Escolar Documentos
Profissional Documentos
Cultura Documentos
PMP
Preparation Training
Your key in Successful Project
Management
Chapter 6
Time Management
AGENDA
Time Management
Processes required to accomplish
timely completion of the project
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
n Estimating
n Network Analysis Techniques
Estimating
Estimating
Activity Duration Estimating
Estimating
Quantitatively Based Durations
Estimating
Quantitatively Based Durations
Estimating
PERT Duration Calculation
Higher
Most Likely
Probability (Used in original CPM Calculations)
Of PERT Weighted Average =
Optimistic + 4 X Most Likely + Pessimistic
Occurrence ( 6 )
Beta Distribution
Calculation of PERT
PROBABILITIES
n TIME ESTIMATE
Te= a + 4b + c
6
n a = OPTIMISTIC
n b= MOST LIKEY
n c = PESSIMISTIC
n TIME VARIANCE
s =c–a
V = s2
6
§ a = OPTIMISTIC
§ c = PESSIMISTIC
Normal Distribution
-1σ +1 σ
-2 σ +2σ
68.26%
95.46%
99.73%
LCL UCL
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 13 +20105394312
n Critical Path
n Early/Late Start and Finish
n Float
A B C
Start Finish
6 Days 7 Days 3 Days
D E F
Start Finish
6 Days 7 Days 3 Days
0 6 6 13 13 16
D E F
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 17 +20105394312
PERT Calculations
-1σ +1 σ
-2 σ +2σ
50%
84.13%
97.73%
99.86%
Project Start Date
• Normal Distribution:
Ø 50% chance - using expected time durations ( Te, )
Akram Al-Najjar, PMP.
PERT Example
Expected Project Duration: 12.33 days
A 2 4 6 4 .67
B 2 3 5 3.33 .5
C 4 7 10 7 1
D 4 5 6 5Akram Al-Najjar,.33
PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 23 +20105394312
PMBOK® Chapter 6
There are 5 major Processes:
1. Activity Definition
2. Activity Sequencing
3. Activity Resource Estimating
4. Activity Duration Estimating
5. Schedule Development
6. Schedule Control
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 24 +20105394312
2/12/2006
Time Management
Planning Controlling
Activity Definition
Activity Definition
Tools & Techniques
• Decomposition
• Templates
• Rolling Wave Planning
• Expert Judgment
• Planning Component
Inputs
• Enterprise Environmental
Factors Outputs
• Organizational Process • Activity list
Assets • Activity Attributes
• Project Scope Statement • Milestone List
• WBS • Requested Changes
• WBS Dictionary Akram Al-Najjar, PMP.
• Project Management Plan Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 28 +20105394312
2/12/2006
n Expert Judgment
n Planning Component
Control Account. (specific components at selected levels)
Planning Package. (a WBS component below the control
account, but above the work package.)
n Activity list –
A list of all the activities that will be performed on
the project and a description of each
Activity Sequencing
Activity Sequencing
Tools & Techniques
• Precedence diagramming
method (PDM)
• Arrow diagramming
method (ADM)
• Schedule network templates
• Dependency determination
• Applying leads and lags
Inputs Outputs
• Project Scope Statement • Project Schedule network
• Activity list diagram
• Activity Attributes • Activity list (updates)
• Milestone List • Activity Attributes (updates)
• Approved Requested • Requested Change
Akram Al-Najjar, PMP.
Changes Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 33 +20105394312
Inputs
A B
Start E Finish
C D
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 35 +20105394312
A B
A B
A B
A B
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 37 +20105394312
Outputs
Inputs
n Activity List
n Activity Attributes
n Resource Availability
n Project Management Plan Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 43 +20105394312
n Consultants
Outputs
n Resource requirements – Description of the
types (e.g., skill levels) and numbers of resources
required by each element of the WBS
Inputs
n Enterprise Environmental Factors: One or more of the
organizations involved in the project may maintain duration
estimating databases and other historical reference data.
n Organizational Process Assets: Historical information
(Section 4.1.1.4) on the likely durations of many categories of
activities is often available.
n Project Scope Statement : The constraints and assumptions
from the project scope statement (Section 5.2.3.1) are
considered when estimating the schedule activity durations.
n Activity List
n Activity Attributes
n Resource requirements – The estimated activity resource
requirements (Section 6.3.3.1) will have an effect on the
duration of the schedule activity.
Inputs ( Cont.)
n Resource Calendar
n Project Management Plan
Risk Register: The risk register has information on
identified project risks that the project team considers when
producing estimates of activity durations and adjusting those
durations for risks.
Outputs
n Activity Duration estimates – Quantitative
assessments of the likely number of work
periods required to complete an activity
Schedule Development
If start and finish dates are not realistic, the project is unlikely
to be finished on schedule
Schedule Development
Tools & Techniques
• Schedule Network Analysis
• Critical Path Method
• Schedule Compression
• What-If Scenario Analysis
• Resource Leveling
• Critical Chain Method
Inputs • Project Management Software
• Organizational Process Assets • Applying Calendars
• Project Scope Statement • Adjusting Leads and Lags
• Activity List • Schedule Model
• Activity Attributes Outputs
• Project Schedule Network Diagrams • Project schedule
• Activity Resource Requirements • Schedule Model Data
• Resource Calendars • Schedule Baseline
• Activity Duration Estimates • Resource-requirement updates
• Project Management Plan • Activity Attributes (Updates)
Risk Register. • Project Calendar (Updates)
• Requested Changes
• Project Management Plan (Updates)
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 53 +20105394312
Inputs
n Organizational Process Assets: such as a
project calendar (a calendar of working days or shifts
that establishes dates on which schedule activities are
worked, and nonworking days on which schedule
activities are idle).
n Project Scope Statement: (Section 5.2.3.1) contains
assumptions and constraints
n Activity List
n Activity Attributes
n Project Schedule Network Diagrams
n Activity Resource Requirements
n Resource Calendars
n Activity Duration Estimates
n Project Management Plan: Risk Register.
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 54 +20105394312
2/12/2006
Outputs
n Project schedule : includes at least a planned start
date and planned finish date for each schedule activity.
Project schedule network diagrams.
Bar charts.
Milestone charts.
n Schedule Model Data
n Schedule Baseline : baseline is a specific version of
the project schedule developed
n Resource Requirements (Updates)
n Activity Attributes (Updates)
n Project Calendar (Updates)
n Requested Changes
n Project Management Plan (Updates)
Akram Al-Najjar, PMP.
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 58 +20105394312
2/12/2006
Network Calculation
Start Date 6/1
6/6 6/10
B 5
6/1 6/5 6/16 6/25 6/26 6/30
6/11 6/15
A 5 5 D 10 E 5
Basic Terminology
Gantt Charts
Task A
Task B
Task C
Task D
June July Aug Sep Oct Nov
Schedule Control
Schedule Control
Tools & Techniques
• Progress Reporting
• Schedule Change Control System
• Performance Measurement
• Project Management Software
• Variance Analysis
• Schedule Comparison Bar Charts
Outputs
• Schedule Model Data (Updates)
Inputs • Schedule Baseline (Updates)
• Schedule Management Plan • Performance Measurements
• Schedule Baseline • Recommended Corrective Actions
• Performance Reports • Organizational Process Assets (Updates)
• Approved Change Requests • Activity List (Updates)
• Activity Attributes (Updates)
• Project Management
Akram Plan PMP. )
(Updates
Al-Najjar,
Planning & Cost Control Manager
Akram_alnajjar@hotmail.com
Source: pmbok guide 2004 Slide 65 +20105394312
Inputs
n Schedule Management Plan : (Section 4.3)
n Schedule Baseline: (Section 6.5.3.1)
n Performance Reports: (Section 10.3.3.1)
n Approved Change Requests : (Section 4.4.1.4)
Outputs
n Schedule Model Data (Updates)
n Schedule Baseline (Updates)
n Performance Measurements
n Requested Changes
n Recommended Corrective Actions
n Organizational Process Assets (Updates)
n Activity List (Updates)
n Activity Attributes (Updates)
n Project Management Plan (Updates)
Short Break
n Any questions?