Siemens Wind Power

Primavera From 0 1835 licenses in 3 years

Siemens AG 2011. All rights reserved.

Siemens Wind Power Facts!


Siemens Wind Power facts

One of the worlds leading suppliers of wind power solutions Installed Base: > 9,600 turbines with > 13,400 MW capacity1) Installed: 2,300 MW in 2010 7,800 employees globally Record order backlog of ~ 11 billion Revenue in 2010: ~ 3,2 billion No. 1 in offshore wind power
1) June 2011

Page 2

Siemens AG 2011. All rights reserved.

Primavera@Wind
Implementation of Primavera in Siemens Wind Power

The i ht Th right project and th right resources at th right ti ! j t d the i ht t the i ht time!

Primavera users 2000 1800 1600 1400 1200 1000 800 600 400 200 0 2008 2009 2010 2011 Primavera users

Page 3

Siemens AG 2011. All rights reserved.

Starting point Winter 2007/2008


Management in Wind Farm installation area have an issue:
The number of wind Farm installation projects is growing and the complexity is increasing

A tool is needed to get overview of:


Schedule Resources Cost

Our CEO Knew Primavera so that was chosen:


60 licenses were bought WestSoft was engaged to implement

Ready to Go-Live in autumn 2008!


Page 4 Siemens AG 2011. All rights reserved.

Step 2 What about the rest?


PM area goes to IT to get IT infrastructure in place.. At the same time the engineering department realize they also need a project , projecttask and ressource management tool, and approach IT

It gets political!

Page 5

Siemens AG 2011. All rights reserved.

Business case Easy

It is essential for both Engineering and Siemens Wind Power as such to be able to effectively control all tasks projects project portfolios and resources in tasks, projects, Engineering The current and future growth presents a challenge in continued efficiency per employee. The efficiency improvement is estimated to be at least 5%, which results in a ROI as defined below: Engineering salary budget FY09 Cost P M th C t Pr Month Increase of effectiveness(%) Saved due to higher effectiveness (month) xxx xxx 5 +500 Mio DKR pr. Month

Page 6

Siemens AG 2011. All rights reserved.

Choose tool: Not that easy

The IT department wants to ensure the right tool is selected. An investigation project is started to investigate SAP/PS MSP and Primavera SAP/PS, Primavera. During the investogatin one more department joined the team: Global Blades Now comes a period of workshops, Product presentations, discussions etc. MSP was quickly ruled out 26 pages of investigation report was created fi ti ti t t d 8 month later the conclusion!

Page 7

Siemens AG 2011. All rights reserved.

Primavera is the preferred platform!

Critical requirements: Support increased day-to-day project management Provide standard project execution structure for planning & monitoring in Projects & Logistics for all regions Enable capacity planning and resource forecasting for equipment/manpower/components across projects Support long-term planning of cross-project uncertainties through what-if scenarios (Not Possible in SAP/PS)

Page 8

Siemens AG 2011. All rights reserved.

Project

The project was approved in may 2009 Primavera specialist was hired Westsoft was involved Get Going!

Page 9

Siemens AG 2011. All rights reserved.

Scope

Engineering: Manpower ressource Management for R&D Projects p g j Task Management in the departments Project Management tool for +50 PMs Time Registration for 600 engineers Overall project schedule for R&D projects using templates Portfolio Overview Global blades Portfolio Overview for internal projects Time Registrati0n on project activities for 120 employees PM tool for +15 PMs Projects & Logistics Project Scheduling tool Critical ressource Management (vessels, cranes.)
Page 10 Siemens AG 2011. All rights reserved.

Scope of work

To create templates for all departments and project types Definition of Roles and Responsibilities IT Infrastructure

Page 11

Siemens AG 2011. All rights reserved.

International Scope
Internationalization - Siemens facilities and offices

Keele (UK) Sheffield (UK) Den Haag (NL) Aachen (DE) Boulder
(Wind & aerodynamics) (mechanics, generators grid, offshore)

Ft. Madison
(Blades)

Madrid Cairo India


(planned)

Beijing

Hutchinson
(nacelle)

Houston Mexico City

Orlando

Aalborg (blades prod. & R&D blade design, planned for Quantum Blade and testing)

Shanghai (blades/ nacelle / hub/ under construction)

Singapore

Engesvang
(blades)

Sao Paolo (planned) Santiago Melbourne

lgod
(hubs)

Brande
(Global HQ)

Hamburg Bremen
(Europe HQ)

Taastrup
(Aerodynamics, structural dynamics, electrical systems)

Supply chain

Sales hubs

Other sales

R&D

Page 12

Siemens AG 2011. All rights reserved.

Timeline

Projects & Logistics area were approved to continue may 2009 and got the infrastructure up and running running. Important milestones: April 1st 2010 all Wind Farm installation projects are included! October 1st. all projects are updated with progress

Engineering and Global Blades: Go-live: april 2010 G li il

Page 13

Siemens AG 2011. All rights reserved.

Challenges!

Siemens AG 2011. All rights reserved.

Growth!
While we were trying to improve the way we work, the company still grows When Primavera started we were 3300 emplyees. Now: +7500 More people are hired than we can manage to get trained. After 3 years, we still have many new and unexperienced users !!! We still Grow!
Employees (by end of fiscal year)
Average growth (05-10): 42% p.a.
Global Denmark 2,200 400 1,800 FY2006 3,300 800 2,500 FY2007 5,300 1,400 3,900 5,500 1,700 3,800 4,200 7,000 2,800

1,200 1,150

50

FY2005

FY2008

FY2009

FY2010

Page 15

Siemens AG 2011. All rights reserved.

Resistance

Management
What do we need that for? Just give me a spreadsheet!

Employees
Primavera is awfull! Double time registrations Planning: I do not need that!

Customers
Using other systems!

Page 16

Siemens AG 2011. All rights reserved.

Primavera Support

We underestimated the requirements for supporting staff pp g We did not manage to get enough people on board in time!

Primavera users 2000 1800 1600 1400 1200 1000 800 600 400 200 Primavera users

Problems: Training Templates Technical isues

0 2008 2009 2010 2011

Support S t 14 12 10

We still miss skilled staff

8 Support 6 4 2 0 2008 2009 2010 2011

Page 17

Siemens AG 2011. All rights reserved.

IT infrastructure

We were first movers on a large number of users on the web interface. Needed some rework and specialist involvement involvement. Performance decreases with the increased number of users. Continued development by IT is required

Page 18

Siemens AG 2011. All rights reserved.

Wrong assumption

Planning and scheduling: PMs must do that! No! Americas knew that and hired planners. Now we are hiring planners in the rest of the world

Page 19

Siemens AG 2011. All rights reserved.

Other experiences

Keeping projects updated with progress is not to be underestimated! Monitoring and follow up is critical Roles and Responsibilities must be clearly defined It must be easy to use a tool, or it will not be used Documentaion is critical! You Y must plan t develop your support staff yourself, so prepare in time t l to d l t t ff lf i ti

Page 20

Siemens AG 2011. All rights reserved.

10

Why did we succeed?

Stubbornness and dedication Good people! Support from WestSoft Urgent needs for support to headcount planning process during financial crisis!

Page 21

Siemens AG 2011. All rights reserved.

Todays status

1835 users totally spread across all of our organisation Primavera is widely accepted and Management have realized the potential Increased demands from the market require more and better project- and portfolio Management Ongoing changes to the organisation forces continued selling

It was the right thing to do!

Page 22

Siemens AG 2011. All rights reserved.

11

Thank you !
Lene Golriz Siemens Wind Power Offshore +45-30375571 Lene.Golriz@siemens.com @