Você está na página 1de 5

Owner: KPIC

Costumer: Namvaran

Stack-4201
namvaran Consulting Engineers
Managers

Location: Kermanshah- Iran


Document No.: SEC-PJ045-ST-IFP-0010

K.P.I.C.

SEC-Project No.: PJ045

WELDING VISUAL INSPECTION PROCEDURE

Purchaser review and comment shall not be assumed to indicate either responsibility or liability f or accuracy and completenes of this document or to alter any contractual terms and conditions. Item Numbers: S-4201 Purchasers Disposition No Comments Comments as Noted Rejected

Date

Name

Initial

SDRL Code A 60

Purchase Order No. I-41D1-B213-01

Document No.

Rev. 02

SEC-PJ045-ST-IFP-0010

02 01 Rev.

02.08.2004 20.06.2004 Issue Date

COMMENT AS NOTED ISSUED FOR COMMENT


DESCRIPTION

M.Z H.H
PRD. BY

M.Z M.Z
CHKD. BY

M.S.KH M.S.KH
APPR. BY

DISCIPLINE

Quality Assurance System Welding Visual Inspesction Procedure

Project No. PJ.045

Rev. 02

Date: 02.08.2004 Sheet 2 of 5

Contents: 1- PURPOSE 2- SCOPE 3- RESPONSIBILITY 4- REFERANCE STANDARD 5- DESCRIPTION 6- ACCEPTANCE STANDARD 7- TEST REPORT 8- DOCUMENTION

Quality Assurance System Welding Visual Inspesction Procedure

Project No. PJ.045

Rev. 02

Date: 02.08.2004 Sheet 3 of 5

WELDING VISUAL INSPECTION PROCEDURE

1) PURPOSE This procedure describes the inspection method for visual inspection of welded joints. 2) SCOPE The following procedure covers the general requirement for welding visual inspection of steel structure parts and header boxes relevant to air cooled heat exchangers.

3) RESPONSIBILITY All welded joints shall be inspect and reported by qualified welding inspector under supervision of quality control manager.

4) REFERENCE STANDARD i) ii) iii) Project specification ASME VIII & ASME V API 661

5) DESCRIPTION 5.1- All joint preparation shall be control by welding inspector before commencement of any welding activity. 5.2- The bevel preparation shall be according to welding details and project drawing or specification, and also the weld seams to be cleaned and free of oil, dust and other contamination before performance of welding activity. 5.3- Butt weld shall be aligned and retained in position during welding. Misalignment will be within the tolerances as per ASME VIII. Div.1 UW-31 5.4- Component may be assembled by bars, clamps, tack welds or other suitable methods. Tack welding of base metal outside area interested by welding shall be avoided whenever possible. Material used for tack welding shall be compatible with base metal.

Quality Assurance System Welding Visual Inspesction Procedure 6) ACCEPTANCE STANDARD

Project No. PJ.045

Rev. 02

Date: 02.08.2004 Sheet 4 of 5

6.1- Surface of welded joints shall be sufficiently uniform, free from coarses, ripples, sharp corners, interpass valleys and shall be suitable for performance of required NDE. The following acceptance criteria apply: ASME sec. VIII Div 1- ASME V and project specification. 6.2-. Cracks, lack of fusion, lack of penetration: Not acceptable 6.3- Undercuts: Max. depth 0.8 mm or 10% of base metal thickness (whichever is less) without however reducing thickness below minimum design thickness. 6.4- Reinforcement: The indication of ASME sec. VIII Div. 1- UW-35 shall be applied. For other defects like porosity, slags, etc. refer to relevant clauses in the applicable code. 7) TEST REPORT All joints shall be inspected visually by manufacturer welding inspector and relevant report shall submit to client authorized inspector for approval.(Attachment 1). 8) DOCUMENTATION Original certificates shall remain in quality control department. One copy to be submitted to client inspector.

Quality Assurance System Welding Visual Inspesction Procedure

Project No. PJ.045

Rev. 02

Date: 02.08.2004 Sheet 5 of 5

SR. NO.

HEADER NO.

JOINT NO.

W. STAMP

RESULT

REMARK

NOTE:

Você também pode gostar