Could any body explain me what is difference between Physical , duration and Units % completes.

Their usage , importance and significance ? Physical % - Based on quantities (denominator Budget Quantities) Duration % - Based on number of days or hours (denominator Original Duration) Units % - Based on Mandays/Manhours (denominator Budget Mandays/Manhours) physical % is the percentage of the actual works done on site compared with the planned quantities . the duration is the percentage of the time elapsed compared with the total duration of the project. how does the progress be recorded in P6 as you have the total scope of the work eg. 1000MT of work to be completed in 10 days. Does p6 calculate the actuals with inputs being provided? I want to know more about it. In infrastructure developement project number of activity involves such as civiil work physical measurement in Cubic Meter where as Mechanical Work measure in MT or Nos.This different quantity convert into weighted percentage to monitor & represent your project task/completion of work only possible when they come under one units.

i want to monitor my project in the manner illustrated in the following example, i need help on which auto cost rules to change. suppose activity is of excavation and scheduled days are 10 and budgeteg manhous(resource) is 100 hrs At the end of 5 days the situation is like i gave RD(5 days) and percent completion of the task is 30% and the resource used is like 65 hrs my question is that i want to keep the PCT, RD and actual quantity not linked with each other ....so which rules of auto cost i shall change I WANT TO REMOVE LINK BETWWEN UPDATE PERCENT COMPLETE AND ACTUALS QUANTITY TO DATE BY UNCHECKING THE RULE "USE THE UPDATE PERCENT COMPLETE AGAINST THE BUDGET TO COMPUTE ACTUAL QUANTITY TO DATE." AS I AM THINKIG THAT MAY BE MY ACTIVTY IS 10% COMPLETE BUT THE RSOURCE THAT HAS BEEN USED IS MORE THAN THE RESOURCE BUGETED FOR 10% COMPLETION OF THAT ACTIVIT. SO I WANT TO GIVE THE RESOURCE UTILIZATION TILL THAT DATE BY MY SELF AND DONT WANT PRIMAVERA TO COMPUTE BY SIMPLY MULTIPLYING PCT COMPLETION TO TOTAL BUDGETED QUANTITY OF THAT ACTIVITY TO CALCULATE VALUES TILL THAT DATE.

Uncheck " Link remaining duration and schedule percent complete" so you can manually enter , Percent complete , remaining duration and resource used Maybe you can assist me with this discussion that continually goes around in my office. How does one measure an activity as being physically complete? I understand the methodology behind all of this, and that it can be equated to units or quantities, and that one doesnt have to link physical percentage complete to the end date etc. But it is measured differently in each software package and P6 is different from P3 which differs from Microsoft What is the standard and best practise in this regards I think it is not possible to equate physical % complete with cash flow.There are items or materials that are so expensive that its percentage as far as cash flow is concern is so high but the actual contribution if it is installed is low. What i am thinking is, an ACTIVITY on part or as a whole should be broken down into phases for physical % comp to be more accurate. Say, Excavation, you can say that physically it is 100% complete but, it could be presented as 90% only with 10% for snagging or any corrective/additional works. Punchlist works or snagging should be given enough duration because it will be used to represent all activities that need corrections or alterations Is it not possible to consider the following? If we recognise that the Project Has a Cashflow and that the cashflow is based on the progress of activities which could have m3 etc or manhours, if we then measure the measurable claim of monthly certificates against work done, we get a measurement of physical work done? Could we not then say, that an activity is a certain percentage physical based on the value of cashflow paid against it?? Using weighted qty by different units of measure monitoring sheet is the only way to go. Example civil you would have excavate by m3, Blinding by concrete m3, Shutering by square meters, Rebar by tons. and you would weigh them excavate = 10%, Blinding = 5%, Shutering = 5%, Rebar = 10%, Concrete = 50%, Inspect = 10%, Handover = 10%. Then do the same for Mechanical, Piping, E&I all by activity numbers. The percentage complete may differ depending on managers and client Norms. That is the only way to measure Physical progress and be sure you are accurate. This system is not always used on projects as it is a lot of work to monitor but if implemented early fairly accurate.

The project was E&M works of a nuclear power station. Every components of the works as small as bolts & nuts have equivalent standard manhours. The weight of each activity (points) was calculated as the sum of the standard manhours of the materials to be used in the activity. For items that cannot be measured in manhours, standard points value were assigned. And in small fragmented mini projects where no physical units are utilised? Establishing training programmes, systems, procedures, studies, country/travel security, HSSE audits, Business Assurance? It has to rely on finger in the wind Team Leader assement. However, weighting/gates/hold point/milestones/interphase milestones agreed up front as deliverables are hit should be transparently recorded. Otherwise, its easy to accept to 90% complete in 10% of the time and embarrassing to have the last 10% of your project take 90% of teh time.

Labour resources I supposed is measurable in terms of time (whether productive or not). When you say Resource Units, It can be a combination of labor, materials and/or equipment. But how are you going to simplify Resource Units? Maybe you can use time, cost and/or quantities. And what is Physical Percentage Progress? For me, you need to consider functionality as well. Any material, equipment installed or its combination need to be measured in terms of functionality.

Based on my experience, using the labour resources to monitor the physical % progress will give more accuracy. The essense of the Schedule is to represent the ongoing activities on the project. Your question about physical % can be answered by knowing how the output is calculated. (i.e. we need to know the exact theory behind the program in order to assess what it is giving us). Naturally, on a project, the Project Manager is asked to monitor the vital signs of the project. Material and shop drawings approvals, Material deliveries, Resources, Quality Control, Cash Flow, milestone, and cutomer expectations). It is much more important to control and monitor the exact requirements for each of the above than looking at a single percentage. Unless you have a correct model of the job and it worked for you before.

What does physical % complete mean?? Ill put a cat amongst the pigeons and say for most projects that rely on physical % complete as an indicator, it is a myth, a spook story that planners tell their kids at night They told me it was 75% complete, BUT its been 75% complete for the last

two weeks and theres been three more people working on the task!! The majority of project teams Ive worked with take % complete to be a faithful representation of how the task / work package / project is progressing, but what data are they actually basing that assumption on? More often than not and left to their own devices, Ill bet theyll use duration. Does this truly represent physical % complete? This method only shows how long a task has been in progress relative to the period of time needed to complete the task. It doesnt tell you anything about the status of the task / work package / project. As physical % complete and to a certain extent % work complete, is so subjective the only reliable indicators are 0% (it hasnt started) or 100% (it is complete). If your teams are using work plans, start by breaking their work plans into event milestones or gateways. Then break down each event milestone into lots of minimilestones (inchstone is the latest buzzword I believe). The principle is much the same as intermediate EV milestones, you weight each mini-milestone with a percentage, when they hit each mini-milestone, you can then manually re-calculate the cumulative physical % complete total. That way at least there is something substantive to base your project reporting on. Use this in conjunction with a milestone slip chart or any other supporting rational and I reckon youll get a fair representation of how the project is progressing. Im not really trying to start a crusade to eradicate physical % complete, but surely just cranking a handle and churning out an ambiguous weekly total isnt really as effective a measure as its made out to be. In my humble opinion, letting your scheduling engine of choice determine project progress is tantamount to a confession of incompetence. I know a certain PM, who will forever remain nameless, that wanted to declare to the customer that their project was currently 27.38% complete!! If anyone could determine progress that accurately, then they should be dedicating their lives to world peace, stopping famine or getting everyone out of the credit crunch because theyre wasted in a PM role!! A long post to digest, but please feel free to discuss. Like Barry Im curious to know how others in the community view physical % complete. In my experience with using physical % complete, it is purely the project managers opinion on where the progress is at. If the planned % complete is showing say 80%, though he knows it hasnt progressed as the schedule calculates, he gives his physical % (say 70%) meaning the ACTUAL percentage complete on the activity or project as a whole. I normally show both the physical and planned % complete on my schedules. So internally we can see where we are at, and clients can view TRUE progress v planned. For my Opinion, % progress of an activity could be monitored by using quantities as a database. It does not need to have all LVL4 or LVL5 activities in your selected scheduling programme.

You can monitore the work done by quantities by excel or office programmes from site to collect data and get higher level % progress. If the item is an Lumpsum activity of a workpack defined, then you can plan the work carefully and you can use the time(ex: For Installations or transportations) or money(ex: For procurement) as % progress monitoring.

In Spider Project activities may have Volumes - physical quantities of work to be done. Resources assigned to activities may have Productivities (volumes that they do in one hour). Entering actual data people enter not percents but actual amounts (volumes) of work that were done on activities. Remaining duration is calculated basing on remaining volumes of work and productivities of assigned resources. I dont see any need in measuring percents when you can measure actual amounts. For me, Physical Percentage cannot be measured in terms of money or time. It can only be measured in terms of actual quantities (or materials / equipment) installed or placed.