Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

[A true translation from the Polish language]

DEVELOPMENT PLAN
for Meeting Current and Future Electricity Demand in the Period 2010 - 2025 Update for 2012-2016

EXCERPT
Konstancin - Jeziorna, July 2011

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

CONTENTS
1. 2. 3. 4. 5. 6. 7. INTRODUCTION ..............................................................................................................2 PLANNING PERIOD OF 2012-2016 ................................................................................2 FORECASTED POWER AND ELECTRICITY DEMAND COVERAGE ......................5 EFFECTS OF UPDATED TGDP IMPLEMENTATION ...................................................9 SUMMARY .....................................................................................................................10 GRID DIAGRAMS .........................................................................................................11 LIST OF VENTURES ......................................................................................................13

List of abbreviations TGDP Development Plan for Meeting Current and Future Electricity Demand in the Period 2010 - 2025 URE Polish Energy Regulatory Office EU European Union PP Power Plant CHP Utility Combined Heat and Power Plant CU Coal Unit GS Combine Cycle Unit WF Wind Farm NPS National Power System NTS National Transmission System DSO Distribution System Operator IT Information Technology MV Medium Voltage system LV Low Voltage system RES Renewable Energy Sources GDP Gross Domestic Product IRiESP - Instruction of Transmission System Operation and Maintenance NAP National Action Plan EP 2030 Energy Policy of Poland until 2030, November 2009 ENTSOE European Network of Transmission System Operators for Electricity ATR Autotransformer APKO Automatic Anti-Swinging and Overloading Protection System SE - Substation OPGW Optical Power Ground Wire

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

1. INTRODUCTION
In view of: 1. Approval by President of the Polish Energy Regulatory Office (URE) of the Draft Development Plan for Meeting Current and Future Electricity Demand in the Period 2010 - 2025 (hereinafter TGDP) with respect to the year 2010, submitted by PSE Operator S.A. in 2009 (document DTA-431-23(48)/2009/M of 29.12.2009) 2. Approval by President of the Energy Regulatory Authority of the Draft Development Plan for Meeting Current and Future Electricity Demand in the Period 2010 - 2025 (hereinafter A1 TGDP) with respect to the year 2011, submitted by PSE Operator S.A. in 2010 (document DTA-4310-44(18)/2010/M of 21.12.2010). 3. Approval by President of the Energy Regulatory Authority of the Draft Development Plan for Meeting Current and Future Electricity Demand in the Period 2010 - 2025 (hereinafter A2 TGDP) with respect to the years 2012 to 2016, submitted by PSE Operator S.A. in 2011 (document DTA-4310-32(18)/2011/M of 29.06.2011) In fulfilling the obligation stipulated in Sec. III.E.1. Use of IRiESP (Instruction of Transmission System Operation and Maintenance), PSE Operator S.A. hereby publishes an excerpt from Draft Update to Development Plan for meeting current and future electricity demand in the period 2010 2025 with respect to the years 2012-2016 approved by the President of the Energy Regulatory Authority in 2011 The general directions of development of the transmission grid, as presented in the draft update of TGDP submitted for approval in 2011, are in line with TGDP. The investment plans described in the present update, resulting from the approved TGDP for 2010-2025, were notified with regard to the most essential central planning documents: the draft National Spatial Management Concept, provincial spatial management plans and the program of government ventures aimed at the development of electrical power transmission grid.

2. PLANNING PERIOD OF 2012-2016


The planning period covers investment ventures required to execute the provisions of connection contracts for conventional units. The list of connection agreements concluded by PSE Operator S.A. for conventional units is shown in Table 1.
Table 1 - List of Conventional Units (including gas and steam units) which have signed agreements on connection to the transmission grid
Item 1 2 3 4 5 6 7 Investment PP Bechatw 1000 MW Unit PP Kozienice CHP Siekierki 1000 MW Unit PP Ostroka C GS Unit Wocawek 2x900 MW Units PP Opole GS Unit CHP Stalowa Wola Applicant PGE Elektrownia Bechatw S.A. Elektrownia Kozienice S.A. Vattenfall Heat Poland S.A. ENERGA Elektrownie Ostroka S.A. Polski Koncern Naftowy ORLEN S.A. PGE Elektrownia Opole S.A. Elektrociepownia Stalowa Wola S.A. Type CU CU CU CU GS CU GS Date of conclusion 2005-04-01 2008-12-23 2009-11-20 2010-02-02 2010-03-09 2010-03-31 2011-06-16 Total: Power, MW 858 1000 480 1000 500 1800 422 6060 MW

The fulfilment by PSE Operator S.A. of the investment ventures for connection of new conventional sources is exposed to certain risks due to possible abandonment by the investor
2

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

of implementation of the venture or postponement of its construction. Therefore, the schedule for completion of a venture resulting from facility connection may be changed or, in an extreme situation, may be discontinued if the investor withdraws from the construction project. Just like in case of conventional sources, in the planning period of 2012 - 2016, PSE Operator S.A. focuses on creating conditions for connection and evacuation of power from RES (chiefly wind farms). The list of connection agreements concluded by PSE Operator S.A. for wind farms is shown in Table 2.
Table 2 List of Wind Farms which have signed a Transmission Grid Connection Agreement
Item 1 2 3 4 5 6 7 8 9 Investment Kukowo-Dargoleza WF Chwiram WF Osieki WF Choczewo WF Darowo WF Potgowo WF Supsk WF (Wierzbicin II) Malechowo WF Pelplin WF Applicant Megawatt Polska Sp. z o.o. Megawatt NW Sp. z o.o. Elektrownia Wiatrowa Gniewino Sp. z o.o. WINDCOM Sp. z o.o. Wind Invest Sp. z o.o. EWG Supsk Sp. z o.o. Green Power Polska Sp. z o.o. EWG Energia Sp. z o.o. WIND Sp. z o.o. Type WF WF WF WF WF WF WF WF WF Date of conclusion 2007-07-18 2010-03-08 2010-03-10 2010-05-05 2010-06-14 2010-08-20 2010-08-20 2011-05-16 2011-06-20 Total: Power, MW 240 120 90 111 250 320 240 160 190 1721 MW

Distribution of RES planned to be connected within Poland is shown in Diagram 1. The diagram shows distribution of power quantities applied for wind farm constructions, broken down by characteristic areas of the country, including: specific connection conditions and connection agreements signed.

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

Diagram 1 Distribution of RES planned to be connected within Poland

Key

Conditions issued for wind farm connection to NTS Contracts signed for wind farm connection to NTS

The current status with respect to connection agreement signed and conditions issued for wind farm connection to NTS

Diagram 1 illustrates that the main group of investors planning to construct wind farms are located in the northern and western parts of Poland, but the connection contracts signed apply to the northern part only. PSE Operator S.A. specified connection conditions for wind farms for 4462.1 MW and signed connection contract for 1721 MW. It may mean that, in total, wind farms of 6183,1 MW will be connected to the transmission grid. In this respect, it should also be emphasized that PSE Operator S.A. agreed with DSO the conditions of connection to 110 kV grid for wind farms to the total power of ca. 9150 MW, of which more than 3000 MW applies to northern Poland. Additionally, also the wind farms operating and planned to be connected to MV and LV network should be taken into account, estimated at more than 2500 MW. From today's point of view it is difficult to determine how realistic construction of all the projects is, but their completion in accordance with the applications submitted by investors would lead to the ratios required by the EU law regarding the obligation to purchase renewable energy imposed on Poland being exceeded at least twice.

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

PSE Operator S.A. has planned to develop the transmission grid in the northern part of Poland in order to evacuate the forecasted power surpluses from wind farms to the south, which should also enable meeting the obligations under the national energy policy. Construction of technical infrastructure required for managing its operation and ensuring transmission system safety will also be continued simultaneously with the extension of the transmission grid. It applies amongst other things to: - construction of reactive power compensation systems in accordance with the system requirements, - construction of monitoring systems for management of the operation of the grid and its components, - construction of management system for NPS operation, - construction of systems for energy market management in NPS, - construction of other telecommunication and IT systems supporting the core operator activity. The actions undertaken with the aim of extending/enhancement of the transmission grid were in most cases agreed with DSO as actions aimed to extend the closed 400, 220 and 110kV grid. In more distant future, actions are to be taken to prepare a closed grid development plan together with DSO. The planning process takes into account the objectives and directions of activities indicated in the strategic national documents, and in the European Union law. In this respect, the objectives set forth in the Polish Energy Policy were given priority: - increased safety of electricity supplies, - diversification of electricity generation structure by introduction of nuclear power - development of the use of renewable energy sources, - improvement of energy efficiency, - development of common electricity market by cross-border interconnections, - limitation of power sector impact upon the environment. Additionally, the climate package objectives were also taken into consideration.

3. FORECASTED POWER AND ELECTRICITY DEMAND COVERAGE


The forecasts for power and electricity demand coverage remain unchanged and are compliant with the TGDP submitted and approved for 2010-2025. In the period of economic down-turn in Poland, no GDP decrease was observed, and the drop in electricity consumption in 2009 was compensated for as early as 2010.

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

Diagram 2. Peak demand forecast according to Forecasted Scenario in MW


50 000

40 000

30 000

MW
20 000

10 000

0 2005 2010 2015 2020 2025

Years

Annual average forecasted growth of peak capacity demand in 2011-2025 will be 2.2%. Diagram 3 Electricity demand forecast according to Forecasted Scenario in TWh
400,0

300,0

TWh

200,0

100,0

0,0 2005 2010 2015 Years 2020 2025

The average annual forecasted growth of electricity demand in 2011 -2025 will be 2.2 %. Forecasted growth of heat capacity from new utility plants and RES (wind farms) is shown in Diagrams 4 and 5.

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

Diagram 4. Forecasted growth of heat capacity from new utility plants


12000
Nuclear power plants

10000
New capacities in new locations

8000

New capacities in existing power plants

[MW]

6000

4000

2000

0 2011 2012 2013 2014


Year

2015

2020

2025

Diagram 5. Forecast of new renewable sources development


10000
Biomass/Biogas

8000

Hydro Wind

[MW]

6000

4000

2000

0 2010 2015 2020 2025

Year
Schedule of changes to RES maximum output capacity is based on the data of the National Action Plan with respect to energy from renewable sources (NAP) - for the years 2011-2020 and information contained in EP 2030 - for the years 2021-2025. Assumptions for anticipated cross-border exchange volumes have not been changed. Nevertheless, it should be emphasized that with respect to interconnections with the Ukrainian system (750 kV line) and Belarusian one (construction of 400 kV Narew Ro line), the deadline for their completion depends on carrying out the procedures for making the
7

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

transmission capacities available and arrangements with the foreign partner. Additionally, the increase of export capacities regarding the interconnection with Sweden depends on expansion of the NTS in the north of Poland and construction of new generation sources in this area. The increase of import and export potential of NPS are based on the following planned investment ventures connected with extension of cross-border interconnections: A. Asynchronous: Construction of Poland-Lithuania interconnection, to include double circuit 400 kV line Ek (PL) Alytus (LT) with the required enhancement of the Polish and Lithuanian transmission system. Power exchange will be performed through direct current links on Lithuanian side in Alytus substation. The connection is planned to be started up in 2015 (Phase I) and conditions for target volume of exchange are planned to be accomplished around 2020 (Phase II). Re-starting the Poland-Ukraine interconnection at the voltage of 750 kV. Two cooperation variants are taken into consideration: through direct current links of 2x600 MW to be installed in Rzeszw substation or in the form of parallel operation of the Ukrainian system with ENTSOE. The connection is planned to be started up in 2015 at the earliest. Construction of Poland-Belarus interconnection, including double circuit line 400 kV Narew -Ro with DC link on the Belarusian side in Ro substation. The inactive 220 kV Biaystok - Ro line will be used to construct a new line. The connection is planned to be started up in 2015 at the earliest. B. Synchronous Construction of transformer phase shifters on the existing Poland-Germany interconnections and connecting the Krajnik-Vierraden 400 kV line. Start-up of the phase shifters is planned for 2014. Construction of third Poland-Germany interconnection includes construction of double circuit 400 kV line connecting a substation in the western part of NTS with Eisenhuttenstadt substation on the side of Germany. The connection is planned to be started up in 2020 at he earliest.

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

4. EFFECTS OF UPDATED TGDP IMPLEMENTATION


The tables and diagrams below show effects of ventures included in the said TGDP update.
Table 3. Effects of investment ventures for transmission lines in the period 2012-2016

Diagram 6. Effects of investment ventures for 400 kV transmission lines


1400 1250 1200 1000 800 km 600 400 200 76 0 2012 2013 2014 Year new modernized 2015 2016 127 124 167 722 1148 1098 1377 1250

Diagram 7. Effects of investment ventures for 220 kV transmission grids:


900 800 700 600 500 km 400 300 200 100 0 0 2012 2013 2014 Year new modernized 2015 2016 83 0 83 1 37 115 470 734 842

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

Table 4. Effects of investment ventures with respect to ATR installation in [MVA]

Diagram 8. Effects of investment ventures with respect to ATR installation in [MVA]


9000 8000 7000
6150 8610

6000 MVA 5000 4000


3030

5820

3345 2795 2000 2000 2795 2500

3000 2000 1000


0 0 1800 1000 1925

0 2012 2013 2014 Year 400/220 400/110 220/110 2015 2016

5. SUMMARY
Taking into consideration the external conditions and obligations imposed under the Energy Law, PSE Operator S.A. should have the capacity to implement the ventures included in the plan and to provide funds on a long-term basis from its own resources (tariffs) and from external sources of financing. Ensuring adequate financing for the planned investment outlays is a pre-condition to implementing the planned investments aimed at ensuring national energy safety. The Polish legal system regulating the investment processes of line facilities calls for changes and initiatives to make it more efficient encounter numerous obstacles. For these reasons the grid investments required to ensure the safety of NPS are either not implemented or implemented with substantial delays. It poses considerable risk of Poland and PSE Operator not being able to meet the obligations contained in the Polish Energy Policy, EU Directives, as well as the Polish Energy Law. Amendments to the current laws are necessary to eliminate the existing barriers and to enable reduction of twenty-year delays in extension/enhancement of the transmission grid.

10

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

6. GRID DIAGRAMS
Diagram 9 shows the diagram of transmission grid - as of 2011. Diagram 9. Transmission grid diagram as at 2011

400 kV temporary operating at 220 kV 450 kV DC cable

Diagram 10 shows a diagram of transmission grid with highlighted investments planned for 2012 to 2016.

11

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

Diagram 10. Transmission grid diagram in 2011


Industrial grid diagram with highlighted investments scheduled for 2012-2016

Key

400 kV temporary operating at 220 kV 450 kV DC cable Completed investment ventures Investment ventures in progress

12

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT

7. LIST OF VENTURES
The list of ventures scheduled for 2012-1016 is presented in Table 5. Table 5. List of Ventures Scheduled for 2012-2016.
Item

Venture

1
1.1. 1.1.1 1.1.2 1.2. 1.2.1 1.3. 1.3.1 1.3.2 1.3.3 1.3.4 1.4. 1.4.1 1.4.2 1.4.3 1.4.4 1.5. 1.5.1

PSE-CENTRE AREA
220/110 Ek Substation Enhancement of 220/110 kV Ek substation to include 400 kV switchgear(Phase I and II) Installation of 400/110 kV 330 MVA TR in Ek substation 400 kV oma Substation Construction of oma 400 kV substation 400/110 kV Narew Substation Enhancement of 400 kV switchgear in 400/110 kV Narew substation (for Ostroka) Enhancement of 400/110 kV Narew substation Installation of 400/110 kV 330 MVA TR in Narew substation Installation of reactor at 400 kV switchboard in Narew substation 400/220/110 kV Otarzew Substation Construction of 400/220/110 kV Otarzew substation Installation of 400/220 kV 500 MVA TR in Otarzew substation Installation of 400/220 kV 500 MVA TR in Otarzew substation Installation of 400/110 kV 330 MVA TR in Otarzew substation 220/110 Ostroka Substation Enhancement of Ostroka substation to include 400 and 110 kV switchgear and modernization of 220 kV switchboard to the extent required for connection

1.5.2

Enhancement of Ostroka substation to include 400 and 110 kV switchgear and modernization of 220 kV switchboard Installation of 400/220 kV 500 MVA TR in Ostroka substation Installation of 400/110 kV 450 MVA TR in Ostroka substation Installation of TR 220/110 kV 275 MVA in Ostroka substation (Phase III) 220/110 kV Pabianice Substation

1.5.3 1.5.4 1.5.5

1.6.1 1.6.2 1.6.3 1.7. 1.7.1 1.8. 1.8.1 1.9. 1.9.1 1.9.2

Modernization of 220/110 Pabianice substation Installation of TR 220/110 kV 275 MVA in Pabianice substation (Phase III) Installation of TR 220/110 kV 275 MVA in Pabianice substation (Phase III) 220/110 kV Piaseczno Substation Modernization and enhancement of 220 kV switchgear in 220/110 kV Piaseczno substation 400/110 kV Pock Substation Enhancement of 400/110 kV Pock substation 400/220 kV Rogowiec Substation Modernization of 400/220 kV Rogowiec substation Modernization of APKO II Phase in Rogowiec substation

13

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
1.10. 1.10.1 1.10.2 1.10.3 1.10.4 1.11. 1.11.1 1.12. 1.12.1 1.13. 1.13.1 1.14. 1.14.1 1.15. 1.15.1 1.16. 1.16.1 1.17. 1.17.1 1.18. 1.18.1 1.19. 1.19.1 1.20. 1.20.1. 1.21. 1.21.1 1.22 1.22.1 1.23. 1.23.1 1.24. 1.24.1 1.25. 1.25.1 1.26. 1.26.1 1.27. 1.27.1 1.28. 1.28.1 400/110 kV Siedlce Ujrzanw Substation Construction of 400/110 kV Siedlce Ujrzanw substation Installation of 400/110 kV 330 MVA TR in Siedlce Ujrzanw substation Enhancement of Siedlce Ujrzanw substation Installation of reactor at 400 kV switchgear in Siedlce Ujrzanw substation 400 or 400/110 kV Stanisaww Substation Construction of 400 kV or 400/110 kV Stanisaww substation 220/110 kV Warszawa Siekierki Substation Construction of 220/110 kV Warszawa Siekierki substation 400 kV Ek - Polish Border line (direction: Alytus) Construction of 400 kV Ek - Polish Border line (direction: Alytus) 400 kV Ek - oma Line Construction of 400 kV Ek oma line 400 kV Kozienice - Otarzew Line Construction of 400 kV Kozienice Otarzew line 400 kV Kozienice - Siedlce Ujrzanw Line Construction of 400 kV Kozienice - Siedlce Ujrzanw line 220 kV Kozienice - Mory/Piaseczno Line Modernization of 220 kV Kozienice Mory/Piaseczno line Phase II 400 kV Miosna - Siedlce Ujrzanw Line Construction of 400 kV Miosna - Siedlce Ujrzanw line 400 kV Miosna - Mociska - Rogowiec Line Modernization of 400 kV Miosna Mociska Rogowiec line with power connection to Otarzew substation 400 kV Miosna - Pock Line Modernization of 400 kV Miosna Pock line 400 kV Narew - oma - Ostroka Line Construction of 400 kV Narew - oma Ostroka line 400 kV Ostroka - Stanisaww Line Construction of 400 kV Ostroka - Stanisaww line 400 kV Ostroka - Olsztyn Mtki Line Construction of 400 kV Ostroka - Olsztyn Mtki line 220 kV Janw - Rogowiec Line Modernization of 220 kV Janw Rogowiec line 220 kV Piotrkw - Rogowiec Line Modernization of 220 kV Piotrkw Rogowiec line 220 kV Pabianice - Rogowiec Line Modernization of 220 kV Pabianice Rogowiec line 220 kV Warszawa Siekierki - Piaseczno Cable Line Construction of 220 kV Warszawa Siekierki Piaseczno cable line 220 kV Janw - Piotrkw Line Modernization of 220 kV Janw - Piotrkw line

14

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
1.29. 1.29.1 220 kV Janw - Zgierz - Adamw Line Modernization of 220 kV Janw - Zgierz - Adamw line

2
2.1. 2.1.1 2.2. 2.2.1 2.3. 2.3.1 2.4. 2.4.1

PSE EAST AREA


220/110 kV Abramowice Substation Modernization (Enhancement) of 220/110 kV Abramowice substation 400/220/110 kV Chem Substation Enhancement of Chem substation to include 400 kV switchgear 220/110 kV Kielce Piaski Substation Enhancement of 220/110 kV Kielce Piaski substation 400/220/110 kV Kozienice Substation Thermal modernization of buildings at the depot facilities at Kozienice substation and modernization of access road to the depot facilities Enhancement of 400/220/110 kV Kozienice substation to connect Unit 11 of Kozienice Power Plant Enhancement of 400/220/110 kV Kozienice substation 400/110 kV Lublin System Substation Enhancement of 400/110 kV Lublin System substation 400/110 kV Ostrowiec Substation Enhancement and modernization of the station and installation of AT 400/110 kV MVA in Ostrowiec substation Installation of 400/110 kV 330 MVA TR in Ostrowiec substation 220/110 kV Radkowice Substation Modernization and enhancement of 220/110 kV Radkowice substation 750/400/110 kV Rzeszw Substation Enhancement of Rzeszw substation Installation of reactor at 400 kV switchgear in Rzeszw substation 220/110 kV Stalowa Wola Substation Enhancement of Stalowa Wola Substation to include 220 kV switchgear Installation of TR 220/110 kV 275 MVA in Stalowa Wola substation (Phase III) Installation of TR 220/110 kV 275 MVA in Stalowa Wola substation (Phase III) 400 kV Chem - Lublin Systemowa Line Construction of 400 kV Chem Lublin Systemowa line 400 kV Kozienice - Ostrowiec Line Modernization of 400 kV Kozienice Ostrowiec line 220 kV Kielce Piaski - Radkowice Line Construction of 220 kV Kielce Piaski Radkowice line 220 kV Stalowa Wola Line - tap into Abramowice - Chmielw Line Construction of 220 kV Stalowa Wola line tap into Abramowice - Chmielw Line 220 kV Kielce - Joachimw Line Modernization of 220 kV Joachimw Kielce line

2.4.2 2.4.3 2.5. 2.5.1 2.6. 2.6.1 2.6.2 2.7. 2.7.1 2.8. 2.8.1 2.8.2 2.9. 2.9.1 2.9.2 2.9.3 2.10. 2.10.1 2.11. 2.11.1 2.12. 2.12.1 2.13. 2.13.1 2.14. 2.14.1

3
3.1 3.1.1

PSE SOUTH AREA


220/110 kV Blachownia Substation Enhancement of 220/110 kV Blachownia substation

15

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
3.1.2 3.1.3 3.2. 3.2.1 3.2.2 3.3. 3.3.1 3.3.2 3.3.3 3.4. 3.4.1 3.5. 3.5.1 3.6. 3.6.1 3.7. 3.7.1 3.8. 3.8.1 3.9. 3.9.1 3.9.2 3.9.3 3.9.4 3.9.5 3.9.6 3.10. 3.10.1 3.11. 3.11.1 3.11.2 3.11.3 3.11.4 3.12. 3.12.1 3.12.2 3.13. 3.13.1 3.14. 3.14.1 3.15. 3.15.1 Connection of 220 kV Groszowice Kdzierzyn line to Blachownia substation Installation of 220/110 kV 275 MVA TR in Blachownia substation 400/220 kV Byczyna Substation Modernization and extension of Byczyna substation and connection of 400 kV line Installation of 400/220 kV 500 MVA TR in Byczyna substation 400/110 kV Dobrze Substation Enhancement of 400 kV switchgear in Dobrze substation Installation of 400/110 kV 330 MVA TR in Dobrze substation Installation of 400/110 kV 330 MVA TR in Dobrze substation 220/110 kV Halemba Substation Modernization of 220/110 kV Halemba substation 220/110 kV Jamki Substation Modernization of 220/110 kV Jamki substation 220/110 kV Komorowice Substation Modernization of Komorowice substation 220/110 kV Kopanina Substation Modernization of 220/110 kV Kopanina substation 220/110 kV Lubocza Substation Enhancement and modernization of 220/110 kV Lubocza substation 400/220 kV Podborze Substation Construction of 400/220 kV Podborze substation Connection of 220 kV Kopanina Liskovec line to Podborze substation Connection of 220 kV Bujakw Liskovec line to Podborze substation Connection of 220 kV Bieru-Komorowice line to Podborze substation Connection of 220 kV Czeczott Moszczenica line to Podborze substation Connection of 400 kV Nosovice Wielopole line to Podborze substation 220/110 kV Siersza substation Modernization of 220/110 kV Siersza Substation 400/220/110 kV Skawina Substation Enhancement of Skawina Substation to include 400 kV and 110 kV switchgear Construction of 400 kV Skawina line tap into Tarnw Tucznawa line Construction of 400 kV Skawina line tap into Rzeszw Tucznawa Line Installation of 400/110 kV 450 MVA TR in Skawina substation 400/110 kV Tarnw Substation Enhancement of Tarnw Substation Installation of reactor at 400 kV switchboard in Tarnw substation 400 kV Mikuowa - Czarna - Joachimw Line Modernization of 400 kV Mikuowa - Czarna - Joachimw line 400 kV Dobrze line - tap into Pasikurowice - Wrocaw Line Construction of 400 kV Dobrze line - tap into Pasikurowice - Wrocaw line 400 kV Wielopole - Blachownia, Kdzierzyn - Groszowice Lines Construction of 400 kV line along the 220 kV Wielopole - Blachownia, Kdzierzyn - Groszowice line

16

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
3.16 3.16.1 3.17. 3.17.1 3.18. 3.18.1 1.19. 3.19.1 3.20. 3.20.1 220 kV kV Byczyna - Jamki, Byczyna - Koksochemia Line Modernization of 220 kV Byczyna-Jamki, Byczyna -Koksochemia line 400 kV Wielopole - Joachimw, Wielopole - Rokitnica Line Modernization of 400 kV Wielopole-Joachimw, Wielopole - Rokitnica line 400 kV Wielopole - Joachimw, Tucznawa - Rogowiec Line Modernization of 400 kV Wielopole-Joachimw, Tucznawa-Rogowiec line 400 kV Tucznawa - Rogowiec, Joachimw - Rogowiec 3 Line Modernization of 400 kV Tucznawa-Rogowiec, Joachimw-Rogowiec line Lines 220 kV within PSE-Poudnie SA Comprehensive modernization of 220 kV lines within PSE-South (which in January 2010 were in the

4
4.1. 4.1.1 4.2. 4.2.1 4.2.2 4.3. 4.3.1 4.4. 4.4.1 4.4.2 4.5. 4.5.1 4.5.2 4.6. 4.6.1. 4.6.2 4.7. 4.7.1 4.7.2 4.8. 4.8.1. 4.9. 4.9.1 4.10. 4.10.1 4.10.2 4.11. 4.11.1 4.11.2 4.11.3

PSE WEST AREA


Mikuowa - wiebodzice Line Construction of 400 kV Mikuowa - wiebodzice line along the course of 220 kV line Baczyna Substation Construction of 400/110 kV Baczyna Substation with connection of Krajnik - Plewiska line Installation of 400/110 kV 450 MVA TR in Baczyna Substation Czarna Substation Enhancement of 400 kV switchgear in Czarna Substation Czerwonak Substation Installation of TR 220/110 kV 275 MVA in Czerwonak Substation (Phase III) Modernization of Czerwonak Substation Glinki Substation Enhancement of 220/110 kV Glinki Substation Installation of TR 220/110 kV 275 MVA in Glinki Substation (Phase III) Krajnik Substation Modernization and enhancement of 400/220 kV Krajnik Substation Installation of phase shifters at Krajnik Vierraden Line Kromolice Substation Construction of 400/110 kV Kromolice Substation Installation of TR 400/110 kV 450 MVA in Kromolice Substation (Phase III) Leszno Gronowo Substation Modernization of 220/110 kV Leszno Gronowo Substation (Phase II) Leniw Substation Modernization of 220/110 kV Leniw substation, including start-up of third ATR Mikuowa Substation Modernization and enhancement of 220/110 kV Mikuowa-Hagenwerder Substation Installation of phase shifters on Mikuowa Hagenwerder Line Ostrw Substation Enhancement of Ostrw Substation Installation of 400/110 kV 450 MVA TR in Ostrw Substation Installation of reactor at 400 kV switchboard in Ostrw Substation

17

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
4.12. 4.12.1 4.13. 4.13.1 4.13.2 4.13.3 4.14. 4.14.1 4.15. 4.15.1 4.15.2 4.15.3 4.16. 4.16.1 4.16.2 4.17. 4.17.1 4.17.2 4.18. 4.18.1 4.18.2 4.19. 4.19.1 4.20. 4.20.1 4.21. 4.21.1 4.22. 4.22.1 4.23. 4.23.1 4.24. 4.24.1 4.25. 4.25.1 4.25.2 4.26. 4.26.1 4.27. 4.27.1 4.28. 4.28.1 Modernization of ukowice Substation Baczyna - Krajnik Line Construction of 400 kV Baczyna Krajnik Line Czarna - Polkowice Line Construction of 400 kV Czarna Polkowice Line Glinki - Recaw Line Construction of 220 kV Glinki Recaw line Gorzw - Leniw line Modenization of 220 kV Gorzw Leniw line Kromolice - Ptnw Line Construction of 400 kV Kromolice Ptnw line along the route of 220kV Plewiska - Konin line Putting 400 kV Kromolice - Ptnw line to Ptnw substation with enhancement of Ptnw station Krajnik - Pomorzany Line Construction of 220 kV Krajnik Pomorzany line Mikuowa - Leniw Line Modernization of 220 kV Mikuowa Leniw line Adamw - Konin line - circuit I Modernization of 220 kV Adamw - Konin line - circuit I Pasikurowice Substation Enhancement of 400/110 kV Pasikurowice Substation Pia Krzewina Substation Enhancement of Pia Krzewina Substation to include 400 kV switchgear Enhancement of 110 kV switchgear in Pia Krzewina Substation for WF Modernization of Pia Krzewina Substation Plewiska Substation Modernization of the generator building in Plewiska Substation and replacement of generators with Polkowice Substation Enhancement of Polkowice Substation to include 400 kV switchgear Installation of 400/110 kV 450 MVA TR in Polkowice Substation Installation of 400/220 kV 500 MVA TR in Polkowice Substation Pomorzany Substation Enhancement of Pomorzany Substation to include 220 kV switchgear Installation of 220/110 kV 275 MVA TR in Pomorzany Substation Recaw Substation Enhancement of Recaw Substation to include 220 kV switchgear Installation of 220/110 kV 275 MVA TR in Recaw Substation wiebodzice Substation Enhancement of 220/110 kV wiebodzice substation to incluce 400 kV switchgear Installation of TR 400/110 kV 450 MVA in wiebodzice Substation (Phase III) Wrocaw Substation Construction of 400/110 kV Wrocaw Substation ukowice Substation

18

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
4.29. 4.29.1 4.30. 4.30.1 4.31. 4.31.1 4.32. 4.32.1 4.33. 4.33.1 4.34. 4.34.1 Adamw - Konin line - circuit II Modernization of 220 kV Adamw - Konin line - circuit II Plewiska - Pozna Poudnie Line Re-construction of 220 kV Plewiska - Pozna Poudnie line in single-circuit section Pasikurowice - Wrocaw Line Construction of 400 kV Pasikurowice Wrocaw Line Pia Krzewina - Plewiska Line Construction of 400 kV Pia Krzewina - Plewiska line Wrocaw - wiebodzice Line Construction of 400 kV line from Wrocaw substation to wiebodzice substation along the 220 kV wiebodzice - Klecina line Purchase of improvements Purchase of improvements for lines: wiebodzice-Klecina and Plewiska-Pia Krzewina resulting from re-construction of the lines to remove collision with motorways constructed by GDDKiA (General 4.35. 4.35.1 4.36. 4.36.1 Directorate for National Roads and Motorways). The line: Polish border - Gubin - Zielona Gra - Plewiska II - Plewiska Third connection defined as double circuit 400 kV line: Polish border-Gubin-Zielona Gra-Plewiska II Plewiska Mikuowa - wiebodzice - Zbkowice - Dobrze Line Double circuit 400 kV line: Mikuowa wiebodzice - Zbkowice Dobrze

5
5.1. 5.1.1 5.1.2 5.1.3 5.2. 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5 5.3. 5.3.1 5.3.2 5.4. 5.4.1 5.5. 5.5.1 5.6. 5.6.1 5.6.2 5.6.3

PSE NORTH AREA


220/110 kV Bydgoszcz Zachd Substation Enhancement of 400 kV switchgear in Bydgoszcz Zachd Substation Enhancement of 220/110 kV Bydgoszcz Zachd Substation Replacement of AT 220/110 kV 275 MVA in Bydgoszcz Zachd Substation (Phase III) 400/220/110 kV Dunowo Substation Enhancement of 400 and 100 kV switchgear in Dunowo Substation Installation of AT 400/110 kV 450 MVA in Dunowo Substation (WF) Connection of Darowo 250 MW wind farm to 400/220/110 kV Dunowo substation Enhancement of Dunowo Substation Installation of TR 400/110 kV 450 MVA in 400/220/110 kV Dunowo Substation( DSO) (Phase III) 400/110 kV Elblg Substation Construction of 400/110 kV Elblg Substation with GBL-OLM line introduction Installation of AT 400/110 kV 450 MVA in Elblg Substation 400/110 kV Gdask Bonia Substation Enhancement of 400/110 kV Gdask Bonia Substation 400/110 kV Gdask Przyja Substation Construction of 400/110 kV Gdask Przyja Substation with connection of arnowiec - Gdask 400/220/110 kV Grudzidz Line Enhancement of 400/220/110 kV Grudzidz Line Installation of AT 400/110 kV 450 MVA in Grudzidz Substation Installation of reactive power compensation devices in Grudzidz Substation

19

Updated Development Plan for meeting current and future electricity demand in the period 2010 - 2025

EXCERPT
5.7. 5.7.1 5.8. 5.8.1 5.8.2 5.9. 5.9.1 5.9.2 5.10. 5.10.1 5.10.2 5.10.3 5.11. 5.11.1 5.12. 5.12.1 5.12.2 5.13. 5.13.1 5.13.2 5.14. 5.14.1 5.15. 5.15.1 5.16. 5.16.1 5.17. 5.17.1 5.18. 5.18.1 5.19. 5.19.1 5.20. 5.20.1 5.21. 5.21.1 5.22. 5.22.1 5.23. 5.23.1 220/110 kV Jasiniec Substation Enhancement of 220/110 kV Jasiniec Substation 400/220/110 kV Olsztyn Mtki Substation Enhancement of 400/110 kV Olsztyn Mtki Substation Installation of reactor at 400 kV switchgear in Olsztyn Mtki Substation 400/110 kV Pelplin Substation Construction of 400/110 kV Pelplin Substation Installation of AT 220/110 kV 160 MVA in Pelplin Substation (with SE OST) 400/110 kV Supsk Substation Enhancement of 400 and 110 kV switchgear at Supsk Substation Installation of AT 400/110 kV 450 MVA in Supsk Substation (DSO) (Phase III) Installation of AT 400/110 kV 450 MVA in Supsk Substation (WF) (Phase III) 220/110 kV Wocawek Azoty Substation Enhancement of 220 kV switchgear in Wocawek Azoty Substation 400/110 kV arnowiec Substation Enhancement of 110 kV switchgear in arnowiec Substation for WF Installation of AT 400/110 kV 450 MVA in arnowiec Substation for WF (Phase III) 400/110 kV ydowo Kierzkowo Substation Construction of 400/110 kV ydowo Kierzkowo Substation Installation of AT 220/110 kV 160 MVA in ydowo Kierzkowo Substation (with SE PAB) 400 kV Grudzidz - Pelplin Line Construction of 400 kV Grudzidz Pelplin Line 400 kV Pelplin - Gdaska Przyja Line Construction of 400 kV Pelplin - Gdask Przyja Line 400 kV Ptnw - Jasiniec Line Construction of 400 kV Ptnw - Jasiniec Line 400 kV Jasiniec - Grudzidz line Construction of 400 kV Jasiniec - Grudzidz Line 400 kV Pia Krzewina - Bydgoszcz Zachd Line Construction of 400 kV Pia Krzewina - Bydgoszcz Zachd Line 400 kV Pia Krzewina - ydowo Line Construction of 400 kV Pia Krzewina ydowo Line 400 kV Pock - Olsztyn Mtki Line Construction of 400 kV Pock - Olsztyn Mtki Line 400 kV ydowo - Gdask Przyja Line Construction of 400 kV ydowo - Gdask Przyja Line 400 kV ydowo - Supsk Line Construction of 400 kV ydowo - Supsk Line 400 kV Grudzidz Wgrowo - Gdask Blonia Line Modernization of 400 kV Grudzidz Wgrowo - Gdask Blonia Line with replacement of earth wire on OPGW