Since our last briefing to the Committee (10/17/2011), the following construction milestones have been completed:
All mechanical systems are in place and functioning Wood floors have been installed in the public areas (lobby, performance chamber) Concrete floors in the lobby and public corridors have been polished to reveal the aggregate Seating has been installed in the performance chamber The rigging system is installed and functioning Internal wayfinding signage installed Landscaping is 80% complete
View of West Side Landscaping from the Loading Dock (Site for Phase II construction)
10
BRANDING PLAN
Develop the brand concept and marketing for the grand opening event
Dallas-based companies SparkFarm worked on the grand opening of the AT&T Performing Arts Center El Creative has worked on branding for Bahama Beach and the Love Field Modernization Program
11
12
Ticketed jazz concert featuring North Texas jazz artists on Saturday night
Free programming targeting families Brief performances throughout the day by local groups (dance, theater, music) Information booths for local arts and cultural groups
13
Exciting and varied schedule of performances by Dallas arts and cultural groups
Lone Star Wind Orchestra (October 2012) Resounding Harmony (November 2012) Turtle Creek Chorale (February 2013) Dallas Black Dance Theater (March 2013)
Please note these are just highlights; additional performances are booked through the year
14
QUESTIONS?
15
APPENDICES
Appendix I City Performance Hall Background Appendix II Project Development
16
Winspear Opera House Wyly Theater Annette Strauss Square Sammons Performance Park City Performance Hall
A development agreement with the Dallas Center for the Performing Arts Foundation was authorized on 9/28/2005
Foundation developed four venues (AT&T Performing Arts Center) City designing and constructing the City Performance Hall
17
Need for the facility identified in the Master Planning process for the performing arts center
Referred to as the third venue Conceived to serve the needs of small and medium arts groups reflecting the diverse communities of Dallas
Inclusion in the Master Plan received broad support from the cultural community
18
19
20
21
Currently under construction is Phase I (60,000 sq. ft), the 750seat theater approved in the 2006 Bond Program Completion of the rest of the 124,000 sq. ft. program to be supported in future bond programs
22
Identified need for 124,000 sq. ft. facility that included a 750seat theater, two flexible theaters, with full complement of public and support spaces Conceived to be implemented in multiple phases
Full lobby fronting Flora with event mezzanine Wood floors Theater seating (750 seats in two levels, orchestra & balcony) Stage pit Stage lighting and controls Performance audio and video system Concert enclosure and acoustical reflector panels Stage rigging and drapery system Motorized acoustical banners
23
City Council approved Construction Manager At-Risk Guaranteed Maximum Price (GMP) construction contract to McCarthy Building Companies on April 22, 2009 (CR 091106)
City Performance Hall construction schedule coordinated with the AT&T PAC Silver Garage (privately funded and located below the City Performance Hall)
Construction trade contracts procured to construct the building within the established GMP
24
Schematic for the full buildout. Phase I (currently under construction) shown inside the red dashed line. Additional phases pending future bond programs.
25