Quick Start Guide

See When Your Project Will Truly Be Done


And How To Get It Done Faster
In 5 Minutes Or Less

Outline of Quick Start Guide

Importing Your Plan from MS Project

• Steps 1-3 (Page 2)


• Steps 4-6 (Page 3)
• Step 8 (Page 4)

Address the uncertainty

• Step 8 (Page 5-6)

Run the analysis

• Step 9 (Pages 6-9)

Create the report

• Step 10 (Page 10)

-1-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

1. Open your file in Microsoft Project. File > Open

Highlight
a file and
select the
file and
Open

Note: If you do not have an MS Project file contact True Project and we will send you one. If you
do not have MS Project at all, True Project can send you a Pertmaster file or help you acquire a
trial version of MS Project.

2. At the top left corner of your screen, select Open In Pertmaster


Select

3. You will see the following screen

Select To the
nearest day and
-2- then select OK
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

4. You will see the following screen

Select Yes

5. If you have already converted your MS Project file to a Pertmaster


file, you will see the following screen

Select Overwrite

6. You will then see the following screen

Select Save ‘File


Name’ without a
baseline

-3-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

7. You will see the following screen

Save your file as a


Pertmaster Plan to the
folder of your choice

Your screen should look similar to a Microsoft Project plan, but now you are on
your way to seeing when your project will be truly done and how you reduce
your project lifecycle!

-4-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

8. Select Risk from the toolbar, select Duration Quick Risk (Shift+F10)
from the drop down menu or click on

You will see the following screen

The value you entered from each task from MS Project is your remaining
duration.

The percent you enter for minimum duration will be x% of the remaining
duration (i.e. if your remaining duration is 10 days and you enter Minimum
duration is 70% of remaining duration, your minimum duration will become
7 days).

The likely duration can also be changed to the percentage of the remaining
duration (i.e. if your remaining duration is 10 days and you enter Likely
duration is 100% of remaining duration, your minimum duration will remain
10 days).

The percent you enter for maximum duration will be x% of you’re the
remaining duration (i.e. if your remaining duration is 10 days and you enter
Maximum duration is 160% of remaining duration, your maximum duration
will become 16 days).

Note: Quick risk is intended to quickly assess risk and uncertainty within a project. It will begin the
dialogue and add valuable insight into the true when, why, what of your project.

-5-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

This will populate the Minimum Duration, Most Likely, Maximum Duration on the
right side of the Pertmaster for Microsoft Project GANNT chart. If you double click
on any of the cells in the Duration Risk column (Triangle (X,X,X)), you can see the
tasks details by selecting the Risks tab and the Duration tab you can see a graphical
interpretation of your distribution.
This will now
create a triangular
distribution for this
task and all other
tasks in the plan.
This will allow the
random number
generator to plug
this range of values
and recalculate
them while running
the simulation. To
view the task
details, double click
on any cell in the
Duration Risk
column

9. Select Risk from the toolbar, select Run Risk Analysis… (F10) from the drop
down menu or click on

You will see the following screen

Select Analyse

-6-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

Select Go

Select OK

You will notice the values in the Preferred Finish Date and Rem Durn columns
change as well as the Gantt chart move.
The range of values you have put in the Minimum Duration, Most Likely Duration,
and Maximum Duration are now being calculated and re-calculated 1000 times to
give you the following information in a histogram.

-7-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less
New Product
Entire Plan : Finish Date

100% 11/22/07 Analysis

95% 10/18/07 Simulation: Latin Hypercube


Iterations: 1000
125 90% 10/05/07
85% 09/28/07 Convergence
80% 09/24/07
Plan Finish Date:
75% 09/18/07 Converged in 200 iterations

Cumulative Frequency
100 (variation < 1% over 100 iterations)
70% 09/13/07 Total Plan Cost:
Converged in 200 iterations
65% 09/10/07 (variation < 1% over 100 iterations)
60% 09/05/07
75 55% 08/31/07 Statistics
Hits

50% 08/29/07 Minimum: 06/01/07


Maximum: 11/22/07
45% 08/24/07 Mean: 08/28/07
Max Hits: 139
40% 08/21/07 Std Deviation: 29.77
50 35% 08/16/07
30% 08/13/07 Selected Confidence
50%: 08/29/07
25% 08/08/07 Deterministic Finish: 06/12/07
Probability (less than 1%)
20% 08/03/07
25
15% 07/30/07
10% 07/20/07
5% 07/10/07
0
06/01/07 06/30/07 07/29/07 08/27/07 09/25/07 10/24/07 11/22/07
Distribution (start of interval)

You have now answered, when will my project get done? Now answer, how my
project will get done, by clicking on

New Product
Entire Plan : Duration

Analysis
00039 - Conduct marketing/technical review 56% Simulation: Latin Hypercube
Iterations: 1000
00099 - Determine if product is meeting customer cost/performance expect 39%
00090 - Start production of commercial product quantities 25% Sensitivity measurement
00102 - Evaluate manufacturing process for stabilityand cost effectiven 24% Spearman's rank correlation
00086 - Design and order newequipment 22% Measured Against: Entire Plan

00087 - Install and test newequipment or equipment modifications 20%


Display settings
00091 - Monitor customer acceptance testing 17%
Normal tasks only
00043 - Produce product for customer evaluation 17% Showing 10 highest tasks
00071 - Complete customer trial monitoring 15%
00048 - Prepare preliminarymanufacturing design 15%

By focusing on the tasks that really matter, you can improve the efficiency of your
project and thereby reduce project lifecycle time.

-8-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

10. Now that you have analyzed the risks in your project, you need to be able to
communicate the results to begin managing the project more efficiently.
Select Reports from the toolbar, and Summary Risk Report from the drop
down menu. You will see the following screen.

You can select the


Milestones to see the
likelihood of each
milestone being
completed on time.

Then Select All


Then Press OK

-9-
Quick Start Guide
See When Your Project Will Truly Be Done
And How To Get It Done Faster
In 5 Minutes Or Less

Congratulations! You’re report is being generated in MS Word.

As a project manager you are now able to:

• Clearly show the tasks with the greatest impact on your project, so you are
able to get the resources you need
• Increase your schedule predictability, so your projects are not late
• Enhance your process and planning, so you are not working around the clock
at the end of your project

Once you have implemented True Project tools and training, you will see the following
results:

• You will be more confident in your schedules, and be seen as a project


manager “you can set your watch to.”
• Your projects will be smarter, and it will be reinforced that the right decision
was made
• You will be more productive, and seen as a very efficient project manager

As a senior manager, you are now able to:

• Reduce project lifecycles to increase your top line


• Improve your time to market to increase your market share
• Create a more efficient project management process to improve your bottom
line

Once you have implemented True Project tools and training, you will see the following
results:

• You will be more in control of your projects and get the results your
company is looking for
• You will have the information to be a more effective and more decisive leader
• You will have the information to make wise decisions to lead your company
to success

We look forward to starting a dialogue with you to determine the best way to make this a
reality for you. Call or email us today.

True Project Inc.


303-595-4700
info@trueproject.com

- 10 -