Action Taken Report Action Taken Report in respect of No. D/200/EO(C-II) dt. 5.9.

11 regarding E-mail Complaint against laying of tiles in flat No. B-10, Palika Niketan, NDMC flats, R.K. Puram, New Delhi. S.No. Defects/Requirement Present Status 1. Bathroom/Toilet Doors are to be change. 2. Kitchen dish wash sink, the old The works has been completed. The one was taken away by the letter of applicant for confirmation is contractors and still not installed enclosed herewith. the new one. 3. Toilet floor is also waiting for tiles and the commode to be changed.

EE(BM-II)

AE-III(BM-II)

SE(BM-I)

Placed below is the list of the Charge incusing of files, F.D.Rs/DDs/Bankers Cheques and Peon Books which are to be handed over to Smt. Asha Arora, Sr. Asstt. (list attached). The remaining files are to be checked. Keys of the almirah are also attached with the list.

Submitted for information please.

A.A.O (BM-II)

H.A (BM-II)

Subject : - Cleaning of Sewer lines at Bapu Dham Housing Complex. It has been reported by the residents of block No. 1 to 3 & 11 to 13 at Bapu Dham Housing Complex that the sewer lines of these blocks are not working properly. The area was inspected by the undersigned and the labour has been deputed for cleaning the sewer lines but it has been observed that the sewer line could not be cleaned even all efforts made by the field staff of Bapu Dham Service Centre. The matter was discussed on phone with Er. M.A Khan, EE(Sewerage) and Er. Iswar Singh, A.E (Sewerage) incharge of Malcha Marg service Centre for cleaning the Sewer lines. Accordingly, as directed by EE (Sewerage), EE (BM-II) is requested that the matter may be forwarded to EE (Sewerage) for cleaning the sewer lines at Bapu Dham Housing Complex by engaging jet pressure/suction machine.

EE(BM-II)

A.E-II(BM-II)

Sub: Improvement to M & CWC, Sarojini Nagar. SH: Improvement works at M & CWC, Sarojini Nagar. Agency: Sh. Navin Kumar Gupta. Payment of Pre-Final Bill PUC is a letter dated 25.10.2011 from Sh. Navin Kumar Gupta contractor for the above cited work. He has stated in his letter that although he had completed the work satisfactorily in May 2011, yet a lot of payment is lying pending with the Department. He has further stated that he has to conduct the marriage of his son in the month of November 2011 (marriage invitation card enclosed) for which he is hard pressed and has requested for release of some amount urgently as pre-final bill for financial relief. Chief Engineer (C-II) has given remarks on the above stated letter:For immediate action please. Please put up ATR. In this regard, it is stated that the total expenditure on his work has exceeded more than the permissible limit i.e. more than 10 % of the approved P.E. The revised estimate of the work has already6 been prepared and submitted for scrutiny. It will take quite some time for the finalization/approval of the revised estimate from the Council. It is therefore, proposed to make payment of pre-final bill to the contractor after necessary scrutiny, to give financial relief to him in anticipation of approval of the revised estimate. The payment to the contactor will be made in anticipation of re-appropriation of funds from the saving of the Head D.4.12.1 (412400), Scheme no. 62, and Name of work Improvement works at Palika Niketan, R.K. Puram with saving of Rs. 30.00 Lacs against Budget Provision of Rs. 165.00 Lacs for Financial Year 2011-12. Submitted for consideration please.

AE-I(BM-II) EE(BM-II), Civil

Sub:- Payment of Telephone No. 23369904.

A bill amounting to Rs. 1384/- (Rs. One Thousand Three Hundred Eighty Four Only) vide bill No. 202545566 dt. 09.11.2011 during the period of 01.10.2011 to 31.10.2011 with due date 30.11.2011 has been received for its payment in r/o the above telephone which is installed in the office of EE(BM-II) S.B.S Place Gole Market.

A contingent bill amounting to Rs. 1384/- (Rs. One Thousand Three Hundred Eighty Four Only) has been prepared and put up for pass and payment before due date.

A.A.O(BM-II) EE (BM-II) Ref. above :C-Bill amounting to Rs. 1384/- (Rs. One Thousand Three Hundred Eighty Four Only) in f/o M.T.N.L in r/o EE(BM-II) S.B.S Gole Market New Delhi. Telephone No. 23369904 has been based as under:Previous Meter & Reading 168113 01.10.2011 Current meter reading & Date 169090 31.10.2011 Metered Call 977 Free Call 60

Net calls Chargeable 917

Call Charges Monthly Service S/tax+Edu. Cess Charges 1004.40 250 129.20

AAO (BM-II)

EE(BM-II)

AO(W-II)

ACTION TAKEN REPORT Sub : Issues & challenges for 12th five year Plan (2012-17) Ref.: (i) F.129/HA/Fin.(B)/ 1762/ D dated 28.10.11 & (ii) 4844/CE(C ) II dated 31.12.11 (iii) D/255/EO (C) - II dt. 03.11.2011 As regards the Action Taken Report in reference to above cited subject, the following projects / schemes are not pertaining to BM-II division. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Shelters J. J. Clusters Rehabilitation of J. J. Cluster Households J. J. Resettlement Colonies Slum Rehabilitation Colonies Unauthorized Regularized Colonies Unauthorized Colonies Urbanized Villages Slum Katras Trans Yamuna Area Development Board Shahjahanabad Redevelopment Corporation Contribution to NCR Planning Board JNNURM Conservancy & Sanitation Services Development of Parks, Community Centres, Approved Colonies.

At present there is no space available to construct new Community Centre & Hostels in BM-II Div.

Submitted please.

(Er. P. K. CHUGH) Executive Engineer (BM-II)

ACTION TAKEN REPORT Sub : Issues & challenges for 12th five year Plan (2012-17) Ref.: (i) F.129/HA/Fin.(B)/ 1762/ D dated 28.10.11 & (ii) 4844/CE(C ) II dated 31.12.11 (iii) D/255/EO (C) - II dt. 03.11.2011 As regards the Action Taken Report in reference to above cited subject, the following projects / schemes are not pertaining to BM-I division. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Shelters J. J. Clusters Rehabilitation of J. J. Cluster Households J. J. Resettlement Colonies Slum Rehabilitation Colonies Unauthorized Regularized Colonies Unauthorized Colonies Urbanized Villages Slum Katras Trans Yamuna Area Development Board Shahjahanabad Redevelopment Corporation Contribution to NCR Planning Board JNNURM Conservancy & Sanitation Services Development of Parks, Community Centres, Approved Colonies.

At present there is no space available to construct new Community Centre & Hostels in BM-I Div.

Submitted please.

Executive Engineer (BM-I)