Escolar Documentos
Profissional Documentos
Cultura Documentos
I. INTRODUCTION
This report discusses my experiences during my fourth and fifth weeks on site. It summarizes the tasks undertaken and the lessons which are apparent from these tasks. Finally the overall conclusions which can be made from the weeks work are given.
Prior to casting, the consultant inspects the column to ensure it meets the specifications. He checks that the column is the right height, the spacing between reinforcement bars is correct and that there is adequate concrete cover to the bars. If any of these requirements are not correct, the request for approval can be rejected. Any problems must be rectified before casting can begin. If it is found that the cover is inadequate, the reinforcement bars must be bent into place. This is done by the machine shown in the following image. Page 1 of 5
Rotana Hotel Project: Al Abdali, Amman, Jordan Engineer In Training Site Experience Weeks Four and Five Report Trainee: Ronan Duffy
Upon approval by the consultant, the shutters are closed and three final checks are performed by the engineer. These include a verticality test, another check to ensure adequate concrete cover and he must ensure the safety rails at the top of the column are installed properly in order for casting to begin. Out of these checks, the verticality test is interesting as a relatively simple method is used. A weight is hung from the top of the formwork. As long as the distance between the string and the shutter at the top is equal to the distance between the string and shutter at the base, the column is vertical.
Page 2 of 5
Rotana Hotel Project: Al Abdali, Amman, Jordan Engineer In Training Site Experience Weeks Four and Five Report Trainee: Ronan Duffy
Interestingly, since shutters only go up on one side there is a risk of pressure building up at the base of the wall. To counteract these pressures, the formwork is anchored in using steel reinforcement bars located at the base of the wall. These bars can be seen in the previous image. The following image shows a schematic representation of this set up.
Page 3 of 5
Rotana Hotel Project: Al Abdali, Amman, Jordan Engineer In Training Site Experience Weeks Four and Five Report Trainee: Ronan Duffy
As with the previous structural elements, the first stage for the core is the construction of a steel cage by the steel fixers. This begins after a level of the core is cast. Within two days, the inner formwork is jacked up. During this time the steel fixers continue constructing the reinforcement cage. Shortly after the raising of the inner formwork, the outer formwork is raised by a crane. The following image depicts this routine operation.
Page 4 of 5
Rotana Hotel Project: Al Abdali, Amman, Jordan Engineer In Training Site Experience Weeks Four and Five Report Trainee: Ronan Duffy
Following this, the steel cage is completed and checks are carried out by the engineer and consultant to ensure the as built cage follows the specifications. Upon approval, casting can begin. Casting usually takes place in the evening and can take several hours. Plasticizers are added to the concrete to increase the flow of the concrete and ensure that it fills the formwork adequately and reduces the chance of honeycombing in the core.
Once casting is complete, the cycle begins again from the start. The overall process of casting one level of the core usually takes between eight and twelve days.
The whole project is a complicated system which relies on its various different components. If any one of these experiences a problem, there will be a knock on effect to the others which could result in a delay to the overall project.
Page 5 of 5