Você está na página 1de 3

Aggregate Mining Unit Operation

Proposed Reclamation Cost Estimation Summary


Recommended Cost

Reclamation Item
Pit Walls

Units

Description

Typical Cost Range

Cu. Yd. Acre Acre Each Stockpiles,Overburden or Fines Areas Cu. Yd. Acre Acre Each Roads (Access) (Roads with Side Slope < 30%) (Roads with Side Slope >30%) Linear Ft. Linear Ft. Acre Acre Structures (Break-up and bury Slab) (Break-up and bury Slab) (Break-up and bury Slab) Sq. Ft. Sq. Ft. Sq. Ft. Linear Mile each Linear Ft. Linear Ft. Linear Ft. Linear Ft. (Break-up and bury) Sq. Ft.

Re-Grading and Topsoiling Costs

$ $ $ $

0.39 - $ 600 - $ 1,175 - $ 5 - $

0.55 900 1,372 30

$ $ $ $

0.44 607 1,175 10

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed) Containerized Trees and Shrubs

Re-Grading and Topsoiling Costs

$ $ $ $

0.39 - $ 600 - $ 1,175 - $ 5 - $

0.55 900 1,372 30

$ $ $ $

0.44 607 1,175 10

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed) Containerized Trees and Shrubs

Re-Grading and Topsoiling Costs Re-Grading and Topsoiling Costs

$ $ $ $

1.21 - $ 2.55 - $ 600 - $ 1,175 - $

1.70 5.42 900 1,372

$ $ $ $

1.70 2.60 607 1,175

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed)

Demolition & Removal - Metal Building Demolition & Removal - Masonry Block Building Demolition & Removal - Concrete Building Powerline Removal (Single Pole Utility) Transformer Removal Demolition - Chain Link Fencing Demolition - Barb Wire Fencing (3 strand) Removal - 15" Culvert Removal - 36" Culvert Demolition - Concrete Pads/Roads 12" Thickness

$ $ $

3.03 - $ 3.50 - $ 15.86 - $

3.40 6.06 87.34

$ $ $ $ $ $

3.40 3.50 15.86 10,000 5,000 3.47 1.94 10.29 17.15 6.78

$ 10,000 $ $ $ $ $ 5,000 3.47 1.94 - $ 10.29 17.15 6.78 1.96

$ $ $ $

Construction Linear Ft. Sq. Yard Material Haulage for Backfill Cu. Yard Cu. Yard Care and Maintenance Ton Each Trash Disposal Site Monitor and Reporting $ $ 55.00 - $ 1,500 - $ 65.00 3,000 $ $ 60.00 2,000 Truck and Loader - 2000Ft. One Way Dozer and Scraper - 1000Ft. One Way $ $ 1.03 - $ 0.50 - $ 1.12 0.72 $ $ 1.03 0.72 Construction - Barb Wire Fencing (3 strand) Install Rip Rap Erosion Lining $ $ 1.88 - $ 23.75 - $ 4.51 54.69 $ $ 1.88 23.75

Estimated Reclamation Operating and Material (O&M) Cost Sub-Total

Administrative Costs % of O&M Cost % of O&M Cost % of O&M Cost % of O&M Cost % of O&M Cost Contigency General Mobilization / De-Mobilization Indirect costs Contractor Profit Contract Administation 7% 1% 2% 9% 10% 20% 5% 30% 12% 18% 10% 4% 2% 10% 10%

Total Estimated Financial Assurance Amount

BROWN AND CALDWELL P:\Arizona Rock Products - ARPA\130387 - Reclamation Development\Deliverables\Reports\Aggregate Mining Unit Reclamation Cost Estimate Summary.xls 7/26/2006

Example Cost Estimation


Example Sand & Gravel Mining Company - Plant 1 (250 Ac Operation in Phoenix Valley Area
Pit is approximately 2,000 feet by 4,000 feet and 50 feet deep, pit walls require 300,000 cubic yards of balanced cut-fill material movement to create 3H:1V reclaim slopes Overburden dump is 300 feet by 500 feet and 50 feet high, requires approximately 80,000 cubic yards of balanced cut-fill material movement to create 3H:1V reclaim slope There are approximately 16,000 feet of access roads (40 feet wide) on site, 4,000 feet of those roads will remain after reclamation There is a metal shop building 30 feet by 60 feet on concrete slab, a truck scale (15 by 100 slab), and a masonary block scalehouse on slab (20 by 40) The property has approximately 12,000 feet of chain link fencing that needs to be demolished and hauled away There is one 3-phase powerline (and associated transformers) that runs approximately 2,000 feet on the property There is enough topsoil stored in the berms along the pit crests to cover the entire disturbed area

Proposed Reclamation Cost Estimation Summary - WorkSheet


Reclamation Item
Pit Walls Cu. Yd. Acre Acre Each Stockpiles,Overburden or Fines Areas Cu. Yd. Acre Acre Each Roads (Access) (Roads with Side Slope < 30%) (Roads with Side Slope >30%) Linear Ft. Linear Ft. Acre Acre Structures (Break-up and bury Slab) (Break-up and bury Slab) (Break-up and bury Slab) Sq. Ft. Sq. Ft. Sq. Ft. Linear Mile each Linear Ft. Linear Ft. Linear Ft. Linear Ft. (Break-up and bury) Construction Linear Ft. Sq. Yard Material Haulage for Backfill Cu. Yard Cu. Yard Care and Maintenance Ton Annual Trash Disposal Site Monitor and Reporting $ $ 60.00 2,000 16 2 $ $ 1,000 4,000 Truck and Loader - 2000Ft. One Way Dozer and Scraper - 1000Ft. One Way $ $ 1.03 0.72 $ $ Construction - Barb Wire Fencing (3 strand) Install Rip Rap Erosion Lining $ $ 1.88 23.75 $ $ Sq. Ft. Demolition & Removal - Metal Building Demolition & Removal - Masonry Block Building Demolition & Removal - Concrete Building Powerline Removal (Single Pole Utility) Transformer Removal Demolition - Chain Link Fencing Demolition - Barb Wire Fencing (3 strand) Removal - 15" Culvert Removal - 36" Culvert Demolition - Concrete Pads/Roads 12" Thickness $ $ $ $ $ $ $ $ $ 3.40 3.50 15.86 10,000 5,000 3.47 1.94 10.29 17.15 6.78 1,500 0.38 3 12,000 1,800 800 $ $ $ $ $ $ $ $ $ $ 6,100 2,800 3,800 15,000 41,600 10,200 Re-Grading and Topsoiling Costs Re-Grading and Topsoiling Costs $ $ $ $ 1.70 2.60 607 1,175 11 12,000 $ $ $ $ 20,400 6,700 Re-Grading and Topsoiling Costs $ $ $ $ 0.44 607 1,175 10 100 80,000 4 $ $ $ $ 35,200 2,100 1,000 Re-Grading and Topsoiling Costs $ $ $ $ 0.44 607 1,175 10 300,000 184 $ $ $ $ 132,000 111,700 -

Units

Description

Suggested Cost

Number of Units

Reclamation Cost

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed) Containerized Trees and Shrubs

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed) Containerized Trees and Shrubs

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed)

Estimated Reclamation Operating and Material (O&M) Cost Sub-Total =


Administrative Costs % of O&M Cost % of O&M Cost % of O&M Cost % of O&M Cost % of O&M Cost Contigency General Mobilization / De-Mobilization Indirect costs Contractor Profit Contract Administation 10% 4% 2% 10% 10%

393,600

$ $ $ $ $

39,400 15,700 7,900 39,400 39,400

Total Estimated Financial Assurance Amount =

535,400

BROWN AND CALDWELL P:\Arizona Rock Products - ARPA\130387 - Reclamation Development\Deliverables\Reports\Aggregate Mining Unit Reclamation Cost Estimate Summary.xls 7/26/2006

Aggregate Mining Unit Operation


Proposed Reclamation Cost Estimation Summary - WorkSheet
Reclamation Item
Pit Walls Cu. Yd. Acre Acre Each Stockpiles,Overburden or Fines Areas Cu. Yd. Acre Acre Each Roads (Access) (Roads with Side Slope < 30%) (Roads with Side Slope >30%) Linear Ft. Linear Ft. Acre Acre Structures (Break-up and bury Slab) (Break-up and bury Slab) (Break-up and bury Slab) Sq. Ft. Sq. Ft. Sq. Ft. Linear Mile each Linear Ft. Linear Ft. Linear Ft. Linear Ft. (Break-up and bury) Construction Linear Ft. Sq. Yard Material Haulage for Backfill Cu. Yard Cu. Yard Care and Maintenance Ton Annual Trash Disposal Site Monitor and Reporting $ $ 60.00 2,000 Truck and Loader - 2000Ft. One Way Dozer and Scraper - 1000Ft. One Way $ $ 1.03 0.72 Construction - Barb Wire Fencing (3 strand) Install Rip Rap Erosion Lining $ $ 1.88 23.75 Sq. Ft. Demolition & Removal - Metal Building Demolition & Removal - Masonry Block Building Demolition & Removal - Concrete Building Powerline Removal (Single Pole Utility) Transformer Removal Demolition - Chain Link Fencing Demolition - Barb Wire Fencing (3 strand) Removal - 15" Culvert Removal - 36" Culvert Demolition - Concrete Pads/Roads 12" Thickness $ $ $ $ $ $ $ $ $ 3.40 3.50 15.86 10,000 5,000 3.47 1.94 10.29 17.15 6.78 Re-Grading and Topsoiling Costs Re-Grading and Topsoiling Costs $ $ $ $ 1.70 2.60 607 1,175 Re-Grading and Topsoiling Costs $ $ $ $ 0.44 607 1,175 10 Re-Grading and Topsoiling Costs $ $ $ $ 0.44 607 1,175 10

Units

Description

Suggested Cost

Number of Units

Reclamation Cost

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed) Containerized Trees and Shrubs

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed) Containerized Trees and Shrubs

Revegetation Cost (Disc) Revegetation Cost (Hydro-seed)

Estimated Reclamation Operating and Material (O&M) Cost Sub-Total =

Administrative Costs % of O&M Cost % of O&M Cost % of O&M Cost % of O&M Cost % of O&M Cost Contigency General Mobilization / De-Mobilization Indirect costs Contractor Profit Contract Administation 10% 4% 2% 10% 10%

Total Estimated Financial Assurance Amount =

BROWN AND CALDWELL P:\Arizona Rock Products - ARPA\130387 - Reclamation Development\Deliverables\Reports\Aggregate Mining Unit Reclamation Cost Estimate Summary.xls 7/26/2006

Você também pode gostar