principal irritant in improving the pace of road project development. While enhanced developer involvement, good resource availability and increased government efforts have emerged as a positive, some more action is required to speed up the approvals process. We believe if the regulatory side of approvals is taken care of, ramping up execution will not be too challenging.
2 Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction Contents

Our modus operandi .................................................................................................... 3 Why focus on execution? .............................................................................................. 4 Land acquisition .......................................................................................................... 6 Utility shifting and other local clearances ...................................................................... 13 Railways, forest & environmental approvals .................................................................. 16 Resource availability issues ........................................................................................ 18 Cash contracts continue to get delayed ........................................................................ 22 Outlook on road projects execution.............................................................................. 23 Major project details .................................................................................................. 24 Dhule-Palasner Project ............................................................................................ 24 Hyderabad outer ring road project ............................................................................ 26 ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. Pimpalgaon-Nashik-Gonde project ............................................................................ 29 Ranchi ring road project .......................................................................................... 31

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Our modus operandi


We travelled more than 8,500 km by road, air and railway and visited various road projects across North, South, East, and West India. We met developers, contractors and subVisited road projects across the country to understand ground level execution issues contractors executing projects with a cumulative cost of ~ INR 65 bn. Apart from interacting with project managers and engineers, we also met some bankers financing these road builders.

What was the scope of projects covered?


We have tried to cover the widest possible array of road projects in terms of geography, project cost, mandate of project (toll/annuity/EPC) and mode of execution (developer / sub contractor). This was to ensure that we do not restrict ourself to any one particular kind of project and interact with a wide spectrum of industry participants. To better understand execution issues across the industry, we tried to diversify the type of projects visited. Fig. 1: Projects visited across India

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Google Maps, Edelweiss research

Table 1: Covering entire spectrum of road projects We covered every type of road project possible

Scope of projects visited 2 lane 4 lane 6 lane 8 lane access controlled expressway Regions visited North India West India South India East India

Mode of projects visited BOT toll project BOT annuity project State govt EPC project District road project Cost of projects visited < INR 1 bn INR 1 - 5 bn INR 5 - 10 bn INR 10+ bn
Source: Edelweiss research

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Why focus on execution?


Between 1951 and 2006, while Indias vehicle population posted a CAGR of close to 11% and freight and passenger traffic carried by road posted 10% CAGR, the total road length registered a mere 3.9% CAGR with the National Highway (NH) segment increasing at a minuscule 2.2% CAGR. Pace as well as quality of road length addition in the country has been disappointing Also, the quality of roads is abysmal. The Global Competitiveness Report 2010-11 ranks India at a dismal 90th spot as far as quality of roads is concerned, way below neighbours China (53rd), Sri Lanka (55th) and Pakistan (72nd). This shows that the pace as well as quality of road length addition in the country has remained tardy over the years. While things have definitely improved, particularly in the NH segment, since the start of the National Highway Development Programme (NHDP), we have still fallen short of targets. This can be attributed to: (i) slowdown in the pace of project awards in 2006-08 due to regulatory issues and recession; and (ii) execution issues on road projects as manifested in cost and time overruns. Table 2: Physical targets and achievements for NHDP
2007-08 Category Widening to 4-lanes and strengthening (kms.) Target 2,885 Achievement 1,683 2008-09 Target 3,520 Achievement 2,203 2009-10 Target 3,165 Achievement 2,693

Source: Govt documents, Edelweiss research

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. Over FY09-10, the government has initiated many steps which have enhanced the
attractiveness of road projects for developers and ensured pick up in the pace of project awards. With most regulatory issues being sorted out and ~ 26,000 km of projects to be awarded over the next 4-5 years under NHDP, we believe project award is unlikely to be a major dampener going forward (even if pace of project award may not be uniform). This leaves execution issues on road projects as the principal irritant in improving the pace of road development.

How big an issue is execution and what are the costs involved?
As per the government, ~68% of projects undertaken by the National Highway Authority Most road projects witness time/cost overruns of India (NHAI) so far have been delayed (includes both completed and under implementation projects). The World Bank had carried out a time and cost overrun analysis on on-going and completed national highway and state highway contracts a couple of years ago. The results of the study are given below: Table 3: Time and cost over-run details

% Overrun [over original estimates of time and costs] NHAI and <25% state govt contracts 25-50% 50-75% 75-100% >100%

Completed contracts (%) Time 29.4 15.0 33.0 15.0 7.6 Cost 55.8 40.5 3.7 0.0 0.0

Completed + ongoing Contracts (%) Time 10.4 9.7 38.1 29.5 12.3 Cost 53.7 31.6 9.7 5.0 0.0

Source: World Bank, Edelweiss research

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
The study indicates that 90% of all contracts had a time overrun of more than 25%; 46% had a cost-overrun of more than 25%. The cost overrun figures for completed contracts do not include a large portion of pending claims and arbitration orders. As per Execution is a big concern in road development estimates, ~ INR 100 bn is locked in disputes between the government and contractors. Thus, execution remains a major issue in road development; the final costs of road project implementation are much higher than initially envisaged.

What are the major execution issues?


Major issues in road project execution can be broadly categorised into: 1. Regulatory issues 2. Land acquisition Utility shifting and other local clearances Other approvals like forest, railways etc.

Resource availability issues Manpower availability Raw material availability Availability of financing Equipment availability Sub-contractors availability

Our trip was aimed at getting to the root of the execution issues listed above.

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Land acquisition
How big is this problem?
Land acquisition is the biggest issue in road development As per World Bank, on an average, it takes 50% more time than scheduled to hand over encumbrance-free land to contractors for national highway projects. Also, according to a survey of 190 infrastructure projects facing delays, 70% were delayed due to land acquisition problems. This indicates that land acquisition is arguably the biggest hurdle afflicting road development. Fig. 2: Delayed due to reluctance of farmers to hand over land Fig. 3: Problems due to protest over demolition of structure

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

What are the relevant regulations?

Source:Edelweiss research

Land acquisition for development projects in India happens through the Land Acquisition Act (LAA), 1894. However, land acquisition for national highways is carried out under a separate law known as the National Highway Act (NHA), 1956. State governments sometimes constitute a specific law for land acquisition (land acquisition in India is a Concurrent subject as per the Indian Constitution which gives state governments the right to legislate on the matter).

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
What is the process for land acquisition?
The various steps involved in the process of land acquisition for National Highways are given below: Fig. 4: Land acquisition process for national highways
Govt expresses its intention to acquire the land (3A notification)

Carrying out of surveys, inspection etc., setting out of boundaries and intended lines of work

Hearing objections from concerned persons

Award finalisation at the Special Land Acquisition Officer (SLAO) level

Determination of amount payable as compensation

Decleration of acquisition after disposing off objections (3D notification)

Approval at the NHAI Project implementation unit / NHAI hedaquarter

Disbursement of compensation amount

Physical possession

Source: Govt documents, Edelweiss research

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

What are the reasons behind difficulties in land acquisition?


acquisition. Prominent amongst them are:

We learnt from our visit that there are multiple reasons behind difficulties in land

Institutional framework and dependence on local authorities: When land is to be acquired under the NHA, 1956, the NHAI generally relies on the district administration since the relevant land records are with the revenue department. The district administration appoints an Additional District Magistrate or Sub-Divisional Magistrate as the competent authority for this purpose. Sometimes, there is delay in the appointment of a competent authority by the state government which further delays the process. Also, this means that NHAI is dependent on the district administration for the land acquisition process. Since NHAI has no control on district administration (for which land acquisition is not a priority issue due to other responsibilities), the entire process becomes dependent on the proactiveness of district officials. Sometimes, local officials are transferred, which again hampers the process.

NHAI depends on local authorities for land acquisition

Special land acquisition cells enhancing coordination but local authorities still the key: Over the past year, NHAI has set up local cells to enhance coordination in land acquisition with local authorities. These units carry out the following functions: Prepare the notification under section 3A (Intention to acquire land). Prepare the notification under section 3D (1). Disburse the compensation to land owners. These units coordinate with local officials to ensure that the process of land

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
acquisition is smooth. Our interaction with developers reveals that there definitely has been improvement on the ground level with the setting up of such cells. However, in case district administration officials are not dynamic and cannot handle various problems which emerge from time to time with regards to land acquisition, the entire process is still delayed. Indeed, developers raised serious concerns regarding the motivation levels of local authorities. Fragmented land holdings: The fragmented nature of land holdings in rural areas means that a large number of landowners need to be compensated for their land. According to data from the Ministry of Agriculture, 62% of farmers have land holdings of less than one hectare. This creates problems in land acquisition. Fig. 5: Land acquisition delayed due to nearby farm land Fig. 6: Land acquisition stuck due to dispute over compensation amount

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source:Edelweiss research

Lack of clear land titles: Unclear land titles and absent/incomplete revenue records in villages are the biggest constraints in timely land acquisition. The process gets bogged down due to the problem in finding the rightful owner of the land. This is because land records are generally outdated, inaccurate and/or incomprehensive.

Lack of clear land titles and inadequate DPRs create hurdles

This gives rise to frequent disputes, which result in litigation. This is a problem which no amount of NHAI/developer involvement can solve. For e.g., news reports suggest that land acquisition progress in Jharkhand had been hit due to inadequate land revenue records reflecting ownership; the maps were as old as 1912 and the state government is now developing land records by way of physical verification. Similarly, in case there has been an informal division of land amongst family members, it is not reflected in records of the revenue department. Also, in case the land belongs to tribals, the acquisition process further suffers since there is restriction on sale of land from tribals to non-tribals. Inadequate land acquisition plans: Many a times, land acquisition plans as formulated according to the detailed project report (DPR) are inadequate; this is because the professionals involved in preparing DPRs do not have sufficient knowledge of land acquisition. The design consultants do not have sufficient expertise in preparing proper land acquisition plans; also, land acquisition plans are unrealistic due to deficiencies in on-the-ground verification of the design/alignment.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
Lack of uniformity in state government regulations: There is lack of uniformity across state governments in terms of statutes. For e.g., the Uttar Pradesh government had earlier imposed a condition that NHAI will have to guarantee development of a 10 m wide strip of plantation along either side of highways if the Institutional framework for land acquisition is inadequate project involves felling of existing trees. This affects land acquisition progress. Lack of adequate compensation and methodology of computation: We understand that compensation for land acquired is also a big issue impeding land acquisition. The bone of contention here is both the eventual quantum of compensation and the methodology used to arrive at the figure. The NHA, 1956, provides for compensation based on: (a) market value of the land on the date of publication of 3A notification; (b) extra payments for trees, crops, houses, or other immovable properties; and (c) payments for damage due to severing of land, residence, or place of business. A lot of discretion is vested with state authorities during the entire process and, many a times, there is lack of clear cut procedures for the same. This results in grievances against authorities which delays actual possession of land by the government. Various problems related to compensation are detailed below: Sometimes, valuation of land, as determined by authorities, is based on sale deeds recorded with revenue offices; this is way below prevailing market prices and is a cause of heartburn for the landowner. Over the past couple of years, land prices EDT. DownloadPDF. ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 in some parts of rural India have increased sharply due to expansion of rural roads and improvement in accessibility. This has resulted in many landowners demanding higher compensation than the official acquisition rate. Also, sometimes, there is a dispute between state and central governments over the manner of compensating affected land owners. This is also because many states have their own land acquisition and rehabilitation laws, which differ from NHA, 1956. This means that even after publication of 3D notification signifying the acquisition of land by the government, the valuation of the land, approval of the same, disbursement and physical possession of the land by the developer takes a long time. In theory, the land acquisition is complete as soon as the relevant government notification is issued; however, in practice, developers have to wait for a long time in getting unencumbered access to the land.

What is developers viewpoint?


Our interaction with various developers threw some interesting takeaways: Developers lending a helping hand in land acquisition process Developers have become involved in land acquisition process: A large number of projects which have been commissioned over the past couple of years had been delayed due to land acquisition problems . However, developers have also learnt from past mistakes and have realized that they need to be proactive to facilitate coordination between various government departments to ensure that land acquisition is completed on time in order to save time and cost (for BOT projects). To this extent, developers have become involved in the land acquisition process. This includes hiring retired officials (earlier involved in land acquisition) to ensure smooth running of the process. In fact, we came to know of instances where

10

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
developers have themselves acquired certain stretches of land which were proving to be problematic so as to ensure speedy completion of the land acquisition process. Developers indicate more efforts from state government could help: While most developers indicated that NHAI emphasis on land acquisition has improved, Developers want more efforts from state governments they also highlighted that developer involvement is not the panacea of all problems; beyond a particular level, land acquisition progress ultimately depends on the level of state government involvement. They highlighted that states where authorities are proactive (Gujarat, Rajasthan) are the best places to work. On the other hand, projects in certain states like West Bengal, Kerala, Uttar Pradesh, Orissa etc., continue to face problems. Thus, overall while there has been some progress on the land acquisition front, it is sporadic in nature and still depends on developer involvement. Land acquired is not continuous but piecemeal: Developers indicated that many a times, land parcels acquired are not continuous , i.e., they are piecemeal and at quite a distance from each other. This creates problems in execution since it leads to increase in inefficiencies due to less than optimal utilisation of equipments. Unencumbered access to land still a problem: As highlighted above, even after acquisition of land, various encumbrances mean that developers ability to undertake work in a continuous uninterrupted manner is constrained. Unencumbered access to land thus still remains a problem. Land acquisition process needs to be initiated earlier in project lifecycle: Currently, the land acquisition process continues well into the execution period, thereby affecting the construction schedule. Developers suggested the process needs to be initiated at the design stage itself, well before the beginning of civil work. ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. To this end, a comprehensive land survey should be completed before land acquisition schedules are prepared and included in DPRs.

Our view
We believe that while the land acquisition process has improved, many issues remain to be tackled before pace of road development picks up. Our key learning from the visit is as follows: Land acquisition continues to remain the single biggest issue faced by developers Project execution could reduce by up to six months, if land acquisition is completed within schedule Our interaction with developers/contractors indicated that land acquisition continues to remain the single biggest issue troubling developers. This was the unanimous feedback received across all projects that we visited. Most developers indicated that execution time of projects could be reduced by up to six months in case land acquisition is completed in the scheduled time. However, this is hardly the case with developers having to contend with numerous delays due to non-availability of land. Cost/time overruns in future projects may not be substantial and likely to be lesser than past projects With developers lending a helping hand to the government, project execution was on the right track for most BOT projects we visited. This leads us to believe that cost/time overruns in future BOT projects may not be substantial and is likely to be lesser than in past projects. Calculation methodology of land acquisition needs closer scrutiny The revised guidelines for road project awards announced last year state that a LoA will be issued only when 80% of the land required is under possession. However, the calculation of this figure needs a closer look. The Right of Way (RoW) or the land

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

11

Construction
required for any project includes the portion of the land for existing road as well, i.e., for a four laning project, the RoW includes the land of the existing 2 lane project. As a result, a substantial quantity of land required is available upfront. For e.g., the RoW of ~40-45 m required for a 4 lane road includes the existing 2 lane road (usually 10 m wide). Thus, any figure with respect to land acquisition progress needs to be considered in the proper perspective. Recent news flow suggest that governments efforts bearing fruit Recent news articles suggest that governments efforts on the land acquisition front have resulted in improvement. News articles point that: NHAI took possession of 3,022 hectares in Q1FY11. This is almost half the size of the total land possessed (6,244 hectares) by NHAI in 2009-10 which itself was a huge improvement over the 3,120 hectares acquired in 2008-09 and 3,684 hectares acquired in 2007-08. The total land acquired by NHAI was at a relatively higher level at 5,513 hectares in 2006-07. Under section 3G of the NHAI Act, which makes the government liable to pay compensation to the land owner, NHAI has issued notification for 2,204 hectares in Apr-Jul 2010, compared with 3,605 hectares in the previous fiscal. Out of the total 60,500 hectares land required for various stages under the NHDP, the government has managed to acquire around 25,000 hectares. Enhanced support from state government the key

Enhanced support from While NHAI and the roads ministry are doing all they can to improve the land state governments is key acquisition process, on big kicker can come only if the respective state ISIEmergingMarketsPDF in-universal from 203.123.142.250 the 2011-10-05 03:13:58 EDT. DownloadPDF. to speedier road governments pull up their socks and improve coordination at the ground level. In execution this context, the signing of state support agreements (SSAs) by 24 states and Union Territories with the roads ministry is a step in the right direction. The agreement empowers the concessionaire with access to the site and right of way in accordance with the provisions of the respective concession agreements without hindrance from any government agency or person claiming it. Proposed National Highway Amendment Bill will be a key monitorable The proposed National Highway Amendment Bill is being keenly watched with regards to changes in the regulation regarding national highways. News reports suggest a couple of important recommendations as per the draft bill. If a planned road is abandoned, the original owner will reserve the right to buy back the land by returning the money paid by the government for purchase. Further, the owner will not have to pay the appreciation price but only that received when he or she sold the land. It has been proposed that a two-step mechanism be introduced for calculating cost of land at the time of acquisition by NHAI. In the first step, price of the land will be calculated on the basis of the average land price of top 50% sales (in terms of value) in the past three years. The land cost will also be estimated according to the price guidelines for the area maintained by the collector in charge. After arriving at the two values, the higher of the two will prevail as the price that the NHAI will pay to the land owner. Currently, the land price is calculated based on the average price of all land sales in the area in the past three years. The new mechanism proposed, however, takes into account the top 50% values of land sale in three years.

12

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
It is also proposed that the person who sells the land to NHAI should get solatium for better rehabilitation and resettlement. It is proposed that the land owner gets 60% of the agreed sale price of the land as compensation for displacement in addition to the land price. Land acquisition will be an important parameter in determining the success of the 20 km/day initiative It is proposed that a time limit of three months be imposed for the aggrieved to approach an arbitrator in the case of land sale. The current form of bill places no such time limit, leaving it open ended. The arbitrator will also be required to give a decision within six months.

Achieving 20 km/day hinges on land acquisition success


Land acquisition will be an important parameter in determining the success of the 20 km/day initiative. As the recent protests by farmers in Uttar Pradesh over land acquisition for an expressway demonstrated, land acquisition remains a contentious topic in the Indian infra scene. The sooner the outstanding issues are resolved, the better it will be for progress of road development.

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

13

Construction

Utility shifting and other local clearances


How big is this problem?
Utility shifting and other local clearances is another problem facing road projects. Many Utility shifting and other local clearances delay project execution times, while land acquisition is complete, unencumbered access to the land and initiation of execution is not possible due to delays in shifting of utilities and other approvals. Sometimes design and layout of the project have to be changed due to problems in utility shifting. A World Bank study highlighted had indicated that on an average, shifting of electrical utilities took about 33 months, telephone utilities about 31 months and water utilities about 29 months, against the planned target of about 18 months for all these utilities more than a year of delay. Fig. 7: Problems in shifting of power lines Fig. 8: While tree cutting has been completed, power lines still needs to be shifted

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Edelweiss research

14

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
Various clearances involved
Utility shifting: When it comes to utility shifting, major problems are shifting of transmission towers, electric wires, telephone cables, water pipes, etc. Local clearances: Various local clearances required are given below: Table 4: Various local level clearances required

Sl. No. 1 2 3 4 5 6 7 8

Description of permits/licenses required Labour license Registration under building and other construction workers' act Blasting permissions Approvals from village panchayat for installation of crusher, batching plant, asphat plant etc Approval from Pollution Control Board for installation of crusher, batching plant, asphat plant etc Blasting permission from District Collector License for use of explosive from Chief Controller of explosive Permission for installation and operation of HSD consumer pump
Source: Edelweiss research

Agencies involved
For utility shifting, developers need to coordinate with various government departments like the telecom department, the local municipal board and local bodies for water and power maintenance. ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. Lack of proper coordination between For other local clearances, entities involved are the village panchayats/municipal board, govt departments delays District Collector, Pollution Control Board and other government bodies. utility shifting

Reasons behind delays in utility shifting/other clearances


We learnt from our visit that there are multiple reasons behind difficulties in utility shifting/other clearances. Prominent amongst them are: Lack of proper coordination between the implementing agency and respective utility departments Inadequate investigations during DPR preparation and lack of proper utility mapping; sometimes contractors come to know of utilities (underground ones) during the project implementation stage. The road implementing agency has no leverage on utility relocation departments.

Developer viewpoint on utility shifting/other local clearances


Our interaction with various developers threw some interesting takeaways: Better coordination between different government departments required Developers highlighted the need of better coordination between various government departments. Like land acquisition, utility shifting stretches late into the execution period, thereby preventing developers from optimal use of resources. Presence of a dedicated agency helps - Our interaction with developers indicated that the presence of a dedicated agency (like Hyderabad Growth Corridor for Hyderabad outer ring road project) helps in better coordination amongst government departments.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

15

Construction
Developers giving a helping hand to government - Like land acquisition, developers have also become involved in utility shifting/other clearances. They have themselves approached the concerned authorities to ensure smooth coordination Better coordination between various agencies can enhance road development between various entities.

Our view
We believe the challenges in utility shifting are far lower than those in land acquisition as the factors involved are less complex. Also, with a little improvement in coordination between various agencies, there can be a marked upturn in the pace of road project development.

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

16

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Railways, forest & environmental approvals


In every NHAI or state highway project that we visited, there was an issue with a railway over bridge (ROB) or with regards to area under the forest department. Getting approval from railways or the Ministry of Environment and Forests (MoEF) is a tough task for developers. An approval for cutting trees can take up to 30 months. Similarly, approval for a railway over bridge (ROB) from railways can take 15-18 months.

Getting approval from railways or MoEF is a tough task for developers

Reasons behind delays in getting railways, forest and environmental approvals


The reason for delays in getting these approvals is primarily the cumbersome process involved. For e.g., in case of a forest clearance, the developer first receives an in principle approval which stipulates certain specific conditions. Only when all the conditions are fulfilled is the final clearance issued. begin until the final clearance has been achieved. Road projects which pass through a national park or sanctuary require the approval of the National Board of Wildlife (NBW) even for the very first step like undertaking a The process for environmental clearance can take up to a year survey. News reports suggest that there is a lack of a standard procedure for clearance of such projects and the matter has been raised before an Empowered Group of Ministers (EGoM), which is expected to meet shortly to prepare the required norms for such projects. Project implementation cannot

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. Apart from the central government represented by the MoEF, developers have to face
additional conditions imposed by the forest department in the state government. For environmental clearance, the proposal needs to be submitted at the feasibility stage itself. A complete assessment of the environmental impact is done and the project is examined by an expert committee. The whole process can easily take up to an year. In the recent past, many projects have been stuck due to delay in approvals in one of the above parameters. For e.g., news reports suggest that only recently, the standing committee of NBW, rejected NHAIs proposal to divert 85 hectares of forest land for fourlaning in an 85 km stretch on national highway No. 6.

Our view
After interacting with project managers, we believe that railways and forest approvals are emerging as major choke points. Even the proactive efforts of NHAI or developers usually fail in front of these departments since they follow their own procedures which usually take time.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

17

Construction
Fig. 9: Project delayed due to construction of an ROB for which permission was pending for long

Source: Edelweiss research

g i n g M a r k e t s P D F i n We had a chance to examine delays due to ROBs firsthand. In a project, which has been
under implementation for the past four years, the entire road widening part of the project has been complete for some time now. The only portion where work was still pending were a couple of ROBs.

Fig. 10: Project stalled due to delays in approval for cutting trees

Fig. 11: Project delayed due to delays in approvals from forest department

Source: Edelweiss research

Similarly, the process for environmental clearances involves a number of NGOs; a single objection from them can cause a major delay. Sometimes, project alignment itself has to be changed to accommodate demands of the forest department.

18 D o

Edelweiss Securities Limited w n l o a d e d b y i n u n i v e r s a l

Construction

Resource availability issues


After looking at the regulatory approval scenario, we now focus our attention on resource availability issues i.e., the ease of building asset base in terms of manpower, equipments, raw materials, financing and execution multipliers (sub-contractor). Our interaction with project execution personnel pointed out a few positives which we have listed below: Scarcity of quality manpower resources at middle management level

Quality manpower resources at middle management level are scarce


We observed that there is a scarcity of experienced and good quality manpower resources at the middle management level (civil engineers with 10-15 years of experience). Contractors attributed this to the migration of civil engineers to IT companies (starting from the mid 1990s). As a result, there is a shortage of skilled professionals at the middle management level. Also, most contractors believed that the shortage is likely to emerge as a big issue going ahead with the large scale up in infrastructure spending planned in the coming years. However, unskilled or semi skilled manpower is not an issue. We believe contractors have also realized the benefit of developing their own talent base to cope with the anticipated increase in human resource crunch going ahead. Recent news flow suggests that Gammon India has started its own training center in Mysore with a view to create a pool of skilled workforce trained in various skilled disciplines including masonry, plastering, scaffolding, carpentry, electrical work, painting and

plumbing. ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Availability of plant/equipment and raw material is not a constraint


Our interaction with project personnel indicated that there were no major issues with the availability of either plant/machinery or with raw materials. Funding is easily available for enhancing the fixed asset base. In fact, many contractors opined that it is easier to get funding for equipment finance than getting their non-fund based banking facilities enhanced. They attributed this to the presence of NBFCs in the equipment finance space. Fig. 12: Fixed asset base is easy to expand Fig. 13: Equipment availability is not a concern

Source: Edelweiss research

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

19

Construction
Also, raw material constraints are few; in fact, resources mobilisation was in full swing in practically all locations that we visited even before the work at the site was started/scheduled to start. Even in areas where there were some issues with raw material availability, contractors had the foresight of planning for this beforehand. Fig. 14: Raw material is easily available Fig. 15: No problems in raw material supply

Source: Edelweiss research

For e.g., in Haryana where the state government has imposed a ban on mining of major minerals in Faridabad, Gurgaon and Mewat districts for 10 years, alternate supply arrangements from Rajasthan were already in place. This ensured that project ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. implementation was not affected.

No shortage of quality subcontractors


Most developers that we interacted with indicated that there is no dearth of subcontractors in the industry. There are enough small contractors willing to work for developers. We visited a few projects being executed by these sub-contractors and found that the asset base, both in terms of equipment and manpower, with these subThere are enough small contractors willing to work for developers contractors was substantial. These sub-contractors also had easy access to funding which is crucial to their growth prospects. Responsibilities clearly outlined: In projects where the execution is being carried out by a sub-contractor, the role of developers veers more towards project monitoring and supervising the implementation schedule. Developers have their own set of technical personnel engaged at the site who oversee the project execution. There are weekly review meetings with sub-contractors to keep a tab on progress of the project. Sub-contractors have adequate asset base: We also met a few sub-contractors and visited projects being executed by them. Here again, the fact that these subcontractors had their own asset base and qualified manpower came through. Our interaction with these sub-contractors revealed that they had scaled up their execution capabilities over the years which was reflected in the average size of projects being undertaken by them.

20

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
Fig. 16: Sub-contractors have good quality asset base Fig. 17: Sub-contractors have adequate technical acumen

Source: Edelweiss research

These sub-contractors also had their own laboratories for ensuring the quality of work being undertaken. Fig. 18: Quality check at a sub-contractors site

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Edelweiss research

When it comes to the selection process undertaken by developers for choosing subcontractors for any project, the asset base and past work are crucial parameters. Traditional developer-sub-contractor relationships changing: Also, some subcontractors indicated that developers had started giving them incentives for upgrading execution capabilities in terms of asset base and manpower resources. This was being done by developers in the form of assuring the sub-contractor of a minimum volume of work every year for a fixed period of time. We believe this is a

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

21

Construction
win-win situation for both parties involved as sub-contractors get to enhance their execution capabilities and also learn from project management skills of experienced developers; for developers, the benefit is in the multiplier effect brought in by subcontractors. Fig. 19: Sub-contractors have built up execution capabilities and asset base over the years

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Edelweiss research

Funding not an issue: We enquired about the ease of availing financing for purchasing equipments etc. Here again, sub-contractors indicated that they were not facing any shortage. They had relationships with multiple banks and fund availability was not an issue. Interaction with financial institutions corroborates findings: We also

interacted with a couple of financial institutions who fund sub-contractors. They corroborated sub-contractors feedback and were optimistic about future growth prospects of these sub-contractors. These institutions had witnessed growth trajectories of these sub-contractors for the past many years and sounded confident in their ability to scale up their business.

Our view
We believe there is no shortage of resource availability, be it manpower, equipments, raw materials, financing or sub-contractors. Even if there is any temporary resource There is no shortage of resource availability, be it manpower, equipment, raw materials, financing or sub-contractors crunch, the entrepreneurial spirit of contractors ensures that these are taken care of adequately. Also, with multiple providers of these resources (in terms of equipment manufacturers, banks and other financial institutions etc.), the timeliness and cost efficacy of supply is also reasonably ensures. One more positive thing is that even the small sized entities have access to these resources; also, these resources are not geographically concentrated. What this means is that if the regulatory side of approvals is taken care of, ramping up execution will not be too challenging.

22

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Cash contracts continue to get delayed


We visited a number of projects being implemented on cash contract basis. The primary difference between these projects and BOT projects lies in the mode of funding; while cash contracts are funded by the government, in BOT projects, the developer has to tie up the Most cash contracts continue to get delayed financing i.e., in BOT projects, developers own money is at stake. As is natural, the commitment towards avoiding cost/time overrun is higher in BOT projects. It was not surprising to find that almost every cash contracting project that we visited was running behind schedule. Since there is no incentive for contractors to get involved in the process of land acquisition and other regulatory approvals, most contractors adopt a laidback attitude with regards to cash contracts. They were content with religiously documenting their machine/labour idle time for the purpose of claims adjustment at a later stage. The entire responsibility for getting regulatory approvals in this case lies with the client (NHAI/State PWD etc). The process is rarely completed in time due to bureaucratic hurdles. Thus, cash contracts continue to get delayed. As is natural, the chances of legal disputes at a later stage in such projects are also much higher. Fig. 20: Project stalled due to delays in land acquisition Fig. 21: Project stuck due to delays in utility shifting

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Edelweiss research

The delay in cash contracts is also due to the fact that the incentive payment for an early completion of a cash contract project is minuscule as compared to those for BOT projects (bonus annuities or early toll collection). Hence, contractors are also not proactive in completion of cash contracts on time. Data from NHAI corroborates our hypothesis. Of the 136 projects which were running late w.r.t. their original implementation schedule at Sep 2010 end, only 28 were on BOT basis (toll or annuity), balance were all cash contracts. It needs to be kept in mind that only ~ 9% of projects in the NHDP work plan for future (approved last year) are proposed to be completed under the EPC mode. This means that future delays in NHAI projects may be lesser than the past due to smaller share of cash contracts. However, for state government roads and district roads which continue to be implemented on EPC basis, there is no such ray of hope.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

23

Construction

Outlook on road projects execution


Over FY09-10, the government has initiated many steps to ensure that there is a pick-up in the pace of project award. We believe project award is unlikely to be a major dampener going forward; this leaves execution issues as the principal irritant in improving the pace of road project development. Our interaction with developers and other project execution personnel has convinced us that there are quite a few positives when it comes to road project execution. Enhanced developer involvement, good resource availability and increased government efforts are likely to ensure that the execution on road projects is likely to improve going ahead. However, regulatory constraints continue to stifle efforts to build 20 km/day of roads. We believe if the regulatory side of approvals is taken care of, ramping up execution will not be too challenging.

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

24

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Major project details


We highlight the key learnings from some major projects we visited:

Dhule-Palasner project
Key project specific details: Developer: Hindustan Construction / Sadbhav Engg / John Laing consortium Project scope: Design, engineering, finance, procurement, construction, operation and maintenance of 4/6 laning of Madhya Pradesh/ Maharashtra border-Dhule Section of NH-3 from km 168.500 to km 265.000 in Maharashtra under NHDP Phase III A on BOT (Toll) basis. The concession period is 18 years including construction period of 30 months. Client: NHAI Project award date: Jan 2009 Scheduled completion date: June 2012 Total project cost: INR 14.2 bn Significance of the project: The project involves expansion of an existing 2 lane stretch on NH-3 into 4 lane. National Highway 3 (NH-3), which is commonly referred to as the Mumbai-Agra Highway, is a major Indian national highway that runs through the states of Uttar Pradesh, Rajasthan, Madhya Pradesh and Maharashtra. The highway originates in Agra in Uttar Pradesh, travels South-West through ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58and Indore in Madhya Pradesh, and Dhaulpur in Rajasthan, Gwalior, Shivpuri, Guna, EDT. DownloadPDF. Dhule, Nashik, Thane and terminates at Mumbai in Maharashtra. NH 3 runs for a distance of 1,161 km. The project starts from the city of Dhule. At Dhule, NH-3 crosses National Highway 6 (NH-6) which is a busy national highway that runs through Gujarat, Maharashtra, Chhattisgarh, Orissa, Jharkhand and West Bengal. NH-6 passes through the cities of Surat, Dhule, Nagpur, Raipur, Sambalpur, Kolkata, running over 1,949 km from Hazira to Kolkata. Fig. 22: Location of the project Fig. 23: Project stretch

Source: Maps of India, Google map, Edelweiss research

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

25

Construction
Key observations from site visit: Land acquisition problems and forest clearance big challenges: We learnt that the project faced land acquisition problems in the beginning. This was primarily due to resistance from land owners who were demanding a higher compensation for their land. There was some opposition amongst people due to compensation rates being different from village to village. Also, land acquisition was not lateral in nature. Moreover, since the project passes through a stretch which has forests, clearance from MoEF was required. This took some time. Local resistance led to design changes: Since the project passes through an urban area, there was a demand from the local population to include certain underpasses which were earlier not part of the original scope of the project. This issue has been sorted out now. The changes have been incorporated and the additional cost to be incurred has also been approved by the client. Project designed keeping future needs in mind: The project has been designed keeping in mind the expected traffic growth in the future. As a result, even though the project will be a 4 lane road after completion, various structures such as flyovers, bridges etc., which are being built will have 6 lanes. We believe this is a step in the right direction to ensure that the project can handle the increase in traffic ahead and that future capacity expansion will not be difficult. Fig. 24: Execution underway on a major bridge Fig. 25: Construction in full swing on a bridge across a river

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Edelweiss research

Despite challenges, project running ahead of schedule: Despite the challenges mentioned above, the project has been running ahead of schedule. This is primarily due to the developers proactive attitude, aided by the NHAI. The developer mobilised resources as soon as the project was awarded. Also, a major effort was put in identifying the challenges in land acquisition, forest clearance etc., in the initial part of the project itself. Close coordination with various government departments has ensured that all local clearances have been achieved; design changes have also been incorporated. Significant progress on the land acquisition front has also been achieved. As a result, currently the project is ahead of schedule.

26

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
Fig. 26: Execution on track after resolution of land acquisition issues Fig. 27: In spite of heavy traffic, construction is ahead of schedule

Source: Edelweiss research

The progress on the project is commendable considering that the stretch lies on a busy route. There was heavy traffic on the road; despite this, construction was in full swing. Crushers, wet mix plants, batching and asphalt plants were in operation; similarly, machines like excavators, pavers, graders etc., were also working.

Hyderabad outer ring road project


Key project specific details are: ISIEmergingMarketsPDF in-universal from 203.123.142.250 on Expressway 03:13:58 EDT. DownloadPDF. Road stretch: Cyberabad 2011-10-05 Developer: Gayatri Projects consortium Project scope: Design, construction, development, finance, operation and

maintenance of an eight lane access controlled expressway from Kollur to Patancheru (km. 12 to km 23.70). The project is on BOT-annuity basis under Phase II programme of Hyderabad outer ring road (ORR). Client: Hyderabad Growth Corridor (HGCL), an SPV formed for development for the Hyderabad outer ring road by the state government. Date of commencement: Dec 2007 Total project cost: INR 5.01 bn Significance of the project: The Hyderabad ORR is aimed at the development of well planned and well connected urban settlements around the Hyderabad Metropolitan area. The 159 km long ring road provides connectivity to various state and national highways to bypass the city of Hyderabad. The proposed corridor is expected to relieve congestion in the metropolitan area and inner ring road, provide orbital linkage to radial arterial roads, provide link to the proposed MRTS and bus system and provide quick access to the international airport from strategic parts of the city.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

27

Construction
Fig. 28: Outer ring road project in Hyderabad city Fig. 29: Project stretch (Cyberabad expressway)

Source: HUDA, Edelweiss research

Key observations from site visit: Major portion of project completed: Work on majority of the project stretch has been completed. Construction is still going on a small stretch of the road. Fig. 30: Completed portion of the expressway Fig. 31: Work going on a small stretch of road ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Source: Edelweiss research

Land acquisition problems delays project: The project has been delayed due to land acquisition problems. Our interaction with project personnel indicated that majority of the work has been completed. However, land acquisition problem for a small stretch of land has meant that the work is incomplete on that portion of the project.

28

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
Fig. 32: Project stalled due to land acquisition issues Fig. 33: Progress hampered by delays in land acquisition

Source: Edelweiss research

A look at the website of Hyderabad Metropolitan Development Authority indicates that this indeed is the case. Of the RoW of 11.7 km required for the project, only 11.2 km has been handed over. Utility shifting: Apart from land acquisition, the project progress was also hampered by delays in utility shifting. This happened due to delay in getting approval for shifting power transmission lines.

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF. Fig. 34: Shifting of power transmission lines delayed Fig. 35: Utility shifting hampers project completion
project execution schedule

Source: Edelweiss research

The developer has been coordinating with HGCL for getting the approval for this purpose. Timely land acquisition could have avoided the delay: The project has been delayed by more than three months due to delay in land acquisition/utility shifting. To put things in perspective, an identical project on the same road by the same developer has been completed six months ahead of schedule i.e. Hyderabad Expressway is a 13 km stretch of Hyderabad ORR from Bongulur to Tukkuguda. This project (again an access controlled 8 lane expressway) being undertaken by a consortium headed by Gayatri Projects has been completed 6

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

29

Construction
months ahead of schedule. This was possible due to timely handover of land required for the project. Key learning: Despite being close to an urban area which raises its own set of execution challenges, the developer has been able to build a good quality road ahead of schedule when RoW was available; however, when land acquisition/utility shifting is delayed, the project is delayed too despite the best efforts of the developer.

Pimpalgaon-Nashik-Gonde project
Key project specific details: Developer: L&T / Ashoka Buildcon consortium Project scope: Design, engineering, finance, procurement, construction, operation and maintenance of 6 laning of Pimpalgaon-Nashik-Gonde Section of NH3 from 380 kms to 440 kms in Maharashtra under NHDP Phase III A on BOT (toll) basis. The project involves construction of 452 lane kms of roads. The concession period will expire in January 2029. Client: NHAI Project award date: Jan 2009. Construction began in January 2010. Scheduled completion date: July 2012 Total project cost: ~ INR 17 bn Significance of the project: The project involves expansion of an existing 2 lane stretch on NH-3 into 6 lane. The project runs from Pimpalgaon to Gonde via Nashik with Gonde lying on the busy ISIEmergingMarketsPDF in-universal from 203.123.142.250 on Nashik today 03:13:58 the fastest growing cities in India Mumbai-Nashik highway. 2011-10-05 is one of EDT. DownloadPDF. and has been identified as a tier-2 metro. The city's economy is driven chiefly by the engineering and manufacturing industry; many auto majors and original equipment manufacturers have their plants here and have spawned a huge network of auto component suppliers and engineering ancillary services. Fig. 36: Location of the project Fig. 37: Project stretch

Source: Maps of India, Google Maps, Edelweiss research

30

Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction
Key observations from site visit Land acquisition and utility shifting a key test: Since the project passes through the city of Nashik, land acquisition and utility shifting have emerged as a key test for the developer. We surmise that many small commercial establishments will have to be shifted to get the land required for road widening. Management of existing traffic will be the key: Since the project passes through a heavy traffic density area, developers have to undertake the construction work along with managing existing traffic. The project also contains an elevated corridor for traffic to bypass the underlying city congestion. Execution happening on both sides of the road: The existing road is 2 lane. Due to heavy growth in traffic, it is being directly widened to 6 lanes (instead of the more usual 2-to-4 laning in the first part and 4-to-6 laning thereafter). As a result, construction is being carried out on both sides of the road. Despite the challenging task, we believe the developer was carrying out work admirably. We did not see any disruption in traffic; work was going on smoothly.

Fig. 38: Land acquired for widening on both sides of road

Fig. 39: Construction in full swing

Source: Edelweiss research

Raw material availability enhances efficiencies: The project benefits from easy and cost effective raw material availability as the sources of raw material are close to the project site. This has in turn led to smooth resource mobilization. Ashoka Buildcon has two captive RMC plants with a capacity of 60 and 120 cubic meters per hour which are being used in execution of the project (Source: IPO prospectus).

Edelweiss Securities Limited D o w n l o a d e d b y i n u n i v e r s

31 a l

Construction
Fig. 40: Adequate asset base helps in resource mobilisation Fig. 41: Convenient raw material availability near project site

Source: Edelweiss research

Project progress on track: In spite of the project lying on a busy route which brings traffic management into the picture, execution was on track. Construction was going ahead at full speed, aided by easy raw material availability and adequate resource mobilisation. Land acquisition challenges have been adequately met with good progress on land parcels located within the city. As a result, construction on the project is progressing satisfactorily.

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Ranchi ring road project

Key project specific details: Developer: IL & FS Transportation Networks Project scope: The project is concerned with improvement of the Ranchi ring road (Sec III, IV, V and VI). It involves design, engineering, finance, procurement, construction, operation and maintenance of 6 lane divided carriageway on BOT (annuity) basis. The length of the project is 36.2 km. The concession period is 17.5 years (including construction period of 30 months). Ranchi ring road is part of the Jharkhand Accelerated Road Development Programme (JARDP) which involves development of select road stretches in the state of Jharkhand. The total length covered under the programme is 1002 lane km; of this, phase I involves 3 projects (Ranchi ring road, Ranchi to Patratu road and Patratu to Ramgarh road) spread over 466 lane km while the balance comes under phase II. The Jharkhand government is a stakeholder in JARDP with it holding 26% equity in the SPV for the project. Client: Road construction department, Govt of Jharkhand Date of commencement: March 2010 EPC cost: INR 4.77 bn EPC contractor: Sadbhav Engg Significance of the project: The project aims to ease traffic congestion in and around the city of Ranchi, the capital of the mineral rich state of Jharkhand. Ranchi boasts of a number of industrial facilities which are located in and around the city. With rapid growth in trade, commerce, and industry in the city, the traffic has jumped sharply.
32 Edelweiss Securities Limited

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

Fig. 42: Location of the project

Fig. 43: Ranchi ring road

Source: Maps of India, Company, Edelweiss research

Key observations from site visit Involvement of state govt helped in land acquisition: Since the state government holds a stake in the project SPV, there was a high degree of involvement from state officials in the project. This has helped in regulatory i n g M a r k e P D F i n approvals like land acquisition, utility shifting, t etc. s Intensive project monitoring on the part of developers: The developer has given the EPC contract to a third party contractor. Developers involvement is in terms of design and value engineering, project development, consultancy and management as well as operations and maintenance management. To this end, the developer is intensely involved in all the facets of the project including review of the project construction also. There are regular review meetings to take stock of progress as well as to assess and to plan for future milestones. Well qualified EPC contractor(s): The EPC contractor(s) engaged in the project are well qualifiedboth in terms of having a substantial equipment base and technical/human resources. This has helped in the smooth implementation of the project. The plant/machinery deployed at the site included batching plants, excavators, graders, compactors, tippers, pavers, rollers, transit mixers, crushers etc.

Edelweiss Securities Limited D o w n l o a d e d b y i n u n i v e r s

33 a l

Construction
Fig. 44: Excellent asset base with EPC contractors Fig. 45: Equipment strength not lacking in case of contractors

Source: Edelweiss research

Construction in full swing: The project involves construction of various structures like flyovers, RoBs/RuBs and major/minor bridges. At certain points, it intersects existing national highways as well. Regulatory approvals for various structures were in place and execution was in full swing. Overall, the project is progressing as per schedule. Fig. 46: Work on structures is going on I S I E m e r g i Fig. 47: Execution is progressing as per schedule a r k e t s P D F i

Source: Edelweiss research

Key learning: In case the state government is actively involved, getting regulatory approvals becomes easy. Also, regular project monitoring and review along with intensive developer involvement is the key for a project being on the right track. This, when supported by well qualified contractors, leads to smooth project execution.

34 D o

Edelweiss Securities Limited w n l o a d e d b y i n u n i v e r s a l

Construction
NOTES:

ISIEmergingMarketsPDF

in-universal

from

203.123.142.250

on

2011-10-05

03:13:58

EDT.

DownloadPDF.

Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging

35 Unauthorized

Markets.

Construction
NOTES:

36 D o

Edelweiss Securities Limited w n l o a d e d b y i n u n i v e r s a l

Construction
Edelweiss Securities Limited, 14th Floor, Express Towers, Nariman Point, Mumbai 400 021, Board: (91-22) 2286 4400, Email: research@edelcap.com
Vikas Khemani Nischal Maheshwari Head Head Institutional Equities Research vikas.khemani@edelcap.com nischal.maheshwari@edelcap.com +91 22 2286 4206 +91 22 6623 3411

Coverage group(s) of stocks by primary analyst(s): Construction


Consolidated Construction Co., C and C Construction, Gammon India, Hindustan Construction Co., IRB Infrastructure, IVRCL Infra, Jaiprakash Associates, BL Kashyap & Sons Ltd, Man Infraconstruction, Nagarjuna Construction Co, Patel Engineering Ltd, Simplex Infrastructures Ltd

EW Indices
1,400

Recent Research

Date
1,250 1,100 950 800 20-Nov-09 20-May-10 20-Nov-10 Nifty

Company IVRCL Infra

Title

Price (INR) Recos 133 Buy

16-Nov-10

Weak quarter; strong order book the only silver lining; Result Update

15-Nov-10

Patel Stable performance; Engineering progress on asset ownership ventures; Result Update Man Steady revenue growth; Infraconst. margins decline; Result Update

372

Buy

12-Nov-10

339

Hold

EW Construction Index

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.


Edelweiss Research Coverage Universe Buy Rating Distribution* * 3 stocks under review > 50bn Market Cap (INR) 110 Between 10bn and 50 bn 53 < 10bn 13 116 Hold 45 Rating Interpretation Reduce 12 Total 176 Rating Buy Hold Reduce Expected to appreciate more than 15% over a 12-month period appreciate up to 15% over a 12-month period depreciate more than 5% over a 12-month period

Distribution of Ratings / Market Cap

Access the entire repository of Edelweiss Research on www.edelresearch.com


This document has been prepared by Edelweiss Securities Limited (Edelweiss). Edelweiss, its holding company and associate companies are a full service, integrated investment banking, portfolio management and brokerage group. Our research analysts and sales persons provide important input into our investment banking activities. This document does not constitute an offer or solicitation for the purchase or sale of any financial instrument or as an official confirmation of any transaction. The information contained herein is from publicly available data or other sources believed to be reliable, but we do not represent that it is accurate or complete and it should not be relied on as such. Edelweiss or any of its affiliates/ group companies shall not be in any way responsible for any loss or damage that may arise to any person from any inadvertent error in the information contained in this report. This document is provided for assistance only and is not intended to be and must not alone be taken as the basis for an investment decision. The user assumes the entire risk of any use made of this information. Each recipient of this document should make such investigation as it deems necessary to arrive at an independent evaluation of an investment in the securities of companies referred to in this document (including the merits and risks involved), and should consult his own advisors to determine the merits and risks of such investment. The investment discussed or views expressed may not be suitable for all investors. We and our affiliates, group companies, officers, directors, and employees may: (a) from time to time, have long or short positions in, and buy or sell the securities thereof, of company (ies) mentioned herein or (b) be engaged in any other transaction involving such securities and earn brokerage or other compensation or act as advisor or lender/borrower to such company (ies) or have other potential conflict of interest with respect to any recommendation and related information and opinions. This information is strictly confidential and is being furnished to you solely for your information. This information should not be reproduced or redistributed or passed on directly or indirectly in any form to any other person or published, copied, in whole or in part, for any purpose. This report is not directed or intended for distribution to, or use by, any person or entity who is a citizen or resident of or located in any locality, state, country or other jurisdiction, where such distribution, publication, availability or use would be contrary to law, regulation or which would subject Edelweiss and affiliates/ group companies to any registration or licensing requirements within such jurisdiction. The distribution of this document in certain jurisdictions may be restricted by law, and persons in whose possession this document comes, should inform themselves about and observe, any such restrictions. The information given in this document is as of the date of this report and there can be no assurance that future results or events will be consistent with this information. This information is subject to change without any prior notice. Edelweiss reserves the right to make modifications and alterations to this statement as may be required from time to time. However, Edelweiss is under no obligation to update or keep the information current. Nevertheless, Edelweiss is committed to providing independent and transparent recommendation to its client and would be happy to provide any information in response to specific client queries. Neither Edelweiss nor any of its affiliates, group companies, directors, employees, agents or representatives shall be liable for any damages whether direct, indirect, special or consequential including lost revenue or lost profits that may arise from or in connection with the use of the information. Past performance is not necessarily a guide to future performance. The disclosures of interest statements incorporated in this document are provided solely to enhance the transparency and should not be treated as endorsement of the views expressed in the report. Edelweiss Securities Limited generally prohibits its analysts, persons reporting to analysts and their family members from maintaining a financial interest in the securities or derivatives of any companies that the analysts cover. The analyst for this report certifies that all of the views expressed in this report accurately reflect his or her personal views about the subject company or companies and its or their securities, and no part of his or her compensation was, is or will be, directly or indirectly related to specific recommendations or views expressed in this report. Copyright 2009 Edelweiss Research (Edelweiss Securities Ltd). All rights reserved

Edelweiss Research is also available on www.edelresearch.com ,Bloomberg EDEL <GO>, Thomson First Call, Reuters and Factset.

Edelweiss Securities Limited Limited 37 Edelweiss Securities

Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Construction

ISIEmergingMarketsPDF in-universal from 203.123.142.250 on 2011-10-05 03:13:58 EDT. DownloadPDF.

Edelweiss Securities Limited, 14th Floor, Express Towers, Nariman Point, Mumbai 400 021 Tel: +91 22 2286 4400. Email: research@edelcap.com
38 Edelweiss Securities Limited Downloaded by in-universal from 203.123.142.250 at 2011-10-05 03:13:58 EDT. ISI Emerging Markets. Unauthorized Distribution Prohibited.

Você também pode gostar