Report of the Interactive workshop on Best Practices for Maintenance of Transmission Lines 29-30 June 2010, at CBIP New

Delhi The committee for CIGRE India and Central Board of Irrigation & Power Organised two days Interactive workshop -30th on Best Practices for Maintenance of Transmission Lines on 29 June 2010 in the Conference Hall of Central Board of Irrigation & Power, Malcha Marg, New Delhi.

From L-R - Shri V.K. Kanjlia, Secretary, CBIP, Mr. Benoit, GroupeSICAME (CATU), Shri R.N. Nayak, Director (Opn.), Powergrid Shri S.K. Negi, MD, GETCO, Shri L.N. Agrawal, Sr. VP, Indiabulls

The workshop was organized with the aim to interact & discuss the best practices for maintenance of transmission lines amongst the Power Utilities/ Corporations, SEBS, State Govts., IPPs, Energy Planners, Private Entrepreneurs, Developers, Manufacturers, Consultants, Construction Companies, Industry Associations, Technical, Financial and Training Institutions etc. Shri R.N. Nayak, Director (Operation), Power Grid Corporation of India Limited and Shri S.K. Negi, MD, GETCO were the guest of Honor and addressed the participants during Opening session of the workshop.
Shri R.N. Nayak, Director (Opn.), POWERGRID Shri S.K. Negi, MD, GETCO

Shri V.K. Kanjlia, Secretary, CBIP delivered welcome address and Vote of thanks was proposed by Shri P.P. Wahi, Director, CBIP

Shri V.K. Kanjlia, Secretary, CBIP Shri P.P. Wahi, Director, CBIP

Shri L.N. Agrawal, Sr. VP, Indiabulls

Mr. L.N. Agrawal, Sr. Vice President India Bulls and Mr. Benoit, Manager, GroupeSICAME (CATU) also addressed the participants during Opening session.
Mr. Benoit, Manager, GroupeSICAME (CATU)

TOPICS covered in the workshop are:


Maintenance procedures of EHV transmission Lines Probable causes of failure of the transmission line components Condition monitoring of EHV transmission lines Counter measures for pollution Insulator- washing/cleaning Emergency restoration of damaged transmission lines Helicopter maintenance techniques Composite / Polymer insulators Hot- line maintenance Preventive maintenance schedules of Transmission Lines Case studies

FACULTY who delivered lecture are:


Mr. S.K. Negi, MD, GETCO Mr. L.N. Agrawal, Sr. VP, IndiaBulls Mr. Rajeev Kumar , CM(OS), POWERGRID Mr. Gopal Ji , AGM(Engg.), POWERGRID Mr. Benoit, Manager, GroupeSICAME (CATU) Mr. Bhavesh Makwana, Director, Madhav Engineers Pvt. Ltd. Mr. Rajesh Kumar, GM(Engg.), POWERGRID Mr. Rajiv Gandhi, CM(Engg.), POWERGRID Mr. V.K.Khare,GM(O&M), POWERGRID Mr. R.B. Singh, AGM(OS), POWERGRID Mr. Krishna Vaidya, Executive Director, Taurus Technologies Mr. Rajeev Mathur, PCI Ltd. Mr. A. Natrajan, General Manager, WS Industries (I) Ltd.

Shri Rajesh Kumar, General Manager (Engineering), Power Grid and National Representative in CIGRE Study Committee B2 on Over Head Lines is sitting in the audience

View of audience

Report on the Proceeding of workshop by Reporteur Shri Anil Sinha, Consultant The workshop was divided in to one inaugural and six technical sessions, spread over two days. The inaugural session saw many dignitaries grace the dais. The list included: Mr R N Naik, Director, PGCIL, Mr S K Negi, MD, GETCO, Mr L N Agrawal, Sr VP, India Bulls, Mr Benoit, Area Mgr, CATU and Mr V K Kanjlia, Secretary, CBIP. Mr P P Wahi, Director, CBIP, conducted the workshop. Mr Kanjlia initiated the topic and informed that the current inter-regional transmission capacity is around 38000 MW, the country is adding 765 kV lines, along with HVDC links. He put emphasis on proper maintenance practices for the country to reap full benefit of the available infrastructure. Mr Agrawal advocated revision of the available CBIP manual on Transmission Line Maintenance. Among other topics, the manual should cover Disaster Management. He advised that the feedback from the O&M engineers should be one important input for Design Engineering of Transmission Lines. Thereapart, the manual should now cover the newer 765 kV & HVDC lines, as well. He recalled his association with the writing of the current version of the manual and advised chapter-wise revision. In his view, we should consider the example of other nations to calculate availability figure. Mr Benoit emphatically drew the attention towards safety and safe practices during maintenance. Mr Naik reminded the participants of approximately 80000 route-km of transmission lines being added in the next 3 to 4 years. The country already has lines of voltage ranging from 66 kV to 765 kV, with 1200 kV in planning. We also have HVDC line up to 800 kV. Among the common issues narrated by him were, Erosion of tower legs, Theft of metal, Pollution, etc. He drew the attention of the workshop towards the need for innovative maintenance practices to take care of the huge installed base.

PGCIL has been considering novel methods, which included even the use of Aircrafts, Helicopters and Unmanned Drones. Of these, the use of helicopter has been found feasible. PGCIL has been undertaking hotline maintenance, resulting in 99.97% availability of the lines. Mr Naik suggested Vegetation management around the lines, Thermography to detect hot-spots, Measures to reduce Insulator failures, and the use of robots for maintenance activity in future. Mr Negi took pride in informing the gathering of the present good power scenario in Gujrat. The state provides 24x7, nobreak supply, whereby, residents do not need Voltage Stabilisers or Inverters. Among the locational issues, he spoke of the long coast line and wide-spread marshes, supplementing the industrial pollution and fog. Gujrat is also prone to

Cyclones and other detrimental weather phenomena. So maintenance of transmission lines is particularly important in Gujrat. He pointed out that good maintenance starts at good design practice, and expects good execution. Thereafter, one is required to consider Temperature variation, Pollution and Water-logging, among other issues. Mr Agrawal started the technical session with an Overview of best maintenance practices. Considering the fact that he is a major contributor to the CBIP maintenance manual on transmission lines, his considered views on the topic were very well received by the participants. Mr Agrawal informed that even a de-energised line has 1 to 5 kV induced voltage. Hence care must be exercised. He advised the use of modern techniques, e.g., Thermegraphy, and Corona camera. Any contact joint, including mid-span joints, should have less than 5 resistance. If the resistance is over 30, a hot spot will develop. On the issue of Hotline washing, the outer two limbs are aminable to helicopter based washing, but the middle line washing is difficult. There is an ever-present danger of Earth-line fouling. Other issues to keep in mind are: the size of the fuel-tank and the water tank, proximity of a helipad, etc. In his opinion the use of de-miniralised water is not required as the helicopter is not grounded. Mr Agrawal referred to hot-line maintenance of 400 kV and above lines. The two methods suggested were: Bare-hand method & Hot-stick method. In the case of de-energised circuit of a double circuit line, with the other circuit live, the important aspects are: the use of portable earthing, creation of equi-potential zone, removal of line reactors. The tower earthing is expected to be good. Along with maintenance, other activities, e.g., Conductor repair, jointing, insulator replacement, etc may also be undertaken at the same time. Mr Rajeev Kumar, Ch. Manager, PGCIL gave an illuminating presentation on Helicopter Maintenance Techniques. He also advised that cleaning of the transmission line is imperative to keep up the performance level. The more prevelent pollutants affecting a line are: Industrial Vehicular Open burning of agriculture waste Bird droppings

Presence of moisture aids the settling of the pollutant on the line and insulators. Therefore the foggy winter days are bad for the line. Manual cleaning of the line is feasible, but generally requires a shutdown. The persons undertaking the job must be highly skilled. But it does give better results compared to the helicopter based method, which is also much costlier. A helicopter uses up around 100 liters of de-minaralised water per tower and can clean 3 to 4 towers per trip. The arial cleaning requires DGCA clearance and every trip needs ATC permission. The helicopter has maintain very strict clearances, making it a highly skilled job. To date, no Indian pilot has undertaken this work. Settling of pollutant on the insulators can be reduced by the use of polymer type insulators. To a question, Mr Rajeev Kumar clarified that washing of the insulators is done starting from bottom upward. This reduces the chances of a flashover. He also referred to the use of the ERS (Emergency Restoration System). The detailed presentation on the subject was given later in the day. Mr. S K Negis (MD, GETCO) presentation was on the Best Practices for Maintenance of Transmission Lines, which is also topic of the workshop. He continued with his statement of the inaugural session that good maintenance starts with a good design. Among his suggestions are: Create awareness to reduce pollution. Undertake asset management to identify risk spots, then attack the critical zones. River crossings are high risk locations. Do a root-cause analysis of every recorded lie fault, and try to identify if the fault relates to a part lot-wise or make-wise.

The current data points to insulator failure being the single largest root-cause. Experience shows that pre-monsoon preventive maintenance is most effective. The use of polymer insulators in 86 lines led to the trippings drop from 172 to only 4. The next presentation, on Probable causes of failure of the Transmission Line Towers, was by Mr Gopal Ji, AGM, PGCIL. He stated that PGCIL has faced 130 tower failures since 1993. Most were of suspension towers. The analysis of the causes gives the sources as: Hardware, Nut/ Bolts, Fastners Insulator string breakage Theft of metal members/ sabotage by bad eliments Natural disasters Metal corrosion Design defects

Mr Gopal Ji explained in detail the role of wind in the design of the towers. The guidelines on this account have changed. So also has changed the wind map of the country, affecting the design parameters. PGCIL has identified the affected towers and is working to strengthen them. The presentation by Mr Benoit, Area Manager, CATU, was in two parts with the headings Introduction on Electrical Maintenance Operation & Safety while working on live Sub-stations and Lines and Minimum Personal Protective Equipment & Accessories for working on Live Sub-stations, Transmission Lines and Poles: Respect of IEC Norms & Recommendations. Mr Benoit took the subject in depth, listing the hazards in electrical maintenance and describing the different scenarios. As pointed out by him, electrical accident has effects, e.g., Heating, Pressure or Explosion, Luminous output or flash, and Ionization. The prevention of accident can be effected by maintaining a safe distance, by switching off power, and by isolating the risk area. The effect of an electrical accident on humans includes tingling, shock, contraction and more. Mr Benoit advised use of Personal Protective Equipment and following the mandated safety procedure for accident avoidance. In the second presentation, Mr Benoit gave an overview of the services and the products in the portfolio of his company. He gave graphic description of the use equipment, e.g., Gloves. Boots, Stools, Mat, Voltage Detector, Insulating Sticks, Short-circuit & Earthing Systems, etc. Mr. Bhavesh Makwana of Madhav Engineering gave a nice presentation on Hot Line Maintenance. His company provides Tools, Maintenance services and Hands-on Training in cooperation with their offshore partners. He also demonstrated a couple of case studies in support of his claims. His portfolio includes activities/ tools such as String Removal, Scaffolding, Washing, Conductive Suit, and more. Mr Rajeev Kumar of PGCIL gave a detailed presentation on the deployment of Emergency Restoration System (ERS). The participants showed a lot of interest in the ERS. PGCIL maintains 14 sets of ERS in different locations in the country. Each set can set up up to 12 towers in an emergency situation. The towers are pre-assembled sections, which can be fitted together at site, and supported by a set of guy-wires. The use of such towers serves to provide quick emergency support in the case of the failure of one of more towers. A tower may fail due to a natural disaster or due to some anti-social activity. PGCIL, with its 74000 circuit km of EHV & HVDC lines & around 150000 towers, is prone to such accidents. To maintain better availability of its lines, the use of ERS is necessary. While normal restoration of a tower could take up to 3 weeks, by using ERS, the line may be restored in 4-5 days, including transport time. The same ERS may be used for lines of 11 kV to 500 kV. The ERS towers are made of a light Aluminum alloy. It requires no foundation. The process of ERS deployment requires the following steps: Access the damage Clear the location or find clear space to erect ERS Collect the required parameters for the ERS Computer based Design programme Use the programme to do load analysis and check clearances Design and then locate space to locate and fix the guy lines

Mr Rajeev Kumar described the three methods available for erecting the ERS towers at site, namely, Gimble based, Crane lifting, & Winch-line method. The choice of method is as per locational requirement. PGCIL has used the ERS on 72 occasions, till date. They are willing to provide the ERS to other organizations in an emergency situation. The workshop was attended by about 80 participants from all over the country and the presentations were very much appreciated by the participants. A CD of all the presentation made during the workshop was distributed to the participants. This workshop was grand success with the guidance & excellent support by Shri Rajesh Kumar, General Manager (Engineering), Power Grid Corporation of India and National Representative in CIGRE Study Committee B2 on Overhead Lines.

SOCIETY CIGRE INDIA


CIGRE (Conseil International des Grands Rseaux lectriques - International Council on Large Electrical Systems) is one of the leading worldwide Organizations on Electric Power Systems, covering their technical, economic, environmental, organisational and regulatory aspects. CIGRE aims to: Facilitate and develop the exchange of engineering knowledge and information, between engineering personnel and technical specialists in all countries as regards generation and high voltage transmission of electricity. Add value to the knowledge and information exchanged by synthesizing state-of-the-art and world practices. Make managers, decision-makers and regulators aware of the synthesis of CIGRE's work, in the area of electric power.

Thus, CIGREs mission is to enable collection and dissemination of knowledge in its domain. An important tool to further this mission is the bi-annual Sessions held in Paris, in the later half of August of the respective year. This year the CIGRE Session 2010 is scheduled for 22.-27. August 2010. The members worldwide contribute papers describing latest innovations and experiences in the area of interest. The council selects a bouquet of papers covering the entire spectrum, for deliberations during the session. Prior to the actual session a number of specialists in the relevant areas study the papers and report the requirement of additional information/ clarifications/ enhancements there to. These questions/ comments are then distributed to the local CIGRE organisations in the member countries. CBIP, which is the National Committee of CIGRE in India, had organised this National Conference with two-fold aim. To spread the latest knowledge in this field, as per the papers being taken up at the CIGRE Session 2010, to the Indian Power Sector. To solicit the views of the Indian Power Sector on the stand to be taken by the Indian Members of the various Study Groups of CIGRE, on the queries raised, during the session.

The idea is not just to broad-base the knowledge exchange, but also to ensure presentation of the India-specific point of view to the international audience.

CIGRE has 16 study groups, each specializing in one specific domain. India has a member in each of these groups. Accordingly, CBIP/ CIGRE-India divided this three-day conference in to sections. The respective CIGRE Group member chaired the session. The participants were acquainted with the papers selected by CIGRE Group, by way of a summary presentation of each paper and the queries there to. The audience was then invited to present their views in respect of the queries, including, any India-specific issues. Over the years this format has emerged as the most effective. The participation to the conference was open to the Power Sector, irrespective of their membership of CIGRE. This enabled even the non-members to take advantage of the knowledge exchange, as well as, to contribute to the formulation of the Indian Stand-Point at the main session at Paris. With a large participation of around a hundred, and an extremely lively debate all through, the aim of this National Conference was very well achieved. All the participants deserve thanks and acknowledgement for their contribution.

The conference started with the Inaugural Session with Mr. B P Rao, CMD, BHEL, Mr N N Misra, ED, NTPCL, Dr. V.K. Garg, Chairperson, Regulatory Commission, Goa & UT and Mr V K Kanjlia, Secretary, CBIP on the Dias.

Mr P P Wahi, Director, CBIP, conducted the session. The distinguished penal lauded the aim of the conference and exhorted the participants to take advantage of the opportunity presented and contribute to the aim of the conference. After the Inaugural session came the technical sessions. These were in the given order. Study Group A1- Rotating Machines, chaired by Mr A K Gupta, GM, NTPC Ltd., with the support of Mr D K Chaturvedi, DGM, NTPC Ltd. Study Group A2 Transformers, chaired by Mr M Vijaykumaran, AREVA and supported by Mr M L Jain, EMCO. Study Group A3 High Voltage Equipment, chaired by Mr N N Misra, ED, NTPC Ltd., supported by Mr S P Hambarde, AGM, NTPC Ltd. Study Group B1 Insulated Cables, chaired by Mr Deepal Shah, Country Manager, Brugg Cables. Study Group B2 Overhead Lines, chaired by Mr Rajesh Kumar, GM, PGCIL and supported by Mr Rajeev Gandhi, CM, PGCIL. Study Group B3 Substations, chaired by Mr D Raina, GM, Tata Power, supported by Mr Maharaja, Tata Power. Mr Negi of GETCO was also present on the Dias. Study Group B5 Protection and Automation, chaired by Mr S G Patki, GM, Tata Power, with Mr M V Kini & Mr H B Mukund. Later Mr Mata Prasad also joined the panel. Study Group D1 Material or Emerging Techniques, chaired by Mr Jitin Sunder, BHEL, with Mr Seifert, LAPP Insulators, and Mata Prasad also on the dias. Study Group C2 System Operation and Control, chaired by Mr S K Soonee, CEO, POSOCO, supported by Mr Vivek Panday, PGCIL. Study Group C1 System Development & Economics, chaired by Mr Y K Sehgal, ED, PGCIL, and supported by Mr Subir Sen, DGM, PGCIL.

Study Group C6 Distributed Systems & Dispersed Generation, chaired by Mr K V S Baba, GM PGCIL, supported by Mr Dhananjay Kumar, PGCIL. Study Group D2 Information Systems & Telecommunications, Mr N S Sodha, GM, PGCIL, supported by Mr A K Mishra, DGM, PGCIL. Mr Sodha supplemented by a brief presentation on Smart Grid & Phaser Measurement. Mr Saran of PGCIL gave a small presentation on the Communication Network of PGCIL. Study Group B4 - HVDC and Power Electronics, chaired by Mr R P Sasmal, ED, PGCIL. Mr Sasmal also conducted a short tutorial on HVDC. Study Group C5 Electricity Market & Regulation, chaired by Mr S K Soonee, CEO, POSOCO, and supported by Mr S C Saxena, PGCIL. The presentation of every session is included in the Compact Disk supplied to the participants. The Summary of the papers for presentation at the CIGRE session, and the Queries are included there in. Apart from these sessions, there was an interesting and informative presentation on Composite Insulators by Mr J M Seifert, Director R&D and Quality Engineering, LAPP Insulators GmbH, Germany. Among the interesting information provided by Mr Seifert: Ceramic Insulators are in use since 1910. Silicon Surface treatment provides Hydrophobicity. Composites started in 1955, with improvements in the material continuing. The Industry Standards for Composite Insulators are in place since last 15 years. Germans like to innovate in big steps, and come out with Versions. Japanese, on the other hand, practice the Keizan technique of continuous improvement. There are two methods of producing Composite Insulators, Injection Molding or Extrusion. The Composite Insulators are not to be cleaned, as the Hydrophobicity is transferred to the deposited pollution layer. Cleaning would destroy this property. At higher voltages, the Glass or Ceramic Insulator would be 50% or more long, when compared to a Composite Insulator.

Mr P P Wahi, Director, CBIP, appealed to the participants to take up membership of CIGRE and/ or CBIP, in the interest of spreading the technology related information to a wider audience. In his support he made a presentation on CIGRE and CBIP. All the sessions invited keen contribution by the participants. They were interested in understanding the new technology presented and readily gave their views on the observations contained in the papers. Many interesting cross debates took place, at times going much beyond the scope of the CIGRE papers. Some of the issues taken up for debate included: Life-time management of old machines. PDM for Generators & Transformers. Guidelines for the installation of filters in the old machines. Hydrogen cooled Machines. Use of Transformers much beyond their project life. Use of FO sensors for temperature/ thermal event detection. Damage to 400 kV cable due to wrong transportation. Shortage of Supervisory Experts. Bird-pecking on Composite Insulators. Gas Insulated Transmission Line vs Cable. Suggested use of Numerical Relays in the place of Protection Relays. Need to re-look the Substation clearances, in view of the voltage up-conversions. Use of IEC 61850 leading to reduction in cabling at the substation. The suggested use of PMUs, while the analysis technology is lacking. 0 The limit on Composite Insulator temperature to max. 55 C, even as the conductor temperature rises to over 0 200 C. The requirement to integrate every new station with the State Estimator. The need to measure temperature and humidity at every station. In view of the large-scale interest created in the proceedings of the conference, participants felt that the three-day period allotted was on the lower side, and should be enhanced in future. M/s NTPC Ltd, BHEL and Power System Operation Corporation (POSOCO) were the Co-organiser and M/s Reliance Power Transmission Limited were the co-sponsor for the conference. Total 125 professionals participated in the conference.