MECHANICAL COMMISSIONING STATION: NTPC-RAMAGUNDAM SYSTEM : PLANT ITEM : SCRAPER CONVEYOR REF : M 18/2 SHEET 1 OF 3 1 X 500 MW UNIT :7

LOCATION:

PLANT NOMENCLATURE: _________________________________________________ MANUFACTURER ___________________ SRL. NO. __________________________ NO . ACTIVITY STATUS (YES/NO) REMARKS

1.

General conditions satisfy the Site Standing Instruction as listed in the PLANT ITEM COMMISSIONING ESSENTAL PRE REQUISITES (SCL MSI/1). The name plate legend agrees with the approved NTPC Plant nomenclature is clearly visible, securely fixed, durable and correlates with remote labels. Installation is complete and correct in accordance with approved drawings and specification. Adequate access for adjustment, maintenance and repairs is provided. Verify that all construction Dobris is removed from the scraper conveyer through.

2.

3.

4.

5.

NAME MECH.ERECT. NTPC ELECT.ERECT. COMMNG. C&I BHEL ERECT. COMMNG.

SIGNATURE

DATE

CONTRACTOR

MECHANICAL COMMISSIONING STATION: NTPC-RAMAGUNDAM SYSTEM : PLANT ITEM : SCRAPER CONVEYOR REF : M 18/2 NO . SHEET 2 OF 3 STATUS REMARKS (YES/NO) 1 X 500 MW UNIT :7

LOCATION:

ACTIVITY

6.

Check that LP water connection to scraper conveyer trough is made correctly. Check that HP water connection to scraper bar cleaning is made and nozzle is installed correctly. Check the reduction gearbox as per SCL Verify that drive chin sprocket bearings are greased and chains have been lubricated properly.

7.

8. 9.

10. Check that scraper conveyer pulleys are rotating smoothly and freely. 11. Check that conveyer bars coated with lubricant. 12. Check that motor trial run has been taken satisfactorily. 13. Verify that protection and interlocks of scraper conveyor checked out satisfactorily. 14. Verify that S.C.C. is taken. Record the ref.no. and effective date.

NAME MECH.ERECT. NTPC ELECT.ERECT. COMMNG. C&I BHEL ERECT. COMMNG.

SIGNATURE

DATE

CONTRACTOR

MECHANICAL COMMISSIONING STATION: NTPC-RAMAGUNDAM SYSTEM : PLANT ITEM : SCRAPER CONVEYOR REF : M 18/2 NO . SHEET 3 OF 3 STATUS REMARKS (YES/NO) 1 X 500 MW UNIT :7

LOCATION:

ACTIVITY

15. Verify that the operation of emergency push button has been checked. 16. Start the scraper conveyor trial run and continue the trial run for 6 hrs. and observe. 16. Smooth functioning of scraper conveyer. 1 Smooth functioning of tension adjusting device. 16. 2 Smooth functioning of nozzles for cleaning of scraper bars. 16. 3

NAME MECH.ERECT. NTPC ELECT.ERECT. COMMNG. C&I BHEL ERECT. COMMNG.

SIGNATURE

DATE

CONTRACTOR